A three-layer optimization method for building energy systems considering building structural parameters

Through the three-layer optimization model, combined with DeST and Matlab, the problem of neglecting structural parameters in the building energy system is solved, and the collaborative optimization of building design, capacity configuration and operation scheduling is realized, which improves the economy and environmental protection of the building and reduces energy consumption. consumption demand.

CN118296708BActive Publication Date: 2024-10-22SHANDONG JIANZHU UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410510985.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-26
Publication Date
2024-10-22
Estimated Expiration
2044-04-26

AI Technical Summary

Technical Problem

Existing building energy system optimization methods ignore the impact of building structural parameters on energy consumption demand, resulting in the inability to achieve optimal economic and environmental protection throughout the life cycle.

Method used

A three-layer optimization model is adopted, including building structure design, energy system capacity configuration and operation scheduling. The physical structure model and mathematical model are established through DeST and Matlab, and multi-objective optimization algorithms are used to solve to obtain the optimal building structure parameters and energy system capacity configuration. Ensuring minimal construction costs, minimal load demands, minimal energy system operating costs, minimal carbon emissions and optimal user comfort.

Benefits of technology

It achieves collaborative optimization of building design, capacity configuration and system operation scheduling, reduces building energy consumption requirements, improves the economy and applicability of the entire life cycle, and avoids high energy consumption and equipment redundancy problems caused by unreasonable design. Balances economy and energy consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118296708B_ABST
    Figure CN118296708B_ABST
Patent Text Reader

Abstract

The present application specifically relates to a three-layer optimization method for a building energy system that takes into account building structural parameters. The method is implemented based on a three-layer optimization model of building structure design, capacity configuration, and operation scheduling. The first-layer model is used to calculate construction costs and load demands. The second-layer model is combined with the load demands of the first-layer model to calculate the energy system capacity planning costs and the upper limit of the energy system capacity. The third-layer model determines the output plan of functional equipment based on the calculation results of the first two layers. The present application solves the problem that the building energy system cannot achieve optimal economic operation throughout the life cycle due to ignoring the impact of building structural parameters on building loads. The present application avoids problems such as high building energy consumption demand and redundant equipment configuration caused by unreasonable building design, improves the economy and applicability of the building throughout its life cycle, and can achieve mutual coordination between passive energy saving of building structures and active energy saving of equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of building energy system optimization, and specifically relates to a three-layer optimization method for building energy systems taking into account building structural parameters. Background Art

[0002] The operating energy consumption of a building mainly depends on the design of the building envelope. In recent years, some scholars have proposed the concept of "passive cooling" building design, which prevents the heat outside the building from entering the interior through the building envelope, thereby reducing the cooling energy consumption. Compared with ordinary building envelopes, the use of building materials with a lower thermal conductivity and a reasonable maintenance structure can increase the overall heat capacity of the building, so that the building can store more heat, delay the temperature rise of the outer surface of the wall, and effectively reduce the increase in building energy consumption caused by the rise in ambient temperature. Therefore, the use of different building materials and envelopes will affect the heat gain of the building, and then affect the capacity configuration and operation scheduling of the building energy system.

[0003] In the existing practice of building energy system optimization, only the capacity configuration and operation scheduling process of the building energy system are considered, while the impact of the building structure itself on the building energy consumption demand is ignored. Specifically, without considering the parameters of the building structure itself, it is impossible to reflect the operating economy and environmental protection of the building structure throughout its life cycle. Summary of the invention

[0004] The present invention provides a three-layer optimization method for a building energy system taking into account building structural parameters, which solves the problem that the building energy system cannot achieve optimal economic efficiency throughout the life cycle due to ignoring the impact of building structural parameters on building loads.

[0005] The technical solution of the present invention is as follows:

[0006] A three-layer optimization method for a building energy system considering building structural parameters is implemented based on a three-layer optimization model of building structure design-capacity configuration-operation scheduling. The first layer model is used to calculate the construction cost and load demand. The second layer model is combined with the load demand of the first layer model to calculate the energy system capacity planning cost and the upper limit of the energy system capacity. The third layer model determines the output plan of the functional equipment based on the calculation results of the first two layers. The method specifically includes the following steps:

[0007] Step 1: Use DeST to establish a physical structure model of the target building, reserve a data interface containing building structure parameters in the model, and establish a building structure design model with the building structure parameters as decision variables based on the M function in Matlab. The building structure design model takes the minimum construction cost and the minimum load demand as the optimization objectives. A multi-objective optimization algorithm is used to solve the two-dimensional Pareto solution set of the building structure design model and make decisions on it to obtain the optimal building structure parameters of the target building, and the construction cost and load demand of the target building are calculated based on the optimal building structure parameters;

