A method for real-time determination of the elevation of a steel girder cable-stayed bridge during cantilever construction
By decomposing the pre-lifting value during construction and establishing the component quality relationship, the cantilever construction elevation of the steel beam cable-stayed bridge can be calculated in real time, solving the problem of difficulty in accurately determining the elevation during construction and improving construction accuracy.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- JSTI GRP INSPECTION & CERTIFICATION CO LTD
- Filing Date
- 2024-01-02
- Publication Date
- 2026-05-29
AI Technical Summary
In the cantilever construction of steel girder cable-stayed bridges, existing technologies make it difficult to accurately determine the construction elevation in real time, resulting in large errors after the structure is installed and making it difficult to match the design alignment.
By decomposing the pre-lift value into multiple parts and establishing the relationship between the mass of each component, the construction elevation is calculated in real time using simple multiplication and addition operations. This includes decomposing the pre-lift value and deformation on the left and right sides, and calculating the actual elevation in combination with the design elevation.
It enables real-time and accurate calculation of elevation during on-site installation, improves the precision of structural elevation control, and reduces construction errors.