Electric vehicle charging and discharging scheduling methods, devices, equipment, and storage media
By determining the status information and priority indicators of electric vehicles, and adopting orderly charging or bidirectional charging and discharging strategies, the problem of electric vehicle charging and discharging scheduling is solved, the grid load balance is optimized, and power quality and energy efficiency are improved.
Patent Information
- Application Number
- CN202311811527.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-26
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-12-26
AI Technical Summary
How to effectively schedule the charging and discharging of electric vehicles to solve the problems of grid overload, power quality degradation, and energy efficiency reduction caused by large-scale electric vehicle deployment.
By determining the status information of electric vehicles, priority indicators are calculated, and electric vehicles are scheduled according to the priority indicators. This includes determining the main and auxiliary indicators, classifying the charging and discharging states, and using orderly charging or bidirectional charging and discharging strategies to schedule the charging and discharging of electric vehicles.
It has enabled optimized scheduling of electric vehicle charging and discharging, solved the grid load balance problem, and improved power quality and energy efficiency.
Smart Images

Figure CN117962681B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of charge and discharge scheduling technology, and in particular to a method, apparatus, device, and storage medium for charging and discharging scheduling of electric vehicles. Background Technology
[0002] With increasing concern about fossil fuel consumption and global warming, new energy electric vehicles have become an important mode of transportation. Inevitably, large-scale deployment of electric vehicles may lead to grid overload, degraded power quality, and reduced energy efficiency. Vehicle-to-Grid (V2G) technology has emerged to address this need, aiming to enable interaction between electric vehicles and the power grid. This allows electric vehicles to absorb electricity when grid load is low and release it when grid load is high, earning profits from the price difference.
[0003] However, with the increasing number of electric vehicles participating in grid interaction, how to schedule the charging and discharging of electric vehicles is an urgent problem to be solved. Summary of the Invention
[0004] Therefore, it is necessary to provide a method, apparatus, device, and storage medium for electric vehicle charging and discharging scheduling that can solve the problem of electric vehicle charging and discharging scheduling, in response to the above-mentioned technical problems.
[0005] Firstly, this application provides a method for scheduling the charging and discharging of an electric vehicle, the method comprising:
[0006] Determine the status information of multiple electric vehicles;
[0007] Determine the priority indicators for each electric vehicle based on its status information;
[0008] Each electric vehicle is scheduled and processed according to its corresponding priority index.
[0009] In one embodiment, the aforementioned state information includes the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, the decision interval time, and the remaining parking time. Priority indicators include primary and secondary indicators. Based on the state information, the priority indicators corresponding to each electric vehicle are determined, including:
[0010] The charging duration is determined based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval.
[0011] Based on the charging demand duration and remaining parking time, the main and auxiliary indicators for each electric vehicle are determined.
[0012] In one embodiment, the main and auxiliary indicators for each electric vehicle are determined based on the charging demand duration and remaining parking time, including:
[0013] Calculate the sum of charging demand duration and smoothing term;
[0014] Calculate the difference between the remaining parking time and the smoothing term;
[0015] Calculate the ratio between the sum and the difference to obtain the main indicators; and
[0016] The difference between the remaining parking time and the charging demand time is calculated to obtain an auxiliary indicator.
[0017] In one embodiment, the process for determining the charging demand duration includes:
[0018] Calculate the difference between the energy demand at the departure time and the energy state at the current decision time;
[0019] Calculate the product between the charging / discharging power and the decision interval time;
[0020] Calculate the ratio between the difference and the product to obtain the charging time requirement.
[0021] In one embodiment, the scheduling process for each electric vehicle based on its corresponding priority index includes:
[0022] The charging and discharging states of each electric vehicle are determined based on the main and auxiliary indicators.
[0023] Based on the charging / discharging status and key indicators of each electric vehicle, multiple electric vehicles are sorted, and charging / discharging processes are performed on the electric vehicles according to the sorting results.
[0024] In one embodiment, determining the charging and discharging state of each electric vehicle based on primary and secondary indicators includes:
[0025] If the main indicators of the electric vehicle exceed the first preset value, the charging / discharging state is determined to be one where charging is necessary.
[0026] If the main indicators of the electric vehicle are less than the second preset value, the charging / discharging state is determined to be a state where discharge is mandatory; wherein the second preset value is less than the first preset value.
[0027] If the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are less than or equal to the first preset value, the charging and discharging state is determined to be rechargeable but not dischargeable.
[0028] If the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are greater than or equal to the third preset value, the charging / discharging state is determined to be dischargeable but not rechargeable.
[0029] When the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are between the third and first preset values, the charging / discharging state is determined to be rechargeable.
[0030] In one embodiment, the above-mentioned charging and discharging process for multiple electric vehicles based on the sorting result includes:
[0031] Acquire target interaction strategies;
[0032] Based on the target interaction strategy and ranking results, charge and discharge processes are performed on multiple electric vehicles.
[0033] Secondly, this application also provides a charging and discharging scheduling device for electric vehicles. The device includes:
[0034] The information determination module is used to determine the status information of multiple electric vehicles;
[0035] The indicator determination module is used to determine the priority indicators for each electric vehicle based on the status information.
[0036] The scheduling and processing module is used to schedule electric vehicles according to their respective priority indicators.
