A real-time analysis method and system for distribution network status

By constructing a real-time power outage and restoration accurate analysis and judgment model and a dynamic storage data container, the problem of insufficient timeliness and accuracy of the active sensing technology of the distribution network is solved, and the rapid and accurate positioning of power outage events and the analysis and judgment of fault causes are achieved, improving Improved repair efficiency.

CN118312549BActive Publication Date: 2024-10-18STATE GRID JIANGXI ELECTRIC POWER CO LTD RES INST +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410742095.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-11
Publication Date
2024-10-18
Estimated Expiration
2044-06-11

AI Technical Summary

Technical Problem

The existing distribution network active sensing technology lacks timeliness and accuracy, resulting in poor power outage recovery speed and quality, and cannot meet the need for fast and accurate emergency repairs.

Method used

A real-time analysis method of distribution network status is adopted. Through data acquisition, data preprocessing and accurate analysis and judgment of power interruption and restoration based on two-way mutual calibration of nodes, a real-time accurate analysis and judgment model of power interruption and restoration is constructed, and a dynamic storage data container is used to store the power interruption and restoration accurately. The power restoration event is deduced and completed from the bottom up, the fault node is located, and the fault type and cause are studied and judged.

Benefits of technology

It significantly improves the real-time and accuracy of power outage events, reduces the problem of inaccurate hierarchical positioning, helps to quickly find fault points, narrows the scope of power outages, and improves power supply recovery efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118312549B_ABST
    Figure CN118312549B_ABST
Patent Text Reader

Abstract

The present invention discloses a real-time analysis method and system for the state of a distribution network. The method of the present invention comprises the following steps: acquiring data from a multi-source system, establishing a dynamic storage data container, automatically inserting and releasing original data such as shutdown, power restoration and processing events, measurements, etc., building a real-time shutdown and power restoration accurate judgment model, judging the shutdown and power restoration states of nodes at all levels, and publishing and displaying the judgment results after shutdown and power restoration. The present invention constructs a real-time shutdown and power restoration accurate judgment model, establishes a dynamic storage data container, derives and completes shutdown and power restoration events from the bottom up, and layers and locates nodes for real-time events, thereby greatly improving the real-time and accuracy of the judgment. The proposed shutdown and power restoration accurate judgment model can be applied to various judgment scenarios such as severe weather fault location, small current grounding fault, non-automatic switch fault and other derivative scenarios.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of real-time analysis of distribution network status, and in particular to a real-time analysis method and system for distribution network status. Background Art

[0002] With the rapid development of urban and rural economy, higher requirements are placed on the reliability of distribution networks. Users hope that the power grid can have fewer power outages or no power outages. From the perspective of the power grid, in the past, when there was a power outage, users had to report it and then find the fault point. This passive form of repair is not conducive to the speed and quality of repair. In order to ensure the rapid recovery of power outages, it is necessary to change from passive to active and carry out power grid repair work quickly and proactively.

[0003] Distribution networks have long faced the problem of incomplete perception of user power outages and power restorations. The timeliness and accuracy of existing active sensing technologies cannot fully meet the needs of emergency repairs. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present invention provides a method and system for real-time analysis of distribution network status, which aims to solve the problems in the background technology.

[0005] To achieve the above object, the present invention provides the following technical solution: a method for real-time analysis of distribution network status, comprising the following steps:

[0006] Step S1: data acquisition;

[0007] Based on the data center, the power outage and restoration events and measurement data from the control cloud, distribution automation master station, and power consumption information collection system are obtained, including the power outage and restoration events and voltage, current, and power measurement data of 10kV main lines, 10kV branches, distribution substations, and users; based on the business center, the substation, 10kV line, switch, distribution substation, user ledger, and topology data from the PMS3.0, i.e., the power grid resource business center, and the marketing 2.0 system are obtained;

[0008] Step S2: data preprocessing;

[0009] Normalize the power outage and restoration events and measurement data obtained in step S1; establish a storage data container, insert the power outage and restoration events into the storage data container according to the occurrence time of the power outage event, and associate them with the substation-10kV line-distribution station area-user topology to form a dynamic storage data container;

[0010] Step S3: Accurately judge power outage and power restoration based on node bidirectional mutual calibration;

[0011] Build a real-time power outage and restoration accurate judgment model, use dynamic storage data containers to deduce and complete power outage and restoration events from bottom to top, and layer and locate real-time events; through the derivation of the topology tree, judge the switch state changes and the scope of influence, and further judge the fault type and fault cause;

[0012] Step S4: Real-time analysis of the power outage scope;

[0013] Based on a determined time range and according to power outage and power restoration events, the geographical location information of the lines and distribution substations is used to determine the areas that are still out of power and the areas that have been restored, and the information is displayed based on a map of the power grid.

[0014] Furthermore, the specific process of step S1 is as follows:

[0015] Step S1.1: Obtain ledger and topological data; specifically, obtain the ledger, topological relationship and geographic location information of the substation, 10kV line, switch, distribution area and user from the business middle station;

[0016] Step S1.2: Obtain real-time events; specifically, use the data center to obtain power outage events from the control cloud, distribution automation master station, and power consumption information collection system;

[0017] Step S1.3: Obtain measurement data; specifically, use the data center to obtain voltage, current and power measurement data from the control cloud, distribution automation master station and power consumption information collection system, and perform automatic verification of the network topology.

[0018] Furthermore, the specific process of step S1.2 is as follows:

[0019] Step S1.21: Obtain the switch position change alarm data table, SOE alarm data table and accident total alarm data table from the control cloud and the distribution automation master station respectively; obtain the power outage and restoration events of the distribution station area and the power outage and restoration events of the user from the power consumption information collection system;

[0020] The specific process of step S1.3 is as follows:

[0021] Step S1.31: Check whether the network topology relationship of substation-10kV line-distribution substation area-user is accurate, and identify and correct abnormal network topology relationships.

[0022] Furthermore, the specific process of step S2 is as follows:

[0023] Step S2.1: Data cleaning; specifically, remove abnormal data from the following three points:

[0024] First, timeout data, the time difference between the power outage event and the current time exceeds Δ t 1 power outage event is eliminated;

[0025] Second, timing error time: for the same power outage and power restoration event, if the power restoration event is earlier than the power outage event, the power restoration event will be eliminated;

[0026] Third, if the key fields are missing, the power outage and power restoration events that lack the power outage and restoration event time, terminal or meter number will be eliminated;

[0027] Step S2.2: Establish a dynamic storage data container; Specifically, establish a dynamic storage data container for storing real-time power outage and power restoration events, with the current time t is the midpoint of the dynamic storage data container, and the left and right offset times of the dynamic storage data container are Δ tl and Δ tr , the left boundary of the dynamic storage data container is t -Δ tl , the right boundary of the dynamic storage data container is t +Δ tr ; Periodically calibrate the boundaries of the dynamic storage data container, specifically, update the left boundary of the dynamic storage data container, delete expired data in the dynamic storage data container, update the right boundary of the dynamic storage data container, and insert data from the right position into the dynamic storage data container in sequence according to the power-off and power-on event timing, and locate the order of inserting the power-off and power-on events according to the positions of the inserted power-off and power-on events in the dynamic storage data container;

[0028] Step S2.3: Establish the relationship between events and topology; specifically, based on the equipment identification carried by the power outage and power restoration events, associate the power outage events with the 10kV lines, distribution substations, and users, apply the relationship of the automatic verification of the network topology in step S1.3, complete the association of the power outage events with the substations, 10kV lines, distribution substations, and users, generate a universal format event, and enter the dynamic storage data container; wherein, the 10kV line includes a 10kV main line and a 10kV branch line.

