A pre-embedded kit for a large-adjustment slab track jack and its construction method
By using pre-embedded kits to fix the jacks in the ballastless track, the problems of imperfect jack placement and adhesion were solved, achieving stability and safety during large track height adjustments and reducing construction and maintenance costs.
Patent Information
- Application Number
- CN202311703273.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-12
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2043-12-12
AI Technical Summary
In the existing technology, the way jacks are arranged in ballastless tracks is not perfect, and there is a lack of measures to prevent concrete from sticking to the jacks, which makes it impossible to meet the demand for large track height adjustments and affects train operation safety.
The large-adjustment plate-type ballastless track jack pre-embedded kit is adopted, including components such as foundation sleeve, fixed cover plate, fixed frame, and oil pipe sleeve. The position is fixed by pouring concrete, and buffer material is set in the sleeve to protect the jack and ensure its stability and sealing.
It effectively secures and protects the jacks, ensuring stable operation of the track under large adjustments, reducing construction costs, and facilitating operation and maintenance.
Smart Images

Figure CN117822354B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of railway track settlement adjustment technology, and more specifically to a pre-embedded kit for a large-adjustment slab track ballastless track and its construction method. Background Technology
[0002] Ballastless tracks are affected by various factors such as environment and load during their service life. In some sections with large deformation, significant foundation settlement deformation can occur, affecting track smoothness and endangering train operation safety. Since the height adjustment range of the fastening system is limited and cannot meet the requirements for large height adjustments, a new technology for large-scale height adjustment ballastless tracks has emerged, based on the CRTSⅢ type slab ballastless track structure. This technology adds jacks to the existing CRTSⅢ type slab ballastless track base plate. The jacks are located below the self-compacting concrete layer and can lift the self-compacting concrete layer and a series of components above it, compensating for track settlement and thus enabling continuous large-scale track lifting operations. However, the jack placement method and device are not yet perfect, and there is a lack of preventative measures to prevent the concrete from adhering to the jacks during base plate pouring. In order to provide good protection for the jacks during the service life of the ballastless track, a simpler, more precise, and safer jack placement solution for large-adjustment slab ballastless track is needed. Summary of the Invention
[0003] The purpose of this invention is to provide a pre-embedded kit for a large-adjustment slab track jack and a construction method thereof, in order to solve the technical problems existing in the background art.
[0004] To achieve the above objectives, the present invention adopts the following technical solution:
[0005] A pre-embedded kit for a large-adjustment slab-type ballastless track jack includes:
[0006] A base sleeve is placed inside the ballastless track base plate mold; the base sleeve has an installation cavity for fixing the jack.
[0007] A fixed cover plate, which is detachably connected to the top of the base sleeve;
[0008] A fixing frame is used to pre-fix the fixing cover plate to the side mold of the base plate; the position of the fixing foundation sleeve is achieved by pouring concrete for the base plate.
[0009] The oil pipe sleeve is connected to the bottom of the foundation sleeve and is cast inside the base plate. It is used to reserve the position of the oil pipe for the jack inside the base plate.
[0010] In some embodiments, the fixing frame is connected to the base plate side mold by a bolt fixing device, the bolt fixing device including a U-shaped clamp and a bolt for locking.
[0011] In some embodiments, the system further includes a lifting sleeve, which is slidably disposed within the mounting cavity of the base sleeve, and the top of the base sleeve has a top cover for covering the opening of the mounting cavity, and the lifting sleeve has a receiving cavity for accommodating a jack.
[0012] In some embodiments, cushioning material is evenly distributed on the inner wall of the base sleeve and below the top cover of the lifting sleeve.
[0013] In some embodiments, the tubing sleeve is further provided with a movably connected tubing sleeve cap.
[0014] This embodiment also provides a construction method for a large-adjustment slab track jack pre-embedded kit, including the following steps:
[0015] S1. The oil pipe sleeve and the foundation sleeve are welded together during prefabrication. The jack is placed inside the foundation sleeve, and the oil pipe is connected to the jack through the oil pipe sleeve. The oil pipe sleeve cover is fastened to the oil pipe sleeve.
[0016] S2. Determine the position of the fixing clip by measurement, install the fixing clip on the side mold of the base plate, tighten the bolts of the fixing clip to fix it, and then measure to confirm that the position is correct.
[0017] S3. Close and fix the fixing cover plate on the fixing clamp to the foundation sleeve. The fixing cover plate should be level with the base plate. Check whether the foundation sleeve is well sealed.
