Construction device for pier column reinforcement parts

By welding steel mesh onto the positioning frame and using hooks and flexible cables for lifting, combined with threaded sleeves and extrusion cone sleeves to connect the main reinforcement bars, the problems of low efficiency and high cost in pier column reinforcement binding construction were solved, achieving efficient and economical pier column reinforcement component construction.

CN117306400BActive Publication Date: 2026-05-19CCCC SECOND HARBOR ENGINEERING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
CCCC SECOND HARBOR ENGINEERING CO LTD
Filing Date
2023-09-28
Publication Date
2026-05-19

AI Technical Summary

Technical Problem

The existing pier column reinforcement binding construction is inefficient, and the reinforcement components are complex and costly to manufacture, making it difficult to promote on a large scale.

Method used

The steel mesh is welded onto the positioning jig, and then lifted separately using hooks and flexible cables. The main reinforcement bars are connected by threaded sleeves and extrusion cone sleeves. The steel mesh is fabricated in the factory and then welded and assembled on site.

Benefits of technology

It improves the efficiency of rebar tying, reduces costs, and ensures construction accuracy and progress, resulting in good economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117306400B_ABST
    Figure CN117306400B_ABST
Patent Text Reader

Abstract

The application provides a kind of pier column steel part vertical non-matching forming industrialized construction method and construction device, comprising the following steps: S1, according to the shape and size of the steel mesh required by pier column design;S2, complete the welding of steel mesh;S3, steel mesh is placed in bracket;S4, use hook and cable to hoist the whole bracket and steel mesh into the first operation platform;S5, the two sides of the lifting appliance are installed with flexible cable;S6, the steel mesh of each layer is hung on the corresponding hook on the flexible cable;S7, the steel mesh in the bracket is hoisted in turn and the separation of the steel mesh is completed to form the mesh intermediate body;S8, continue to lift the hook to fix the lifting appliance and the upper cross beam on both sides;S9, install the alignment hanger on the lower side of the hook, and fix the main reinforcement in the mesh intermediate body through the positioning sleeve on the alignment hanger. The application is designed ingeniously, can greatly improve the production efficiency of steel parts, at the same time ensure the construction quality, thereby improve the efficiency of project construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of bridge construction technology, and in particular to a construction device for steel reinforcement components for bridge piers. Background Technology

[0002] Bridge piers are a crucial structural component. The reinforcement binding of pier piers is primarily done manually, with each rebar installed individually, resulting in low efficiency and limited quality control. Currently, some pier piers utilize prefabricated rebar components, while others employ a matching process. In this method, adjacent sections of the main reinforcement bars are connected using threaded sleeves during positioning. Once the main reinforcement bars are securely welded to the stirrups, the threaded sleeves are disassembled, and the previous section is transported to the pier for hoisting and installation, with the next section then matching. Other rebar components use extruded conical sleeves, where the main reinforcement bar joints can be on the same cross-section, eliminating the need for matching. However, both of these rebar component methods have significant drawbacks: matching rebar components are cumbersome to install and cannot achieve true effective matching, making it difficult to install even matched main reinforcement bar joints during installation. The extruded conical sleeve method is also extremely costly, resulting in poor overall economic efficiency and hindering widespread adoption. Summary of the Invention

[0003] This invention provides a construction device for pier column steel reinforcement components, which solves the technical problems of complex manufacturing process, long processing time, high cost, low construction efficiency, and unsuitability for large-scale use of pier column steel reinforcement components.

[0004] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is: a construction device for steel reinforcement components of pier columns, comprising the following steps:

[0005] S1. Design the shape and size of the steel mesh according to the needs of the pier column;

[0006] S2. The steel mesh is welded on the positioning jig using the first stirrup, the second stirrup, the first hook bar, the second hook bar, and the third stirrup.

[0007] S3. Place the completed steel mesh into the brackets respectively, and move them to the first operating platform when the design capacity is reached;

[0008] S4. By adjusting the vertical beams on the two first support frames, keep the two vertical beams in an open-up state, and then use hooks and cables to hoist the bracket and steel mesh as a whole into the upper support plate of the first fixing component.

[0009] S5. Disconnect the connection between the hook and the bracket, then install the lifting device at the bottom of the hook, and install flexible cables on both sides of the lifting device;

[0010] S6. Move the lifting device to the uppermost steel mesh, and then hang the steel mesh of each layer on the corresponding hooks on the flexible cable in turn;

[0011] S7. Lift the hook upwards to hoist the steel mesh inside the bracket in sequence and complete the separation of the steel mesh to form the middle body of the mesh;

[0012] S8. Continue to lift the hook to secure the lifting device and the upper crossbeams on both sides, and then disconnect the hook from the lifting device;

[0013] S9. Install the alignment bracket on the lower side of the hook, and fix the alignment bracket on the lower side of the bracket. Pass the main reinforcement through the positioning sleeve on the alignment bracket into the middle body of the mesh, and fix the upper part of the middle body of the mesh through the first threaded sleeve.

