Performance test method of high voltage inverter under high load

By establishing a random sample library and high-load adaptive classification, designing a multi-level load test plan, and using a steady-state evaluation network to generate comprehensive performance evaluation values, the problem of incomplete performance evaluation of high-voltage inverters in the existing technology is solved and a more accurate performance evaluation.

CN118277795BActive Publication Date: 2024-10-11JIANGSU LI TONG RUI POWER ELECTRONIC TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410694670.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-31
Publication Date
2024-10-11
Estimated Expiration
2044-05-31

AI Technical Summary

Technical Problem

Existing technology cannot dynamically evaluate the performance of high-voltage inverters under various load conditions, resulting in incomplete and inaccurate performance evaluation.

Method used

By establishing a random sample library and high-load adaptive grading, we build N-level load test levels, design test plans for fixed load and changing load, use the steady-state evaluation network to generate calibration test values ​​and steady-state coefficients, and perform weighted calculations to generate comprehensive Performance evaluation value.

Benefits of technology

It provides richer, more comprehensive and more accurate performance evaluation information and avoids inaccurate test results caused by sample selection bias.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118277795B_ABST
    Figure CN118277795B_ABST
Patent Text Reader

Abstract

The present application provides a performance test method for a high-voltage inverter under high load, and relates to the field of performance test technology. The method includes: establishing a random sample library, performing adaptive grading of high load, establishing N-level load test levels, establishing a test plan, performing sample performance testing to establish a performance test data set, configuring an evaluation function, inputting the performance test data set into an evaluation network to generate calibrated test values ​​and steady-state coefficients corresponding to each test plan, performing weighted calculations, and finally generating performance test results for the high-voltage inverter to be tested. The present application can solve the problems that the samples selected in the prior art lack extensiveness, cannot dynamically perform load testing, and cannot comprehensively evaluate the performance of high-voltage inverters under a variety of load conditions, resulting in incomplete performance evaluation and inaccurate performance testing, avoids the problem of inaccurate test results caused by sample selection bias, and provides richer, more comprehensive, and more accurate performance evaluation information.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of performance testing, and in particular to a performance testing method for a high-voltage inverter under high load. Background Art

[0002] With the continuous advancement of industrial technology, high-voltage inverters are increasingly used in manufacturing, petrochemical, water conservancy and other fields, especially in situations that require high-performance power transmission and energy-saving operation. In order to ensure that high-voltage inverters can operate stably under high load conditions and meet the requirements of industrial production for equipment reliability, efficiency and response speed, the corresponding performance testing methods are particularly important.

[0003] At present, traditional high-voltage inverter testing only focuses on performance under fixed load conditions, but ignores the situation where the load will continue to change during actual use.

[0004] In summary, the samples selected by the prior art lack comprehensiveness, cannot perform load testing dynamically, and cannot comprehensively evaluate the performance of high-voltage inverters under various load conditions, resulting in incomplete performance evaluation and inaccurate performance testing. Summary of the invention

[0005] The purpose of this application is to provide a performance testing method for a high-voltage inverter under high load, so as to solve the problem that the samples selected in the prior art lack extensiveness, cannot perform load testing dynamically, and cannot comprehensively evaluate the performance of the high-voltage inverter under various load conditions, resulting in incomplete performance evaluation and inaccurate performance testing.

[0006] In view of the above problems, the present application provides a performance testing method for a high-voltage inverter under high load.

[0007] The present application provides a performance test method for a high-voltage inverter under high load, wherein the method comprises: establishing a random sample library, wherein the random sample library is a sample library constructed after selecting a high-voltage inverter sample to be tested according to a random sampling rule, and performing basic parameter information collection of the high-voltage inverter; performing adaptive grading of high load, establishing N-level load test levels, wherein the N-level load test levels correspond to N-1 load change intervals, and the adaptive grading is obtained by analyzing the basic parameter information; establishing a test scheme based on the N-level load test levels, wherein the test scheme includes a fixed load test scheme and a variable load test scheme, and performing sample performance testing in the random sample library with the test scheme to establish a performance test data set; configuring an evaluation coefficient mapped to a fixed load and a variable load, inputting the performance test data set into a steady-state evaluation network, and generating calibrated test values ​​and steady-state coefficients corresponding to each test scheme; performing weighted calculation according to the calibrated test value, steady-state coefficient and evaluation coefficient to generate a comprehensive performance evaluation value, and generating a performance test result of the high-voltage inverter to be tested based on the comprehensive performance evaluation value, the calibrated test value and the steady-state coefficient.

