Method and device for constructing hot dry rock thermal storage based on fracture filling zone and coarse mineral crystal
By using thermal shock and hydrodynamic forces to form a fracture network in hot dry rock, the problems of high hydraulic fracturing construction costs and poor heat transfer effects are solved, and low-cost and efficient construction of hot dry rock thermal storage is achieved.
Patent Information
- Application Number
- CN202311672222.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-07
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2043-12-07
AI Technical Summary
In the existing dry hot rock geothermal mining process, hydraulic fracturing construction is stressful and costly, and the artificial heat storage fracture system constructed is low in complexity, has poor heat exchange effect, and has safety hazards.
A dry hot rock thermal storage construction method based on fracture filling zones and coarse mineral crystals is adopted. By injecting water into the deep heterogeneous coarse-grained parent rock, thermal shock and hydrodynamic effects are used to form thermal fractures, and the water circulates between the ground and the well. A complex fracture network is formed, and a primary fracture and secondary fracture system is constructed.
It achieves low-cost and efficient construction of a complex fracture system to meet the volume requirements of hot dry rock heat storage, reduces construction costs, avoids the safety hazards of giant hydraulic fracturing, and improves the heat transfer effect.
Smart Images

Figure CN117605452B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of hot dry rock thermal reservoir construction, and relates to a method and device for constructing hot dry rock thermal reservoir based on fracture filling zones and coarse mineral crystals. Background Art
[0002] Hot dry rock geothermal resources have the advantages of high temperature, rich reserves, and wide distribution. At present, the international community generally uses the Enhanced Geothermal System (EGS) for hot dry rock geothermal exploitation. Its core mechanism is to use giant hydraulic fracturing technology to build artificial heat storage for heat extraction. The lithology of hot dry rock formations is mainly granite. Due to its extremely low permeability and high strength, as well as the influence of deep hot dry rock formation stress on the expansion of hydraulic fractures, giant hydraulic fracturing construction is difficult and the engineering cost is high. The constructed fracture systems are mostly single fractures, the fracture system complexity is low, and the heat exchange effect is poor, making it difficult to achieve commercial utilization of hot dry rock geothermal energy. In addition, the high injection pressure during hydraulic fracturing may also induce earthquakes, posing a safety hazard. Summary of the invention
[0003] The present invention overcomes the shortcomings of the prior art and proposes a method and device for constructing a hot dry rock thermal reservoir based on fracture filling zones and coarse mineral crystals. The invention solves the technical problems in the current hot dry rock geothermal EGS mining process, such as high hydraulic fracturing construction pressure and high cost, low complexity of the constructed artificial thermal reservoir fracture system, and poor heat exchange effect.
[0004] In order to achieve the above object, the present invention is implemented through the following technical solutions.
[0005] The method for constructing a thermal reservoir based on a fracture filling zone and coarse mineral crystal dry hot rock includes the following steps:
[0006] 1) Select deep heterogeneous coarse-grained parent rock with fracture filling zone as the target stratum for hot dry rock reservoir construction;
[0007] 2) Construction of main fractures: water is injected into the target formation and covers all fracture filling zones; the temperature difference caused by water injection into the rock mass generates thermal stress. When the thermal stress at the crystal interface under thermal shock reaches the sum of the rock mass tensile strength and the normal ground stress, thermal fracture occurs, thereby forming a thermal fracture crack at the cementation interface between the fracture filling zone and the parent rock; then water with a height of h is injected to expand the thermal fracture crack at the cementation interface between the fracture filling zone and the parent rock to form a main fracture; h is calculated by the combination of formula (III) and formula (IV):
[0008]
[0009]
[0010] Where:
[0011] p - Fluid pressure, MPa; - Fluid (water) density, 1000kg / m 3 ; g-gravitational acceleration, 10N / kg; h-fluid height, m; -Thermal stress at the crystal interface, MPa; -Normal in-situ stress, MPa; K Ic - fracture toughness, ; - crack half length, m;
[0012] 3) Construction of secondary fractures: Inject normal temperature water into the target formation, and form water circulation between the ground and the well through a water pump. Under the action of thermal shock and hydrodynamic force, multi-level fractures are formed in the target formation along the boundaries of heterogeneous coarse mineral crystals in the surrounding rock of the fracture filling zone; the fractures at each level are interconnected, completing the construction of a hot dry rock thermal reservoir with a complex fracture network.