[0014] S10. Limit the middle body of the mesh by the vertical supports inside the two second operating platforms, adjust the height of the middle body of the mesh, and support the bottom of the middle body of the mesh on the positioning rod.

[0015] S11. After the intermediate body of the mesh and the main reinforcement are stable, the intermediate body of the mesh and the main reinforcement are fixed by binding and welding to form the steel reinforcement component.

[0016] S12. Hoist the steel reinforcement components to the top of the pier and fix them with the pre-embedded reinforcement, and then carry out the subsequent pouring process.

[0017] S13. Repeat S2 to S12 until all steel reinforcement components are completed.

[0018] In the preferred embodiment, in S3, by adjusting the positions of the first baffle and the second baffle on both sides of the bracket, the spacing between the two first baffles is matched with the length of the steel mesh, and the two sides of the steel mesh are just in contact with the inner side of the first baffle.

[0019] In the preferred embodiment, in step S5, after the bracket and hook are separated, the bolts on the second baffle and the bottom plate are removed, the locking pins on the second baffle and the bottom plate are released, and the second baffle is adjusted from a vertical state to a horizontal state by the bolts, thus completely releasing the constraint on the steel mesh.

[0020] In the preferred embodiment, in S5, a flexible cable of appropriate length is pre-cut according to the height of the steel reinforcement component, and then a fixing component is installed on the flexible cable. The hook is fixed by connecting the fixing component and the flexible cable. Multiple fixing components are evenly arranged on the flexible cable, and the distance between two fixing components is the spacing between two adjacent steel meshes.

[0021] In the preferred embodiment, before S9, the bracket is removed from the tray, and the two alignment hangers located on the upper and lower sides of the middle body of the mesh are placed facing each other, with the lower alignment hanger placed on the tray.

[0022] In the preferred embodiment, in S10, the alignment bracket located on the upper side is supported and fixed by multiple legs, with the lower part of the legs fixed to the adjusting pad.

[0023] In the preferred embodiment, in S12, the main reinforcement bars are connected to the pre-embedded reinforcement bars on the pier column through the second threaded sleeve and the extrusion cone sleeve respectively. After they are fixed in place, the upper alignment hanger is removed and lifted and removed using a hook, while the alignment hanger on the pallet is removed at the same time.

[0024] In the preferred embodiment, the system includes a positioning jig, a first operating platform, a bracket, a lifting device, an alignment bracket, and a second operating platform. The positioning jig is used to complete the welding of the steel mesh. The first operating platform includes two first support frames arranged opposite each other. The upper and lower sides of the first support frames are respectively provided with a lower crossbeam and an upper crossbeam. A first fixing member is provided on the lower crossbeam, and a second fixing member is slidably provided on the upper crossbeam. The second fixing member is connected to the first fixing member through a vertical beam. The second fixing member and the vertical beam are hinged. The upper support of the first fixing member is provided with a support plate.

[0025] The bracket includes a base plate, two first baffles are slidably provided on both sides of the base plate along the length direction, the bottom of the first baffles are connected to the base plate by bolts, two slide plates are slidably provided on both sides of the base plate along the width direction, the slide plates are connected to the base plate by bolts, and the slide plates are hinged to the second baffles by a shaft, with bolts passing through the second baffles and the base plate;

[0026] The upper side of the lifting device is hinged with a folding plate for connecting with the upper crossbeam. Multiple positioning sleeves are evenly arranged on the alignment frame. The diameter of the positioning sleeves matches the diameter of the main reinforcement. Flexible cables are detachably provided on both sides of the lifting device. Multiple hooks are evenly arranged on the flexible cables.

[0027] The second operating platform includes two second support frames arranged opposite each other. The bottoms of the two second support frames are connected by a pad plate. Multiple adjusting pads are provided on the pad plate. The vertical support is fixed on the pad plate. The pad plate is also provided with adjusting pads for fixing the outriggers.

[0028] In the preferred embodiment, the hook is connected to the flexible cable via a fixing component. The fixing component includes two parallel connecting blocks. A through groove is provided through the middle of the connecting blocks. A first notch is provided on one side of the connecting blocks. Two through holes are provided through the first notch. A limiting groove is provided on one side of the through groove. The flexible cable passes through the through groove, and the hook is located in the limiting groove. The U-shaped rod fixes the hook and the flexible cable with a nut.

[0029] In the preferred embodiment, the limiting groove is tapered, the small ends of the two limiting grooves are arranged opposite each other, and a locking component is provided between the two connecting blocks. The locking component includes a sealing plate, a second notch is provided on the sealing plate, a constraint sleeve is provided on one side of the second notch, the inner diameter of the constraint sleeve matches the outer diameter of the flexible cable, the constraint sleeve passes through the limiting groove, and an ear plate is provided on the outer side of the connecting block. The two ear plates on the same side are connected by a locking pin and a nut.