[0018] S4. Pour the base plate concrete. After the base plate is poured and formed, check whether the position of the foundation sleeve is correct.
[0019] S5. Loosen the bolts of the fixing clamp, separate the fixing cover plate from the base sleeve, and leave the base sleeve inside the base plate;
[0020] S6. Install the lifting sleeve, close it with the foundation sleeve, and check if the seal is good.
[0021] S7. Use a manual hydraulic pump to check the lifting and lowering of the jack to ensure that the jack can work normally, and finally reset it.
[0022] In step S2, the fixing clip is installed on the side mold of the base plate, and its position should be aligned with the center of the groove of the base plate.
[0023] In step S3, it is necessary to ensure that the fixed cover plate 5 and the base sleeve 1 are completely closed without any gaps.
[0024] The beneficial effects of this invention compared to the prior art are:
[0025] This invention provides excellent fixation and protection for pre-embedded jacks in slab track with large adjustment ranges, offering a streamlined process from layout and installation to use. The invention features a stable structure, rational connections between components, and tight contact between the kit, base plate, and jacks, ensuring optimal performance throughout its service life. Its simple structure facilitates operation, and the reusable fixing clips and covers contribute to its low cost and widespread adoption. Attached Figure Description
[0026] Figure 1 This is a schematic diagram of the basic sleeve of the present invention;
[0027] Figure 2 This is a schematic diagram of the lifting sleeve of the present invention;
[0028] Figure 3 This is a schematic diagram of the oil pipe sleeve of the present invention;
[0029] Figure 4 This is a schematic diagram of the fixing cover plate and fixing clip of the present invention;
[0030] Figure 5 This is a schematic diagram of the combination of the basic sleeve and the lifting sleeve of the present invention;
[0031] Figure 6 This is a schematic diagram of the structure of the basic sleeve and lifting sleeve combination of the present invention;
[0032] Figure 7 This is a schematic diagram of the pre-embedded kit for the large adjustment plate ballastless track jack of the present invention.
[0033] Figure 8 This is a schematic diagram of the pre-embedded kit for the large adjustment plate ballastless track jack of the present invention;
[0034] Figure 9 This is a schematic diagram showing the cooperation between the fixing clip and the side mold of the base plate of the present invention;
[0035] Figure 10 and Figure 11 All of these are schematic diagrams of the base plate with the jack pre-embedded in the present invention;
[0036] In the above attached figures: 1-base sleeve, 2-lifting sleeve, 3-oil pipe sleeve, 4-fixing clamp, 5-fixing cover plate, 6-oil pipe sleeve cover, 7-base plate side mold, 8-base plate. Detailed Implementation
[0037] To make the objectives, technical solutions, and advantages of this application clearer, the technical solutions in the embodiments of this application will be described in more detail below with reference to the accompanying drawings. In the drawings, the same or similar reference numerals denote the same or similar components or components having the same or similar functions throughout. The described embodiments are some, but not all, of the embodiments of this application. The embodiments described below with reference to the accompanying drawings are exemplary and intended to explain this application, and should not be construed as limiting this application. All other embodiments obtained by those skilled in the art based on the embodiments of this application without creative effort are within the scope of protection of this application.
[0038] The embodiments of this application will now be described in detail with reference to the accompanying drawings.
[0039] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, an indirect connection through an intermediate medium, or the internal communication of two components or the interaction between two components. Those skilled in the art can understand the specific meaning of the above terms in this application according to the specific circumstances.
[0040] In the description of this application, it should be understood that the terms "upper", "lower", "front", "back", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the accompanying drawings, and are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this application.
[0041] Furthermore, the terms “comprising” and “having”, and any variations thereof, are intended to cover non-exclusive inclusion, such that a process, method, system, product, or display that includes a series of steps or units is not necessarily limited to those steps or units that are explicitly listed, but may include other steps or units that are not explicitly listed or that are inherent to such process, method, product, or display.
[0042] The following will combine Figures 1-11 This application provides a detailed description of a large-adjustment slab track jack pre-embedded kit and construction method, as described in the embodiments of this application. It is worth noting that the following embodiments are merely for explaining this application and do not constitute a limitation thereof.
[0043] Example 1:
[0044] See Figure 1-11The diagram shown is a schematic representation of a specific embodiment of the present invention. A pre-embedded kit for a large-adjustment slab-type ballastless track jack consists of a foundation sleeve 1, a lifting sleeve 2, an oil pipe sleeve 3, a fixing clamp 4, a fixing cover plate 5, and an oil pipe sleeve cover 6.
