A bridge reconstruction construction method integrating BIM technology and algorithm model

By integrating BIM technology and algorithm model construction methods, the problem of difficult evaluation of the load and stress distribution relationship during bridge reconstruction is solved, accurate location selection of strengthened structures is achieved, the reconstruction plan is optimized, costs are saved and the safety and stress of the bridge are improved. Sustainability.

CN117473620BActive Publication Date: 2024-10-18QINGDAO ELINK GRP INC CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202311479553.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-08
Publication Date
2024-10-18
Estimated Expiration
2043-11-08

AI Technical Summary

Technical Problem

Existing bridge reconstruction plans lack the lowest-cost reconstruction plan while ensuring load requirements, and it is difficult to effectively evaluate the distance relationship, load balance relationship, and stress distribution relationship between different reconstruction locations, making it difficult to control the cost and effect of the reconstruction.

Method used

Using a construction method that integrates BIM technology and algorithm models, we obtain basic construction information of the bridge through measurement and detection, design standard stress distribution, conduct finite element analysis, calculate stress differences, iteratively select the location of the strengthened structure, simulate the strengthened structure, and optimize the stress distribution. , choose the most economical renovation and enhancement plan.

Benefits of technology

It improves the accuracy and reliability of the reconstruction plan, saves reconstruction costs, extends the service life of the bridge, improves structural safety, reduces resource waste, complies with the principle of sustainable development, and improves the work efficiency of engineers.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The present invention provides a bridge reconstruction construction method that integrates BIM technology and algorithm models, belongs to the field of building technology, and solves the problem that it is difficult to adopt the reconstruction plan with the lowest cost while ensuring the load requirements. The present invention uses BIM to model, analyze and simulate multiple schemes for the bridge to be reconstructed. The gap between the actual load of the bridge to be reconstructed and the traffic load requirement is calculated, and the reinforcement data required for each part of the bridge to be reconstructed is calculated based on the gap. Further select the combination of locations with larger damage for the first reinforcement, and predict the overall reconstruction cost and effect based on multiple simulated reconstructions of different combinations, so as to adopt the most appropriate reconstruction plan according to the needs. The present invention can improve the bearing capacity of the bridge in a targeted manner by first strengthening the structure at several weak locations, and further optimize the comprehensive reconstruction plan for the entire bridge. This can save a lot of reconstruction costs, especially for large-span bridges.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of building technology and relates to bridge maintenance, in particular to a bridge reconstruction construction method integrating BIM technology and algorithm model. Background Art

[0002] Building Information Modeling (BIM) is to establish a building model based on the relevant information data of the construction project, and simulate the real information of the building through digital information simulation. It has eight characteristics: information completeness, information relevance, information consistency, visualization, coordination, simulation, optimization and mappability.

[0003] BIM can be used to analyze the strength values ​​of various parts of a bridge. This is an important application of BIM in the engineering field. BIM models can contain detailed building structure information, including the geometry of the bridge, material properties, construction details, etc., which can be used for strength analysis and structural analysis. BIM can also perform simulation design and simulation analysis on bridges.

[0004] After a period of use, bridges may develop various damages and wear, such as concrete cracks, corrosion, fatigue, steel structure corrosion, etc. The renovation process usually involves repairing these damages to restore the structural integrity and safety of the bridge. This may include concrete repair, steel structure corrosion protection, bearing replacement and other work. Some bridges also need to adapt to greater traffic loads, such as heavier vehicles or higher traffic density. Bridge renovation can include increasing the load-bearing capacity of the bridge, which may require strengthening the structure, adding supports, replacing beams, strengthening the bottom of beams, etc.

