A method for correcting the deviation of existing track bed with embedded long sleepers
By adjusting the track slab position using reaction piers and correction mechanisms during the track maintenance window of high-speed railway operating lines, the problem of track deviation in long-sleeper embedded ballastless track beds was solved, achieving a safe and controllable track correction effect.
Patent Information
- Application Number
- CN202311024537.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-15
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-08-15
AI Technical Summary
On high-speed railway operating lines, deformation of the long-sleeper embedded ballastless track foundation causes track irregularities that are seriously beyond the scope of maintenance and management, making it impossible to use fasteners for fine adjustment. This also poses risks to construction safety and operational interruption.
During the track maintenance window, the track slab is gradually adjusted to the target position by setting up reaction blocks, separating the track slab from the underlying structure, injecting quick-setting mortar bags, and using lateral limiting and correction mechanisms. Polymer cement mortar is then used to repair the voids, ensuring construction safety and operational continuity.
This method enables the safe and effective correction of track deviations without affecting normal railway operations, avoiding the complex process of raising the base plate and track bed as a whole, simplifying the construction process, and improving controllability.
Smart Images

Figure CN117026708B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of ballastless track correction technology, specifically relating to a method for correcting the deviation of existing track long sleeper embedded ballastless track bed. Background Technology
[0002] With the continuous development of my country's economy, the number of high-speed railways in operation has increased. In some sections, due to various unfavorable factors such as geology, environment, and human factors, foundation deformation has occurred, causing the track alignment to deviate from the original design plane and elevation. When the track irregularities caused by the deformation of the long-sleeper embedded ballastless track foundation seriously exceed the scope of maintenance and management and cannot be finely adjusted using fasteners, effective remediation measures must be adopted to ensure uninterrupted train operation. The remediation of subsidence and deviation of existing high-speed railway ballastless tracks presents the following key construction challenges: Firstly, completing track alignment remediation on an operational high-speed railway line inherently carries certain safety risks; secondly, while ensuring the normal use of existing equipment, it is crucial to adopt reasonable construction techniques and methods, equip appropriate tooling and equipment, and safely and reliably complete the renovation task, ensuring the safety of both the construction and operational lines—this is the top priority of the project. Summary of the Invention
[0003] This invention addresses the issue of unevenness in the ballastless track alignment caused by deformation of the foundation structure on high-speed railway lines that has become severely beyond the scope of maintenance and management and cannot be finely adjusted using fasteners. It provides a remedial measure to ensure uninterrupted operation when such unevenness occurs. This method is applicable to long-sleeper embedded ballastless track beds that have only sunk or have simultaneously shifted.
[0004] This invention provides the following technical solution: a method for correcting the offset of existing track bed with embedded long sleepers, to be implemented during train operation windows, comprising the following steps:
[0005] S1: Determine the deviation between the current track alignment and the target alignment in the correction area;
[0006] S2: Set up reaction piers on both sides of the line;
[0007] S3: After the track slab is separated from the lower structure, a void layer is formed between the layers. Before the void layer is fully filled and restored, and before the end of the skylight period, quick-hardening mortar bags are injected into the cut surface to temporarily fill the void layer; a lateral limit is set between the separated track slab and the reaction pier.
[0008] S4: Remove the concrete at the start and end points of the track slab correction unit;
[0009] S5: Raise the track slab to the target elevation position;
[0010] S6: Release the lateral limit and set up a lateral loading mechanism between the track slab and the reaction pier for lateral correction;
[0011] S7: After the track slab is corrected to the target plane position, the void layer under the track slab is repaired. Lateral restraint is applied before the track slab finally restores the structural integrity. After the void layer repair material reaches the design strength, the track slab is anchored with rebars one by one in the separation range from the lower structure.
[0012] S8: Restore the section of track slab that was removed; clear and restore the original site at the reaction pier.
[0013] Further, step S1 specifically includes: using a level and a total station to verify the CPⅢ data of the construction section, reviewing the precision measurement network, using a fine-tuning trolley to collect the geometric dimensions of the line, investigating the height adjustment pads and gauge blocks of each fastener in the rectification section, and determining the deviation value between the current track surface alignment and the target alignment in the correction area.
[0014] Furthermore, the displacement of the track slab is monitored synchronously throughout the process of raising the track slab and lateral correction. A total station is used to monitor the centerline offset and elevation. After each track window is completed, the geometric dimensions of the track are checked to ensure that the track is ready for operation.
[0015] Furthermore, a combination of screw rod and inner and outer threaded sleeves is used to lift the track slab. The bottom of the inner and outer threaded sleeves is temporarily bonded to the bottom steel gasket to seal the bottom opening of the pipe. Holes are drilled on the top surface of the track slab, penetrating its thickness. Rebar adhesive is placed in the holes, and the inner and outer threaded sleeves that are bonded to the bottom steel gasket are installed in the holes so that the outer walls of the inner and outer threaded sleeves are bonded to the hole walls. The screw rod is screwed into the inner and outer threaded sleeves, and the top of the screw rod extends out from the top surface of the track slab. A wrench is connected to the top of the screw rod, and the screw rod is rotated to lift the track slab.