[0013] Preferably, the method for manufacturing the thermal fracture cracks is: constructing a water injection well on the ground to the bottom of the target formation, and lowering a water pump to the bottom of the target formation; setting a surface water pump on the ground, turning on the surface water pump, and injecting water into the wellbore through the annulus between the water pump pipe in the injection well and the wellbore casing to cover all fracture filling zones in the target formation; after the water temperature stabilizes, using the water pump to pump out all the water in the wellbore, and waiting for the heat storage temperature to recover; repeating the water injection and pumping operations to form thermal fracture cracks at the cementation interface between the fracture filling zone and the parent rock.
[0014] Preferably, the number of repetitions of the water injection and pumping operations is determined by the physical, mechanical and mineralogical properties of the fracture filling zone and the parent rock of the target formation, obtained through laboratory tests, so as to form thermal fractures with a fracture half-length ≥ 0.01 m at the cementation interface between the fracture filling zone and the parent rock.
[0015] Preferably, the thermal stress at the crystal interface under thermal shock Satisfy the formula :
[0016]
[0017] In step 2), the temperature of the injected water = the temperature of the target formation - ΔT; the ΔT satisfies the formula (II):
[0018]
[0019] Where:
[0020] -Thermal stress at the crystal interface under thermal shock, MPa;
[0021] -Normal in-situ stress, MPa;
[0022] -Tensile strength, MPa;
[0023] E1, E2-elastic modulus of two adjacent mineral particles, MPa;
[0024] - Thermal expansion coefficient of two adjacent mineral particles, °C -1 ;
[0025] ΔT – temperature difference, °C.
[0026] Preferably, step 3) is to fill the wellbore of the injection well with 20°C normal temperature water, and then start the water pump simultaneously to cause the water to circulate from the ground to the annulus to the water pump pipe to the ground. Under the action of thermal shock and hydrodynamic force, secondary fractures are formed in the target formation along the boundaries of heterogeneous coarse mineral crystals in the surrounding rock of the fracture filling zone. At the same time, the main fractures and secondary fractures are interconnected to complete the construction of a hot dry rock thermal reservoir containing a complex fracture network.
[0027] Preferably, when the temperature difference ΔT between the target formation and the normal temperature water is brought into equation (V), the thermal stress When the sum of the rock mass tensile strength and the normal in-situ stress is reached, it indicates that the cementation interface between the fracture filling zone and the parent rock has generated primary cracks due to thermal expansion, and the primary cracks can be directly used as primary cracks; then step 2) is omitted and secondary cracks are directly constructed; the formula (V) is:
[0028] ;
[0029] Where:
[0030] -Thermal stress at the crystal interface under thermal expansion, MPa;
[0031] E1, E2-elastic modulus of two adjacent mineral particles, MPa;
[0032] - Thermal expansion coefficient of two adjacent mineral particles, °C -1 ;
[0033] ΔT – temperature difference, °C.
[0034] More preferably, the deep heterogeneous coarse-grained rock layer is a granite matrix, and when the temperature of the target formation is ≥400°C, the primary fractures at the cementation interface between the fracture filling zone and the matrix are used as the main fractures.
[0035] The hot dry rock thermal reservoir construction device used in the method for constructing a hot dry rock thermal reservoir based on fracture filling zones and coarse mineral crystals is to construct a water injection well on the ground to the bottom of the target formation; all formations above the target formation are cemented with casing, and the entire section of the target formation is completed with bare holes; a water pump is set at the bottom of the target formation, and a surface water pump is set on the ground; a water pump pipe is lowered into the water injection well; the surface water pump is turned on to inject water into the target formation through the annulus between the water pump pipe and the wellbore casing and cover all fracture filling zones in the target formation.