[0008] One or more technical solutions provided in this application have at least the following technical effects or advantages:

[0009] By establishing a random sample library, the random sample library is a sample library constructed after selecting the high-voltage inverter samples to be tested according to random sampling rules, and performing basic parameter information collection of the high-voltage inverter; performing high-load adaptive grading, establishing N-level load test levels, wherein the N-level load test levels correspond to N-1 load change intervals, and the adaptive grading is obtained by analyzing the basic parameter information; establishing a test plan based on the N-level load test level, wherein the test plan includes a fixed load test plan and a variable load test plan, and executing the sample performance test in the random sample library with the test plan to establish a performance test data set; configuring the evaluation coefficients mapped with the fixed load and the variable load, and The performance test data set is input into the steady-state evaluation network to generate calibrated test values ​​and steady-state coefficients corresponding to each test scheme; weighted calculation is performed according to the calibrated test values, steady-state coefficients and evaluation coefficients to generate a comprehensive performance evaluation value, and the performance test results of the high-voltage inverter to be tested are generated based on the comprehensive performance evaluation value, the calibrated test value and the steady-state coefficient, which effectively solves the problems that the samples selected in the prior art lack extensiveness, cannot dynamically perform load testing, and cannot comprehensively evaluate the performance of the high-voltage inverter under various load conditions, resulting in incomplete performance evaluation and inaccurate performance testing, avoids the problem of inaccurate test results caused by sample selection bias, and provides richer, more comprehensive and more accurate performance evaluation information.

[0010] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented according to the contents of the specification, and in order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are specifically cited below. It should be understood that the content described in this section is not intended to identify the key or important features of the embodiments of the present application, nor is it intended to limit the scope of the present application. Other features of the present application will become easy to understand through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] In order to more clearly illustrate the technical solutions in the present application or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying any creative work.

[0012] Figure 1 This is a flow chart of a performance testing method for a high-voltage inverter under high load according to the present invention. DETAILED DESCRIPTION

[0013] The present application provides a performance testing method for a high-voltage inverter under high load, thereby solving the problem that the samples selected in the prior art lack comprehensiveness, cannot perform load testing dynamically, and cannot comprehensively evaluate the performance of the high-voltage inverter under various load conditions, resulting in incomplete performance evaluation and inaccurate performance testing. It avoids the problem of inaccurate test results caused by sample selection bias, and provides richer, more comprehensive and more accurate performance evaluation information.

[0014] Below, the technical solutions in the present application will be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments of the present application. It should be understood that the present application is not limited to the example embodiments described herein. Based on the embodiments of the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application. It should also be noted that, for the convenience of description, only the parts related to the present application are shown in the accompanying drawings, rather than all of them.

[0015] Please refer to the attached Figure 1 The present application provides a performance test method for a high-voltage inverter under high load, wherein the method specifically comprises the following steps:

[0016] S1: Establishing a random sample library, wherein the random sample library is a sample library constructed by selecting high-voltage inverter samples to be tested according to a random sampling rule, and performing basic parameter information collection of the high-voltage inverter;

[0017] Specifically, methods such as random number generators or drawing lots can be used to ensure the randomness of sample selection. Ensure that the probability of each high-voltage inverter being selected is equal to avoid bias. Randomly select samples from all high-voltage inverters to be tested. Record the unique identifier or number of the selected high-voltage inverter. Organize the selected high-voltage inverter sample information into a database or list. Basic parameters include model, rated power, rated voltage, rated current, manufacturer, production date, and operating environment, such as temperature, humidity, etc. For each high-voltage inverter in the random sample library, write them into the information library one by one according to the information collection table.