[0037] Thirdly, this application also provides a computer device. The computer device includes a memory and a processor, the memory storing a computer program, and the processor executing the computer program to perform the following steps:
[0038] Determine the status information of multiple electric vehicles;
[0039] Determine the priority indicators for each electric vehicle based on its status information;
[0040] Each electric vehicle is scheduled and processed according to its corresponding priority index.
[0041] Fourthly, this application also provides a computer-readable storage medium. This computer-readable storage medium stores a computer program thereon, which, when executed by a processor, performs the following steps:
[0042] Determine the status information of multiple electric vehicles;
[0043] Determine the priority indicators for each electric vehicle based on its status information;
[0044] Each electric vehicle is scheduled and processed according to its corresponding priority index.
[0045] Fifthly, this application also provides a computer program product. This computer program product includes a computer program that, when executed by a processor, performs the following steps:
[0046] Determine the status information of multiple electric vehicles;
[0047] Determine the priority indicators for each electric vehicle based on its status information;
[0048] Each electric vehicle is scheduled and processed according to its corresponding priority index.
[0049] The aforementioned electric vehicle charging and discharging scheduling method, apparatus, device, and storage medium first determine the state information of multiple electric vehicles, then determine the priority index corresponding to each electric vehicle based on the state information, and finally schedule each electric vehicle according to its priority index. This application embodiment, by determining the state information of multiple electric vehicles, quantitatively judges the charging and discharging priority level of each electric vehicle at the current decision moment, and uses priority indexes to schedule the charging and discharging of electric vehicles, effectively solving the electric vehicle charging and discharging scheduling problem and reducing decision-making difficulty. Attached Figure Description
[0050] Figure 1 This is an application environment diagram of an electric vehicle charging and discharging scheduling method in one embodiment;
[0051] Figure 2 This is a flowchart illustrating an electric vehicle charging and discharging scheduling method in one embodiment;
[0052] Figure 3 This is a flowchart illustrating the process of determining the priority indicators for each electric vehicle in one embodiment.
[0053] Figure 4 This is a flowchart illustrating the process of determining the charging demand duration in one embodiment;
[0054] Figure 5 This is a schematic diagram of the scheduling process in one embodiment;
[0055] Figure 6a One of the charging and discharging states of an electric vehicle;
[0056] Figure 6b This is the second charging / discharging state of an electric vehicle.
[0057] Figure 6c The third state of charging and discharging for electric vehicles;
[0058] Figure 6d The fourth state of charging and discharging for electric vehicles;
[0059] Figure 6e The fifth state of charging and discharging for electric vehicles;
[0060] Figure 7 This is a schematic diagram of the charging and discharging process for multiple electric vehicles in one embodiment.
[0061] Figure 8 This is a structural block diagram of an electric vehicle charging and discharging scheduling device in one embodiment;
[0062] Figure 9 This is an internal structural diagram of a computer device in one embodiment. Detailed Implementation
[0063] To make the objectives, technical solutions, and advantages of this application clearer, the following detailed description is provided in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the scope of this application.
[0064] First, before introducing the technical solutions of the embodiments of this application in detail, the technical background on which the embodiments of this application are based will be introduced.
[0065] Based on vehicle scale and scheduling requirements, control methods for electric vehicle (EV) interaction with the power grid can be categorized into three types: centralized control, distributed control, and hierarchical control. Centralized control involves aggregating information from all EVs into a single control center, which centrally formulates charging and discharging plans for the EVs. While simple and easy to implement, centralized control requires the control center to handle information storage and optimization calculations, making it unable to cope with the computational burden caused by large-scale EV grid integration. Distributed control is suitable for large-scale, decentralized EV charging scheduling scenarios. It formulates charging and discharging plans based on price and regulatory information, distributing the optimization computational burden across the EVs, thus reducing the control center's computational and communication costs. Hierarchical control breaks down large-scale EV clusters into multiple smaller clusters, with a top-level control center coordinating the operation of multiple control centers. Each control center focuses only on the charging and discharging optimization of its own cluster.
[0066] Based on this, this application provides a method, apparatus, device, and storage medium for electric vehicle charging and discharging scheduling, aiming to solve the above-mentioned technical problems.
[0067] The electric vehicle charging and discharging scheduling method provided in this application embodiment can be applied to, for example... Figure 1The application environment is illustrated. Electric vehicles are positioned on the far right. Users obtain incentive information to express their willingness to participate. The charging station's equipment layer extracts vehicle information, including charging demand, service type, and acceptable scheduling time slots, thereby calculating the station's controllable capacity. This information is then uploaded to the operator's load aggregation platform. The interaction between the load aggregation platform and the top-level control platform is complex, involving energy interaction, scheduling capacity information, strategy information flow, and economic incentive information. The top-level control platform integrates grid information, electricity price information, and traffic information, develops scheduling strategies, and distributes them to the aggregation platform. The aggregation platform decomposes the adjustment instructions and sends them to the charging operation platform, which executes power regulation. Finally, the charging operation platform feeds back the execution results to the aggregation platform and the dispatch center.
