A method for constructing ballastless track slabs
By using multiple track panel hangers and template side bracing devices of different sizes, the problem of low equipment turnover efficiency in track slab construction was solved, achieving efficient track slab paving and quality control, and reducing construction costs.
Patent Information
- Application Number
- CN202410063113.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-16
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2044-01-16
AI Technical Summary
In existing technologies, track slab construction requires the use of large gantry cranes to transport construction equipment, resulting in low construction efficiency and high costs, especially affecting the progress when constructing in confined spaces.
Multiple rail panel hangers and formwork side support devices of different sizes are used. The side formwork is supported by the upper buckle beam, side support seat and bottom support, which reduces the space occupied by the support structure and realizes efficient laying of rail panels and equipment turnover by using rail panel hangers.
It improves construction efficiency, reduces construction costs, ensures the construction quality and precision of track slabs, and is suitable for various construction environments.
Smart Images

Figure CN117702552B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of railway track laying, and in particular to a method for constructing ballastless track slabs. Background Technology
[0002] The ballast slab concrete is a crucial component of the double-block ballastless track structure, and its performance significantly impacts the smoothness and durability of the track structure. The core challenges in ballast slab construction lie in the precise positioning and placement of sleepers and the accurate alignment of multiple rail panels. Currently, automated sleeper-separating platforms are primarily used for high-precision sleeper separation, followed by the installation of rails to form rail panels. Automatic fine-tuning equipment for double-block ballastless track is then used to fine-tune the formed rail panels, greatly improving the high-precision construction of long-distance tracks.
[0003] Chinese patent CN101413236A, published in the relevant technology, proposes a construction method for CRTSⅡ type double-block ballastless track slabs. This method includes the construction of the ballastless track support layer, installation of supports, installation of steel formwork track, laying of track slab reinforcement, pouring of track slab concrete, installation of sleepers, finishing, and curing. It utilizes a complete set of equipment for construction, featuring high mechanization, high construction efficiency, and a short construction cycle. The measurement technology is advanced, with strict measurement standards and high accuracy, allowing for quick and convenient on-site operation. It also allows for segmented laying, providing great flexibility in arranging the construction sequence of each section.
[0004] The aforementioned technologies have the following drawbacks: When pouring concrete for the track slab, side formwork and expansion joint partitions are required to form the concrete pouring space. Furthermore, to prevent bulging, numerous side supports are needed on the outside of the side formwork to meet its support requirements. However, this results in numerous diagonal braces along the track edge, significantly occupying the construction site and hindering the turnover efficiency of construction equipment such as the automatic sleeper distribution platform and the automatic fine-tuning equipment for ballastless track, thus significantly impacting construction efficiency. Using large gantry cranes to move various construction equipment or track panels not only increases construction costs but also complicates equipment turnover scheduling on the construction site, especially in confined spaces such as tunnels or culverts, which will affect the construction progress. Summary of the Invention
[0005] In order to improve the problems of the need to use large gantry cranes to transfer construction equipment and the impact of track panels on construction efficiency and cost in the existing track slab construction, this application provides a method for constructing ballastless track slabs.
[0006] The ballastless track slab construction method provided in this application adopts the following technical solution:
[0007] A method for constructing ballastless track slabs includes the following steps:
[0008] S1. Measure and lay out the track centerline and track centerline control points according to the designed track bed slab position;
[0009] S2. Reinforcing bar binding: Bind the bottom layer of reinforcing bars of the track bed slab according to the relevant contents of the ballastless track construction drawings, and use insulating clips for binding;
[0010] S3. Rail panel assembly: The sleepers are separated using an automatic sleeper-separating platform, and rails are installed on the sleepers to form rail panels. The rail panels are then transferred to the paving area using a rail panel lifting device.
[0011] S4. Coarse laying of the track panel: The elevation of the track panel is roughly adjusted using the track panel lifting device, and the rails on two adjacent track panels are connected with fishplates.
[0012] S5. Template installation: Install side templates and expansion joint partitions, drive anchor nails into the ground outside the side templates, and install template side support devices and template top fasteners to fix the side templates.
[0013] S6. Fine-tuning of the track panel: The track panel is fine-tuned using an automatic fine-tuning device for ballastless track.