[0018] S2: Execute adaptive grading of high load, establish N-level load test levels, wherein the N-level load test levels correspond to N-1 load change intervals, and the adaptive grading is obtained by analyzing the basic parameter information;

[0019] Specifically, rated power, rated voltage, rated current, etc. can be used as the basis for load classification. These parameters will directly affect the load capacity of the high-voltage inverter. According to actual needs, determine the appropriate number of load test levels N. This number should be able to reflect the performance of the high-voltage inverter under different loads. Use statistical analysis and data mining techniques, such as cluster analysis and principal component analysis, to process basic parameter information. Divide N-1 load change intervals according to parameter distribution and actual needs. These intervals should be able to cover the actual working load range that the high-voltage inverter may encounter. Based on the divided load change intervals, establish an adaptive classification model. This model can automatically determine the load level to which the high-voltage inverter belongs based on its parameter information. The model can use machine learning algorithms, such as decision trees and random forests, to improve the accuracy and efficiency of classification. Use a part of high-voltage inverter samples with known performance to verify the model to ensure the accuracy and reliability of classification. Adjust and optimize the model based on the verification results to improve its prediction performance. For new high-voltage inverter samples, use the established adaptive classification model for automatic classification.

[0020] S3: establishing a test plan based on the N-level load test level, wherein the test plan includes a fixed load test plan and a variable load test plan, and executing a sample performance test in a random sample library with the test plan to establish a performance test data set;

[0021] Specifically, the test scheme for fixed load includes selecting several key load levels from N load test levels, which should be representative of the working conditions of the high-voltage inverter under different loads. For each selected load level, set specific test conditions, such as input voltage, frequency, ambient temperature, etc. Ensure that the power supply, load simulator, measuring instruments and other equipment required for the test are complete and calibrated. Set the high-voltage inverter to operate at the selected load level. Monitor and record key performance indicators, such as efficiency, temperature rise, harmonic distortion, etc. The test scheme for variable load includes designing a continuous load change mode from low to high or from high to low according to N-1 load change intervals. Different load change modes such as step change and ramp change can be designed. Determine the parameters and performance indicators that need to be monitored during the load change process. Ensure that the test equipment can simulate complex load changes and record data in real time. Make the high-voltage inverter operate under the designed load change mode. Monitor and record the performance indicators of the high-voltage inverter during the load change process in real time. Randomly select a certain number of high-voltage inverters from the random sample library as test objects. For each selected sample, test it according to the fixed load and variable load test schemes mentioned above. Record the performance indicators of each sample at each load level and load variation mode in detail. Perform statistical analysis and comparison on the test data to evaluate the performance differences between different samples. Organize the test data of all samples into a standardized data set. Perform quality checks on the data set to ensure the accuracy and completeness of the data.

[0022] S4: configuring evaluation coefficients mapped with fixed loads and variable loads, inputting the performance test data set into a steady-state evaluation network, and generating calibration test values ​​and steady-state coefficients corresponding to each test scheme;

[0023] Specifically, for fixed loads and variable loads, evaluation coefficients are configured respectively. These coefficients are used to quantify the weights of different performance indicators in the overall evaluation. For example, for fixed loads, the performance indicators of interest include efficiency, power factor, harmonic distortion, etc.; for variable loads, dynamic response speed, stability, etc. also need to be concerned. The steady-state evaluation network is a model used to process performance test data sets and output calibrated test values ​​and steady-state coefficients. This network can be a weighted scoring system or a machine learning model such as a neural network or a support vector machine. The input of the network is the various performance indicators in the performance test data set, and the output is the calibrated test value and steady-state coefficient. The collected performance test data set is input into the steady-state evaluation network. The data set should contain various performance indicators of the high-voltage inverter under each test scheme. The steady-state evaluation network will generate a calibrated test value for each test scheme based on the input performance indicators and evaluation coefficients. This value is an overall evaluation of the performance of the high-voltage inverter under the test scheme. At the same time, the network will also generate a steady-state coefficient to represent the performance stability of the high-voltage inverter when it is in steady-state operation.