[0008] Step 2: Based on the load demand calculated in step 1, an energy system capacity planning model is established with the minimum energy system capacity configuration cost of the target building and the maximum adjustable load as the optimization goal; a multi-objective optimization algorithm is used to solve the two-dimensional Pareto solution set of the energy system capacity planning model and make decisions on it to obtain the optimal capacity of the energy system of the target building, and the energy system capacity planning cost and the upper limit of the energy system capacity are calculated based on the optimal capacity of the energy system;

[0009] Step three: Based on the upper limit of the energy system capacity calculated in step two, an energy system operation optimization model is established with the optimization objectives of minimizing the energy system operation cost, minimizing the carbon emissions, and maximizing the user comfort; a multi-objective optimization algorithm is used to solve the three-dimensional Pareto solution set of the energy system operation optimization model and make decisions on it to obtain the optimal output plan of the energy system power supply equipment of the target building.

[0010] Furthermore, in the step 1, the building structure design model takes the upper temperature limit, the upper construction cost limit and the upper site area limit as constraints.

[0011] Furthermore, in step 1, the load demand includes summer cooling demand load and winter heating demand load;

[0012] The calculation formula for the summer cooling demand load is:

[0013] ;

[0014] Where: For building Cooling load demand during the time period; , , They are walls, windows, and roofs. The amount of heat transferred from the outside during the period; is the energy consumption ratio of the building under different body coefficients;

[0015] The calculation formula for the winter heat demand load is:

[0016] ;

[0017] Where: For building The heating load demand during the period, , , They are walls, windows, and roofs. The amount of heat dissipated to the outdoors during a period of time.

[0018] Furthermore, the wall The heat transfer from the outside during the period is calculated as:

[0019] ;

[0020] For the wall The amount of heat transferred from the outside during the period; is the average thermal conductivity of the wall; is the outdoor temperature; is the indoor temperature; is the wall thickness; For the Wall area of ​​facing wall; For the Window-to-wall ratio coefficient of the facing wall; is the time interval;

[0021] The window is The heat transfer from the outside during the period is calculated as:

[0022] ;

[0023] In the formula, is the average thermal conductivity of the window surface; For the The wall area facing the window;

[0024] Roof The heat transfer from the outside during the period is calculated as:

[0025]

[0026] In the formula, is the average thermal conductivity of the roof; is the area of ​​the roof.

[0027] Furthermore, the wall The calculation formula for the heat dissipated from the outside during the period is:

[0028] ;

[0029] In the formula, For the wall The amount of heat dissipated to the outdoors during the period;

[0030] The window is The calculation formula for the heat dissipated from the outside during the period is:

[0031] ;

[0032] In the formula, For the window The amount of heat dissipated to the outdoors during the period;

[0033] Roof The calculation formula for the heat dissipated from the outside during the period is:

[0034] ;

[0035] In the formula, For the roof The amount of heat dissipated to the outdoors during a period of time.

[0036] Furthermore, in step 1, the calculation formula of the construction cost is as follows:

[0037] ;

[0038] Where: , , They are the unit volume costs of walls, windows, and roofs respectively; , , are the thickness of the wall, window, and roof respectively; is the window-to-wall ratio.

[0039] Furthermore, the step 2, based on the load demand calculated in the step 1, takes the energy system capacity configuration cost of the target building as the minimum and the adjustable load as the maximum as the optimization goal, before establishing the energy system capacity planning model, further includes the following steps:

[0040] Based on the operating characteristics of the energy supply equipment, the energy supply equipment is configured and a mathematical model of the configured energy supply equipment is built; the power generation data of the energy supply equipment and the user's electricity consumption data are obtained through the historical database, and the power generation and electricity consumption on a typical day are predicted; when predicting, the impact of climate conditions and differences in energy consumption behavior on renewable energy power generation and user electricity load demand is considered, and a robust optimization method is used to deal with source-load uncertainty problems.

[0041] Furthermore, in step 3, the user's satisfaction with the demand response is evaluated based on the user's comfort level, and the user's behavior of participating in the demand response includes:

[0042] Interruptible load, where the interruptible load is defined as the electricity demand that users can partially or completely reduce according to supply and demand conditions;

[0043] Transferable electric load, which is defined as the electric load whose total electric power required during the dispatch period remains unchanged but the electric power consumption in each period can fluctuate within a certain range;

[0044] Transferable heat load, which is defined as a heat load in which the total heat required during the scheduling period remains unchanged, but the heat consumption in each period can fluctuate within a certain range;

[0045] The adjustable cooling load is defined as the cooling load that is reduced within the range of human comfort acceptable by utilizing the cooling and heat storage characteristics of the building itself.