[0029] Furthermore, the specific process of step S2.3 is as follows:

[0030] Step S2.31: After associating the 10kV main line power outage event from the control cloud with the distribution station account, that is, the distribution station area account obtained in step S1.1, the feeder number, feeder name, 10kV main line power outage event time, protection warning, and switch change are obtained. In the case where the dispatching side and the distribution station account cannot be directly matched, the substation and feeder name are extracted according to the protection alarm and switch change signal content sent by the dispatching side, and matched with the substation and feeder name established in step S1.3 to obtain the corresponding feeder number and name, and the 10kV main line power outage event type is marked according to the source;

[0031] Step S2.32: after associating the 10kV branch line power outage event from the distribution automation master station with the distribution station account through the feeder or switch number and switch name in the 10kV branch line power outage event, the feeder number, feeder name, switch number, switch name, 10kV branch line power outage event time, protection alarm, switch position information are obtained, and the 10kV branch line power outage event type is marked according to the source;

[0032] Step S2.33: The distribution station area power outage event from the power consumption information collection system is associated with the marketing ledger, i.e., the ledger of the marketing 2.0 system obtained in step S1.1, through the terminal or meter number in the distribution station area power outage event, to obtain the distribution station area to which the distribution station area power outage event belongs, and then connected with the distribution station ledger. After being associated with the distribution station ledger, the feeder number, feeder name, distribution station area number, station area name, and distribution station area power outage event time are obtained. If it is a distribution station area power restoration event, the distribution station area power outage and restoration event time are included, and the distribution station area power outage and restoration event types are marked according to the source;

[0033] Step S2.34: Associate the user power outage event from the electricity consumption information collection system with the marketing ledger through the user meter number in the user power outage event, obtain the user and the distribution station area to which they belong in the user power outage event, and connect it with the distribution station ledger. After associating with the distribution station ledger, the feeder number, feeder name, distribution station area number, distribution station area name, user number, user name, and user power outage event time are obtained. If it is a user power-on event, the user power-off and power-on event times are included, and the type of user power outage event is marked according to the source.

[0034] Furthermore, the specific process of step S3 is as follows:

[0035] Step S3.1: Data diversion; Specifically, for each type of power outage event in the dynamic storage data container, mark it according to the source and type; set a six-bit event mark yourself , the first to sixth digits represent substation and upper power outage events, 10kV main line power outage events, 10kV branch line power outage events, distribution area power outage events, user power outage events, and low-voltage power outage events generated by user power outage events. Each digit is assigned 0, 1, and 2, representing non-such events, native power outage events, and derived events, respectively; when yourself ='000021', indicating a low voltage power outage event generated by a user power outage event. you= '002100' indicates a 10kV branch line power outage event generated by a power outage event in a distribution substation area; the event type is marked and a data diversion channel is established, the data diversion channel includes an event diversion channel within the substation area tg , In-line event diversion channel le And the upper power outage event diversion channel sn ; Event diversion channel within the station area tg Including user power outage events and low-voltage power outage events, event diversion channels within the line le Including power outage events in distribution substation area, 10kV main line power outage events and 10kV branch line power outage events, and upper power outage event diversion channels sn Including 10kV main line power outage events and 10kV branch line power outage events that have been judged, that is, generated events;

[0036] Step S3.2: Establish a power outage event node merging model; define the power outage event node merging model as d 2 u 1. The specific rules of the power outage event node merging model are as follows: through the established data diversion channel, the target data is taken out from the dynamic storage data container, and the target data is the current time t Does not exceed the set threshold dt When the power outage event in the target data is a superior power outage event without the same substation-10kV line-distribution station area-user network topology, the target data is deduplicated according to the object and the number of unique events in the target data is counted. Holy When the number of unique events does not meet the requirement, a null value is returned. Otherwise, the proportion of the target event in the same level event diversion channel is updated according to the increase in the number of events in the dynamic storage data container. n , when the specified ratio is not reached ro When n < ro , returns null until n ≥ ro , start upgrading and merging events; when the power outage event in the target data is a higher-level power outage event under the same station-line-transformer-user network topology, the event at this level is marked as a sub-event of the higher-level power outage event, put into the corresponding event cluster, and shield the event at this level. The 10kV branch line power outage event is merged into the event clusters of the substation and upper-level power outage event and the 10kV main line power outage event, and so on to complete the merging of the substation area power outage event, the low-voltage power outage event, and the user power outage event;

[0037] Step S3.3: Upgrading and merging power outage events: Pushing the original power outage events in the dynamic storage data container to the diversion channel for real-time classification, aggregation and judgment, and updating the judgment results in the dynamic storage data container to generate the final event;

[0038] Step S3.4: Accuracy correction of power outage events: For the original power outage events, the accuracy is verified by mutual verification of other information except the original power outage events;

[0039] Step S3.5: Supplement the judgment results: Based on the accurate fault judgment, supplement the information sources other than power outage and power restoration events to expand the judgment scope;

[0040] Step S3.6: Storage of analysis and judgment results: The final event generated by the completed analysis and judgment is stored in the established result library to generate the latest analysis and judgment event.

[0041] Furthermore, the specific process of step S3.3 is as follows:

[0042] Step S3.31: User event escalation:

[0043] (1) Upgrade the power outage event in the distribution area. For the user power outage event with event type '000001', enter the event diversion channel within the distribution area tg , and upgrade and merge the user power outage events through the power outage event node merging model established in step S3.2. When the number of power outage events in the same distribution station area is greater than the first event number preset value u 1, and the ratio of the number of users without power to the number of users in the distribution area exceeds the first preset ratio value n 1. Generate event type yourself ='000201' power outage event in the distribution area, and enter the event diversion channel within the line le ;

[0044] (2) Upgrade user power outage events. For user power outage events with event type '000001', when the number of power outage events in the same distribution area is greater than the second event number preset value, u 2, and the power outage event upgrade conditions of the distribution station area are not met, and the event type is generated yourself = low voltage power outage event of '000021';

[0045] Step S3.32: Distribution area event upgrade:

[0046] (1) Upgrade 10kV main line power outage event. For power outage event type yourself =['000100','000201'] power outage event in the distribution area, enter the event diversion channel within the line le , and upgrade and merge the power outage events in the distribution area. When the number of power outage events in the distribution area under the same line reaches the third event number preset value u 3. The ratio of the number of power outage distribution areas to the number of all distribution areas under the line reaches the second preset ratio. n 2. Generate event type yourself ='020100' main line power outage event, and enter the upper power outage event diversion channel sn ;

[0047] (2) Upgrade the 10kV branch line power outage event to the event diversion channel entering the line le When the number of power outage events in the distribution area under the same line reaches the fourth event number preset value u At 4:00, further determine the proportion of the number of power distribution areas that are out of power. When the ratio of the number of power distribution areas that are out of power to the number of all power distribution areas under the line reaches the third preset ratio n 3. When the 10kV main line power outage event upgrade conditions are not met, an event type is generated yourself =Special branch line power outage event of '022100', and enter the upper power outage event diversion channel sn , otherwise an event type is generated yourself = 10kV branch line power outage event at '002100';

[0048] Step S3.33: Line power outage event upgrade: For power outage event type yourself =['010000','020100','022100'] 10kV main line power outage event, special branch line power outage event, in the upper power outage event diversion channel sn When the number of different 10kV main line outage events and special branch line outage events under the same substation or the same busbar reaches the fifth event number preset value, u 5. The number of 10kV main lines corresponding to the power outage line in this substation or under the same bus reaches the fourth preset ratio n 4, and all sources of events involved in the upgrade are yourself = '010000' 10kV main line power outage event, then the event type is generated yourself ='210000' of the upper power outage event, otherwise an event type is generated yourself =Superior power outage event of '200100';

[0049] Step S3.34: Event update after upgrade: After the event is upgraded, all non-highest power outage events in the event cluster are marked as sub-events and blocked when the event is released. When the highest event is the original power outage event, the original power outage event unique identifier is still used. them If the event is generated after the upgrade, the unique identifier of the event generated after the upgrade is automatically generated during the upgrade. them , and insert the events generated after the upgrade into the dynamic storage data container; the event time after the upgrade merge it is is the average event time of the event cluster, and the event cluster is updated according to the time of the last upgrade and merge. eu , and insert it into the dynamic storage data container;

[0050] The specific process of step S3.4 is:

[0051] Step S3.41: Generate a flash outage event: The dynamic storage data container contains a power outage event and a power restoration event. The power restoration event includes the power outage time. it is And the power-on time and , when step S3.2 obtains the target event, the power outage event and power restoration event of the same device are obtained, and the event and > it is , it is marked as a flash outage event; when the event cluster of the power outage event included in the power outage event upgraded and merged in step S3.3 has a proportion reaching the fifth preset proportion value n If the power outage event of 5 meets the flash outage judgment standard, the upgraded power outage event corresponding to the event cluster is marked as a flash outage event, and the power restoration time of the event is generated according to the average power restoration time. and ;

[0052] Step S3.42: Secondary verification of the original power outage event: Verify the following events before the event is released:

[0053] (1) For event type yourself ='000100', according to the event source, if it is a power outage event for the entire substation area that has been verified by the source, that is, the event itself includes a power outage event for the substation area and a power outage event for some users, then this verification is passed; if it is a power outage event for the substation terminal, then the event cluster of the power outage event for the distribution substation area is verified; if the number of user power outage events included in the event cluster is greater than the preset value of the number of events or the ratio of the power outage users to the number of users in the substation area reaches the preset value of the ratio, then the accuracy verification of the power outage event for the distribution substation area is passed;

[0054] (2) For event type yourself ='000001', a single-user power outage event channel is established. Before the event is released and the event is not involved in the upgrade and merging, the event is stored in the single-user power outage event channel, the event waiting time is extended, and the voltage and current data of the called user are supplemented. When the voltage or current data of the called user is normal, it is marked as untrue and deleted, otherwise the accuracy of the user power outage event is verified.

