A combined permanent and temporary basement structure and its construction method

By using connecting steel bars and waterproofing structures in the basement structure, the problem of unstable connection between the diaphragm wall and the basement structure was solved, achieving higher connection strength and waterproofing performance, and reducing safety hazards.

CN117988389BActive Publication Date: 2026-11-17ZHEJIANG HUAJIAN ENG MANAGEMENT CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410229846.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-29
Publication Date
2026-11-17
Estimated Expiration
2044-02-29

AI Technical Summary

Technical Problem

The structural integrity of the diaphragm wall and the basement is difficult to guarantee. The connection stability between the support structure in the foundation pit and the basement structure is poor, and it cannot effectively withstand the lateral pressure of the surrounding soil, which poses a safety hazard.

Method used

The first and second connecting steel bars are inserted into the support structure through a drive assembly to enhance the connection stability between the roof slab and the support structure, and combined with a waterproof structure to improve the connection strength and waterproofing capability.

Benefits of technology

It enhances the connection strength between the basement structure and the supporting structure, improves the bearing capacity of the surrounding soil, reduces safety hazards, and improves construction efficiency and waterproofing capabilities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117988389B_ABST
    Figure CN117988389B_ABST
Patent Text Reader

Abstract

This application relates to a combined permanent and temporary basement structure and its construction method, belonging to the technical field of basements. The structure includes a roof slab and a floor slab; a support structure, with a first connecting component fixing the support structure to the roof slab and a second connecting component fixing the support structure to the floor slab; the first connecting component includes a first connecting steel bar disposed within the roof slab, and a first driving component within the roof slab for inserting the first connecting steel bar into the support structure; the second connecting component includes a second connecting steel bar disposed within the floor slab, and a second driving component within the floor slab for inserting the second connecting steel bar into the support structure. This application has the effect of reducing safety hazards.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the technical field of basements, and in particular to a permanent-temporary combined basement structure and its construction method. Background Technology

[0002] A basement is a room whose floor level is more than half the room's net height below the outdoor ground level. Multi-story and high-rise buildings require deeper foundations, and to utilize this height, a basement is built beneath the ground floor, increasing usable space and saving the need for backfilling the floor. Basement construction requires excavation of a foundation pit. A continuous underground wall is installed around the pit, and a combination of internal and external support methods is used to ensure the smooth progress of the construction.

[0003] In practical engineering applications, it is difficult to guarantee the structural integrity of the diaphragm wall and the basement. The connection stability between the support structure in the foundation pit and the basement structure is poor, which makes it unable to withstand the lateral pressure of the surrounding soil and poses a safety hazard. Summary of the Invention

[0004] To reduce safety hazards, this application provides a combined permanent and temporary basement structure and its construction method.

[0005] Firstly, this application provides a combined permanent and temporary basement structure, employing the following technical solution: A combined permanent and temporary basement structure includes: The building structure includes the roof slab and the floor slab; The support structure has a first connecting component that fixes the support structure to the roof slab, and a second connecting component that fixes the support structure to the base slab. The first connecting component includes a first connecting steel bar, which is disposed within the roof slab, and a first driving component for inserting the first connecting steel bar into the support structure is disposed within the roof slab. The second connecting component includes a second connecting steel bar, which is disposed within the base plate. A second driving component for inserting the second connecting steel bar into the support structure is disposed within the base plate.

[0006] Using the above technical solution, during the construction of the roof slab, the first connecting steel bar is inserted into the support structure via the first driving component, enhancing the connection stability between the roof slab and the support structure; during the construction of the bottom slab, the second connecting steel bar is inserted into the support structure via the second driving component, enhancing the connection stability between the bottom slab and the support structure. Through this structure, the connection strength between the roof slab and the support structure, and between the bottom slab and the support structure, is enhanced, thereby improving the bearing capacity against the surrounding soil and achieving the effect of reducing safety hazards.