[0045] The foundation sleeve is used to fix the position of the jacks inside the ballastless track base plate, and also to accommodate and protect the lifting sleeve and the jacks. Four sleeves are installed on the base plate.
[0046] The lifting sleeve can be integrated with the foundation sleeve to protect the jack piston during jacking and prevent concrete from flowing into the foundation sleeve and sticking to the jack when pouring the upper level after jacking.
[0047] The oil pipe sleeve is connected to the bottom of the foundation sleeve and is cast inside the base plate. It is used to reserve the position of the oil pipe in the base plate and to protect the jack oil pipe.
[0048] One end of the fixing clamp is a bolt fixing device for securing it to the side mold of the base plate, and the other end is connected to the fixing cover plate. The bolt fixing device includes a U-shaped clamp and a bolt for locking. The fixing clamp is connected and fixed to the side mold of the base plate through the U-shaped clamp and the bolt. This ensures that the fixing cover plate is level with the base plate and its position remains unchanged.
[0049] The fixing cover plate is used to fix the foundation sleeve and ensure that the position of the foundation sleeve in the base plate remains unchanged.
[0050] The oil pipe sleeve cap is used to seal the oil pipe sleeve and prevent dust, moisture and other substances from entering.
[0051] The foundation sleeve is placed inside the ballastless track base plate mold. The position of the foundation sleeve is fixed by pouring concrete for the base plate. The foundation sleeve can be closed with the lifting sleeve as one unit. The space inside the sleeve is reserved to be the same size as the jack. The foundation sleeve is on the outside and the lifting sleeve is on the inside. They can slide against each other to lift the jack.
[0052] The jack is placed inside the foundation sleeve, and then the lifting sleeve is installed. Cushioning material is evenly distributed on the inner sides of both sleeves, specifically on the inner wall of the foundation sleeve and under the top cover of the lifting sleeve. The cushioning material can be rubber pads. This ensures good sealing and protects the jack from damage under complex environments and train loads.
[0053] The oil pipe sleeve is connected to the foundation sleeve, extends out from the side of the base plate, and is cast into the base plate. The oil pipe extends into the sleeve through the oil pipe sleeve and connects to the jack cylinder to realize oil injection and lifting.
[0054] When the jack is raised and lowered, the lifting sleeve moves together with the jack piston, which can provide good protection for the jack during its service life. The structure is stable and the manufacturing and maintenance costs are low.
[0055] The fixing clamp and fixing cover plate are used to fix the position of the foundation sleeve and prevent the foundation sleeve from moving during the pouring of the base plate. The bolts of the fixing clamp are used to tightly connect with the side mold of the base plate. The fixing cover plate has a ring of sealing material, which can be locked with the foundation sleeve to prevent concrete from entering the base plate.
[0056] The oil pipe sleeve cap also has a ring of sealing material to seal the oil pipe sleeve and prevent dust and other dirt from entering.
[0057] In this embodiment, the combination of the manual hydraulic pump, jack, and oil pipe, if used individually, is considered existing technology and will not be discussed further here. Besides using a manual hydraulic pump to control the lifting and lowering of the jack, a one-button automatic control jack can also be selected.
[0058] In this embodiment, the number of jacks in a ballastless track is designed to be 4, and they are evenly arranged in the base plate.
[0059] Example 2;
[0060] See Figure 1-11 As shown, a construction method for a pre-embedded kit for a large-adjustment slab track jack includes the following steps:
[0061] S1. The oil pipe sleeve 3 and the foundation sleeve 1 are welded together in the factory during prefabrication. The jack is placed in the foundation sleeve 1, and the oil pipe is connected to the jack through the oil pipe sleeve 3. The oil pipe sleeve cover 6 is fastened to the oil pipe sleeve 3.
[0062] S2. Determine the position of the fixing clip 4 by measurement, install the fixing clip 4 on the side mold 7 of the base plate, tighten the bolts of the fixing clip 4 to fix it, and then measure to confirm that the position is correct.
[0063] S3. Close and fix the fixing cover plate 5 on the fixing clamp 4 to the base sleeve 1. The fixing cover plate 5 is level with the base plate 8. Check whether the base sleeve 1 is well sealed.
[0064] S4. Pour concrete for base plate 8. After base plate 8 is poured and formed, check whether the position of foundation sleeve 1 is correct.
[0065] S5. Loosen the fixing clamp bolt 4 to separate the fixing cover plate 5 from the base sleeve 1. The base sleeve 1 remains inside the base plate 8.