[0055] Furthermore, the specific process of step S3.5 is as follows:

[0056] Step S3.51: Lightning tripping fault: obtain real-time source-end ground lightning data from the lightning location system or the meteorological bureau, remove duplicates and clean the real-time source-end ground lightning data to form lightning strike data, and establish a real-time lightning tripping analysis model;

[0057] (1) Real-time analysis and establishment of a lightning dynamic storage data container to store the analysis results: When a 10kV line fails and the power outage occurs, obtain the time when the failure occurred. it isThe difference does not exceed Δ lt If there is lightning strike data in this time period, calculate the shortest distance δ between the lightning strike and the towers along the line. lg , when the distance does not exceed the maximum lightning radius estimated to cause line tripping ltg , that is, satisfying δ lg < ltg , store relevant information in the lightning dynamic storage data container, including power outage events id , power outages, lightning strikes id , lightning strike time, lightning strike point coordinates, lightning current amplitude, nearest tower and tower coordinates, when δ lg < ltg If there is more than one lightning strike, all lightning strikes that meet the conditions and the tower information along the line are stored;

[0058] (2) For the 10kV main line and 10kV branch line fault power outages that have completed steps S3.1 to S3.4, before the event is released, the number of lightning strikes that meet the conditions is counted through the established lightning tripping real-time judgment model, and the field ' li 'And assign statistical results and add fields' lia ' and store the closest to the lightning strike point g The coordinates of the towers along the line;

[0059] Step S3.52: Non-automatic fault switch analysis: For 10kV branch line fault power outage, when the action switch after the fault power outage is a distribution automation switch, the power outage event contains the action switch information; when the action switch is a non-automatic switch, the power outage event does not contain the action switch information. By establishing a 10kV line-switch-distribution substation area topology tree, the substation area affected by the branch line power outage is calculated, and the switch status in the topology tree is derived;

[0060] Step S3.53: Determine the scope of the small current grounding fault through joint analysis of multi-source data;

[0061] (1) Obtaining low current ground fault alarms from the control cloud eg , including fault bus and fault time;

[0062] (2) The distribution automation master station accesses the equipment information from the data center, and uses the ground fault results of multiple devices on a 10kV line for comprehensive analysis. When the ground fault line reported by the distribution automation master station is consistent with the substation line selection result, it indicates that the corresponding 10kV line is faulty. After the faulty line is determined, when the selection consistency rate of multiple distribution automation terminals on the line exceeds the set threshold, y , indicating that there is a ground fault in the corresponding 10kV line section, and the line and section selection of the ground fault is completed;

[0063] (3) For lines without line selection or section selection devices or lines in substations that are inconsistent with the distribution automation analysis results, when the fault occurs during thunderstorms, obtain alarm events related to small current ground faults in a certain area. eg The time difference between the previous and the next time does not exceed Δ lg The lightning strike data was used to calculate the number of lightning strikes and lightning current amplitude near all 10kV line towers under the substation busbar, and weights were assigned to the lightning strike distance, number of lightning strikes, lightning current amplitude, and lightning strike time difference parameters. The machine learning model was used to identify the distribution lines and tower sections with the highest probability of failure, and the line and section selection for grounding faults was completed.

[0064] Step S35.4: Distinguish between fault power outage and planned power outage: Obtain the power outage plan entered from the dispatching OMS and the intelligent power supply service command system, and associate it with the power outage event that has been determined. When the power outage plan covers the scope of the power outage event, and the power outage event falls on the planned day, the power outage is a planned power outage, and a special mark is made, which will be removed when the fault power outage is released;

[0065] The specific process of step S3.6 is:

[0066] S36.1: Data storage model: Establish a data storage model for storage; the data content of the data storage model includes event identification them , organizational relationship, topological relationship, and the proportion of failures in the derivation process of non-native power outage events fr That is, the proportion of power outage users in the power distribution area, the proportion of power outage lines in the power distribution area, the proportion of power outage lines in the substation, and the impact range of non-original power outage events fn That is, the users affected by low-voltage power outages and the areas and duration of power outages affected by 10kV branch line power outages it is , Power-on time and If the power is not restored, it will be empty, the last updated time ut and event entry time it ;

[0067] Step S36.2: Data storage process: calculate the waiting time of the identified event, obtain the dynamic storage data container data, and filter the last update time ut The current time exceeds the set waiting time Δ your The waiting time is differentiated according to different event types, and the events that meet the conditions are inserted into the established result library in the order of the dynamic storage data container and stored in the database;

[0068] Step S36.3: Message release: The power outage event that has been analyzed and judged is displayed or published to the client through the Internet area. When publishing through the Internet area, the analysis result is penetrated to the Internet area through the internal and external network two-way isolation device, and sensitive information is shielded when publishing.

[0069] Furthermore, the specific process of step S4 is as follows:

[0070] Step S4.1: Power-on event analysis: When the conditions for generating a flash stop event are not met, a power-on time will be inserted according to the data storage model. and The power outage event with a null value is stored in the dynamic storage data container; when a new power-on event enters the dynamic storage data container, the power outage events of the same level and the upper level of the new power-on event are searched. it is The difference between the power outage time of the new power restoration event and the power outage time of the new power restoration event is less than the specified value, and the impact range of the power outage event is fn If the device contains a new power-on event, it is considered as the same power outage event. When the power-on ratio of the original power outage event exceeds the specified threshold rf At that time, it was determined that the original power outage had been completely restored;

[0071] Step S4.2: Display of power outage and power restoration scope:

[0072] (1) According to the power outage and restoration events, the power outage range is automatically counted from top to bottom according to the topological relationship; if a power outage event occurs at a certain node, the devices below the node are marked as power outages, and the number of households during the power outage is counted = power outage duration × number of power outage users; when the number of households during the power outage exceeds the threshold sh 1:00, power outage range, yellow; when the number of households exceeds the threshold sh At 2 o'clock, the power outage range is colored red, and the levels are set according to actual needs;

[0073] (2) Display the power outage equipment and areas on a grid map according to the selected time period, and display the power outage equipment according to the specified color and status.

[0074] A real-time analysis system for distribution network status is applied to a real-time analysis method for distribution network status, comprising: a data acquisition module, a data preprocessing module, a fault analysis module, a fault information publishing module, and a power outage range automatic statistics module; the data acquisition module is used to connect an enterprise middle platform and a real-time measurement center to obtain data from multiple source systems; the data preprocessing module is used to establish a dynamic storage data container to automatically insert and release power outage and power restoration events; the fault analysis module is used to build a real-time power outage and power restoration accurate analysis model to analyze the power outage and power restoration status of equipment at all levels; the fault information publishing module is used to achieve the penetration of internal and external network information and publish fault information; the power outage range automatic statistics module is used to count the power outage and power restoration range and display it in a power grid map.

[0075] Compared with the existing technology, the present invention has the following beneficial effects:

[0076] (1) The present invention constructs a real-time power outage and restoration accurate judgment model, establishes a dynamic storage data container, deduces and completes power outage and restoration events from bottom to top, and layers and locates nodes of real-time events, thereby greatly improving the real-time and accuracy of power outage event judgment.

[0077] (2) The present invention can significantly reduce the problem of inaccurate positioning of power outage and power restoration levels, and is helpful in quickly finding the fault point, reducing the scope of power outage, and restoring power supply based on the analysis information during emergency repairs. The proposed accurate analysis model for power outage and power restoration can be applied to various analysis scenarios such as fault location in severe weather, small current grounding faults, and non-automatic switch faults, and has great room for expansion. BRIEF DESCRIPTION OF THE DRAWINGS

[0078] Figure 1 The present invention is a flow chart of the method.