[0007] Optionally, the support structure includes a diaphragm wall and an inner lining wall, with a waterproof structure between the diaphragm wall and the inner lining wall. The waterproof structure includes a connecting frame and a waterstop. A connecting groove is provided through the side wall of the connecting frame, and a connecting strip adapted to the connecting groove is fixedly connected to the edge of the waterstop. A grouting hole is provided through the side wall of the connecting frame.

[0008] By adopting the above technical solution, the waterstop can prevent water from flowing into the basement through the support structure, thereby improving the waterproofing capacity of the support structure and extending the service life of the basement. The connecting strip is inserted into the connecting groove, and then grout is injected into the connecting frame through the grouting hole to fix the waterstop. The installation method of the waterproof structure is simple and improves construction efficiency.

[0009] Optionally, a through groove communicating with the connecting slot is provided on one side of the connecting frame, a limiting seat is slidably connected in the through groove, a fixing groove for the limiting seat to pass through is provided in the connecting strip, and a fixing component for fixing the limiting seat is provided in the connecting frame.

[0010] By adopting the above technical solution, after the connecting strip passes through the connecting groove, the limiting seat passes through the fixing groove, and then the limiting seat is fixed by the fixing component. In this way, the waterstop is fixed to the connecting frame by the connecting strip, thereby reducing the movement of the waterstop during grouting and improving the construction quality of the waterproof structure.

[0011] Optionally, the connecting frame has a slot on the inner wall of the connecting groove that is compatible with the limiting seat, and the connecting frame has a limiting groove on the inner wall of the slot. The fixing component is set in the limiting groove. The fixing component includes a limiting rod and a return spring. The limiting rod is slidably adapted to the limiting groove. The two ends of the return spring are fixed to the limiting rod and the connecting frame, respectively. An inclined surface is opened on one side of the limiting rod. An insertion hole adapted to the insertion of the limiting rod is opened in the limiting seat.

[0012] Using the above technical solution, after the limiting seat passes through the fixing groove, when the limiting seat is inserted into the slot, the limiting seat presses the limiting rod through the inclined surface. The limiting rod is compressed and compresses the return spring. When the limiting rod is aligned with the insertion hole, the return spring releases its elastic force and inserts the limiting rod into the insertion hole. Thus, the limiting seat is fixed in the connecting frame through the insertion and matching of the insertion hole and the insertion rod. Then, the waterstop is fixed to the connecting frame through the connecting strap.

[0013] Optionally, the surface of the roof slab is provided with a first cavity, the side wall of the roof slab is provided with a first through hole that connects the first cavity to the outside, the first connecting steel bar is provided in the first through hole, and the inner wall of the roof slab at the first cavity is provided with a first sliding groove that communicates with the first through hole. The first driving component is disposed in the first slide groove. The first driving component includes a first movable seat, which is connected to the first connecting steel bar. The first movable seat is slidably adapted to the first slide groove. Both sides of the first movable seat are spherically hinged with first balls. The inner wall of the roof slab at the first slide groove is provided with a first rolling groove adapted to the rolling of the first balls.

[0014] Using the above technical solution, when grouting the first cavity, the concrete slurry inserts the first connecting steel bar into the support structure through the first movable seat, thereby improving the connection stability between the support structure and the roof slab; during the movement of the first movable seat, the first ball rolls along the first roller groove, replacing sliding friction with rolling friction, reducing the friction force when the first movable seat moves, thereby making the first movable seat move smoothly.

[0015] Optionally, one end of the first connecting steel bar is rotatably connected to the first movable seat, a first rotating block is fixedly provided on the inner wall of the first through hole in the roof slab, and a first rotating groove is spirally opened on the outer wall of the first connecting steel bar to slide and adapt to the first rotating block.

[0016] Using the above technical solution, when the first moving seat moves, the first connecting steel bar slides in the first through hole, thereby causing the first connecting steel bar to rotate in the first through hole by the first rotating block sliding along the first rotating groove, thus achieving the effect of the first connecting steel bar rotating forward; the first rotating block is set in the first rotating groove, so that the first connecting steel bar is not easy to disengage from the first through hole.