[0005] To evaluate the safety and performance of a bridge, it is necessary to calculate and analyze the various stress values ​​of the bridge to ensure that they are within the allowable range. If the stress value exceeds the bearing capacity of the material, it may cause damage or destruction to the structure, so measures must be taken to strengthen or redesign the bridge. The existing bridge reconstruction scheme is only to simply calculate the structural features that need to be strengthened in each part of the bridge, but the bridge reconstruction is often an overall multi-point position reconstruction, and the distance relationship, load balance relationship, and stress distribution relationship between different reconstruction positions. The reconstruction scheme has many combinations and specific parameter adjustment methods. Because the reconstruction combination method and reconstruction order change within a certain range, the specific reconstruction scheme adopted affects the overall reconstruction cost and effect. The existing bridge reconstruction scheme lacks research in this area, making it difficult to adopt the reconstruction scheme with the lowest cost while ensuring the load requirements. Summary of the invention

[0006] The purpose of the present invention is to address the above-mentioned problems in the existing technology and to propose a bridge reconstruction construction method integrating BIM technology and algorithm model.

[0007] The purpose of the present invention can be achieved by the following technical solutions: A bridge reconstruction construction method integrating BIM technology and algorithm model, comprising the following steps:

[0008] S1. Obtain the basic construction information parameters of the reconstructed bridge through measurement and testing, and obtain the traffic load requirements of the reconstructed bridge. According to the traffic load requirements, the type of reconstructed bridge and the total span of the reconstructed bridge, design the standard stress distribution of the bridge;

[0009] S2. Input the above basic construction information parameters to establish a BIM reconstruction bridge model, perform finite element analysis and load analysis on the reconstruction bridge through BIM, obtain the actual stress distribution of the reconstruction bridge through finite element analysis, compare the actual stress value of each part in the actual stress distribution with the standard stress value of each part in the standard stress distribution, and obtain the stress difference at each position of the reconstruction bridge along the total span;

[0010] S3, dividing the reconstructed bridge into several unit lengths along the total span, selecting at least one position with the maximum stress difference in each unit length in turn, and calculating the strengthening structure parameters corresponding to each position with the maximum stress difference through BIM;

[0011] S4. Select several maximum stress difference positions in the BIM-reconstructed bridge model, and simulate adding the reinforcement structure calculated by BIM one by one. After further simulation and reinforcement at several maximum stress difference positions, calculate the remaining stress distribution; after N iterations, select different combinations of maximum stress difference positions for reinforcement simulation, and calculate N different remaining stress distributions accordingly;

[0012] S5. In N iterative operations, a group of stress distributions with the smallest overall change from the actual stress distribution is selected, and a combination of several positions with the largest stress difference values ​​corresponding to the smallest group of stress distributions is selected as the most economical transformation and strengthening plan.

[0013] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, in step S1, the basic construction information includes measuring the structural parameters of the reconstructed bridge, and the basic construction information also includes detecting the material parameters and weathering erosion parameters of the bridge.

[0014] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, in step S1, the traffic load requirements include at least the highest standards for traffic type, load level, axle weight, wheelbase, and number of lanes.

[0015] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, in step S2, finite element analysis includes establishing a finite element model, solving analysis and analysis results. The establishment of the finite element model specifically converts the geometric shape and structural details of the reconstructed bridge into a finite element model; the solving analysis specifically calculates the stress, strain and displacement parameters on each finite element by solving the finite element model.

[0016] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, in step S3, the magnitude of the stress difference is divided according to levels, and the maximum level of stress difference is the maximum difference range.

[0017] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, in step S4, the number of positions with the maximum stress difference is selected to range from 3 positions to 1 / 3 of the total stress difference position.

[0018] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, in step S4, the reinforcement structure is specifically reinforcement ribs, piers and / or suspension cables; the reinforcement structure parameters are the material, area, length, thickness, shape of the reinforcement ribs, the material, shape, diameter of the piers, and the material, length, diameter, quantity, and density of the suspension cables.

[0019] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, in step S2, the actual stress values ​​include bending stress, shear stress, compressive stress, tensile stress, shear deformation, and extrusion stress.

