Digital bridge hydraulic climbing formwork synchronous climbing PLC closed-loop intelligent control equipment

Through the digital bridge hydraulic climbing form synchronization PLC closed-loop intelligent control system and structural design, the problem of bridge hydraulic climbing form shaking under strong winds was solved, the stability of the climbing form and the tightness of cement were improved, and construction safety was ensured.

CN117107642BActive Publication Date: 2024-10-25CHONGQING COMM CONSTR GRP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310986031.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-08-07
Publication Date
2024-10-25
Estimated Expiration
2043-08-07

AI Technical Summary

Technical Problem

In strong winds, the bridge's hydraulic climbing formwork lacks ventilation, causing the formwork to sway on the top of the bridge pier, posing a safety hazard.

Method used

The digital bridge hydraulic climbing formwork is used to synchronize the PLC closed-loop intelligent control system, including sensor configuration, hydraulic actuator, PLC controller and intelligent control algorithm, to monitor and adjust the position, speed, pressure and tilt angle of the climbing formwork in real time to achieve precise control through the hydraulic system. Climb control, reduce wind resistance through sliding baffles and impeller structures, and use wind power and vibrating plates to tighten cement.

Benefits of technology

It improves the stability and safety of the climbing formwork, reduces the impact of wind on the formwork, ensures the safety of the equipment and the tightness of the cement, and avoids cement falling off and gravel falling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117107642B_ABST
    Figure CN117107642B_ABST
Patent Text Reader

Abstract

The present application provides a PLC closed-loop intelligent control system and equipment for synchronous climbing of a digital bridge hydraulic climbing formwork, including a frame plate, the frame plate includes a guide structure and a base plate, the inner side of the top of the base plate is equidistantly provided with a guide structure, the guide structure is composed of an orientation groove and a guide groove, a template is movably installed on the inner side of the top of the guide structure, ventilation grooves are equidistantly opened on the surface of the template, a baffle is movably installed inside the ventilation groove, and both ends of the top and bottom of the baffle are fixedly installed with limiting balls. The present application sets a slidable baffle, when the upper mold is being demolded, the limiting ball at the bottom of the baffle is blocked, so that the baffle is folded to the middle, and then a ventilation groove appears in the middle of the upper mold, so that the wind resistance of the upper mold at high altitude can be reduced, thereby solving the problem of equipment instability caused by excessive wind at high altitude in the prior art.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of construction, and in particular to a PLC closed-loop intelligent control system and equipment for synchronous climbing of a digital bridge hydraulic climbing formwork. Background Art

[0002] Climbing formwork is the abbreviation of climbing formwork, also known as jumping formwork abroad. It consists of three parts: climbing formwork, climbing frame and climbing equipment. It is an effective tool in the construction of high-rise structures such as shear wall systems, cylinder systems and bridge piers. Due to its self-climbing ability, it does not require lifting machinery, which reduces the lifting workload of transportation machinery during construction. Hanging scaffolding on the self-climbing formwork can eliminate the external scaffolding during the construction process.

[0003] When building a bridge by the river, the wind on the river is usually strong, especially at high altitudes. Therefore, when the hydraulic climbing formwork used in building a bridge by the river is used at high altitudes, in strong winds, the formwork rises to a high place, and the formwork is not breathable, which causes the formwork to shake on the top of the pier, causing the equipment to shake when the pier rises, posing a safety hazard.

[0004] Therefore, we made improvements to this and proposed a PLC closed-loop intelligent control system and equipment for the synchronous climbing of digital bridge hydraulic climbing formwork. Summary of the invention

[0005] The purpose of the present invention is to address the current situation of strong winds, where the template rises to a high place and the template is not air-permeable, causing the template to shake on the top of the pier, causing the equipment to shake when the pier rises, thus posing a safety hazard.

[0006] In order to achieve the above-mentioned purpose of the invention, the present invention provides the following digital bridge hydraulic climbing formwork synchronous climbing PLC closed-loop intelligent control system and equipment to improve the above-mentioned problems.

[0007] The specific application is as follows:

[0008] The PLC closed-loop intelligent control system for synchronous climbing of the hydraulic climbing formwork of a digital bridge includes a. sensor configuration for real-time monitoring of parameters such as position, speed, pressure and tilt angle of the digital bridge climbing formwork;

[0009] b. Hydraulic actuator, which controls the climbing process of the bridge climbing formwork by adjusting the working parameters of the hydraulic system;

[0010] c. PLC controller, which receives sensor data and processes it in real time to generate control instructions for controlling the hydraulic actuator;

[0011] d. Intelligent control algorithms that calculate and adjust the control instructions of the hydraulic system in real time based on information such as sensor data, setpoints and bridge characteristics;

[0012] e. Hydraulic climbing formwork safety monitoring system, used to monitor and protect the safety of hydraulic climbing formwork operations in real time.

[0013] As a preferred technical solution of the present application, the sensor configuration includes a position sensor, a speed sensor, a pressure sensor and a tilt sensor.