[0068] In one exemplary embodiment, such as Figure 2 As shown, this application provides a method for scheduling the charging and discharging of an electric vehicle, which is applied to... Figure 1 The top-level control platform in the system will be used as an example for explanation, including the following S101 to S103. Among them:
[0069] S101, determine the status information of multiple electric vehicles.
[0070] In this embodiment, when a user expresses their willingness to participate, the charging station's equipment layer extracts the vehicle information of the electric vehicle and uploads it to the operator's load aggregation platform. The load aggregation platform interacts with the top-level control platform, and ultimately, the top-level control platform obtains vehicle information and determines the vehicle's status information based on this information. The vehicle information may include charging demand, service type, and acceptable scheduling time. The status information may include state of charge, energy status, remaining parking time, and charging demand time, etc.
[0071] S102, determine the priority indicators for each electric vehicle based on the status information.
[0072] In this embodiment, based on the status information determined in the above embodiments, the top-level control platform can input the status information into a pre-established scheduling model to determine the priority index corresponding to each electric vehicle. Alternatively, the priority index corresponding to each electric vehicle can be determined according to a pre-established relationship table between status information and priority index.
[0073] S103, schedules each electric vehicle according to its priority index.
[0074] Among them, scheduling refers to charging or discharging each electric vehicle.
[0075] In this embodiment, based on the priority indicators obtained in the above embodiments, the top-level control platform can sort these priority indicators and schedule each electric vehicle according to the sorting results. Alternatively, it can determine the charging / discharging state of the electric vehicle and then schedule each electric vehicle according to the charging / discharging state and the corresponding priority indicators.
[0076] The aforementioned electric vehicle charging and discharging method first determines the state information of multiple electric vehicles, then determines the priority index corresponding to each electric vehicle based on the state information, and finally schedules each electric vehicle according to its priority index. This embodiment of the application, by determining the state information of multiple electric vehicles, quantitatively judges the charging and discharging priority level of each electric vehicle at the current decision moment, and schedules the charging and discharging of electric vehicles based on priority indexes, effectively solving the electric vehicle charging and discharging scheduling problem and reducing decision-making difficulty.
[0077] In one exemplary embodiment, based on the above embodiments, please refer to... Figure 3 This application embodiment relates to a process for determining the priority index corresponding to each electric vehicle based on status information, including the following S201 to S202. Wherein:
[0078] S201 determines the charging duration based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval.
[0079] In the above embodiments, the status information includes the energy demand at the departure time, the energy status at the current decision time, the charging and discharging power, the decision interval time, and the remaining parking time. The priority indicators include primary indicators and auxiliary indicators.
[0080] In this embodiment, the top-level control platform can input the energy demand at the departure time, the energy status at the current decision time, the charging and discharging power, the decision interval time, and the remaining parking time determined in the above embodiments into the calculation model to obtain the charging demand duration.
[0081] S202 determines the main and auxiliary indicators for each electric vehicle based on the charging demand duration and remaining parking time.
[0082] Among them, the main indicators are used to determine the priority of charging / discharging electric vehicles. The higher the value, the more urgent the charging demand, and vice versa. The auxiliary indicators are used to determine the dividing point between charging and discharging.
[0083] In this embodiment, based on the charging demand duration determined in the above embodiments, the top-level control platform can also input the charging demand duration and remaining parking time into the calculation model to determine the main and auxiliary indicators corresponding to each electric vehicle. Alternatively, the charging demand duration and remaining parking time can be weighted and summed to obtain the main and auxiliary indicators corresponding to each electric vehicle.
[0084] This application embodiment determines the charging demand duration and remaining parking time, determines the main indicators and auxiliary indicators corresponding to each electric vehicle to determine the scheduling order, and classifies the charging and discharging states according to the auxiliary indicators, thereby reasonably scheduling the charging and discharging of electric vehicles.
[0085] In one exemplary embodiment, based on the above embodiments, please refer to... Figure 4 The process for determining the charging time requirement mentioned above includes the following steps S301 to S303. Wherein:
[0086] S301, calculate the difference between the energy demand at the departure time and the energy state at the current decision time.
[0087] In this embodiment, based on the energy demand at the departure time and the energy state at the current decision time obtained from the above embodiments, the top-level control platform can calculate the difference between the energy demand at the departure time and the energy state at the current decision time.
[0088] S302, calculate the product between charging / discharging power and decision interval time.
[0089] In this embodiment, based on the charging / discharging power and decision interval time obtained from the above embodiments, the top-level control platform can calculate the product between the charging / discharging power and the decision interval time.
[0090] S303, calculate the ratio between the difference and the product to obtain the charging time requirement.
[0091] In this embodiment, based on the difference and product obtained in the above embodiments, the top-level control platform can calculate the ratio between the difference and the product using formula (1) to obtain the charging demand duration. Formula (1) is as follows:
[0092]
[0093] Where t represents the charging time requirement. Energy requirements at the moment of departure The energy state at the current decision-making moment. Δt represents the charging / discharging power, and Δt represents the decision interval.
[0094] This application uses a constructed calculation formula to obtain the charging demand duration for subsequent calculation of main and auxiliary indicators.
[0095] In one exemplary embodiment, based on the above embodiments, please refer to... Figure 5 This application embodiment relates to a process for scheduling electric vehicles according to their respective priority indicators, including the following steps S401 to S402. Wherein:
[0096] S401 determines the charging and discharging status of each electric vehicle based on the main and auxiliary indicators.
