A method for constructing a suspended elevator shaft
By using a simulated construction suspension frame and pre-embedded deformation monitors, the problems of limited space and difficult dismantling during the construction of suspended elevator shafts were solved, enabling orderly construction and safety monitoring, and ensuring the seismic isolation effect.
Patent Information
- Application Number
- CN202311006956.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-10
- Publication Date
- 2025-10-28
- Estimated Expiration
- 2043-08-10
AI Technical Summary
In the existing construction of suspended elevator shafts, the distance between the suspended elevator shaft and the basement elevator drop plate is small, resulting in no operating space for construction workers, difficulty in removing the support body, and difficulty in ensuring the seismic isolation effect.
A top-down simulated construction suspension frame is adopted, with pre-embedded suspension frame deformation monitors. Precast wall panels are installed layer by layer through the suspension frame, avoiding the laying of a support foundation layer inside the basement elevator slab, and ensuring that the shaft and the basement elevator slab are disconnected below the seismic isolation layer.
This enabled the orderly construction of the suspended elevator shaft, avoiding the difficulties of dismantling the supporting foundation layer in a confined space, ensuring the seismic isolation effect, and allowing for real-time monitoring of the elevator shaft's operational safety through a monitor.
Smart Images

Figure CN117027322B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of suspended elevator shaft construction technology, and specifically relates to a method for constructing a suspended elevator shaft. Background Technology
[0002] Seismic isolation structures are widely used in many buildings, such as elevators. Elevator shafts are the channels through which elevators are installed, and their dimensions are determined by the elevator model. Existing seismic isolation elevator shafts effectively assist in elevator installation and use, and can also filter out frequencies in the incoming seismic waves that resonate with the structure, thus providing excellent seismic wave shielding. The seismic isolation elevator shaft needs to be disconnected from the basement elevator slab below the isolation layer, and then connected to the upper structure of the isolation layer to form a suspended elevator shaft. However, the small distance between the suspended elevator shaft and the basement elevator slab results in insufficient operating space for construction workers, and makes the later dismantling of the bottom and side supports difficult. Summary of the Invention
[0003] The technical problem to be solved by this invention is to address the shortcomings of the prior art by providing a method for constructing suspended elevator shafts. This method utilizes a simulated suspended frame from top to bottom, providing an installation foundation for the precast wall panels of the suspended elevator shaft. This avoids laying a support foundation layer inside the basement elevator slab. The precast wall panels are then assembled sequentially from bottom to top, ensuring orderly construction and eliminating the need for later removal of the support foundation layer in confined spaces. This ensures the shaft of the seismic isolation elevator shaft is disconnected from the basement elevator slab below the seismic isolation layer. Simultaneously, a deformation monitor is embedded in the suspended frame to monitor real-time deformation data, thus monitoring the safe operation of the suspended elevator shaft and facilitating widespread use.
[0004] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is: a method for constructing a suspended elevator shaft, characterized in that the method includes the following steps:
[0005] Step 1: Constructing the suspended frame, the process is as follows:
[0006] Step 101: Install elevator shaft suspension frame embedded parts in the seismic isolation layer, and fix the first layer suspension frame to the elevator shaft suspension frame embedded parts.
[0007] Step 102: Connect the bottom of the first-layer suspension frame using the first-layer supporting steel beam;
[0008] Step 103: Fix the second layer of suspension frame to the bottom of the first layer of supporting steel beam;
[0009] Step 104: Use the second layer of supporting steel beams to connect the bottom of the second layer of suspension frame;
[0010] Step 105: Fix the third layer of suspension frame to the bottom of the second layer support steel beam;
[0011] Step 106: Use the third-layer supporting steel beam to connect the bottom of the third-layer suspension frame to form a suspension frame, which extends into the basement elevator lowering slab.