[0014] As a preferred technical solution of the present application, the position sensor is arranged on the inner side of the upper frame to detect the position of the template, the speed sensor is located at the bottom of the upper frame to detect the moving speed of the four corners of the upper frame, the pressure sensor is located between the upper frame and the base to detect the load-bearing capacity of the frame, and the tilt sensor is located between the template and the upper frame to detect the degree of inclination of the template.

[0015] As the preferred technical solution of the present application, the hydraulic actuator realizes precise climbing control of the bridge climbing formwork by adjusting parameters such as the hydraulic oil flow, pressure and valve status of the hydraulic system.

[0016] As a preferred technical solution of the present application, the PLC controller receives sensor data, performs data processing and logical operations, generates control instructions for controlling the hydraulic actuator, and realizes closed-loop control of the climbing process.

[0017] As the preferred technical solution of this application, the intelligent control algorithm combines sensor data, set values, bridge characteristics and other information, and calculates and adjusts the control instructions of the hydraulic system in real time through model prediction, adaptive control and optimization algorithms to improve the stability, accuracy and safety of climbing.

[0018] The digital bridge hydraulic climbing formwork synchronous climbing equipment comprises a frame plate, the frame plate includes a guide structure and a base plate, the inner side of the top of the base plate is equidistantly provided with a guide structure, the guide structure is composed of an orientation groove and a guide groove, a template is movably installed on the inner side of the top of the guide structure, ventilation grooves are equidistantly opened on the surface of the template, a baffle is movably installed inside the ventilation groove, limiting balls are fixedly installed at both ends of the top and bottom of the baffle, a limiting column is fixedly installed in the middle of the bottom of the baffle, the limiting ball is slidably engaged in the orientation groove, the limiting column is slidably engaged in the guide groove, and the limiting column at the top of the baffle is slidably engaged in the top of the inner cavity of the ventilation groove.

[0019] As a preferred technical solution of the present application, a driving structure is fixedly installed at both ends of the template, and the driving structure includes an impeller, a driving shaft and a generator. The generator is fixedly installed between two adjacent base plates, and the driving shaft is fixedly connected to the transmission shaft of the generator. The impeller is fixedly connected to the top of the driving shaft, and two driving gears are fixedly installed equidistantly in the middle of the driving shaft.

[0020] As a preferred technical solution of the present application, two groups of vibration structures are fixedly installed on the outer side of the template, and the vibration structure includes a rotating shaft and a vibration plate. The vibration plate is fixedly installed on the surface of the baffle, and the rotating shaft is rotatably installed on the outer side of the template. Cams are fixedly installed at equal intervals on the surface of the rotating shaft, and the cams are located on the outer side of the vibration plate and fit onto the surface of the vibration plate.

[0021] As a preferred technical solution of the present application, a pair of upper mold structures are provided on the outer side of the template, and the upper mold structure includes an electric telescopic cylinder and an articulated rod. A pair of articulated rods are movably hinged on the outer side of the bottom of the template, and the outer end of the top of the articulated rod is movably hinged with an electric telescopic cylinder. The top of the electric telescopic cylinder is movably hinged to the outer side of the template. A traction structure is fixedly installed on the bottom of the frame plate, and the traction structure includes a lower frame body and a flap, and the flap is movably hinged to the inner side of the lower frame body. Both ends of the top of the flap are fixedly connected with a traction rope, and the top of the traction rope is fixedly connected to the side of the articulated rod, and wire poles are fixedly installed on both sides of the top of the bottom plate, and the traction rope is located on the inner side of the wire poles. Wire holes are opened on both sides of the top of the bottom plate, and wire fixers are fixedly installed on the upper sides of both sides of the lower frame, and the traction rope passes through the wire fixer and the wire hole.

[0022] Compared with the prior art, the present invention has the following beneficial effects:

[0023] In the scheme of this application:

[0024] 1. By setting a slidable baffle, when the upper mold is being demoulded, the limiting ball at the bottom of the baffle is blocked, so that the baffle is folded toward the middle, and a ventilation slot appears in the middle of the upper mold, so that the wind resistance of the upper mold at high altitude can be reduced, thereby solving the problem of equipment instability caused by excessive wind in the high altitude in the prior art;

[0025] 2. The impellers arranged at the four corners of the upper mold drive the vibration sheet attached to the outside of the baffle, and the vibration of the vibration sheet causes the baffle to shake continuously, so that the cement entering the template can be more compact, so that the cement between the templates can be compacted, thereby solving the problem that the cement in the template cannot be vibrated and compacted at high altitude in the prior art;

[0026] 3. By setting a generator between adjacent upper molds and fixing the bottom end of the impeller to the rotating shaft of the generator, when the impeller rotates, the impeller will automatically rotate under the action of wind force, thereby generating electricity, and the electrical equipment is powered by the electricity generated by wind force;