[0097] In this embodiment, based on the primary and secondary indicators obtained in the above embodiments, the top-level control platform can store the primary and secondary indicators in their respective matrices, and determine the charging and discharging state of each electric vehicle according to the pre-set thresholds and the primary and secondary indicators. Alternatively, the primary and secondary indicators can be input into a pre-built state determination model to determine the charging and discharging state of each electric vehicle.
[0098] S402: Based on the charging / discharging status and main indicators of each electric vehicle, sort the multiple electric vehicles and perform charging / discharging processing on the multiple electric vehicles according to the sorting results.
[0099] The calculation formulas for the main indicators are shown in formula (2):
[0100]
[0101] The calculation formula for the auxiliary indicators is shown in formula (3):
[0102] index auxiliary =Tt (3)
[0103] Where, index major and index auxiliary These represent the primary and secondary indicators, respectively. t represents the charging demand duration. To prevent meaningless situations where the priority indicator equals 0 or the indicator denominator equals 0, T represents the remaining parking time. A smoothing term is added to the primary indicator. The smoothing term is a value close to 0, for example, 0.01.
[0104] In this embodiment, based on the key indicators and charge / discharge states obtained from the above embodiments, the top-level control platform can sort the electric vehicles according to their key indicators, obtaining the sorting results in either sequential or reverse order. Based on the sorting results, the electric vehicles are then charged or discharged according to their corresponding charge / discharge states. For example, if the key indicators of vehicles A, B, and C are 1.2, 1.1, and -1.4 respectively, their corresponding charge / discharge states are: must charge, can be charged but not discharged, and must discharge. The sorting result is C, B, A. Based on this sorting result, electric vehicle A is prioritized for charging, electric vehicle B is charged but not discharged according to actual conditions, and electric vehicle C is discharged.
[0105] In this embodiment of the application, the charging and discharging states of each electric vehicle can be quantitatively determined through primary and secondary indicators, thereby enabling accurate determination of the charging and discharging status of the vehicle at the current decision-making moment.
[0106] In one exemplary embodiment, based on the above embodiments, this application relates to a process for determining the charging and discharging state of each electric vehicle according to primary and secondary indicators, including the following:
[0107] This application's embodiments classify electric vehicles into the following five charging and discharging states.
[0108] Status 1: Charging is required. This corresponds to situations where the electric vehicle's charging time is greater than or equal to the remaining parking time. Figure 6a As shown.
[0109] State 2: Discharge is required, corresponding to situations where the electric vehicle's discharge demand time is greater than or equal to the remaining parking time. Under a bidirectional charging and discharging strategy, there are special scenarios where users exploit peak-valley electricity prices for arbitrage. Therefore, the energy state demand of an electric vehicle leaving a charging station may be less than its energy state upon arrival at the charging station (discharge demand exists). Figure 6b As shown.
[0110] State 3: Dischargeable but not rechargeable. This corresponds to a situation where, if a charging command is executed at the current moment, the electric vehicle will not be able to meet the owner's charging needs during the parking period. Figure 6c As shown.
[0111] Status 4: Rechargeable but not discharging. This corresponds to a situation where, if an electric vehicle executes a discharge command at the current moment, it will not be able to meet the owner's discharge needs during the parking period. Figure 6d As shown.
[0112] State 5: Rechargeable and dischargeable, indicating that the vehicle is eligible for any form of dispatch at the current decision-making moment, such as... Figure 6e As shown.
[0113] As shown in Table 1, taking the decision time T=3 as an example, the first preset value is 1, the second preset value is -1, and the third preset value is 2T-1=5, where the second preset value is less than the first preset value. This application embodiment lists vehicle information in five charging / discharging states. Among them:
[0114] Table 1
[0115]
[0116] Scenario 1: If the main indicators of an electric vehicle exceed a first preset value, the charging / discharging state is determined to require charging. (i.e., index) major >1.
[0117] Scenario 2: If the main indicators of the electric vehicle are lower than the second preset value, the charging / discharging state is determined to require discharging. (i.e., index) major ≤-1.
[0118] Scenario 3: If the main indicators of the electric vehicle are between the first and second preset values, and the auxiliary indicators are less than or equal to the first preset value, the charging / discharging state is determined to be rechargeable but not dischargeable. That is, -1. <index major <1&index auxiliary ≤1.
[0119] Scenario 4: If the main indicators of the electric vehicle are between the first and second preset values, and the auxiliary indicators are greater than or equal to the third preset value, the charging / discharging state is determined to be dischargeable but not rechargeable. That is, -1. <index major <1&index auxiliary ≤2T-1.
[0120] Scenario 5: When the main indicators of the electric vehicle are between the first and second preset values, and the auxiliary indicators are between the third and first preset values, the charging / discharging state is determined to be both rechargeable and dischargeable. That is, -1. <index major <1&1≤index auxiliary ≤2T-1.
[0121] In this embodiment of the application, the charging and discharging state of each electric vehicle can be accurately determined by setting a threshold.