[0036] Preferably, when the surface water pump is working at a high flow rate, the flow rate of the surface water pump is ≥160m 3 / h; When the ground water pump and the water pump work synchronously with a small flow rate, the flow rate of the two is 10-30m 3 / h, achieving low-cost water circulation.
[0037] Preferably, the distance between the water pump and the bottom of the target formation is ≤40 cm.
[0038] The beneficial effects of the present invention compared with the prior art are as follows:
[0039] (1) The present invention induces the formation of primary fractures along the cementation interface between the parent rock and the fracture filling zone in the target dry hot rock formation through the thermal shock and hydrodynamic effects generated during the water injection process, and simultaneously forms secondary fractures along the boundaries of heterogeneous coarse mineral crystals in the surrounding rock of the fracture filling zone and the dissolved pores in the fracture filling zone. The expansion of the pores and fractures in the above-mentioned areas will break away from the control of geostress, interconnect with each other, and eventually form a complex fracture system.
[0040] (2) Geological tectonic movements and a good diagenetic environment at depth ensure the universality and complexity of the occurrence of heterogeneous coarse mineral crystals in the fracture filling zone and the parent rock. Therefore, the primary and secondary fracture systems formed are sufficient to meet the volume requirements of the hot dry rock heat reservoir.
[0041] (3) The present invention omits the giant hydraulic fracturing step, avoids the ancillary technical problems of giant hydraulic fracturing, greatly simplifies the construction process of hot dry rock thermal reservoirs, reduces construction costs, and can construct hot dry rock high-permeability thermal reservoirs on a large scale and efficiently.
[0042] (4) The present invention is applicable to the construction of medium-high temperature hot dry rock thermal reservoirs containing fracture filling zones and heterogeneous coarse mineral crystals. It can also provide a reference for the construction of shale gas, natural gas, petroleum and other reservoirs containing fracture filling zones and heterogeneous coarse mineral crystals. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 It is a construction process diagram of the method for constructing a hot dry rock thermal reservoir based on fracture filling zones and heterogeneous coarse mineral crystals of the present invention.
[0044] Figure 2It is a schematic diagram of the local situation of the medium-high temperature hot dry rock target formation before water injection in Example 1.
[0045] Figure 3 This is a schematic diagram of the local fracture development in the target formation of medium-high temperature hot dry rock in the early stage of water injection in Example 1.
[0046] Figure 4 It is a schematic diagram of the local fracture development in the target formation of medium-high temperature hot dry rock at the end of water injection in Example 1.
[0047] Figure 5 It is a schematic diagram of the local situation of the high-temperature hot dry rock target formation before water injection in Example 2.
[0048] Figure 6 This is a schematic diagram of the local fracture development in the target formation of high-temperature hot dry rock in the early stage of water injection in Example 2.
[0049] Figure 7 This is a schematic diagram of the local fracture development in the target formation of high-temperature hot dry rock at the end of water injection in Example 2.
[0050] In the figure, 1-target formation; 2-granite parent rock; 3-fracture filling zone; 4-first coarse mineral crystal; 5-dissolution pore; 7-water injection well; 8-cementing section; 9-open hole; 10-pressure sensor; 11-water pump; 12-surface water pump; 13-water pump pipe; 14-annulus between wellbore casing; 15-cementation interface; 16-main fracture; 17-seepage channel; 18-coarse mineral crystal boundary; 19-secondary thermal fracture; 20-second coarse mineral crystal; 22-primary fracture. DETAILED DESCRIPTION
[0051] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present invention clearer, the present invention is further described in detail in conjunction with the embodiments and the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. The technical solutions of the present invention are described in detail below in conjunction with the embodiments and the accompanying drawings, but the scope of protection is not limited thereto.