[0027] 4. The flap set on the lower frame is used to shield the space between the lower frame and the pier wall, and the top of the flap is connected to the upper mold through a traction rope. When the upper mold is withdrawn, the top of the flap is pulled up by the traction rope. At the same time, when the upper mold is clamped, the flap will automatically cover the gap between the pier wall and the lower frame under the action of gravity, thereby preventing the gravel above from falling through the gap and automatically realizing the flipping of the flap;

[0028] 5. By cutting the impeller obliquely, the expansion piece in the middle of the impeller can be expanded and contracted, and then cooperate with the repulsion of like charges between the electromagnet and the electromagnetic ring, so that the impeller can bend after the electromagnet is energized. At this time, the impeller will retract the expansion piece, thereby increasing the gravity and stiffness of the impeller, thereby producing a strong collision with the template. When the template collides with the impeller after the cement pier wall solidifies, the vibration piece on the template can separate the template from the cement pier wall at a high vibration frequency, thereby facilitating demoulding of the template and preventing the cement on the cement pier wall from sticking to the template and causing the cement to fall off. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 Diagram of the PLC closed-loop intelligent control system for the synchronous climbing of the hydraulic climbing formwork of the digital bridge provided for this application;

[0030] Figure 2 The overall structural diagram of the digital bridge hydraulic climbing formwork synchronous climbing equipment provided in this application;

[0031] Figure 3 A schematic diagram of the inner structure of the digital bridge hydraulic climbing formwork synchronous climbing device provided in this application;

[0032] Figure 4 A schematic diagram of the structure of one side of the digital bridge hydraulic climbing formwork synchronous climbing device provided in this application;

[0033] Figure 5 Schematic diagram of the baffle structure of the digital bridge hydraulic climbing formwork synchronous climbing equipment provided for this application;

[0034] Figure 6 Schematic diagram of the frame structure of the digital bridge hydraulic climbing formwork synchronous climbing equipment provided for this application;

[0035] Figure 7 A schematic diagram of the side view structure of the baffle of the digital bridge hydraulic climbing formwork synchronous climbing device provided in this application;

[0036] Figure 8 The digital bridge hydraulic climbing formwork synchronous climbing device provided for this application Figure 7 A schematic diagram of the enlarged structure at point A;

[0037] Fig. 9 A schematic diagram of the driving structure of the digital bridge hydraulic climbing formwork synchronous climbing device provided in this application;

[0038] Fig.10 The digital bridge hydraulic climbing formwork synchronous climbing device provided for this application Fig. 9 A schematic diagram of the enlarged structure at B;

[0039] Fig.11 A schematic diagram of the partial structure of the digital bridge hydraulic climbing formwork synchronous climbing equipment provided in this application.

[0040] Indicated in the figure:

[0041] 1. Frame; 101. Bottom plate; 102. Motor; 103. Threaded rod; 104. Wire hole; 2. Guide structure; 201. Orientation slot; 202. Guide slot; 3. Template; 301. Ventilation slot; 302. Baffle; 303. Stop ball; 304. Stop column; 305. Positioning bolt; 4. Vibration structure; 401. Rotating shaft; 402. Cam; 403. Vibration plate; 404. Driven gear; 5. Driving structure; 501. Impeller; 502. Driving shaft; 503. Generator; 504. Driving Gear; 505, limit hook; 506, telescopic piece; 507, electromagnet; 508, iron rod; 509, magnet; 510, electromagnetic ring; 6, upper mold structure; 601, electric telescopic cylinder; 602, hinged rod; 7, traction structure; 701, lower frame; 702, flap; 703, traction rope; 704, wire holder; 705, wire column; 8, fixing structure; 801, installation groove; 802, support spring; 803, reset spring; 804, positioning rod; 805, push rod; 806, extrusion block. DETAILED DESCRIPTION

[0042] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0043] As described in the background technology, in the case of strong winds, the template rises to a high place, and the template is not air-permeable, which causes the template to shake on the top of the pier, causing the equipment to shake when the pier rises, posing a safety hazard.

[0044] In order to solve this technical problem, the present invention provides a PLC closed-loop intelligent control system and equipment for synchronous climbing of a digital bridge hydraulic climbing formwork, which is applied to a hydraulic climbing formwork.