[0017] Optionally, the surface of the base plate is provided with a second cavity, the side wall of the base plate is provided with a second through hole that connects the second cavity to the outside, the second connecting steel bar is provided in the second through hole, and the inner wall of the base plate at the second cavity is provided with a second sliding groove that communicates with the second through hole. The second drive assembly is disposed in the second slide groove. The second drive assembly includes a second movable seat, which is connected to the second connecting steel bar. The second movable seat is slidably adapted to the second slide groove. Both sides of the second movable seat are ball-jointed with second balls. The inner wall of the bottom plate at the second slide groove is provided with a second rolling groove adapted to the rolling of the second balls.

[0018] Using the above technical solution, when grouting the second cavity, the concrete slurry inserts the second connecting steel bar into the support structure through the second movable seat, thereby improving the connection stability between the support structure and the bottom plate; during the movement of the second movable seat, the second ball rolls along the second roller groove, replacing sliding friction with rolling friction, reducing the friction force when the second movable seat moves, thereby making the movement of the second movable seat smooth.

[0019] Optionally, one end of the second connecting steel bar is rotatably connected to the second movable seat, a second rotating block is fixedly provided on the inner wall of the bottom plate at the second through hole, and a second rotating groove is spirally opened on the outer wall of the second connecting steel bar to slide and adapt to the second rotating block.

[0020] Using the above technical solution, when the second moving seat moves, the second connecting steel bar slides in the second through hole, thereby causing the second connecting steel bar to rotate in the second through hole by the second rotating block sliding along the second rotating groove, thus achieving the effect of the second connecting steel bar rotating forward; the second rotating block is set in the second rotating groove, so that the second connecting steel bar is not easy to disengage from the second through hole.

[0021] Secondly, this application provides a construction method for a combined permanent and temporary basement structure, employing the following technical solution: A combined permanent and temporary basement structure and its construction method, comprising the following steps: S1. Construction of the support structure: After the support structure is completed, the waterproof structure is embedded between the underground continuous wall and the inner lining wall, and then grout is injected into the connecting frame through the grouting port. S2. During the construction of the base slab, grout is injected into the second cavity until it is filled. At this point, the second connecting steel bar connects the support structure to the base slab. S3. Construction of the supporting structure, using lattice columns to support the roof slab; S4. During the construction of the roof slab, grout is injected into the first cavity until the first cavity is filled. At this time, the first connecting steel bar connects the support structure to the roof slab. S5. Secondary construction of the supporting structure: secondary grouting of the lattice columns to transform the temporary supports into permanent supports.

[0022] Optionally, S1 involves roughening the diaphragm wall and the inner lining wall.

[0023] By adopting the above technical solution, the bonding strength of the joint surface is increased by roughening treatment, and the tightness of the support structure connection is improved.

[0024] In summary, this application includes the following beneficial technical effects: Grouting the first cavity causes the first movable seat to drive the first connecting steel bar to be inserted into the support structure, and grouting the second cavity causes the second movable seat to drive the second connecting steel bar to be inserted into the support structure, thereby enhancing the connection strength between the basement structure and the support structure, and thus improving the bearing capacity of the surrounding soil, achieving the effect of reducing safety hazards. Attached Figure Description

[0025] Figure 1 This is a structural schematic diagram of a combined permanent and temporary basement structure according to an embodiment of this application; Figure 2This is a structural schematic diagram illustrating the chamber structure in the embodiments of this application; Figure 3 This is a partial sectional view in an embodiment of this application to illustrate the installation method of the waterstop. Figure 4 This is a partial sectional view in the embodiments of this application to illustrate the installation method of the chamber structure; Figure 5 yes Figure 4 A magnified view of part A in the middle; Figure 6 yes Figure 4 A magnified view of part B in the diagram.

