A smart management method and platform for the renovation of old residential areas

Through the intelligent management method for renovation of old communities and combining safety risk factors and monitoring data, a security risk assessment and monitoring management module has been established, which solves the safety hazard screening and supervision problems of renovation projects of old communities and improves the reliability of construction supervision.

CN117670629BActive Publication Date: 2024-11-19ZHEJIANG SHENGZHI ARCHITECTURAL DESIGN INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311808658.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-12-26
Publication Date
2024-11-19
Estimated Expiration
2043-12-26

AI Technical Summary

Technical Problem

How to establish a unified data supervision platform to achieve unified supervision and handling of renovation projects of different old communities, especially in terms of safety risk assessment and construction supervision, there are difficulties and hidden dangers in analytical aspects.

Method used

By obtaining the safety risk factors and the number of construction personnel of the renovation project, determining the project safety risks, combining monitoring image data to identify safety violations, conducting potential safety risk assessment and screening, establishing a safety risk assessment module, risk project screening module and monitoring management module, Realize safety risk assessment and supervision of old communities.

Benefits of technology

Effectively screen out old communities with greater safety hazards, improve the reliability of construction supervision, avoid the difficulty of monitoring and analysis of all communities by remote cloud platforms, and ensure specific assessment and supervision of potential security risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117670629B_ABST
    Figure CN117670629B_ABST
Patent Text Reader

Abstract

The present invention provides a smart management method and platform for the renovation of old communities, which belongs to the field of data management technology, and specifically includes: determining safety supervision communities based on safety risks of community renovation of different old communities, identifying safety violations of different renovation projects of different safety monitoring communities through monitoring data of monitoring images of different safety supervision communities, and monitoring safety risks of different renovation projects and determining risky renovation projects in combination with security monitoring communities of renovation projects containing safety violations, determining potential safety risks of different old communities through monitoring safety risks of different renovation projects and risky renovation projects, determining risk supervision communities based on potential safety risks, monitoring and managing safety violations of risk supervision communities and safety supervision communities through monitoring data of monitoring images, thereby improving construction safety during the renovation of old communities.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of data management technology, and in particular relates to a smart management method and platform for the renovation of old residential areas. Background Art

[0002] With the increase in years of use, there are currently a large number of old communities in different cities that are in urgent need of renovation. Since there are many projects that need to be renovated in old communities, how to establish a unified data supervision platform to achieve unified supervision and processing of different renovation projects has become a technical problem that needs to be solved urgently.

[0003] In response to the above technical problems, the present invention provides a smart management method and platform for the renovation of old communities. Summary of the invention

[0004] To achieve the purpose of the present invention, the present invention adopts the following technical solutions:

[0005] According to one aspect of the present invention, a smart management method for the renovation of old residential areas is provided.

[0006] A smart management method for the renovation of old residential areas, characterized by comprising:

[0007] S1: Obtaining renovation projects of different old residential communities, and determining the project safety risks of the different renovation projects based at least on the safety risk factors of the different renovation projects and the number of construction personnel, and determining the community renovation safety risks of the old residential communities based on the project safety risks of the different renovation projects;

[0008] S2 determines the safety supervision community based on the safety risks of the community renovation of different old communities, identifies the safety violations of different renovation projects of different safety supervision communities through the monitoring data of the monitoring images of different safety supervision communities, and determines the monitoring safety risks of different renovation projects and risk renovation projects in combination with the safety monitoring communities of the renovation projects containing the safety violations;

[0009] S3 determines the potential safety risks of different old communities by monitoring safety risks of different renovation projects and risk renovation projects, and determines risky supervision communities based on the potential safety risks, and monitors and manages safety violations in risky supervision communities and safety supervision communities through monitoring data from surveillance images.

[0010] The beneficial effects of the present invention are:

[0011] 1. The safety risks of the renovation of old communities are determined through the project safety risks of different renovation projects. The old communities with greater safety hazards are screened out based on the differences in safety hazards of different renovation projects in different old communities, avoiding the technical problem of greater analysis difficulty caused by the remote cloud platform monitoring and analyzing all old communities.