[0014] S7. Concrete pouring: pour concrete continuously in one direction for each sleeper, allowing the concrete to flow naturally from one end of the sleeper to the other. After the concrete flows naturally from under the sleeper to the next sleeper, move forward to the next sleeper and continue pouring.
[0015] S8. Concrete curing.
[0016] Furthermore, the template side support device includes a side support base and a middle support member and a bottom support member installed on the side support base. The middle support member is used to support the middle part of the side template, and the bottom support member is used to support the bottom of the side template. The side support base is provided with a hole for engaging with the anchor nail.
[0017] Furthermore, the central support member includes a central support screw threaded through the upper part of the side support seat, and the central support screw is horizontally arranged; the bottom support member includes a bottom support block horizontally fixed to the central support member and a bottom support screw threaded through the bottom support block vertically.
[0018] Furthermore, the template fastening device includes an upper fastening beam that overlaps the top of the side template and is orthogonal to the extension direction of the side template. Fastening plates are fixed to the bottom of both ends of the upper fastening beam, and horizontally arranged upper fastening screws are threaded through the fastening plates.
[0019] Furthermore, the rail panel lifting device includes multiple gantry frames and longitudinal beams fixed between two adjacent gantry frames. The longitudinal beams are arranged along the extension direction of the side template. The span of the gantry frame is greater than the outer distance between two oppositely arranged template side support devices. The gantry frame is equipped with an electric hoist and a hanging rope. The bottom of the gantry frame is equipped with rollers.
[0020] It also includes multiple rail support beams arranged at intervals along the extension direction of the side template. Each rail support beam has an elevation adjusting screw threaded through both ends. An adjusting nut located at the lower end of the rail support beam is screwed onto the elevation adjusting screw. Both rails in the rail panel are installed on the rail support beams.
[0021] Furthermore, the rail panel hangers are provided in multiples, and at least one of the rail panel hangers can pass through the gantry of another rail panel hanger.
[0022] Furthermore, if the track panel is placed for more than 12 hours or the ambient temperature changes by more than 15°C after fine-tuning in step S6, the track panel needs to be readjusted. The adjustment is carried out in the order of "centerline first, then elevation". The eight adjacent sets of rail bearing beams on the two connected track panels are numbered 1 to 8 in sequence. Among them, rail bearing beams No. 4 and No. 5 are the two closest rail bearing beams of the two connected track panels. The elevation is adjusted in the order of 1→4→5→8→2→3→6→7→1→2→3→4→5→6→7→8.
[0023] Furthermore, when readjusting the next set of two docked rail sections, at least one rail-bearing beam corresponding to 8 to 10 sleepers from the previous set of rail sections is overlapped.
[0024] Furthermore, in step S7, during the pouring process, the concrete is poured back and forth in a zigzag pattern between the two-block sleepers, and manual vibration is used. Each pouring section is equipped with at least 4 immersion vibrators, and the vibrators are prevented from touching the rail panel during vibration.
[0025] Furthermore, in step S7, after the concrete has initially set, the adjusting nut on the elevation adjusting screw and the fishplate and rail fastener at the rail panel connection end are loosened to release the rail stress.
[0026] In summary, the beneficial technical effects of this application are as follows:
[0027] 1. By setting the upper buckle screw on the upper buckle beam and the middle support screw and bottom support screw on the side support seat, the space occupied by the side formwork support structure is greatly reduced. This allows the efficient laying of the rail panel and the turnover efficiency of various construction equipment to be achieved by using multiple rail panel lifting tools of different sizes in this application when hoisting and transferring the rail panel. This greatly improves construction efficiency, controls construction costs, and makes it easy for construction personnel to operate.
[0028] 2. After the track panel is finely adjusted, multiple rail-bearing beams are adjusted in a specific sequence, starting with the ends and then moving to the middle. On the one hand, this can prevent the rails from deforming under the weight of multiple sleepers due to excessive adjustment time, thus avoiding sleeper position shifts. On the other hand, when readjusting the track panel, it can ensure both the adjustment accuracy of the two adjacent rails and the alignment accuracy of the two rails after they are joined, thereby greatly improving the construction quality of the track bed slab. Attached Figure Description
[0029] Figure 1 This is a schematic diagram of the process flow of an embodiment of this application;
[0030] Figure 2 This is a schematic diagram of the track panel lifting device according to an embodiment of this application;
[0031] Figure 3 This is a schematic diagram of the structure of the track panel lifting device, the template side support device, and the template upper fastening device used in conjunction with each other according to an embodiment of this application;
[0032] Figure 4 yes Figure 3 A magnified view of part A in the middle;
[0033] Figure 5 yes Figure 3 A magnified view of part B in the diagram.