[0030] The beneficial effects of this invention are as follows: This solution facilitates material sourcing and rapid fabrication by disassembling the reinforcing mesh. The positioning jig ensures the installation accuracy of different stirrups and hook bars, thereby guaranteeing the fabrication accuracy of the reinforcing mesh. Simultaneously, the overall welding is performed robotically. The reinforcing mesh is fabricated in the factory and then transported to the project construction site for on-site welding and assembly. Different reinforcing meshes are lifted using flexible cables and hooks, avoiding excessive space occupation and ensuring relatively uniform spacing between different meshes, resulting in good overall fabrication accuracy. After the reinforcing mesh is divided, the main reinforcing bars are directly inserted into the mesh body, and a few main reinforcing bars are welded to the contact points of multiple layers of reinforcing mesh to form the reinforcing mesh component. Compared with other processes, this method features simple operation, good adaptability of main reinforcing bar connections, ensures construction progress, and has good economic benefits. Attached Figure Description

[0031] The present invention will be further described below with reference to the accompanying drawings and embodiments:

[0032] Figure 1 This is a schematic diagram of the steel mesh assembly of the present invention;

[0033] Figure 2 This is a schematic diagram of the reinforcing mesh of the present invention;

[0034] Figure 3 This is a top view of the steel mesh of the present invention placed on the bracket;

[0035] Figure 4 This is a front view schematic diagram of the steel mesh of the present invention placed on the bracket;

[0036] Figure 5 This is a schematic diagram of the first operating platform of the present invention;

[0037] Figure 6 This is the state one where the steel mesh of the present invention is hoisted to the first operating platform;

[0038] Figure 7 This is the second state of the present invention: the steel mesh is hoisted to the first operating platform.

[0039] Figure 8 This is the third state of the present invention, where the steel mesh is hoisted to the first operating platform;

[0040] Figure 9 This is a schematic diagram of the flexible cable and hook for installing the lifting device of the present invention;

[0041] Figure 10 This is a schematic diagram of the hook-separated steel mesh of the present invention, state one;

[0042] Figure 11 This is a schematic diagram of the hook separating the steel mesh of the present invention, state two;

[0043] Figure 12 This is a schematic diagram of the hook installation, alignment, and main reinforcement bar insertion of the hanger frame according to the present invention;

[0044] Figure 13 This is a schematic diagram of the main reinforcement bar installation of the steel mesh of the present invention, state one;

[0045] Figure 14 This is a schematic diagram of the main reinforcement bar installation of the steel mesh of the present invention, state two;

[0046] Figure 15 This is a schematic diagram of the steel reinforcement component of the present invention;

[0047] Figure 16 This is a schematic diagram of the pier column of the present invention;

[0048] Figure 17 This is a schematic diagram of the installation of the reinforcing steel components on the pier column of the present invention, state one;

[0049] Figure 18 This is a schematic diagram of the installation of the reinforcing steel components on the pier column of the present invention, state two;

[0050] Figure 19 This is a schematic diagram of the flexible cable mounting hook structure of the present invention;

[0051] Figure 20 yes Figure 19 A schematic diagram of the fixed component structure;

[0052] Figure 21 yes Figure 19 Schematic diagram of the exploded structure, state one;

[0053] Figure 22 yes Figure 19 The schematic diagram of the explosion structure, state two.

[0054] In the diagram: 1. First stirrup; 2. Second stirrup; 3. First hook reinforcement; 4. Second hook reinforcement; 5. Third stirrup; 6. Steel mesh; 7. First operating platform; 701. First support frame; 702. Lower crossbeam; 703. Upper crossbeam; 704. First fastener; 705. Second fastener; 706. Vertical beam; 707. Support plate; 8. Bracket; 801. First baffle; 802. Second baffle; 803. Base plate; 804. Bolt; 805. Shaft; 806. Hook; 9. Cable; 10. Lifting device; 11. Flexible cable; 12. Hook; 13. Alignment hanger; 14. Main reinforcement; 15. Second operating platform; 16. Vertical brace; 1601. Positioning rod; 16. 02; Adjusting pad 1603; Second support frame 1604; Pad plate 1605; First threaded sleeve 17; Pier column 18; Embedded reinforcement 19; Extrusion cone sleeve 20; Second threaded sleeve 21; Fixing component 22; Connecting block 2201; Through groove 2202; First notch 2203; Through hole 2204; Limiting groove 2205; Taper 2206; Ear plate 2207; Locking nail 2208; Nut 2209; U-shaped rod 2210; Locking component 23; Sealing layer plate 2301; Constraint sleeve 2302; Second notch 2303; Positioning sleeve 24; Mesh intermediate body 25; Reinforcing steel component 26; Support leg 27. Detailed Implementation