[0045] Specifically, please refer to Figure 1 The digital bridge hydraulic climbing formwork synchronous climbing device specifically includes a. sensor configuration for real-time monitoring of parameters such as position, speed, pressure and tilt angle of the digital bridge climbing formwork; b. hydraulic actuator for controlling the climbing process of the bridge climbing formwork by adjusting the working parameters of the hydraulic system; c. PLC controller for receiving sensor data and processing it in real time to generate control instructions for controlling the hydraulic actuator; d. An intelligent control algorithm calculates and adjusts the control instructions of the hydraulic system in real time based on information such as sensor data, set values ​​and bridge characteristics; e. A hydraulic climbing formwork safety monitoring system is used to monitor and protect the safety of hydraulic climbing formwork operations in real time. The sensor configuration includes a position sensor, a speed sensor, a pressure sensor and a tilt sensor. The position sensor is arranged on the inner side of the upper frame to detect the position of the formwork. The speed sensor is located at the bottom of the upper frame to detect the moving speed of the four corners of the upper frame. The pressure sensor is located between the upper frame and the base to detect the load-bearing capacity of the frame. The tilt sensor is located between the formwork and the upper frame to detect the degree of inclination of the formwork. The hydraulic actuator realizes precise climbing control of the bridge climbing formwork by adjusting parameters such as the hydraulic oil flow, pressure and valve status of the hydraulic system. The PLC controller receives sensor data, performs data processing and logic operations, generates control instructions for controlling the hydraulic actuator, and realizes closed-loop control of the climbing process. The intelligent control algorithm combines information such as sensor data, set values ​​and bridge characteristics.

[0046] The digital bridge hydraulic climbing formwork synchronous climbing PLC closed-loop intelligent control system provided by the present invention calculates and adjusts the control instructions of the hydraulic system in real time through means such as model prediction, adaptive control and optimization algorithm, so as to improve the stability, accuracy and safety of climbing.

[0047] In order to enable those skilled in the art to better understand the solutions of the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings.

[0048] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features and technical solutions in the embodiments may be combined with each other.

[0049] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0050] Example 1

[0051] Please refer to Figure 2 , Figure 4 and Figure 7 The digital bridge hydraulic climbing formwork synchronous climbing device comprises a frame plate 1, the frame plate 1 comprises a guide structure 2 and a bottom plate 101, the inner side of the top of the bottom plate 101 is equidistantly provided with a guide structure 2, the guide structure 2 is composed of an orientation groove 201 and a guide groove 202, a template 3 is movably installed on the inner side of the top of the guide structure 2, ventilation grooves 301 are equidistantly opened on the surface of the template 3, a baffle 302 is movably installed inside the ventilation groove 301, both ends of the top and bottom of the baffle 302 are fixedly installed with a limit column 304, a limit ball 303 is fixedly installed in the middle of the bottom of the baffle 302, and the limit ball 303 is fixedly installed in the middle of the bottom of the baffle 302. 03 is slidably engaged in the directional groove 201, the limiting column 304 is slidably engaged in the guide groove 202, and the limiting column 304 on the top of the baffle 302 is slidably engaged in the top of the inner cavity of the ventilation groove 301. Before the upper mold is applied, the template 3 will move outward as a whole. At this time, the limiting ball 303 and the limiting column 304 at the bottom of the baffle 302 on the inner side of the template 3 are restricted by the directional groove 201 and the guide groove 202 at the bottom, and will bend, thereby opening the ventilation groove 301. At this time, at high altitude, the ventilation groove 301 can reduce the wind force on the template 3 as a whole, thereby making the template 3 more stable.

[0052] By setting a slidable baffle, when the upper mold is being demolded, the limiting ball at the bottom end of the baffle is blocked, so that the baffle is folded toward the middle, and then a ventilation groove appears in the middle of the upper mold, so that the wind resistance of the upper mold at high altitude can be reduced, thereby solving the problem of excessive wind resistance at high altitude causing equipment instability in the prior art.

[0053] Please refer to Figure 2 , Figure 4 and Figure 5 , digital bridge hydraulic climbing formwork synchronous climbing equipment, both ends of the formwork 3 are fixedly installed with a driving structure 5, the driving structure 5 includes an impeller 501, a driving shaft 502 and a generator 503, the generator 503 is fixedly installed at the bottom end of the side of the formwork 3, the drive shaft of the generator 503 is fixedly connected with the driving shaft 502, the impeller 501 is fixedly connected to the top of the driving shaft 502, and two driving gears 504 are fixedly installed at equal distances in the middle of the driving shaft 502. At high altitudes, due to the strong wind force, the impeller 501 will continue to rotate under the action of the wind, so that the impeller 501 pulls the driving shaft 502 at the bottom to rotate, and then the generator 503 generates electrical energy, and the electrical energy generated by the generator 503 can power electrical equipment.

[0054] By setting a generator between adjacent upper molds and fixing the bottom end of the impeller to the rotating shaft of the generator, when the impeller rotates, the impeller will automatically rotate under the action of wind force, thereby generating electricity and powering electrical equipment through the electricity generated by wind force.

[0055] Example 2

[0056] The digital bridge hydraulic climbing formwork synchronous climbing device provided in Example 1 is further optimized, specifically, as follows: Figure 5 and Figure 7 As shown, two groups of vibration structures 4 are fixedly installed on the outer side of the template 3, and the vibration structure 4 includes a rotating shaft 401 and a vibration plate 403. The vibration plate 403 is fixedly installed on the surface of the baffle 302, and the rotating shaft 401 is rotatably installed on the outer side of the template 3. Cams 402 are equidistantly fixedly installed on the surface of the rotating shaft 401. The cams 402 are located on the outer side of the vibration plate 403 and fit on the surface of the vibration plate 403. The rotating shaft 401 rotates to pull the cam 402 to rotate, so that the cam 402 squeezes the vibration plate 403 on the surface of the baffle 302, and then the cam 402 makes the vibration plate 403 vibrate continuously during the rapid rotation process, thereby vibrating the baffle 302, so that the cement filled into the inner side of the template 3 can be vibrated, and the cement filling is made more compact.