[0016] Furthermore, the track slab separation of the double-block ballastless track bed is achieved using a horizontal cutting wire saw. The horizontal cutting wire saw includes a track trolley and a first cutting wire. The track trolley slides on the track via its traveling wheels. The track trolley carries an equipment frame, which is equipped with two guide wheels, several auxiliary wheels, a drive wheel, and a torque output mechanism. The two guide wheels are located on both sides of the track slab. The closed loop of the first cutting wire has a disconnectable joint. The first cutting wire is broken at the joint and passes through the track slab through a drilled hole before being reconnected into a loop. The first cutting wire is held and tensioned on the two guide wheels, several auxiliary wheels, and the drive wheel. The drive wheel is connected to the torque output mechanism to drive the first cutting wire to rotate cyclically for cutting operations. The cutting wire segment located between the two guide wheels is aligned with the connection line between the track slab and the base plate.
[0017] Furthermore, the auxiliary wheels include a reversing auxiliary wheel and two tensioning auxiliary wheels. The first cutting rope starts from the guide wheel on the left side of the track plate, changes direction via the reversing auxiliary wheel, passes sequentially above the first tensioning auxiliary wheel and below the second tensioning auxiliary wheel, and then changes direction via the drive wheel and the guide wheel on the right side of the track plate to return to the starting point.
[0018] Furthermore, the track slab separation in the turnout area employs a transverse cutting wire saw. The transverse cutting wire saw includes a base, a main arm, an upper crawling frame, a lower crawling frame, and a second cutting wire. The base is fixed relative to the track slab to support the entire wire saw. The main arm is fixed to the base and has a linear guide rail perpendicular to the track slab surface. The upper and lower crawling frames are slidably mounted on the main arm in cooperation with the guide rail. The upper crawling frame has n auxiliary wheels, where n is an integer ≥ 2, and the lower crawling frame has n-1 drive wheels and two guide wheels. The axes of rotation of the auxiliary wheels and drive wheels are parallel and... The wheel rims are in the same plane, and the power wheel is located between the two auxiliary wheels in space. Two guide wheels are distributed on both sides of the n-1 power wheels. The annular second cutting rope has a disconnectable joint. There are two holes drilled at the front and back of the track plate. The second cutting rope is disconnected from the joint, passes through the drilled holes, is fitted onto the track plate between the two drilled holes, and is then connected to form a ring. The second cutting rope is reciprocated and stored between the n auxiliary wheels and the n-1 power wheels. It is guided to the cutting position by the guide wheels on both sides. The rotation of the power wheel drives the second cutting rope to perform the cutting operation. As the cutting progresses, the upper climbing frame is adjusted to tighten the second cutting rope.
[0019] Furthermore, the lateral limiting mechanism includes a fixed-end base support, a fixed-end base support sleeve, a movable-end base support ball joint, a movable-end base support, a rotating sleeve, and a rotating lead screw; the fixed-end base support sleeve is fixedly connected to the fixed-end base support, and the fixed-end base support sleeve is perpendicular to the back of the fixed-end base support, the back of the fixed-end base support is the surface that contacts the support pier, and the fixed-end base support sleeve is engraved with internal threads; the movable-end base support ball joint is fixedly connected to the movable-end base support, and the movable-end base support ball joint is perpendicular to the back of the movable-end base support. The back of the movable end support is the surface that contacts the track slab; the rotating sleeve is movably fitted onto the ball rod of the movable end support, and the end of the ball rod of the movable end support abuts against the support part inside the rotating sleeve. The rotating sleeve is engraved with internal threads; one end of the rotating screw is threaded into and tightened to fix the rotating sleeve, and the other end is threaded into the fixed end support sleeve. The rotating sleeve rotates with the rotating screw, and the rotating screw rotates in and out relative to the fixed end support sleeve, so that the lateral limiting support is placed between the track slab and the support pier.
[0020] Furthermore, the insulating plate connected by the internal thread of the rotating sleeve serves as a support, and the surface of the movable end bottom support ball rod that contacts the insulating plate is spherical; the end of the rotating screw that is screwed into the rotating sleeve abuts against the insulating plate; the movable end bottom support ball rod includes a cylindrical section and a ball head, the cylindrical section is connected to the movable end bottom support, and the ball head is coaxially fixed to the cantilevered end of the cylindrical section; one end of the rotating sleeve has a bottom, and the bottom plate has a hole that matches the cylindrical section, through which the rotating sleeve can be rotatably fitted onto the movable end bottom support ball rod, and the tube hole of the rotating sleeve includes a smooth section that matches the ball head and an internal thread section that matches the external thread of the insulating plate.