[0055] like Figure 1-18 A construction device for reinforcing steel components of a pier column includes the following steps:

[0056] S1. Design the shape and dimensions of the steel mesh 6 according to the requirements of the pier 18;

[0057] S2. Weld the steel mesh 6 on the positioning frame using the first stirrup 1, the second stirrup 2, the first hook bar 3, the second hook bar 4, and the third stirrup 5. According to the size requirements of the pier column steel stirrups, make a stirrup positioning frame. The frame is equipped with stirrup positioning slots and hook bar positioning slots. The steel positioning slots are based on the center line of the steel bar. The slot width is 3mm larger than the stirrup diameter, and the slot positioning height deviation is 5mm.

[0058] The stirrups and hook reinforcement units are pre-bent and fabricated on a stirrup bending machine. The bending radius deviation of the stirrups is 1cm, and the spacing deviation of the bent edges of the hook reinforcements is 5mm. A robotic arm automatically picks up the stirrup units and places them in the corresponding slots of the rebar mesh jig. Then, the positioning clamps on the jig clamp the stirrup units, and a welding robotic arm welds adjacent ring-shaped stirrup units together to form a ring. After the outer and inner rings of the stirrups in the same layer are fabricated, the robotic arm picks up and installs the hook reinforcements in the corresponding slots. The hook reinforcement units are welded together with the inner and outer rings of the stirrups by the robotic arm to connect with the stirrups and form mesh sheets. After the sheets are fabricated, a handling robotic arm directly stacks the rebar mesh sheets onto designated brackets. The brackets can precisely hold the rebar mesh sheets, ensuring that multiple rebar mesh sheets are arranged neatly and the outer contours of the stirrups are on the same plane.

[0059] S3. Place the completed steel mesh 6 into the bracket 8 respectively. When the design capacity is reached, move it to the first operating platform 7. After placing a certain number of steel mesh on the bracket 8, transport it together with the bracket to the component assembly frame via a flatbed truck. Ensure smooth and convenient overall flow, high production efficiency, and stable cycle time.

[0060] S4. By adjusting the vertical beams 706 on the two first support frames 701, the two vertical beams 706 are kept in an open-up state. Then, the bracket 8 and the steel mesh 6 are hoisted together and placed on the upper support plate 707 of the first fixing member 704 using the hook 9 and the cable 10. This ensures stable support for the bracket 8 and high overall construction precision. The support plate adopts a spiral jacking method, which makes it easy to ensure that the steel mesh 6 is in a horizontal installation state.

[0061] S5. Disconnect the connection between the hook 9 and the bracket 8, and then install the lifting device 11 at the bottom of the hook 9. Install the flexible cable 12 on both sides of the lifting device 11.

[0062] S6. Move the lifting device 11 to the uppermost steel mesh 6, and then hang the steel mesh 6 of each layer on the corresponding hooks 13 on the flexible cable 12 in sequence; the hooks 13 can conveniently and quickly hang and fix the steel mesh 6.

[0063] Six flexible cables 12 are used. Hooks 13 on the flexible cables 12 are hung on the outside of the component lifting device, one at each of the four corners and one on each of the long sides. The steel mesh is lifted sequentially and hooked onto the hooks. A staggered limiting fixture is provided corresponding to the main reinforcement 15. The positioning rods 1602 are staggered, arranged in order of height, with the positioning rods 1602 and the main reinforcement 15 directly opposite each other. A first threaded sleeve 17 is installed at the other end of the main reinforcement. The diameter of the first threaded sleeve 17 is larger than the positioning hole of the main reinforcement on the alignment hanger 14. This allows the main reinforcement to be supported on the alignment hanger 14. The other end is supported by the main reinforcement positioning rod 1602.

[0064] S7. Lift the hook 9 upwards to hoist the steel mesh 6 inside the bracket 8 in sequence and complete the separation of the steel mesh 6 to form the mesh intermediate body 25;

[0065] S8. Continue to lift the hook 9 to fix the lifting device 11 and the upper crossbeams 703 on both sides, and then disconnect the hook 9 from the lifting device 11.

[0066] S9. Install the alignment bracket 14 on the lower side of the hook 9, and fix the alignment bracket 14 on the lower side of the bracket 8. Pass the main rib 15 through the positioning sleeve 24 on the alignment bracket 14 into the mesh intermediate body 25, and fix the upper part of the mesh intermediate body 25 through the first threaded sleeve 17.

[0067] The top posture of the main reinforcement bars was checked using a total station to ensure that the outer contours of all steel mesh panels were on the same plane. Then, a total of 8 main reinforcement bars at the four corners, the middle of the long side, and the middle of the short plate were welded firmly to the steel mesh panel. Then, four long Φ20 round steel bars (2 short and 2 long) were used to clamp the main reinforcement bars 15 in the middle in four directions and tied to the bottom layer of stirrups with tie wire. The same method was used for the inner main reinforcement bars and the steel mesh panel to form a semi-stable steel reinforcement component with the steel mesh panel and the main reinforcement bars.