[0024] S5: Perform weighted calculation according to the calibration test value, steady-state coefficient and evaluation coefficient to generate a comprehensive performance evaluation value, and generate a performance test result of the high-voltage inverter to be tested based on the comprehensive performance evaluation value, calibration test value and steady-state coefficient.

[0025] Specifically, multiply the calibrated test values ​​of each test scheme, including fixed load and variable load, with their corresponding evaluation coefficients to obtain the weighted calibrated test values ​​of the test scheme. Next, multiply the steady-state coefficient with its corresponding evaluation coefficient to obtain the weighted steady-state coefficient. Finally, add all weighted calibrated test values ​​and weighted steady-state coefficients to obtain a comprehensive performance evaluation value. This value comprehensively considers the performance of the high-voltage inverter under different test schemes and the stability of steady-state operation. The comprehensive performance evaluation value, the calibrated test values ​​and steady-state coefficients of each test scheme are organized into a detailed performance test report. List the specific performance indicators, calibrated test values, steady-state coefficients of each test scheme and their contribution to the comprehensive performance evaluation value.

[0026] Furthermore, step S4 of the present application also includes:

[0027] Inputting the test plan into the steady-state evaluation network to perform classifier initialization in the steady-state evaluation network;

[0028] After the performance test data set is input into the steady-state evaluation network, the data is classified by a classifier, and the classification results are respectively sent to M sub-classifiers mapped one-to-one with the classification results;

[0029] For any one of the M sub-classifiers, perform extreme value extraction of the corresponding classification result, use the minimum value extraction result as the calibration test value, establish a basic penalty coefficient based on the difference between the maximum value and the calibration test value, establish an additional penalty coefficient based on the distribution discrete state of the data relative to the calibration test value, compensate the basic penalty coefficient with the additional penalty coefficient, and establish a steady-state coefficient;

[0030] Output the calibration test values ​​and steady-state coefficients corresponding to all M sub-classifiers.

[0031] Specifically, the test schemes of fixed load and variable load are input into the steady-state evaluation network. The classifier is initialized in the network. The function of this classifier is to classify the performance test data set according to the set rules or features. When the performance test data set is input into the steady-state evaluation network, the classifier will classify the data set according to the preset rules or algorithms. The classification results will be sent to M sub-classifiers mapped one by one with the classification results. Each sub-classifier is responsible for processing a specific type of data. For each sub-classifier, it will process the corresponding classified data. The minimum value of the performance index is extracted from the classified data, and this minimum value is used as the calibration test value of the category. The difference between the maximum value of the performance index in the category and the calibration test value, that is, the minimum value, is calculated. This difference reflects the fluctuation range of the performance in the category and can be used as the basic penalty coefficient. The data distribution discrete state relative to the calibration test value is analyzed. If the data distribution is relatively discrete, it means that the performance stability is poor, and an additional penalty coefficient is added to reflect this instability. The additional penalty coefficient is combined with the basic penalty coefficient to obtain the steady-state coefficient. This steady-state coefficient takes into account both the fluctuation range of the performance and the discreteness of the data, and can more comprehensively evaluate the steady-state performance of the high-voltage inverter. The calibration test values ​​and steady-state coefficients corresponding to all M sub-classifiers are output. These output values ​​can be used as the basic data for subsequent comprehensive performance evaluation.

[0032] Furthermore, the present application also includes:

[0033] Inputting the steady-state coefficient into an additional test matching model and outputting an additional extraction number;

[0034] Constructing an evaluation interval with the subclassifier, wherein the evaluation interval includes a reward interval less than a calibrated test value, a stable interval constructed by the calibrated test value and the mean, a basic penalty interval constructed by the mean and the maximum value, and an abnormal penalty interval greater than the maximum value;

[0035] Performing an additional sampling test with the additional sampling number, and evaluating the sampling test result with an evaluation interval;

[0036] The comprehensive performance evaluation value compensation is performed according to the evaluation result.

