Step-by-step drilling construction method for rectangular anti-slide piles with airbag retaining walls and horizontal cantilever.
By using the airbag wall-supported drilling method, combined with multi-functional drilling components and airbag support, the problem of drilling rectangular anti-slide pile holes in soft soil, gravel, and pebble strata has been solved. This method achieves efficient and low-cost rectangular pile hole formation, prevents collapse, and saves mud materials.
Patent Information
- Application Number
- CN202311091355.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-29
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-08-29
AI Technical Summary
Existing drilling rigs are difficult to drill rectangular anti-slide pile holes with horizontal cantilever or haunched horizontal cantilever structures in soft soil, gravel, pebbles, and accumulated masses. They also have low construction efficiency, high cost, require auxiliary machinery or mud slurry for wall protection, and have low integration.
The airbag wall support drilling method is adopted. Through the multi-functional drilling components and airbag support at the bottom of the drilling rig, the airbag supports the surrounding soil and rock during the drilling process. Combined with the vertical and horizontal multi-functional drilling components, vertical and horizontal cantilever pile holes are drilled in stages, integrating drilling and slag removal functions to achieve hole formation in one go.
It effectively prevents pile hole collapse in soft soil, gravel, pebble and accumulated strata, saves mud materials, improves construction efficiency, reduces costs, and enables the one-time drilling of rectangular pile holes in horizontal cantilever structures, reducing construction procedures.
Smart Images

Figure CN117072053B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the technical field of anti-slide pile drilling construction, and in particular to a step-by-step drilling construction method for rectangular anti-slide piles with airbag-supported walls and horizontal cantilever. Background Technology
[0002] In engineering projects such as slope protection, roadbed construction, foundation pit excavation, and tunnel entrance / exit construction, anti-slide piles are the most effective measure to transfer the lateral thrust of the soil and rock mass to the stable strata below the sliding surface, resisting lateral thrust and mitigating engineering and geological hazards. Anti-slide piles are divided into rectangular cross-section anti-slide piles and circular cross-section anti-slide piles. Rectangular anti-slide piles have advantages such as high lateral stiffness and high single pile bearing capacity, effectively enhancing anti-slide force and increasing the anti-slide coefficient. Therefore, rectangular cross-section anti-slide piles are widely used in various engineering fields.
[0003] Traditional rectangular cross-section anti-slide piles have large cross-sections and cannot fully utilize the strength of the soil and rock in front of the pile. For anti-slide piles with horizontal cantilever structures, the horizontal cantilever can fully utilize the strength of the soil and rock in front of the pile, improving the anti-slide capacity of the pile. However, drilling the horizontal cantilever pile holes for rectangular anti-slide piles with horizontal cantilever structures is extremely difficult. Traditional rectangular cross-section anti-slide piles are usually excavated manually or mechanically. Manual excavation accounts for 65% of all collapse accidents during pile construction and is inefficient and costly, while mechanical excavation is safer and more efficient. For soft soil, gravel, pebbles, and other fractured soil and rock masses, measures such as mud slurry wall protection are required during pile hole excavation to prevent collapse. Therefore, using mechanical drilling to excavate pile holes for rectangular anti-slide piles with horizontal cantilever structures in soft soil and fractured soil and rock layers is of great significance for ensuring the safety of construction personnel and improving efficiency.
[0004] Currently, there are various rectangular drilling equipment and mechanical excavation methods, such as: Patent No. CN 106836354 A, "Mechanical Hole Forming Device for Rectangular Anti-slide Piles", uses multiple cutting blades to form a rectangular shovel head. The rear end of the shovel head is equipped with a counterweight or hydraulic propulsion device to realize the drilling of rectangular pile holes.
[0005] Patent No. CN 103244053 A "Rectangular Drilling Machine" mainly uses two cam bodies to drive two T-shaped cutter heads evenly distributed at the bottom of two steel frames to move towards each other and back and forth, cutting the soil into rectangular holes.
[0006] Patent No. CN 104533300 A, "Rectangular Drilling Machine", has a conical drill bit at the bottom of a rectangular transmission box and cross-shaped long cutters on the four sides. The conical drill bit drills in to form a circular pile hole, and then the cross-shaped long cutters rotate and cut to shape it into a rectangular pile hole.
[0007] The patent number CN 207715083 U, "A Rectangular Anti-slide Pile Drilling Rig", mainly involves setting a circular drill cylinder and a rectangular drill cylinder at the bottom of the drill rod. The circular drill cylinder is screwed in to form a circular pile hole, and then the rectangular drill cylinder cuts the soil around the circular pile hole to form a rectangular pile hole.
[0008] Patent No. CN 105951798 A, "A Rectangular Drilling Machine", mainly uses a motor to drive four concave cylindrical parts with agitators to cut the soil and drill rectangular pile holes.
[0009] Regarding mechanical drilling methods for rectangular anti-slide piles, for example: Patent No. CN 108678661 A, "Method for Drilling Holes for Square Anti-slide Piles and Square Drill Bit for Drilling Holes", utilizes a rotary drilling rig with a circular drill bit to drill at least one row of circular pilot holes sequentially along the length of the cross-section of the square anti-slide pile hole. The rows of circular pilot holes are connected, and the sidewalls of the square anti-slide pile hole are tangent to the edges of the adjacent circular pilot holes. Then, a square drill bit is used to sweep the hole, so that the square drill bit cuts down along the outline of the square anti-slide pile hole to remove excess soil. This process is repeated until the design requirements are met.
[0010] Patent No. CN110593753 A, "Method for Rapid Mechanical Hole Formation of Rectangular Anti-slide Piles," first uses a rotary drilling rig with a round drill bit to drill pilot holes at the four corners until the designed pile bottom elevation is reached. Then, a trenching machine is used to trim the pilot holes in three sections, employing a three-stage grab bucket operation: first, grabbing along the long side of the anti-slide pile from the pilot hole location until the designed hole depth is reached; second, grabbing along the other long side of the anti-slide pile from the pilot hole location until the designed hole depth is reached; third, grabbing the remaining middle section until the designed hole depth is reached. If encountering complex and hard strata such as hard gravelly soil or calcareous cemented layers, the trenching machine stops grabbing the soil, and the hard layers are broken using a long-arm hydraulic breaker.
[0011] Patent No. CN 110820733 A, "An Improved Simple Rectangular Anti-slide Pile Mechanical Rapid Hole Formation Construction Method", mainly involves two rotary excavations of circular pile holes, connecting the circular pile holes and over-excavating beyond the outline of the rectangular pile hole. After placing a rectangular steel cylinder inside the pile hole, the over-excavated part is poured to form the rectangular pile hole.