[0012] 2. In the present invention, by combining the actual situation of safety violations in different renovation projects to monitor safety risks of different renovation projects and determine risky renovation projects, it is possible to screen risky renovation projects with higher construction safety risks from the perspective of actual monitoring data, and also lays a foundation for combining actual data to realize specific assessment of safety risks in different old communities.

[0013] 3. In the present invention, by evaluating the potential safety risks of different old communities and screening risk-supervised communities, it is possible to screen old communities with higher potential safety risks from the perspective of actual safety supervision data, thereby avoiding the emergence of safety hazards caused by inadequate safety supervision of old communities with higher potential safety risks, and further improving the reliability of construction supervision in old communities.

[0014] A further technical solution is that the safety risk factors include object impact, falling from height, collapse risk, mechanical injury, and electrical safety.

[0015] A further technical solution is that the number of construction workers for the renovation project is determined according to the construction volume of the renovation project, specifically, a construction volume interval that matches the construction volume is determined according to the construction volume of the renovation project, and the number of construction workers for the renovation project is determined through the construction volume interval.

[0016] A further technical solution is that the method for determining the project safety risk of the transformation project is:

[0017] Determine the number of high-risk safety factors and the number of general safety factors of the renovation project through the safety risk factors of the renovation project, and determine the risk factor assessment amount of the renovation project based on the number of high-risk safety factors and the number of general safety factors;

[0018] The project safety risk of the renovation project is determined based on the risk factor assessment amount of the renovation project and the number of construction personnel.

[0019] A further technical solution is that the high-risk safety factors and general safety factors are determined based on the accident hazards and accident probability of the safety factors.

[0020] A further technical solution is that the high-risk safety factors and general safety factors are determined based on the matching results of the safety factors with a preset safety factor database.

[0021] A further technical solution is that the security violation behavior is determined based on the analysis results of the monitoring data of the monitoring image. Specifically, the security violation behavior in different monitoring images is determined by an image recognition model.

[0022] In a second aspect, the present invention provides a smart management platform for the renovation of old residential areas, which adopts the above-mentioned smart management method for the renovation of old residential areas, and specifically includes:

[0023] Safety risk assessment module, risk project screening module, monitoring and management module;

[0024] The safety risk assessment module is responsible for obtaining renovation projects of different old communities, and determining the project safety risks of different renovation projects based at least on the safety risk factors of different renovation projects and the number of construction personnel, and determining the safety risks of the renovation of the old communities through the project safety risks of different renovation projects;

[0025] The risk project screening module is responsible for determining the safety supervision community based on the community renovation safety risks of different old communities, identifying the safety violations of different renovation projects of different safety monitoring communities through the monitoring data of the monitoring images of different safety supervision communities, and combining the safety monitoring communities of the renovation projects containing the safety violations to monitor the safety risks of different renovation projects and determine the risky renovation projects;

[0026] The monitoring and management module is responsible for determining the potential safety risks of different old communities through monitoring safety risks of different renovation projects and risk renovation projects, and determining risky supervision communities based on the potential safety risks, and monitoring and managing safety violations in risky supervision communities and safety supervision communities through monitoring data from surveillance images.

[0027] Other features and advantages will be described in the following description. The objects and other advantages of the present invention are realized and obtained by the structures particularly pointed out in the description and drawings.

[0028] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] The above and other features and advantages of the present invention will become more apparent by describing in detail exemplary embodiments thereof with reference to the attached drawings.

[0030] Figure 1 It is a flow chart of a smart management method for the renovation of old residential areas;

[0031] Figure 2 It is a flow chart of the method for determining the safety risks of the renovation of old residential areas;

[0032] Figure 3 It is a framework diagram of a smart management platform for the renovation of old residential communities. DETAILED DESCRIPTION

[0033] In order to enable those skilled in the art to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this specification, not all of the embodiments. Based on the embodiments of this specification, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of this specification.