[0068] S10. Limit the mesh intermediate body 25 by the vertical supports 1601 inside the two second operating platforms 16, adjust the height of the mesh intermediate body 25, and support the bottom of the mesh intermediate body 25 on the positioning rod 1602.

[0069] S11. After the intermediate body 25 of the mesh and the main reinforcement 15 are stable, the intermediate body 25 of the mesh and the main reinforcement 15 are fixed by binding and welding to form the steel reinforcement component 26; the main reinforcement that is welded to the main reinforcement of the steel mesh is connected to the main reinforcement of the previous segment through the extrusion cone sleeve 20, and other main reinforcements are connected to the corresponding main reinforcements through the second threaded sleeve 21. When connecting the second threaded sleeve 21, the main reinforcement does not need long and short wires, and the main reinforcement of the flexible connection can be directly screwed into the sleeve.

[0070] S12. Hoist the steel reinforcement component 26 to the upper part of the pier column 18 and fix it with the pre-embedded reinforcement 19 for subsequent pouring process; hoist the steel reinforcement component 26 together with the alignment hanger 14 onto the pier column. The alignment hanger 14 is equipped with a support rod at the bottom, which is supported on the already poured concrete surface. The other main reinforcement bars 15 rest on the main reinforcement bars connected to the previous segment. A total station prism is set on the eight main reinforcement bars welded to the steel mesh 6 to detect the posture of the component. Then, the component is adjusted by pushing it with a hydraulic cylinder, thereby adjusting the posture of the steel reinforcement component; close the formwork for pouring and curing. Before pouring, the second threaded sleeve at the end of the main reinforcement bar needs to be fitted with a protective sleeve to prevent it from being contaminated by concrete and affecting its use.

[0071] S13. Repeat S2 to S12 until all steel reinforcement components 26 are completed.

[0072] Based on the planar layout of the main reinforcement bars 18 and the height of the main reinforcement bars 15, a jig for assembling the steel reinforcement component 26 is designed. This jig is used for positioning the multi-layer steel mesh 6, adjusting and fixing the spacing between the mesh pieces, and supporting and positioning the component during hoisting. After the steel mesh is fabricated inside the mesh jig, it is transported to the component jig (first operating platform 7), and the spacing of the steel mesh 6 is adjusted. Then, the main reinforcement bars 15 are inserted. After approximately 20% of the main reinforcement bars at the fixed position are firmly welded to the multi-layer mesh, the steel reinforcement component 26 is hoisted onto the tower as a whole. After measuring and adjusting the posture of the mesh and the main reinforcement bars, the main reinforcement bars are then connected. The welded main reinforcement bars are connected using extrusion tapered sleeves 20, and other main reinforcement bars are connected using second threaded sleeves 21.

[0073] This technology eliminates the need for matching and installation of the main reinforcing bars in the fabrication of steel reinforcement components. The main reinforcing bar connections primarily utilize traditional threaded sleeve connections, resulting in low costs. The steel mesh is fabricated within a jig, and after inserting the main reinforcing bars for shaping, the spacing of the steel mesh is widened to form a steel reinforcement component primarily composed of steel mesh.

[0074] In the preferred embodiment, in step S3, by adjusting the positions of the first baffles 801 and the second baffles 802 on both sides of the bracket 8, the spacing between the two first baffles 801 is ensured to match the length of the steel mesh 6, and the two sides of the steel mesh 6 are precisely fitted against the inner sides of the first baffles 801. The bracket 8 is adjustable, which facilitates initial support of weight and subsequent easy removal.

[0075] In the preferred embodiment, in step S5, after the bracket 8 and hook 9 are separated, the bolts 804 on the second baffle 802 and the base plate 803 are removed, the locking pins on the second baffle 802 and the base plate 803 are released, and the second baffle 802 is adjusted from a vertical state to a horizontal state using the bolts 804, completely releasing the constraint on the steel mesh 6. This structure makes the subsequent separation and lifting of the steel mesh 6 more convenient and avoids interference after the bracket 8 is completely removed.

[0076] In the preferred embodiment, in step S5, a flexible cable 12 of appropriate length is pre-cut according to the height of the reinforcing steel component 26. Then, a fixing component 22 is installed on the flexible cable 12. The hook 13 is connected and fixed to the flexible cable 12 via the fixing component 22. Multiple fixing components 22 are evenly distributed on the flexible cable 12, and the distance between two fixing components 22 is the spacing between two adjacent reinforcing steel mesh pieces 6. This structure facilitates accurate installation of the hook 13 at different positions, allows for convenient adjustment, and enables the distance between different fixing components 22 to be changed according to design requirements, resulting in better performance.