[0057] Impellers arranged at the four corners of the upper mold are used to drive a vibration plate attached to the outside of the baffle. The vibration of the vibration plate causes the baffle to shake continuously, so that the cement entering the template can be more compact. In this way, the cement between the templates can be compacted, thereby solving the problem in the prior art that the cement in the template cannot be vibrated and compacted at high altitudes.

[0058] Further, such as Figure 4 and Figure 5 As shown, limit hooks 505 are fixedly installed on both sides of the template 3, and the limit hooks 505 are clamped on the side of the driving shaft 502. A driven gear 404 is fixedly installed on the end of the rotating shaft 401, and the driven gear 404 is meshed with the side of the driving gear 504. The impeller 501 rotates continuously under the action of wind force and then pulls the driven gear 404 to rotate synchronously through the driving gear 504, thereby rotating the rotating shaft 401. Here, the driving gear 504 and the driven gear 404 are both conical gears, and the two are meshed with each other, and the impeller 501 is used as a driving device.

[0059] The impeller 501 is used to drive the driven gear 404 to rotate, and then the cam 402 is driven to rotate, so as to save the driving source, thereby saving electricity and reducing consumption on the equipment. At the same time, the side of the driving shaft 502 is limited by the limiting hook 505 to ensure that the driving shaft 502 can rotate normally.

[0060] Example 3

[0061] The digital bridge hydraulic climbing formwork synchronous climbing device provided in Example 1 or 2 is further optimized, specifically, as follows Figure 2 , Figure 3 and Figure 4 As shown, a pair of upper mold structures 6 are provided on the outer side of the template 3, and the upper mold structure 6 includes an electric telescopic cylinder 601 and a hinged rod 602. A pair of hinged rods 602 are movably hinged on the outer side of the bottom of the template 3, and the outer end of the top of the hinged rod 602 is movably hinged with an electric telescopic cylinder 601. The top of the electric telescopic cylinder 601 is movably hinged to the outer side of the template 3. A traction structure 7 is fixedly installed at the bottom of the frame 1. The traction structure 7 includes a lower frame 701 and a flap 702. The flap 702 is movably hinged to the inner side of the lower frame 701. Both ends of the top of the flap 702 are fixedly connected with traction ropes 703. Positioning bolts are equidistantly provided in the middle of the template 3. 305, the positioning bolt 305 is stuck on the pier wall, and the top of the traction rope 703 is fixedly connected to the side of the hinged rod 602. When the template 3 moves outward, the hinged rod 602 on the outside of the template 3 will pull the traction rope 703 to move, so that the traction rope 703 pulls the flap 702 to flip over. When the template 3 is in a closed state, the flap 702 will automatically fit with the pier wall under the action of gravity, thereby preventing the risk of falling gravel. When the template 3 moves to the outside, the flap 702 will flip upward under the traction of the traction rope 703, so that the flap 702 is opened, which makes it convenient for the equipment to rise.

[0062] The flap set on the lower frame is used to shield the lower frame and the pier wall, and the top of the flap is connected to the upper mold by a traction rope. When the upper mold is withdrawn, the top of the flap is pulled up by the traction rope, and when the upper mold is clamped, the flap will automatically cover the gap between the pier wall and the lower frame under the action of gravity, thereby preventing the gravel above from falling through the gap and automatically realizing the flipping of the flap.

[0063] Further, such as Figure 4 and Figure 6 As shown, wire posts 705 are fixedly installed on both sides of the top of the base plate 101, and the traction rope 703 is located on the inner side of the wire posts 705. Wire holes 104 are opened on both sides of the top of the base plate 101, and wire holders 704 are fixedly installed on the upper part of both sides of the lower frame 701. The traction rope 703 passes through the wire holders 704 and the wire holes 104, and the traction rope 703 is threaded through the wire holes 104 and the wire holders 704, thereby facilitating the threading of the traction rope 703. The traction rope 703 is guided by the wire posts 705 so that the movement of the traction rope 703 can facilitate the lifting and lowering of the flap 702.

[0064] This makes it easy to flip the flap 702, so that the flap 702 can not only prevent the debris from falling and protect the staff, but also facilitate the lifting and lowering of the equipment as a whole. After the flap 702 is opened, it will not generate friction with the pier wall.

