Construction method for replaceable vibration damping pad track bed under special working conditions of railway stations

By adopting assembly line construction methods and mechanized equipment under special working conditions at the station, the problems of high labor intensity and slow construction speed in traditional construction were solved, achieving efficient construction of vibration-damping track bed and meeting the requirements for construction quality and speed.

CN118241509BActive Publication Date: 2026-11-17CHINA RAILWAY 12TH BUREAU GRP CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410161430.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-05
Publication Date
2026-11-17
Estimated Expiration
2044-02-05

AI Technical Summary

Technical Problem

Traditional construction methods are labor-intensive, slow, and time-sensitive under the special conditions of stations. Furthermore, manual paving cannot effectively connect different work processes, resulting in low construction efficiency.

Method used

The construction method adopts a flow-line operation approach and utilizes mechanized equipment. By setting up auxiliary concrete support piers and equipment travel tracks, the construction process is optimized to achieve effective connection between various processes and mechanized operation.

Benefits of technology

This reduced the intensity of manual labor, improved construction efficiency, shortened the construction cycle, ensured the smooth replacement of the vibration damping pad track bed, and met the requirements for construction quality and speed.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118241509B_ABST
    Figure CN118241509B_ABST
Patent Text Reader

Abstract

This invention discloses a construction method for a replaceable vibration-damping track bed under special station conditions. It includes construction preparation, fabrication of auxiliary concrete support piers and installation of running rails, installation and testing of base expansion anchor bolts, binding of base reinforcement and side wall reinforcement, installation of base center trench and side formwork, base concrete pouring and curing, installation of limit boss embedded parts and side wall formwork, side wall concrete pouring and curing, laying of base and side wall vibration-damping pads, installation of embedded steel plates on the top of the center trench, track panel assembly, transportation, erection and initial adjustment, binding of track bed reinforcement and fixing of expansion joints, installation of drainage ditch cover angle steel and formwork, track fine-tuning, track bed concrete pouring and curing, and installation of drainage ditch cover plates in the center trench. This invention's construction method allows for mechanized construction, largely overcomes the shortcomings of the aforementioned prior art, saves time and labor, significantly improves construction efficiency, enriches subway construction technology, and has extremely broad application value.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of subway track engineering construction technology, specifically to a construction method for a replaceable vibration damping pad track bed under special station conditions. Background Technology

[0002] With the rapid development of China's economy, urban rail transit has become a major mode of transportation for citizens in many large cities. In terms of quality improvement, higher demands are being placed on subway operating speeds and noise pollution from nearby office and residential areas. The type of vibration-damping track bed is particularly important. During the initial construction phase, when comparing economic and vibration-damping effects, selecting a more cost-effective vibration-damping track bed of the same grade can achieve the required vibration reduction effect, meet noise reduction requirements, ensure passenger comfort, and consider the feasibility of maintenance and operation throughout the entire life cycle. Based on relevant technologies, a new type of replaceable vibration-damping track bed is adopted for track construction.

[0003] During construction, taking into account the structural characteristics of the vibration damping pad track bed itself and the spatial constraints of the platform slab within the station area, the traditional construction method is manual scattering construction, which mainly relies on manual material handling, on-site assembly, and ground pump pouring. Each process must be completed within the entire station area before the next process can be carried out. This method has disadvantages such as high labor intensity, slow construction speed, poor civilized construction, and difficulty in construction organization and quality assurance during tight schedules. Summary of the Invention

[0004] To address the aforementioned technical problems, this invention proposes a construction method for replaceable vibration-damping track bed in special working conditions at railway stations. This method involves a streamlined construction process between different steps, reducing the intensity of heavy manual labor, improving construction efficiency through mechanized equipment, shortening the construction cycle, and ensuring the smooth replacement of the vibration-damping pads.

[0005] This invention is achieved using the following technical solution: a construction method for a replaceable vibration-damping track bed under special working conditions at a station, comprising the following steps: construction preparation, fabrication of auxiliary concrete support piers and installation of running rails, installation and testing of base expansion anchor bolts, binding of base reinforcement and side wall reinforcement, installation of base center ditch and side formwork, base concrete pouring and curing, installation of limit boss embedded parts and side wall formwork, side wall concrete pouring and curing, laying of base and side wall vibration-damping pads, installation of embedded steel plate at the top of center ditch, track panel assembly, transportation, erection and initial adjustment, binding of track bed reinforcement and fixing of expansion joints, installation of drainage ditch cover angle steel and formwork, track fine adjustment, track bed concrete pouring and curing, and installation of drainage ditch cover in the center ditch. The construction preparation steps include the work site relocation step, the CPⅢ control network and benchmark surveying step, and the base roughening and cleaning step.