[0021] Furthermore, in step S7: the void between the track slab and the lower structure is repaired with polymer cement mortar and pressure grouting is used; during grouting, limiting measures are taken to prevent the track slab from floating and shifting.
[0022] Compared with the prior art, the advantages of the present invention are:
[0023] This invention provides a method for correcting the deviation of existing track bed with embedded long sleepers. By determining the correction area, the elevation of the ballastless track to be corrected, and the amount of lateral correction, this application avoids the need to lift the entire base plate and track bed slab and then move the entire track bed laterally without affecting the normal operation of the railway line. This method directly separates the connection between the base plate and the track slab, lifts the track slab with a screw rod, and then moves the track slab laterally. Therefore, it does not affect the rails, has a simple process, good controllability, and solves the problem of the track bed being too heavy to correct. Attached Figure Description
[0024] Figure 1 This is a cross-sectional view of the ballastless track bed with embedded sleepers in a condition awaiting renovation.
[0025] Figure 2 A schematic diagram illustrating the use of a horizontal wire saw.
[0026] Figure 3 This is a schematic diagram of the drive wheel of a horizontal wire saw.
[0027] Figure 4 This is a schematic diagram illustrating the use of the lateral limit switch;
[0028] Figure 5 This is a schematic diagram of the lateral limiting structure;
[0029] Figure 6 A sectional view showing the lateral restraint;
[0030] Figure 7 This is a schematic diagram of the track slab lifting process;
[0031] Figure 8 A schematic diagram illustrating the use of a wire saw for horizontal cutting.
[0032] Figure 9 This is a front view of a transverse wire saw.
[0033] Figure 10 This is a side view of a transverse wire saw.
[0034] In the diagram: 1-Trolley; 2-Walking wheel; 3-Equipment frame; 4-First guide wheel; 5-First cutting rope; 6-Drive wheel; 7-Reversing auxiliary wheel; 8-Steering wheel; 9-Tensioning auxiliary wheel; 10-Motor; 11-Track; 12-Base; 13-Main frame arm; 14-Upper climbing frame; 15-Lower climbing frame; 16-Second cutting rope; 17-Auxiliary wheel; 18-Power wheel; 19-Second guide wheel; 20-Diagonal brace; 21-Diagonal brace 22-Adjusting fixing clip; 23-Screw; 24-Crawling gear; 25-Limit wheel; 26-Rack; 27-Fixed end base support; 28-Fixed end base support sleeve; 29-Moving end base support ball rod; 30-Rotating sleeve; 31-Rotating lead screw; 32-Isolation plate; 33-Trajectory plate; 34-Reaction block; 35-Nut; 36-Lead screw; 37-Internal and external threaded sleeve; 38-Pipe bottom steel washer; 39-Wrench; 40-Base plate;
[0035] A1 - Lateral limit; A2 - Lifting mechanism; A3 - Cutting layer; A4 - Lateral loading mechanism; B1 - Existing rail surface elevation; B2 - Target rail surface elevation; C1 - Existing track centerline; C2 - Target track centerline. Detailed Implementation
[0036] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0037] like Figure 1 As shown: The track centerline and track surface elevation have deviated, and corrective measures need to be implemented.
[0038] A method for correcting the offset of existing track bed with embedded long sleepers, to be implemented during the track maintenance window, includes the following steps:
[0039] S1: Use a level and total station to verify the CPⅢ data of the construction section, check the precision measurement network, use a fine adjustment trolley to collect the geometric dimensions of the line, investigate the height adjustment pads and gauge blocks of each fastener in the rectification section, and determine the deviation value between the current track surface alignment and the target alignment in the correction area.
[0040] S2: Based on the structural characteristics of ballastless track, corresponding reaction piers 34 are set on both sides of the track. The force-bearing surface of the reaction piers 34 is parallel to the side of the track slab 33.
[0041] S3: Separate track slab 33 by horizontally cutting along the bottom of track slab 33 using a wire saw. The wire saw cut should ensure no damage to the reinforcing steel bars within track slab 33 and base plate 40. After separation, a void layer will form between the track slab 33 and base plate 40. Before the void layer is fully filled and restored, and before the end of the track maintenance window, quick-setting mortar bags should be poured into the wire saw cut surface to temporarily fill or support the void layer. A lateral restraint should be installed between the separated track slab 33 and the reaction pier 34 to ensure track stability and train safety during speed-limited operation.
[0042] S4: To reduce the lateral stiffness of track slab 33, decrease the correction resistance, and prevent cracking of track slab 33, remove the concrete at the start and end points of the track slab correction unit. The concrete removal area should be located in the exact middle of the two sleepers, and 200mm should be removed longitudinally along the track. The track slab reinforcement should be preserved during removal.