[0065] Further, such as Figure 4 As shown, the two ends of the electric telescopic cylinder 601 are respectively movably hinged on the back side of the template 3 and the outer end of the hinged rod 602, so that the electric telescopic cylinder 601 can flip the template 3 by contraction, and the bottom end of the template 3 and the hinged rod 602 are hingedly connected, so as to facilitate the angle adjustment of the template 3. The outer end of the base plate 101 is fixedly installed with a motor 102, and the output end of the motor 102 is transmission-connected with a threaded rod 103. The slider at the bottom of the hinged rod 602 is threadedly connected to the threaded rod 103, and the threaded rod 103 is driven to rotate by the motor 102, so that the template 3 is translated in the horizontal direction, thereby playing the role of fixing and lowering the mold.

[0066] The outer side of the upper mold is supported by an electric telescopic cylinder so that the upper mold can remain clamped inward. The setting of the electric telescopic cylinder can provide good support for the template and ensure the stability of the template during docking.

[0067] Further, such as Figure 6 As shown, the slide groove of the guide groove 202 is set to a shape inclined inward, and the length of the guide groove 202 exceeds the length of the directional groove 201. The limiting ball 303 is first limited by the directional groove 201, and then the limiting column 304 is limited and guided by the guide groove 202, so that the baffle 302 can be bent and the ventilation groove 301 can be opened. At the same time, the cam 402 is located on the outside of the vibration plate 403. When the template 3 moves outward as a whole, the baffle 302 loses the support of the concrete pier wall. At this time, the vibration plate 403 on the outside of the baffle 302 will be squeezed inward by the cam 402, thereby causing the baffle 302 to open to the middle of the inside.

[0068] The ventilation slot 301 is opened by bending the baffle 302, so that the ventilation slot 301 can guide the air at a high altitude, thereby reducing the wind force on the equipment at a high altitude.

[0069] Further, such as Fig. 9 , Fig.10 and Fig.11As shown, the rotating shaft at the bottom end of the impeller 501 is movably hinged at the top of the driving shaft 502, and the side circumference of the impeller 501 is telescopically sleeved with six telescopic pieces 506 at equal angles. An electromagnet 507 is sleeved in the middle of the impeller 501, and an iron rod 508 is fixedly connected to the bottom of the electromagnet 507. The iron rod 508 is slidably sleeved in the middle of the rotating shaft at the bottom of the impeller 501. A mounting groove 801 is opened in the middle of the limit hook 505, and a support spring 802 and a return spring are fixedly installed on the side and bottom of the mounting groove 801 respectively. 803, a positioning rod 804 is fixedly connected to the inner side of the support spring 802, an extrusion block 806 is fixedly connected to the top of the reset spring 803, the positioning rod 804 is located on the outer side of the extrusion block 806, a top of the extrusion block 806 is fixedly connected to a push rod 805, a magnet 509 is provided on the top of the drive shaft 502, the bottom end of the iron rod 508 is clamped on the top of the drive shaft 502, an electromagnetic ring 510 is fixedly installed in the middle of the drive shaft 502, and the top of the drive shaft 502 is inclined toward the outer sides of the two adjacent templates 3.

[0070] When the electromagnet 507 is energized and acquires magnetism, the iron rod 508 has the same magnetism, and the iron rod 508 and the magnet 509 produce a repulsive reaction, so that the iron rod 508 pushes the electromagnet 507 upward, and at the same time, the electromagnet 507 absorbs the expansion piece 506 on the side of the impeller 501 to the middle, so that the expansion piece 506 is stored inside the impeller 501, thereby increasing the weight of the impeller 501 and the tantrum of the outer side. When the iron rod 508 rises, the push rod 805 loses its extrusion. At this time, the push rod 805 will rise upward under the support of the return spring 803 at the bottom, thereby raising the extrusion block 806, and then fixing the side of the drive shaft 502 through the positioning rod 804 to limit the rotation of the drive shaft 502. At this time, the impeller 501 will fall downward under the action of gravity, and the side of the impeller 501 is designed with a horizontal rounded counterweight block. , multiple counterweights are distributed in a ring shape, which plays the role of an inertia wheel, making it easier for the impeller 501 to rotate under the action of wind. When the expansion piece 506 falls to the lowest end, the expansion piece 506 collides with the templates 3 on both sides at the same time. At this time, the template 3 will vibrate, thereby causing the vibration piece 403 on the template 3 to vibrate. When the expansion piece 506 collides with the template 3, the electromagnetic ring 510 is energized, so that the electromagnet 507 in the middle of the impeller 501 has a repulsive reaction with the electromagnetic ring 510, thereby causing the impeller 501 to flip upward, and then the electromagnetic ring 510 is de-energized, and this cycle is repeated, so that the expansion piece 506 continuously collides with the side of the template 3, thereby causing the vibration piece 403 to separate from the template 3 and the cement pier wall during the vibration with the template 3, thereby facilitating the demoulding between the template 3 and the cement pier wall.

