A high-rise, ultra-long cantilever slab formwork support frame
By setting multiple sets of components on the fixing ring of the cantilever slab formwork, and using sharp plug rods and sliding groove structures, the stability problem of the fixing ring when the concrete has not hardened is solved, thus achieving stable fixation of the cantilever slab formwork and a firm connection after the concrete has hardened.
Patent Information
- Application Number
- CN202310973161.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-04
- Publication Date
- 2025-11-14
- Estimated Expiration
- 2043-08-04
AI Technical Summary
The existing cantilever slab formwork lacks supporting components for the fixing rings when the concrete has not hardened, causing the fixing rings to tilt and become unstable, thus affecting the fixing effect of the cantilever slab formwork.
A high-rise ultra-long cantilever slab formwork support frame was designed. By setting components such as a fixed plate, crossbar, collar, moving rod, connecting rod, plug rod, tilting frame and extension rod on the fixed ring, the sharp plug rod is inserted into the concrete. The fixed ring is stably positioned in the concrete by the cooperation of multiple sets of convex rings, grooves, support rods and protective plates.
It improves the stability of the fixing ring in concrete, prevents tilting, ensures the safe fixation of the cantilever slab formwork, avoids the generation of air bubbles at the bottom of the fixing ring during concrete solidification, and enhances the stability and safety of the overall structure.
Smart Images

Figure CN116971601B_ABST
Abstract
Citation Information
Patent Citations
High-rise cantilever I-steel embedded ring recycling device
CN115749245A
Adjusting handrail with protection function for building construction
CN216240114U