[0043] S5: Raise the track slab 33 to the target elevation position.
[0044] S6: Release the lateral restraints and install a lateral loading mechanism between the track slab 33 and the reaction pier 34. Use the reaction pier as a support to correct the lateral deviation of the track slab 33. Remove and adjust the fasteners as needed based on the on-site alignment control conditions, and replace them with standard fasteners. When correcting the deviation of ballastless track, the jacking load should be applied in stages, and the loading magnitude and speed should be adjusted according to the displacement of the track structure.
[0045] S7: After track slab 33 is corrected to the target plane position, the void layer under track slab 33 is repaired. Before repairing the void layer, weak interlayers and debris within the void layer should be cleaned. The void layer between track slab 33 and the lower structure is repaired with polymer cement mortar using pressure grouting. During grouting, limiting measures are taken to prevent track slab 33 from floating and shifting. The elevation and centerline of the track slab need to be monitored in real time during grouting. If any abnormality is found, grouting should be stopped immediately and dealt with. Lateral limiting is applied before track slab 33 finally restores its structural integrity. After the void layer repair material reaches the design strength, rebar anchoring is carried out on a sleeper-by-sleeve basis within the separation range between track slab 33 and the lower structure.
[0046] S8: Use polymer concrete to restore the removed section of track slab 33; remove and restore the original site at reaction pier 34.
[0047] During the lifting of track slab 33 and lateral correction, the displacement of the track slab is monitored synchronously throughout the process. A total station is used to monitor the centerline offset and elevation, which should not exceed the target alignment B2 and C2. During the offset of track slab 33, a dedicated person is assigned to observe the surrounding track structure and reaction piers. If cracks are found in the track structure or displacement of reaction piers, they should be rectified immediately. After the completion of each track window, the geometric dimensions of the line are checked, and the geometric dimensions of the line must meet the conditions for line opening.
[0048] like Figure 7 As shown: A combination of screw rod 36 and inner and outer threaded sleeves 37 is used to lift the track slab 33. The bottom of the inner and outer threaded sleeves 33 is temporarily bonded to the bottom steel gasket 38 to seal the bottom opening of the pipe, preventing the anchoring adhesive from flowing into the inner and outer threaded sleeves 33. A hole is drilled on the top surface of the track slab 33, penetrating its thickness. Anchoring adhesive is placed in the hole, and the inner and outer threaded sleeves 37, which are bonded to the bottom steel gasket 38, are installed in the hole so that the outer wall of the inner and outer threaded sleeves 37 is bonded to the hole wall. Screw rod 36 is screwed into the inner and outer threaded sleeves 37. The bottom end of screw rod 36 is rounded, and the top of screw rod 36 extends from the top surface of track slab 33. A wrench 39 is connected to the top of screw rod 36. Rotating screw rod 36 lifts track slab 33.
[0049] The fully threaded exterior of the inner and outer threaded sleeve 37 increases friction, while the threaded lower part of the interior concentrates the force on the bottom of the track slab 33 during lifting, effectively preventing cracks on the surface of the track slab 33. The hexagonal cap at the top of the lead screw 36 is cut from a single piece of lead screw, making it less prone to breakage during track slab lifting. The steel gasket 38 at the bottom of the pipe prevents anchoring adhesive from entering the pipe during the installation of the inner and outer threaded sleeve 37. After the lead screw 36 is screwed in, the steel gasket bears the force, preventing the lead screw 36 from abrading the bottom concrete. At the same time, when the track slab 33 slides during correction, the rounded bottom of the lead screw 36 and the steel gasket 38 at the bottom of the pipe can slide easily, reducing correction resistance.
[0050] The track slabs in the double-block ballastless track bed and the turnout area are cut using different tools.
[0051] The track slab separation of the double-block ballastless track bed is achieved using a horizontal cutting wire saw. The horizontal cutting wire saw includes a track trolley 1 and a first cutting wire 5. The track trolley 1 slides on the track 11 via its traveling wheels 2. The track trolley 1 carries an equipment frame 3, which is equipped with two first guide wheels 4, several auxiliary wheels, a drive wheel 6, and a torque output mechanism. The two first guide wheels 4 are located on both sides of the track slab. The first guide wheels 4 are connected to the equipment frame 3 via a steering wheel 8. The axis of the steering wheel 8 is vertical. The closed loop of the first cutting wire 5 has a disconnectable joint. The first cutting wire 5 is disconnected from the joint. The first cutting wire 5 passes through the track slab through a drilled hole and is then reconnected to form a loop. The first cutting wire 5 is held and tensioned on the two first guide wheels 4, several auxiliary wheels, and the drive wheel 6. The drive wheel 6 is connected to the torque output mechanism to drive the first cutting wire 5 to rotate cyclically for cutting operations. The cutting wire segment located between the two first guide wheels 4 is aligned with the connection line between the track slab and the base plate.