[0012] Patent No. CN 110714460 A, "A Mechanical Method for Drilling Rectangular Anti-slide Piles with Reduced Filling Coefficient", and Patent No. CN 113605387, "A Fully Mechanical Construction Method for Rectangular Anti-slide Piles", both mainly involve two or more rotary excavations of circular pile holes. The circular pile holes are connected or partially overlapped and tangent to the outline of the rectangular pile hole. The rectangular pile hole is formed by mechanically removing slag and repairing the hole around the perimeter of the pile hole.
[0013] The patent number CN 111691408 A, "A Construction Method for Rectangular Anti-slide Piles in Soft Rock Layers", mainly involves first drilling a rectangular groove along the outline of a rectangular pile hole using a small-diameter rotary drilling rig, with the small-diameter pile hole tangent to the outline of the rectangular pile hole. Then, a large-diameter rotary drilling rig is used to partially overlap the small-diameter pile hole, and the pile hole is mechanically cleaned and repaired to form a rectangular pile hole.
[0014] However, the following problems exist: (1) Existing drilling machines mainly form vertical rectangular pile holes in rock and soil. They cannot drill rectangular anti-slide pile holes with horizontal cantilever or haunched horizontal cantilever structure in soil, nor can they drill in soft soil, gravel, pebbles, accumulated bodies and other strata; (2) Other machinery or auxiliary measures are required for hole repair, resulting in low drilling efficiency and high cost, and it is impossible to drill rectangular pile holes in one go; (3) Other machinery (grab bucket) or auxiliary measures (slurry positive circulation slag removal method) are used to clean the slag in the pile hole. The integration of drilling and slag removal equipment is low, resulting in low drilling efficiency and high cost. Summary of the Invention
[0015] The purpose of this invention is to address the shortcomings of the prior art by providing a step-by-step drilling method for rectangular anti-slide piles with airbag-supported walls and horizontal cantilever. For drilling pile holes in strata such as soft soil, gravel, pebbles, and accumulated masses, the drilling rig is hoisted by cables. A multi-functional drilling assembly with vertical and horizontal cutters and roller cutters arranged at intervals is installed at the bottom of the rig. The roller cutter blades are higher than the auger cutters, facilitating rock fracturing by the roller cutters followed by crushing by the auger cutters. An airbag is fitted around the drilling rig and inflated during the drilling process. The airbag supports the surrounding soil and rock mass and follows the drilling. The multi-functional assembly is initially driven by the pressure generated by the rig's own weight. The drilling rig can drill vertical rectangular pile holes to the designed depth of the horizontal cantilever using a vertical drill bit. Then, it drills horizontal cantilever rectangular pile holes using a multi-functional drilling assembly with a multi-stage hydraulic system on its back. Alternatively, it can drill both haunched and horizontal cantilever pile holes simultaneously in both vertical and horizontal directions using the multi-functional drilling assembly. After drilling is completed, the multi-functional drilling assembly is retrieved. Finally, the multi-functional drilling assembly continues drilling vertically to the designed depth. This allows for the drilling of pile holes with horizontal cantilever or haunched horizontal cantilever rectangular anti-slide piles in soft soil, gravel, pebbles, and silt formations, saving time and construction costs, improving work efficiency, and ensuring project quality and the safety of construction personnel.
[0016] The objective of this invention is achieved through the following technical solutions: A method for staged drilling of rectangular anti-slide piles with airbag-supported walls and horizontal cantilever, characterized in that the method includes the following steps: (S1) A rock cuttings handling mechanism and a multi-functional drilling assembly are sequentially installed on the drilling rig from top to bottom, and an airbag assembly is installed around the drilling rig to support it; wherein: The multi-functional drilling assembly includes several cylindrical drilling assemblies, a U-shaped fork plate, a sliding reaction frame, and a horizontal hydraulic cylinder. The cylindrical drilling assemblies are mounted on the U-shaped fork plate and arranged in a matrix on both the vertical and horizontal planes. The horizontal hydraulic cylinder is fixed on the sliding reaction frame and drives the U-shaped fork plate to move laterally. (S2) The piston rod of the horizontal hydraulic cylinder is placed in the standby state with the minimum stroke, and the cylindrical drilling assembly in the multi-functional drilling assembly on the horizontal plane is controlled to drill downward into the rock and soil until the design depth of the horizontal cantilever pile hole is reached, so as to form the free section of the rectangular pile hole. (S3) Move the multi-functional drilling assembly upward to the top design elevation of the haunch hole, activate the cylindrical drilling assembly and the horizontal hydraulic cylinder in the vertical and horizontal planes of the multi-functional drilling assembly, and under the drive of the horizontal hydraulic cylinder, the cylindrical drilling assembly in the vertical and horizontal planes of the multi-functional drilling assembly drills the haunch hole to the side of the rectangular pile hole. (S4) Control the horizontal hydraulic cylinder to drive the cylindrical drilling assembly on the vertical plane of the multi-functional drilling assembly to drill outwards the horizontal cantilever pile hole until the designed length of the horizontal cantilever pile hole is reached. (S5) Retract the piston rod of the horizontal hydraulic cylinder to the minimum stroke and stop working, close the cylindrical drill assembly on the vertical plane of the multi-functional drill assembly, open the cylindrical drill assembly on the horizontal plane of the multi-functional drill assembly, and continue to control the cylindrical drill assembly on the horizontal plane of the multi-functional drill assembly to drill vertically downward to the design depth of the rectangular pile hole to form the embedded section of the rectangular pile hole, thereby forming a rectangular anti-sliding pile hole; (S6) The drilling rig is disengaged from the rectangular pile hole, and reinforced concrete is poured into the rectangular anti-slide pile hole to form a rectangular anti-slide pile.
[0017] The drilling rig is hoisted by a drilling vehicle equipped with a cable. The drilling vehicle includes a vehicle-mounted platform, a steel column, a tie rod, a hinge shaft, a guide rail, a slider, a steel cantilever beam, a winch motor, and a cable support. The steel column is vertically mounted on the vehicle-mounted platform. The upper end of the tie rod is hinged to the upper end of the steel column, and the lower end is hinged to the hinge shaft fixed on the vehicle-mounted platform. The guide rail is vertically mounted and fixed along the steel column. The slider is slidably mounted on the guide rail. The steel cantilever beam is fixed to the slider. The winch motor is fixed to the steel cantilever beam, and the cable support is fixed below the steel cantilever beam. The winch motor drives the cable to move up and down in the vertical direction.