[0026] Explanation of reference numerals in the attached drawings: 1. Roof slab; 11. First connecting reinforcement bar; 111. First rotating groove; 12. First cavity; 13. First through hole; 14. First chute; 15. First roller groove; 16. First rotating block; 2. Base plate; 21. Second connecting reinforcement bar; 211. Second rotating groove; 22. Second cavity; 23. Second through hole; 24. Second chute; 25. Second roller groove; 26. Second rotating block; 3. Support structure; 31. Diaphragm wall; 32. Internal... 4. Lining wall; 5. First drive assembly; 6. First movable seat; 7. First ball bearing; 8. Second drive assembly; 9. Second movable seat; 10. Second ball bearing; 11. Connecting frame; 12. Connecting groove; 13. Grouting hole; 24. Through groove; 15. Limiting seat; 16. Insertion hole; 27. Slot; 38. Limiting groove; 49. Waterstop strip; 20. Connecting strip; 21. Fixing groove; 20. Fixing assembly; 31. Limiting rod; 42. Inclined surface; 53. Return spring. Detailed Implementation

[0027] The following is in conjunction with the appendix Figure 1-6 This application will be described in further detail.

[0028] This application discloses a combined permanent and temporary basement structure.

[0029] refer to Figure 1 and Figure 2 A permanent and temporary combined basement structure includes a chamber structure, a support structure 3 is provided around the chamber structure, a first connecting component and a second connecting component are provided between the support structure 3 and the chamber structure, the support structure 3 includes a diaphragm wall 31 and an inner lining wall 32, and a waterproof structure is provided between the diaphragm wall 31 and the inner lining wall 32.

[0030] A diaphragm wall 31 and an inner lining wall 32 are constructed inside the foundation pit to support the inside of the foundation pit. The waterproof structure inside the support structure 3 can reduce water seepage into the chamber structure.

[0031] refer to Figure 1 and Figure 3There are multiple waterproof structures. In this embodiment, there are four waterproof structures. The waterproof structure includes a connecting frame 6 and a waterstop 7. The connecting frame 6 is a square frame structure. Connecting grooves 61 are opened through the side walls of the connecting frame 6. Grouting holes 62 are opened through the connecting grooves 61 on both sides of the connecting frame 6. Connecting strips 71 are fixedly connected to the side walls of the waterstop 7. The connecting grooves 61 are inserted and matched one by one. A fixing groove 711 is opened through the surface of one side of the connecting strip 71.

[0032] refer to Figure 1 and Figure 3 The connecting frame 6 has a through groove 63 on the side facing the inner lining wall 32, which is connected to the connecting groove 61. A limiting seat 64 is slidably connected in the through groove 63. The limiting seat 64 is inserted into the fixing groove 711. A through hole 641 is provided in the limiting seat 64. Multiple through holes 641 are provided. The inner wall of the connecting frame 6 at the connecting groove 61 has a slot 65 that is inserted into the limiting seat 64.

[0033] refer to Figure 3 The connecting frame 6 has a limiting groove 66 on the inner wall of the slot 65. Multiple limiting grooves 66 are provided, and the number of limiting grooves 66 is the same as the number of insertion holes 641 and corresponds one-to-one. A fixing component 8 is provided in the limiting groove 66. The fixing component 8 includes a limiting rod 81 and a return spring 82. The limiting rod 81 is slidably adapted to the limiting groove 66 and is inserted into the insertion hole 641. The two ends of the return spring 82 are fixed to the limiting rod 81 and the connecting frame 6, respectively. An inclined surface 811 is provided at the end of the limiting rod 81 away from the return spring 82.

[0034] The worker lays the waterstop 7 flat inside the connecting frame 6, then passes the connecting strip 71 through the connecting groove 61, and then pushes the limiting seat 64, which passes through the fixing groove 711. After passing through the fixing groove 711, the limiting seat 64 contacts the inclined surface 811 of the limiting rod 81. The worker continues to push the limiting seat 64, which pulls the limiting rod 81 into the limiting groove 66 through the inclined surface 811. At this time, the return spring 82 is compressed by the pressure of the limiting rod 81. After the limiting rod 81 is aligned with the insertion hole 641, the return spring 82 releases its elasticity and inserts the limiting rod 81 into the insertion hole 641, thereby fixing the waterstop 7 inside the connecting frame 6.