[0012] Step 2: Constructing the elevator shaft bottom plate: Hoist the elevator shaft bottom plate from the shaft opening into the suspension frame and install it on the third-floor support steel beam;
[0013] Step 3: Construct the third layer of precast wall panels: hoist the third layer of precast wall panels into the suspension frame through the well opening and install them on the third layer of suspension frame;
[0014] Step 4: Construct the second layer of precast wall panels: hoist the second layer of precast wall panels into the suspension frame through the well opening and install them on the second layer of suspension frame;
[0015] Step 5: Construct the first layer of precast wall panels: hoist the first layer of precast wall panels from the well hole into the suspension frame and install them on the first layer of suspension frame;
[0016] Step 6: Pre-embed the deformation monitoring device for the suspension frame;
[0017] Step 7: Waterproofing and seepage prevention treatment: Apply waterproofing and seepage prevention treatment to all joints.
[0018] The above-mentioned method for constructing a suspended elevator shaft is characterized in that: the first layer of suspended frame, the first layer of supporting steel beam, the second layer of suspended frame, the second layer of supporting steel beam, the third layer of suspended frame, and the third layer of supporting steel beam are all galvanized anti-corrosion steel structures; the structural dimensions of the first layer of suspended frame, the second layer of suspended frame, and the third layer of suspended frame are all the same, and the first layer of suspended frame, the second layer of suspended frame, and the third layer of suspended frame are aligned and connected sequentially from top to bottom; the structural dimensions of the first layer of supporting steel beam, the second layer of supporting steel beam, and the third layer of supporting steel beam are all the same, and the first layer of supporting steel beam, the second layer of supporting steel beam, and the third layer of supporting steel beam are arranged in parallel sequentially from top to bottom.
[0019] The above-mentioned method for constructing a suspended elevator shaft is characterized in that: the first layer of the suspended frame, the second layer of the suspended frame, and the third layer of the suspended frame each include four vertical angle steels arranged in an array and symmetrically arranged at the center, and a T-shaped steel strip is provided between two adjacent vertical angle steels along the circumferential direction; the first layer of the supporting steel beam, the second layer of the supporting steel beam, and the third layer of the supporting steel beam each include multiple horizontal angle steels, and the multiple horizontal angle steels are connected in sequence to form a rectangular ring.
[0020] The above-mentioned method for constructing a suspended elevator shaft is characterized in that: the third layer precast wall panel, the second layer precast wall panel and the first layer precast wall panel each include two left side wall precast panels, two right side wall precast panels, one front side wall precast panel and one rear side wall precast panel, and the front side wall precast panel and the rear side wall precast panel each include a first side wall precast panel and a second side wall precast panel.
[0021] The above-mentioned method for constructing a suspended elevator shaft is characterized in that: during the third step of construction, the two left side precast panels of the third layer precast wall panel are first installed into the two spaces formed by the two vertical angle steels and T-shaped steel strips on the left side of the third layer suspension frame, and the two right side precast panels of the third layer precast wall panel are installed into the two spaces formed by the two vertical angle steels and T-shaped steel strips on the right side of the third layer suspension frame, and the bottoms of the two left side precast panels and the two right side precast panels of the third layer precast wall panel abut against the bottom plate of the elevator shaft, and the tops of the two left side precast panels and the two right side precast panels of the third layer precast wall panel abut against the bottom of the second layer support steel beam;
[0022] Then, install the first side wall precast panel of the front and rear side wall precast panels of the third layer into the gap between the T-shaped steel strip and the left side wall precast panel at the corresponding positions.
[0023] Finally, the precast panels of the front and rear sides of the third layer of precast wall panels are installed into the gaps between the T-shaped steel strips and the right side wall panels at the corresponding positions.
[0024] The bottoms of the first and second precast side walls of the third layer precast wall panel abut against the bottom slab of the elevator shaft, and the tops of the first and second precast side walls of the third layer precast wall panel abut against the bottom of the second layer supporting steel beam.