[0018] The rock slag treatment mechanism includes a mixing device, a crushing device, a slag suction system, a slag discharge system, and a grouting system. The slag suction port of the mixing box of the mixing device is connected to the slag suction system via the crushing device. The slag discharge port of the mixing box is connected to the slag discharge system. A pipe fixing frame is provided above the mixing mechanism of the mixing device. The airbag assembly is installed on the pipe fixing frame or the pipe fixing frame and the mixing device. The grout outlet of the grouting system extends into the multi-functional drilling assembly.
[0019] The stirring mechanism includes a main gear and several auxiliary gears meshing with and transmitting power to the main gear. The main gear is driven to rotate by a stirring motor. A main stirring shaft extending into the stirring tank is coaxially mounted on the main gear, and stirring blades are mounted on the main stirring shaft. A secondary stirring shaft extending into the stirring tank is coaxially mounted on the auxiliary gears, and stirring blades are mounted on the secondary stirring shaft. The slag suction system includes a main slag suction pipe and a multi-functional slag suction branch pipe branching from the suction port of the main slag suction pipe. The suction head of the multi-functional slag suction branch pipe is connected to the multi-functional drill assembly. Each suction head is equipped with a multi-functional slag suction valve. The multi-functional slag suction branch pipe is connected to the main slag suction pipe through a telescopic pipe.
[0020] The grouting system includes a main grouting pipe, a grouting pump, and multi-functional grouting branch pipes. One end of the main grouting pipe is connected to the grouting pump located on the ground, and the other end is connected to several multi-functional grouting branch pipes. The nozzles of the multi-functional grouting branch pipes are connected to the multi-functional drilling assembly. Each nozzle is equipped with a multi-functional grouting valve. The multi-functional grouting branch pipes are connected to the main grouting pipe via telescopic pipes. The slag discharge system includes a slag discharge pipe and a slag discharge pump. One end of the slag discharge pump is connected to the slag discharge pipe, and the other end is connected to the slag discharge port on the mixing tank.
[0021] The slag suction main pipe, the grouting main pipe, and the slag discharge pipe are all arranged and fixed along the pipe fixing frame.
[0022] The airbag assembly includes an airbag unit arranged along the pipe fixing frame or the periphery of the pipe fixing frame and the stirring device, and an air pump connected to the airbag unit via an air pipe and located on the ground. The airbag unit is fixed to the pipe fixing frame by a ring clamp, and air valves are provided at the top and bottom of the airbag unit.
[0023] The U-shaped fork plate consists of a web, wing plates on both sides of the web, and a steel support in the middle of the web. The web includes a horizontal web and a vertical web. The cylindrical drill assembly includes two cylinders, a motor that drives the cylinders to rotate, a plurality of hobbing cutter assemblies spaced apart on the surface of the cylinders, and a plurality of reamer assemblies arranged between adjacent hobbing cutter assemblies. The hobbing cutter assembly includes a hobbing cutter base and a ring of hobbing cutters fixed on the hobbing cutter base. The reamer assembly includes a reamer base and reamers that are inclined and fixed on the reamer base. The motor shaft passes through the cylinders on both sides, and the end of the motor shaft is correspondingly disposed in the shaft holes of the wing plates on both sides of the U-shaped fork plate. The outer shell of the motor is welded and fixed to the steel support.
[0024] The sliding reaction frame includes a reaction plate, a rail plate, and a connecting plate. The rail plate is installed on the top of the reaction plate, and T-shaped slide rails are fixed on both sides of the bottom of the rail plate. The connecting plate is fixed on both sides of the web of the U-shaped fork plate. A slider is fixed on the top of the connecting plate, and a T-shaped slide groove that mates with the T-shaped slide rail is opened in the slider. The cylinder end face of the horizontal hydraulic cylinder is fixed on the reaction plate of the sliding reaction frame, and the piston rod of the horizontal hydraulic cylinder is connected to the vertical web of the U-shaped fork plate.
[0025] The advantages of this invention are: (1) When drilling pile holes in strata such as soft soil, gravel, pebbles, and accumulation bodies, airbags can effectively support the pile holes and prevent them from collapsing. (2) When drilling rectangular pile holes, a large amount of mud is not needed in the pile hole for slag removal and pile hole support. Mud is only filled after the hole is formed, which can save mud materials and improve construction efficiency. (3) To realize the drilling of horizontal cantilever or rectangular pile holes with haunches in strata such as soft soil, gravel, pebbles, and accumulation. (4) Both the horizontal cantilever structure and the vertical pile body can be drilled in one go without the need for other mechanical assistance, thereby improving construction efficiency and saving construction and equipment costs; (5) The rock is crushed twice by the crushing box, which can better discharge it from the pile hole and prevent the slag discharge pipe from being blocked; (6) The drilling rig has a high degree of integration and has both drilling and slag removal functions, which realizes uninterrupted synchronous operation of drilling and slag removal, reduces construction procedures, saves construction costs, and improves drilling efficiency. Attached Figure Description