[0034] Explanation of reference numerals in the attached figures:
[0035] 1. Railway tracks;
[0036] 2. Side formwork;
[0037] 31. Side support; 311. Embedded hole; 32. Central support screw; 33. Bottom support block; 34. Bottom support screw;
[0038] 41. Upper buckle beam; 42. Buckle plate; 43. Upper buckle bolt;
[0039] 51. Gantry; 52. Longitudinal beam; 53. Roller;
[0040] 61. Rail support beam; 62. Elevation adjustment screw. Detailed Implementation
[0041] The technical solutions of this application will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this application. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0042] This application discloses a method for constructing ballastless track slabs. (Refer to...) Figure 1 , Figure 2 and Figure 3 A method for constructing ballastless track slabs includes the following steps:
[0043] S1. Measure and set out the line. According to the design position of the track slab, set out the center line of the line and the control points of the track center line. Use an ink line to mark the center line of the track. If it is a roadbed track slab, the edge line of the track slab also needs to be set out on the concrete surface of the base plate and the position of the edge line is marked with an ink line.
[0044] S2. Reinforcing bar binding: Bind the bottom layer of the track bed slab reinforcing bars according to the relevant contents of the ballastless track construction drawing, and use insulating clips for binding. Specifically, before binding, it is necessary to conduct measurement and layout, and set out and mark a track center control point every 10m along the track direction, and use this reference point to pop out the track center line and the longitudinal reinforcing bar edge line of the track bed slab.
[0045] S3. Rail panel assembly: The sleepers are separated using an automatic sleeper-separating platform, and rails 1 are installed on the sleepers using rail fasteners to form rail panels. The rail panels are then transferred to the paving area using a rail panel lifting device.
[0046] S4. Coarse laying of rail panels: The elevation of the rail panels is roughly adjusted using rail panel lifting equipment, and the rails 1 on two adjacent rail panels are connected with fishplates. After the coarse laying is completed, the rail panel lifting equipment continues to move the next set of rail panels to the next paving area to achieve continuous online paving.
[0047] S5. Template installation: Install side template 2 and expansion joint partition, drive anchor nails into the ground outside side template 2, and install template side support device and template top fastening device to fix side template 2.
[0048] S6. Track panel fine adjustment: The track panel is finely adjusted using automatic fine adjustment equipment for ballastless track.
[0049] S7. Concrete pouring: pour concrete continuously in one direction for each sleeper, allowing the concrete to flow naturally from one end of the sleeper to the other. After the concrete flows naturally from under the sleeper to the next sleeper, move forward to the next sleeper and continue pouring.
[0050] S8. Concrete curing: A "one geotextile, one membrane, one drip irrigation" method is used. After the concrete has initially set (approximately 3-4 hours after pouring), first cover it with geotextile, then install three drip irrigation pipes, and finally cover it with plastic film. After final setting (i.e., when the concrete turns white, approximately 7-10 hours after pouring), connect branch water pipes to drip irrigation tape for curing. The curing time should be no less than 7 days.
[0051] Among them, reference Figure 3 and Figure 5The template side support device includes a side support base 31 and a middle support member and a bottom support member installed on the side support base 31. The middle support member is used to support the middle part of the side template 2, and the bottom support member is used to support the bottom of the side template 2. The side support base 31 is provided with a hole 311 for engaging with the anchor nail. Specifically, the middle support member includes a middle support screw 32 threaded through the upper part of the side support base 31. The middle support screw 32 is horizontally arranged, and its free end abuts against the outer wall of the middle part of the side template 2. The bottom support member includes a bottom support block 33 horizontally fixed to the middle support member and a bottom support screw 34 threaded through the bottom support block 33 vertically. The free end of the bottom support screw 34 abuts against the bottom end of the side template 2.