[0079] Figure 2 It is a system structure diagram of the present invention. DETAILED DESCRIPTION

[0080] like Figure 1 As shown, the present invention provides a technical solution: a real-time analysis method for distribution network status, comprising the following steps:

[0081] Step S1: data acquisition;

[0082] Based on the data center, the power outage and restoration events and measurement data from the control cloud, distribution automation master station, and power consumption information collection system are obtained, including the power outage and restoration events and voltage, current, and power measurement data of 10kV main lines, 10kV branches, distribution stations, and users; based on the business center, the substation, 10kV line, switch, distribution station, user ledger, and topology data from the PMS3.0, i.e., the power grid resource business center and the marketing 2.0 system are obtained; specifically:

[0083] Step S1.1: Obtain ledger and topological data; specifically, obtain the ledger, topological relationship, geographic location and other information of the substation, 10kV line, switch, distribution area and user from the business middle station.

[0084] Step S1.2: Obtain real-time events; specifically, use the data center to obtain power outage events from the control cloud, distribution automation master station, and power consumption information collection system;

[0085] Step S1.21: Obtain the switch position change alarm data table, SOE alarm data table and accident total alarm data table from the control cloud and the distribution automation master station respectively; obtain the power outage and restoration events of the distribution station area and the power outage and restoration events of the user from the power consumption information collection system; in actual implementation, the above data can also be obtained through other technical routes.

[0086] Step S1.3: Obtain measurement data; specifically, use the data center to obtain voltage, current and power measurement data from the control cloud, distribution automation master station and power consumption information collection system, and perform automatic verification of the network topology.

[0087] Step S1.31: Based on the voltage correlation verification, the algorithms of geographic coordinate anomaly, power line loss anomaly and outage verification are supplemented to verify whether the network topology relationship of substation-10kV line-distribution station area-user is accurate, and the abnormal network topology relationship is identified and corrected.

[0088] Step S2: data preprocessing;

[0089] Normalize the power outage and restoration events and measurement data obtained in step S1; establish a storage data container, insert the power outage and restoration events into the storage data container according to the occurrence time of the power outage event, and associate them with the substation-10kV line-distribution station area-user topology to form a dynamic storage data container.

[0090] Step S2.1: Data cleaning; Specifically, in order to achieve high real-time fault analysis, abnormal data needs to be removed from the following three points:

[0091] First, timeout data, the time difference between the power outage event and the current time exceeds Δ t 1 power outage event is eliminated;

[0092] Second, timing error time: for the same power outage and power restoration event, if the power restoration event is earlier than the power outage event, the power restoration event will be eliminated;

[0093] Third, due to the lack of key fields, the power outage and power restoration events that are missing the time, terminal or meter number of the power outage and power restoration event will be eliminated.

[0094] Step S2.2: Establish a dynamic storage data container; Specifically, establish a dynamic storage data container for storing real-time power outage and power restoration events, with the current time t is the midpoint of the dynamic storage data container, and the left and right offset times of the dynamic storage data container are Δ tl and Δ tr , the left boundary of the dynamic storage data container is t -Δ tl , the right boundary of the dynamic storage data container is t +Δ tr; Periodically calibrate the boundaries of the dynamic storage data container, specifically, update the left boundary of the dynamic storage data container, delete expired data in the dynamic storage data container, update the right boundary of the dynamic storage data container, and insert power outage and power restoration events into the dynamic storage data container in sequence from the right position according to the timing of the power outage and power restoration events, and locate the order of inserting the power outage and power restoration events according to the position of the inserted power outage and power restoration events in the dynamic storage data container.

[0095] Step S2.3: Establish the relationship between events and topology; specifically, based on the equipment identification carried by the power outage and power restoration events, associate the power outage events with the 10kV lines, distribution substations, and users, apply the relationship of the automatic verification of the network topology in step S1.3, complete the association of the power outage events with the substations, 10kV lines, distribution substations, and users, generate a universal format event, and enter the dynamic storage data container; wherein, the 10kV line includes a 10kV main line and a 10kV branch line.

[0096] Step S2.31: After associating the 10kV main line power outage event from the control cloud with the distribution station ledger, that is, the distribution station area ledger obtained in step S1.1, the feeder number, feeder name, 10kV main line power outage event time, protection warning, and switch change are obtained. For the situation where the dispatching side and the distribution station ledger cannot be directly matched, the substation and feeder names are extracted according to the protection alarm and switch change signal content sent by the dispatching side, and matched with the substation and feeder names established in step S1.3 to obtain the corresponding feeder number and name, and the 10kV main line power outage event type is marked according to the source.

[0097] Step S2.32: After associating the 10kV branch power outage event from the distribution automation master station with the distribution station account through the feeder or switch number and switch name in the 10kV branch power outage event, the feeder number, feeder name, switch number, switch name, 10kV branch power outage event time, protection alarm, and switch change information are obtained, and the 10kV branch power outage event type is marked according to the source.

[0098] Step S2.33: Associate the distribution station area power outage event from the electricity consumption information collection system with the marketing ledger, i.e., the ledger of the marketing 2.0 system obtained in step S1.1, through the terminal or meter number in the distribution station area power outage event, to obtain the distribution station area to which the distribution station area power outage event belongs, and then connect it with the distribution station ledger. After associating with the distribution station ledger, the feeder number, feeder name, distribution station area number, station name, and distribution station area power outage event time are obtained. If it is a distribution station area power restoration event, the distribution station area power outage and restoration event time are included, and the distribution station area power outage and restoration event types are marked according to the source.

[0099] Step S2.34: Associate the user power outage event from the electricity consumption information collection system with the marketing ledger through the user meter number in the user power outage event, obtain the user and the distribution station area to which they belong in the user power outage event, and connect it with the distribution station ledger. After associating with the distribution station ledger, the feeder number, feeder name, distribution station area number, distribution station area name, user number, user name, and user power outage event time are obtained. If it is a user power-on event, the user power-off and power-on event times are included, and the type of user power outage event is marked according to the source.

[0100] Step S3: Accurately judge power outage and power restoration based on node bidirectional mutual calibration;

[0101] A real-time accurate judgment model for power outage and restoration is constructed, and the power outage and restoration events are deduced and completed from the bottom up using a dynamic storage data container, and the real-time events are layered and the nodes are located. By deducing the topological tree, the switch state changes and the impact range are judged, and the fault type and cause are further judged. In this embodiment, the cause of the power outage caused by the fault can be judged or the fault point can be located by supplementing the perception source. The power outage event is used as an example for introduction.

[0102] Step S3.1: data splitting;

[0103] For each type of power outage event in the dynamic storage data container, mark it according to the source and type; set a six-bit event mark yourself , the first to sixth digits represent substation and upper power outage events, 10kV main line power outage events, 10kV branch line power outage events, distribution area power outage events, user power outage events, and low-voltage power outage events generated by user power outage events. Each digit is assigned 0, 1, and 2, representing non-such events, native power outage events, and derived events, respectively; when yourself ='000021', indicating a low voltage power outage event generated by a user power outage event. you= '002100' indicates a 10kV branch line power outage event generated by a power outage event in a distribution substation area; the event type is marked and a data diversion channel is established, the data diversion channel includes an event diversion channel within the substation area tg , In-line event diversion channel le And the upper power outage event diversion channel sn ; Event diversion channel within the station area tg Including user power outage events and low-voltage power outage events, event diversion channels within the line le Including power outage events in distribution substation area, 10kV main line power outage events and 10kV branch line power outage events, and upper power outage event diversion channels sn This includes 10kV main line power outage events and 10kV branch line power outage events that have been analyzed and judged, that is, the generated events.

[0104] Step S3.2: Establish a power outage event node merging model; define the power outage event node merging model as d 2 u 1. The specific rules of the power outage event node merging model are as follows: through the established data diversion channel, the target data is taken out from the dynamic storage data container, and the target data is the current time t Does not exceed the set threshold dt If the power outage event in the target data is a higher-level power outage event without the same substation-10kV line-distribution station area-user network topology, the target data is deduplicated according to the object and the number of unique events in the target data is counted. Holy When the number of unique events does not meet the requirement, a null value is returned. Otherwise, the proportion of the target event in the same level event diversion channel is updated according to the increase in the number of events in the dynamic storage data container. n , when the specified ratio is not reached ro When n < ro , returns null until n ≥ ro , start upgrading and merging events; when the power outage event in the target data is a higher-level power outage event under the same station-line-transformer-user network topology, the event at this level is marked as a sub-event of the higher-level power outage event, put into the corresponding event cluster, and shield the event at this level. The 10kV branch line power outage event should be merged into the event clusters of substation and upper-level power outage events and 10kV main line power outage events. The merging of substation area power outage events, low-voltage power outage events, and user power outage events can be completed by analogy.

