Fire safety control system and method for electrochemical energy storage station

By constructing and fitting the detection threshold and accuracy curve during battery life, finding poles to correct the detection threshold, the problem of frequent false alarms of fire safety equipment in electrochemical energy storage stations is solved, and dynamic response to different lifespans is achieved to reduce errors Call the police.

CN117558111BActive Publication Date: 2024-12-03宁波北仑第三集装箱码头有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311499143.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-09
Publication Date
2024-12-03
Estimated Expiration
2043-11-09

AI Technical Summary

Technical Problem

The existing electrochemical energy storage station fire safety equipment cannot dynamically adjust the alarm response according to different battery life periods and thermal runaway risks, resulting in frequent false alarms and the detector accuracy deviates with time, making it difficult to set reasonable action thresholds to reduce false alarms.

Method used

By constructing a data set in the test environment, plotting and fitting the curves between detection threshold and detection accuracy, finding poles to characterize the impact relationship of the detection equipment, and calculating the correction amount to dynamically set the detection threshold to reduce false alarms.

Benefits of technology

It realizes dynamically setting the action threshold of fire safety equipment according to the battery life period, reducing the potential for false detection, taking into account detection sensitivity, and effectively reducing false operation of alarm systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117558111B_ABST
    Figure CN117558111B_ABST
Patent Text Reader

Abstract

The present invention discloses an electrochemical energy storage fire safety control system and method, and finds an index that can characterize the influence relationship between the detection threshold and detection accuracy of the detection equipment under different battery life periods, different battery operating parameters, and different detection parameters. The index is expressed by the pole in the third fitting curve, and the pole that characterizes the above influence relationship is found in the third fitting curve by drawing the V-P and P-V curves, the first and second fitting curves, and calculating the distance #imgabs0#. After finding the pole, the detection accuracy coordinate value P of the pole on the third fitting curve is used to calculate the distance between the pole and the detection accuracy. e , find P in the reverse direction on the first fitting curve or the second fitting curve e The corresponding detection threshold coordinate value V e , and by calculating the correction amount for B x‑1 The detection threshold V calculated under the same operating conditions during the life span x‑1 After correction, we get B x The detection threshold V x , reducing false alarm system operations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of fire safety control of energy storage stations, and in particular to a fire safety control system and method for an electrochemical energy storage station. Background Art

[0002] Electrochemical energy storage includes lead-acid batteries, sodium-sulfur batteries, lithium-ion batteries, etc. Electrochemical energy storage stations are comprehensive energy storage stations formed by various types of electrochemical energy storage. Battery thermal runaway is the main cause of safety accidents such as fires in electrochemical energy storage stations. After thermal runaway, flammable gases such as hydrogen and carbon monoxide will be released. Battery packs at different battery life periods have different thermal runaway risks, different degrees of danger after thermal runaway, and different concentrations of flammable gases released. Fire safety equipment should have different alarm response requirements for battery packs at different life periods with different thermal runaway risks and different degrees of danger after thermal runaway to reduce false alarms. However, there is currently no fire safety equipment on the market that can dynamically adjust the alarm accuracy according to different life periods and different thermal runaway risks.

[0003] In addition, at present, the fire prevention of electrochemical energy storage stations generally adopts the installation of combustible gas detectors, temperature and smoke detectors, etc., but in order to ensure the safety of the energy storage station, the action thresholds of these detectors are usually set relatively low, resulting in frequent false alarms of the alarm system, which brings troubles. In addition, the accuracy of fire safety equipment such as detectors will deviate over time. Therefore, how to set a reasonable action threshold for deviated equipment to reduce false alarms is also a problem that needs to be considered and solved in the field of fire safety technology of electrochemical energy storage stations. Summary of the invention

[0004] The present invention provides a fire safety control system and method for an electrochemical energy storage station. Through a set of algorithms, the action thresholds of fire safety equipment with different accuracies are dynamically set under the premise of considering the thermal runaway risks of battery packs in different life periods, thereby reducing the false detection of fire safety hazards by the electrochemical energy storage station.