[0037] Specifically, the steady-state coefficient is input into an additional test matching model. This model is a pre-trained algorithm used to predict or recommend further additional tests based on the steady-state coefficient. The additional test matching model will output one or more additional draws based on the input steady-state coefficient. These additional draws represent the number of times, types, or specific parameters that require additional performance tests. Subclassifiers are used to construct evaluation intervals. Including, reward intervals, the range in which the performance index is less than the calibration test value, indicating that the performance is better than expected. Stable intervals, the performance index is between the calibration test value and the mean, indicating that the performance is stable and in line with expectations. Basic penalty intervals, the performance index is between the mean and the maximum value, indicating that the performance is slightly lower than the best state, but still within an acceptable range. Constant penalty intervals, the range in which the performance index is greater than the maximum value, indicating that the performance is abnormal and requires further attention or adjustment. Additional performance tests are performed based on the additional draws. The results of the additional draw test are compared with the evaluation interval. According to the interval in which the test result falls, a corresponding evaluation is given, such as reward, stability, basic penalty, or abnormal penalty. According to the evaluation results, the comprehensive performance evaluation value calculated previously is compensated. If the additional test results are excellent and fall into the reward range, the comprehensive performance evaluation value can be appropriately increased. If the additional test results are poor and fall into the penalty range, the comprehensive performance evaluation value needs to be reduced. The specific value or proportion of compensation can be determined according to the actual situation and preset rules.

[0038] Furthermore, step S3 of the present application also includes:

[0039] Calculating parameter key values ​​for parameters characterizing performance data of the high-voltage inverter, wherein the parameter key value is a parameter key ratio calculated using historical data, and the sum of the parameter key values ​​of all parameters is 1;

[0040] All parameters are sorted in order according to the parameter key values, and the parameter key values ​​are accumulated in order, and the separation parameters are located by the preset threshold and the accumulation result;

[0041] Determine whether the parameter key value of the separation parameter and the parameter key value of the next sequence meet a difference threshold;

[0042] If not, the next-order parameter is updated to a separation parameter, and the updated separation parameter and the preceding parameter are used as key parameters;

[0043] The performance test data set is established by monitoring the key parameters of the performance test process.

[0044] Specifically, historical performance data of high-voltage inverters are collected. These data are analyzed to determine which parameters have a critical impact on the performance of the inverter. For each parameter, its importance or criticality ratio in the historical data is calculated, and this ratio is called the parameter key value. Ensure that the sum of the key values ​​of all parameters is 1, so that the key value of each parameter represents its weight in the overall performance evaluation. Use the calculated parameter key values ​​to sort all parameters from the most critical to the least critical. The sorted parameter key values ​​are sequentially accumulated. A preset threshold is set, which is a value between 0 and 1 set by a technician in this field. When the accumulated key value reaches or exceeds this threshold, the accumulation is stopped, and the corresponding parameter at this time is defined as the separation parameter. Check whether the difference between the key value of the separation parameter and the next-rank parameter meets a preset difference threshold. If the difference does not meet the preset difference threshold, that is, the key values ​​of the two are not much different, the next-rank parameter is also regarded as a key parameter and updated to a new separation parameter. Repeat this process until the difference between the key value of the separation parameter and the next-rank parameter meets the difference threshold. The key parameters finally determined include the original separation parameters and all key parameters added during the judgment process. These key parameters are the indicators that need to be monitored during the performance test. When performing the high-voltage inverter performance test, focus on monitoring the key parameters determined above. Record the real-time data of these key parameters during the test.

[0045] Furthermore, the present application also includes:

[0046] If satisfied, the current separation parameter is retained, and the current separation parameter and the preceding parameter are used as key parameters;

[0047] The performance test data set is established by monitoring the key parameters of the performance test process.

[0048] Specifically, since the difference between the key value of the separation parameter and the key value of the parameter after it meets the difference threshold, it means that the separation parameter is indeed an important node in terms of performance impact. Keep the current separation parameter as the defining point of the key parameter. The separation parameter and all its predecessor parameters, that is, the parameters before the separation parameter in the sorting, are regarded as key parameters. These parameters play an important role in performance evaluation, and their changes have a significant impact on the overall performance of the high-voltage inverter. When performing the performance test of the high-voltage inverter, the key parameters determined above are monitored in real time. Set up corresponding sensors and data acquisition systems to ensure that the changes of these key parameters can be accurately captured. During the monitoring process, record the real-time data of all key parameters. These data will be integrated into a performance test data set for subsequent performance evaluation, fault prediction, optimization decision-making, etc. The data set should include timestamps, parameter names, parameter values, and possible other relevant information to facilitate subsequent data analysis and processing.