[0052] The system includes several auxiliary wheels, including a reversing auxiliary wheel 7 and two tensioning auxiliary wheels 9. The first cutting rope 5 starts from the first guide wheel 4 on the left side of the track plate, changes direction via the reversing auxiliary wheel 7, passes above the first tensioning auxiliary wheel 9 and below the second tensioning auxiliary wheel 9, and then changes direction again via the drive wheel 6 and the first guide wheel 4 on the right side of the track plate to return to the starting point. The first cutting rope 5 increases its contact length with the drive wheel 6 by being moved up and down by the two tensioning auxiliary wheels 9, preventing the drive wheel 6 from slipping due to insufficient friction.
[0053] like Figure 3 The drive wheel 6 has a coaxial structure of a pulley and a wire rope pulley. The pulley is connected to the output pulley of the torque output mechanism via a transmission belt, and the cutting rope 5 is wound around the wire rope pulley. The torque output mechanism is a motor 10, which is powered by a cable or by a generator installed on the track trolley 1.
[0054] The equipment frame 3 includes an upper crossarm and a lower crossarm, which are connected by columns at both ends. The lower crossarm is placed horizontally on the track trolley 1, and the steering wheel 8 is installed at the bottom of the column. The equipment frame 3 is connected to the column by a support rod.
[0055] Because the track slabs are wider in the turnout area, horizontal wire saws cannot be used there. Figure 8 , Figure 9 , Figure 10 As shown: The track slab separation in the turnout area is achieved using a transverse cutting wire saw. The transverse cutting wire saw includes a base 12, a main frame arm 13, an upper crawling frame 14, a lower crawling frame 15, and a second cutting wire 16. The base 12 is fixed relative to the track slab to support the entire wire saw. The main frame arm 13 is fixed to the base 12 and has a linear guide rail perpendicular to the track slab surface. The upper crawling frame 14 and the lower crawling frame 15 are slidably mounted on the main frame arm 13 in cooperation with the guide rail. The upper crawling frame 14 has n auxiliary wheels 17, where n is an integer ≥ 2. The lower crawling frame 15 has n-1 drive wheels 18 and two second guide wheels 19. The axles of the auxiliary wheels 17 and the drive wheels 18 are parallel to each other. The wheels and rims are in the same plane. Spatially, the power wheel 18 is located between the two auxiliary wheels 17, and the two second guide wheels 19 are distributed on both sides of the n-1 power wheels 18. The annular second cutting rope 16 has a detachable joint. The track plate has two holes at the front and back. The second cutting rope 16 is broken from the joint, passes through the holes, is fitted onto the track plate between the two holes, and then reconnected to form a ring. The second cutting rope 16 is reciprocated and stored between the n auxiliary wheels 17 and the n-1 power wheels 18, and is guided to the cutting position by the second guide wheels 19 on both sides. The rotation of the power wheel 18 drives the second cutting rope 16 to perform the cutting operation. As the cutting progresses, the upper climbing frame 14 is adjusted to tighten the second cutting rope 16.
[0056] The main frame arm 13 is made of square steel. The main frame arm 13 body serves as a linear slide rail. A rack 25 parallel to its length is fixed on the main frame arm 13. The upper crawling frame 14 and the lower crawling frame 15 are clamped on the main frame arm 13 and driven to climb along the main frame arm 13 by the crawling gear 23 of their respective power mechanisms meshing with the rack 25.
[0057] The upper crawler frame 14 is clamped onto the main frame arm 13 by two rows of limit wheels 24. A crawler gear 23 of the power mechanism of the upper crawler frame 14 meshes with a rack 25. The limit wheels 24 act as sliding limits, keeping the upper crawler frame 14 on the main frame arm 13 and sliding in a straight line. The crawler gear 23 meshes with the rack 25 to drive the upper crawler frame 14 to move and fix the upper crawler frame 14 at a preset position.
[0058] The lower crawler frame 15 is connected to the main frame arm 13 through its own sliding groove. The two crawler gears 23 of the power mechanism of the lower crawler frame 15 mesh with the rack 25. The two crawler gears 23 are used to maintain the stable sliding contact between the lower crawler frame 15 and the main frame arm 13. On the other hand, the two crawler gears 23 mesh with the rack 25 to drive the lower crawler frame 15 to move and fix the lower crawler frame 15 at a preset position.
[0059] As the distance between the upper crawler 14 and the lower crawler 15 increases, a longer second cutting rope 16 is stored between the auxiliary wheel 17 and the power wheel 18. As the distance between the upper crawler 14 and the lower crawler 15 decreases, the longer second cutting rope 16 is released into the cutting area. Adjusting the distance between the upper crawler 14 and the lower crawler 15 changes the tension of the second cutting rope 16.