[0026] Figure 1 This is a schematic diagram of the rectangular deep hole drilling rig with airbag wall protection drill bit of the present invention; Figure 2 This is a schematic diagram of the cross-sectional positions of the rectangular deep hole drilling rig with airbag wall protection drill bit of the present invention; Figure 3 This is a partial schematic diagram of the rectangular deep hole drilling rig with airbag wall protection drill bit of the present invention; Figure 4 for Figure 2 Sectional view of AA in the middle; Figure 5 for Figure 2 Cross-sectional view of the middle section (BB); Figure 6 for Figure 2 CC section view; Figure 7 for Figure 2 Cross-sectional view of DD in the middle; Figure 8 This is a schematic diagram of the multifunctional drilling assembly of the present invention; Figure 9 for Figure 8 EE cross-section; Figure 10 for Figure 2 Cross-sectional view of FF in the middle; Figure 11 for Figure 2 Cross-sectional view of GG in China; Figure 12 for Figure 2 Cross-sectional view of HH section; Figure 13 for Figure 2 Section II; Figure 14 This is a schematic diagram of the airbag assembly of the present invention; Figure 15 This is a schematic diagram of the step-by-step drilling construction method for the rectangular anti-slide pile with airbag wall protection and horizontal cantilever of the present invention. like Figure 1-15 As shown in the figure, the labels represent: 1. Multifunctional drilling assembly; 2. Mixing device; 3. Crushing device; 4. Slag suction system; 5. Pipe fixing frame; 6. Slag discharge system; 7. Grouting system; 8. Airbag assembly; 9. Drilling rig. 11. Cylindrical drill assembly, 12. U-shaped fork plate, 13. Sliding reaction frame, 14. Horizontal hydraulic cylinder, 111. Column, 112. Auger assembly, 113. Roller assembly, 114. Motor, 115. Motor shaft, 1121. Auger base, 1122. Auger, 1131. Roller base, 1132. Roller, 121. Wing plate, 122. Vertical web plate, 123. Horizontal web plate, 124. Steel support, 125. Shaft hole, 126. Multifunctional slag suction branch pipe through hole, 127. Multifunctional slag suction main pipe through hole, 128. Multifunctional grouting branch pipe through hole, 129. Multifunctional grouting main pipe through hole, 131. Reaction plate, 132. Rail plate, 133. T-shaped slide rail, 134. Slider, 135. T-shaped slide groove, 136. Connecting plate; 21. Mixing tank; 22. Double-layer large blades; 23. Main mixing shaft; 24. Double-layer small blades; 25. Auxiliary mixing shaft; 26. Single-layer small blades; 27. Main gear; 28. Main gear isolation pad; 29. Auxiliary gear; 210. Auxiliary gear isolation pad; 211. Steel cover plate; 212. Mixing motor; 31. Crushing box; 32. Middle partition; 33. Connecting pipe; 34. Frame; 35. Fan motor; 36. Fan blades; 37. Crushing blade; 38. Filter screen; 41. Main suction pipe for slag removal; 42. Multi-functional suction branch pipe for slag removal; 43. Telescopic pipe; 44. Suction head; 45. Multi-functional suction valve for slag removal. 51. Top steel plate, 52. Middle steel plate, 53. Bottom steel plate, 54. Side upright plate, 55. Square through hole, 56. Slag discharge pipe fixing hole, 57. Grouting pipe fixing hole; 61. Slag discharge pipe; 62. Slag discharge pump; 71. Grouting main pipe; 72. Grouting pump; 73. Multi-functional grouting branch pipe; 74. Nozzle; 75. Multi-functional grouting valve; 81. Air tube, 82. Air pump, 83. Airbag unit, 84. Upper air valve, 85. Bottom air valve, 86. End ring, 87. Middle ring; 91. Hoist motor; 92. Fixed shaft; 93. Cable; 94. Cable support; 95. Steel cantilever beam; 96. Slider; 97. Steel column; 98. Guide rail; 99. Hinge shaft; 910. Tie rod; 911. Vehicle platform; a. fractured rock formation, b. drilling rig, c. free section pile hole, d. haunch hole, e. horizontal cantilever pile hole, f. embedded section pile hole, g. rectangular casing, h. mud, i. reinforcing cage, j. concrete, k. concrete grouting pipe. Implementation
[0027] The features and other related features of the present invention will be further described in detail below with reference to the accompanying drawings and embodiments, so as to facilitate understanding by those skilled in the art: Example: Figure 1-15 As shown, this embodiment relates to a step-by-step drilling construction method for rectangular anti-slide piles with airbag wall protection and horizontal cantilever. It utilizes a rectangular deep hole drilling rig with airbag wall protection and reversible drill bit for construction. The rectangular deep hole drilling rig includes a drilling rig 9 and a drilling machine hoisted by a cable 93 on the drilling rig 9. The drilling rig includes a rock debris treatment mechanism and a multi-functional drilling assembly 1 connected sequentially from top to bottom. A pipe fixing frame 5 is provided on the rock debris treatment mechanism. An airbag assembly 8 is installed around the pipe fixing frame 5 (or both the pipe fixing frame 5 and the mixing device 2). The rock debris treatment mechanism includes a mixing device 2, a crushing device 3, a slag suction system 4, a slag discharge system 6, and a grouting system 7.
[0028] like Figure 1 As shown, the drilling rig 9 includes a winch motor 91, a fixed shaft 92, a cable 93, a cable bracket 94, a steel cantilever beam 95, a slider 96, a steel column 97, a guide rail 98, a hinge shaft 99, a tie rod 910, and a vehicle-mounted platform 911. The vehicle-mounted platform 911 has tracked wheels and is located on the ground. The steel column 97 is vertically mounted at the front end of the vehicle-mounted platform 911. The tie rod 910 provides diagonal bracing reinforcement to the steel column 97. Specifically, the upper end of the tie rod 910 is hinged to the upper end of the steel column 97, and the lower end... The system is hinged to the hinge shaft 99 of the vehicle platform 911; the guide rail 98 is fixedly attached to the steel column 97 to form a vertical track; the slider 96 is slidably mounted on the guide rail 98 and can slide vertically under the drive of the power mechanism; the steel cantilever beam 95 is fixed to the slider 96; the cable bracket 94 is fixed to the bottom surface of the steel cantilever beam 95; the winch motor 91 is fixed to the steel cantilever beam 95 via the fixed shaft 92; the winch motor 91 is used to drive the cable 93 and the drilling rig suspended at its lower end to perform lifting and lowering movements. It should be noted that, due to the large weight of the drilling rig, it can move downwards under its own weight, eliminating the need for the drill rod to press down as before; and the cable 93 has sufficient length to meet the drilling requirements for rectangular deep holes.
[0029] like Figure 1-9 As shown, the multi-functional drilling assembly 1 can be used for deep hole drilling of rectangular anti-slide piles, excavation of horizontal cantilever pile holes, and excavation of haunched holes. The multi-functional drilling assembly 1 includes several horizontally arranged cylindrical drilling assemblies 11, U-shaped fork plates 12, sliding reaction frames 13, and horizontal hydraulic cylinders 14. The cylindrical drilling assemblies 11 are mounted on the U-shaped fork plates 12 and arranged in a matrix on both the vertical and horizontal planes. That is, the multi-functional drilling assembly 1 can form a rectangular excavation surface on both the vertical and horizontal planes. In this embodiment, the cylindrical drilling assemblies 11 are arranged in a right-angled plane. The horizontal hydraulic cylinders 14 are fixed on the sliding reaction frames 13 and drive the U-shaped fork plates 12 to move laterally, thereby driving the cylindrical drilling assemblies 11 to move laterally synchronously.