[0034] Method Example

[0035] To solve the above problems, according to one aspect of the present invention, Figure 1 As shown, a smart management method for the renovation of old residential areas is provided, which is characterized by specifically including:

[0036] S1: Obtaining renovation projects of different old residential communities, and determining the project safety risks of the different renovation projects based at least on the safety risk factors of the different renovation projects and the number of construction personnel, and determining the community renovation safety risks of the old residential communities based on the project safety risks of the different renovation projects;

[0037] Specifically, the safety risk factors include object impact, falling from height, collapse risk, mechanical injury, and electrical safety.

[0038] Furthermore, the number of construction workers of the renovation project is determined according to the construction volume of the renovation project. Specifically, the construction volume interval that matches the construction volume is determined according to the construction volume of the renovation project, and the number of construction workers of the renovation project is determined through the construction volume interval.

[0039] In one possible embodiment, the method for determining the project safety risk of the transformation project in step S1 is:

[0040] Determine the number of high-risk safety factors and the number of general safety factors of the renovation project through the safety risk factors of the renovation project, and determine the risk factor assessment amount of the renovation project based on the number of high-risk safety factors and the number of general safety factors;

[0041] The project safety risk of the renovation project is determined based on the risk factor assessment amount of the renovation project and the number of construction personnel.

[0042] Specifically, the high-risk safety factors and general safety factors are determined based on the accident hazards and accident occurrence probabilities of the safety factors.

[0043] It can be understood that the high-risk safety factors and general safety factors are determined based on the matching results of the safety factors with a preset safety factor database.

[0044] In one possible embodiment, Figure 2 As shown, the method for determining the safety risk of the community renovation of the old community in the above step S1 is:

[0045] Determine the risk renovation projects of the renovation projects based on the project safety risks of different renovation projects, and judge whether the number of risk renovation projects of the old community meets the requirements. If so, proceed to the next step; if not, determine that the old community is a safety supervision community;

[0046] Determine the total number of construction personnel in the old community based on the number of construction personnel in different renovation projects, determine the risk control interval corresponding to the old community based on the total number of construction personnel in the old community, and determine the quantity threshold of risk renovation projects in the old community based on the risk control interval, and determine whether the number of risk renovation projects in the old community meets the requirements through the quantity threshold, if yes, proceed to the next step, if not, determine that the old community is a safety supervision community;

[0047] Determine the comprehensive project safety risk of the risk renovation project of the old community according to the number of risk renovation projects of the old community and the project safety risks of different risk renovation projects, and determine whether the comprehensive project safety risk of the risk renovation project of the old community meets the requirements in combination with the risk control interval of the old community. If so, proceed to the next step; if not, determine that the old community is a safety supervision community;

[0048] The project safety risks of different renovation projects in the old community and the number of renovation projects are obtained, and the safety risks of the renovation of the old community are determined based on the comprehensive project safety risks of the risky renovation projects in the old community and the total number of construction workers in the old community.

[0049] It should be noted that the value range of the community renovation risk of the old community is between 0 and 1. When the community renovation risk of the old community does not meet the requirements, the old community will be treated as a safety supervision community.

[0050] In another possible embodiment, the method for determining the safety risk of the community reconstruction of the old community in the above step S2 is:

[0051] Determine the risk renovation projects of the renovation projects based on the project safety risks of different renovation projects, and judge whether the number of risk renovation projects of the old community meets the requirements. If so, proceed to the next step; if not, determine that the old community is a safety supervision community;

[0052] Determine the total number of construction personnel in the old community based on the number of construction personnel in different renovation projects, determine the risk control interval corresponding to the old community and the project risk threshold matched by the risk control interval according to the total number of construction personnel in the old community, determine the renovation projects of concern in the renovation projects by using the project risk threshold, and judge whether the number of renovation projects of concern in the old community meets the requirements. If so, proceed to the next step; if not, determine that the old community is a safety supervision community;

[0053] Determine the comprehensive project safety risks of the risk renovation projects in the old community according to the number of risk renovation projects in the old community and the project safety risks of different risk renovation projects; determine the comprehensive project safety risks of the focus renovation projects in the old community according to the number of focus renovation projects in the old community and the project safety risks of different focus renovation projects;

[0054] The project safety risks of different renovation projects in the old community and the number of renovation projects are obtained, and the safety risks of the community renovation of the old community are determined based on the comprehensive project safety risks of the risky renovation projects in the old community, the comprehensive project safety risks of the focus renovation projects and the total number of construction personnel in the old community.