[0035] refer to Figure 2 , Figure 4 and Figure 5The room structure includes a roof slab 1, which is arranged horizontally. A first cavity 12 is formed on the upper surface of the roof slab 1. A first sliding groove 14 is formed on the inner sidewalls of the roof slab 1 around the first cavity 12. A first driving component 4 is provided in the first sliding groove 14. The first driving component 4 includes a first movable seat 41, which is slidably adapted to the first sliding groove 14.

[0036] refer to Figure 5 The upper and lower surfaces of the first movable seat 41 are both ball-jointed with multiple first balls 411. The inner top and bottom walls of the roof plate 1 at the first sliding groove 14 are provided with first rolling grooves 15 that are adapted to the rolling of the first balls 411.

[0037] refer to Figure 1 and Figure 5 The roof slab 1 has a first through hole 13 on each of its four sides, which connects the first cavity 12 to the outside. Each side wall of the roof slab 1 has multiple first through holes 13. A first rotating block 16 is fixedly connected to the inner wall of the roof slab 1 at the first through hole 13. The first rotating block 16 is hemispherical. A first connecting component is set in the first through hole 13. The first connecting component includes a first connecting steel bar 11. The end of the first connecting steel bar 11 away from the support structure 3 is rotatably connected to the first moving seat 41. The outer wall of the first connecting steel bar 11 is spirally provided with a first rotating groove 111 that is slidably adapted to the first rotating block 16.

[0038] After grout is injected into the first cavity 12, the concrete grout squeezes the first movable seat 41, and the first movable seat 41 slides in the first sliding groove 14. The movement of the first movable seat 41 drives the first ball 411 to roll along the first rolling groove 15. At the same time, the first movable seat 41 drives the first connecting steel bar 11 to move in the first through hole 13. When the first connecting steel bar 11 moves in the first through hole 13, the first connecting steel bar 11 causes the first rotating block 16 to slide in the first rotating groove 111. Thus, the first connecting steel bar 11 spirals closer to the support structure 3 in the first through hole 13 until the first connecting steel bar 11 is inserted into the support structure 3.

[0039] refer to Figure 2 , Figure 4 and Figure 6 The chamber structure also includes a base plate 2, which is arranged in a horizontal direction. A second cavity 22 is formed on the upper surface of the base plate 2. A second sliding groove 24 is formed on the inner sidewalls of the base plate 2 around the second cavity 22. A second drive assembly 5 is provided in the second sliding groove 24. The second drive assembly 5 includes a second movable seat 51, which is slidably adapted to the second sliding groove 24.

[0040] refer to Figure 6The upper and lower surfaces of the second movable seat 51 are both ball-jointed with multiple second balls 511. The bottom plate 2 has a second rolling groove 25 on the inner top wall and inner bottom wall of the second sliding groove 24, which is adapted to the rolling of the second balls 511.

[0041] refer to Figure 1 and Figure 6 The bottom plate 2 has second through holes 23 on all four sides of its sidewalls, which connect the second cavity 22 to the outside. Each sidewall of the bottom plate 2 has multiple second through holes 23. A second rotating block 26 is fixedly connected to the inner wall of the bottom plate 2 at the second through hole 23. The second rotating block 26 is hemispherical. A second connecting component is disposed in the second through hole 23. The second connecting component includes a second connecting steel bar 21. The end of the second connecting steel bar 21 away from the support structure 3 is rotatably connected to the second moving seat 51. The outer wall of the second connecting steel bar 21 is spirally provided with a second rotating groove 211 that is adapted to slide with the second rotating block 26.