[0025] The above-mentioned method for constructing a suspended elevator shaft is characterized in that: during step four, the two left-side precast panels of the second-layer precast wall panel are first installed into the two spaces formed by the two vertical angle steels and T-shaped steel strips on the left side of the third-layer suspended frame, and the two right-side precast panels of the second-layer precast wall panel are installed into the two spaces formed by the two vertical angle steels and T-shaped steel strips on the right side of the third-layer suspended frame, and the bottoms of the two left-side precast panels and the two right-side precast panels of the second-layer precast wall panel abut against the top of the second-layer supporting steel beam, and the tops of the two left-side precast panels and the two right-side precast panels of the second-layer precast wall panel abut against the bottom of the first-layer supporting steel beam;
[0026] Then, install the first side wall precast panel of the front and rear side wall precast panels of the second layer into the gap between the T-shaped steel strip and the left side wall precast panel at the corresponding positions.
[0027] Finally, the precast panels of the front and rear sides of the second layer of precast wall panels are installed into the gaps between the T-shaped steel strips and the right side wall panels at the corresponding positions.
[0028] The bottom of the first and second precast side walls of the second layer of precast wall panels abut against the top of the second layer of supporting steel beams, and the top of the first and second precast side walls of the second layer of precast wall panels abut against the bottom of the first layer of supporting steel beams.
[0029] The above-mentioned method for constructing a suspended elevator shaft is characterized in that: during step five, the two left-side precast panels of the first-layer precast wall panel are first installed into the two spaces formed by the two left vertical angle steels and T-shaped steel strips in the third-layer suspended frame, and the two right-side precast panels of the first-layer precast wall panel are first installed into the two spaces formed by the two right vertical angle steels and T-shaped steel strips in the third-layer suspended frame, and the bottoms of the two left-side precast panels and the two right-side precast panels of the first-layer precast wall panel abut against the top of the first-layer supporting steel beam, and the tops of the two left-side precast panels and the two right-side precast panels of the first-layer precast wall panel abut against the bottom of the seismic isolation layer;
[0030] Then, install the first side wall precast panels of the front and rear side wall precast panels of the first layer of precast wall panels into the gaps between the T-shaped steel strips and the left side wall precast panels at the corresponding positions.
[0031] Finally, the precast panels of the front and rear sides of the first layer of precast wall panels are installed into the gaps between the T-shaped steel strips and the right side wall panels at the corresponding positions.
[0032] The bottom of the first and second precast side walls of the first layer of precast wall panels abut against the top of the first layer of supporting steel beams, and the top of the first and second precast side walls of the first layer of precast wall panels abut against the bottom of the seismic isolation layer.
[0033] The above-mentioned method for constructing a suspended elevator shaft is characterized in that: the suspended frame deformation monitor includes multiple displacement sensors.
[0034] The beneficial effects of this invention are that by adopting a simulated construction suspension frame from top to bottom, an installation foundation is provided for the prefabricated wall panels of the suspended elevator shaft, avoiding the need to lay a supporting foundation layer inside the basement elevator slab. Then, by assembling the prefabricated wall panels sequentially from bottom to top, the construction is orderly and eliminates the construction process of dismantling the supporting foundation layer in a confined space later. This ensures that the shaft of the seismic isolation elevator shaft is disconnected from the basement elevator slab below the seismic isolation layer. At the same time, a suspension frame deformation monitor is embedded in the suspension frame to monitor the real-time data of whether the suspension frame is deformed, and to monitor the safe operation status of the suspended elevator shaft, which is convenient for widespread use.
[0035] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. Attached Figure Description
[0036] Figure 1 This is a schematic diagram of the first layer of the suspended frame for the construction of this invention.
[0037] Figure 2 This is a schematic diagram of the suspended frame after the construction of this invention.
[0038] Figure 3 This is a schematic diagram of the construction elevator shaft bottom plate of the present invention.