[0049] Furthermore, step S3 of the present application also includes:

[0050] Calling N-1 load change intervals, wherein the N-1 load change intervals are load change intervals established with adjacent N load test levels;

[0051] Perform uniform change distribution based on the interval extreme value for N-1 load change intervals, and establish a test plan for the first load change based on the uniform change distribution result;

[0052] Perform non-uniform change distribution based on the interval extreme value for N-1 load change intervals, and establish a test plan for the second load change based on the non-uniform change distribution result;

[0053] The establishment of the test scheme for changing load is completed according to the test scheme for the first changing load and the test scheme for the second changing load.

[0054] Specifically, the N load levels that need to be tested for the high-voltage inverter are identified. These levels are determined based on the actual application scenario. Since there are N load levels, there will be N-1 change intervals between adjacent load levels. For example, if there are 3 load levels, light load, medium load, and heavy load, then there will be 2 change intervals, light load to medium load, and medium load to heavy load. For each load change interval, determine its extreme values, that is, the minimum load and maximum load of each interval. Achieve uniform load changes within these intervals. For example, if a certain interval is from 50% load to 75% load, then the test points can be designed to increase uniformly in steps of 5% or 10%, such as 50%, 55%, 60% to 75%. Based on this uniform distribution, a test plan for the first change load is formulated, which will include multiple test points that increase or decrease in fixed steps between each load level. Unlike uniform distribution, non-uniform distribution will perform more intensive testing at some load points and sparse testing at other points. This distribution is determined based on factors such as previous test experience, failure history, and performance degradation areas. For example, if historical data shows that performance fluctuates greatly around 65% load, it makes sense to set more test points in this area. Based on the results of the non-uniform distribution, develop a test plan for the second variable load. Combine the test plan for the first variable load with the test plan for the second variable load to form a comprehensive test plan. This test plan should cover all critical load points and potential performance fluctuation areas to ensure that the performance of the high-voltage inverter under various load conditions can be fully verified.

[0055] Furthermore, the present application also includes:

[0056] Determining whether the steady-state coefficient meets a preset steady-state threshold;

[0057] If the preset steady-state threshold cannot be met, a test warning is generated;

[0058] Performance test management is performed according to the test warning.

[0059] Specifically, the steady-state coefficient during the operation of the high-voltage inverter is obtained. This steady-state coefficient is obtained through real-time monitoring and data collection. Then, this steady-state coefficient is compared with the preset steady-state threshold. The preset steady-state threshold is a range or specific value set according to the design requirements, industry standards or historical data of the inverter, which is used to determine whether the inverter is in a stable working state. If the steady-state coefficient does not meet the preset steady-state threshold, that is, it exceeds or falls below the threshold range, it means that there is a problem or instability in the performance of the high-voltage inverter. In this case, a test warning is generated. This warning can be a signal, message or record to notify the management personnel or the test team. The test warning should contain specific information about the abnormal steady-state coefficient, such as abnormal value, occurrence time, possible cause, etc. The warning can be sent to relevant personnel through sound, light, email, text message or other communication methods. Once the test warning is received, the performance test management team should respond immediately. First verify the accuracy of the warning information and check the relevant data and system status. Then, analyze the possible causes of the abnormal steady-state coefficient, which include hardware failure, software error, external interference, etc. Based on the analysis results, formulate corresponding measures to solve the problem, such as repair, replacement of parts, adjustment of control parameters, etc.

[0060] Furthermore, the present application also includes:

[0061] Perform abnormal maintenance records and establish abnormal statistics for non-high-voltage inverters themselves;

[0062] Sensitive concerns of the performance test are generated according to the abnormal statistics, and subsequent performance test management is performed based on the sensitive concerns.