[0020] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, in step S2, finite element analysis divides the BIM reconstruction bridge model into a finite number of units, performs a maximum load application simulation in each unit, and records the unit range affected by the maximum load, calculates the maximum stress of each unit through BIM, and then combines the maximum stress of each unit through finite element analysis to form the actual stress distribution of the reconstruction bridge;

[0021] In step S3, the load difference between the traffic load and the maximum load of each unit is calculated, and BIM calculates the cross-sectional area of ​​the reinforced structure according to the ratio of the load difference to the stress difference, and then takes the unit range affected by the maximum load as the plane area of ​​the reinforced structure, and obtains the simulated entity of the reinforced structure through the cross-sectional area and the plane area;

[0022] In step S4, a reinforced structure simulation entity is added at the corresponding maximum stress difference position to form a simulated reinforced modified structure.

[0023] Since several reinforced parts are simulated on the bridge, these reinforced parts have a strength supporting effect on a certain range around them, thereby changing the stress distribution of the entire bridge. Reinforcement schemes at different locations and with different numbers have different effects on the initial transformation of the entire bridge.

[0024] In the above-mentioned bridge reconstruction construction method integrating BIM technology and algorithm model, the N-times iterative operation includes the following steps:

[0025] First, any three positions with the maximum stress difference are determined as the starting points of the iteration, and enhanced simulation is performed on these three positions with the maximum stress difference until all the positions with the maximum stress difference complete the enhanced simulation with a combination of three quantities; then, enhanced simulation is performed on any four positions with the maximum stress difference until all the positions with the maximum stress difference complete the enhanced simulation with a combination of four quantities; thus, the number of combinations reaches a natural number that is 1 / 3 of the number of total stress difference positions, and a total of N enhanced simulations are performed, corresponding to N stress distributions.

[0026] Iterative operations are used to perform operations on all combinations, thereby avoiding omissions or duplications.

[0027] The working principle of this construction method is: use BIM to model, analyze and simulate multiple schemes of bridge reconstruction. Calculate the gap between the actual load of the bridge to be reconstructed and the traffic load requirements, and calculate the reinforcement data required for each part of the bridge to be reconstructed based on the gap. Further select the combination of the locations with the largest damage for the first reinforcement, and predict the overall reconstruction cost and effect based on multiple simulation reconstructions of different combinations, so as to adopt the most appropriate reconstruction scheme according to the needs.

[0028] Compared with the existing technology, the bridge reconstruction construction method integrating BIM technology and algorithm model has the following beneficial effects:

[0029] 1. Improved accuracy and reliability: Through BIM technology and algorithm model analysis, the actual stress distribution and structural performance of the bridge can be simulated more accurately, rather than relying solely on traditional empirical design methods. This improves the accuracy and reliability of the renovation plan.

[0030] 2. Cost savings: By strengthening the structure at several weak locations first, the bridge's load-bearing capacity can be improved in a targeted manner, and the overall reconstruction plan for the entire bridge can be further optimized. This can save a lot of reconstruction costs, especially for long-span bridges.

[0031] 3. Extend lifespan: By optimizing and strengthening the structural solution, the service life of the bridge can be extended, and the frequency and cost of maintenance and repair can be reduced. This helps to improve the sustainability of the bridge.

[0032] 4. Improve safety: Strengthening weak points can significantly improve the structural safety of bridges, reduce the risk of potential structural damage or collapse, and thus protect the safety of traffic and pedestrians.

[0033] 5. Sustainability and environmental protection: By reducing unnecessary transformation, it reduces resource waste, helps reduce environmental impact, and complies with the principle of sustainable development.

[0034] 6. Improve efficiency: The use of BIM technology and algorithm models can automate many analysis and calculation processes, improve the work efficiency of engineers and designers, and shorten project completion time.

[0035] 7. Personalized design: This method allows the renovation plan to be customized according to different bridge types, total spans and stress distribution conditions to meet the needs of specific bridges and improve the degree of personalization of the renovation. DETAILED DESCRIPTION

[0036] The following are specific embodiments of the present invention, which further describe the technical solutions of the present invention, but the present invention is not limited to these embodiments.