[0039] Figure 4 This is a schematic diagram of the construction of the third layer of precast wall panels according to the present invention.
[0040] Figure 5 This is a schematic diagram of the construction of the second layer of precast wall panels according to the present invention.
[0041] Figure 6 This is a schematic diagram of the construction of the first layer of precast wall panels according to the present invention.
[0042] Figure 7 This is a rendering showing the effect of the completed construction of this invention.
[0043] Figure 8 This is a flowchart of the method of the present invention.
[0044] Explanation of reference numerals in the attached figures:
[0045] 1—Seismic isolation layer; 2—Well opening; 3—Basement elevator drop slab;
[0046] 4—First layer of suspension frame; 5—First layer of supporting steel beam; 6—Second layer of suspension frame;
[0047] 7—Second-layer supporting steel beam; 8—Third-layer suspension frame; 9—Third-layer supporting steel beam;
[0048] 10—Elevator shaft bottom slab; 11—Left side wall precast slab; 12—Right side wall precast slab;
[0049] 13—First side wall precast panel; 14—Second side wall precast panel; 15—Second layer precast wall panel;
[0050] 16—First layer of precast wall panel; 17—Vertical angle steel; 18—T-shaped steel strip. Detailed Implementation
[0051] like Figures 1 to 8 As shown, a method for constructing a suspended elevator shaft according to the present invention includes the following steps:
[0052] Step 1: Constructing the suspended frame, the process is as follows:
[0053] Step 101: Install elevator shaft suspension frame embedded parts in the seismic isolation layer 1, and fix the first layer suspension frame 4 to the elevator shaft suspension frame embedded parts.
[0054] Step 102: Connect the bottom of the first layer suspension frame 4 with the first layer support steel beam 5 rings;
[0055] Step 103: Fix the second layer suspension frame 6 to the bottom of the first layer support steel beam 5;
[0056] Step 104: Connect the bottom of the second-layer suspension frame 6 using the 7 rings of the second-layer support steel beam;
[0057] Step 105: Fix the third layer suspension frame 8 to the bottom of the second layer support steel beam 7;
[0058] Step 106: Use the third layer support steel beam 9 rings to connect the bottom of the third layer suspension frame 8 to form a suspension frame, which extends into the basement elevator drop plate 3;
[0059] Step 2, Construction of elevator shaft bottom plate: The elevator shaft bottom plate 10 is hoisted from the shaft hole 2 into the suspension frame and installed on the third-floor support steel beam 9;
[0060] Step 3: Construct the third layer of precast wall panels: hoist the third layer of precast wall panels into the suspension frame through well hole 2 and install them on the third layer suspension frame 8;
[0061] Step 4: Construct the second layer of precast wall panels: hoist the second layer of precast wall panels 15 from the well hole 2 into the suspension frame and install them on the second layer of suspension frame 6;
[0062] Step 5: Construct the first layer of precast wall panels: hoist the first layer of precast wall panels 16 from the well hole 2 into the suspension frame and install them on the first layer of suspension frame 4;
[0063] Step 6: Pre-embed the deformation monitoring device for the suspension frame;
[0064] Step 7: Waterproofing and seepage prevention treatment: Apply waterproofing and seepage prevention treatment to all joints.
[0065] It should be noted that by adopting a simulated construction suspension frame from top to bottom, an installation foundation is provided for the prefabricated wall panels of the suspended elevator shaft. This avoids laying a support foundation layer inside the elevator drop slab in the basement. Then, by assembling the prefabricated wall panels from bottom to top, the construction is orderly and eliminates the construction process of removing the support foundation layer in a confined space later. This ensures that the shaft of the seismic isolation elevator shaft is disconnected from the elevator drop slab in the basement at the bottom of the seismic isolation layer. At the same time, a suspension frame deformation monitor is embedded in the suspension frame to monitor the real-time data of whether the suspension frame is deformed and to monitor the safe operation status of the suspended elevator shaft.