[0055] In the present invention, the safety risks of the renovation of old communities are determined by the project safety risks of different renovation projects, so that the old communities with greater safety hazards can be screened out based on the differences in safety hazards of different renovation projects in different old communities, thereby avoiding the technical problem of greater analysis difficulty caused by the remote cloud platform monitoring and analyzing all old communities.

[0056] S2 determines the safety supervision community based on the safety risks of the community renovation of different old communities, identifies the safety violations of different renovation projects of different safety supervision communities through the monitoring data of the monitoring images of different safety supervision communities, and determines the monitoring safety risks of different renovation projects and risk renovation projects in combination with the safety monitoring communities of the renovation projects containing the safety violations;

[0057] It is understandable that the security violation behavior is determined based on the analysis results of the monitoring data of the monitoring image. Specifically, the security violation behavior in different monitoring images is determined through an image recognition model.

[0058] In one possible embodiment, the method for determining the monitoring safety risk of the transformation project in step S2 is:

[0059] S21: taking the security monitoring area of ​​the renovation project containing the security violation as the violation monitoring area, taking the security monitoring area containing the renovation project as the matching monitoring area, and judging whether there is a violation monitoring area in the renovation project. If so, proceed to the next step. If not, determining the monitoring security risk of the renovation project by presetting the security risk;

[0060] S22 determines the security violation types of different violation monitoring cells and the number of violations of security violation behaviors of different security violation types based on the identification results of security violation behaviors of different violation monitoring cells, and determines the security violation risks of different violation monitoring cells in combination with the number of violations of security violation behaviors of different security violation types in different violation monitoring cells;

[0061] S23 determines whether there is a violation monitoring community whose security violation risk does not meet the requirements. If yes, proceed to the next step; if no, proceed to step S25;

[0062] S24 determines whether the number of illegal monitoring cells whose security violation risk does not meet the requirement meets the requirement, if so, proceeds to the next step, if not, determines the monitoring security risk of the renovation project according to the number of illegal monitoring cells whose security violation risk does not meet the requirement;

[0063] S25 obtains the number of illegal monitoring cells whose security violation risks do not meet the requirements, and determines the monitoring security risk of the renovation project based on the security violation risks of different illegal monitoring cells, the number of illegal monitoring cells, and the proportion of the number of matching monitoring cells.

[0064] Further, judging whether the number of violation monitoring cells whose security violation risk does not meet the requirement meets the requirement specifically includes:

[0065] A threshold number of monitoring cells for violation of the renovation project whose security violation risk does not meet the requirement is determined based on the number of matching monitoring cells, and whether the number of monitoring cells for violation of the renovation project whose security violation risk does not meet the requirement is determined based on the threshold number of monitoring cells for violation of the renovation project.

[0066] In another possible embodiment, the method for determining the monitoring safety risk of the transformation project in the above step S2 is:

[0067] The security monitoring area of ​​the renovation project containing the security violation is used as the violation monitoring area, and the security monitoring area containing the renovation project is used as the matching monitoring area. When there is no violation monitoring area in the renovation project, the monitoring security risk of the renovation project is determined by presetting the security risk;

[0068] When there are illegal monitoring cells in the renovation project, determine whether the number of the matching monitoring cells is less than the preset number of monitoring cells. If so, determine the monitoring safety risk of the renovation project based on the number of the illegal monitoring cells and the number of matching monitoring cells. If not, proceed to the next step.

[0069] Determine the security violation types of different violation monitoring cells and the number of security violation violations of different security violation types based on the identification results of security violation behaviors of different violation monitoring cells, and determine the security violation risks of different violation monitoring cells in combination with the number of security violation violations of different security violation types of different violation monitoring cells;

[0070] The number of illegal monitoring cells whose security violation risk does not meet the requirement is obtained, and the monitoring security risk of the transformation project is determined based on the security violation risks of different illegal monitoring cells, the number of illegal monitoring cells, and the proportion of the number of matching monitoring cells.