[0005] To achieve this object, the present invention adopts the following technical solutions:

[0006] A fire safety control method for an electrochemical energy storage station is provided, comprising the steps of:

[0007] S1, build test environment at different battery life periods B x The test battery pack is tested at different battery operating parameters P B , different detection parameters P A The data set of detection threshold V and detection accuracy P under ;

[0008] S2, draw the test battery group in B in the same xy axis coordinate system xQuantitative P during life span B , P A A VP curve and a PV curve under certain conditions, and fitting the VP curve and the PV curve by a first fitting function to obtain a first fitting curve corresponding to the VP curve and a second fitting curve corresponding to the PV curve;

[0009] S3, calculating the distance between each first point i on the VP curve and a second point j on the PV curve having a horizontally and vertically inverted coordinate value relationship with the first point i.

[0010] S4, according to each And the corresponding P, drawn in the xy axis coordinate system curve;

[0011] S5, fitting the The data points on the curve are obtained to obtain a third fitting curve, and then each pole e in the third fitting curve is extracted, and the detection accuracy coordinate value P of each pole e on the third fitting curve is obtained. e ;

[0012] S6, finding a point with coordinate value P on the first fitting curve or the second fitting curve. e The detection threshold coordinate value V of the fitting point e , and follow V e The values ​​are arranged from small to large to form V e Sorted list of values;

[0013] S7, for the estimated B x A real battery pack during the battery life, and the battery operating parameters collected from the real battery pack are P B At B x-1 P during battery life B The detection threshold V is set for the real battery pack under the condition x-1 For quantitative analysis, the detection parameter P is simulated A , calculate each P A The detection accuracy P′ of the detection equipment under analog quantity is arranged from large to small to form a P′ value sorting list;

[0014] S8, from the V e Extract the data pairs V with the same sorting order from the value sorting list and the P′ value sorting list e -P′, then V e -P′ is the data point plotted in the same xy axis coordinate system e -P' curve and P'-V ecurve, and calculate the V e -P' curve on the first point r and the P'-V e The distance between the second point s on the curve and the first point r having the coordinates inverted horizontally and vertically

[0015] S9, calculate each The distance coordinate value L from each pole e on the third fitting curve e , and arrange the first difference absolute values ​​from small to large to form a first difference absolute value list;

[0016] S10, extracting the first difference absolute values ​​ranked top q from the first difference absolute value list, and then e The detection threshold coordinate value V corresponding to each of the poles e used to calculate each of the first difference absolute values ​​extracted is found in the value sorting list. e ;

[0017] S11, calculating the detection threshold coordinate value V found in step S10 e The absolute values ​​of the second differences between the two, then calculate the average of the absolute values ​​of the second differences, and solve for V x-1 The difference between the average value and the detection device is used as the detection device for the B x The actual battery pack during its life is P B The detection threshold V under the condition x .

[0018] Preferably, the battery operating parameter P B Including battery temperature and battery power after charging or discharging stabilizes.

[0019] Preferably, the detection parameter P A It is the concentration of combustible gas or smoke.

[0020] Preferably, the first fitting function in step S2 is a quadratic equation or a cubic equation.

[0021] Preferably, the second fitting function in step S5 is a sixth-order equation.

[0022] The present invention also provides an electrochemical energy storage station fire safety control system, comprising:

[0023] The dataset construction module is used to construct the B x The test battery pack is tested at different battery operating parameters P B , different detection parameters P AThe data set of detection threshold V and detection accuracy P under ;

[0024] The first curve drawing module is connected to the data set building module and is used to draw the test battery group in B in the xy axis coordinate system. x Quantitative P during life span B , P A A VP curve and a PV curve under the following conditions, wherein the x-axis of the VP curve is the y-axis of the PV curve, and the VP curve and the PV curve are fitted by a first fitting function to obtain a first fitting curve corresponding to the VP curve and a second fitting curve corresponding to the PV curve;

[0025] a first distance calculation module, connected to the first curve drawing module, for calculating the distance between each first point i on the VP curve and a second point j on the PV curve having a horizontal and vertical inverted coordinate relationship with the first point i;