[0046] Further, in step three, the user comfort includes electricity comfort, heat comfort and cooling comfort;

[0047] The power comfort level is defined as the ratio of interruptible load and transferable load to the total load in each period:

[0048] ;

[0049] In the formula, For the comfort of electricity use; for t The amount of power load reduction during the period; , For users in t Increase or decrease in electrical load during the period; It is the user's initial heat load demand.

[0050] The thermal comfort is defined as the ratio of the transferable heat load participating in the scheduling to the total heat load in each period:

[0051] ;

[0052] In the formula, For thermal comfort, , For users in t Increase or decrease in electrical load during the period; It is the user's initial heat load demand.

[0053] The cooling comfort is defined as the ratio of the total value of the predicted average evaluation index after participating in the cooling load demand response during working hours to the total value of the predicted average evaluation index of the initial cooling load:

[0054] ;

[0055] In the formula, For cold comfort; The comfort level of users after participating in cooling load demand response; Provides user comfort before participating in cooling load demand response;

[0056] The relationship between indoor temperature and predicted average evaluation index is as follows:

[0057] ;

[0058] Where: To predict the average evaluation index value; and They are the energy metabolism rate of the human body and the mechanical power produced; It is the ratio of the body area covered by clothing to the exposed area; is the surface heat transfer coefficient; is the indoor pressure; and are the average radiation temperature and the clothing outer surface temperature respectively.

[0059] Due to the adoption of the above technical solution, the beneficial effects of this application are as follows:

[0060] 1. This application establishes an optimization model from three levels: building structure design, capacity configuration, and operation scheduling. Building structure design is the first level. The first level considers parameters such as thermal conductivity of building materials, wall thickness, window-to-wall ratio, and external shading structure to determine the building load demand and construction cost. Capacity configuration is the second level. The second level considers source-load uncertainty, grid regulation requirements, and building load requirements obtained from the first level to determine the configuration capacity and configuration cost of each energy supply equipment. Operation scheduling is the third level. The third level considers both the equipment operation characteristics and the construction cost and configuration capacity obtained from the first two levels to determine the operation scheduling plan of the building energy system. This application can achieve coordination among building design, capacity configuration, and system operation scheduling from three levels, avoid problems such as high building energy consumption demand and redundant equipment configuration caused by unreasonable building design, and improve the economy and applicability of the building throughout its life cycle.

[0061] 2. This application builds a user building physical model based on energy consumption simulation software such as DeST, uses Matlab to establish the optimal building design model, and optimizes the decision variables of the building structure design model through algorithm iteration. This application can improve the economy of the building in the design stage, reduce the building energy consumption demand, change the problem of the disconnection between traditional building design and building energy system, balance the economy and energy consumption in the building design process, and achieve the coordination of passive energy saving of building structure and active energy saving of equipment.

[0062] 3. This application is based on the user demand response model and uses user comfort to evaluate the user's satisfaction with the demand response. User comfort comprehensively and fully reflects the overall system's response to user demand from three dimensions: electricity comfort, heat comfort, and cooling comfort, and ultimately gives the optimal output plan for energy supply equipment based on user demand response.

[0063] 4. This application considers the operating characteristics of energy supply equipment in building energy systems and builds a mathematical model of energy supply equipment; analyzes the uncertainty of power generation and user demand of renewable energy units in building energy systems, and establishes a source-load uncertainty analysis model in combination with grid regulation requirements, and uses robust optimization methods to deal with source-load uncertainty issues. A building energy system capacity configuration model is established with economy and adjustable energy as the goals. A multi-objective optimization method is used to solve and obtain the optimal equipment capacity configuration strategy for the building energy system. This changes the previous process of equipment capacity configuration of building energy systems, which rarely considers issues such as risk fluctuations and grid regulation, and improves the ability of building energy systems to respond to extreme weather and grid regulation requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0064] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:

[0065] Figure 1 A schematic flow chart of a three-layer optimization method for a building energy system considering building structural parameters provided in this application;

[0066] Figure 2 Flow chart of step 1 in this application. DETAILED DESCRIPTION

[0067] Based on the background technology, in order to solve the problem that the building energy system in the prior art cannot quantify the operation economy and environmental protection due to ignoring the building structure parameters, this application provides a three-layer optimization method for the building energy system considering the building structure parameters, as shown in the attached Figure 1 As shown, the following steps are included:

[0068] Step 1: Use DeST to establish a numerical model of the target building, reserve a data interface containing building structure parameters in the numerical model, and establish a building structure design model with the building structure parameters as decision variables based on the M function in Matlab. The building structure design model takes the minimum construction cost and the minimum load demand as the optimization objectives. A multi-objective optimization algorithm is used to solve the two-dimensional Pareto solution set of the building structure design model and make decisions to obtain the optimal building structure parameters of the target building, and the construction cost and load demand of the target building are calculated based on the optimal building structure parameters.