[0077] In the preferred embodiment, before step S9, the bracket 8 is removed from the support plate 707, and the two alignment hangers 14 located on the upper and lower sides of the mesh middle body 25 are placed facing each other, with the lower alignment hanger 14 placed on the support plate 707. This structure facilitates the insertion of the main reinforcement 15, provides a larger overall construction space, and ensures construction convenience.

[0078] In the preferred embodiment, in S10, the alignment hanger 14 located on the upper side is supported and fixed by multiple legs 27, the lower part of which is fixed to the adjusting pad 1603. This structure allows the adjusting pad 1603 to stably adjust the state of the alignment hanger 14, keeping it in a relatively horizontal state, thereby ensuring good welding quality between the main rib 15 and the mesh intermediate body 25.

[0079] In the preferred embodiment, in S12, the main reinforcing bars 15 are connected to the pre-embedded reinforcing bars 19 on the pier column 18 via the second threaded sleeve 21 and the extrusion cone sleeve 20, respectively. After being fixed in place, the upper alignment hanger 14 is removed and lifted off using the hook 9, while the alignment hanger 14 on the support plate 707 is also removed. This avoids the high economic cost of using extrusion cone sleeves 20 throughout, and the fixing points are set as needed, resulting in overall stable stress and saving materials.

[0080] like Figure 19-22 In the preferred embodiment, the system includes a positioning frame, a first operating platform 7, a bracket 8, a lifting device 11, an alignment bracket 14, and a second operating platform 16. The positioning frame is used to complete the welding of the steel mesh 6. The first operating platform 7 includes two first support frames 701 arranged opposite to each other. The upper and lower sides of the first support frames 701 are respectively provided with a lower crossbeam 702 and an upper crossbeam 703. A first fixing member 704 is provided on the lower crossbeam 702, and a second fixing member 705 is slidably provided on the upper crossbeam 703. The second fixing member 705 is connected to the first fixing member 704 through a vertical beam 706. The second fixing member 705 and the vertical beam 706 are hinged. A support plate 707 is provided on the upper support of the first fixing member 704.

[0081] The bracket 8 includes a base plate 803. Two first baffles 801 are slidably provided on both sides of the base plate 803 along its length. The bottom of the first baffles 801 is connected to the base plate 803 by bolts 804. Two sliding plates 806 are slidably provided on both sides of the base plate 803 along its width. The sliding plates 806 are connected to the base plate 803 by bolts 804. A second baffle 802 is hinged to the sliding plates 806 by a shaft 805. Bolts 804 pass through the second baffle 802 and the base plate 803. The second baffle 802 and the base plate 803 can be fixed by bolts 804. The second baffle 802 can be fixed and locked in a perpendicular state to the base plate 803 by bolts 804.

[0082] The upper side of the lifting device 11 is hinged with a folding plate for connecting with the upper crossbeam 703. Multiple positioning sleeves 24 are evenly arranged on the alignment hanger 14. The diameter of the positioning sleeves 24 matches the diameter of the main rib 15. Flexible cables 12 are detachably provided on both sides of the lifting device 11. Multiple hooks 13 are evenly arranged on the flexible cables 12.

[0083] The second operating platform 16 includes two opposing second support frames 1604, the bottoms of which are connected by a pad 1605. Multiple adjusting pads 1603 are provided on the pad 1605. A vertical support 1601 is fixed to the pad 1605, and the pad 1605 also has adjusting pads 1603 for fixing the support legs 27. This structure allows for large-scale, rapid production of the steel mesh 6 in the factory. After production, it is transported to the project construction site for the fabrication of the steel reinforcement components 26. Due to the large size and heavy weight of the steel mesh 6, the combination of factory and construction site operations ensures high overall construction efficiency.

[0084] In the preferred embodiment, the hook 13 is connected to the flexible cable 12 via a fixing component 22. The fixing component 22 includes two parallel connecting blocks 2201. A through groove 2202 is provided through the middle of the connecting block 2201. A first notch 2203 is provided on one side of the connecting block 2201. Two through holes 2204 are provided through the first notch 2203. A limiting groove 2205 is provided on one side of the through groove 2202. The flexible cable 12 passes through the through groove 2202, and the hook 13 is located in the limiting groove 2205. The U-shaped rod 2210 fixes the hook 13 and the flexible cable 12 with a nut 2209. This structure allows the hook 13 to be stably installed on the flexible cable 12, while maintaining overall stability under force. The hook 13 has high installation accuracy, which facilitates more uniform placement of the reinforcing mesh 6 and improves the overall performance.