[0105] Step S3.3: Upgrading and merging of power outage events; by pushing the original power outage events in the dynamic storage data container to the diversion channel for real-time classification, aggregation and judgment, the judgment results are updated in the dynamic storage data container to generate the final event.

[0106] Step S3.31: User event upgrade: (1) Upgrade the power outage event in the distribution area. For the user power outage event with event type '000001', enter the event diversion channel within the distribution area. tg , and upgrade and merge the user power outage events through the power outage event node merging model established in step S3.2. When the number of power outage events in the same distribution station area is lt Greater than the first event quantity preset value u 1, and the ratio of the number of users without power to the number of users in the distribution area exceeds the first preset ratio value n 1. Generate event type yourself ='000201' power outage event in the distribution area, and enter the event diversion channel within the line le ;

[0107] (2) Upgrade user power outage events. For user power outage events with event type '000001', when the number of power outage events in the same distribution area is lt Greater than the second event quantity preset value u 2, and the power outage event upgrade conditions of the distribution station area are not met, and the event type is generated yourself = Low voltage power outage event of '000021'.

[0108] Step S3.32: Distribution area event upgrade: (1) Upgrade 10kV main line power outage event. yourself =['000100','000201'] power outage event in the distribution area, enter the event diversion channel within the line le , and upgrade and merge the power outage events in the distribution area. When the number of power outage events in the distribution area under the same line lt Reach the third event quantity preset value u 3. The ratio of the number of power outage distribution areas to the number of all distribution areas under the line reaches the second preset ratio. n 2. Generate event type yourself ='020100' main line power outage event, and enter the upper power outage event diversion channel sn ;

[0109] (2) Upgrade the 10kV branch line power outage event to the event diversion channel entering the line le The number of power outage events in the distribution area under the same line lt Reached the fourth event quantity preset value u At 4:00, further determine the proportion of the number of power distribution areas that are out of power. When the ratio of the number of power distribution areas that are out of power to the number of all power distribution areas under the line reaches the third preset ratio n 3. When the 10kV main line power outage event upgrade conditions are not met, an event type is generated yourself =Special branch line power outage event of '022100', and enter the upper power outage event diversion channel sn , otherwise an event type is generated yourself = 10kV branch line power outage event at '002100'.

[0110] Step S3.33: Line power outage event upgrade: For power outage event type yourself =['010000','020100','022100'] 10kV main line power outage event, special branch line power outage event, in the upper power outage event diversion channel sn When the number of different 10kV main line outage events and special branch line outage events under the same substation or the same busbar is upgraded and merged,lt Reached the fifth event quantity preset value u 5. The number of 10kV main lines corresponding to the power outage line in this substation or under the same bus reaches the fourth preset ratio n 4, and all sources of events involved in the upgrade are yourself = '010000' 10kV main line power outage event, then the event type is generated yourself ='210000' of the upper power outage event, otherwise an event type is generated yourself = The superior power outage event of '200100'.

[0111] Step S3.34: Event update after upgrade: After the event is upgraded, all non-highest power outage events in the event cluster are marked as sub-events and blocked when the event is released. When the highest event is the original power outage event, the original power outage event unique identifier is still used. them If the event is generated after the upgrade, the unique identifier of the event generated after the upgrade is automatically generated during the upgrade. them , and insert the events generated after the upgrade into the dynamic storage data container; the event time after the upgrade merge it is is the average event time of the event cluster, and the event cluster is updated according to the time of the last upgrade and merge. eu , and inserted into the dynamic storage data container.

[0112] Step S3.4: Accuracy correction of power outage events: For primary power outage events, the accuracy is verified by mutual verification of other information except the primary power outage event.

[0113] Step S3.41: Generate a flash outage event: The dynamic storage data container contains a power outage event and a power restoration event. The power restoration event includes the power outage time. it is And the power-on time and , when step S3.2 obtains the target event, the power outage event and power restoration event of the same device are obtained, and the event and > it is , it is marked as a flash outage event; when the event cluster of the power outage event included in the power outage event upgraded and merged in step S3.3 has a proportion reaching the fifth preset proportion value n If the power outage event of 5 meets the flash outage judgment standard, the upgraded power outage event corresponding to the event cluster is marked as a flash outage event, and the power restoration time of the event is generated according to the average power restoration time. and .

[0114] Step S3.42: Secondary verification of original power outage events: Considering the source and characteristics of the events, there is a possibility of false alarms for original distribution station area power outage events and user power outage events. Therefore, the following two types of events need to be verified before the event is released.

[0115] (1) For event type yourself ='000100' of the distribution area power outage event, according to the event source, when it is a power outage event of the entire area that has been verified by the source, that is, the event itself contains the power outage event of the area and the power outage event of some users, then through this verification, when it is a power outage event of the area terminal, the event cluster of the distribution area power outage event is verified. When the number of user power outage events contained in the event cluster is greater than the preset value of the specified event number u 1' or the ratio of power outage users to the number of users in the area reaches the preset value n 1', then the accuracy of the power outage event in the distribution station area is verified;

[0116] (2) For event type yourself ='000001', a single-user power outage event channel is established. Before the event is released and the event is not involved in the upgrade and merging, the event is stored in the single-user power outage event channel, the event waiting time is extended, and the voltage and current data of the called user are supplemented. When the voltage or current data of the called user is normal, it is marked as untrue and deleted, otherwise the accuracy of the user power outage event is verified.

[0117] Step S3.5: Supplement the analysis results: Based on the accurate fault analysis, supplement the information sources other than power outage and power restoration events to expand the scope of analysis.

[0118] Step S3.51: Lightning tripping failure: obtain real-time source-end ground-to-ground lightning data from the lightning location system or the meteorological bureau through the data middle platform, database service, FTP, etc., deduplicate and clean the real-time source-end ground-to-ground lightning data to form lightning strike data, and establish a real-time lightning tripping analysis model.

[0119] (1) Real-time analysis and establishment of a lightning dynamic storage data container to store the analysis results: When a 10kV line fails and the power outage occurs, obtain the time when the failure occurred. it is The difference does not exceed Δ lt If there is lightning strike data in this time period, calculate the shortest distance δ between the lightning strike and the towers along the line. lg , when the distance does not exceed the maximum lightning radius estimated to cause line tripping ltg , that is, satisfying δ lg < ltg , store relevant information in the lightning dynamic storage data container, including power outage events id , power outages, lightning strikes id , lightning strike time, lightning strike point coordinates, lightning current amplitude, nearest tower and tower coordinates, when δ lg < ltg If there is more than one lightning strike, the information of all lightning strikes that meet the conditions and the towers along the line are stored.

[0120] (2) For the 10kV main line and 10kV branch line fault power outages that have completed steps S3.1 to S3.4, before the event is released, the number of lightning strikes that meet the conditions is counted through the established lightning tripping real-time judgment model, and the field ' li 'And assign statistical results and add fields' lia ' and store the closest to the lightning strike point g The coordinates of the towers along the line.

[0121] Step S3.52: Non-automatic fault switch analysis: For 10kV branch line fault power outages, when the action switch after the fault power outage is a distribution automation switch, the power outage event contains the action switch information; when the action switch is a non-automatic switch, the power outage event does not contain the action switch information. By establishing a 10kV line-switch-distribution substation topology tree, the substation range affected by the branch line power outage is calculated, and the switch status in the topology tree is derived.

[0122] Step S3.53: Small current grounding fault: A 10kV line grounding fault will not directly cause a power outage. However, when the grounding line and grounding section cannot be checked, it is necessary to determine the grounding fault point by testing the line, which will expand the scope of the power outage. Through the joint analysis of multi-source data, the scope of the small current grounding fault can be determined.

[0123] (1) Obtaining small current ground fault alarms from the control cloud through the data center and other forms eg , including the fault bus, fault time, and if the substation is equipped with a small current grounding line selection device, there should also be line selection analysis results.

[0124] (2) The distribution automation master station accesses the distribution terminal FTU, station terminal DTU, fault indicator and other equipment information from the data center, and uses the ground fault results of multiple devices on a 10kV line for comprehensive judgment. If the ground fault line reported by the distribution automation master station is consistent with the substation line selection result, it indicates that the corresponding 10kV line is faulty. After the faulty line is determined, if the selection consistency rate of multiple distribution automation terminals on the line exceeds the set threshold, y , indicating that the corresponding 10kV line section is suspected to have a ground fault, and the line and section selection of the ground fault is completed.