[0069] DeST mainly focuses on the analysis of thermal coefficients in the architectural design stage, air conditioning design scheme and detailed design stage. In the architectural design stage, the thermal environment of the building is simulated by inputting the parameters of the building envelope components, such as window-to-wall ratio and insulation, to provide a reference for architects through thermal environment indicators. In the air conditioning scheme design stage, the simulation analysis of the air conditioning system mainly evaluates and analyzes the partitions of the building. By comparing different air conditioning schemes, the thermal environment parameters and energy consumption economy of the inspection period are comprehensively compared to the future indoor thermal conditions and dissatisfaction rates of different schemes. In the detailed design stage, the module simulates the transmission and distribution system, selects fans and pump equipment according to the building function and energy consumption status, and selects the economy of different transmission system schemes through the comparison of comprehensive indicators.

[0070] The building structure parameters in step 1 include but are not limited to: exterior walls, exterior windows, roofs, floors, and floor slabs. If the temperature difference between rooms in the building is large, the building structure parameters should also include interior walls and interior doors.

[0071] In the building preprocessing stage in DeST, the room number will be automatically given. In the room function module, thermal disturbance, temperature and humidity requirements can also be set.

[0072] The numerical model of the target building established in DeST needs to interact with Matlab, and a two-way connection channel is established between DeST and Matlab through the database. Specifically, MySQL is used to establish a building load simulation database, and Matlab is connected to the database through the database connection toolbox. The algorithm is used to generate the initial values ​​of the building structure parameters, and then the values ​​are saved in the database. Then, the database interface is called in the DeST software to read the initial values ​​of the building structure parameters in the database, the building load conditions are calculated, and the results are returned to the database. Matlab obtains the calculated value of the building load by calling the database, and then calculates the construction cost of the target building through the formula. After obtaining the construction cost and load demand of the target building, the above two calculation results are called as fitness in the fitness function of the algorithm for subsequent calculations.

[0073] For detailed steps in step 1, please refer to the attached Figure 2 , the multi-objective optimization algorithm in step 2 and step 3 is Figure 2 Similarly, different inputs can be implemented to the algorithm according to different requirements.

[0074] Step 2: Based on the load demand calculated in step 1, an energy system capacity planning model is established with the optimization goal of minimizing the energy system capacity configuration cost of the target building and maximizing the adjustable load; a multi-objective optimization algorithm is used to solve the two-dimensional Pareto solution set of the energy system capacity planning model and make decisions on it to obtain the optimal capacity of the energy system of the target building, and the energy system capacity planning cost and the upper limit of the energy system capacity are calculated based on the optimal capacity of the energy system.

[0075] Step three: Based on the upper limit of the energy system capacity calculated in step two, an energy system operation optimization model is established with the optimization objectives of minimizing the energy system operation cost, minimizing the carbon emissions, and maximizing the user comfort; a multi-objective optimization algorithm is used to solve the three-dimensional Pareto solution set of the energy system operation optimization model and make decisions on it to obtain the optimal output plan of the energy system power supply equipment of the target building.

[0076] As a preferred implementation of the present application, in step 1, the building structure design model takes the upper temperature limit, the upper construction cost limit, and the upper site area limit as constraints.

[0077] As a preferred implementation of the present application, in step 1, the load demand includes summer cooling demand load and winter heating demand load;

[0078] The external envelope structure is an important part that isolates the building from the environment. Different envelope structure materials have different specific heat capacities and thermal conductivity coefficients. The impact of the two on the envelope structure is manifested as follows: due to the existence of wall heat storage, the time of occurrence of the indoor air temperature peak is delayed, and the peak temperature is reduced, which leads to a decrease in indoor air temperature fluctuations and a stable room temperature. Therefore, the heat storage characteristics of the envelope structure can delay and reduce the impact of outdoor high-temperature air and solar radiation on indoor air temperature. The thermal conductivity coefficient determines the wall heat transfer coefficient, which in turn affects the heat transfer between the envelope structure and the indoor and outdoor. The smaller the thermal conductivity coefficient, the stronger the wall insulation capacity, and the more difficult it is for changes in external temperature to affect the indoor through the wall. For the convenience of expression, the average thermal conductivity of the wall is used instead of the method of indicating the thermal conductivity of all structural layers layer by layer. The average thermal conductivity of the wall is the sum of the product of the thermal conductivity of each layer of the wall and the wall thickness fraction. The calculation formula is:

[0079] ;

[0080] In the formula, is the average thermal conductivity of the wall; is the thermal conductivity of a certain layer of the composite wall; It is the proportional coefficient corresponding to a certain layer of wall in the composite wall.