[0066] In this embodiment, the first layer suspension frame 4, the first layer support steel beam 5, the second layer suspension frame 6, the second layer support steel beam 7, the third layer suspension frame 8, and the third layer support steel beam 9 are all galvanized anti-corrosion steel structures. The first layer suspension frame 4, the second layer suspension frame 6, and the third layer suspension frame 8 have the same structural dimensions and are aligned and connected sequentially from top to bottom. The first layer support steel beam 5, the second layer support steel beam 7, and the third layer support steel beam 9 have the same structural dimensions and are arranged in parallel sequentially from top to bottom.
[0067] In this embodiment, the first layer suspension frame 4, the second layer suspension frame 6, and the third layer suspension frame 8 each include four vertical angle steels 17 arranged in an array and centrally symmetrically, and a T-shaped steel strip 18 is provided between two adjacent vertical angle steels 17 along the circumferential direction; the first layer support steel beam 5, the second layer support steel beam 7, and the third layer support steel beam 9 each include multiple horizontal angle steels, and the multiple horizontal angle steels are connected in sequence to form a rectangular ring.
[0068] It should be noted that the number of T-shaped steel strips 18 to be set between two adjacent vertical angle steels 17 along the circumferential direction can be selected according to the size of the elevator shaft and the support strength, which has strong scalability.
[0069] In this embodiment, the third layer precast wall panel, the second layer precast wall panel 15 and the first layer precast wall panel 16 each include two left side wall precast panels 11, two right side wall precast panels 12, one front side wall precast panel and one rear side wall precast panel. The front side wall precast panel and the rear side wall precast panel each include a first side wall precast panel 13 and a second side wall precast panel 14.
[0070] In this embodiment, during the construction of step three, the two left-side precast wall panels 11 of the third-layer precast wall panel are first installed into the two spaces formed by the two left-side vertical angle steels 17 and T-shaped steel strips 18 in the third-layer suspension frame 8, and the two right-side precast wall panels 12 of the third-layer precast wall panel are installed into the two spaces formed by the two right-side vertical angle steels 17 and T-shaped steel strips 18 in the third-layer suspension frame 8. The bottoms of the two left-side precast wall panels 11 and the two right-side precast wall panels 12 of the third-layer precast wall panel abut against the elevator shaft bottom plate 10, and the tops of the two left-side precast wall panels 11 and the two right-side precast wall panels 12 of the third-layer precast wall panel abut against the bottom of the second-layer support steel beam 7.
[0071] Then, the first side wall precast panel 13 of the front side wall precast panel and the rear side wall precast panel of the third layer are installed into the gap between the T-shaped steel strip 18 and the left side wall precast panel 11 at the corresponding positions.
[0072] Finally, the second side wall precast slab 14 of the front side wall precast slab and the rear side wall precast slab of the third layer precast wall slab are installed into the gap between the T-shaped steel strip 18 and the right side wall precast slab 12 at the corresponding positions.
[0073] The bottoms of the first side wall precast slab 13 and the second side wall precast slab 14 of the third layer precast wall panel both abut against the elevator shaft bottom slab 10, and the tops of the first side wall precast slab 13 and the second side wall precast slab 14 of the third layer precast wall panel both abut against the bottom of the second layer support steel beam 7.
[0074] In this embodiment, during step four of construction, the two left-side precast wall panels 11 of the second-layer precast wall panel are first installed into the two spaces formed by the two left-side vertical angle steels 17 and T-shaped steel strips 18 in the third-layer suspension frame 8, and the two right-side precast wall panels 12 of the second-layer precast wall panel are installed into the two spaces formed by the two right-side vertical angle steels 17 and T-shaped steel strips 18 in the third-layer suspension frame 8. The bottoms of the two left-side precast wall panels 11 and the two right-side precast wall panels 12 of the second-layer precast wall panel abut against the top of the second-layer support steel beam 7, and the tops of the two left-side precast wall panels 11 and the two right-side precast wall panels 12 of the second-layer precast wall panel abut against the bottom of the first-layer support steel beam 5.