[0006] Further, the steps for fabricating auxiliary concrete support piers and installing the running rails are as follows: The auxiliary concrete support piers are positioned and laid out. Each auxiliary concrete support pier is vertically arranged with four Φ20 vertical threaded steel bars in a square, with a height of 900mm. The structural base plate is drilled to a depth of 100mm. The top of the vertical threaded steel bars is equipped with right-angle hooks. Three Φ8 stirrups are set at the top, middle and bottom respectively. Two of the vertical threaded steel bars of each auxiliary concrete support pier are welded with threaded rods at the top and extend out of the top surface of the auxiliary concrete support pier for bolt and pressure plate fixing of the equipment running rail. Φ200mm PVC pipes are used as the outer formwork of the auxiliary concrete support piers. Iron wire is used for four-way reinforcement. C40 concrete of the same grade as the track bed sidewall is poured and compacted with a 30 vibrator. The concrete surface of the pier top is smooth.

[0007] Further, the steps for fabricating auxiliary concrete support piers and installing the running rails are as follows: The installed travel rails are equipment travel rails, which are made of 24kg / m steel rails. The center distance between the two rails is 3.1m. The rails are placed on auxiliary concrete support piers, and the bottom of the rails is leveled with rubber pads between them and the auxiliary concrete support piers. Two pre-embedded threaded rods, matching bolts, and pressure plates in each auxiliary concrete support pier effectively connect and fix the rails.

[0008] Further, the steps for pouring and curing the base concrete: Concrete is fed through the manhole discharge chute into the hopper on the rail transport tanker or rail transport flatbed car and transported to the work surface. The rail-laying crane lifts the hopper and pours the concrete from the direction of incoming material from near to far. During the pouring process, the material is symmetrically released with the central water ditch of the base. A φ50mm immersion vibrator is used for vibration, and the vibration time, moving distance and insertion depth are strictly controlled to prevent under-vibration and over-vibration.

[0009] Further, the installation steps for the limiting boss embedded parts and side wall formwork are as follows: Steel limiting bosses are symmetrically embedded in the side walls, with accurate positioning. Φ8 hook nails are installed on the back side and welded firmly to the main reinforcement to prevent displacement. The PVC pipes on the outside of the auxiliary concrete support piers are removed using a handheld cutting machine. The side wall formwork is assembled using 400mm high flat formwork. Before installation, it is ground and coated with release agent. The lines are straight and the fixation is stable. The part between the two retaining walls should not have a narrow top and wide bottom. The expansion joints of polyethylene foam boards are set and fixed perpendicularly to the base position.

[0010] Furthermore, the track panel assembly, transportation, erection, and initial adjustment: The assembled 25-meter rail panels are transported to the work site using a railcar. Two rail-laying cranes then lift the rail panels to the installation position. Support frames are installed at 3-meter intervals along the rail panels. Small steel plates of 200×200×8mm are placed under the vertical support rods to prevent damage to the vibration damping pads due to localized stress. Based on the initial adjustment data, the workers use an L-shaped ruler to perform initial adjustments on the rail panel support frames using a benchmark. The initial adjustment accuracy is controlled to be within ±10mm for elevation, ±2mm for track gauge, 4mm for direction, and within 1 / 1000 for track gauge variation. The rail base slope is controlled between 1 / 30 and 1 / 50.

[0011] Further, the installation steps for the angle steel and formwork of the drainage ditch cover are as follows: The center ditch of the track bed adopts a standardized modular frame template. After the template is assembled, the ditch cover is installed with ∠100×100×6mm angle steel. The angle steel is tightly attached to the ditch template. The longitudinal and transverse joints of the angle steel are spliced ​​with tongue and groove joints. Overlapping is not allowed to form misalignment. The height is controlled by the rail bottom elevation. Self-made auxiliary tools are used to ensure the accuracy of the angle steel in terms of level and position. Ф12 steel bar hooks are welded at equal intervals on the bottom and back of the angle steel. The hooks are welded to the main reinforcement of the track bed to form an integral whole to avoid deformation affecting the installation accuracy of the ditch cover. 30mm thick foam board is pasted on the Z-shaped sealing strip around the top of the side walls. After the track bed is poured, it is removed and polyurethane sealant is filled in for waterproofing.

[0012] Further, the concrete pouring and curing steps for the track bed: After the track panel is finely adjusted, the track bed concrete pouring should be completed within 24 hours. Protect the fasteners and track rails to avoid concrete contamination. The pouring method is to use the track-laying crane to lift the material bucket and pour it continuously in layers from near to far. For curved sections, pour from the inside to the outside. Use a φ50mm immersion vibrator to vibrate each sleeper hole and go deep into the bottom of the sleeper to strengthen the vibration quality and avoid gaps and voids around and at the bottom of the sleeper.