[0026] The second curve drawing module is connected to the first distance calculation module and the data set construction module, and is used to And the corresponding P, drawn in the xy axis coordinate system curve;

[0027] P e A coordinate value acquisition module connected to the second curve drawing module is used to fit the second curve through a second fitting function. The data points on the curve are obtained to obtain a third fitting curve, and then each pole e in the third fitting curve is extracted, and the detection accuracy coordinate value P of each pole e on the third fitting curve is obtained. e ;

[0028] V e The value sorting list forms a module, connecting the P e The coordinate value acquisition module and the first curve drawing module are used to find a coordinate value P on the first fitting curve or the second fitting curve. e The detection threshold coordinate value V of the fitting point e , and follow V e The values ​​are arranged from small to large to form V e Sorted list of values;

[0029] The P′ value sorting list formation module is used to estimate the B value in the real environment. x A real battery pack during the battery life, and the battery operating parameters collected from the real battery pack are P B At B x-1 P during battery life BThe detection threshold V is set for the real battery pack under the condition x-1 For quantitative analysis, the detection parameter P is simulated A , calculate each P A The detection accuracy P′ of the detection equipment under analog quantity is arranged from large to small to form a P′ value sorting list;

[0030] The second distance calculation module is connected to the V e The value sorting list forming module and the P' value sorting list forming module are used to form the V e Extract the data pairs V with the same sorting order from the value sorting list and the P′ value sorting list e -P′, then V e -P′ is the data point plotted in the same xy axis coordinate system e -P' curve and P'-V e curve, and calculate the V e -P' curve on the first point r and the P'-V e The distance L between the second point s on the curve and the first point r having the coordinates inverted horizontally and vertically s r ;

[0031] The first difference absolute value calculation module is connected to the second distance module and is used to calculate each L s r The distance coordinate value L from each pole e on the third fitting curve e , and arrange the first difference absolute values ​​from small to large to form a first difference absolute value list;

[0032] V e A value finding module is connected to the first difference absolute value calculation module and the V e A value sorting list forming module is used to extract the first difference absolute values ​​ranked first from the first difference absolute value list, and then in the V e The detection threshold coordinate value V corresponding to each of the poles e used to calculate each of the first difference absolute values ​​extracted is found in the value sorting list. e ;

[0033] The second difference absolute value calculation module is connected to the V e A value search module is used to calculate the coordinate value V of each detection threshold value found e The absolute value of the second difference between the two pairs;

[0034] V xA detection threshold calculation module, connected to the second difference absolute value calculation module, is used to calculate the average value of each second difference absolute value and solve V x-1 The difference between the average value and the detection device is used as the detection device for the B x The actual battery pack during its life is P B The detection threshold V under the condition x .

[0035] Through a large amount of experimental data, the present invention finds an index that can characterize the influence relationship between the detection threshold and detection accuracy of the detection device under different battery life periods, different battery operating parameters, and different detection parameters. The index is expressed by the extreme points in the third fitting curve, and the VP curve and PV curve, the first fitting curve and the second fitting curve of the test battery group under different working conditions during different battery life periods are drawn, and the distance is calculated. The pole that represents the above-mentioned influence relationship is found in the third fitting curve. After the pole is found, the detection accuracy coordinate value P of the pole on the third fitting curve is used. e , find P in the reverse direction on the first fitting curve or the second fitting curve e The corresponding detection threshold coordinate value V e , and calculate the average value of the absolute value of the second difference, and use the average value as the correction amount to correct B x-1 The detection threshold V calculated under the same operating conditions during the life span x-1 After correction, we get B x The detection threshold V x . With V x It is the basis for deciding whether to adopt fire-fighting measures and can effectively reduce false alarm system operations while taking into account detection sensitivity. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0037] Figure 1 It is a diagram of the implementation steps of the fire safety control method of the electrochemical energy storage station provided by one embodiment of the present invention;

[0038] Figure 2 It is a schematic diagram of the VP curve, the PV curve, the first fitting curve corresponding to the VP curve, and the second fitting curve corresponding to the PV curve drawn in the same xy axis coordinate system;

[0039] Figure 3 yes Curves and A schematic diagram of a third fitting curve corresponding to the curve in an xy axis coordinate system;

[0040] Figure 4 It is a structural schematic diagram of a fire safety control system for an electrochemical energy storage station provided in one embodiment of the present invention. DETAILED DESCRIPTION

[0041] The technical solution of the present invention is further described below with reference to the accompanying drawings and through specific implementation methods.