[0042] After grouting into the second cavity 22, the concrete grout squeezes the second movable seat 51, which slides in the second groove 24. The movement of the second movable seat 51 drives the second ball bearing 511 to roll along the second groove 25. At the same time, the second movable seat 51 drives the second connecting steel bar 21 to move in the second through hole 23. When the second connecting steel bar 21 moves in the second through hole 23, it causes the second rotating block 26 to slide in the second rotating groove 211. Thus, the second connecting steel bar 21 spirals closer to the support structure 3 in the second through hole 23 until the second connecting steel bar 21 is inserted into the support structure 3.

[0043] The implementation principle of a combined permanent and temporary basement structure in this application embodiment is as follows: The connecting strap 71 is passed through the connecting groove 61. Workers push the limiting seat 64, which passes through the fixing groove 711, squeezing the limiting rod 81 into the limiting groove 66 until the limiting rod 81 aligns with the insertion hole 641. Then, the return spring 82 releases its elasticity, inserting the limiting rod 81 into the insertion hole 641. After the waterproof structure is installed, workers inject grout into the second cavity 22, causing the second movable seat 51 to drive the second connecting steel bar 21 into the bottom of the support structure 3. Then, workers inject grout into the first cavity 12, causing the first movable seat 41 to drive the first connecting steel bar 11 into the top of the support structure 3. Through this structure, the connection strength between the support structure 3 and the chamber structure is improved, thereby reducing safety hazards.

[0044] This application also discloses a construction method for a combined permanent and temporary basement structure.

[0045] Includes the following steps: S1. Construction of support structure 3: After the support structure 3 is completed, the waterproof structure is embedded between the underground continuous wall 31 and the inner lining wall 32, and then grout is injected into the connecting frame 6 through the grouting port. S2, during the construction of the base plate 2, grout is injected into the second cavity 22 until the second cavity 22 is filled. At this time, the second connecting steel bar 21 connects the support structure 3 to the base plate 2. S3. Construction of the supporting structure, using lattice columns to support the roof slab 1; S4. During the construction of the roof slab 1, grout is injected into the first cavity 12 until the first cavity 12 is filled. At this time, the first connecting steel bar 11 connects the support structure 3 to the roof slab 1. S5. Secondary construction of the supporting structure: secondary grouting of the lattice columns to transform the temporary supports into permanent supports.

[0046] The embodiments described in this specific implementation are preferred embodiments of this application and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.