[0071] In the present invention, by combining the actual situation of safety violations in different renovation projects to monitor safety risks of different renovation projects and determine risky renovation projects, it is possible to screen risky renovation projects with higher construction safety risks from the perspective of actual monitoring data, and also lays a foundation for combining actual data to realize specific assessment of safety risks of different old communities.

[0072] S3 determines the potential safety risks of different old communities by monitoring safety risks of different renovation projects and risk renovation projects, and determines risky supervision communities based on the potential safety risks, and monitors and manages safety violations in risky supervision communities and safety supervision communities through monitoring data from surveillance images.

[0073] In one possible embodiment, the method for determining the potential security risk of the old community in step S3 is:

[0074] When the number of risky renovation projects in the old residential area is greater than the preset number of projects, the old residential area is determined to be a risky supervision area;

[0075] When the number of risky renovation projects in the old residential area is not greater than the preset number of projects, the security monitoring area containing the renovation project is used as the matching monitoring area, and the weight values ​​of different renovation projects are determined by the number of matching monitoring areas of different renovation projects, and the risk weights and risk weights of the risky renovation projects in the old residential area are determined based on the weight values ​​of different risky renovation projects and the monitoring safety risks of different risky renovation projects;

[0076] When the risk weights of the risk renovation projects of the old residential area do not meet the requirements, the old residential area is determined to be a risk supervision area;

[0077] When the risk weights of the risk renovation projects in the old community meet the requirements, the monitored safety risks of different renovation projects in the old community and the number of renovation projects are obtained, and the potential safety risks of the old community are determined based on the risk weights of the risk renovation projects in the old community.

[0078] In another possible embodiment, the method for determining the potential security risk of the old community in step S1 is:

[0079] S31 determines whether the number of risky renovation projects in the old residential area is greater than the preset number of projects. If so, the old residential area is determined to be a risky supervision area. If not, proceed to the next step.

[0080] S32 uses the security monitoring area including the renovation project as the matching monitoring area, determines the weight values ​​of different renovation projects according to the number of matching monitoring areas of different renovation projects, and determines the modified monitoring safety risks of different risk renovation projects of the old community based on the weight values ​​of different risk renovation projects and the monitoring safety risks of different risk renovation projects, and determines whether the maximum value of the modified monitoring safety risk of the risk renovation project meets the requirements, if so, proceeds to step S34, if not, proceeds to the next step;

[0081] S33 determines the sum of risk weights of the risk renovation projects of the old community based on the weight values ​​of different risk renovation projects and the monitoring safety risks of different risk renovation projects, and judges whether the sum of risk weights of the risk renovation projects of the old community meets the requirements. If so, proceed to the next step; if not, determine that the old community is a risk supervision community;

[0082] S34 obtains the monitored safety risks of different renovation projects in the old community and the number of renovation projects, and determines the potential safety risks of the old community in combination with the risk weights of the risk renovation projects in the old community.

[0083] In the present invention, by evaluating the potential safety risks of different old communities and screening the risk supervision communities, it is possible to screen the old communities with higher potential safety risks from the perspective of actual safety supervision data, thereby avoiding the emergence of safety hazards caused by inadequate safety supervision of old communities with higher potential safety risks, and further improving the reliability of construction supervision in old communities.

[0084] Example 2

[0085] On the other hand, Figure 3 As shown, the present invention provides a smart management platform for the renovation of old residential areas, which adopts the above-mentioned smart management method for the renovation of old residential areas, and specifically includes:

[0086] Safety risk assessment module, risk project screening module, monitoring and management module;

[0087] The safety risk assessment module is responsible for obtaining renovation projects of different old communities, and determining the project safety risks of different renovation projects based at least on the safety risk factors of different renovation projects and the number of construction personnel, and determining the safety risks of the renovation of the old communities through the project safety risks of different renovation projects;

[0088] The risk project screening module is responsible for determining the safety supervision community based on the community renovation safety risks of different old communities, identifying the safety violations of different renovation projects of different safety monitoring communities through the monitoring data of the monitoring images of different safety supervision communities, and combining the safety monitoring communities of the renovation projects containing the safety violations to monitor the safety risks of different renovation projects and determine the risky renovation projects;

[0089] The monitoring and management module is responsible for determining the potential safety risks of different old communities through monitoring safety risks of different renovation projects and risk renovation projects, and determining risky supervision communities based on the potential safety risks, and monitoring and managing safety violations in risky supervision communities and safety supervision communities through monitoring data from surveillance images.