[0052] Example 1
[0053] like Figure 1 , Figure 2 , Figure 3 and Figure 4As shown, in this embodiment, a method for constructing a medium-high temperature hot dry rock thermal reservoir based on a fracture filling zone and heterogeneous coarse mineral crystals is selected as the target formation 1 for the construction of hot dry rock thermal reservoirs according to relevant hydrological and geological exploration data. The target formation 1 has an average burial depth of 2000m, a thickness of 400m, and a temperature of 180°C. The target formation 1 consists of a granite parent rock 2 and a fracture filling zone 3. The main mineral properties of the granite parent rock 2 and the fracture filling zone 3 are shown in Table 1. Among them, amphibole constitutes the first coarse mineral crystal 4 in the granite parent rock 2. The hydrothermal fluid produced by volcanic activity contains acidic components such as H2S, HCL, HF, SO2, CO, CO2, etc. The fracture filling zone 3 forms a large number of dissolution pores 5 due to the dissolution of acidic substances. The target stratum 1 selected in this embodiment contains 8 fracture filling zones 3, the average interval between two adjacent fracture filling zones 3 in the vertical direction is 50m, and contains a fracture filling zone 3 with a length of 3km and a thickness of 20cm. Figure 2 . Construct a water injection well 7 on the ground to the bottom of the target formation 1. The water injection well 7 above the target formation 1 is completely provided with a cementing section 8. An open hole 9 is provided on the water injection well 7 that enters the entire section of the target formation 1. A water pump 11 equipped with a temperature sensor and a pressure sensor 10 is lowered to the bottom of the target formation 1. The distance between the water pump 11 and the bottom of the target formation 1 is 40 cm.
[0054]
[0055] During the water injection process of hot dry rock reservoir construction, water injected into high-temperature rock mass will generate temperature difference, thus generating thermal stress. According to the maximum tensile stress criterion, when the maximum tensile stress, i.e. the thermal stress at the crystal interface under thermal shock, reaches the tensile strength of the rock mass, thermal cracking will occur, that is, it satisfies:
[0056]
[0057]
[0058] Where:
[0059] -Thermal stress at the crystal interface under thermal shock, MPa;
[0060] -Normal in-situ stress, MPa;
[0061] -Tensile strength, MPa;
[0062] E1, E2-elastic modulus of two adjacent mineral particles, MPa;
[0063] - Thermal expansion coefficient of two adjacent mineral particles, °C-1 ;
[0064] ΔT – temperature difference, °C.
[0065] The target stratum is buried at a depth of 2000m. The laboratory measured the tensile strength of granite parent rock to be 15MPa, and the tensile strength of granite with cemented interface to be 9MPa. , (II) Calculation shows that when the temperature difference ΔT is between 128-141°C, thermal cracks will only be formed at the cementation interface 15 between the fracture filling zone 3 and the granite parent rock 2.
[0066] According to the above calculation results, the surface water pump 12 is turned on to inject water with a specific temperature of 50°C (the temperature difference with the target formation 1 is 130°C) into the target formation 1 through the annulus 14 between the water pump pipe 13 and the well casing until all the fracture filling zones 3 in the target formation 1 are covered. The water injection flow rate is 200m 3 / h to reduce the heat exchange between water and cementing section 8. Under the action of thermal shock, thermal fracture occurs and cracks are formed at the cementing interface 15 between the fracture filling zone 3 and the granite parent rock 2. After the temperature sensor monitors that the water temperature is stable, the water in the wellbore is completely pumped out by the water pump 11, and the heat storage temperature is waited for to recover.
[0067] The laboratory measured that under the conditions of rock mass temperature of 180℃ and injection water temperature of 50℃, 5 cycles of thermal shock can form a crack with a half-length a of 0.01m at the cementing interface 15 between the fracture filling zone 3 and the granite parent rock 2. Therefore, repeating the 50℃ water injection and extraction cycle 5 times, a crack with a half-length a of 0.01m is formed at the cementing interface 15 between the fracture filling zone 3 and the granite parent rock 2.