[0013] Further, the concrete pouring and curing steps for the track bed: After curing, the process holes of the track support frame were sealed with fine stone concrete in a timely manner, the equipment running rails were removed, and the equipment was transferred to the front working face. The auxiliary concrete support piers that protruded above the top of the side wall were cut off, and the defects of the track bed were treated.

[0014] Further, the installation steps for the center ditch cover plate of the track bed are as follows: After the center ditch of the track bed is cleaned and inspected and approved, a concrete T-shaped ditch cover is installed. A damping pad is installed under the ditch cover. The damping pad is made of two pieces of 94mm and 82mm spliced ​​together to form an L shape and placed on a ∠100×100×6 angle steel. The thickness is 12mm. The corner of the damping pad should be flat, incomplete and not warped to ensure that the ditch cover can be installed smoothly and stably on the tongue and groove of the track bed. The protruding part under the ditch cover should be slightly lower than the top surface of the damping pad by 10-20mm to prevent the damping pad from moving outward.

[0015] This invention solves the technical problems of current vibration damping pad track bed structures and platform structure limits not meeting the spatial requirements for mechanical construction operations by setting auxiliary concrete support piers as track supports for the track laying equipment. Through optimization of construction process, it solves the problems of manual scattered laying construction under special working conditions in stations, where materials are all handled manually, processes cannot be effectively connected, and construction is time-consuming, labor-intensive, and slow.

[0016] The invention has a simple manufacturing process, readily available materials, and uses waste materials to save costs. The construction method of the invention has the conditions for mechanized construction, solves the aforementioned shortcomings to the greatest extent, saves time and labor during construction, greatly improves construction efficiency, enriches subway construction technology, and has extremely wide promotion value. Attached Figure Description

[0017] Figure 1 This invention provides a process flow diagram for the construction method of replaceable vibration damping pad track bed under special working conditions at stations. Figure 2 This is a schematic diagram of the auxiliary concrete support pier of the present invention; Figure 3 This is an elevation view of the relative position of the auxiliary concrete support pier of the present invention within the platform area and the track bed; Figure 4 This is a plan view showing the relative position of the auxiliary concrete support pier of the present invention within the platform area and the track bed.

[0018] In the diagram: 1. Auxiliary concrete support pier; 11. Structural base slab; 12. Vertical threaded steel bar; 13. Stirrup; 14. Threaded bolt; 15. Pressure plate; 2. Equipment traveling rail; 3. Expansion anchor bolt; 4. Base center ditch; 5. Ditch cover; 6. Vibration damping pad; 7. Angle steel; 8. Damping pad; 9. Track rail; 91. Sleeper; 10. Terminal block. Detailed Implementation

[0019] To better understand the purpose, structure, and function of this invention, the following description, in conjunction with the accompanying drawings, provides a more detailed account of a construction method for a replaceable vibration-damping track bed under special working conditions in railway stations.

[0020] like Figures 1-4 As shown, a construction method for a replaceable vibration-damping track bed under special working conditions in a station includes the following steps: 1. Construction preparation: 1.1 Relocation of the work site The handover work site is inspected to check for leaks, water accumulation, laitance, and debris on the base plate; the base elevation is re-measured; whether the pre-buried pipes are left behind or encroach on the lines; and lighting and power cables are laid.

[0021] 1.2 CPⅢ Control Network and Benchmark Surveying A CPⅢ control network is established based on the control point results submitted by the third-party measurement unit. Control points are arranged in pairs along the line, and the distance between each pair of control points is within 30m to 60m depending on the visibility. For rectangular tunnels in stations, CPⅢ control points are set on the platform end side and side wall. The next step can only be carried out after the CPⅢ control network evaluation results meet the specifications.

[0022] The CPⅢ control network is used to install the benchmarks. One benchmark is installed at a 5-meter interval along the line direction. A separate control benchmark is installed for each of the five key points of the curve. The benchmark data is collected and the track adjustment data is calculated.

[0023] 1.3 Base roughening and cleaning The station structure base plate 11 is roughened to a depth of 5~10mm, with a longitudinal and transverse distance of no more than 100mm. The cleaned base surface has obvious unevenness, and at least 75% of the surface is new. After roughening, the base surface is cleaned of loose ballast, debris, etc., and there is no water accumulation, to ensure effective bonding between the track bed and the structural base plate.