[0037] The bridge reconstruction construction method integrating BIM technology and algorithm model includes the following steps:

[0038] S1. Obtain the basic construction information parameters of the reconstructed bridge through measurement and testing, and obtain the traffic load requirements of the reconstructed bridge. According to the traffic load requirements, the type of reconstructed bridge and the total span of the reconstructed bridge, design the standard stress distribution of the bridge;

[0039] Different types of bridge structures respond differently to traffic loads. Suspension bridges, beam bridges, arch bridges and other structures have different characteristics when facing loads, so they need to be considered according to the type of bridge. The larger the total span of the bridge, the greater the loads such as bending moment and shear force on its structure. Therefore, the total span is an important design parameter that directly affects the bridge's ability to bear traffic loads. In summary, under the premise of known traffic load requirements, the type of bridge to be renovated and the total span of the renovated bridge, the standard stress parameters of each part of the corresponding type of bridge can be obtained through the existing calculation method as the target parameters for the renovated bridge.

[0040] S2. Input the above basic construction information parameters to establish a BIM reconstruction bridge model, perform finite element analysis and load analysis on the reconstruction bridge through BIM, obtain the actual stress distribution of the reconstruction bridge through finite element analysis, compare the actual stress value of each part in the actual stress distribution with the standard stress value of each part in the standard stress distribution, and obtain the stress difference at each position of the reconstruction bridge along the total span;

[0041] BIM models can be integrated with finite element analysis software, which can perform detailed strength and stress analysis on various parts of the bridge. This includes the calculation of stress, deformation, displacement and other parameters of the bridge's beams, piers, arches, suspension cables and other components. The results of the finite element analysis include information such as stress distribution, displacement, deflection, etc. of the bridge under different load conditions. These results can be used to evaluate the structural performance of the bridge, determine whether it meets the design requirements, and optimize the design scheme. BIM can be used to simulate the impact of different types of loads (static and dynamic) on the bridge, including vehicle loads, wind loads, snow loads, earthquake loads, etc. BIM models and BIM data analysis are existing functions of existing BIM software, so their specific modeling and analysis processes are not described in detail.

[0042] S3, dividing the reconstructed bridge into several unit lengths along the total span, selecting at least one position with the maximum stress difference in each unit length in turn, and calculating the strengthening structure parameters corresponding to each position with the maximum stress difference through BIM;

[0043] S4. Select several maximum stress difference positions in the BIM-reconstructed bridge model, and simulate adding the reinforcement structure calculated by BIM one by one. After further simulation and reinforcement at several maximum stress difference positions, calculate the remaining stress distribution; after N iterations, select different combinations of maximum stress difference positions for reinforcement simulation, and calculate N different remaining stress distributions accordingly;

[0044] By strengthening weak locations, the overall structural strength and rigidity of the bridge can be improved, and its load-bearing capacity and ability to resist deformation can be increased. This helps improve the structural safety of the bridge and reduce the risk of structural damage or collapse. The load of the bridge will be transmitted to different parts through the structure. When a weak location is strengthened, this location can bear a larger load. This will reduce the load of other locations that originally carried a larger load to a certain extent, thereby improving the load distribution of the entire bridge structure.

[0045] S5. In N iterative operations, a group of stress distributions with the smallest overall change from the actual stress distribution is selected, and a combination of several positions with the largest stress difference values ​​corresponding to the smallest group of stress distributions is selected as the most economical transformation and strengthening plan.

[0046] The most economical renovation and reinforcement plan is used as the minimum renovation limit for bridge renovation, that is, the most economical renovation and reinforcement plan is the minimum standard to ensure that the bridge meets the traffic load requirements after renovation.

[0047] In step S1, the basic construction information includes measuring the structural parameters of the renovated bridge, and the basic construction information also includes detecting the material parameters and weathering erosion parameters of the bridge. The structural parameters of the bridge specifically refer to the span of the bridge, the height of the piers, the width of the main beam, the overall length, etc. These parameters are very important for determining the bending, shearing, and flexural properties of the bridge structure. The material parameters of the bridge specifically include the strength grade of the concrete, the strength of the steel, etc. These parameters are used to determine the selection and performance requirements of the bridge material. The weathering erosion parameters specifically refer to the hardness, density, and adhesion of the bridge concrete. The above parameters and measurement and detection methods are all existing technologies, so they are not described in detail here.