[0030] The U-shaped fork plate 12 consists of a web, wing plates 121 on both sides of the web, and a steel support 124 in the middle of the web. The web includes a horizontal web 123 and a vertical web 122, which form a right-angled surface structure, corresponding to the arrangement of the cylindrical drill assembly 11. The cylindrical drill assembly 11 includes two cylindrical drills and a motor 114 that drives the cylindrical drills to rotate. In this embodiment, there are a total of 5 sets of cylindrical drill assemblies 11 (10 cylindrical drills in total), with 2 sets of cylindrical drill assemblies 11 (4 cylindrical drills in total) on the vertical plane and 4 sets of cylindrical drill assemblies 11 (8 cylindrical drills in total) on the horizontal plane. The cylindrical drill consists of a cylinder 111, several roller cutter assemblies 113 spaced apart on the surface of the cylinder 111, and several reamer assemblies 112 spaced apart between adjacent roller cutter assemblies 113 on the surface of the cylinder 111. Specifically, the height of the roller cutter assembly 113 protruding from the cylinder 111 is higher than that of the reamer assembly 112. Therefore, when cutting rock, the roller cutter 1132 on the roller cutter assembly 113 contacts the rock first, that is, the roller cutter assembly 113 presses the rock surface as a whole first. The rock is split into several large blocks, which are then further cut into smaller diameter rock blocks (or rock debris) by the cutter assembly 112. The cutter assembly 113 includes a cutter base 1131 and a ring of cutters 1132 fixed on the cutter base 1131. The cutter assembly 112 includes a cutter base 1121 and cutters 1122. The cutters 1122 are installed at an angle under the fixation of the cutter base 1121 to facilitate the excavation of rock strata. For rock masses, if the cutters 1132 are used to directly crush the rock mass at the excavation face or the cutters 1122 are used for direct excavation, the strength, hardness, and wear resistance of the cutter and cutter materials need to meet high requirements, which not only increases the difficulty of developing cutter and cutter materials but also increases construction costs. The combination of roller cutter 1132 and auger cutter 1122, where roller cutter 1132 only fractures the rock mass at the excavation face, reducing its strength and making it easier for auger cutter 1122 to cut the rock, not only reduces the requirements for the strength, hardness, and wear resistance of the roller cutter and auger cutter materials, but also reduces wear on the cutter and auger cutter. Therefore, the method of combining roller cutter 1132 first fracturing the rock mass at the excavation face with auger cutter 1122 cutting the fractured low-strength rock mass not only improves work efficiency but also reduces tool wear and lowers construction costs. Steel support 124 is welded or bolted to the housing of motor 114. The motor shaft 115 of motor 114 drives the rotation of the cylinders 111 on both sides, and the end of motor shaft 115 is supported in the shaft holes 125 of the two side flanges 121.The sliding reaction frame 13 includes a reaction plate 131, a rail plate 132, and a connecting plate 136. The rail plate 132 is installed on top of the reaction plate 131. T-shaped slide rails 133 are fixed on both sides of the bottom of the rail plate 132. The connecting plate 136 is fixed on both sides of the web of the U-shaped fork plate 12. A slider 134 is fixed on the top of the connecting plate 136, and a T-shaped groove 135 that mates with the T-shaped slide rails 133 is opened in the slider 134. The cylinder end face of the horizontal hydraulic cylinder 14 is fixed on the sliding reaction plate 131. On the reaction plate 131 of the force frame 13, the piston rod of the horizontal hydraulic cylinder 14 is connected to the vertical web plate 122 of the U-shaped fork plate 12. The horizontal hydraulic cylinder 14 drives the vertical web plate 122 of the U-shaped fork plate 12 to drive the slider 134 on the connecting plate 136 to move laterally. Due to the cooperation between the T-shaped groove 135 in the slider 134 and the T-shaped slide rail 133 on the rail plate 132, it can play a guiding role, ensuring the stability and safety of the lateral movement of the multi-functional drill assembly 1.
[0031] When the multi-functional drilling assembly 1 is drilling deep holes for rectangular anti-slide piles, the horizontal hydraulic cylinder 14 is not working (the piston rod of the horizontal hydraulic cylinder 14 is at its minimum stroke), and the cylindrical drilling assembly 11 on the horizontal plane of the multi-functional drilling assembly 1 is working, drilling the rectangular deep hole downwards. When the multi-functional drilling assembly 1 is excavating horizontal cantilever pile holes, the horizontal hydraulic cylinder 14 is working (the piston rod of the horizontal hydraulic cylinder 14 extends to the side), and the cylindrical drilling assembly 11 on the vertical plane of the multi-functional drilling assembly 1 is working, drilling the horizontal cantilever pile holes to the side. When the multi-functional drilling assembly 1 is excavating haunched holes, the horizontal hydraulic cylinder 14 is working (the piston rod of the horizontal hydraulic cylinder 14 extends to the side), and the cylindrical drilling assembly 11 on both the vertical and horizontal planes of the multi-functional drilling assembly 1 is working, drilling the haunched holes downwards and to the side.
[0032] In addition, the track plate 132 is provided with a multi-functional slag suction main pipe through hole 127 and a multi-functional grouting main pipe through hole 129, which are used to fix the slag suction main pipe 41 of the slag suction system 4 and the grouting main pipe 71 of the grouting system 7, respectively. The web plate is provided with a multi-functional slag suction branch pipe through hole 126 and a multi-functional grouting branch pipe through hole 128, which are used to fix the multi-functional slag suction branch pipe 42 of the slag suction system 4 and the multi-functional grouting branch pipe 73 of the grouting system 7, respectively. The multi-functional slag suction branch pipe 42 is connected to the slag suction main pipe 41 by a telescopic pipe 43, and the multi-functional grouting branch pipe 73 is also connected to the grouting main pipe 71 by a telescopic pipe 43, so that when the multi-functional drilling assembly 1 moves laterally, the multi-functional slag suction branch pipe 42 and the multi-functional grouting branch pipe 73 also move accordingly.
[0033] like Figure 1-14 As shown, the rock slag treatment mechanism includes a mixing device 2, a crushing device 3, a slag suction system 4, a slag discharge system 6, and a grouting system 7.