[0060] The base 12 is reinforced by a diagonal brace 20 connected to the main frame arm 13. The diagonal brace 20 is located on the side of the main frame arm 13 facing away from the cutting area of the second cutting rope 16. Several vertically arranged diagonal brace adjustment and fixing clips 21 are distributed on the main frame arm 13 above the range of motion of the upper climbing frame 14. The lower end of the diagonal brace 20 is connected to the base 12, and the upper end is optionally connected to the diagonal brace adjustment and fixing clip 21.
[0061] The wheel leg supporting the second guide wheel 19 is connected to the lower crawler frame 15 via a vertical pivot. Swinging the second guide wheel 19 can change the cutting direction of the second cutting rope 16.
[0062] The main frame arm 13 and the base 12 are bolted together to form an L-shape. The upper climbing frame 14 is connected to the main frame arm 13 by eight silicone climbing limit wheels with a diameter of 5cm. One power climbing gear is installed on each side of the upper climbing frame 14, meshing with the rack 25 on the main frame arm 13 to adjust the elevation of the upper climbing frame 14. Two power wheels 8 are installed on the lower climbing frame 15, and two second guide wheels 19 are installed at the bottom to guide the direction of the second cutting rope 16. Two power wheels 8 are also installed on each side of the lower climbing frame 15. The crawling gear meshes with the rack 25 on the main frame arm 13, thereby adjusting the elevation of the lower crawling frame 15. The base 12 is anchored to the base surface with four 2cm diameter screws and then bolted together. The second cutting rope 16 passes through the right guide wheel, the top right auxiliary wheel, the right power wheel, the top middle auxiliary wheel, the left power wheel, the top left auxiliary wheel, and returns to the left guide wheel. It then passes through the transverse hole of the track plate and connects to the second cutting rope 16 joint, forming a closed loop to form a transverse second cutting rope saw for ballastless track bed correction. The second cutting rope 16 is driven by the rotation of the power wheel 18 to perform horizontal transverse cutting of concrete. As the cutting progresses, the upper crawling frame 14 is adjusted to tighten the second cutting rope 16 for cutting.
[0063] like Figure 4 , Figure 5 , Figure 6 As shown: The lateral limiting mechanism includes a fixed-end base 26, a fixed-end base sleeve 27, a movable-end base rod 28, a movable-end base 29, a rotating sleeve 30, and a rotating screw 31; the fixed-end base sleeve 27 is fixedly connected to the fixed-end base 26, and the back of the fixed-end base sleeve 27 is perpendicular to the back of the fixed-end base 26. The back of the fixed-end base 26 is the surface that contacts the support pier, and the fixed-end base sleeve 27 is engraved with internal threads; the movable-end base rod 28 is fixedly connected to the movable-end base 29, and the back of the movable-end base rod 28 is perpendicular to the back of the movable-end base 29. The surface is vertical, and the back of the movable end support 29 is the surface that contacts the track slab; the rotating sleeve 30 is movably sleeved on the movable end support ball rod 28, and the end of the movable end support ball rod 28 abuts against the support part inside the rotating sleeve 30. The rotating sleeve 30 is engraved with internal threads; one end of the rotating screw 31 is threaded into and tightened to the rotating sleeve 30, and the other end is threaded into the fixed end support sleeve 27. The rotating sleeve 30 rotates with the rotating screw 31, and the rotating screw 31 rotates in and out relative to the fixed end support sleeve 27, so that the lateral limiting support is placed between the track slab and the support pier.
[0064] The internally threaded isolation plate 32 of the rotating sleeve 30 serves as a support. The surface of the movable end bottom support ball rod 28 that contacts the isolation plate 32 is spherical. The movable end bottom support ball rod 28 remains stationary, and the friction between the isolation plate 32 and the movable end bottom support ball rod 28 is reduced when the rotating sleeve 30 rotates. The end of the rotating screw 31 that is screwed into the rotating sleeve 30 abuts against the isolation plate 32. The movable end bottom support ball rod 28 includes a cylindrical section and a ball head. The cylindrical section and the movable end bottom support 28... 9 are connected, and the ball head is coaxially fixed to the cantilever end of the cylindrical section; one end of the rotating sleeve 30 has a bottom, and the bottom plate has a hole that matches the cylindrical section. The rotating sleeve 30 is rotatably sleeved on the movable end bottom support ball rod 28 through the hole. The tube hole of the rotating sleeve 30 includes a smooth hole section that matches the ball head and an internal thread section that matches the external thread of the isolation plate 32. The ball head of the movable end bottom support ball rod 28 slides in contact with the rotating sleeve 30 and radially supports the rotating sleeve 30.