[0048] In step S1, the traffic load requirements include at least the highest standards for traffic type, load level, axle weight, wheelbase, and number of lanes. The traffic load requirements are the maximum standards that the bridge can bear after it is renovated and strengthened. A major component of the traffic load is the weight of different types of vehicles, including cars, trucks, public transportation vehicles, and trains. The weight of these vehicles will be transferred to the bridge structure, exerting a load on it. Different types of vehicles produce different loads. The axle weight and wheelbase of vehicles such as trucks, cars, and public transportation vehicles will affect the distribution of the load. Trucks usually have larger axle weights, while cars may distribute the load on the front and rear axles.

[0049] In step S2, the finite element analysis includes establishing a finite element model, solving the analysis and the analysis results. The establishment of the finite element model specifically converts the geometric shape and structural details of the reconstructed bridge into a finite element model; specifically involves decomposing the bridge into finite elements, usually small three-dimensional units, such as triangular or quadrilateral elements, as well as line elements and nodes. These elements are connected by nodes to form a finite element mesh for the entire bridge. The solution analysis specifically calculates the stress, strain, and displacement parameters on each finite element by solving the finite element model. This can be done through numerical calculation techniques such as the finite element method or the finite difference method. The analysis results include stress distribution, displacement, and deflection information of the bridge under different load conditions.

[0050] In step S3, the magnitude of the stress difference is divided into grades, and the stress difference of the maximum grade is the maximum difference range. By categorizing the stress difference into a range, the coverage area of ​​the maximum stress difference position is expanded to a certain extent, so as to facilitate the selection of the reinforcement area and position.

[0051] In step S4, the number of positions with maximum stress difference values ​​is selected to range from 3 positions to 1 / 3 of the total stress difference value positions.

[0052] In step S4, the reinforcement structure is specifically reinforcement ribs, piers and / or suspension cables; the reinforcement structure parameters are the material, area, length, thickness, shape of the reinforcement ribs, the material, shape, diameter of the piers, and the material, length, diameter, quantity, and density of the suspension cables. The reinforcement ribs are used to strengthen the local structure of the bridge and the bridge body, the piers are used to strengthen the support of the local part of the bridge, and the suspension cables are used to strengthen the suspension of the local part of the bridge. In summary, the load distribution of the entire bridge structure is optimized and the bearing capacity is improved.

[0053] In step S2, the actual stress values ​​include bending stress, shear stress, compressive stress, tensile stress, shear deformation, and extrusion stress.

[0054] Bending stress: Bending stress is caused by loads (such as traffic loads) that are perpendicular to the bridge's axis. This stress causes compression and tension in the bridge's beams and beam base. The calculation of bending stress usually takes into account the cross-sectional shape of the bridge, the material properties and the load distribution.

[0055] Shear stress: Shear stress is caused by the bridge being subjected to lateral loads, such as lateral distribution of traffic loads or wind loads. This stress occurs in the cross-section of the bridge's beams and beam bottoms, resulting in a lateral stress distribution.

[0056] Compressive stress: Compressive stress is caused by compressive loads on the bridge perpendicular to its axis. This stress usually occurs in parts such as piers, pier tops and abutments where the concrete or other materials are subjected to compressive forces.

[0057] Tensile Stress: Tensile stress is caused due to tensile loads applied to the bridge perpendicular to its axis. This stress may occur in supporting beams, cables, cantilevers, etc. of the bridge where the material is subjected to tensile forces.

[0058] Shear deformation: Shear deformation is caused by the horizontal displacement of parts of the bridge structure relative to each other. This deformation usually leads to the generation of shear stress.

[0059] Extrusion stress: Extrusion stress refers to the stress distribution inside the material when it is subjected to compressive loads in a bridge.