[0034] The mixing device 2 mainly includes a mixing box 21 and a mixing mechanism. The mixing box 21 is fixedly installed on the upper surface of the sliding reaction frame 13 (rail plate 132). The mixing mechanism includes a main gear 27 and multiple auxiliary gears 29 meshing with it. The main gear 27 is driven to rotate by the mixing motor 212, which in turn drives the auxiliary gears 29 to rotate. A mixing main shaft 23 extending into the mixing box 21 is coaxially arranged on the main gear 27. The mixing main shaft 23 is equipped with mixing blades, which are double-layered large blades 22. Each auxiliary gear 29 is coaxially arranged with a mixing auxiliary shaft 25 extending into the mixing box 21. The mixing auxiliary shaft 25 is also equipped with mixing blades. Some of the mixing auxiliary shafts 25 have double-layered small blades 24, while others have single-layered small blades 26. By mixing the rock debris and mud in the mixing box 21, a uniformly mixed mud can be obtained, which is convenient for discharge. To prevent slurry from seeping into the gearbox containing the main gear 27 and auxiliary gear 29 during mixing, a main gear isolation pad 28 is provided at the connection point between the main mixing shaft 23 and the mixing box 21, and an auxiliary gear isolation pad 210 is provided at the connection point between the auxiliary mixing shaft 25 and the mixing box 21. Figure 3 As shown, a steel cover plate 211 is located on top of the gearbox containing the main gear 27 and the auxiliary gear 29, for connecting to the pipe fixing bracket 5. The mixing tank 21 is equipped with a slag suction port and a slag discharge port.
[0035] A slag suction system 4 is connected to the slag suction port of the mixing tank 21. The slag suction system 4 mainly includes a slag suction main pipe 41 and a multi-functional slag suction branch pipe 42. One end of the slag suction main pipe 41 is connected to the slag suction port of the mixing tank 21 via the crushing device 3. The other end of the slag suction main pipe 41 (i.e. the suction end) is connected to multiple multi-functional slag suction branch pipes 42. The multi-functional slag suction branch pipe 42 extends into the multi-functional drill assembly 1, and the suction head 44 of the multi-functional slag suction branch pipe 42 is close to the cylindrical drill assembly 11 so that it can suck up the rock slag dug out by cutting. A multi-functional slag suction valve 45 is set at the suction head 44 to control the opening and closing of the pipeline.
[0036] The extracted rock debris is crushed into fine particles by the crushing device 3 and then enters the mixing tank 21. The crushing device 3 mainly includes a crushing box 31, a partition plate 32, a connecting pipe 33, a frame 34, a blower motor 35, blower blades 36, a crushing blade 37, and a filter screen 38. The partition plate 32 is inclined in the crushing box 31 to form a ramp that facilitates the flow of rock debris. The blower motor 35 is installed on the top plate in the crushing box 31 via the frame 34. The blower motor 35 has blower blades 36 on its rotating shaft. The high-speed rotating blower motor 35 and blower blades 36 can create negative pressure in the slag suction main pipe 41. A crushing blade 37 is installed at the installation location of the blower motor 35 so that the extracted rock debris must be crushed by the crushing blade 37 before entering the mixing tank 21 through the connecting pipe 33. A screen 38 is installed at the end face of the blower motor 35 to filter large rock debris particles and prevent rock debris from flowing into the mixing tank 21 from the blower motor 35.
[0037] The grouting system 7 extends into the multi-functional drilling assembly 1. The grouting system 7 mainly includes a main grouting pipe 71, a grouting pump 72, and multi-functional grouting branch pipes 73. One end of the main grouting pipe 71 is connected to the grouting pump 72 located on the ground, and the other end is connected to several multi-functional grouting branch pipes 73. The multi-functional grouting branch pipes 73 extend into the multi-functional drilling assembly 1, and the nozzles 74 of the multi-functional grouting branch pipes 73 are located near the cylindrical drilling assembly 11. Grouting system 7 injects mud into the rock cuttings, mixing the rock cuttings with the mud, facilitating extraction by the slag suction system 4. A multi-functional grouting valve 75 is installed at the nozzle 74 to control the flow of the pipeline.
[0038] The slag discharge port of the mixing tank 21 is connected to the slag discharge system 6 on the ground. The slag discharge system 6 includes a slag discharge pipe 61 and a slag discharge pump 62. The lower end of the slag discharge pipe 61 is connected to the slag discharge port of the mixing tank 61 and extends downward to a certain depth to facilitate the pumping out more mud. The slag discharge pipe 61 pumps the well-mixed mud from the mixing tank 21 to the ground for collection and treatment through the slag discharge pump 62.
[0039] like Figure 1-14 As shown, the pipe fixing bracket 5 has a box-shaped structure, including a top steel plate 51, a middle steel plate 52, a bottom steel plate 53, and several side upright plates 54 connecting the three. Furthermore, a square through hole 55 is provided on the bottom steel plate 53 of the pipe fixing bracket 5 for installing the mixing motor 212. Additionally, slag discharge pipe fixing holes 56 for the slag discharge pipe 61 and grouting pipe fixing holes 57 for the grouting main pipe 71 are also provided on the top steel plate 51, the middle steel plate 52, and the bottom steel plate 53. To prevent pipe swaying during drilling, the pipe fixing bracket 5 provides fixation for each passing pipe.
[0040] like Figure 1-14As shown, the airbag assembly 8 includes an airbag unit 83 arranged around the periphery of the pipe fixing frame 5 (or both the pipe fixing frame 5 and the mixing device 2) and an air pump 82 connected to the airbag unit 83 via an air pipe 81 and located on the ground. The air pump 82 can inflate the airbag unit 83. The airbag unit 83 is fixed to the side plate 54 of the pipe fixing frame 5 by end rings 86 and middle rings 87. Air valves are provided at the top and bottom of the airbag unit 83, namely an upper air valve 84 and a bottom air valve 85, for inflating and deflating the airbag unit 83. During the drilling of the pile hole, the air valve is closed, and the air pump 82 inflates the airbag unit 83, so that the airbag unit 83 supports the rock and soil around the drilled pile hole and follows the drilling. When support is not needed, the air valve can be opened to deflate the airbag unit 83.
[0041] like Figure 1-15 As shown, the construction method includes the following steps: (1) Excavate free section pile hole c in fractured rock stratum a, and install rectangular casing g in free section pile hole c, with the upper end of rectangular casing g extending above the ground.
[0042] (2) The drilling rig b is placed in the free section pile hole c through the rectangular casing g, and the drilling rig b is supported on the surrounding rock and soil with the help of the airbag assembly 8. The cylindrical drilling assembly 11 on the horizontal plane of the multi-functional drilling assembly 1 on the drilling rig b continues to drill downwards to the free section pile hole c until the designed depth of the horizontal cantilever pile hole e. During this process, the suction head 44 on the multi-functional slag suction branch pipe 42 and the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drilling assembly 11 on the horizontal plane perform slag suction and grouting respectively.