[0063] Specifically, when an abnormality occurs in a high-voltage inverter or other related equipment, respond and record the abnormality. The abnormal maintenance record should include information such as the time, location, specific phenomenon, possible causes, measures taken, and maintenance results of the abnormality. In addition to recording the abnormality of the high-voltage inverter itself, it is also necessary to pay attention to the abnormalities of other equipment or systems related to it. These non-inverter abnormalities include power supply fluctuations, excessively high or low ambient temperature, external interference, etc. By analyzing the abnormal statistical data, it is possible to identify which factors most affect the performance of the high-voltage inverter. These factors become sensitive points of concern in subsequent performance tests, that is, aspects that need special attention and monitoring during testing. When performing performance testing, set the corresponding test conditions and monitoring indicators according to the identified sensitive points of concern. For example, if power supply fluctuations are identified as a sensitive factor, different power supply conditions should be simulated in the test to observe the performance of the high-voltage inverter. By focusing on the sensitive points of concern, the performance of the high-voltage inverter can be more effectively evaluated and potential problems can be discovered in a timely manner.

[0064] In summary, the performance testing method of a high-voltage inverter under high load provided by the present application has the following technical effects:

[0065] By establishing a random sample library, the random sample library is a sample library constructed after selecting the high-voltage inverter samples to be tested according to random sampling rules, and performing basic parameter information collection of the high-voltage inverter; performing high-load adaptive grading, establishing N-level load test levels, wherein the N-level load test levels correspond to N-1 load change intervals, and the adaptive grading is obtained by analyzing the basic parameter information; establishing a test plan based on the N-level load test level, wherein the test plan includes a fixed load test plan and a variable load test plan, and executing the sample performance test in the random sample library with the test plan to establish a performance test data set; configuring the evaluation coefficients mapped with the fixed load and the variable load, and The performance test data set is input into the steady-state evaluation network to generate calibrated test values ​​and steady-state coefficients corresponding to each test scheme; weighted calculation is performed according to the calibrated test values, steady-state coefficients and evaluation coefficients to generate a comprehensive performance evaluation value, and the performance test results of the high-voltage inverter to be tested are generated based on the comprehensive performance evaluation value, the calibrated test value and the steady-state coefficient, which effectively solves the problems that the samples selected in the prior art lack extensiveness, cannot dynamically perform load testing, and cannot comprehensively evaluate the performance of the high-voltage inverter under various load conditions, resulting in incomplete performance evaluation and inaccurate performance testing, avoids the problem of inaccurate test results caused by sample selection bias, and provides richer, more comprehensive and more accurate performance evaluation information.

[0066] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

[0067] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application belong to the scope of the present application and its equivalent technology, the present application is also intended to include these modifications and variations.

Claims

1. A performance test method for a high voltage inverter under high load, characterized in that: The method comprises: Establishing a random sample library, wherein the random sample library is a sample library constructed after selecting high-voltage inverter samples to be tested according to a random sampling rule, and performing basic parameter information collection of the high-voltage inverter; Performing adaptive grading of high loads to establish N-level load test levels, wherein the N-level load test levels correspond to N-1 load variation intervals, and the adaptive grading is obtained by analyzing the basic parameter information; A test scheme is established based on the N-level load test levels, wherein the test scheme includes a fixed load test scheme and a variable load test scheme, and the sample performance test in the random sample library is executed with the test scheme to establish a performance test data set. The fixed load test scheme includes selecting multiple key load levels from the N-level load test levels, setting voltage, frequency, and ambient temperature test conditions for each selected load level, setting the high-voltage inverter to operate at the selected load level, and monitoring and recording key performance indicators. The variable load test scheme includes designing a step change mode and a ramp change mode of the load from low to high or from high to low according to N-1 load change intervals, and the high-voltage inverter operates in the designed load change mode, and real-time monitoring and recording of the performance indicators of the high-voltage inverter during the load change process; Configure evaluation coefficients mapped with fixed loads and variable loads, input the performance test data set into a steady-state evaluation network, and generate calibration test values ​​and steady-state coefficients corresponding to each test scheme; Performing weighted calculation according to the calibration test value, steady-state coefficient and evaluation coefficient to generate a comprehensive performance evaluation value, and generating a performance test result of the high-voltage inverter to be tested based on the comprehensive performance evaluation value, the calibration test value and the steady-state coefficient; The step of inputting the performance test data set into the steady-state evaluation network to generate calibration test values ​​and steady-state coefficients corresponding to each test scheme includes: Inputting the test plan into the steady-state evaluation network to perform classifier initialization in the steady-state evaluation network; After the performance test data set is input into the steady-state evaluation network, the data is classified by a classifier, and the classification results are respectively sent to M sub-classifiers mapped one-to-one with the classification results; For any one of the M sub-classifiers, perform extreme value extraction of the corresponding classification result, use the minimum value extraction result as the calibration test value, establish a basic penalty coefficient based on the difference between the maximum value and the calibration test value, establish an additional penalty coefficient based on the distribution discrete state of the data relative to the calibration test value, compensate the basic penalty coefficient with the additional penalty coefficient, and establish a steady-state coefficient; Output the calibration test values ​​and steady-state coefficients corresponding to all M sub-classifiers.