[0042] Among them, the drawings are only used for illustrative explanations, and they only represent schematic diagrams rather than actual pictures, and should not be understood as limitations on the present invention. In order to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of actual products. For those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.

[0043] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "inside", "outside", etc. appear to indicate the orientation or position relationship, it is based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the terms describing the position relationship in the drawings are only used for illustrative purposes and cannot be understood as a limitation on the present invention. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0044] In the description of the present invention, unless otherwise clearly specified and limited, if the term "connection" or the like appears to indicate the connection relationship between components, the term should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two components or the interaction relationship between two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0045] The fire safety control method of the electrochemical energy storage station provided by the embodiment of the present invention is as follows: Figure 1 As shown, the steps include:

[0046] L1, finding the extreme point of the influence relationship between the detection threshold and the detection accuracy of the detection device under the specified working conditions during the specified battery life;

[0047] L2, through the detection accuracy coordinate value of the pole on the third fitting curve, search for the detection threshold coordinate value corresponding to the detection accuracy index value on the first fitting curve or the second fitting curve in the reverse direction;

[0048] L3, by calculating the correction amount, the detection threshold calculated under the same specified working conditions during the historical battery life is corrected to obtain the detection threshold of the detection device during the current battery life period, and the current battery life period is the next life period of the historical battery life period.

[0049] Specifically, the fire safety control method of the electrochemical energy storage station includes the following steps:

[0050] S1, build test environment at different battery life periods B x The test battery pack (during the xth battery life) is tested at different battery operating parameters P B , different detection parameters P A The data set of detection threshold V and detection accuracy P under ;

[0051] The following is an example of how to construct a dataset:

[0052] Assume that the battery operating parameters P B Including battery temperature and battery power after charging is stable, detection parameter P A is the concentration of carbon monoxide released from the test battery pack (simulated release, the simulated release method is, for example, releasing a specified concentration of carbon monoxide from a specified outlet of the test battery pack), the battery life of the test battery pack is B x The constructed data set is B of the test battery pack of this type and model. x During the battery life, P B , P A For quantitative (such as P B The battery temperature is 40°C, the battery charging power is 110W, P B It is the value in a stable state. For example, after the battery pack starts charging, the charging power is stable at 110W, and the battery temperature is stable between 39.5-40.5℃. A The carbon monoxide concentration is 60 mg / m 3 ), the corresponding detection accuracy P calculated under different detection thresholds V, the data set is expressed as {fixed value B x Quantitative P B Quantitative P A , variable V, variable P}.

[0053] S2, draw the test battery group in B in the same xy axis coordinate system x Quantitative P during life span B , P AThe VP curve and PV curve under the following conditions (the VP curve is plotted in the first quadrant of the xy axis coordinate system, the x axis of the VP curve is the detection accuracy P, the y axis is the detection threshold V, and the PV curve is plotted in the third quadrant of the xy axis coordinate system), and the VP curve and the PV curve are fitted by the first fitting function to obtain the first fitting curve corresponding to the VP curve (such as Figure 2 ” in the figure) and the second fitting curve corresponding to the PV curve (as shown in the figure “100” in the figure) Figure 2 (shown as reference numeral "200" in the figure). It should be noted that the first fitting function preferably adopts a quadratic equation or a cubic equation. The expression of the quadratic equation is: y = ax 2 +bx+c; the expression of a cubic equation is: y=ax 3 +bx 2 +cx+d. When fitting the first fitting curve, the detection threshold V is used as the independent variable of the first fitting function, and the detection accuracy P is used as the dependent variable of the first fitting function. When fitting the second fitting curve, the independent variable and the dependent variable of the first fitting function are opposite to those when fitting the first fitting curve. The term coefficients of the first fitting function, such as a, b, c, and d in a cubic equation, can be estimated by existing algorithms such as the least squares method. The estimation method of the term coefficients is not within the scope of the rights protection claimed by the present invention, so it will not be specifically described.