[0071] Further, such as Fig. 9 , Fig.10 and Fig.11As shown, a horizontal counterweight is arranged on the outer side of the expansion piece 506. When the impeller 501 at the top of the drive shaft 502 is in the numerical position, the electromagnet 507 is powered off. At this time, the electromagnet 507 will carry the iron rod 508 under the magnetic attraction of the magnet 509 and insert the iron rod 508 into the top of the drive shaft 502. At this time, the top rod 805 inside the drive shaft 502 will be squeezed and will drop downward, and squeeze the positioning rod 804 to the side, so that the positioning rod 804 will be separated from the bottom of the squeezing block 806, thereby making the drive shaft 502 lose its restriction. At this time, the impeller 501 at the top of the drive shaft 502 will rotate under the action of wind force, and at the same time, the expansion piece 506 on the outer side of the drive shaft 502 will automatically extend outward and open due to the action of centrifugal force during the rotation process.

[0072] Therefore, after the template 3 is separated from the pier wall, the impeller 501 at the top of the driving shaft 502 can rotate under the action of wind force, and then the rotation of the impeller 501 drives the generator 503 at the bottom to generate electricity.

[0073] The use process of the digital bridge hydraulic climbing formwork synchronous climbing PLC closed-loop intelligent control system and equipment provided by the present invention is as follows:

[0074] Four frame plates 1 are arranged on the four side walls of the pier body, the wall mount is fixedly installed by embedded parts, the template 3 is arranged on the top of the frame plate 1, a row of ventilation slots 301 are evenly spaced on the surface of the template 3, and the ventilation slots 301 are sealed by baffles 302. When the template 3 is withdrawn under the traction of the upper mold structure 6, the threaded rod 103 is controlled to rotate by the motor 102, so that the hinged rod 602 moves the template 3 outward, and at this time, the limiting ball 303 and the limiting column 304 at the bottom end of the baffle 302 inside the ventilation slot 301 are respectively slidably engaged with The directional groove 201 and the guide groove 202 are arranged in the direction groove 201 and the guide groove 202, so that the baffle plate 302 is bent toward the middle, and then the ventilation groove 301 is opened. When the equipment climbs as a whole, the template 3 rises as a whole, so that when the template 3 rises to a high place, the wind can pass through the ventilation groove 301, thereby reducing the wind force on the template 3, and making the equipment more stable; when the motor 102 controls the upper mold structure 6 to send the template 3 to the inside for mold closing, the template 3 will squeeze the baffle plate 302 inward during the process of moving inward, so that the baffle plate 302 is supported inside the ventilation groove 301. The impellers 501 on the four sides of the template 3 can rotate quickly under the action of wind, and the rotating shaft 401 is rotated through the driving gear 504 and the driven gear 404. The rotating shaft 401 will continuously vibrate the vibration plate 403 during the rotation, so that the vibration plate 403 hits the baffle 302, so that the baffle 302 is constantly shaken, so that the cement inside the template 3 can be deposited more tightly; the impeller 501 will cause the generator 503 to generate electrical energy during the rotation, so that the generator 503 can generate electricity. The electric energy generated by the motor 503 can power the equipment; when the template 3 moves outward, the hinged rod 602 pulls the traction rope 703, so that the traction rope 703 pulls the top of the flap 702, so that the flap 702 flips open, so that the template 3 and the traction structure 7 can be easily lifted and lowered. When the template 3 is attached to the side of the pier wall for closing, the flap 702 will automatically fit to the side of the pier wall under the action of gravity, so that the flap 702 seals the gap between the equipment and the pier wall to prevent gravel from falling.

[0075] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0076] Obviously, the embodiments described above are only some embodiments of the present invention, rather than all embodiments. The preferred embodiments of the present invention are given in the accompanying drawings, but they do not limit the patent scope of the present invention. The present invention can be implemented in many different forms. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the present invention more thorough and comprehensive. Although the present invention has been described in detail with reference to the aforementioned embodiments, for those skilled in the art, it is still possible to modify the technical solutions recorded in the aforementioned specific embodiments, or to perform equivalent replacements for some of the technical features therein. Any equivalent structure made using the contents of the specification and drawings of the present invention, directly or indirectly used in other related technical fields, is also within the scope of patent protection of the present invention.