[0052] Furthermore, referring to Figure 3 and Figure 4 The template fastening device includes an upper fastening beam 41 that overlaps the top of the side template 2 and is orthogonal to the extension direction of the side template 2. Both ends of the upper fastening beam 41 are fixed to the bottom of the fastening plate 42. A horizontally arranged upper fastening screw 43 is threaded through the fastening plate 42. The free end of the upper fastening screw 43 abuts against the upper outer wall of the side template 2.
[0053] Additionally, refer to Figure 2 and Figure 3 The track panel lifting device includes multiple gantry frames 51 and longitudinal beams 52 fixed between two adjacent gantry frames 51. The longitudinal beams 52 are arranged along the extension direction of the side formwork 2 and two are arranged at both ends of the span direction of the gantry frame 51. The span of the gantry frame 51 is greater than the outer distance between the two oppositely arranged formwork side support devices. The gantry frame 51 is equipped with an electric hoist and a hanging rope, and the bottom of the gantry frame 51 is equipped with rollers 53.
[0054] The track panel lifting device also includes multiple rail-bearing beams 61 arranged sequentially at intervals along the extension direction of the side template 2. Both ends of the rail-bearing beams 61 are equipped with elevation adjusting screws 62, and adjusting nuts located at the lower end of the rail-bearing beams 61 are screwed onto the elevation adjusting screws 62. Both rails 1 in the track panel are installed on the rail-bearing beams 61. Two slots for the rails 1 to pass through are opened on the rail-bearing beams 61. Mounting plates are fixed to the two opposite sides of the slots along the length direction of the rail-bearing beams 61. Two fishplates are set between the two opposite mounting plates. The rails 1 are bolted and fixed to the rail-bearing beams 61 by the two fishplates and the two mounting plates located on both sides of its length direction.
[0055] In actual construction, multiple rail panel lifting devices are set up, and at least one rail panel lifting device can pass through the gantry 51 of another rail panel lifting device. That is, at least two sets of rail panel lifting devices of different sizes are set up on the construction site, and one rail panel lifting device can pass through the other rail panel lifting device without being interfered with by the formwork side support device.
[0056] With this setup, during the construction of the track bed slab, after the track panels are assembled, a set of track panels is fixed to a set of multiple rail-bearing beams 61, and then hoisted using an electric hoist and slings on the gantry 51. Subsequently, the track panels are moved to the paving area using rollers 53 on the gantry 51. The adjusting nuts on the elevation adjusting screws 62 at both ends of the rail-bearing beams 61 are adjusted to the appropriate dimensions for the current construction. The track panels are then lowered to the ground, and after the rail-bearing beams 61 are leveled, the two rails 1 that are connected to each other on adjacent track panels are connected using fishplates. In this way, the initial installation of multiple track panels can be achieved.
[0057] Furthermore, by utilizing multiple track panel lifting devices of different sizes, the next track panel can be lifted and transferred immediately after the previous track panel is roughly laid. The upper locking bolt 43 on the upper locking beam 41 supports the upper part of the side formwork 2, the middle support bolt 32 on the side support seat 31 supports the middle part of the side formwork 2, and the bottom support bolt 34 on the side support seat 31 supports the bottom of the side formwork 2. This effectively secures the side formwork 2 to prevent bulging and ensures the quality of the track bed slab pouring. In addition, the side support seat 31 is fixed with anchor bolts, which significantly reduces the space occupied by the side formwork 2 support structure compared to conventional side support setups. This allows for efficient track panel laying and improved equipment turnover efficiency using only the multiple track panel lifting devices of different sizes available in this application, greatly improving construction efficiency, controlling construction costs, and facilitating convenient operation for construction personnel.
[0058] In addition, during actual construction, if the track panels placed for more than 12 hours after fine-tuning in step S6 or if the ambient temperature changes by more than 15°C, the track panels need to be readjusted. The adjustment should be performed according to the principle of "centerline first, then elevation." Specifically, the eight adjacent sets of rail bearing beams 61 on the two connected track panels are numbered sequentially from 1 to 8, with rail bearing beam 61 No. 1 located on the side closest to the already constructed track slab. Rail bearing beams 61 No. 4 and No. 5 are the two closest rail bearing beams 61 between the two connected track panels. The elevation is adjusted in the order 1→4→5→8→2→3→6→7→1→2→3→4→5→6→7→8. Furthermore, when readjusting the next set of two connected track panels, at least one rail bearing beam 61 corresponding to the 8-10 sleepers in the previous set of track panels should be overlapped.