[0075] Then, the first side wall precast panel 13 of the front side wall precast panel and the rear side wall precast panel of the second layer of precast wall panels are installed into the gap between the T-shaped steel strip 18 and the left side wall precast panel 11 at the corresponding positions.
[0076] Finally, the second side wall precast panels 14 of the front and rear side wall precast panels of the second layer of precast wall panels are installed into the gap between the T-shaped steel strip 18 and the right side wall precast panel 12 at the corresponding positions.
[0077] The bottom of the first side wall precast panel 13 and the second side wall precast panel 14 of the second layer precast wall panel both abut against the top of the second layer support steel beam 7, and the top of the first side wall precast panel 13 and the second side wall precast panel 14 of the second layer precast wall panel both abut against the bottom of the first layer support steel beam 5.
[0078] In this embodiment, during step five of the construction, the two left-side precast wall panels 11 of the first-layer precast wall panel are first installed into the two spaces formed by the two left-side vertical angle steels 17 and T-shaped steel strips 18 in the third-layer suspension frame 8, and the two right-side precast wall panels 12 of the first-layer precast wall panel are installed into the two spaces formed by the two right-side vertical angle steels 17 and T-shaped steel strips 18 in the third-layer suspension frame 8. The bottoms of the two left-side precast wall panels 11 and the two right-side precast wall panels 12 of the first-layer precast wall panel abut against the top of the first-layer support steel beam 5, and the tops of the two left-side precast wall panels 11 and the two right-side precast wall panels 12 of the first-layer precast wall panel abut against the bottom of the seismic isolation layer 1.
[0079] Then, the first side wall precast panel 13 of the front side wall precast panel and the rear side wall precast panel of the first layer of precast wall panels are installed into the gap between the T-shaped steel strip 18 and the left side wall precast panel 11 at the corresponding positions.
[0080] Finally, the precast slabs of the front and rear walls of the first layer of precast wall panels are installed into the gaps between the T-shaped steel strips 18 and the right wall precast slabs 12 at the corresponding positions.
[0081] The bottom of the first side wall precast slab 13 and the second side wall precast slab 14 of the first layer of precast wall panels both abut against the top of the first layer support steel beam 5, and the top of the first side wall precast slab 13 and the second side wall precast slab 14 of the first layer of precast wall panels both abut against the bottom of the seismic isolation layer 1.
[0082] In this embodiment, the suspension frame deformation monitor includes multiple displacement sensors.
[0083] During construction, the two components at all splicing points are connected by a mechanical rigid connection to ensure the construction quality of the elevator shaft.
[0084] The above description is merely a preferred embodiment of the present invention and does not constitute any limitation on the present invention. Any simple modifications, alterations, or equivalent structural changes made to the above embodiments based on the technical essence of the present invention shall still fall within the protection scope of the present invention.