[0125] (3) For lines without line selection or section selection devices or lines in substations that are inconsistent with the distribution automation judgment results, if the fault occurs during thunderstorms, obtain alarm events related to small current ground faults in a certain area. eg The time difference between the previous and the next time does not exceed Δ lgThe lightning strike data was used to calculate the number of lightning strikes and lightning current amplitude near all 10kV line towers under the busbar of the substation, and weights were assigned to parameters such as lightning strike distance, number of lightning strikes, lightning current amplitude, and lightning strike time difference. The machine learning model was used to identify the distribution lines and possible tower sections with the highest probability of failure, and complete the line and section selection for grounding faults.

[0126] Step S35.4: Distinguish between fault power outage and planned power outage: Obtain the power outage plan entered from the dispatching OMS and the intelligent power supply service command system, and associate it with the determined power outage event. If the power outage plan covers the scope of the power outage event, and the power outage event falls on the planned day, then the power outage is a planned power outage and should be specially marked and removed when the fault power outage is released.

[0127] Step S35.5: This solution is not limited to the fault type analysis given above. In actual applications, the analysis of other fault types such as short circuit, phase loss, line break, tree barrier, flood, wind disaster, etc. can also be supplemented based on the accurate fault analysis method proposed in this patent.

[0128] Step S3.6: Storage of analysis and judgment results: The final event generated by the completed analysis and judgment is stored in the established result library to generate the latest analysis and judgment event.

[0129] S36.1: Data storage model: Establish a unified data storage model for storage. This patent proposes an example of a data storage model format. The data content of the data storage model should at least include event identifiers. them , organizational relationship, topological relationship, and the proportion of failures in the derivation process of non-native power outage events fr (Percentage of power outage users in the power distribution area, percentage of power outage lines in the power distribution area, percentage of power outage lines in substations), impact range of non-original power outage events fn (users affected by low-voltage power outages and areas affected by 10kV branch line power outages), power outage time it is , Power-on time and (null value if power is not restored), last updated time ut , Event storage time it .

[0130] Step S36.2: Data storage process: calculate the waiting time of the identified event, obtain the dynamic storage data container data, and filter the last update time ut The current time exceeds the set waiting time Δ your The waiting time is differentiated according to different event types, and the events that meet the conditions are inserted into the established result library in the order of the dynamic storage data container and stored in the database.

[0131] Step S36.3: Message release: The power outage event that has been analyzed and judged is displayed or published to the client through the Internet area. When publishing through the Internet area, the analysis result is penetrated to the Internet area through the internal and external network two-way isolation device, and sensitive information is shielded when publishing.

[0132] Step S4: Real-time analysis of the power outage scope;

[0133] Based on the determined time range and according to the power outage and restoration events, the geographical location information of the lines and distribution stations is used to determine the areas that are still out of power and the areas that have been restored, and the results are displayed based on a grid map;

[0134] Step S4.1: Power restoration event analysis: To ensure the real-time release of power outage events, when the conditions for generating a flash outage event are not met, a power restoration time will be inserted according to the data storage model. and The power outage event with a null value is stored in the dynamic storage data container; when a new power-on event enters the dynamic storage data container, the power outage events of the same level and the upper level of the new power-on event are searched. it is The difference between the power outage time of the new power restoration event and the power outage time of the new power restoration event is less than the specified value, and the impact range of the power outage event is fn If the device contains a new power-on event, it is considered as the same power outage event. When the power-on ratio of the original power outage event exceeds the specified threshold rf At that time, it was judged that the original power outage had been completely restored.

[0135] Step S4.2: Display of power outage and power restoration scope:

[0136] (1) According to the power outage and restoration events, the power outage range is automatically counted from top to bottom according to the topological relationship; if a power outage event occurs at a certain node, the devices below the node are marked as power outages, and the number of households during the power outage is counted = power outage duration × number of power outage users; if the number of households during the power outage exceeds the threshold sh 1:00, the power outage has a large impact, and is marked yellow; the number of households exceeds the threshold during the power outage sh At 2 o'clock, the power outage has a large impact and is colored red. The levels are set according to actual needs.

[0137] (2) Based on the selected time period, the power outage equipment and areas are displayed on a grid map. The power outage of the equipment is displayed according to the specified color and status. For example, red flashing indicates a power outage, and blue indicates normal. The changes in power outage and restoration within a time period are displayed on a timeline according to the power outage and restoration status of the equipment at each time point.

[0138] like Figure 2As shown, a real-time analysis system for distribution network status is applied to the real-time analysis method for distribution network status, including: a data acquisition module, a data preprocessing module, a fault analysis module, a fault information publishing module, and an automatic power outage range statistics module; the data acquisition module is used to connect the enterprise middle platform and the real-time measurement center to obtain data from multiple source systems; the data preprocessing module is used to establish a dynamic storage data container to automatically insert and release power outage and power restoration events; the fault analysis module is used to build a real-time power outage and power restoration accurate analysis model to analyze the power outage and power restoration status of equipment at all levels; the fault information publishing module is used to realize the penetration of internal and external network information and publish fault information; the power outage range automatic statistics module is used to count the power outage and power restoration range and display it in a power grid map.

[0139] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A real-time analysis method for distribution network status, It is characterized in that The steps include: Step S1: data acquisition; Based on the data center, the power outage and restoration events and measurement data from the control cloud, distribution automation master station, and power consumption information collection system are obtained, including the power outage and restoration events and voltage, current, and power measurement data of 10kV main lines, 10kV branches, distribution substations, and users; based on the business center, the substation, 10kV line, switch, distribution substation, user ledger, and topology data from the PMS3.0, i.e., the power grid resource business center, and the marketing 2.0 system are obtained; Step S2: data preprocessing; Normalize the power outage and restoration events and measurement data obtained in step S1; establish a storage data container, insert the power outage and restoration events into the storage data container according to the occurrence time of the power outage event, and associate them with the substation-10kV line-distribution station area-user topology to form a dynamic storage data container; Step S3: Accurately judge power outage and power restoration based on node bidirectional mutual calibration; Build a real-time power outage and restoration accurate judgment model, use dynamic storage data containers to deduce and complete power outage and restoration events from bottom to top, and layer and locate real-time events; through the derivation of the topology tree, judge the switch state changes and the scope of influence, and further judge the fault type and fault cause; The specific process of step S3 is: Step S3.1: Data diversion; Specifically, for each type of power outage event in the dynamic storage data container, mark it according to the source and type; set a six-bit event mark te , the first to sixth digits represent substation and upper power outage events, 10kV main line power outage events, 10kV branch line power outage events, distribution area power outage events, user power outage events, and low-voltage power outage events generated by user power outage events. Each digit is assigned 0, 1, and 2, representing non-such events, native power outage events, and derived events, respectively; when te ='000021', indicating a low voltage power outage event generated by a user power outage event. te= '002100' indicates a 10kV branch line power outage event generated by a power outage event in a distribution substation area; the event type is marked and a data diversion channel is established, the data diversion channel includes an event diversion channel within the substation area tg , In-line event diversion channel le And the upper power outage event diversion channel s ; The event diversion channel within the station area tg Including user power outage events and low-voltage power outage events, event diversion channels within the line le Including power outage events in distribution substation area, 10kV main line power outage events and 10kV branch line power outage events, and upper power outage event diversion channels s Including 10kV main line power outage events and 10kV branch line power outage events that have been judged, that is, generated events; Step S3.2: Establish a power outage event node merging model; define the power outage event node merging model as d 2 u 1. The specific rules of the power outage event node merging model are as follows: through the established data diversion channel, the target data is taken out from the dynamic storage data container, and the target data is the current time t Does not exceed the set threshold dt When the power outage event in the target data is a superior power outage event without the same substation-10kV line-distribution station area-user network topology, the target data is deduplicated according to the object and the number of unique events in the target data is counted. sf When the number of unique events does not meet the requirement, a null value is returned. Otherwise, the proportion of the target event in the same level event diversion channel is updated according to the increase in the number of events in the dynamic storage data container. n , when the specified ratio is not reached ro When n < ro , returns null until n ≥ ro , start upgrading and merging events; When the power outage event in the target data is a higher-level power outage event under the same station-line-transformer-user network topology, the event at this level is marked as a sub-event of the higher-level power outage event, put into the corresponding event cluster, and the event at this level is shielded. The 10kV branch line power outage event is merged into the event clusters of substation and upper-level power outage events and 10kV main line power outage events, and so on to complete the merging of substation area power outage events, low-voltage power outage events, and user power outage events; Step S3.3: Upgrading and merging of power outage events; The original power outage events in the dynamic storage data container are pushed to the diversion channel for real-time classification, aggregation and analysis. The analysis results are updated in the dynamic storage data container to generate the final event. Step S3.4: Accuracy correction of power outage events: For the original power outage events, the accuracy is verified by mutual verification of other information except the original power outage events; Step S3.5: Supplement the judgment results: Based on the accurate fault judgment, supplement the information sources other than power outage and power restoration events to expand the judgment scope; Step S3.6: Storage of judgment results: The final event generated by the judgment is stored in the established result library to generate the latest judgment event; The specific process of step S3.3 is: Step S3.31: User event escalation: (1) Upgrade the power outage event in the distribution area. For the user power outage event with event type '000001', enter the event diversion channel within the distribution area tg , and upgrade and merge the user power outage events through the power outage event node merging model established in step S3.