[0081] The calculation formula for the heat absorbed by the wall from the outside is:

[0082] ;

[0083] Where: For the wall The amount of heat transferred from the outside during the period; is the average thermal conductivity of the wall; is the outdoor temperature; is the indoor temperature; is the wall thickness; For the Wall area of ​​facing wall; For the Window-to-wall ratio coefficient of the facing wall; For the time interval.

[0084] Similarly, the calculation formula for the window's heat absorption from the outside is:

[0085] ;

[0086] In the formula, is the average thermal conductivity of the window surface; For the Area of ​​window surface

[0087] The calculation formula for the heat absorbed by the roof from the outside is:

[0088] ;

[0089] In the formula, is the average thermal conductivity of the roof; is the area of ​​the roof.

[0090] If the heat absorbed by the building during the day is regarded as the heat that needs to be offset by cooling in summer, the calculation formula for the summer cooling demand load is:

[0091] ;

[0092] Where: For building Cooling load demand during the time period; , , They are walls, windows, and roofs. The amount of heat transferred from the outside during the period; The energy consumption ratio of the building under different body coefficients is shown in Table 1.

[0093] Table 1 Relationship between building shape coefficient and energy consumption of different planes

[0094]

[0095] During the transition season, since the difference between indoor and outdoor temperatures is not large, there is no need to turn on air conditioning or heating, so the heat transfer between indoor and outdoor environments is not considered.

[0096] In the winter energy supply stage, since the outdoor temperature is lower than the indoor temperature, the indoor heat will be lost to the outside. Therefore, it is necessary to calculate the heat lost to the outside through the walls, windows, and roofs to ensure the indoor office and living needs. According to the above formula, the heat transfer from the indoor wall to the outdoor is:

[0097] ;

[0098] Similarly, the calculation formula for the heat dissipation from the window to the outside is:

[0099] ;

[0100] The calculation formula for heat dissipation from the roof to the outside is:

[0101] ;

[0102] If the heat lost from the building to the outside is regarded as the heat required for heating in winter, the calculation formula for the winter heat demand load is:

[0103] ;

[0104] Where: For building The heating load demand during the period, , , They are walls, windows, and roofs. The amount of heat dissipated to the outdoors during a period of time.

[0105] As a preferred implementation of the present application, in step 1, the calculation formula of the construction cost is as follows:

[0106] ;

[0107] Where: , , They are the unit volume costs of walls, windows, and roofs respectively; , , are the thickness of walls, windows and roof respectively.

[0108] In the energy-saving and thermal insulation system of residential exterior envelope structures, the exterior wall is the part that contributes the most to energy saving. Exterior wall insulation can effectively reduce the air conditioning load caused by heat transfer from the exterior wall of the building. The type of insulation material and its thickness are crucial to the energy-saving effect and economic benefits, and are important measures to achieve building energy saving. The thickness of the exterior wall insulation layer is an important parameter that determines the insulation level of the building. Generally, as the thickness of the insulation layer increases, the thermal insulation performance of the envelope structure improves, the building load decreases, and the operating costs of the air conditioning and heating systems also decrease accordingly, but at the same time the building cost increases accordingly. Therefore, from an engineering perspective, it is necessary to reasonably set the thickness of the wall insulation layer to minimize the total cost of the building life cycle.

[0109] As a preferred implementation of the present application, the step 2 further includes the following steps before establishing the energy system capacity planning model based on the load demand calculated in the step 1, with the energy system capacity configuration cost of the target building being minimized and the adjustable load being maximized as the optimization goal:

[0110] Based on the operating characteristics of the energy supply equipment, the energy supply equipment is configured and a mathematical model of the configured energy supply equipment is built; the power generation data of the energy supply equipment and the user's electricity consumption data are obtained through the historical database, and the power generation and electricity consumption on a typical day are predicted; when predicting, the impact of climate conditions and differences in energy consumption behavior on renewable energy power generation and user electricity load demand is considered, and a robust optimization method is used to deal with source-load uncertainty problems.

[0111] Robust optimization methods are used to deal with the uncertainty of photovoltaic, wind power generation and user power load during system operation optimization, random variables Fluctuates within a certain range:

[0112] ;

[0113] Where: , They represent the upper and lower limits of the fluctuation of the uncertain variable respectively; is the coefficient of fluctuation; the worst case interval considering uncertain variables is In order to avoid making overly conservative decisions, a robustness coefficient is introduced To control, ,in is the set of uncertain parameter variables in the system, and After that, the fluctuation range of the uncertain variable is .