[0122] In one exemplary embodiment, based on the above embodiments, please refer to... Figure 7 This application embodiment relates to a process of charging and discharging multiple electric vehicles according to a sorting result, including the following steps S601 to S602. Wherein:
[0123] S601, Obtain the target interaction strategy.
[0124] Among them, the target interaction strategy includes an ordered charging strategy or a bidirectional charging and discharging strategy.
[0125] In this embodiment of the application, the top-level control platform can obtain the target interaction strategy input by the user, or it can automatically generate the target interaction strategy.
[0126] S602 performs charging and discharging processing on multiple electric vehicles based on the target interaction strategy and ranking results.
[0127] In this embodiment, based on the target interaction strategy and sorting results obtained from the above embodiments, the top-level control platform can correct the difference between the current charging / discharging power and the guidance power curve, provided that the charging / discharging needs of the vehicle are guaranteed: if it is less than the guidance power at the current moment, electric vehicles with charging capacity are scheduled to charge to increase the charging power and reduce the deviation from the guidance charging power; otherwise, electric vehicles with discharging capacity are scheduled to discharge to increase the discharging power and reduce the deviation from the guidance discharging power.
[0128] When the strategy is an orderly charging strategy, the top-level control platform will integrate grid information, electricity price information, and traffic information, and send dispatch instructions to the aggregation platform. The aggregation platform will decompose the adjustment instructions and send the decomposed instructions to the charging operation platform. The charging operation platform will execute power regulation to ensure that electric vehicles are charged according to priority based on vehicle charging demand and to find the minimum deviation. Finally, the charging operation platform will feed back the execution results to the aggregation platform and the dispatch center.
[0129] When the strategy is a two-way interactive strategy, based on the same interaction method, the charging and discharging needs of vehicles are guaranteed. During the off-peak load period, electric vehicles are charged according to priority to find the minimum deviation. During the peak load period, electric vehicles are discharged according to priority to find the minimum deviation.
[0130] In an exemplary embodiment, based on the above embodiments, the method of this application embodiment further includes the following steps:
[0131] Step 1: Determine the energy demand at the departure time of multiple electric vehicles, the energy state at the current decision time, the charging and discharging power, the decision interval time, and the remaining parking time;
[0132] Step 2: Calculate the difference between the energy demand at the departure time and the energy state at the current decision time; calculate the product between the charging / discharging power and the decision interval time; calculate the ratio between the difference and the product to obtain the charging demand duration;
[0133] Step 3: Determine the charging demand duration based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval; determine the main and auxiliary indicators for each electric vehicle based on the charging demand duration and the remaining parking time.
[0134] Step 4: If the main indicator of the electric vehicle is greater than the first preset value, determine the charging / discharging state as "must charge"; if the main indicator of the electric vehicle is less than the second preset value, determine the charging / discharging state as "must discharge"; wherein the second preset value is less than the first preset value; if the main indicator of the electric vehicle is between the first and second preset values, and the auxiliary indicator is less than or equal to the first preset value, determine the charging / discharging state as "rechargeable but not dischargeable"; if the main indicator of the electric vehicle is between the first and second preset values, and the auxiliary indicator is greater than or equal to the third preset value, determine the charging / discharging state as "dischargeable but not rechargeable"; if the main indicator of the electric vehicle is between the first and second preset values, and the auxiliary indicator is not equal to either the third or the first preset value, determine the charging / discharging state as "dischargeable and rechargeable".
[0135] Step 5: Sort the electric vehicles according to their charging / discharging status and key indicators to obtain the sorting results;
[0136] Step 6: Obtain the target interaction strategy; based on the target interaction strategy and the ranking results, perform charging and discharging processing on multiple electric vehicles.
[0137] It should be understood that although the steps in the flowcharts of the embodiments described above are shown sequentially according to the arrows, these steps are not necessarily executed in the order indicated by the arrows. Unless explicitly stated herein, there is no strict order restriction on the execution of these steps, and they can be executed in other orders. Moreover, at least some steps in the flowcharts of the embodiments described above may include multiple steps or multiple stages. These steps or stages are not necessarily completed at the same time, but can be executed at different times. The execution order of these steps or stages is not necessarily sequential, but can be performed alternately or in turn with other steps or at least some of the steps or stages of other steps.
[0138] Based on the same inventive concept, this application also provides an electric vehicle charging and discharging scheduling device for implementing the electric vehicle charging and discharging scheduling method described above. The solution provided by this device is similar to the solution described in the above method; therefore, the specific limitations in one or more embodiments of the electric vehicle charging and discharging scheduling device provided below can be found in the limitations of the electric vehicle charging and discharging scheduling method described above, and will not be repeated here.
[0139] In one embodiment, such as Figure 8 As shown, an electric vehicle charging and discharging scheduling device 600 is provided, comprising:
[0140] Information determination module 601 is used to determine the status information of multiple electric vehicles;
[0141] The indicator determination module 602 is used to determine the priority indicators corresponding to each electric vehicle based on the status information.
[0142] The scheduling processing module 603 is used to schedule each electric vehicle according to the priority index corresponding to each electric vehicle.
[0143] In one embodiment, the aforementioned status information includes energy demand at the departure time, energy state at the current decision time, charging and discharging power, decision interval time, and remaining parking time; the priority indicators include primary indicators and auxiliary indicators; the aforementioned indicator determination module 602 includes:
[0144] The duration determination unit is used to determine the charging demand duration based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval time.