[0054] S3, calculating the distance between each first point i on the VP curve and a second point j on the PV curve having a horizontal and vertical inverted coordinate relationship with the first point i.

[0055] like Figure 2 Example in .

[0056] S4, according to each The corresponding P is plotted in the xy axis coordinate system as Figure 3 shown curve, The curve takes P as the horizontal axis coordinate value and is the vertical axis coordinate value; The corresponding P is calculated The vertical axis coordinate value of the first point i or the horizontal axis coordinate value of the second point j at the time;

[0057] S5, fitting by the second fitting function Each data point on the curve is used to obtain the third fitting curve (such as Figure 3 Then, each extreme point e in the third fitting curve is extracted (including Figure 3The peak point m shown by the reference numeral “400” and the valley point n shown by the reference numeral “500”) are obtained, and the detection accuracy coordinate value P of each pole e on the third fitting curve is obtained. e ;

[0058] It should be noted that the second fitting function is preferably a univariate sixth-order equation. When fitting the third fitting curve, P and The independent variable and dependent variable of the univariate sextic function are fitted respectively. The coefficients of the terms of the univariate sextic function can also be calculated by applying existing algorithms such as the least squares method. The method for calculating the coefficients of the terms of the univariate sextic equation is also not within the scope of the rights protected by the present invention, so it will not be elaborated in detail.

[0059] S6, find a point with coordinate value P on the first fitting curve or the second fitting curve. e The detection threshold coordinate value V of the fitting point e , and follow V e The values ​​are arranged from small to large to form V e Sorted list of values;

[0060] S7, estimated in the real environment in B x The actual battery pack during the battery life, and the battery operating parameters collected from the actual battery pack are P B At B x-1 The detection threshold V set for the real battery pack during the battery life x-1 For quantitative analysis, the detection parameter P was simulated. A , calculate each P A The detection accuracy P′ of the detection equipment under analog quantity is arranged from large to small to form a P′ value sorting list;

[0061] It should be emphasized here that when drawing the VP curve or PV curve in step S2, P A For quantitative analysis, the detection threshold V is a variable, and in step S7, P A is a variable, the detection threshold V x-1 For quantitative. A The meaning of the variable is P A The gas concentration of the reference type is different, such as P A In step S2, the concentration of carbon monoxide is quantitative, which is a fixed value, while in step S7, the concentration of carbon monoxide is a simulated value, which is a variable. It is a simulated concentration with different P values. A The simulation method of the quantity is: generate and release carbon monoxide of corresponding concentration from a specified position of the real battery pack through a gas generator such as a carbon monoxide generator.

[0062] S8, from V eExtract the data pairs V with the same sorting order from the value sorting list and the P′ value sorting list e -P′, then V e -P′ is the data point plotted in the same xy axis coordinate system e -P' curve and P'-V e Curve (the drawing method is the same as VP curve and PV curve, no further description), and calculate V e -P' curve first point r and P'-V e The distance between the second point s on the curve and the first point r, whose coordinates are inverted horizontally and vertically

[0063] S9, calculate each The distance coordinate value L from each pole e on the third fitting curve e , and arrange the first difference absolute values ​​from small to large to form a first difference absolute value list;

[0064] S10, extract the top q first difference absolute values ​​from the first difference absolute value list, and then e The detection threshold coordinate value V corresponding to each pole e used to calculate the absolute value of each first difference extracted is found in the value sorting list. e ;

[0065] S11, calculate the coordinate values ​​V of each detection threshold found in step S10 e The absolute value of the second difference between the two, then calculate the average of the absolute values ​​of the second differences, and solve for V x-1 The difference from the average value is used as the detection device for the B x The actual battery pack during its life is P B The detection threshold V under the condition z .