[0114] This embodiment mainly considers the uncertainty of photovoltaic, wind power generation and electric load prediction:

[0115] ;

[0116] Where: To calculate auxiliary variables; and represent photovoltaic power, wind power and electric load respectively.

[0117] in, Indicates the degree of robustness and adjusts the uncertainty. Its value is an integer between 0 and 24. For example, The larger the value, the greater the uncertainty of photovoltaic power generation, corresponding to the "worse" scenario, so the optimization result is more conservative; conversely, The smaller the value, the more the fluctuation range of photovoltaic power generation is concentrated near the average value, the less uncertainty there is, and the optimization result is more risky. When , it is transformed into a mean deterministic model. Robust optimization can cope with all possible scenarios in the setting, and after satisfying the constraints in different scenarios, it can find the optimal system scheduling result based on the worst case.

[0118] In a specific embodiment of the above implementation, the energy supply equipment includes: photovoltaics, gas turbines, waste heat boilers, absorption refrigerators, ground source heat pumps, electric boilers, gas boilers, power storage devices, cold storage devices and heat storage devices.

[0119] As a preferred implementation of the present application, in step 2, the energy system capacity planning model is constrained by upper and lower limits of equipment capacity configuration, energy bus balance, upper limit of interconnecting pipeline transportation capacity, and upper limit of energy storage charging and discharging.

[0120] In step 2, the energy system capacity configuration cost model is as follows:

[0121] ;

[0122] In the formula, Indicates Installation cost per unit capacity of the equipment; Indicates the device Capacity; Indicates the device service life; Represents the discount rate.

[0123] The adjustable load model is as follows:

[0124] ;

[0125] In the formula, It represents the conventional energy storage configuration capacity during the building capacity configuration process; Indicates the actual energy storage configuration capacity of the building.

[0126] As a preferred implementation of the present application, in step three, the energy system operation optimization model is constrained by upper and lower limits of equipment output, equipment climbing constraints, energy bus balance, upper limit of interconnecting pipeline transportation capacity, and upper limit of energy storage charging and discharging.

[0127] As a preferred implementation of the present application, in step 3, the user's satisfaction with the demand response is evaluated based on the user's comfort level, and the user's demand includes:

[0128] Interruptible loads are defined as the electricity demand that users can partially or completely reduce according to supply and demand conditions. For interruptible loads:

[0129] ;

[0130] In the formula, for t The amount of power load reduction during the period; for t The maximum reduction in power load during the period; The time period during which the power load can be reduced.

[0131] Transferable electric load, which is defined as the electric load whose total power required during the dispatch period remains unchanged, but the power consumption in each period can fluctuate within a certain range. For transferable electric load:

[0132] ;

[0133] In the formula, , They represent the increase and decrease of the user's electric load in time period t respectively; , Respectively indicate that the user t Increase or decrease in electrical load during the period; It is the user's transferable electric load identifier. When the electric load increases, When , it indicates that the electrical load is reduced; , They respectively represent the time periods when the user's electricity load can increase or decrease.

[0134] Transferable heat load, which is defined as a heat load whose total heat required during the scheduling period remains unchanged, but the heat used in each period can fluctuate within a certain range. Transferable heat load needs to ensure that the total power demand of the heat load remains unchanged during the operation cycle, but there are no continuity and time series restrictions, and its operation flexibility is high within an acceptable transfer time interval. For transferable heat load:

[0135] ;

[0136] Where: , Respectively indicate that the user t Increase or decrease in electrical load during the period; , Respectively indicate that the user t Increase or decrease in electrical load during the period; is a user transferable heat load identifier, When the heat load increases, When , it indicates that the heat load is reduced; , They respectively represent the time periods when the user's electricity load can increase or decrease.

[0137] Adjustable cooling load, the adjustable cooling load is defined as the cooling load that is reduced within the range of human comfort acceptable by utilizing the building's own cooling and heat storage characteristics. There is a certain ambiguity in the user's perception of temperature comfort, and adjusting the indoor temperature within a certain range will not significantly affect the user experience. This feature can be used to improve the ability to adjust the cooling load. In addition, there is thermal inertia in the cooling system, and the terminal thermal perception has a delay. Therefore, the adjustment parameters of the cooling system can be optimized to improve the overall load adjustment capacity of the building's integrated energy system. For adjustable cooling load:

[0138] ;

[0139] Where: , They are The cooling load before and after the users in the time period participate in the cooling load demand response; for The outdoor temperature during the time period; for Initial indoor temperature setting for the time period; for Minimum indoor temperature setting for the time period; for Indoor temperature during the time period; Adjust parameters for buildings; and are the equivalent thermal resistance and equivalent heat capacity in the cooling building room respectively; is the time interval; for The maximum adjustable value of cooling load during a period; for Adjustment value of cooling load in each period; This is the time period during which the user's cooling load can be adjusted.