[0024] 2. Fabrication of auxiliary concrete support piers and installation of traveling rails: 2.1 Fabrication of auxiliary concrete support piers Based on the minimum span of the track-laying crane with a wheel spacing of 3.1 meters, and the distance from the center of the track to the platform outline of 1.6 meters, which just meets the equipment clearance, auxiliary concrete support piers 1 are set up symmetrically on both sides of the center of the track with a distance of 1.55 meters on each side and a longitudinal spacing of 1.2 meters. Care should be taken to avoid the position of the embedded parts of the unit plate limit boss. The spacing can be adjusted appropriately.

[0025] The auxiliary concrete support pier 1 is positioned and laid out. Each auxiliary concrete support pier 1 is vertically arranged with four Φ20 vertical threaded steel bars 12 in a square, with a height of 900mm. The structural base plate 11 is drilled and inserted to a depth of 100mm. The top of the vertical threaded steel bars 12 is equipped with a right-angle hook. Three Φ8 stirrups 13 are respectively set in the upper, middle and lower parts. Two of the vertical threaded steel bars 12 in each auxiliary concrete support pier 1 are welded with threaded rods 14 at the top and extend out of the top surface of the auxiliary concrete support pier 1 for bolting and pressure plate 15 to fix the equipment running rail 2. Φ200mm PVC pipe is used as the outer formwork of the auxiliary concrete support pier 1. Iron wire is used for four-way reinforcement. C40 concrete of the same grade as the side wall of the track bed is poured and compacted with a 30 vibrator. The concrete surface of the pier top is smooth.

[0026] 2.2 Installation of running rails The equipment travel rail 2 uses 24kg / m steel rails, with a center distance of 3.1m between the two rails. The rails are placed on auxiliary concrete support piers 1, and the bottom of the rails is leveled with rubber pads between them and the auxiliary concrete support piers 1. Two pre-embedded threaded rods 14 in each auxiliary concrete support pier 1, along with matching bolts and pressure plates 15, effectively connect and fix the rails.

[0027] 3. Installation and inspection of base expansion anchor bolts: In rectangular and horseshoe-shaped tunnel sections, YG2 type M16x245 expansion anchor bolts (3 bolts) are installed, with four bolts per row, a row spacing of 600mm along the track direction, an implantation depth of 135mm, and an exposed height of 110mm, to achieve a tight connection between the track bed and the substructure. For every 5000 expansion anchor bolts, 5 bolts are randomly selected for pull-out testing, and the tensile strength meets the requirement of 19kN.

[0028] 4. Binding of foundation reinforcement and side wall reinforcement: The steel bars are centrally cut and processed in the processing plant, then transported by a rail-laying crane. The base formwork edges are marked according to control benchmarks, and the spacing between longitudinal and transverse steel bars is controlled using rulers and fixtures made from the steel bars. The bars are then tied and welded on-site. After the steel bars are tied, at least four C40 concrete spacers are installed per square meter, with a protective layer thickness of not less than 40mm.

[0029] 5. Installation of the central drainage ditch and side formwork of the base: The central drainage ditch 4 of the base adopts a fully enclosed structure using standardized steel formwork. Before installation, steel bars are welded into the central drainage ditch 4 to form an H-shaped support, which is used to control the elevation and position of the drainage ditch at the bottom of the standardized steel formwork and to prevent it from floating. A release agent is applied to the formwork. The side formwork uses flat steel formwork assembly. One end of the adjustable diagonal brace is inserted into the pre-drilled hole in the formwork rib, and the other end is fixed to the structural base plate 11, ensuring that the formwork is firmly installed and that there are no misalignments. Expansion joints are firmly fixed to prevent deformation.

[0030] Every meter on both sides of the template of the central drainage ditch 4, control points for the elevation of the top surface of the base are attached. Every 10 meters on both sides of the central drainage ditch 4, 12mm diameter threaded steel bars are inserted into the center of the base. Control marks are made and steel wires are used to connect the points longitudinally. The two ends are tightened and fixed firmly, which also serves as the longitudinal control line for the top surface of the base.

[0031] 6. Foundation concrete pouring and curing: Concrete is fed through the manhole discharge chute into the hopper on the rail transport tanker or rail transport flatbed car and transported to the work surface. The rail-laying crane lifts the hopper and pours the concrete from the direction of incoming material from near to far. During the pouring process, the material is symmetrically released with the central water ditch 4 of the base. A φ50mm immersion vibrator is used for vibration. The vibration time, moving distance and insertion depth are strictly controlled to prevent under-vibration and over-vibration.

[0032] The flatness of the base surface requires high precision. After vibration, use an aluminum alloy scraper to fill and level the concrete surface in stages according to the control lines. The concrete surface should be smoothed and finished no less than 3 times. The flatness of the base surface should be 5mm / m. The elevation construction accuracy at the point where the base is close to the center of the drainage ditch 4 and the drainage ditch cover 5 is ±5mm.