[0060] In step S2, the finite element analysis divides the BIM reconstruction bridge model into a finite number of units, performs a maximum load application simulation in each unit, and records the unit range affected by the maximum load, calculates the maximum stress of each unit through BIM, and then combines the maximum stress of each unit through finite element analysis to form the actual stress distribution of the reconstruction bridge;

[0061] In step S3, the load difference between the traffic load and the maximum load of each unit is calculated, and BIM calculates the cross-sectional area of ​​the reinforced structure according to the ratio of the load difference to the stress difference, and then takes the unit range affected by the maximum load as the plane area of ​​the reinforced structure, and obtains the simulated entity of the reinforced structure through the cross-sectional area and the plane area;

[0062] In step S4, a reinforced structure simulation entity is added at the corresponding maximum stress difference position to form a simulated reinforced modified structure.

[0063] Since several reinforced parts are simulated on the bridge, these reinforced parts have a strength supporting effect on a certain range around them, thereby changing the stress distribution of the entire bridge. Reinforcement schemes at different locations and with different numbers have different effects on the initial transformation of the entire bridge.

[0064] The N-iteration operation includes the following steps:

[0065] First, any three positions with the maximum stress difference are determined as the starting points of the iteration, and enhanced simulation is performed on these three positions with the maximum stress difference until all the positions with the maximum stress difference complete the enhanced simulation with a combination of three quantities; then, enhanced simulation is performed on any four positions with the maximum stress difference until all the positions with the maximum stress difference complete the enhanced simulation with a combination of four quantities; thus, the number of combinations reaches a natural number that is 1 / 3 of the number of total stress difference positions, and a total of N enhanced simulations are performed, corresponding to N stress distributions.

[0066] Iterative operations are used to perform operations on all combinations, thereby avoiding omissions or duplications.

[0067] BIM is the building information model, which is used to describe computer-aided designs that are mainly three-dimensional, object-oriented, and related to architecture. BIM is a 3D model architecture with digital and standardized integrated computer information. It is a facility that digitally represents the physical characteristics and functions of buildings and covers structured data sets. With the development of BIM technology, bridge load analysis can now be assisted by bridge rated load analysis and modeling software BIM. BIM uses a simplified process to perform rated load analysis and modeling on existing and planned bridge projects, so that the final results meet the latest regulations for load resistance coefficient design, load factor design, and allowable stress design.

[0068] Finite element analysis is the process of converting a design model into a finite element model. Specifically, it uses mathematical approximation methods to simulate real physical systems, such as geometry and load conditions. By using simple and interactive elements, i.e. units, a finite number of unknown quantities can be used to approximate a real system with infinite unknown quantities. The specific steps are as follows: 1. Preprocessing is the beginning stage of the entire analysis process. Its purpose is to establish a structural finite element analysis model that conforms to the actual situation. It is generally divided into the following several operation links: (1) Analysis environment setting. After entering the environment setting interface of the finite element analysis software, specify the analysis work name and the title of the graphic display, and start a new structural analysis. (2) Define units and material types. Define the unit types (bar units, plate units, solid units, etc.) and their related parameters required in the analysis process. Specify the material model used in the analysis and the corresponding material parameters (such as elastic modulus, Poisson's ratio, density, etc. of linear elastic materials). (3) Establishing geometric models: In finite element software, the geometric models of all problems are composed of various graphic elements (referred to as primitives) such as key points, lines, surfaces, and bodies. The primitive levels are from high to low, namely, bodies, surfaces, lines, and key points. Geometric models can be established in two ways: bottom-up or top-down. (4) Meshing: Perform unit division on the geometric model to form a finite element mesh. Generally, the division of finite element meshes in finite element software is divided into three steps: defining the unit properties to be divided, specifying the density of mesh division, and executing mesh division. (5) Define boundaries and constraints: In the above finite element model, introduce the boundary conditions of the actual structure, the coupling relationship between the degrees of freedom, and some other conditions. The above are all conventional applications in the prior art.

[0069] Finite element analysis is used to calculate the maximum load that each unit can bear based on the component type, material, and size parameters of the BIM-modified bridge model. The specific steps are as follows: Define boundary conditions: Define the boundary conditions of the model, including supports, loads, constraints, etc. These conditions will affect the behavior and response of the structure. Material properties: Assign appropriate properties to the materials in the model, such as elastic modulus, Poisson's ratio, density, etc. These properties describe the mechanical properties of the material. Load application: Loads are an important part of structural analysis. Define the type, magnitude, and direction of the load. The maximum load is usually one of the key load conditions. Run the analysis: Once the model, boundary conditions, and loads are defined, run the finite element analysis software for numerical analysis. Result interpretation: After the analysis is completed, the response data of the structure including information such as the maximum load is obtained. This is an existing function of the finite element analysis software.