[0140] In a specific example of the above implementation, in step three, the user comfort includes electricity comfort, heat comfort and cooling comfort;

[0141] The power comfort level is defined as the ratio of interruptible load and transferable load to the total load in each period:

[0142] ;

[0143] In the formula, For the comfort of electricity use; is the amount of power load reduction during period t; , For users in t Increase or decrease in electrical load during the period; It is the user's initial heat load demand.

[0144] The thermal comfort is defined as the ratio of the transferable heat load participating in the scheduling to the total heat load in each period:

[0145] ;

[0146] In the formula, For thermal comfort, , For users in t Increase or decrease in electrical load during the period; is the initial heat load demand.

[0147] The cooling comfort is defined as the ratio of the total value of the predicted average evaluation index after participating in the cooling load demand response during working hours to the total value of the predicted average evaluation index of the initial cooling load:

[0148] ;

[0149] In the formula, For cold comfort; The comfort level of users after participating in cooling load demand response; Provides user comfort before participating in cooling load demand response;

[0150] The relationship between indoor temperature and predicted average evaluation index is as follows:

[0151] ;

[0152] Where: To predict the average evaluation index value; and They are the energy metabolism rate of the human body and the mechanical power produced; It is the ratio of the body area covered by clothing to the exposed area; is the surface heat transfer coefficient; is the indoor pressure; and are the average radiation temperature and the clothing outer surface temperature respectively.

[0153] In the specific implementation, the user's working hours can be set to 9 h -17 h Participate in cooling load demand response.

[0154] In step three, the building energy system operating costs can be modeled as follows:

[0155] ;

[0156] In the formula, For the system Time period The amount of energy purchased; for Time period the price of the energy source; For the Equipment in Output power during the time period; For the Operation and maintenance costs per unit output of the equipment; For energy storage devices Participation in the The power of the electricity market transaction method; For the The unit price of a power market transaction method.

[0157] Building carbon emissions models can be used:

[0158] ;

[0159] Where: For the purchase The unit carbon emission coefficient of the energy source.

[0160] Building user comfort models can be:

[0161] ;

[0162] Determined using entropy weights , , The value of .

[0163] Anything not described in this application can be achieved by adopting or drawing on existing technologies.

[0164] The above is only an embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included in the scope of the claims of the present application.

Claims

1. A three-layer optimization method for building energy system considering building structural parameters, characterized in that: This method is based on a three-layer optimization model of building structure design-capacity configuration-operation scheduling. The first layer model is used to calculate the construction cost and load demand. The second layer model is combined with the load demand of the first layer model to calculate the energy system capacity planning cost and the upper limit of the energy system capacity. The third layer model determines the output plan of the functional equipment based on the calculation results of the first two layers. This method specifically includes the following steps: Step 1: Use DeST to establish a physical structure model of the target building, reserve a data interface containing building structure parameters in the model, and establish a building structure design model with the building structure parameters as decision variables based on the M function in Matlab. The building structure design model takes the minimum construction cost and the minimum load demand as the optimization objectives. A multi-objective optimization algorithm is used to solve the two-dimensional Pareto solution set of the building structure design model and make decisions on it to obtain the optimal building structure parameters of the target building, and the construction cost and load demand of the target building are calculated based on the optimal building structure parameters; Step 2: Based on the load demand calculated in step 1, an energy system capacity planning model is established with the minimum energy system capacity configuration cost of the target building and the maximum adjustable load as the optimization goal; a multi-objective optimization algorithm is used to solve the two-dimensional Pareto solution set of the energy system capacity planning model and make decisions on it to obtain the optimal capacity of the energy system of the target building, and the energy system capacity planning cost and the upper limit of the energy system capacity are calculated based on the optimal capacity of the energy system; Step 3: Based on the upper limit of the energy system capacity calculated in step 2, an energy system operation optimization model is established with the optimization objectives of minimizing the energy system operation cost, minimizing the carbon emissions, and maximizing the user comfort; a multi-objective optimization algorithm is used to solve the three-dimensional Pareto solution set of the energy system operation optimization model and make decisions on it to obtain the optimal output plan of the energy system power supply equipment of the target building; In step 3, the user's satisfaction with the demand response is evaluated based on the user's comfort level. The user's behaviors in participating in the demand response include: Interruptible load, where the interruptible load is defined as the electricity demand that users can partially or completely reduce according to supply and demand conditions; Transferable electric load, which is defined as the electric load whose total electric power required during the dispatch period remains unchanged but the electric power consumption in each period can fluctuate within a certain range; Transferable heat load, which is defined as a heat load in which the total heat required during the scheduling period remains unchanged, but the heat consumption in each period can fluctuate within a certain range; Adjustable cooling load, which is defined as the cooling load that is reduced within the range of human comfort acceptable by utilizing the cooling and heat storage characteristics of the building itself; In step 3, user comfort includes electricity comfort, heat comfort and cooling comfort; The power comfort level is defined as the ratio of interruptible load and transferable load to the total load in each period: ; In the formula, For the comfort of electricity use; for t The amount of power load reduction during the period; , For users in t Increase or decrease in electrical load during the period; The initial heat load demand of the user; The thermal comfort is defined as the ratio of the transferable heat load participating in the scheduling to the total heat load in each period: ; In the formula, For thermal comfort, , For users in t Increase or decrease in electrical load during the period; The initial heat load demand of the user; The cooling comfort is defined as the ratio of the total value of the predicted average evaluation index after participating in the cooling load demand response during working hours to the total value of the predicted average evaluation index of the initial cooling load: ; In the formula, For cold comfort; The comfort level of users after participating in cooling load demand response; Provides user comfort before participating in cooling load demand response; The relationship between indoor temperature and predicted average evaluation index is as follows: Where: To predict the average evaluation index value; and They are the energy metabolism rate of the human body and the mechanical power produced; It is the ratio of the body area covered by clothing to the exposed area; is the surface heat transfer coefficient; is the indoor pressure; and are the average radiation temperature and the clothing outer surface temperature respectively.