[0033] After the concrete is poured and the surface is dry, it should be covered and watered for curing immediately. After the concrete reaches a certain strength, the formwork should be removed in time, and the surface should be covered with geotextile to continue curing for at least 7 days. During the curing period, the concrete surface should always be kept moist.

[0034] 7. Installation of embedded parts for limiting bosses and side wall formwork: Steel limiting bosses are symmetrically embedded in the side walls, accurately positioned, with Φ8 hook nails installed on the back side and firmly welded to the main reinforcement to prevent displacement. The PVC pipe on the outer side of the auxiliary concrete support pier 1 is removed using a handheld cutting machine.

[0035] The side wall formwork uses 400mm high flat formwork assembly. Before installation, it is sanded and coated with release agent. The lines are straight and the formwork is firmly fixed. The section between the two retaining walls should not be narrower at the top and wider at the bottom. The expansion joints of the polyethylene foam board are set and fixed perpendicularly to the base.

[0036] 8. Concrete pouring and curing of side walls: Concrete is transported to the work site using rail transport equipment. The small crane used for track laying lifts the hopper and slides the concrete from the far end to the near end into the side wall under the traveling track using a chute. An immersion vibrator is used for compaction. The compaction point is kept at a certain distance from the section being poured to avoid affecting the stability of the auxiliary concrete support pier 1. The top surface of the wall is set with a 3% outward transverse slope. The top surface of the side wall is smoothed and finished at least 3 times. It is then covered with geotextile for moisture retention and curing for at least 7 days.

[0037] 9. Laying of vibration damping pads for the base and side walls: The elevation and flatness of the top surface of the base were re-measured, and the defects were ground and repaired to ensure that the elevation meets ±5mm and the flatness meets 5mm / m.

[0038] The vibration damping pad 6 consists of four parts: a covering layer, a woven layer, an interlayer, and a damping layer. It mainly provides elasticity through the lower damping layer. The top surface of the track bed base is covered with a 30mm thick vibration damping pad 6, the sides are covered with 27mm thick vibration damping pads 6, the longitudinal sides of the limiting boss are covered with 8mm thick elastic pads, and the bottom and transverse sides are covered with foam boards.

[0039] Cutting of vibration damping pad 6: Cut according to the laying width measured on site, and cut the length according to the unit board length. The edges and corners of the cut vibration damping pad 6 should be straight to ensure the overall appearance after laying.

[0040] Installation of vibration damping pads 6: They should be laid vertically (parallel to the track direction), and the gap width between vibration damping pads 6 should be less than or equal to 10mm. The vibration damping pads 6 should be laid smoothly without bulges. For ease of replacement, rivet splicing is not recommended, and vibration damping pads 6 are not allowed to be spliced ​​under a single track slab.

[0041] Sealing of vibration damping pad 6: After the vibration damping pad 6 is laid in place, it should be wrapped with 2mm thick geotextile and sealed with sealing strip. The bottom vibration damping pad 6 and the side vibration damping pad 6 are sealed with "L" shaped sealing strip, and the edge of the vibration damping pad 6 at the center ditch of the track bed and the upper edge of the side vibration damping pad 6 are sealed with "Z" shaped sealing strip.

[0042] 10. Installation of embedded parts in the steel plate at the top of the central ditch: For the floating slab track bed, a 5mm thick rigid cover plate is placed on the central drainage ditch 4 of the base without a track bed center ditch and then placed on a vibration damping pad 6. Ф12 threaded steel hooks are installed on the cover plate and reliably tied to the track bed slab reinforcement to prevent deformation. This location serves as the load-bearing surface for later jacking operations. To prevent grout leakage at the joints of the cover plates, the gaps between the cover plates should be sealed with tape.

[0043] 11. Track panel assembly, transportation, erection, and initial adjustment: At the track-laying base, the base gantry crane is used to assemble the rail panels according to the rail distribution instructions, strictly controlling the track gauge and sleeper spacing. On curved sections, the rails are cut to the required shortening amount according to the instructions to meet design and specification requirements.

[0044] The assembled 25-meter rail panels were transported to the work site using a railcar. Two rail-laying cranes then lifted the rail panels to the installation position. Support frames were installed at 3-meter intervals along the rail panels, with small 200×200×8mm steel plates placed under the vertical support rods to prevent damage to the vibration damping pads due to localized stress. Workers used a ruler to perform initial adjustments to the rail panel support frames based on the initial adjustment data, ensuring the initial adjustment accuracy was controlled within ±10mm for elevation, ±2mm for track gauge, 4mm for direction, and a track gauge variation rate within 1 / 1000. The rail base slope was controlled between 1 / 30 and 1 / 50.