[0068] The cracks formed during the water injection process of thermal reservoir construction are open cracks (Type I cracks). According to the stress intensity factor fracture criterion of linear elastic fracture mechanics theory, for open cracks, when the stress intensity factor at the crack tip is greater than or equal to the rock fracture toughness, the cracks begin to expand. Considering the stress conditions of the rock mass during the water injection process, the cracks will expand when the following conditions are met:
[0069]
[0070]
[0071] Where:
[0072] p - Fluid pressure, MPa;
[0073] - Fluid (water) density, 1000kg / m 3 ;
[0074] g-gravitational acceleration, 10N / kg;
[0075] h-fluid height, m;
[0076] -Thermal stress at the crystal interface, MPa;
[0077] -Normal in-situ stress, MPa;
[0078] K Ic - fracture toughness, ;
[0079] - Crack half length, m.
[0080] The target stratum 1 is buried at a depth of 2000m. When the injection water temperature is 50℃, that is, the temperature difference between water and target formation 1 is 130℃, it can be calculated by formula (II) that the thermal stress in granite matrix 2 under thermal shock can reach 50MPa, and the thermal stress at the cementation interface 15 between fracture filling zone 3 and granite matrix 2 can reach 60MPa. The experimental test shows that the fracture toughness of matrix at 180℃ is 2 The fracture toughness of the cementation interface 15 between the fracture filling zone 3 and the granite parent rock 2 is 1.8 ; The half length a of the fracture is 0.01 m. It can be calculated from formulas (III) and (IV) that when the injection water depth is between 16 and 1128 m, the fracture will only expand at the cementation interface 15 between the fracture filling zone 3 and the granite parent rock 2.
[0081] According to the above calculation results, the surface water pump 12 is used to inject water with a temperature of 50°C (the temperature difference with the target formation is 130°C) into the target formation 1 through the annulus 14 between the water pump pipe 13 and the well casing. The water injection depth is controlled between 600-700m according to the pressure monitored by the pressure sensor 10, and the water injection flow rate is 200m 3 / h to reduce the heat exchange between water and cementing section 8. Under the action of thermal shock and hydrodynamic force, the target formation 1 forms a main fracture 16 at the cementing interface 15 between the fracture filling zone 3 and the granite parent rock 2. Figure 3 .
[0082] After the main crack 16 is constructed, 20℃ normal temperature water is poured at 200m 3 / h flow rate to fill the injection well 7. Then adjust the surface water pump 12 and start the water pump 11 synchronously, so that the water forms a low-cost circulation of the surface-annulus-water pump pipe 13-surface, and continuously thermally shocks the target formation 1. The flow rates of the surface water pump 12 and the water pump 11 are both 20m 3 / h. The water pump 11 has a filtering device, which can effectively filter out impurities such as rock debris. - (IV) It can be calculated that when the injection water temperature is 20°C (the temperature difference with the target formation 1 is 160°C) and the fluid pressure is 20MPa (2000m water pressure), under the action of thermal shock and hydrodynamic force, the target formation 1 will form secondary thermal fractures 19 along the coarse mineral crystal boundary 18 of the first coarse mineral crystal 4 in the surrounding rock of the fracture filling zone 3. The dissolved pores 5 in the fracture filling zone 3 will be interconnected to form seepage channels 17, see Figure 4 At the same time, the main fractures 16 at the cementation interface 15 between the fracture filling zone 3 and the granite parent rock 2, the seepage channels 17 inside the fracture filling zone 3 and the secondary thermal fractures 19 at the coarse mineral crystal boundary 18 of the first coarse mineral crystal 4 further expand and interpenetrate, completing the construction of a dry hot rock thermal reservoir with a complex fracture network. Figure 4 .