[0066] What needs to be explained here is B x Life span compared to B x-1 The life period is later in the time sequence. For example, assuming that the battery pack has three life periods, the life periods are the first life period, the second life period, and the third life period from early to late. Assuming that B z-1 The life span is the second life span, then B zThe period is the third life period. Experiments have found that the later the life cycle of a battery pack is, the greater the risk of thermal runaway, and once thermal runaway occurs, a higher concentration of combustible gas is usually released more quickly and in a shorter time. Therefore, for battery packs in the later life period, more accurate detection equipment is needed to respond in a very short time after thermal runaway occurs. Therefore, the detection threshold is set lower than that in the previous life period. The present invention is combined with a large number of experiments, and through the above method, a large number of studies have been conducted on how the detection equipment adjusts the detection threshold for battery packs in different life periods to ensure timely response after thermal runaway occurs in the battery pack. The results show that the above method ensures detection accuracy for battery packs in different life periods, while effectively reducing false alarms.

[0067] The present invention also provides a fire safety control system for an electrochemical energy storage station, such as Figure 4 As shown, including:

[0068] The dataset construction module is used to construct the B z The test battery pack is tested at different battery operating parameters P B , different detection parameters P A The data set of detection threshold V and detection accuracy P under ;

[0069] The first curve drawing module is connected to the data set building module and is used to draw the test battery group in B in the xy axis coordinate system. x Quantitative P during life span B , P A The VP curve and the PV curve under the conditions, the x-axis of the VP curve is the y-axis of the PV curve, and the VP curve and the PV curve are fitted by the first fitting function to obtain a first fitting curve corresponding to the VP curve and a second fitting curve corresponding to the PV curve;

[0070] The first distance calculation module is connected to the first curve drawing module and is used to calculate the distance between each first point i on the VP curve and a second point j on the PV curve whose coordinate values ​​are inverted horizontally and vertically with the first point i.

[0071] The second curve drawing module is used to draw a curve according to each And the corresponding P, drawn in the xy axis coordinate system curve;

[0072] P e A coordinate value acquisition module connected to the second curve drawing module for fitting through a second fitting function The data points on the curve are obtained to obtain the third fitting curve, and then each pole e in the third fitting curve is extracted, and the detection accuracy coordinate value P of each pole e on the third fitting curve is obtained.e ;

[0073] V e The value sorting list forms a module, which is connected to P e The coordinate value acquisition module and the first curve drawing module are used to find a coordinate value P on the first fitting curve or the second fitting curve. e The detection threshold coordinate value V of the fitting point e , and follow V e The values ​​are arranged from small to large to form V e Sorted list of values;

[0074] The P′ value sorting list formation module is used to estimate the B value in the real environment. x The actual battery pack during the battery life, and the battery operating parameters collected from the actual battery pack are P B At B x-1 P during battery life B The detection threshold V is set for the real battery pack under the condition x-1 For quantitative analysis, the detection parameter P was simulated. A , calculate each P A The detection accuracy P′ of the detection equipment under analog quantity is arranged from large to small to form a P′ value sorting list;

[0075] The second distance calculation module is connected to V e The value sorting list forming module and the P′ value sorting list forming module are used to form the P′ value sorting list from V e Extract the data pairs V with the same sorting order from the value sorting list and the P′ value sorting list e -P′, then V e -P′ is the data point plotted in the same xy axis coordinate system e -P' curve and P'-V e curve, and calculate V e -P' curve first point r and P'-V e The distance between the second point s on the curve and the first point r with the coordinates inverted horizontally and vertically

[0076] The first difference absolute value calculation module is connected to the second distance module and is used to calculate each The distance coordinate value L from each pole e on the third fitting curve e , and arrange the first difference absolute values ​​from small to large to form a first difference absolute value list;

[0077] V e The value search module is connected to the first difference absolute value calculation module and V eThe value sorting list forming module is used to extract the first difference absolute values ​​ranked top q from the first difference absolute value list, and then e The detection threshold coordinate value V corresponding to each pole e used to calculate the absolute value of each first difference extracted is found in the value sorting list. e ;

[0078] The second difference absolute value calculation module is connected to V e The value search module is used to calculate the coordinate value V of each detection threshold found e The absolute value of the second difference between the two pairs;

[0079] V x The detection threshold calculation module is connected to the second difference absolute value calculation module to calculate the average value of each second difference absolute value and solve V x-1 The difference from the average value is used as the detection device for B x The actual battery pack during its life is P B The detection threshold V under the condition x .