[0045] 12. Track bed reinforcement binding and expansion joint fixing: After the initial track panel adjustment is completed, the track bed reinforcement is tied according to the unit slabs. The two outermost Ф16 steel bars on both sides of the upper longitudinal layer of the track bed reinforcement are grounding steel bars. At the inner end of each track bed block, a Ф16 transverse steel bar is welded to the upper layer of reinforcement to connect with the four longitudinal grounding steel bars. The transverse and longitudinal grounding steel bars are connected by L-shaped steel bars, with a single-sided weld of not less than 10d and a weld thickness of not less than 6mm. The reinforcement is tied using a reverse figure-eight binding method, ensuring a secure binding. After the reinforcement is tied, the binding points are checked to prevent omissions. Spacers are installed at least four C40 concrete spacers per square meter, with a protective layer thickness of not less than 40mm.

[0046] Grounding terminals 10 are divided into Type I and Type II, symmetrically set at both ends of the expansion joint, with a center distance of 250mm between the terminals. The top surface of the terminal is at the same height as the track bed surface. Grounding terminals 10 are welded to the longitudinal grounding steel bars. The expansion joint is a 30mm polyethylene foam board that is vertically aligned with the butt joint of the two bottom steel plates. Self-made tooling is used to firmly fix the expansion joint board and grounding terminals 10 to ensure that the expansion joint is straight and does not deform, and that the position and height of the terminals are fixed reliably.

[0047] 13. Installation of angle steel and formwork for drainage ditch covers: The center ditch of the track bed uses a standardized modular frame template. After the template is assembled, ∠100×100×6mm angle steel 7 is installed as the ditch cover. The angle steel 7 is tightly attached to the ditch template, and tongue and groove joints are used at the longitudinal and transverse intersections of the angle steel 7 to prevent overlapping and misalignment. The height is controlled by the rail bottom elevation. Self-made auxiliary tools are used to ensure the horizontality and accurate positioning of the angle steel 7. Ф12 steel hooks are welded at equal intervals on the bottom and back of the angle steel 7. The hooks are welded to the main reinforcement of the track bed to form a whole, avoiding deformation that could affect the installation accuracy of the ditch cover 5. A 30mm thick foam board is adhered to the Z-shaped sealing strip at the top of the side walls. After the track bed is poured, this foam board is removed, and polyurethane sealant is used to seal the top for waterproofing.

[0048] 14. Track fine-tuning: The CPⅢ control network was adopted, and the track panels were fine-tuned using a total station and a fine-tuning trolley. Based on on-site measured data, four people simultaneously adjusted the front and rear support frames of the fine-tuning trolley. Elevation and direction were adjusted by adjusting the vertical and lateral support rods of the track panels, with repeated adjustments made first to elevation and then to direction. After the first round of adjustments, a second round of overall measurement and fine-tuning was conducted for confirmation. After fine-tuning, the deviation between the track panels and the design values ​​was controlled within ±5mm in elevation, ±1mm in gauge, and 2mm in direction, with a gauge variation rate within 1 / 1000. A rail base slope detector was used to check each sleeper individually, and the rail base slope was controlled between 1 / 35 and 1 / 45.

[0049] 15. Concrete pouring and curing of the track bed: After the track panel fine-tuning is completed, the track bed concrete pouring should be completed within 24 hours. Protect the fasteners and track rails to prevent concrete contamination. The pouring method involves using a track-laying crane to continuously pour the concrete in layers from near to far, with pouring from the inside to the outside on curved sections. Use a φ50mm immersion vibrator to vibrate each sleeper hole, extending it deep into the bottom of the sleeper to enhance vibration quality and prevent gaps or voids around and at the bottom of the sleeper.

[0050] When pouring concrete to the expansion joints of the track bed, the concrete on both sides of the expansion joint should be poured symmetrically in layers to avoid uneven pressure on the foam plastic board of the expansion joint, which could cause the board to tilt. A self-made finishing tool should be used to control the elevation and flatness of the track bed surface. During the first finishing of the expansion joint, a wooden trowel should be used to compact the concrete on both sides, and the height on both sides should be controlled to avoid misalignment. The overall track bed concrete surface should be smoothed and finished at least three times.

[0051] After the concrete is poured and the surface is dry, it should be covered and watered for curing immediately. After the concrete strength reaches 5MPa, the track support frame and lateral struts should be removed one by one, the central trench formwork should be removed, and the concrete should be covered with geotextile for continued curing for at least 14 days. During the curing period, the concrete surface should always be kept moist.