[0145] The indicator determination unit is used to determine the main and auxiliary indicators for each electric vehicle based on the charging demand duration and remaining parking time.
[0146] In one embodiment, the duration determination unit includes:
[0147] The difference determination sub-unit is used to calculate the difference between the energy demand at the departure time and the energy state at the current decision time;
[0148] The product determination subunit is used to calculate the product between the charge / discharge power and the decision interval time;
[0149] The duration determination sub-unit is used to calculate the ratio between the difference and the product to obtain the charging demand duration.
[0150] In one embodiment, the scheduling processing module 603 includes:
[0151] The status determination unit is used to determine the charging and discharging status of each electric vehicle based on the main indicators and auxiliary indicators.
[0152] The scheduling and processing unit is used to sort multiple electric vehicles according to their charging and discharging status and key indicators, and to perform charging and discharging processing on the multiple electric vehicles according to the sorting results.
[0153] In one embodiment, the state determination unit includes:
[0154] The first state determination subunit is used to determine that the charging / discharging state must be charged when the main indicators of the electric vehicle are greater than the first preset value.
[0155] The second state determination subunit is used to determine that the charging / discharging state must be discharged when the main indicators of the electric vehicle are less than a second preset value; wherein the second preset value is less than a first preset value.
[0156] The third state determination subunit is used to determine the charging and discharging state as rechargeable but not dischargeable when the main indicators of the electric vehicle are between the first preset value and the second preset value, and the auxiliary indicators are less than or equal to the first preset value.
[0157] The fourth state determination subunit is used to determine the charging / discharging state as dischargeable but not rechargeable when the main indicators of the electric vehicle are between the first and second preset values and the auxiliary indicators are greater than or equal to the third preset value.
[0158] The fifth state determination subunit is used to determine the charging / discharging state as rechargeable and dischargeable when the main indicators corresponding to the electric vehicle are between the first preset value and the second preset value, and the auxiliary indicators are between the third preset value and the first preset value.
[0159] In one embodiment, the scheduling processing unit includes:
[0160] The strategy acquisition subunit is used to acquire the target interaction strategy;
[0161] The scheduling and processing subunit is used to perform charging and discharging processing on multiple electric vehicles according to the target interaction strategy and the sorting results.
[0162] Each module in the aforementioned electric vehicle charging and discharging scheduling device can be implemented entirely or partially through software, hardware, or a combination thereof. These modules can be embedded in or independent of the processor in a computer device, or stored in the memory of a computer device as software, so that the processor can call and execute the corresponding operations of each module.
[0163] In one embodiment, a computer device is provided, which may be a server, and its internal structure diagram may be as follows: Figure 9As shown, this computer device includes a processor, memory, input / output (I / O) interfaces, and a communication interface. The processor, memory, and I / O interfaces are connected via a system bus, and the communication interface is also connected to the system bus via the I / O interfaces. The processor provides computational and control capabilities. The memory includes non-volatile storage media and internal memory. The non-volatile storage media stores the operating system, computer programs, and databases. The internal memory provides the environment for the operating system and computer programs stored in the non-volatile storage media to run. The I / O interfaces are used for exchanging information between the processor and external devices. The communication interface is used for communicating with external terminals via a network connection. When the computer program is executed by the processor, it implements a charging and discharging scheduling method for electric vehicles.
[0164] Those skilled in the art will understand that Figure 9 The structure shown is merely a block diagram of a portion of the structure related to the present application and does not constitute a limitation on the computer device to which the present application is applied. Specific computer devices may include more or fewer components than those shown in the figure, or combine certain components, or have different component arrangements.
[0165] In one embodiment, a computer device is provided, including a memory and a processor, wherein the memory stores a computer program, and the processor executes the computer program to perform the following steps:
[0166] Determine the status information of multiple electric vehicles;
[0167] Determine the priority indicators for each electric vehicle based on its status information;
[0168] Each electric vehicle is scheduled and processed according to its corresponding priority index.
[0169] In one embodiment, the processor, when executing a computer program, also performs the following steps:
[0170] The charging duration is determined based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval.
[0171] Based on the charging demand duration and remaining parking time, the main and auxiliary indicators for each electric vehicle are determined.
[0172] In one embodiment, the processor, when executing a computer program, also performs the following steps:
[0173] Calculate the difference between the energy demand at the departure time and the energy state at the current decision time;
[0174] Calculate the product between the charging / discharging power and the decision interval time;
[0175] Calculate the ratio between the difference and the product to obtain the charging time requirement.
[0176] In one embodiment, the processor, when executing a computer program, also performs the following steps:
[0177] The charging and discharging states of each electric vehicle are determined based on the main and auxiliary indicators.
[0178] Based on the charging / discharging status and key indicators of each electric vehicle, multiple electric vehicles are sorted, and charging / discharging processes are performed on the electric vehicles according to the sorting results.
[0179] In one embodiment, the processor, when executing a computer program, also performs the following steps:
[0180] If the main indicators of the electric vehicle exceed the first preset value, the charging / discharging state is determined to be one where charging is necessary.