[0070] In the finite element analysis application of BIM, when the maximum load is applied to a unit, the load influence is gradually reduced from the unit as the center to the surrounding units until the load influence outside a certain range is negligible. The units within this range are all the units affected by the maximum load. This is an existing function of the finite element analysis software.

[0071] The BIM model can include finite element analysis software to form an integrated bridge data analysis. BIM bridge data analysis specifically includes inputting building dimensions, etc., and calculating the stress values ​​of the building unit positions obtained through existing mechanical formulas. For example, the stress formula: σ=P / A. P is the load; A. is the original cross-sectional area of ​​the specimen. Load refers to the external force applied to an object, which can be gravity, pressure, tension, shear, etc. Stress is the internal stress generated by an object after being subjected to a load, which can be tensile stress, compressive stress, shear stress, etc. The above are all conventional applications in the prior art.

[0072] The working principle of this construction method is: use BIM to model, analyze and simulate multiple schemes of bridge reconstruction. Calculate the gap between the actual load of the bridge to be reconstructed and the traffic load requirements, and calculate the reinforcement data required for each part of the bridge to be reconstructed based on the gap. Further select the combination of the locations with the largest damage for the first reinforcement, and predict the overall reconstruction cost and effect based on multiple simulation reconstructions of different combinations, so as to adopt the most appropriate reconstruction scheme according to the needs.

[0073] Compared with the existing technology, the bridge reconstruction construction method integrating BIM technology and algorithm model has the following beneficial effects:

[0074] 1. Improved accuracy and reliability: Through BIM technology and algorithm model analysis, the actual stress distribution and structural performance of the bridge can be simulated more accurately, rather than relying solely on traditional empirical design methods. This improves the accuracy and reliability of the renovation plan.

[0075] 2. Cost savings: By strengthening the structure at several weak locations first, the bridge's load-bearing capacity can be improved in a targeted manner, and the overall reconstruction plan for the entire bridge can be further optimized. This can save a lot of reconstruction costs, especially for long-span bridges.

[0076] 3. Extend lifespan: By optimizing and strengthening the structural solution, the service life of the bridge can be extended, and the frequency and cost of maintenance and repair can be reduced. This helps to improve the sustainability of the bridge.

[0077] 4. Improve safety: Strengthening weak points can significantly improve the structural safety of bridges, reduce the risk of potential structural damage or collapse, and thus protect the safety of traffic and pedestrians.

[0078] 5. Sustainability and environmental protection: By reducing unnecessary transformation, it reduces resource waste, helps reduce environmental impact, and complies with the principle of sustainable development.

[0079] 6. Improve efficiency: The use of BIM technology and algorithm models can automate many analysis and calculation processes, improve the work efficiency of engineers and designers, and shorten project completion time.

[0080] 7. Personalized design: This method allows the renovation plan to be customized according to different bridge types, total spans and stress distribution conditions to meet the needs of specific bridges and improve the degree of personalization of the renovation.

[0081] The specific embodiments described herein are merely examples of the spirit of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in similar ways, but they will not deviate from the spirit of the present invention or exceed the scope defined by the appended claims.