[0083] Example 2
[0084] like Figure 1 , Figure 5 , Figure 6 and Figure 7 As shown, in this embodiment, a method for constructing a high-temperature hot dry rock thermal reservoir based on a fracture filling zone and heterogeneous coarse mineral crystals is selected, according to relevant hydrological and geological exploration data, as the target stratum 1 for the construction of hot dry rock thermal reservoirs. The target stratum 1 has an average burial depth of 2000m, a thickness of 500m, and a temperature of 400°C. The target stratum 1 consists of a granite parent rock 2 and a fracture filling zone 3. The main minerals of the granite parent rock 2 and the fracture filling zone 3 of the target stratum 1 are the same as those in Example 1. Hornblende constitutes the second coarse mineral crystals 20 in the granite parent rock 2. The fracture filling zone 3 contains dissolved pores 5. The target stratum 1 contains 10 fracture filling zones 3, and the average interval between two adjacent fracture filling zones 3 in the vertical direction is 50m, and there is a fracture filling zone 3 with a length of 4km and a width of 30cm, see Figure 5 .
[0085] A water injection well 7 is constructed on the ground to the bottom of the target formation 1, and the cementing process of the water injection well 7 is the same as that of Example 1. A water pump 11 equipped with a temperature sensor and a pressure sensor 10 is lowered to the bottom of the target formation 1, and the distance between the water pump 11 and the bottom of the target formation 1 is 40 cm.
[0086] As the temperature of the hot dry rock formation increases, the mineral crystals that make up the hot dry rock mass will undergo thermal expansion. According to the maximum tensile stress criterion, when the maximum tensile stress reaches the tensile strength of the rock mass, thermal fracture will occur. The extreme heterogeneity of the granite parent rock 2 and the fracture filling zone 3 leads to significant differences in the thermal expansion of adjacent mineral crystals at the cementation interface 15 between the two, which eventually forms thermal fracture cracks. The laboratory measured that the tensile strength of the granite parent rock 2 in this embodiment is 15MPa, and the tensile strength of the granite at the cementation interface 15 is 9MPa. The thermal stress calculation formula (V) at the interface between two adjacent mineral crystals in the rock mass under thermal expansion is combined with the formula It can be calculated that when the target formation stress is 50MPa (buried at a depth of 2000m) and the target formation temperature is 400℃, a thermal fracture will be formed at the cementation interface 15 between the fracture filling zone 3 and the granite parent rock 2. Figure 5 As shown, under the action of high temperature of 400°C, primary fractures 22 have been formed at the cementation interface 15 between the fracture filling zone 3 and the granite parent rock 2 in the hot dry rock target formation.
[0087]
[0088] Where:
[0089] -Thermal stress at the crystal interface under thermal expansion, MPa;
[0090] E1, E2-elastic modulus of two adjacent mineral particles, MPa;
[0091] - Thermal expansion coefficient of two adjacent mineral particles, °C -1 ;
[0092] ΔT – temperature difference, °C.
[0093] Open the ground water pump 12 to pump 20℃ normal temperature water at 200m 3 / h flow rate is injected into the target formation 1 through the annulus 14 between the water pump pipe 13 and the well casing until the injection well 7 is filled. Then the surface water pump 12 is adjusted and the water pump 11 is started synchronously to promote the water to form a low-cost circulation of the surface-annulus-water pump pipe 13-surface, and continuously thermally shock the target formation 1. The flow rates of the surface water pump 12 and the water pump 11 are both 20m 3 / h. The water pump 11 has a filtering device that can effectively filter impurities such as rock debris. - (IV) Calculations show that when the temperature difference between the injected water and the target formation is 380°C and the fluid pressure is 20 MPa (2000 m water pressure), under the action of thermal shock and hydrodynamic force, the primary fracture 22 at the cementation interface 15 between the granite parent rock 2 and the fracture filling zone 3 will first evolve into a main fracture 16 with a longer length and wider width, and the fracture extension direction is still in the direction of the cementation interface 15; the dissolved pores 5 in the fracture filling zone 3 will interconnect to form a seepage channel 17; the coarse mineral crystal boundary 18 of the second coarse mineral crystal 20 in the granite parent rock 2 will form a secondary thermal fracture 19, see Figure 6 At the same time, the main cracks 16 at the cementation interface 15, the seepage channels 17 inside the fracture filling zone 3, and the secondary thermal cracks 19 at the coarse mineral crystal boundary 18 of the second coarse mineral crystal 20 further expand and interpenetrate each other, completing the large-scale and efficient construction of a high-permeability heat reservoir of hot dry rocks with a complex fracture network. Figure 7 .