2. A three-layer optimization method for building energy system considering building structural parameters according to claim 1, characterized in that: In the step 1, the building structure design model takes the upper temperature limit, the upper construction cost limit and the upper site area limit as constraints.

3. A three-layer optimization method for building energy system considering building structural parameters according to claim 1, characterized in that: In the step 1, the load demand includes summer cooling demand load and winter heating demand load; The calculation formula for the summer cooling demand load is: ; Where: For building Cooling load demand during the time period; , , They are walls, windows, and roofs. The amount of heat transferred from the outside during the period; is the energy consumption ratio of the building under different body coefficients; The calculation formula for the winter heat demand load is: ; Where: For building The heating load demand during the period, , , They are walls, windows, and roofs. The amount of heat dissipated to the outdoors during a period of time.

4. A three-layer optimization method for building energy system considering building structural parameters according to claim 3, characterized in that: The wall The heat transfer from the outside during the period is calculated as: ; For the wall The amount of heat transferred from the outside during the period; is the average thermal conductivity of the wall; is the outdoor temperature; is the indoor temperature; is the wall thickness; For the Wall area of ​​facing wall; For the Window-to-wall ratio coefficient of the facing wall; is the time interval; Window The heat transfer from the outside during the period is calculated as: ; In the formula, is the average thermal conductivity of the window surface; For the The wall area facing the window; Roof The heat transfer from the outside during the period is calculated as: In the formula, is the average thermal conductivity of the roof; is the area of ​​the roof.

5. A three-layer optimization method for building energy system considering building structural parameters according to claim 3, characterized in that: The wall The calculation formula for heat dissipated from the outside during a period is: ; In the formula, For the wall The amount of heat dissipated to the outdoors during the period; Window The calculation formula for heat dissipated from the outside during a period is: ; In the formula, For the window The amount of heat dissipated to the outdoors during the period; Roof The calculation formula for heat dissipated from the outside during a period is: ; In the formula, For the roof The amount of heat dissipated to the outdoors during a period of time.

6. A three-layer optimization method for building energy system considering building structural parameters according to claim 1, characterized in that: In step 1, the calculation formula of the construction cost is as follows: ; Where: , , They are the unit volume costs of walls, windows, and roofs respectively; , , are the thickness of the wall, window, and roof respectively; is the window-to-wall ratio.

7. A three-layer optimization method for building energy system considering building structural parameters according to claim 1, characterized in that: The step 2, based on the load demand calculated in the step 1, takes the energy system capacity configuration cost of the target building to be the minimum and the adjustable load to be the maximum, before establishing the energy system capacity planning model, further includes the following steps: Based on the operating characteristics of the energy supply equipment, the energy supply equipment is configured and a mathematical model of the configured energy supply equipment is built; the power generation data of the energy supply equipment and the user's electricity consumption data are obtained through the historical database, and the power generation and electricity consumption on a typical day are predicted; when predicting, the impact of climate conditions and differences in energy consumption behavior on renewable energy power generation and user electricity load demand is considered, and a robust optimization method is used to deal with source-load uncertainty problems.