Claims

1. A bridge reconstruction construction method integrating BIM technology and algorithm model, characterized in that: The following steps are involved: S1. Obtain the basic construction information parameters of the reconstructed bridge through measurement and testing, and obtain the traffic load requirements of the reconstructed bridge. According to the traffic load requirements, the type of reconstructed bridge and the total span of the reconstructed bridge, design the standard stress distribution of the bridge; S2. Input the above basic construction information parameters to establish a BIM reconstruction bridge model, perform finite element analysis and load analysis on the reconstruction bridge through BIM, obtain the actual stress distribution of the reconstruction bridge through finite element analysis, compare the actual stress value of each part in the actual stress distribution with the standard stress value of each part in the standard stress distribution, and obtain the stress difference at each position of the reconstruction bridge along the total span; In step S2, the finite element analysis includes establishing a finite element model, solving analysis and analysis results. The finite element model is established by converting the geometric shape and structural details of the reconstructed bridge into a finite element model. The solution analysis is specifically performed by solving the finite element model to calculate the stress, strain and displacement parameters on each finite element. In step S2, the actual stress values ​​include bending stress, shear stress, compressive stress, tensile stress, shear deformation, and extrusion stress; In step S2, the finite element analysis divides the BIM reconstruction bridge model into a finite number of units, performs a maximum load application simulation in each unit, and records the unit range affected by the maximum load, calculates the maximum stress of each unit through BIM, and then combines the maximum stress of each unit through finite element analysis to form the actual stress distribution of the reconstruction bridge; S3, dividing the reconstructed bridge into several unit lengths along the total span, selecting at least one position with the maximum stress difference in each unit length in turn, and calculating the strengthening structure parameters corresponding to each position with the maximum stress difference through BIM; In step S3, the load difference between the traffic load and the maximum load of each unit is calculated, and BIM calculates the cross-sectional area of ​​the reinforced structure according to the ratio of the load difference to the stress difference, and then takes the unit range affected by the maximum load as the plane area of ​​the reinforced structure, and obtains the simulated entity of the reinforced structure through the cross-sectional area and the plane area; S4. Select several maximum stress difference positions in the BIM-reconstructed bridge model, and simulate adding the reinforcement structure calculated by BIM one by one. After further simulation and reinforcement at several maximum stress difference positions, calculate the remaining stress distribution; after N iterations, select different combinations of maximum stress difference positions for reinforcement simulation, and calculate N different remaining stress distributions accordingly; In step S4, the number of positions with the maximum stress difference is selected to be in the range of 3 positions to 1 / 3 of the total stress difference position; In step S4, a reinforced structure simulation entity is added at the corresponding maximum stress difference position to form a simulated reinforced modified structure; The N-iteration operation includes the following steps: First, any three positions with the maximum stress difference are determined as the starting points of the iteration, and the three positions with the maximum stress difference are strengthened by simulation until all the positions with the maximum stress difference are strengthened by combinations of three numbers; then any four positions with the maximum stress difference are strengthened by simulation until all the positions with the maximum stress difference are strengthened by combinations of four numbers; thus, the number of combinations reaches a natural number that is 1 / 3 of the number of total stress difference positions, and after N times of strengthening simulation, N stress distributions are corresponding; S5. In N iterative operations, a group of stress distributions with the smallest overall change from the actual stress distribution is selected, and a combination of several positions with the largest stress difference values ​​corresponding to the smallest group of stress distributions is selected as the most economical transformation and strengthening plan.

2. The bridge reconstruction construction method integrating BIM technology and algorithm model as claimed in claim 1, characterized in that: In step S1, the basic construction information includes measuring the structural parameters of the renovated bridge, and the basic construction information also includes detecting the material parameters and weathering erosion parameters of the bridge.

3. The bridge reconstruction construction method integrating BIM technology and algorithm model as claimed in claim 1, characterized in that: In step S1, the traffic load requirements include at least the highest standards for traffic type, load level, axle weight, wheelbase, and number of lanes.

4. The bridge reconstruction construction method integrating BIM technology and algorithm model as claimed in claim 1, characterized in that: In step S3, the magnitude of the stress difference is divided into levels, and the stress difference of the maximum level is the maximum difference range.

5. The bridge reconstruction construction method integrating BIM technology and algorithm model as claimed in claim 1, characterized in that: In step S4, the reinforcement structure is specifically reinforcement ribs, piers and / or suspension cables; the reinforcement structure parameters are the material, area, length, thickness, shape of the reinforcement ribs, the material, shape, diameter of the piers, and the material, length, diameter, quantity, and density of the suspension cables.

Citation Information

Patent Citations

  • Method for actively reinforcing wide-span concrete case beam bridge web

    CN101435184A