Claims

1. A permanent temporary combined basement structure, characterized by: include: The room structure includes a roof slab (1) and a floor slab (2); The support structure (3) is provided with a first connecting component that fixes the two together between the support structure (3) and the roof slab (1), and a second connecting component that fixes the two together between the support structure (3) and the bottom slab (2). The first connecting component includes a first connecting steel bar (11), which is disposed in the roof slab (1). The roof slab (1) is provided with a first driving component (4) for inserting the first connecting steel bar (11) into the support structure (3). The second connecting component includes a second connecting steel bar (21), which is disposed in the base plate (2). The base plate (2) is provided with a second driving component (5) for inserting the second connecting steel bar (21) into the support structure (3). The support structure (3) includes a diaphragm wall (31) and an inner lining wall (32). A waterproof structure is provided between the diaphragm wall (31) and the inner lining wall (32). The waterproof structure includes a connecting frame (6) and a waterstop (7). A connecting groove (61) is provided through the side wall of the connecting frame (6). A connecting strip (71) adapted to the connecting groove (61) is fixedly connected to the edge of the waterstop (7). A grouting hole (62) is provided through the side wall of the connecting frame (6). The connecting frame (6) has a through groove (63) on one side that communicates with the connecting groove (61). A limiting seat (64) is slidably connected in the through groove (63). A fixing groove (711) for the limiting seat (64) to pass through is provided in the connecting strip (71). A fixing component (8) for fixing the limiting seat (64) is provided in the connecting frame (6). The connecting frame (6) has a slot (65) on the inner wall of the connecting groove (61) that is compatible with the limiting seat (64) for insertion, and the connecting frame (6) has a limiting groove (66) on the inner wall of the slot (65); The fixing component (8) is set in the limiting groove (66). The fixing component (8) includes a limiting rod (81) and a return spring (82). The limiting rod (81) is slidably adapted to the limiting groove (66). The two ends of the return spring (82) are fixed to the limiting rod (81) and the connecting frame (6) respectively. An inclined surface (811) is opened on one side of the limiting rod (81). An insertion hole (641) adapted to the insertion of the limiting rod (81) is opened in the limiting seat (64). The surface of the roof slab (1) is provided with a first cavity (12), and the side wall of the roof slab (1) is provided with a first through hole (13) that connects the first cavity (12) to the outside. The first connecting steel bar (11) is provided in the first through hole (13). The inner wall of the roof slab (1) at the first cavity (12) is provided with a first groove (14), and the first groove (14) is connected to the first through hole (13). The first drive assembly (4) is disposed in the first slide groove (14). The first drive assembly (4) includes a first movable seat (41), which is connected to the first connecting steel bar (11). The first movable seat (41) is slidably adapted to the first slide groove (14). The first movable seat (41) is spherically hinged with first balls (411) on both sides. The roof slab (1) has a first rolling groove (15) on the inner wall of the first slide groove (14) that is adapted to the rolling of the first balls (411). One end of the first connecting steel bar (11) is rotatably connected to the first movable seat (41). The roof plate (1) has a first rotating block (16) fixed on the inner wall at the first through hole (13). The outer wall of the first connecting steel bar (11) is spirally provided with a first rotating groove (111) that is slidably adapted to the first rotating block (16). The surface of the base plate (2) is provided with a second cavity (22), and the side wall of the base plate (2) is provided with a second through hole (23) that connects the second cavity (22) to the outside. The second connecting steel bar (21) is provided in the second through hole (23). The inner wall of the base plate (2) at the second cavity (22) is provided with a second sliding groove (24), and the second sliding groove (24) is connected to the second through hole (23). The second drive assembly (5) is disposed in the second slide groove (24). The second drive assembly (5) includes a second movable seat (51), which is connected to the second connecting steel bar (21). The second movable seat (51) is slidably adapted to the second slide groove (24). The two sides of the second movable seat (51) are spherically hinged with second balls (511). The bottom plate (2) has a second rolling groove (25) on the inner wall of the second slide groove (24) that is adapted to the rolling of the second balls (511). One end of the second connecting steel bar (21) is rotatably connected to the second movable seat (51). The bottom plate (2) has a second rotating block (26) fixed on the inner wall of the second through hole (23). The outer wall of the second connecting steel bar (21) is spirally provided with a second rotating groove (211) that is adapted to slide with the second rotating block (26).

2. A construction method of a permanent-temporary combined basement structure using the permanent-temporary combined basement structure according to claim 1, characterized in that: Includes the following steps: S1. Construction of support structure (3): After the support structure (3) is completed, the waterproof structure is embedded between the underground continuous wall (31) and the inner lining wall (32), and then grout is injected into the connecting frame (6) through the grouting hole. S2. Construction of the base plate (2): Grouting is injected into the second cavity (22) until the second cavity (22) is filled. At this time, the second connecting steel bar (21) connects the support structure (3) to the base plate (2). S3. Construction of the supporting structure, using lattice columns to support the roof slab (1); S4. Construction of roof slab (1): Grouting is injected into the first cavity (12) until the first cavity (12) is filled. At this time, the first connecting steel bar (11) connects the support structure (3) with the roof slab (1). S5. Secondary construction of the supporting structure: secondary grouting of the lattice columns to transform the temporary supports into permanent supports.

3. The construction method for a combined permanent and temporary basement structure according to claim 2, characterized in that: In S1, the diaphragm wall (31) and the inner lining wall (32) are roughened.

Citation Information

Patent Citations

  • Permanent and temporary combined basement structure and construction method thereof