[0090] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the device, equipment, and non-volatile computer storage medium embodiments, since they are basically similar to the method embodiments, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.

[0091] The above is a description of a specific embodiment of the specification. Other embodiments are within the scope of the appended claims. In some cases, the actions or steps recorded in the claims can be performed in an order different from that in the embodiments and still achieve the desired results. In addition, the processes depicted in the drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.

[0092] The above description is only one or more embodiments of this specification and is not intended to limit this specification. For those skilled in the art, one or more embodiments of this specification may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of one or more embodiments of this specification shall be included in the scope of the claims of this specification.

Claims

1. A smart management method for the renovation of old residential areas, characterized in that: Specifically include: Obtaining renovation projects of different old residential communities, and determining the project safety risks of the different renovation projects based at least on the safety risk factors of the different renovation projects and the number of construction personnel, and determining the safety risks of the renovation of the old residential communities through the project safety risks of the different renovation projects; Determine the safety supervision community based on the safety risks of the community renovation of different old communities, identify the safety violations of different renovation projects of different safety supervision communities through the monitoring data of the monitoring images of different safety supervision communities, and determine the monitoring safety risks of different renovation projects and risk renovation projects in combination with the safety monitoring communities of the renovation projects containing the safety violations; Determine the potential safety risks of different old communities through monitoring safety risks of different renovation projects and risk renovation projects, determine risky supervision communities based on the potential safety risks, and monitor and manage safety violations in risky supervision communities and safety supervision communities through monitoring data of surveillance images; The method for determining the safety risk of the renovation of the old residential area is as follows: Determine the risk renovation projects of the renovation projects based on the project safety risks of different renovation projects, and judge whether the number of risk renovation projects of the old community meets the requirements. If so, proceed to the next step; if not, determine that the old community is a safety supervision community; Determine the total number of construction personnel in the old community based on the number of construction personnel in different renovation projects, determine the risk control interval corresponding to the old community based on the total number of construction personnel in the old community, and determine the quantity threshold of risk renovation projects in the old community based on the risk control interval, and determine whether the number of risk renovation projects in the old community meets the requirements through the quantity threshold, if yes, proceed to the next step, if not, determine that the old community is a safety supervision community; Determine the comprehensive project safety risk of the risk renovation project of the old community according to the number of risk renovation projects of the old community and the project safety risks of different risk renovation projects, and determine whether the comprehensive project safety risk of the risk renovation project of the old community meets the requirements in combination with the risk control interval of the old community. If so, proceed to the next step; if not, determine that the old community is a safety supervision community; Obtaining the project safety risks of different renovation projects in the old community and the number of renovation projects, and determining the community renovation safety risks of the old community in combination with the project comprehensive safety risks of the risky renovation projects of the old community and the total number of construction workers in the old community; The method for determining the monitoring safety risk of the transformation project is: S21: taking the security monitoring area of ​​the renovation project containing the security violation as the violation monitoring area, taking the security monitoring area containing the renovation project as the matching monitoring area, and judging whether there is a violation monitoring area in the renovation project. If so, proceed to the next step. If not, determining the monitoring security risk of the renovation project by presetting the security risk; S22 determines the security violation types of different violation monitoring cells and the number of violations of security violation behaviors of different security violation types based on the identification results of security violation behaviors of different violation monitoring cells, and determines the security violation risks of different violation monitoring cells in combination with the number of violations of security violation behaviors of different security violation types in different violation monitoring cells; S23 determines whether there is a violation monitoring community whose security violation risk does not meet the requirements. If yes, proceed to the next step; if no, proceed to step S25; S24 determines whether the number of illegal monitoring cells whose security violation risk does not meet the requirement meets the requirement, if so, proceeds to the next step, if not, determines the monitoring security risk of the renovation project according to the number of illegal monitoring cells whose security violation risk does not meet the requirement; S25: obtaining the number of illegal monitoring cells whose security violation risk does not meet the requirement, and determining the monitoring security risk of the transformation project based on the security violation risks of different illegal monitoring cells, the number of illegal monitoring cells, and the proportion of the number of matching monitoring cells; The method for determining the potential safety risks of the old residential area is as follows: S31 determines whether the number of risky renovation projects in the old residential area is greater than the preset number of projects. If so, the old residential area is determined to be a risky supervision area. If not, proceed to the next step. S32 uses the security monitoring area including the renovation project as the matching monitoring area, determines the weight values ​​of different renovation projects according to the number of matching monitoring areas of different renovation projects, and determines the modified monitoring safety risks of different risk renovation projects of the old community based on the weight values ​​of different risk renovation projects and the monitoring safety risks of different risk renovation projects, and determines whether the maximum value of the modified monitoring safety risk of the risk renovation project meets the requirements, if so, proceeds to step S34, if not, proceeds to the next step; S33 determines the sum of risk weights of the risk renovation projects of the old community based on the weight values ​​of different risk renovation projects and the monitoring safety risks of different risk renovation projects, and judges whether the sum of risk weights of the risk renovation projects of the old community meets the requirements. If so, proceed to the next step; if not, determine that the old community is a risk supervision community; S34: obtaining the monitored safety risks of different renovation projects in the old residential area and the number of renovation projects, and determining the potential safety risks of the old residential area in combination with the risk weights of the risk renovation projects in the old residential area; The method for determining the project safety risk of the transformation project is: Determine the number of high-risk safety factors and the number of general safety factors of the renovation project through the safety risk factors of the renovation project, and determine the risk factor assessment amount of the renovation project based on the number of high-risk safety factors and the number of general safety factors; The project safety risk of the renovation project is determined based on the risk factor assessment amount of the renovation project and the number of construction personnel.