[0094] The above content is a further detailed description of the present invention in combination with a specific preferred embodiment. It cannot be determined that the specific embodiments of the present invention are limited to this. For ordinary technicians in the technical field to which the present invention belongs, several simple deductions or substitutions can be made without departing from the present invention, which should be regarded as belonging to the present invention and the scope of patent protection determined by the submitted claims.
Claims
1. A method for constructing a hot dry rock thermal reservoir based on fracture filling zones and coarse mineral crystals, characterized in that: The following steps are involved: 1) Selecting deep heterogeneous coarse-grained parent rock with fracture filling zone (3) as the target stratum (1) for hot dry rock reservoir construction; 2) Construction of the main fracture (16): 50°C water is injected into the target formation (1) and covers all fracture filling zones (3); the temperature difference generated by the water injection into the rock mass generates thermal stress. When the thermal stress at the crystal interface under thermal shock reaches the sum of the rock mass tensile strength and the normal ground stress, thermal fracture occurs, thereby forming a thermal fracture fracture at the cementation interface (15) between the fracture filling zone (3) and the parent rock; then water with a height of h is injected to cause the thermal fracture fracture to expand at the cementation interface (15) between the fracture filling zone (3) and the parent rock, thereby forming a main fracture (16); h is calculated by the combination of formula III and formula IV: Where: p - Fluid pressure, MPa; - Fluid density, 1000kg / m 3 ; g-gravitational acceleration, 10N / kg; h-fluid height, m; -Thermal stress at the crystal interface, MPa; -Normal in-situ stress, MPa; K Ic -Fracture toughness, MPa•m 1 / 2 ; α- crack half length, m; The method for manufacturing the thermal fracture cracks is as follows: constructing a water injection well (7) on the ground to the bottom of the target formation (1), and lowering a water pump (11) to the bottom of the target formation (1); setting a surface water pump (12) on the ground, turning on the surface water pump (12), and injecting water into the wellbore through the annulus (14) between the water pump pipe (13) in the injection well (7) and the wellbore casing to cover all fracture filling zones (3) in the target formation (1); after the water temperature stabilizes, using the water pump (11) to pump out all the water in the wellbore, and waiting for the heat storage temperature to recover; repeating the water injection and pumping operations to form thermal fracture cracks at the cementation interface (15) between the fracture filling zone (3) and the parent rock; Thermal stress at the crystal interface under thermal shock Satisfies Formula I: (I) In step 2), the temperature of the injected water = the temperature of the target formation (1) - ΔT; the ΔT satisfies formula II: (Ⅱ) Where: -Thermal stress at the crystal interface under thermal shock, MPa; -Normal in-situ stress, MPa; -Tensile strength, MPa; E1, E2-elastic modulus of two adjacent mineral particles, MPa; - Thermal expansion coefficient of two adjacent mineral particles, °C -1 ; ΔT-temperature difference, °C; 3) Construction of secondary fractures: 20°C normal temperature water is injected into the target formation (1), and water circulation is formed between the ground and the well through a water pump (11). Under the action of thermal shock and hydrodynamic force, multi-layered fractures are formed in the target formation (1) along the boundaries of heterogeneous coarse mineral crystals in the surrounding rock of the fracture filling zone; the fractures at each layer are interconnected, completing the construction of a hot dry rock thermal reservoir containing a complex fracture network; When the temperature difference ΔT between the target stratum (1) and the normal temperature water is brought into the formula V and the thermal stress σ is obtained, it is indicated that the cementation interface (15) between the fracture filling zone (3) and the parent rock has generated a primary fracture (22) due to thermal expansion, and the primary fracture (22) is directly used as the main fracture (16); then step 2 is omitted and the secondary fracture is directly constructed; (V); Where: -Thermal stress at the crystal interface under thermal expansion, MPa; E1, E2-elastic modulus of two adjacent mineral particles, MPa; - Thermal expansion coefficient of two adjacent mineral particles, °C -1 ; ΔT – temperature difference, °C.