[0080] In summary, the present invention has found an indicator that can characterize the influence relationship between the detection threshold and detection accuracy of the detection device under different battery life periods, different battery operating parameters, and different detection parameters. The indicator is expressed by the extreme points in the third fitting curve, and by drawing the VP and PV curves of the test battery pack under different working conditions during different battery life periods, the first and second fitting curves, and by calculating the distance The pole that represents the above-mentioned influence relationship is found in the third fitting curve. After the pole is found, the detection accuracy coordinate value P of the pole on the third fitting curve is used. e , find P in the reverse direction on the first fitting curve or the second fitting curve e The corresponding detection threshold coordinate value V e , and by calculating the correction amount for B x-1 The detection threshold V calculated under the same operating conditions during the life span x-1 After correction, we get B x The detection threshold V x , reducing false alarm system operations.

[0081] It should be noted that the above specific implementations are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art should understand that various modifications, equivalent substitutions, changes, etc. can be made to the present invention. However, as long as these changes do not deviate from the spirit of the present invention, they should be within the scope of protection of the present invention. In addition, some terms used in the specification and claims of this application are not restrictive, but are only for the convenience of description.

Claims

1. A fire safety control method for an electrochemical energy storage station, characterized in that: Includes steps: S1, build test environment at different battery life periods B x The test battery pack is tested at different battery operating parameters P B , different detection parameters P A The data set of detection threshold V and detection accuracy P under ; S2, draw the test battery group in B in the same xy axis coordinate system x Quantitative P during life span B , P A A VP curve and a PV curve under certain conditions, and fitting the VP curve and the PV curve by a first fitting function to obtain a first fitting curve corresponding to the VP curve and a second fitting curve corresponding to the PV curve; S3, calculating the distance between each first point i on the VP curve and a second point j on the PV curve having a horizontally and vertically inverted coordinate value relationship with the first point i. S4, according to each And the corresponding P, drawn in the xy axis coordinate system curve; S5, fitting the The data points on the curve are obtained to obtain a third fitting curve, and then each pole e in the third fitting curve is extracted, and the detection accuracy coordinate value P of each pole e on the third fitting curve is obtained. e ; S6, finding a point with coordinate value P on the first fitting curve or the second fitting curve. e The detection threshold coordinate value V of the fitting point e , and follow V e The values ​​are arranged from small to large to form V e Sorted list of values; S7, for the estimated B x A real battery pack during the battery life, and the battery operating parameters collected from the real battery pack are P B At B x-1 P during battery life B The detection threshold V is set for the real battery pack under the condition x-1 For quantitative analysis, the detection parameter P is simulated A , calculate each P A Detection accuracy P of the detection equipment under analog quantity ′ , and follow P ′ The values ​​are arranged from large to small to form P ′ Sorted list of values; S8, from the V e The sorted list of values ​​and the P ′ Extract the data pairs with the same sorting order from the value sorting list V e -P ′ , then V e -P ′ Draw V for the data points in the same xy axis coordinate system e -P ′ Curve and P ′ -V e curve, and calculate the V e -P ′ The first point r on the curve and the P ′ -V e The distance between the second point s on the curve and the first point r having the coordinates inverted horizontally and vertically S9, calculate each The distance coordinate value L from each pole e on the third fitting curve e , and arrange the first difference absolute values ​​from small to large to form a first difference absolute value list; S10, extracting the first difference absolute values ​​ranked top q from the first difference absolute value list, and then e The detection threshold coordinate value V corresponding to each of the poles e used to calculate each of the first difference absolute values ​​extracted is found in the value sorting list. e ; S11, calculating the detection threshold coordinate value V found in step S10 e The absolute values ​​of the second differences between the two, then calculate the average of the absolute values ​​of the second differences, and solve for V x-1 The difference between the average value and the detection device is used as the detection device for the B x The actual battery pack during its life is P B The detection threshold V under the condition x .