[0059] Therefore, on the one hand, it can avoid the deformation of rail 1 under the gravity of multiple sleepers after the track panel adjustment time is too long, which would cause the sleeper position to shift; on the other hand, when readjusting the track panel, adjusting multiple rail bearing beams 61 in a specific order, first the ends and then the middle, can ensure the adjustment accuracy of the two adjacent rails 1 themselves, as well as the alignment accuracy of the two rails 1 after they are joined, thereby greatly improving the construction quality of the track bed slab.
[0060] Meanwhile, in step S7, during pouring, the concrete is poured back and forth in a zigzag pattern between the double-block sleepers, and manual vibration is used. Each pouring section is equipped with at least four immersion vibrators. During vibration, avoid touching the rail panel with the vibrators, and use a quick insertion and slow withdrawal method. The vibration spacing is controlled at approximately 50cm. The vibration duration is based on ensuring the concrete does not settle and is uniform and dense; over-vibration and under-vibration must be avoided. During the pouring process, the concrete at the bottom of the sleepers should be vibrated more intensely. Two types of vibrators are used for concrete vibration: a Φ50 vibrator is used vertically up and down at multiple points in the middle of the track slab for initial vibration, and rushing the material is strictly prohibited. After the initial leveling of the concrete, a Φ30 vibrator is used for secondary vibration around the sleepers. This promotes the compaction of the concrete before it sets, ensuring the quality of the track slab.
[0061] Furthermore, after the concrete has initially set in step S7, the elevation adjusting screw 62 and the fishplate and rail fasteners at the rail panel connection end are loosened to release the stress on rail 1 and ensure the installation stability of the sleeper. Specifically, after the concrete has initially set, the adjusting nut on the elevation adjusting screw 62 is loosened by 1 / 4 to 1 / 2 turn (1 to 2 mm), and the fishplate bolts are loosened at the same time to put the rail in a relaxed state. About 2 hours after loosening the adjusting nut on the elevation adjusting screw 62, all rail fasteners are loosened.
[0062] The implementation principle of the ballastless track slab construction method in this application embodiment is as follows:
[0063] During the construction of the track bed slab, the use of multiple track panel lifting devices of different sizes allows for the hoisting and transfer of the next track panel immediately after the previous one has been roughly laid. Furthermore, the upper locking bolt 43 on the upper locking beam 41 supports the upper part of the side formwork 2, the middle support bolt 32 on the side support seat 31 supports the middle part of the side formwork 2, and the bottom support bolt 34 on the side support seat 31 supports the bottom of the side formwork 2. This effectively secures the side formwork 2 to prevent bulging and ensures the quality of the track bed slab pouring. In addition, the side support seat 31 is fixed with anchor bolts, significantly reducing the space occupied by the side formwork 2 support structure compared to conventional side support setups. This allows for efficient track panel laying and improved equipment turnover efficiency using only the multiple track panel lifting devices of different sizes described in this application, greatly improving construction efficiency, controlling construction costs, and facilitating convenient operation for construction personnel.
[0064] Unless otherwise defined, the technical or scientific terms used in this application shall have the ordinary meaning understood by one of ordinary skill in the art to which this application pertains. The terms "first," "second," "third," and similar terms used in this application specification and claims do not indicate any order, quantity, or importance, but are merely used to distinguish different components. The terms "an" or "a" and similar terms do not indicate a quantity limitation, but rather indicate the presence of at least one. The terms "comprising" or "including" and similar terms mean that the elements or objects preceding "comprising" or "including" encompass the elements or objects listed following "comprising" or "including" and their equivalents, and do not exclude other elements or objects. "Above," "below," "left," "right," etc., are used only to indicate relative positional relationships; when the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0065] The above are all preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.