Claims
1. A method for constructing a suspended elevator shaft, characterized in that, The method includes the following steps: Step 1: Constructing the suspended frame, the process is as follows: Step 101: Install elevator shaft suspension frame embedded parts in the seismic isolation layer (1) and fix the first layer suspension frame (4) to the elevator shaft suspension frame embedded parts. Step 102: Use the first layer of supporting steel beams (5) to connect the bottom of the first layer of suspension frame (4); Step 103: Fix the second layer suspension frame (6) to the bottom of the first layer support steel beam (5); Step 104: Use the second layer of supporting steel beams (7) to connect the bottom of the second layer of suspension frame (6); Step 105: Fix the third layer suspension frame (8) to the bottom of the second layer support steel beam (7); Step 106: Use the third layer support steel beam (9) to connect the bottom of the third layer suspension frame (8) to form a suspension frame, which extends into the basement elevator drop plate (3); Step 2, Construction of elevator shaft bottom plate: The elevator shaft bottom plate (10) is hoisted from the shaft hole (2) into the suspension frame and installed on the third-floor support steel beam (9); Step 3: Construct the third layer of precast wall panels: hoist the third layer of precast wall panels into the suspension frame through the well hole (2) and install them on the third layer of suspension frame (8); Step 4: Construct the second layer of precast wall panels: hoist the second layer of precast wall panels (15) into the suspension frame through the well hole (2) and install them on the second layer of suspension frame (6); Step 5: Construct the first layer of precast wall panels: hoist the first layer of precast wall panels (16) into the suspension frame through the well hole (2) and install them on the first layer of suspension frame (4); Step 6: Pre-embed the deformation monitoring device for the suspension frame; Step 7: Waterproofing and seepage prevention treatment: Apply waterproofing and seepage prevention treatment to all joints.
2. A method for constructing a suspended elevator shaft according to claim 1, characterized in that: The first layer suspension frame (4), the first layer support steel beam (5), the second layer suspension frame (6), the second layer support steel beam (7), the third layer suspension frame (8), and the third layer support steel beam (9) are all galvanized anti-corrosion steel structures. The structural dimensions of the first layer suspension frame (4), the second layer suspension frame (6), and the third layer suspension frame (8) are all the same, and the first layer suspension frame (4), the second layer suspension frame (6), and the third layer suspension frame (8) are aligned and connected from top to bottom. The structural dimensions of the first layer support steel beam (5), the second layer support steel beam (7), and the third layer support steel beam (9) are all the same, and the first layer support steel beam (5), the second layer support steel beam (7), and the third layer support steel beam (9) are arranged in parallel from top to bottom.
3. A method for constructing a suspended elevator shaft according to claim 2, characterized in that: The first layer suspension frame (4), the second layer suspension frame (6) and the third layer suspension frame (8) each include four vertical angle steels (17) arranged in an array and symmetrically arranged at the center. A T-shaped steel strip (18) is provided between two adjacent vertical angle steels (17) along the circumferential direction. The first layer support steel beam (5), the second layer support steel beam (7) and the third layer support steel beam (9) each include multiple horizontal angle steels. The multiple horizontal angle steels are connected in sequence to form a rectangular ring.
4. A method for constructing a suspended elevator shaft according to claim 3, characterized in that: The third layer precast wall panel, the second layer precast wall panel (15) and the first layer precast wall panel (16) each include two left side wall precast panels (11), two right side wall precast panels (12), one front side wall precast panel and one rear side wall precast panel. The front side wall precast panel and the rear side wall precast panel each include a first side wall precast panel (13) and a second side wall precast panel (14).
5. A method for constructing a suspended elevator shaft according to claim 4, characterized in that: During the construction of step three, the two left wall precast panels (11) of the third layer precast wall panel are first installed into the two spaces formed by the two vertical angle steels (17) and T-shaped steel strips (18) on the left side of the third layer suspension frame (8). The two right wall precast panels (12) of the third layer precast wall panel are installed into the two spaces formed by the two vertical angle steels (17) and T-shaped steel strips (18) on the right side of the third layer suspension frame (8). The bottoms of the two left wall precast panels (11) and the two right wall precast panels (12) of the third layer precast wall panel are all abutted on the bottom plate (10) of the elevator shaft. The tops of the two left wall precast panels (11) and the two right wall precast panels (12) of the third layer precast wall panel are all abutted on the bottom of the second layer support steel beam (7). Then, the first side wall precast panel (13) of the front side wall precast panel and the rear side wall precast panel of the third layer precast wall panel are installed into the gap between the T-shaped steel strip (18) and the left side wall precast panel (11) at the corresponding positions; Finally, the second side wall precast slab (14) of the front side wall precast slab and the rear side wall precast slab of the third layer precast wall slab are installed into the gap between the T-shaped steel strip (18) and the right side wall precast slab (12) at the corresponding positions; The bottoms of the first side wall precast slab (13) and the second side wall precast slab (14) of the third layer precast wall panel both abut against the bottom plate (10) of the elevator shaft, and the tops of the first side wall precast slab (13) and the second side wall precast slab (14) of the third layer precast wall panel both abut against the bottom of the second layer support steel beam (7).