[0052] The various processes are carried out in a continuous flow. After curing, the process holes of the track support frame are sealed with fine aggregate concrete in a timely manner. The equipment running rail 2 is dismantled and transported to the front working face. The auxiliary concrete support pier 1 that protrudes above the top of the side wall is cut off, and the defects in the track bed are treated.

[0053] 16. Installation of center ditch cover plates for track bed: After the center ditch of the track bed is cleaned and inspected and approved, a concrete T-shaped drainage ditch cover 5 is installed. A damping pad 8 is installed under the drainage ditch cover 5. The damping pad 8 is composed of two pieces, 94mm and 82mm, spliced ​​together to form an L-shape and placed on a ∠100×100×6 angle steel 7, with a thickness of 12mm. The corners of the damping pad 8 should be flat, incomplete, and without warping to ensure that the drainage ditch cover 5 can be installed smoothly and stably on the groove of the track bed. The protruding part under the drainage ditch cover 5 should be slightly lower than the top surface of the vibration damping pad 6 by 10-20mm to prevent the vibration damping pad 6 from shifting outwards.

[0054] This invention solves the problems of current vibration-damping track bed structures, platform structure limitations, spatial constraints hindering mechanized construction, and the need for sequential manual laying operations under special station conditions. These problems include reliance on manual material handling, ineffective workflow coordination, high time and labor costs, and slow construction speed. The invention features a simple manufacturing process, readily available materials, and cost savings through the use of recycled materials. Its construction method allows for mechanized construction, maximizing the elimination of the aforementioned drawbacks. It saves time and labor, significantly improves construction efficiency, enriches subway construction technology, and has extremely broad application value.

[0055] It is understood that the present invention has been described through some embodiments, and those skilled in the art will recognize that various changes or equivalent substitutions can be made to these features and embodiments without departing from the spirit and scope of the invention. Furthermore, under the teachings of the present invention, these features and embodiments can be modified to adapt to specific situations and materials without departing from the spirit and scope of the invention. Therefore, the present invention is not limited to the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of this application are within the protection scope of the present invention.

Claims

1. A construction method for a replaceable vibration-damping track bed under special working conditions in railway stations, characterized in that, It includes the following steps: construction preparation, auxiliary concrete support pier fabrication and running rail installation, base expansion anchor bolt installation and testing, base reinforcement and side wall reinforcement binding, base center ditch and side formwork installation, base concrete pouring and curing, limit boss embedded parts and side wall formwork installation, side wall concrete pouring and curing, base and side wall vibration damping pad laying, center ditch top steel plate embedded parts installation, track panel assembly, transportation, erection and initial adjustment, track bed reinforcement binding and expansion joint fixing, ditch cover angle steel and formwork installation, track fine adjustment, track bed concrete pouring and curing, and track bed center ditch ditch cover installation. The construction preparation steps include the work site relocation step, the CPⅢ control network and benchmark surveying step, and the base roughening and cleaning step. Steps for fabricating auxiliary concrete support piers and installing travel rails: The auxiliary concrete support piers are positioned and laid out. Each auxiliary concrete support pier is vertically arranged with four Φ20 vertical threaded steel bars in a square, with a height of 900mm. The structural base plate is drilled to a depth of 100mm. The top of the vertical threaded steel bars is equipped with right-angle hooks. Three Φ8 stirrups are set at the top, middle and bottom respectively. Two of the vertical threaded steel bars of each auxiliary concrete support pier are welded with threaded rods at the top and extend out of the top surface of the auxiliary concrete support pier for bolt and pressure plate fixing of the equipment running rail. Φ200mm PVC pipes are used as the outer formwork of the auxiliary concrete support piers. Iron wire is used for four-way reinforcement. C40 concrete of the same grade as the track bed sidewall is poured and compacted with a φ30 vibrator. The concrete surface of the pier top is smooth. Installation steps for drainage ditch cover angle steel and formwork: The center ditch of the track bed adopts a standardized modular frame template. After the template is assembled, the ditch cover plate is installed with ∠100×100×6mm angle steel. The angle steel is tightly attached to the ditch template. The longitudinal and transverse joints of the angle steel are spliced ​​with tongue and groove joints. Overlapping is not allowed to form misalignment. The height is controlled by the rail bottom elevation. Self-made auxiliary tools are used to ensure the accuracy of the angle steel in terms of level and position. Ф12 steel hooks are welded at equal intervals on the bottom and back of the angle steel. The hooks are welded to the main reinforcement of the track bed to form an integral whole to avoid deformation affecting the installation accuracy of the ditch cover plate. 30mm thick foam board is pasted on the Z-shaped sealing strip around the top of the side walls. After the track bed is poured, it is removed and polyurethane sealant is filled in for waterproofing. Installation steps for the center ditch cover plate of the track bed: After the center ditch of the track bed is cleaned and inspected and approved, a concrete T-shaped ditch cover is installed. A damping pad is installed under the ditch cover. The damping pad is made of two pieces of 94mm and 82mm spliced ​​together to form an L shape and placed on a ∠100×100×6 angle steel. The thickness is 12mm. The corner of the damping pad should be flat and not warped to ensure that the ditch cover can be installed smoothly and stably on the tongue and groove of the track bed. The protruding part under the ditch cover should be slightly lower than the top surface of the damping pad by 10-20mm to prevent the damping pad from moving outward.