2. The method according to claim 1, characterized in that The weighted calculation is performed according to the calibration test value, the steady-state coefficient and the evaluation coefficient to generate a comprehensive performance evaluation value, and the performance test result of the high-voltage inverter to be tested is generated based on the comprehensive performance evaluation value, the calibration test value and the steady-state coefficient, including: Inputting the steady-state coefficient into an additional test matching model and outputting an additional extraction number; Constructing an evaluation interval with the subclassifier, wherein the evaluation interval includes a reward interval less than a calibrated test value, a stable interval constructed by the calibrated test value and the mean, a basic penalty interval constructed by the mean and the maximum value, and an abnormal penalty interval greater than the maximum value; Performing an additional sampling test with the additional sampling number, and evaluating the sampling test result with an evaluation interval; The comprehensive performance evaluation value compensation is performed according to the evaluation result.

3. The method according to claim 1, characterized in that The performing of the sample performance test in the random sample library according to the test scheme to establish a performance test data set includes: Calculating parameter key values ​​for parameters characterizing performance data of the high-voltage inverter, wherein the parameter key value is a parameter key ratio calculated using historical data, and the sum of the parameter key values ​​of all parameters is 1; All parameters are sorted in order according to the parameter key values, and the parameter key values ​​are accumulated in order, and the separation parameters are located by the preset threshold and the accumulation result; Determine whether the parameter key value of the separation parameter and the parameter key value of the next sequence meet a difference threshold; If not, the next-order parameter is updated to a separation parameter, and the updated separation parameter and the preceding parameter are used as key parameters; The performance test data set is established by monitoring the key parameters of the performance test process.

4. The method according to claim 3, characterized in that The determining whether the parameter key value of the separation parameter and the parameter key value of the next sequence meet the difference threshold further includes: If satisfied, the current separation parameter is retained, and the current separation parameter and the preceding parameter are used as key parameters; The performance test data set is established by monitoring the key parameters of the performance test process.

5. The method according to claim 1, characterized in that The test scheme is established based on the N-level load test level, wherein the test scheme includes a fixed load test scheme and a variable load test scheme, including: Calling N-1 load change intervals, wherein the N-1 load change intervals are load change intervals established with adjacent N load test levels; Perform uniform change distribution based on the interval extreme value for N-1 load change intervals, and establish a test plan for the first load change based on the uniform change distribution result; Perform non-uniform change distribution based on the interval extreme value for N-1 load change intervals, and establish a test plan for the second load change based on the non-uniform change distribution result; The establishment of the test scheme for changing load is completed according to the test scheme for the first changing load and the test scheme for the second changing load.

6. The method according to claim 1, characterized in that The method further comprises: Determining whether the steady-state coefficient meets a preset steady-state threshold; If the preset steady-state threshold cannot be met, a test warning is generated; Performance test management is performed according to the test warning.

7. The method according to claim 6, characterized in that The performing performance test management according to the test warning includes: Perform abnormal maintenance records and establish abnormal statistics for non-high-voltage inverters themselves; Sensitive concerns of the performance test are generated according to the abnormal statistics, and subsequent performance test management is performed based on the sensitive concerns.