6. A method for constructing a suspended elevator shaft according to claim 4, characterized in that: During the fourth step of construction, the two left-side precast panels (11) of the second-layer precast wall panel are first installed into the two spaces formed by the two left-side vertical angle steels (17) and T-shaped steel strips (18) in the third-layer suspension frame (8). The two right-side precast panels (12) of the second-layer precast wall panel are then installed into the two spaces formed by the two right-side vertical angle steels (17) and T-shaped steel strips (18) in the third-layer suspension frame (8). The bottoms of the two left-side precast panels (11) and the two right-side precast panels (12) of the second-layer precast wall panel are all abutted against the top of the second-layer support steel beam (7), and the tops of the two left-side precast panels (11) and the two right-side precast panels (12) of the second-layer precast wall panel are all abutted against the bottom of the first-layer support steel beam (5). Then, the first side wall precast panel (13) of the front side wall precast panel and the rear side wall precast panel of the second layer of precast wall panels are installed into the gap between the T-shaped steel strip (18) and the left side wall precast panel (11) at the corresponding positions; Finally, the second side wall precast panels (14) of the front and rear side wall precast panels of the second layer of precast wall panels are installed into the gap between the T-shaped steel strip (18) and the right side wall precast panel (12) at the corresponding positions; The bottom of the first side wall precast slab (13) and the second side wall precast slab (14) of the second layer precast wall panel both abut against the top of the second layer support steel beam (7), and the top of the first side wall precast slab (13) and the second side wall precast slab (14) of the second layer precast wall panel both abut against the bottom of the first layer support steel beam (5).
7. A method for constructing a suspended elevator shaft according to claim 4, characterized in that: During step five of the construction, the two left wall precast panels (11) of the first layer precast wall panel are first installed into the two spaces formed by the two left vertical angle steels (17) and T-shaped steel strips (18) in the third layer suspension frame (8), and the two right wall precast panels (12) of the first layer precast wall panel are installed into the two spaces formed by the two right vertical angle steels (17) and T-shaped steel strips (18) in the third layer suspension frame (8), and the bottoms of the two left wall precast panels (11) and the two right wall precast panels (12) of the first layer precast wall panel abut against the top of the first layer support steel beam (5), and the tops of the two left wall precast panels (11) and the two right wall precast panels (12) of the first layer precast wall panel abut against the bottom of the seismic isolation layer (1); Then, the first side wall precast slab (13) of the front side wall precast slab and the rear side wall precast slab of the first layer of precast wall panels are installed into the gap between the T-shaped steel strip (18) and the left side wall precast slab (11) at the corresponding positions; Finally, the precast slabs of the front and rear sides of the first layer of precast wall panels are installed into the gaps between the T-shaped steel strip (18) and the right side wall panel (12) at the corresponding positions. The bottom of the first side wall precast slab (13) and the second side wall precast slab (14) of the first layer precast wall panel both abut against the top of the first layer support steel beam (5), and the top of the first side wall precast slab (13) and the second side wall precast slab (14) of the first layer precast wall panel both abut against the bottom of the seismic isolation layer (1).
8. A method for constructing a suspended elevator shaft according to claim 1, characterized in that: The suspension frame deformation monitor includes multiple displacement sensors.
Citation Information
Patent Citations
Construction method of suspended elevator shaft of seismic isolation system
CN104963425A
Suspension type elevator shaft pouring structure of shock insulation system and construction method of suspension type elevator shaft pouring structure
CN115142643A