2. When the number of power outage events in the same distribution station area is greater than the first event number preset value u 1 , and the ratio of the number of users with power outage to the number of users in the distribution station area exceeds the first preset ratio value n 1 , generate event type te ='000201' power outage event in the distribution area, and enter the event diversion channel within the line le ; (2) Upgrade user power outage events. For user power outage events with event type '000001', when the number of power outage events in the same distribution area is greater than the second event number preset value, u 2 , and the power outage event upgrade conditions of the distribution station area are not met, the event type is generated te = low voltage power outage event of '000021'; Step S3.32: Distribution area event upgrade: (1) Upgrade 10kV main line power outage event. For power outage event type te =['000100','000201'] power outage event in the distribution area, enter the event diversion channel within the line le , and upgrade and merge the power outage events in the distribution area. When the number of power outage events in the distribution area under the same line reaches the third event number preset value u 3 , and the ratio of the number of power outage distribution stations to the number of all distribution stations under the line reaches the second preset ratio value n 2 , generate event type te ='020100' main line power outage event, and enter the upper power outage event diversion channel s ; (2) Upgrade the 10kV branch line power outage event to the event diversion channel entering the line le When the number of power outage events in the distribution area under the same line reaches the fourth event number preset value u 4 When the ratio of the number of power distribution substations with power outages to the number of all power distribution substations under the line reaches the third preset ratio, n 3 , and if the 10kV main line power outage event upgrade conditions are not met, an event type is generated te =Special branch line power outage event of '022100', and enter the upper power outage event diversion channel s , otherwise an event type is generated te = 10kV branch line power outage event at '002100'; Step S3.33: Line power outage event upgrade: For power outage event type te =['010000','020100','022100'] 10kV main line power outage event, special branch line power outage event, in the upper power outage event diversion channel s When the number of different 10kV main line outage events and special branch line outage events under the same substation or the same busbar reaches the fifth event number preset value, u 5 The number of 10kV main lines corresponding to the power outage line in this substation or under the same bus reaches the fourth preset ratio n 4 , and all sources of events involved in the upgrade are te = '010000' 10kV main line power outage event, then the event type is generated te ='210000' of the upper power outage event, otherwise an event type is generated te =Superior power outage event of '200100'; Step S3.34: Event update after upgrade: After the event is upgraded, all non-highest power outage events in the event cluster are marked as sub-events and blocked when the event is released. When the highest event is the original power outage event, the original power outage event unique identifier is still used. ei If the event is generated after the upgrade, the unique identifier of the event generated after the upgrade is automatically generated during the upgrade. ei , and insert the events generated after the upgrade into the dynamic storage data container; the event time after the upgrade merge es is the average event time of the event cluster, and the event cluster is updated according to the time of the last upgrade and merge. ue , and insert it into the dynamic storage data container; The specific process of step S3.4 is: Step S3.41: Generate a flash outage event: The dynamic storage data container contains a power outage event and a power restoration event. The power restoration event includes the power outage time. es And the power-on time et , when step S3.2 obtains the target event, the power outage event and power restoration event of the same device are obtained, and the event et > es , it is marked as a flash outage event; when the event cluster of the power outage event included in the power outage event upgraded and merged in step S3.3 has a proportion reaching the fifth preset proportion value n 5 If the power outage event meets the flash outage judgment criteria, the upgraded power outage event corresponding to the event cluster is marked as a flash outage event, and the power restoration time of the event is generated according to the average power restoration time. et ; Step S3.42: Secondary verification of the original power outage event: Verify the following events before the event is released: (1) For event type te ='000100', according to the event source, if it is a power outage event for the entire substation area that has been verified by the source, that is, the event itself includes a power outage event for the substation area and a power outage event for some users, then this verification is passed; if it is a power outage event for the substation terminal, then the event cluster of the power outage event for the distribution substation area is verified; if the number of user power outage events included in the event cluster is greater than the preset value of the number of events or the ratio of the power outage users to the number of users in the substation area reaches the preset value of the ratio, then the accuracy verification of the power outage event for the distribution substation area is passed; (2) For event type te ='000001' user power outage event, establish a single user power outage event channel, before the event is released and the event is not involved in the upgrade and merging, store the event in the single user power outage event channel, extend the event waiting time, supplement the user voltage and current data, and when the user voltage or current data is normal, mark it as untrue and delete it, otherwise pass the accuracy check of the user power outage event; The specific process of step S3.5 is: Step S3.51: Lightning tripping fault: obtain real-time source-end ground lightning data from the lightning location system or the meteorological bureau, remove duplicates and clean the real-time source-end ground lightning data to form lightning strike data, and establish a real-time lightning tripping analysis model; (1) Real-time analysis and establishment of a lightning dynamic storage data container to store the analysis results: When a 10kV line fails and the power outage occurs, obtain the time when the failure occurred. es The difference does not exceed Δ lt If there is lightning strike data in this time period, calculate the shortest distance δ between the lightning strike and the towers along the line. lg , when the distance does not exceed the maximum lightning radius estimated to cause line tripping ltg , that is, satisfying δ lg < ltg , store relevant information in the lightning dynamic storage data container, including power outage events id , power outages, lightning strikes id , lightning strike time, lightning strike point coordinates, lightning current amplitude, nearest tower and tower coordinates, when δ lg < ltg If there is more than one lightning strike, all lightning strikes that meet the conditions and the tower information along the line are stored; (2) For the 10kV main line and 10kV branch line fault power outages that have completed steps S3.1 to S3.4, before the event is released, the number of lightning strikes that meet the conditions is counted through the established lightning tripping real-time judgment model, and the field ' li 'And assign statistical results and add fields' lia ' and store the closest to the lightning strike point g The coordinates of the towers along the line; Step S3.52: Non-automatic fault switch analysis: For 10kV branch line fault power outage, when the action switch after the fault power outage is a distribution automation switch, the power outage event contains the action switch information; when the action switch is a non-automatic switch, the power outage event does not contain the action switch information. By establishing a 10kV line-switch-distribution substation area topology tree, the substation area affected by the branch line power outage is calculated, and the switch status in the topology tree is derived; Step S3.53: Determine the scope of the small current grounding fault through joint analysis of multi-source data; (1) Obtaining low current ground fault alarms from the control cloud eg , including fault bus and fault time; (2) The distribution automation master station accesses the equipment information from the data center, and uses the ground fault results of multiple devices on a 10kV line for comprehensive analysis. When the ground fault line reported by the distribution automation master station is consistent with the substation line selection result, it indicates that the corresponding 10kV line is faulty. After the faulty line is determined, when the selection consistency rate of multiple distribution automation terminals on the line exceeds the set threshold, y , indicating that there is a ground fault in the corresponding 10kV line section, and the line and section selection of the ground fault is completed; (3) For lines without line selection or section selection devices or lines in substations that are inconsistent with the distribution automation analysis results, when the fault occurs during thunderstorms, obtain alarm events related to small current ground faults in a certain area. eg The time difference between the previous and the next time does not exceed Δ lg The lightning strike data was used to calculate the number of lightning strikes and lightning current amplitude near all 10kV line towers under the substation busbar, and weights were assigned to the lightning strike distance, number of lightning strikes, lightning current amplitude, and lightning strike time difference parameters. The machine learning model was used to identify the distribution lines and tower sections with the highest probability of failure, and the line and section selection for grounding faults was completed. Step S35.4: Distinguish between fault power outage and planned power outage: Obtain the power outage plan entered from the dispatching OMS and the intelligent power supply service command system, and associate it with the power outage event that has been determined. When the power outage plan covers the scope of the power outage event, and the power outage event falls on the planned day, the power outage is a planned power outage, and a special mark is made, which will be removed when the fault power outage is released; The specific process of step S3.6 is: S36.1: Data storage model: Establish a data storage model for storage; the data content of the data storage model includes event identification ei , organizational relationship, topological relationship, and the proportion of failures in the derivation process of non-native power outage events fr That is, the proportion of power outage users in the power distribution area, the proportion of power outage lines in the power distribution area, the proportion of power outage lines in the substation, and the impact range of non-original power outage events fn That is, the users affected by low-voltage power outages and the areas and duration of power outages affected by 10kV branch line power outages es , Power-on time et If power is not restored, it will be empty, the last updated time ut and event entry time it ; Step S36.2: Data storage process: calculate the waiting time of the identified event, obtain the dynamic storage data container data, and filter the last update time ut The current time exceeds the set waiting time Δ ta The waiting time is differentiated according to different event types, and the events that meet the conditions are inserted into the established result library in the order of the dynamic storage data container and stored in the database; Step S36.3: Message release: Display the power outage event that has been judged or publish it to the client through the Internet region. When publishing through the Internet region, the judgment result is penetrated to the Internet region through the internal and external network bidirectional isolation device, and sensitive information is shielded when publishing; Step S4: Real-time analysis of the power outage scope; Based on a determined time range and according to power outage and power restoration events, the geographical location information of the lines and distribution substations is used to determine the areas that are still out of power and the areas that have been restored, and the information is displayed based on a map of the power grid.