[0085] In the preferred embodiment, the limiting groove 2205 is provided with a taper 2206, and the small ends of the two limiting grooves 2205 are arranged opposite each other. A locking element 23 is also provided between the two connecting blocks 2201. The locking element 23 includes a sealing plate 2301, and a second notch 2303 is provided on the sealing plate 2301. A constraint sleeve 2302 is provided on one side of the second notch 2303. The inner diameter of the constraint sleeve 2302 matches the outer diameter of the flexible cable 12. The constraint sleeve 2302 passes through the limiting groove 2205. An ear plate 2207 is provided on the outer side of the connecting block 2201. The two ear plates 2207 on the same side are connected by a locking pin 2208 and a nut 2209. The locking element 23 is made of rubber. When the locking pin 2208 locks the two connecting blocks 2201, the sealing plate 2301 is squeezed, which will make the constraint sleeve 2302 fit more tightly on the flexible cable 12. At the same time, since the limiting groove 2205 is provided with a taper 2206, the two connecting blocks 2201 are connected to form a taper interlocking effect. The constraint sleeve 2302 is provided with a wire mesh, which can maintain good elasticity while better fitting on the flexible cable 12, thereby providing a stable holding force for the hook 13, ensuring that the hook 13 has a strong load capacity, and ensuring the safe and stable hoisting of the steel mesh 6.

[0086] The above embodiments are merely preferred technical solutions of the present invention and should not be considered as limitations on the present invention. The scope of protection of the present invention should be limited to the technical solutions described in the claims, including equivalent substitutions of the technical features described in the claims. That is, equivalent substitutions and improvements within this scope are also within the scope of protection of the present invention.

Claims

1. A construction device for reinforcing steel components of pier columns, characterized in that: The system includes a positioning frame, a first operating platform (7), a bracket (8), a lifting device (11), an alignment bracket (14), and a second operating platform (16). The positioning frame is used to complete the welding of the steel mesh (6). The first operating platform (7) includes two first support frames (701) arranged opposite to each other. The upper and lower sides of the first support frame (701) are respectively provided with a lower crossbeam (702) and an upper crossbeam (703). A first fixing member (704) is provided on the lower crossbeam (702), and a second fixing member (705) is slidably provided on the upper crossbeam (703). The second fixing member (705) is connected to the first fixing member (704) through a vertical beam (706). The second fixing member (705) and the vertical beam (706) are hinged. A support plate (707) is provided on the upper side of the first fixing member (704). The bracket (8) includes a base plate (803), and two first baffles (801) are slidably provided on both sides of the base plate (803) along the length direction. The bottom of the first baffles (801) is connected to the base plate (803) by bolts (804). Two sliding plates (806) are slidably provided on both sides of the base plate (803) along the width direction. The sliding plates (806) are connected to the base plate (803) by bolts (804). The sliding plates (806) are hinged to a second baffle (802) by a shaft (805). The bolts (804) pass through the second baffle (802) and the base plate (803). The upper side of the lifting device (11) is hinged with a folding plate for connecting with the upper crossbeam (703). Multiple positioning sleeves (24) are evenly arranged on the aligned hanger (14). The diameter of the positioning sleeves (24) matches the diameter of the main reinforcement (15). Flexible cables (12) are detachably provided on both sides of the lifting device (11). Multiple hooks (13) are evenly arranged on the flexible cables (12). The second operating platform (16) includes two second support frames (1604) arranged opposite to each other. The bottoms of the two second support frames (1604) are connected by a pad (1605). Multiple adjusting pads (1603) are provided on the pad (1605). The vertical support (1601) is fixed on the pad (1605). The pad (1605) is also provided with adjusting pads (1603) for fixing the support leg (27). It also includes a positioning rod (1602). The positioning rod (1602) is staggered and arranged in order of height. The positioning rod (1602) and the main rib (15) are directly opposite each other. The construction method for the installation of steel reinforcement components for pier columns includes the following steps: S1. Design the shape and size of the steel mesh (6) according to the needs of the pier (18); S2. The steel mesh (6) is welded on the positioning frame by the first stirrup (1), the second stirrup (2), the first hook bar (3), the second hook bar (4) and the third stirrup (5); S3. Place the completed steel mesh (6) into the bracket (8) respectively, and move it to the first operating platform (7) when the design capacity is reached; S4. By adjusting the vertical beams (706) on the two first support frames (701), keep the two vertical beams (706) in the open-up state, and then use the hook (9) and cable (10) to hoist the bracket (8) and the steel mesh (6) as a whole into the upper support plate (707) of the first fixing member (704); S5. Disconnect the connection between the hook (9) and the bracket (8), and then install the lifting device (11) at the bottom of the hook (9) and install flexible cables (12) on both sides of the lifting device (11). S6. Move the lifting device (11) to the uppermost steel mesh (6), and then hang the steel mesh (6) of each layer on the corresponding hook (13) on the flexible cable (12); S7. Lift the hook (9) upwards to lift the steel mesh (6) in the bracket (8) in sequence and complete the separation of the steel mesh (6) to form the mesh intermediate body (25). S8. Continue to lift the hook (9) to fix the lifting device (11) and the upper crossbeams (703) on both sides, and release the connection between the hook (9) and the lifting device (11); S9. Install the alignment hanger (14) on the lower side of the hook (9), and fix the alignment hanger (14) on the lower side of the bracket (8). Pass the main reinforcement (15) through the positioning sleeve (24) on the alignment hanger (14) into the mesh intermediate body (25), and fix the upper part of the mesh intermediate body (25) through the first threaded sleeve (17). S10. Limit the mesh intermediate body (25) by the vertical supports (1601) inside the two second operating platforms (16), adjust the height of the mesh intermediate body (25), and support the bottom of the mesh intermediate body (25) on the positioning rod (1602). S11. After the intermediate mesh body (25) and the main reinforcement (15) are stable, the intermediate mesh body (25) and the main reinforcement (15) are fixed by binding and welding to form the steel reinforcement component (26). S12. Hoist the steel reinforcement component (26) to the upper part of the pier column (18) and fix it with the pre-embedded reinforcement (19) for subsequent pouring process; S13. Repeat S2~S12 until all steel reinforcement components are completed (26).