2. The smart management method for renovation of old residential areas as claimed in claim 1 is characterized in that: The safety risk factors include object impact, falling from height, collapse risk, mechanical injury, and electrical safety.

3. The smart management method for renovation of old residential areas as claimed in claim 1 is characterized in that: The number of construction workers for the renovation project is determined according to the construction volume of the renovation project. Specifically, the construction volume interval that matches the construction volume is determined according to the construction volume of the renovation project, and the number of construction workers for the renovation project is determined through the construction volume interval.

4. The smart management method for renovation of old residential areas as claimed in claim 1 is characterized in that: The high-risk safety factors and general safety factors are determined based on the accident hazards and accident occurrence probabilities of the safety factors.

5. The smart management method for renovation of old residential areas as claimed in claim 1 is characterized in that: The high-risk safety factors and general safety factors are determined based on the matching results of the safety factors with a preset safety factor database.

6. The smart management method for renovation of old residential areas as claimed in claim 1 is characterized in that: The value range of the community renovation risk of the old community is between 0 and 1. When the community renovation risk of the old community does not meet the requirements, the old community will be used as a safety supervision community.

7. A smart management platform for the renovation of old residential areas, using a smart management method for the renovation of old residential areas as described in any one of claims 1 to 6, characterized in that: Specifically include: Safety risk assessment module, risk project screening module, monitoring and management module; The safety risk assessment module is responsible for obtaining renovation projects of different old communities, and determining the project safety risks of different renovation projects based at least on the safety risk factors of different renovation projects and the number of construction personnel, and determining the safety risks of the renovation of the old communities through the project safety risks of different renovation projects; The risk project screening module is responsible for determining the safety supervision community based on the community renovation safety risks of different old communities, identifying the safety violations of different renovation projects of different safety monitoring communities through the monitoring data of the monitoring images of different safety supervision communities, and combining the safety monitoring communities of the renovation projects containing the safety violations to monitor the safety risks of different renovation projects and determine the risky renovation projects; The monitoring and management module is responsible for determining the potential safety risks of different old communities through monitoring safety risks of different renovation projects and risk renovation projects, and determining risky supervision communities based on the potential safety risks, and monitoring and managing safety violations in risky supervision communities and safety supervision communities through monitoring data from surveillance images.