[0065] A nut 35 is coaxially fixed to the rotating lead screw 31. Torque is applied to the rotating lead screw 31 through the nut 35. When the rotating lead screw 31 is screwed into the rotating sleeve 30 until its end abuts against the isolation plate 32, the nut 35 is aligned with the opening of the rotating sleeve 30. The end of the rotating lead screw 31 that is screwed into the rotating sleeve 30 is a ball head. When the rotating lead screw 31 is rotated in the forward direction, the rotating lead screw 31 is tightly connected to the rotating sleeve 30, and the rotating sleeve 30 rotates with the rotating lead screw 31. The rotating lead screw 31 is screwed out from the fixed end bottom support sleeve 27, and its lateral extension is limited. When the rotating lead screw 31 is rotated in the reverse direction, the rotating lead screw 31 is screwed into the fixed end bottom support sleeve 27, and its lateral shortening is limited.
[0066] The above description of the disclosed embodiments enables those skilled in the art to make or use the invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the invention. Therefore, the invention is not to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A method for correcting the offset of existing track bed with embedded long sleepers, characterized in that: This is to be carried out during the maintenance window for train operation, and includes the following steps: S1: Determine the deviation between the current track alignment and the target alignment in the correction area; S2: Set up reaction piers (34) on both sides of the line; S3: Release the track slab (33). After the track slab (33) is separated from the lower structure, a void layer is formed between the layers. Before the void layer is finally filled and restored, a quick-hardening mortar bag is injected into the cut surface to temporarily fill the void layer before the end of the skylight period. A lateral limit is set between the released track slab (33) and the reaction pier (34). For the separation of track slabs in a double-block ballastless track bed, a horizontal cutting wire saw is used. The horizontal cutting wire saw includes a track trolley (1) and a first cutting wire (5). The track trolley (1) slides on the track (11) via its traveling wheels (2). The track trolley (1) carries an equipment frame (3). The equipment frame (3) is equipped with two first guide wheels (4), several auxiliary wheels, a drive wheel (6), and a torque output mechanism. The two first guide wheels (4) are located on both sides of the track slab. The first guide wheels (4) are connected to the equipment frame (3) via a steering wheel (8). The steering wheel (8) has a vertical shaft. The first cutting rope (5) of the closed loop has a disconnectable joint. The first cutting rope (5) is disconnected from the joint. The first cutting rope (5) passes through the track plate through a drilled hole and is then connected into a loop. The first cutting rope (5) is held on two first guide wheels (4), several auxiliary wheels and drive wheels (6) and is tensioned. The drive wheels (6) are connected to the torque output mechanism to drive the first cutting rope (5) to rotate cyclically to perform cutting operations. The cutting rope segment located between the two first guide wheels (4) is aligned with the connection line between the track plate and the base plate. Several auxiliary wheels include a reversing auxiliary wheel (7) and two tensioning auxiliary wheels (9). The first cutting rope (5) starts from the first guide wheel (4) on the left side of the track plate, changes direction through the reversing auxiliary wheel (7), passes above the first tensioning auxiliary wheel (9) and below the second tensioning auxiliary wheel (9) in sequence, and then changes direction through the drive wheel (6) and the first guide wheel (4) on the right side of the track plate to return to the starting point. For the separation of track slabs in the turnout area, a transverse cutting wire saw is used. The transverse cutting wire saw includes a base (12), a main frame arm (13), an upper climbing frame (14), a lower climbing frame (15), and a second cutting wire (16). The base (12) is fixed relative to the track slab to support the entire wire saw. The main frame arm (13) is fixed on the base (12). The main frame arm (13) has a straight slide rail perpendicular to the track slab surface. The upper climbing frame (14) and the lower climbing frame (15) are slidably mounted on the main frame arm (13) in cooperation with the slide rail. The upper climbing frame (14) has n auxiliary wheels (17), where n is an integer ≥ 2. The lower climbing frame (15) has n-1 drive wheels (18) and two second guide wheels (19). The auxiliary wheels (17) and the drive wheels (18) The rotating shafts of the wheels are parallel and the rims are in the same plane. In space, the power wheel (18) is located between the two auxiliary wheels (17), and the two second guide wheels (19) are distributed on both sides of the n-1 power wheels (18). The ring-shaped second cutting rope (16) has a disconnectable joint. The track plate has two holes at the front and back. The second cutting rope (16) is disconnected from the joint, and after passing through the holes, it is put on the track plate between the two holes and then connected to form a ring. The second cutting rope (16) is stored between the n auxiliary wheels (17) and the n-1 power wheels (18) and is guided to the cutting position by the second guide wheels (19) on both sides. The rotation of the power wheel (18) drives the second cutting rope (16) to perform the cutting operation. As the cutting progress is adjusted, the upper climbing frame (14) is tightened to tighten the second cutting rope (16). S4: Remove the concrete at the start and end points of the track slab correction unit; S5: Raise the track slab (33) to the target elevation position; S6: Release the lateral limit and set a lateral loading mechanism between the track plate (33) and the reaction pier (34) for lateral correction; S7: After the track slab (33) is corrected to the target plane position, the void layer under the track slab (33) is repaired. Before the track slab (33) finally restores the structural integrity, a lateral limit is applied. After the void layer repair material reaches the design strength, the track slab (33) is anchored with rebars one by one in the separation range from the lower structure. S8: Restore the section of track slab (33) that was removed; clear and restore the original site at the reaction pier (34).