2. The fire safety control method of the electrochemical energy storage station according to claim 1, characterized in that: The battery operating parameter P B Including battery temperature and battery power after charging or discharging stabilizes.

3. The fire safety control method of the electrochemical energy storage station according to claim 1, characterized in that: The detection parameter P A It is the concentration of combustible gas or smoke.

4. The fire safety control method of the electrochemical energy storage station according to claim 1, characterized in that: The first fitting function in step S2 is a quadratic equation or a cubic equation.

5. The fire safety control method of the electrochemical energy storage station according to claim 1, characterized in that: The second fitting function in step S5 is a sixth-order equation.

6. An electrochemical energy storage station fire safety control system, characterized in that: include: The dataset construction module is used to construct the B x The test battery pack is tested at different battery operating parameters P B , different detection parameters P A The data set of detection threshold V and detection accuracy P under ; The first curve drawing module is connected to the data set building module and is used to draw the test battery group in B in the xy axis coordinate system. x Quantitative P during life span B , P A A VP curve and a PV curve under the following conditions, wherein the x-axis of the VP curve is the y-axis of the PV curve, and the VP curve and the PV curve are fitted by a first fitting function to obtain a first fitting curve corresponding to the VP curve and a second fitting curve corresponding to the PV curve; a first distance calculation module, connected to the first curve drawing module, for calculating the distance between each first point i on the VP curve and a second point j on the PV curve having a horizontal and vertical inverted coordinate relationship with the first point i; The second curve drawing module is connected to the first distance calculation module and the data set construction module, and is used to And the corresponding P, drawn in the xy axis coordinate system curve; P e A coordinate value acquisition module connected to the second curve drawing module is used to fit the second curve through a second fitting function. The data points on the curve are obtained to obtain a third fitting curve, and then each pole e in the third fitting curve is extracted, and the detection accuracy coordinate value P of each pole e on the third fitting curve is obtained. e ; V e The value sorting list forms a module, connecting the P e The coordinate value acquisition module and the first curve drawing module are used to find a coordinate value P on the first fitting curve or the second fitting curve. e The detection threshold coordinate value V of the fitting point e , and follow V e The values ​​are arranged from small to large to form V e Sorted list of values; P ′ The value sorting list formation module is used to estimate the B value in the real environment. x A real battery pack during the battery life, and the battery operating parameters collected from the real battery pack are P B At B x-1 P during battery life B The detection threshold V is set for the real battery pack under the condition x-1 For quantitative analysis, the detection parameter P is simulated A , calculate each P A Detection accuracy P of the detection equipment under analog quantity ′ , and follow P ′ The values ​​are arranged from large to small to form P ′ Sorted list of values; The second distance calculation module is connected to the V e The sorted list of values ​​forms the module and the P ′ The value sorted list forming module is used to generate the V e The sorted list of values ​​and the P ′ Extract the data pairs with the same sorting order from the value sorting list V e -P ′ , then V e -P ′ Draw V for the data points in the same xy axis coordinate system e -P ′ Curve and P ′ -V e curve, and calculate the V e -P ′ The first point r on the curve and the P ′ -V e The distance between the second point s on the curve and the first point r having the coordinates inverted horizontally and vertically The first difference absolute value calculation module is connected to the second distance calculation module and is used to calculate each The distance coordinate value L from each pole e on the third fitting curve e , and arrange the first difference absolute values ​​from small to large to form a first difference absolute value list; V e A value finding module is connected to the first difference absolute value calculation module and the V e A value sorting list forming module is used to extract the first difference absolute values ​​ranked first from the first difference absolute value list, and then in the V e The detection threshold coordinate value V corresponding to each of the poles e used to calculate each of the first difference absolute values ​​extracted is found in the value sorting list. e ; The second difference absolute value calculation module is connected to the V e A value search module is used to calculate the coordinate value V of each detection threshold value found e The absolute value of the second difference between the two pairs; V x The detection threshold calculation module is connected to the second difference absolute value calculation module, and is used to calculate the average value of each second difference absolute value and solve V x-1 The difference between the average value and the detection device is used as the detection device for the B x The actual battery pack during its life is P B The detection threshold V under the condition x .