[0181] If the main indicators of the electric vehicle are less than the second preset value, the charging / discharging state is determined to be a state where discharge is mandatory; wherein the second preset value is less than the first preset value.
[0182] If the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are less than or equal to the first preset value, the charging and discharging state is determined to be rechargeable but not dischargeable.
[0183] If the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are greater than or equal to the third preset value, the charging / discharging state is determined to be dischargeable but not rechargeable.
[0184] When the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are between the third and first preset values, the charging and discharging state is determined to be rechargeable and dischargeable.
[0185] In one embodiment, the processor, when executing a computer program, also performs the following steps:
[0186] Acquire target interaction strategies;
[0187] Based on the target interaction strategy and ranking results, charge and discharge processes are performed on multiple electric vehicles.
[0188] In one embodiment, a computer-readable storage medium is provided having a computer program stored thereon, the computer program performing the following steps when executed by a processor:
[0189] Determine the status information of multiple electric vehicles;
[0190] Determine the priority indicators for each electric vehicle based on its status information;
[0191] Each electric vehicle is scheduled and processed according to its corresponding priority index.
[0192] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0193] The charging duration is determined based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval.
[0194] Based on the charging demand duration and remaining parking time, the main and auxiliary indicators for each electric vehicle are determined.
[0195] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0196] Calculate the difference between the energy demand at the departure time and the energy state at the current decision time;
[0197] Calculate the product between the charging / discharging power and the decision interval time;
[0198] Calculate the ratio between the difference and the product to obtain the charging time requirement.
[0199] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0200] The charging and discharging states of each electric vehicle are determined based on the main and auxiliary indicators.
[0201] Based on the charging / discharging status and key indicators of each electric vehicle, multiple electric vehicles are sorted, and charging / discharging processes are performed on the electric vehicles according to the sorting results.
[0202] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0203] If the main indicators of the electric vehicle exceed the first preset value, the charging / discharging state is determined to be one where charging is necessary.
[0204] If the main indicators of the electric vehicle are less than the second preset value, the charging / discharging state is determined to be a state where discharge is mandatory; wherein the second preset value is less than the first preset value.
[0205] If the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are less than or equal to the first preset value, the charging and discharging state is determined to be rechargeable but not dischargeable.
[0206] If the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are greater than or equal to the third preset value, the charging / discharging state is determined to be dischargeable but not rechargeable.
[0207] When the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are between the third and first preset values, the charging / discharging state is determined to be rechargeable.
[0208] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0209] Acquire target interaction strategies;
[0210] Based on the target interaction strategy and ranking results, charge and discharge processes are performed on multiple electric vehicles.
[0211] In one embodiment, a computer program product is provided, including a computer program that, when executed by a processor, performs the following steps:
[0212] Determine the status information of multiple electric vehicles;
[0213] Determine the priority indicators for each electric vehicle based on its status information;
[0214] Each electric vehicle is scheduled and processed according to its corresponding priority index.
[0215] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0216] The charging duration is determined based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval.
[0217] Based on the charging demand duration and remaining parking time, the main and auxiliary indicators for each electric vehicle are determined.
[0218] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0219] Calculate the difference between the energy demand at the departure time and the energy state at the current decision time;
[0220] Calculate the product between the charging / discharging power and the decision interval time;
[0221] Calculate the ratio between the difference and the product to obtain the charging time requirement.
[0222] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0223] The charging and discharging states of each electric vehicle are determined based on the main and auxiliary indicators.
[0224] Based on the charging / discharging status and key indicators of each electric vehicle, multiple electric vehicles are sorted, and charging / discharging processes are performed on the electric vehicles according to the sorting results.
[0225] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0226] If the main indicators of the electric vehicle exceed the first preset value, the charging / discharging state is determined to be one where charging is necessary.
[0227] If the main indicators of the electric vehicle are less than the second preset value, the charging / discharging state is determined to be a state where discharge is mandatory; wherein the second preset value is less than the first preset value.
[0228] If the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are less than or equal to the first preset value, the charging and discharging state is determined to be rechargeable but not dischargeable.
[0229] If the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are greater than or equal to the third preset value, the charging / discharging state is determined to be dischargeable but not rechargeable.
[0230] When the main indicators of an electric vehicle are between the first and second preset values, and the auxiliary indicators are between the third and first preset values, the charging / discharging state is determined to be rechargeable.
[0231] In one embodiment, when the computer program is executed by a processor, it also performs the following steps:
[0232] Acquire target interaction strategies;
[0233] Based on the target interaction strategy and ranking results, charge and discharge processes are performed on multiple electric vehicles.
[0234] It should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, data stored, data displayed, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of the relevant data shall comply with the relevant laws, regulations and standards of the relevant countries and regions.
[0235] Those skilled in the art will understand that all or part of the processes in the above embodiments can be implemented by a computer program instructing related hardware. The computer program can be stored in a non-volatile computer-readable storage medium, and when executed, it can include the processes of the embodiments described above. Any references to memory, databases, or other media used in the embodiments provided in this application can include at least one of non-volatile and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. By way of illustration and not limitation, RAM can take many forms, such as Static Random Access Memory (SRAM) or Dynamic Random Access Memory (DRAM). The databases involved in the embodiments provided in this application may include at least one type of relational database and non-relational database. Non-relational databases may include, but are not limited to, blockchain-based distributed databases. The processors involved in the embodiments provided in this application may be general-purpose processors, central processing units, graphics processing units, digital signal processors, programmable logic devices, quantum computing-based data processing logic devices, etc., and are not limited to these.