[0066] S6. Install the lifting sleeve 2 and close it with the foundation sleeve 1. Check that the seal is good.
[0067] S7. Use a manual hydraulic pump to check the lifting and lowering of the jack to ensure that the jack can work normally, and finally reset it.
[0068] In step S1 of this embodiment, the oil pipe is inside the oil pipe sleeve 3 and connected to the hydraulic cylinder of the jack. The operation is a normal jack oil pipe connection scheme, which will not be described in detail here.
[0069] In step S2 of this embodiment, the fixing clip 4 is installed on the side mold 7 of the base plate, and its position should be aligned with the center of the groove of the base plate 8.
[0070] In step S3 of this embodiment, it is necessary to ensure that the fixed cover plate 5 and the base sleeve 1 are completely closed without any gaps.
[0071] In step S4 of this embodiment, it is necessary to ensure that the position of the foundation sleeve 1 remains unchanged during the pouring process, so as to ensure that the distance from the center of the foundation sleeve 1 to the end of the base plate 8 is 910mm and the distance to the side of the base plate 8 is 500mm.
[0072] In step S5 of this embodiment, the fixing clip 4 and the fixing cover plate 5 can be reused after being separated.
[0073] In step S6 of this embodiment, it should be ensured that the lifting sleeve 2 and the base sleeve 1 are completely closed without any gaps.
[0074] In step S7 of this embodiment, the use of a manual hydraulic pump to raise and lower the jack is existing technology and will not be described further here.
[0075] The above description is merely a preferred embodiment of the present invention and is intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A pre-embedded kit for a large-adjustment slab-type ballastless track jack, characterized in that, include: A base sleeve is placed inside the ballastless track base plate mold; the base sleeve has an installation cavity for fixing the jack. A fixed cover plate, which is detachably connected to the top of the base sleeve; A fixing frame is used to pre-fix the fixing cover plate to the side mold of the base plate; the position of the fixing foundation sleeve is achieved by pouring concrete for the base plate. Oil pipe sleeve, which is connected to the bottom of the foundation sleeve and is cast into the base plate, is used to reserve the position of the oil pipe for the jack in the base plate. The fixing frame is connected to the side mold of the base plate by a bolt fixing device, which includes a U-shaped clamp and a bolt for locking. It also includes: a lifting sleeve, which is slidably disposed in the mounting cavity of the base sleeve, and the top of the base sleeve has a top cover for covering the opening of the mounting cavity, and the lifting sleeve is provided with a receiving cavity for accommodating a jack. Buffer material is evenly distributed on the inner wall of the base sleeve and below the top cover of the lifting sleeve; The tubing sleeve is also equipped with a movable tubing sleeve cap.
2. A construction method for a pre-embedded kit for a large-adjustment slab track jack as described in claim 1, characterized in that, Includes the following steps: S1. The oil pipe sleeve and the foundation sleeve are welded together during prefabrication. The jack is placed inside the foundation sleeve, and the oil pipe is connected to the jack through the oil pipe sleeve. The oil pipe sleeve cover is fastened to the oil pipe sleeve. S2. Determine the position of the fixing clip by measurement, install the fixing clip on the side mold of the base plate, tighten the bolts of the fixing clip to fix it, and then measure to confirm that the position is correct. S3. Close and fix the fixing cover plate on the fixing clamp to the base sleeve. The fixing cover plate should be level with the base plate. Check whether the base sleeve is well sealed. S4. Pour the base plate concrete. After the base plate is poured and formed, check whether the position of the foundation sleeve is correct. S5. Loosen the bolts of the fixing clamp, separate the fixing cover plate from the base sleeve, and leave the base sleeve inside the base plate; S6. Install the lifting sleeve, close it with the foundation sleeve, and check if the seal is good. S7. Use a manual hydraulic pump to check the lifting and lowering of the jack to ensure that the jack can work normally, and finally reset it.
3. The construction method of the large adjustment range slab ballastless track jack pre-embedded kit according to claim 2, characterized in that, In step S2, the fixing clip is installed on the side mold of the base plate, and its position should be aligned with the center of the groove of the base plate.
4. The construction method of a large-adjustment slab track jack pre-embedded kit according to claim 2, characterized in that, In step S3, it is necessary to ensure that the fixed cover plate and the base sleeve are completely closed without any gaps.
Citation Information
Patent Citations
Large-adjustment-amount plate type ballastless track
CN211006164U
Drilling device and mounting device for pre-embedded sleeve of ballastless track
CN216474294U