Claims
1. A method for constructing ballastless track slabs, characterized in that, Includes the following steps: S1. Measure and lay out the track centerline and track centerline control points according to the designed track bed slab position; S2. Reinforcing bar binding: Bind the bottom layer of reinforcing bars of the track bed slab according to the relevant contents of the ballastless track construction drawings, and use insulating clips for binding; S3. Rail panel assembly: using an automatic sleeper-splitting platform to split sleepers, and installing rails (1) on the sleepers to form rail panels, and using rail panel lifting equipment to transfer the rail panels to the paving area; S4. The rail panel is roughly laid, and the elevation of the rail panel is roughly adjusted by the rail panel lifting device, and the rails (1) on the two adjacent rail panels are connected by fishplates. S5. Template installation: Install side template (2) and expansion joint partition. Drive anchor nails into the ground outside the side template (2) and install template side support device and template top buckle device to fix the side template (2). S6. Fine-tuning of the track panel: The track panel is fine-tuned using an automatic fine-tuning device for ballastless track. S7. Concrete pouring: pour concrete continuously in one direction for each sleeper, allowing the concrete to flow naturally from one end of the sleeper to the other. After the concrete flows naturally from under the sleeper to the next sleeper, move forward to the next sleeper and continue pouring. S8. Concrete curing; The template side support device includes a side support base (31) and a middle support member and a bottom support member installed on the side support base (31). The middle support member is used to support the middle part of the side template (2), and the bottom support member is used to support the bottom of the side template (2). The side support base (31) is provided with a hole (311) for engaging with the anchor nail. The central support member includes a central support screw (32) threaded through the upper part of the side support seat (31), and the central support screw (32) is horizontally arranged; the bottom support member includes a bottom support block (33) horizontally fixed to the central support member and a bottom support screw (34) threaded through the bottom support block (33) vertically; The template fastening device includes an upper fastening beam (41) that overlaps the top of the side template (2) and is orthogonal to the extension direction of the side template (2). The bottom of both ends of the upper fastening beam (41) is fixed with a fastening plate (42). A horizontally arranged upper fastening screw (43) is threaded through the fastening plate (42). The rail panel lifting device includes multiple gantry frames (51) and longitudinal beams (52) fixed between two adjacent gantry frames (51). The longitudinal beams (52) are arranged along the extension direction of the side template (2). The span of the gantry frame (51) is greater than the outer distance between two oppositely arranged template side support devices. The gantry frame (51) is equipped with an electric hoist and a hanging rope. The bottom of the gantry frame (51) is equipped with rollers (53). It also includes multiple rail support beams (61) arranged at intervals along the extension direction of the side template (2), each rail support beam (61) having an elevation adjustment screw (62) threaded through both ends, and an adjustment nut located at the lower end of the rail support beam (61) screwed onto the elevation adjustment screw (62); both rails (1) in the rail panel are installed on the rail support beams (61); The rail panel lifting device is provided in multiple ways, and at least one of the rail panel lifting devices can pass through the gantry (51) of another rail panel lifting device.
2. The method for constructing ballastless track slabs according to claim 1, characterized in that, If the track panel is placed for more than 12 hours or the ambient temperature changes by more than 15°C after fine-tuning in step S6, the track panel needs to be readjusted. The adjustment is carried out in the order of "centerline first, then elevation". The eight adjacent sets of rail bearing beams (61) on the two connected track panels are numbered 1 to 8 in sequence. Among them, rail bearing beams (61) No. 4 and rail bearing beams (61) No. 5 are the two rail bearing beams (61) that are closest to the two connected track panels. When adjusting the elevation, the adjustment is carried out in the order of 1→4→5→8→2→3→6→7→1→2→3→4→5→6→7→8.
3. The method for constructing ballastless track slabs according to claim 2, characterized in that, When readjusting the next set of two docked rail panels, at least one rail bearing beam (61) corresponding to 8 to 10 sleepers in the previous set of rail panels is overlapped.
4. The method for constructing ballastless track slabs according to claim 1, characterized in that, In step S7, the concrete is poured back and forth in a zigzag pattern between the two-block sleepers, and manual vibration is used. Each pouring section is equipped with at least 4 immersion vibrators. During vibration, the vibrators should be kept away from touching the rail panel.
5. The method for constructing ballastless track slabs according to claim 1, characterized in that, After the concrete has initially set in step S7, loosen the adjusting nut on the elevation adjusting screw (62) and the fishplate and rail fastener at the rail panel docking end to release the stress on the rail (1).
Citation Information
Patent Citations
CRTS II type double-block type non-fragment rail bed board construction method
CN101413236A
Heavy haul railway elastic supporting block type ballastless track construction device and construction method
CN104233909A
Construction tool for ballastless track base plate apron slope
CN209194250U