[0043] (3) After the multi-functional drilling assembly 1 reaches the bottom design elevation of the horizontal cantilever pile hole e, close the cylindrical drilling assembly 11 on the horizontal plane in the multi-functional drilling assembly 1, and move the multi-functional drilling assembly 1 upward to the top design elevation of the haunch hole d. During this process, close the suction head 44 on the multi-functional slag suction branch pipe 42 and the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drilling assembly 11 on the horizontal plane.
[0044] (4) Activate the cylindrical drill assembly 11 on the vertical and horizontal planes and the horizontal hydraulic cylinder 14 in the multi-functional drill assembly 1. While the multi-functional drill assembly 1 moves downward, the piston rod of the horizontal hydraulic cylinder 14 extends to the side of the rock mass to drive the multi-functional drill assembly 1 to move laterally, so that the cylindrical drill assembly 11 on the vertical and horizontal planes of the multi-functional drill assembly 1 drills the rock mass to form a haunch hole d. During this process, the suction head 44 on the multi-functional slag suction branch pipe 42 and the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drill assembly 11 on the vertical and horizontal planes perform slag suction and grouting respectively.
[0045] (5) After the multi-functional drilling assembly 1 reaches the bottom design elevation of the horizontal cantilever pile hole e, the piston rod of the horizontal hydraulic cylinder 14 continues to extend to the side of the rock mass to drive the multi-functional drilling assembly 1 to move laterally, so that the cylindrical drilling assembly 11 on the vertical surface of the multi-functional drilling assembly 1 drills the rock mass to form the horizontal cantilever pile hole e. During this process, the suction head 44 on the multi-functional slag suction branch pipe 42 and the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drilling assembly 11 on the vertical surface perform slag suction and grouting respectively.
[0046] (6) After the horizontal cantilever pile hole e is drilled to the designed length, the cylindrical drill assembly 11 on the vertical plane of the multi-functional drill assembly 1 is closed, and the piston rod of the horizontal hydraulic cylinder 14 is retracted to the minimum stroke, so that the multi-functional drill assembly 1 moves back into the free section pile hole c. During this process, the suction head 44 on the multi-functional slag suction branch pipe 42 and the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drill assembly 11 on the vertical plane are closed; the cylindrical drill assembly 11 on the horizontal plane of the multi-functional drill assembly 1 is opened, and the embedded section pile hole f is drilled downward until the designed depth of the embedded section pile hole f is reached. During this process, the suction head 44 on the multi-functional slag suction branch pipe 42 and the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drill assembly 11 on the horizontal plane perform slag suction and grouting respectively.
[0047] (7) The multi-functional drilling assembly 1 moves upward a certain distance. During this process, the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drilling assembly 11 on the vertical surface performs grouting, and the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drilling assembly 11 on the horizontal surface performs grouting, filling the anti-sliding pile hole with mud h.
[0048] (8) The multi-functional drilling assembly 1 continues to move upward until the drilling rig b disengages from the rectangular casing g. During this process, the nozzle 74 on the multi-functional grouting branch pipe 73 near the cylindrical drilling assembly 11 on the horizontal plane continues to grout so that the anti-slide pile hole is filled with mud h.
[0049] (9) Place the steel cage i into the anti-slide pile hole and keep the upper surface of the mud h level with the ground.
[0050] (10) Insert the concrete grouting pipe k into the free section pile hole c and grout the lower part of the anti-slide pile hole so that concrete j is formed in the lower part of the anti-slide pile hole.
[0051] (11) Grouting is performed on the upper part of the anti-slide pile hole so that concrete j is formed on the upper part of the anti-slide pile hole and the upper surface of concrete j is level with the ground.
[0052] (12) Remove the rectangular casing g.
[0053] The advantages of this embodiment are: (1) When drilling pile holes in strata such as soft soil, gravel, pebbles, and accumulation bodies, airbags can effectively support the pile holes and prevent them from collapsing. (2) When drilling rectangular pile holes, a large amount of mud is not needed in the pile hole for slag removal and pile hole support. Mud is only filled after the hole is formed, which can save mud materials and improve construction efficiency. (3) To realize the drilling of horizontal cantilever or rectangular pile holes with haunches in strata such as soft soil, gravel, pebbles, and accumulation. (4) Both the horizontal cantilever structure and the vertical pile body can be drilled in one go without the need for other mechanical assistance, thereby improving construction efficiency and saving construction and equipment costs; (5) The rock is crushed twice by the crushing box, which can better discharge it from the pile hole and prevent the slag discharge pipe from being blocked; (6) The drilling rig has a high degree of integration and has both drilling and slag removal functions, which realizes uninterrupted synchronous operation of drilling and slag removal, reduces construction procedures, saves construction costs, and improves drilling efficiency.
[0054] Although the above embodiments have described the concept and embodiments of the present invention in detail with reference to the accompanying drawings, those skilled in the art will recognize that various improvements and modifications can still be made to the present invention without departing from the scope of the claims, and therefore will not be elaborated here.
Claims
1. A method for staged drilling construction of rectangular anti-slide piles with airbag-supported walls and horizontal cantilever, characterized in that... The construction method includes the following steps: (S1) A rock cuttings handling mechanism and a multi-functional drilling assembly are sequentially installed on the drilling rig from top to bottom, and an airbag assembly is installed around the drilling rig to support it; wherein: The multi-functional drilling assembly includes several cylindrical drilling assemblies, a U-shaped fork plate, a sliding reaction frame, and a horizontal hydraulic cylinder. The cylindrical drilling assemblies are mounted on the U-shaped fork plate and arranged in a matrix on both the vertical and horizontal planes. The horizontal hydraulic cylinder is fixed on the sliding reaction frame and drives the U-shaped fork plate to move laterally. (S2) The piston rod of the horizontal hydraulic cylinder is placed in the standby state with the minimum stroke, and the cylindrical drilling assembly in the multi-functional drilling assembly on the horizontal plane is controlled to drill downward into the rock and soil until the design depth of the horizontal cantilever pile hole is reached, so as to form the free section of the rectangular pile hole. (S3) Move the multi-functional drilling assembly upward to the top design elevation of the haunch hole, activate the cylindrical drilling assembly and the horizontal hydraulic cylinder in the vertical and horizontal planes of the multi-functional drilling assembly, and under the drive of the horizontal hydraulic cylinder, the cylindrical drilling assembly in the vertical and horizontal planes of the multi-functional drilling assembly drills the haunch hole to the side of the rectangular pile hole. (S4) Control the horizontal hydraulic cylinder to drive the cylindrical drilling assembly on the vertical plane of the multi-functional drilling assembly to drill outwards the horizontal cantilever pile hole until the designed length of the horizontal cantilever pile hole is reached. (S5) Retract the piston rod of the horizontal hydraulic cylinder to the minimum stroke and stop working, close the cylindrical drill assembly on the vertical plane of the multi-functional drill assembly, open the cylindrical drill assembly on the horizontal plane of the multi-functional drill assembly, and continue to control the cylindrical drill assembly on the horizontal plane of the multi-functional drill assembly to drill vertically downward to the design depth of the rectangular pile hole to form the embedded section of the rectangular pile hole, thereby forming a rectangular anti-sliding pile hole; (S6) The drilling rig is disengaged from the rectangular pile hole, and reinforced concrete is poured into the rectangular anti-slide pile hole to form a rectangular anti-slide pile.