2. The method for constructing a hot dry rock thermal reservoir based on fracture filling zones and coarse mineral crystals according to claim 1 is characterized in that: The number of repetitions of the water injection and pumping operations is determined by the physical, mechanical and mineralogical properties of the fracture filling zone (3) and the parent rock of the target formation (1), and is obtained through laboratory tests to form a thermal fracture with a fracture half-length ≥ 0.01 m at the cementation interface (15) between the fracture filling zone (3) and the parent rock.
3. The method for constructing a hot dry rock thermal reservoir based on fracture filling zones and coarse mineral crystals according to claim 1, characterized in that: Step 3) is to fill the wellbore of the water injection well (7) with 20°C normal temperature water, and then simultaneously start the water pump (11) to promote the water to form a circulation of ground-annulus-water pump pipe (13)-ground; under the action of thermal shock and hydrodynamic force, secondary fractures are formed in the target formation (1) along the boundaries of heterogeneous coarse mineral crystals in the surrounding rock of the fracture filling zone (3); at the same time, the main fractures (16) and the secondary fractures are interconnected, completing the construction of a dry hot rock thermal reservoir containing a complex fracture network.
4. The method for constructing a hot dry rock thermal reservoir based on fracture filling zones and coarse mineral crystals according to claim 1, characterized in that: The deep heterogeneous coarse-grained rock layer is a granite parent rock (2). When the temperature of the target stratum (1) is ≥400°C, the primary fractures (22) at the cementation interface (15) between the fracture filling zone (3) and the parent rock are used as the main fractures (16).
5. A hot dry rock thermal reservoir construction device for use in the method for constructing a hot dry rock thermal reservoir based on a fracture filling zone and coarse mineral crystals as described in any one of claims 2 to 4, characterized in that: A water injection well (7) is constructed on the ground to the bottom of the target formation (1); all formations above the target formation (1) are cemented with casing, and the entire section of the target formation (1) is completed with open holes; a water pump (11) is arranged at the bottom of the target formation (1), and a surface water pump (12) is arranged on the ground; a water pump pipe (13) is lowered into the water injection well (7); the surface water pump (12) is turned on, and water is injected into the target formation (1) through the annulus (14) between the water pump pipe (13) and the wellbore casing to cover all fracture filling zones (3) in the target formation (1).
6. The dry hot rock heat storage construction device according to claim 5 is characterized in that: When the surface water pump (12) is working at a high flow rate, the flow rate of the surface water pump (12) is ≥160m 3 / h; when the surface water pump (12) and the water pump (11) work synchronously at a small flow rate, the flow rates of the two are 10-30m 3 / h, achieving low-cost water circulation.
7. The dry hot rock heat storage construction device according to claim 5, characterized in that: The distance between the water pump (11) and the bottom of the target stratum (1) is ≤40 cm.
Citation Information
Patent Citations
Method of forming fractures by means of hydrofracturing assisted by alternate spraying of high- and low-temperature fluids in deep hot dry rock
CN108979609A
Hot dry rock geothermal exploitation method for deep crack later-filling thermal reservoir
CN113389537A