2. A method for real-time analysis of distribution network status according to claim 1, Features: The specific process of step S1 is: Step S1.1: Obtain ledger and topological data; specifically, obtain the ledger, topological relationship and geographic location information of substations, 10kV lines, switches, distribution areas and users from the business middle station; Step S1.2: Obtain real-time events; specifically, use the data center to obtain power outage events from the control cloud, distribution automation master station, and power consumption information collection system; Step S1.3: Obtain measurement data; specifically, use the data center to obtain voltage, current and power measurement data from the control cloud, distribution automation master station and power consumption information collection system, and perform automatic verification of the network topology.

3. A method for real-time analysis of distribution network status according to claim 2, Features: The specific process of step S1.2 is as follows: Step S1.21: Obtain the switch position change alarm data table, SOE alarm data table and accident total alarm data table from the control cloud and the distribution automation master station respectively; obtain the power outage and restoration events of the distribution station area and the power outage and restoration events of the user from the power consumption information collection system; The specific process of step S1.3 is as follows: Step S1.31: Check whether the network topology relationship of substation-10kV line-distribution substation area-user is accurate, and identify and correct abnormal network topology relationships.

4. A method for real-time analysis of distribution network status according to claim 3, Features: The specific process of step S2 is: Step S2.1: Data cleaning; specifically, remove abnormal data from the following three points: First, timeout data, the time difference between the power outage event time and the current time exceeds Δ t 1 Eliminate power outage events; Second, timing error time: for the same power outage and power restoration event, if the power restoration event is earlier than the power outage event, the power restoration event will be eliminated; Third, if the key fields are missing, the power outage and power restoration events that lack the power outage and restoration event time, terminal or meter number will be eliminated; Step S2.2: Establish a dynamic storage data container; Specifically, establish a dynamic storage data container for storing real-time power outage and power restoration events, with the current time t is the midpoint of the dynamic storage data container, and the left and right offset times of the dynamic storage data container are Δ tl and Δ tr , the left boundary of the dynamic storage data container is t -Δ tl , the right boundary of the dynamic storage data container is t +Δ tr ; Periodically calibrate the boundaries of the dynamic storage data container, specifically, update the left boundary of the dynamic storage data container, delete expired data in the dynamic storage data container, update the right boundary of the dynamic storage data container, and insert data from the right position into the dynamic storage data container in sequence according to the power-off and power-on event timing, and locate the order of inserting the power-off and power-on events according to the positions of the inserted power-off and power-on events in the dynamic storage data container; Step S2.3: Establish the relationship between events and topology; specifically, based on the equipment identification carried by the power outage and power restoration events, associate the power outage events with the 10kV lines, distribution substations, and users, apply the relationship of the automatic verification of the network topology in step S1.3, complete the association of the power outage events with the substations, 10kV lines, distribution substations, and users, generate a universal format event, and enter the dynamic storage data container; wherein, the 10kV line includes a 10kV main line and a 10kV branch line.

5. A method for real-time analysis of distribution network status according to claim 4, Features: The specific process of step S2.3 is: Step S2.31: After associating the 10kV main line power outage event from the control cloud with the distribution station account, that is, the distribution station area account obtained in step S1.1, the feeder number, feeder name, 10kV main line power outage event time, protection warning, and switch change are obtained. In the case where the dispatching side and the distribution station account cannot be directly matched, the substation and feeder name are extracted according to the protection alarm and switch change signal content sent by the dispatching side, and matched with the substation and feeder name established in step S1.3 to obtain the corresponding feeder number and name, and the 10kV main line power outage event type is marked according to the source; Step S2.32: after associating the 10kV branch line power outage event from the distribution automation master station with the distribution station account through the feeder or switch number and switch name in the 10kV branch line power outage event, the feeder number, feeder name, switch number, switch name, 10kV branch line power outage event time, protection alarm, switch position information are obtained, and the 10kV branch line power outage event type is marked according to the source; Step S2.33: The distribution station area power outage event from the power consumption information collection system is associated with the marketing ledger, i.e., the ledger of the marketing 2.0 system obtained in step S1.1, through the terminal or meter number in the distribution station area power outage event, to obtain the distribution station area to which the distribution station area power outage event belongs, and then connected with the distribution station ledger. After being associated with the distribution station ledger, the feeder number, feeder name, distribution station area number, station area name, and distribution station area power outage event time are obtained. If it is a distribution station area power restoration event, the distribution station area power outage and restoration event time are included, and the distribution station area power outage and restoration event types are marked according to the source; Step S2.34: Associate the user power outage event from the electricity consumption information collection system with the marketing ledger through the user meter number in the user power outage event, obtain the user and the distribution station area to which they belong in the user power outage event, and connect it with the distribution station ledger. After associating with the distribution station ledger, the feeder number, feeder name, distribution station area number, distribution station area name, user number, user name, and user power outage event time are obtained. If it is a user power-on event, the user power-off and power-on event times are included, and the type of user power outage event is marked according to the source.

6. A method for real-time analysis of distribution network status according to claim 1, Features: The specific process of step S4 is: Step S4.1: Power-on event analysis: When the conditions for generating a flash stop event are not met, a power-on time will be inserted according to the data storage model. et The power outage event with a null value is stored in the dynamic storage data container; when a new power-on event enters the dynamic storage data container, the power outage events of the same level and the upper level of the new power-on event are searched. es The difference between the power outage time of the new power restoration event and the power outage time of the new power restoration event is less than the specified value, and the impact range of the power outage event is fn If the device contains a new power-on event, it is considered as the same power outage event. When the power-on ratio of the original power outage event exceeds the specified threshold rf At that time, it was determined that the original power outage had been completely restored; Step S4.2: Display of power outage and power restoration scope: (1) According to the power outage and restoration events, the power outage range is automatically counted from top to bottom according to the topological relationship; if a power outage event occurs at a certain node, the devices below the node are marked as power outages, and the number of households during the power outage is counted = power outage duration × number of power outage users; when the number of households during the power outage exceeds the threshold sh 1 When the power outage range exceeds the threshold, yellow is used; when the power outage number exceeds the threshold sh 2 When the power outage range is red, the levels are set according to actual needs; (2) Display the power outage equipment and areas on a grid map according to the selected time period, and display the power outage equipment according to the specified color and status.

7. A distribution network status real-time analysis system, applied to the distribution network status real-time analysis method according to any one of claims 1 to 6, It is characterized in that include: Data acquisition module, data preprocessing module, fault analysis module, fault information release module, and automatic power outage range statistics module; the data acquisition module is used to connect the enterprise middle platform and the real-time measurement center to obtain data from multiple source systems; The data preprocessing module is used to establish a dynamic storage data container and automatically insert and release power outage and power restoration events; the fault analysis module is used to build a real-time power outage and power restoration accurate analysis model to analyze the power outage and power restoration status of equipment at all levels; the fault information release module is used to achieve the penetration of internal and external network information and release fault information; the power outage range automatic statistics module is used to count the power outage and power restoration range and display it in a grid map.

Citation Information

Patent Citations

  • Power distribution network digital operation and maintenance method and system and readable storage medium

    CN115983519A

  • Power grid situation awareness fault studying and judging method, system and equipment and storage medium

    CN117559635A