2. The method for correcting the offset of existing railway track with embedded long sleepers according to claim 1, characterized in that, Step S1 specifically includes: using a level and total station to verify the CPⅢ data of the construction section, reviewing the precision measurement network, using a fine-tuning trolley to collect the geometric dimensions of the line, investigating the height adjustment pads and gauge blocks of each fastener in the rectification section, and determining the deviation value between the current track surface alignment and the target alignment in the correction area.
3. The method for correcting the offset of existing track bed with embedded long sleepers according to claim 2, characterized in that: During the process of raising the track slab (33) and lateral correction, the displacement of the track slab is monitored synchronously throughout the process. A total station is used to monitor the centerline offset and elevation. After each skylight is completed, the geometric dimensions of the line are checked and the geometric dimensions of the line must meet the conditions for the line to be opened.
4. The method for correcting the offset of existing railway track bed with embedded long sleepers according to claim 1, characterized in that: The track plate (33) is lifted by a combination of screw rod (36) and inner and outer threaded sleeves (37). The bottom of the inner and outer threaded sleeves (33) is temporarily bonded to the bottom steel gasket (38) to seal the bottom opening of the pipe. A hole is drilled on the top surface of the track plate (33) with the hole depth penetrating its thickness. Rebar adhesive is placed in the hole. The inner and outer threaded sleeves (37) that are bonded to the bottom steel gasket (38) are installed in the hole so that the outer wall of the inner and outer threaded sleeves (37) is bonded to the hole wall. The screw rod (36) is screwed into the inner and outer threaded sleeves (37). The top of the screw rod (36) extends out from the top surface of the track plate (33). A wrench (39) is connected to the top of the screw rod (36). The screw rod (36) is rotated to lift the track plate (33).
5. The method for correcting the offset of existing track bed with embedded long sleepers according to claim 1, characterized in that: The lateral limiting mechanism includes a fixed end base (26), a fixed end base sleeve (27), a movable end base rod (28), a movable end base (29), a rotating sleeve (30), and a rotating screw (31); the fixed end base sleeve (27) is fixedly connected to the fixed end base (26), and the back of the fixed end base sleeve (27) is perpendicular to the back of the fixed end base (26). The back of the fixed end base (26) is the surface that contacts the support pier, and the fixed end base sleeve (27) is engraved with internal threads; the movable end base rod (28) is fixedly connected to the movable end base (29), and the movable end base rod (28) is perpendicular to the back of the movable end base (29). The back is vertical, and the back of the movable end support (29) is the surface that contacts the track plate; the rotating sleeve (30) is movably sleeved on the movable end support ball rod (28), and the end of the movable end support ball rod (28) abuts against the support part inside the rotating sleeve (30). The rotating sleeve (30) is engraved with internal threads; one end of the rotating screw (31) is threaded into and tightened to the rotating sleeve (30), and the other end is threaded into the fixed end support sleeve (27). The rotating sleeve (30) rotates with the rotating screw (31), and the rotating screw (31) rotates in and out relative to the fixed end support sleeve (27), so that the lateral limiting support is placed between the track plate and the support pier.
6. The method for correcting the offset of existing track bed with embedded long sleepers according to claim 5, characterized in that: The internal thread of the rotating sleeve (30) connects to the isolation plate (32) as a support part. The surface of the movable end bottom support ball rod (28) that contacts the isolation plate (32) is spherical. The end of the rotating screw (31) that is screwed into the rotating sleeve (30) abuts against the isolation plate (32). The movable end bottom support ball rod (28) includes a cylindrical section and a ball head. The cylindrical section is connected to the movable end bottom support (29). The ball head is coaxially fixed to the cantilever end of the cylindrical section. One end of the rotating sleeve (30) has a bottom. A hole adapted to the cylindrical section is opened on the bottom plate. The rotating sleeve (30) can be rotatably sleeved on the movable end bottom support ball rod (28) through the hole. The tube hole of the rotating sleeve (30) includes a smooth hole section adapted to the ball head and an internal thread section matching the external thread of the isolation plate (32).
7. The method for correcting the offset of existing track bed with embedded long sleepers according to claim 1, characterized in that, In step S7: the void between the track slab (33) and the lower structure is repaired with polymer cement mortar and pressure grouting is used; during grouting, limiting measures are taken to prevent the track slab (33) from floating and shifting.