2. The construction device for the pier column reinforcement component according to claim 1 is characterized in that: in S3, by adjusting the position of the first baffle (801) and the second baffle (802) on both sides of the bracket (8), the spacing between the two first baffles (801) and the length of the steel mesh (6) are matched, and the two sides of the steel mesh (6) are just in contact with the inner side of the first baffle (801).

3. The construction device for the pier column reinforcement component according to claim 1 is characterized in that: in S5, after the bracket (8) and the hook (9) are separated, the bolts (804) on the second baffle (802) and the bottom plate (803) are removed, the locking of the second baffle (802) and the bottom plate (803) is released, and the second baffle (802) is adjusted from the vertical state to the horizontal state by the bolts (804), and the constraint on the steel mesh (6) is completely released.

4. The construction device for a pier column steel reinforcement component according to claim 1 is characterized in that: in S5, a flexible cable (12) of appropriate length is cut in advance according to the height of the steel reinforcement component (26), and then a fixing component (22) is installed on the flexible cable (12). The hook (13) is connected and fixed through the fixing component (22) and the flexible cable (12). Multiple fixing components (22) are evenly arranged on the flexible cable (12), and the distance between two fixing components (22) is the spacing between two adjacent steel mesh pieces (6).

5. The construction device for a pier column reinforcement component according to claim 1, characterized in that: Before S9, remove the bracket (8) from the tray (707), place the two alignment hangers (14) on the upper and lower sides of the mesh middle body (25) facing each other, and place the lower alignment hanger (14) on the tray (707).

6. The construction device for the steel reinforcement component of the pier column according to claim 1, characterized in that: In S10, the alignment hanger (14) located on the upper side is supported and fixed by multiple legs (27), and the lower part of the legs (27) is fixed on the adjusting pad (1603).

7. The construction device for the steel reinforcement component of a pier column according to claim 1, characterized in that: In S12, the main reinforcement (15) is connected to the pre-embedded reinforcement (19) on the pier (18) through the second threaded sleeve (21) and the extrusion cone sleeve (20). After it is fixed in place, the upper alignment hanger (14) is removed and lifted and removed using the hook (9). At the same time, the alignment hanger (14) on the pallet (707) is removed.

8. The construction device for the steel reinforcement components of a pier column according to claim 1, characterized in that: The hook (13) is connected to the flexible cable (12) by a fixing component (22). The fixing component (22) includes two parallel connecting blocks (2201). A through groove (2202) is provided in the middle of the connecting block (2201). A first notch (2203) is provided on one side of the connecting block (2201). Two through holes (2204) are provided in the first notch (2203). A limiting groove (2205) is provided on one side of the through groove (2202). The flexible cable (12) is inserted in the through groove (2202). The hook (13) is located in the limiting groove (2205). The U-shaped rod (2210) fixes the hook (13) and the flexible cable (12) by a nut (2209).

9. The construction device for a pier column reinforcement component according to claim 8, characterized in that: The limiting groove (2205) is provided with a taper (2206). The small ends of the two limiting grooves (2205) are arranged opposite each other. A locking element (23) is also provided between the two connecting blocks (2201). The locking element (23) includes a sealing plate (2301). A second notch (2303) is provided on the sealing plate (2301). A constraint sleeve (2302) is provided on one side of the second notch (2303). The inner diameter of the constraint sleeve (2302) matches the outer diameter of the flexible cable (12). The constraint sleeve (2302) passes through the limiting groove (2205). An ear plate (2207) is provided on the outer side of the connecting block (2201). The two ear plates (2207) on the same side are connected by a locking pin (2208) and a nut (2209).