Claims

1. Digital bridge hydraulic climbing formwork synchronous climbing PLC closed-loop intelligent control equipment, It is characterized in that include: a. Sensor configuration for real-time monitoring of the position, speed, pressure and inclination angle parameters of the digital bridge climbing formwork; b. Hydraulic actuator, which controls the climbing process of the bridge climbing formwork by adjusting the working parameters of the hydraulic system; c. PLC controller, which receives sensor data and processes it in real time to generate control instructions for controlling the hydraulic actuator; d. Intelligent control algorithm, which calculates and adjusts the control instructions of the hydraulic system in real time based on sensor data, set values ​​and bridge characteristic information; e. Hydraulic climbing formwork safety monitoring system, used to monitor and protect the safety of hydraulic climbing formwork operations in real time; The sensor configuration includes a position sensor, a speed sensor, a pressure sensor and a tilt sensor; The device comprises an upper frame, the upper frame comprises a frame plate (1), the frame plate (1) comprises a guide structure (2) and a bottom plate (101), a template (3) is movably mounted on the inner side of the top of the guide structure (2), the position sensor is arranged on the inner side of the upper frame to detect the position of the template (3), the speed sensor is located at the bottom of the upper frame to detect the moving speed of the four corners of the upper frame, the pressure sensor is located between the upper frame and the base to detect the load-bearing capacity of the frame, and the tilt sensor is located between the template (3) and the upper frame to detect the tilt degree of the template (3); The hydraulic actuator realizes precise climbing control of the bridge climbing formwork by adjusting the hydraulic oil flow, pressure and valve state parameters of the hydraulic system; The PLC controller receives sensor data, performs data processing and logic operations, generates control instructions for controlling the hydraulic actuator, and realizes closed-loop control of the climbing process; The intelligent control algorithm combines sensor data, set values ​​and bridge characteristic information to calculate and adjust the control instructions of the hydraulic system in real time through model prediction, adaptive control and optimization algorithm means to improve the stability, accuracy and safety of climbing; The guide structure (2) is equidistantly provided on the inner side of the top of the bottom plate (101), the guide structure (2) being composed of an orientation groove (201) and a guide groove (202), the surface of the template (3) being equidistantly provided with ventilation grooves (301), a baffle (302) being movably installed inside the ventilation groove (301), both ends of the top and bottom of the baffle (302) being fixedly installed with limit posts (304), a limit ball (303) being fixedly installed in the middle of the bottom of the baffle (302), the limit ball (303) being slidably engaged in the orientation groove (201), the limit post (304) being slidably engaged in the guide groove (202), the limit post (304) at the top of the baffle (302) being slidably engaged in the top of the inner cavity of the ventilation groove (301), the slide groove of the guide groove (202) being arranged to be inclined inwardly, and the length of the guide groove (202) being greater than the length of the orientation groove (201); Before the upper mold is applied, the template (3) as a whole moves outwards. At this time, the limiting ball (303) and the limiting column (304) at the bottom of the baffle (302) inside the template (3) are restricted by the directional groove (201) and the guide groove (202) at the bottom and bend, thereby opening the ventilation groove (301).

2. According to claim 1, the PLC closed-loop intelligent control device for synchronous climbing of the digital bridge hydraulic climbing formwork, It is characterized in that A driving structure (5) is fixedly mounted on both ends of the template (3), the driving structure (5) comprising an impeller (501), a driving shaft (502) and a generator (503), the generator (503) being fixedly mounted on the bottom end of the side of the template (3), the driving shaft (502) being fixedly connected to the transmission shaft of the generator (503), the impeller (501) being fixedly connected to the top end of the driving shaft (502), and two driving gears (504) being fixedly mounted equidistantly in the middle of the driving shaft (502).

3. According to claim 1, the PLC closed-loop intelligent control device for synchronous climbing of the digital bridge hydraulic climbing formwork, It is characterized in that Two groups of vibration structures (4) are fixedly mounted on the outer side of the template (3), and the vibration structure (4) comprises a rotating shaft (401) and a vibration plate (403). The vibration plate (403) is fixedly mounted on the surface of the baffle (302), and the rotating shaft (401) is rotatably mounted on the outer side surface of the template (3). Cams (402) are fixedly mounted at equal intervals on the surface of the rotating shaft (401), and the cams (402) are located on the outer side of the vibration plate (403) and are attached to the surface of the vibration plate (403).

4. According to claim 1, the PLC closed-loop intelligent control device for synchronous climbing of the digital bridge hydraulic climbing formwork, It is characterized in that A pair of upper mold structures (6) are provided on the outer side of the template (3), and the upper mold structures (6) include an electric telescopic cylinder (601) and a hinged rod (602). The outer side of the bottom of the template (3) is movably hinged to a pair of hinged rods (602), and the outer ends of the tops of the hinged rods (602) are movably hinged to the electric telescopic cylinder (601). The top ends of the electric telescopic cylinders (601) are movably hinged to the outer side surface of the template (3). A traction structure (7) is fixedly installed on the bottom of the frame plate (1), and the traction structure (7) includes a lower frame body (701) and a flap (702). The flap (702) is movably hinged to the lower frame body (701). On the inner side of the frame (701), both ends of the top of the flap (702) are fixedly connected with a traction rope (703), the top of the traction rope (703) is fixedly connected to the side of the hinged rod (602), both sides of the top of the bottom plate (101) are fixedly installed with wire posts (705), the traction rope (703) is located on the inner side of the wire posts (705), both sides of the top of the bottom plate (101) are provided with wire holes (104), and both sides of the lower frame (701) are fixedly installed with wire fixers (704), and the traction rope (703) passes through the wire fixers (704) and the wire holes (104).