[0236] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0237] The embodiments described above are merely illustrative of several implementation methods of this application, and while the descriptions are specific and detailed, they should not be construed as limiting the scope of this patent application. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this application, and these all fall within the protection scope of this application. Therefore, the protection scope of this application should be determined by the appended claims.
Claims
1. A method for scheduling the charging and discharging of electric vehicles, characterized in that, The method includes: Determine the status information of multiple electric vehicles; the status information includes the energy demand at the time of departure, the energy status at the current decision time, the charging and discharging power, the decision interval time, and the remaining parking time; The charging duration is determined based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval. Based on the charging demand duration and the remaining parking time, the main and auxiliary indicators for each electric vehicle are determined respectively. The charging / discharging state of each electric vehicle is determined based on the primary and secondary indicators. Specifically, if the primary indicator of the electric vehicle is greater than a first preset value, the charging / discharging state is determined to be "must charge"; if the primary indicator of the electric vehicle is less than a second preset value, the charging / discharging state is determined to be "must discharge"; the second preset value is less than the first preset value. If the primary indicator of the electric vehicle is between the first and second preset values, and the secondary indicator is less than or equal to the first preset value, the charging / discharging state is determined to be "chargeable but not dischargeable"; if the primary indicator of the electric vehicle is between the first and second preset values, and the secondary indicator is greater than or equal to a third preset value, the charging / discharging state is determined to be "dischargeable but not rechargeable"; if the primary indicator of the electric vehicle is between the first and second preset values, and the secondary indicator is between the third and first preset values, the charging / discharging state is determined to be "dischargeable and rechargeable". Based on the charging / discharging state and key indicators of each electric vehicle, the electric vehicles are sorted, and charging / discharging processes are performed on the electric vehicles according to the sorting results.
2. The method according to claim 1, characterized in that, The process of determining the primary and secondary indicators for each electric vehicle based on the charging demand duration and the remaining parking time includes: Calculate the sum of the charging demand duration and the smoothing term; Calculate the difference between the remaining parking time and the smoothing term; The ratio between the sum and the difference is calculated to obtain the main indicator; and The auxiliary indicator is obtained by calculating the difference between the remaining parking time and the charging demand time.
3. The method according to claim 1, characterized in that, The process for determining the charging demand duration includes: Calculate the difference between the energy demand at the departure time and the energy state at the current decision time; Calculate the product between the charge / discharge power and the decision interval time; The charging time requirement is obtained by calculating the ratio between the difference and the product.
4. The method according to claim 1, characterized in that, The step of charging and discharging multiple electric vehicles according to the sorting result includes: Acquire target interaction strategies; Based on the target interaction strategy and the sorting results, the multiple electric vehicles are charged and discharged.
5. A charging and discharging scheduling device for electric vehicles, characterized in that, The device includes: An information determination module is used to determine the status information of multiple electric vehicles; the status information includes the energy demand at the departure time, the energy status at the current decision time, the charging and discharging power, the decision interval time, and the remaining parking time. The indicator determination module is used to determine the charging demand duration based on the energy demand at the departure time, the energy state at the current decision time, the charging and discharging power, and the decision interval time; and to determine the main indicators and auxiliary indicators corresponding to each electric vehicle based on the charging demand duration and the remaining parking time. The scheduling processing module is used to determine the charging / discharging state of each electric vehicle based on the primary indicator and the auxiliary indicator; wherein, if the primary indicator of the electric vehicle is greater than a first preset value, the charging / discharging state is determined to be "must charge"; if the primary indicator of the electric vehicle is less than a second preset value, the charging / discharging state is determined to be "must discharge"; the second preset value is less than the first preset value; if the primary indicator of the electric vehicle is between the first and second preset values, and the auxiliary indicator is less than or equal to the first preset value, the charging / discharging state is determined to be "chargeable but not dischargeable"; if the primary indicator of the electric vehicle is between the first and second preset values, and the auxiliary indicator is greater than or equal to a third preset value, the charging / discharging state is determined to be "dischargeable but not rechargeable"; if the primary indicator of the electric vehicle is between the first and second preset values, and the auxiliary indicator is between the third and first preset values, the charging / discharging state is determined to be "dischargeable and rechargeable"; the module sorts the electric vehicles according to their charging / discharging states and primary indicators, and performs charging / discharging processing on the electric vehicles according to the sorting results.
6. A computer device comprising a memory and a processor, wherein the memory stores a computer program, characterized in that, When the processor executes the computer program, it implements the steps of the method according to any one of claims 1 to 4.
7. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by a processor, it implements the steps of the method according to any one of claims 1 to 4.
Citation Information
Patent Citations
Method, device and equipment for electric vehicle charging regulation
CN110979085A
Electric vehicle demand response capability assessment method based on user demand relaxation
CN112926818A
Intelligent charging electric vehicle energy network connection scheduling method and system
CN113949091A
Device and method for charge / discharge management, and program
JP2015171188A