2. The method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 1, characterized in that... The drilling rig is hoisted by a drilling vehicle equipped with a cable. The drilling vehicle includes a vehicle-mounted platform, a steel column, a tie rod, a hinge shaft, a guide rail, a slider, a steel cantilever beam, a winch motor, and a cable support. The steel column is vertically mounted on the vehicle-mounted platform. The upper end of the tie rod is hinged to the upper end of the steel column, and the lower end is hinged to the hinge shaft fixed on the vehicle-mounted platform. The guide rail is vertically mounted and fixed along the steel column. The slider is slidably mounted on the guide rail. The steel cantilever beam is fixed to the slider. The winch motor is fixed to the steel cantilever beam, and the cable support is fixed below the steel cantilever beam. The winch motor drives the cable to move up and down in the vertical direction.
3. The method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 1, characterized in that... The rock slag treatment mechanism includes a mixing device, a crushing device, a slag suction system, a slag discharge system, and a grouting system. The slag suction port of the mixing box of the mixing device is connected to the slag suction system via the crushing device. The slag discharge port of the mixing box is connected to the slag discharge system. A pipe fixing frame is provided above the mixing mechanism of the mixing device. The airbag assembly is installed on the pipe fixing frame or the pipe fixing frame and the mixing device. The grout outlet of the grouting system extends into the multi-functional drilling assembly.
4. The method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 3, characterized in that... The stirring mechanism includes a main gear and several auxiliary gears that mesh with and drive the main gear. The main gear is driven to rotate by a stirring motor. A stirring main shaft extending into the stirring tank is coaxially mounted on the main gear, and stirring blades are mounted on the stirring main shaft. An auxiliary stirring shaft extending into the stirring tank is coaxially mounted on the auxiliary gear, and stirring blades are mounted on the auxiliary stirring shaft.
5. The method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 3, characterized in that... The slag suction system includes a main slag suction pipe and a multi-functional slag suction branch pipe branching from the suction port of the main slag suction pipe. The suction head of the multi-functional slag suction branch pipe is connected to the multi-functional drill assembly. Each suction head is equipped with a multi-functional slag suction valve. The multi-functional slag suction branch pipe is connected to the main slag suction pipe through a telescopic pipe.
6. The method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 5, characterized in that... The grouting system includes a main grouting pipe, a grouting pump, and multi-functional grouting branch pipes. One end of the main grouting pipe is connected to the grouting pump located on the ground, and the other end is connected to several multi-functional grouting branch pipes. The nozzles of the multi-functional grouting branch pipes are connected to the multi-functional drilling assembly. Each nozzle is equipped with a multi-functional grouting valve. The multi-functional grouting branch pipes are connected to the main grouting pipe via telescopic pipes. The slag discharge system includes a slag discharge pipe and a slag discharge pump. One end of the slag discharge pump is connected to the slag discharge pipe, and the other end is connected to the slag discharge port on the mixing tank.
7. The method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 6, characterized in that... The slag suction main pipe, the grouting main pipe, and the slag discharge pipe are all arranged and fixed along the pipe fixing frame.
8. The method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 3, characterized in that... The airbag assembly includes an airbag unit arranged along the pipe fixing frame or the periphery of the pipe fixing frame and the stirring device, and an air pump connected to the airbag unit via an air pipe and located on the ground. The airbag unit is fixed to the pipe fixing frame by a ring clamp, and air valves are provided at the top and bottom of the airbag unit.
9. A method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 1, characterized in that... The U-shaped fork plate consists of a web, wing plates on both sides of the web, and a steel support in the middle of the web. The web includes a horizontal web and a vertical web. The cylindrical drill assembly includes two cylinders, a motor that drives the cylinders to rotate, a plurality of hobbing cutter assemblies spaced apart on the surface of the cylinders, and a plurality of reamer assemblies arranged between adjacent hobbing cutter assemblies. The hobbing cutter assembly includes a hobbing cutter base and a ring of hobbing cutters fixed on the hobbing cutter base. The reamer assembly includes a reamer base and reamers that are inclined and fixed on the reamer base. The motor shaft passes through the cylinders on both sides, and the end of the motor shaft is correspondingly disposed in the shaft holes of the wing plates on both sides of the U-shaped fork plate. The outer shell of the motor is welded and fixed to the steel support.
10. A method for staged drilling construction of a rectangular anti-slide pile with airbag-supported wall and horizontal cantilever as described in claim 9, characterized in that... The sliding reaction frame includes a reaction plate, a rail plate, and a connecting plate. The rail plate is installed on the top of the reaction plate, and T-shaped slide rails are fixed on both sides of the bottom of the rail plate. The connecting plate is fixed on both sides of the web of the U-shaped fork plate. A slider is fixed on the top of the connecting plate, and a T-shaped slide groove that mates with the T-shaped slide rail is opened in the slider. The cylinder end face of the horizontal hydraulic cylinder is fixed on the reaction plate of the sliding reaction frame, and the piston rod of the horizontal hydraulic cylinder is connected to the vertical web of the U-shaped fork plate.
Citation Information
Patent Citations
Rectangular drilling machine
CN103244053A
Rectangular drilling machine
CN104533300A
Rectangular drilling machine
CN105951798A
Mechanical perforation device for rectangular anti-slide piles
CN106836354A
Square anti-slide pile hole forming method and square drill bit for hole forming
CN108678661A