2. The construction method for replaceable vibration-damping track bed under special working conditions of a station according to claim 1, characterized in that, Steps for fabricating auxiliary concrete support piers and installing travel rails: The installed travel rails are equipment travel rails, which are made of 24kg / m steel rails. The center distance between the two rails is 3.1m. The rails are placed on auxiliary concrete support piers, and the bottom of the rails is leveled with rubber pads between them and the auxiliary concrete support piers. Two pre-embedded threaded rods, matching bolts, and pressure plates in each auxiliary concrete support pier effectively connect and fix the rails.

3. The construction method for replaceable vibration-damping track bed under special working conditions of a station according to claim 2, characterized in that, Steps for pouring and curing foundation concrete: Concrete is fed through the manhole discharge chute into the hopper on the rail transport tanker or rail transport flatbed car and transported to the work surface. The rail-laying crane lifts the hopper and pours the concrete from the direction of incoming material from near to far. During the pouring process, the material is symmetrically released with the central water ditch of the base. A φ50mm immersion vibrator is used for vibration, and the vibration time, moving distance and insertion depth are strictly controlled to prevent under-vibration and over-vibration.

4. The construction method for replaceable vibration-damping track bed under special working conditions of a station according to claim 3, characterized in that, Installation steps for the pre-embedded parts of the limiting boss and the side wall formwork: Steel limiting bosses are symmetrically embedded in the side walls, with accurate positioning. Φ8 hook nails are installed on the back side and welded firmly to the main reinforcement to prevent displacement. The PVC pipes on the outside of the auxiliary concrete support piers are removed using a handheld cutting machine. The side wall formwork is assembled using 400mm high flat formwork. Before installation, it is ground and coated with release agent. The lines are straight and the fixation is stable. The part between the two retaining walls should not have a narrow top and wide bottom. The expansion joints of polyethylene foam boards are set and fixed perpendicularly to the base position.

5. The construction method for replaceable vibration-damping track bed under special working conditions of a station according to claim 4, characterized in that, Track panel assembly, transportation, erection, and initial adjustment: The assembled 25-meter rail panels are transported to the work site using a railcar. Two rail-laying cranes then lift the rail panels to the installation position. Support frames are installed at 3-meter intervals along the rail panels. Small steel plates of 200×200×8mm are placed under the vertical support rods to prevent damage to the vibration damping pads due to localized stress. Based on the initial adjustment data, the workers use an L-shaped ruler to perform initial adjustments on the rail panel support frames using a benchmark. The initial adjustment accuracy is controlled to be within ±10mm for elevation, ±2mm for track gauge, 4mm for direction, and within 1 / 1000 for track gauge variation. The rail base slope is controlled between 1 / 30 and 1 / 50.

6. The construction method for replaceable vibration-damping track bed under special working conditions of a station according to claim 5, characterized in that, Track bed concrete pouring and curing steps: After the track panel is finely adjusted, the track bed concrete pouring should be completed within 24 hours. Protect the fasteners and track rails to avoid concrete contamination. The pouring method is to use the track-laying crane to lift the material bucket and pour it continuously in layers from near to far. For curved sections, pour from the inside to the outside. Use a φ50mm immersion vibrator to vibrate each sleeper hole and go deep into the bottom of the sleeper to strengthen the vibration quality and avoid gaps and voids around and at the bottom of the sleeper.

7. The construction method for replaceable vibration-damping track bed under special working conditions of a station according to claim 6, characterized in that, Track bed concrete pouring and curing steps: After curing, the process holes of the track support frame were sealed with fine stone concrete in a timely manner, the equipment running rails were removed, and the equipment was transferred to the front working face. The auxiliary concrete support piers that protruded above the top of the side wall were cut off, and the defects of the track bed were treated.

Citation Information

Patent Citations

  • Subway track-laying by-pass temporary transition device and construction method thereof

    CN110055835A

  • Subway replaceable frame type vibration reduction floating slab ballast bed construction method

    CN111155361A