An intelligent cost control platform for power transmission and transformation projects

Through the cost intelligent management and control platform of power transmission and transformation projects, the reasonableness evaluation index model is used to conduct real-time analysis of construction data, which solves the problem of difficult cost control during the construction stage, realizes timely monitoring and management of construction data, and avoids cost increases.

CN118313630BActive Publication Date: 2024-10-18ECONOMIC TECH RES INST OF STATE GRID ANHUI ELECTRIC POWER
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202410730702.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-06
Publication Date
2024-10-18
Estimated Expiration
2044-06-06

AI Technical Summary

Technical Problem

Existing technology makes it difficult to effectively control costs from the construction aspects of power transmission and transformation projects, resulting in construction progress and quality issues leading to cost increases.

Method used

Provide an intelligent cost management and control platform for power transmission and transformation projects. By acquiring construction progress data, material usage data, equipment arrangement data and construction plan data, it builds a reasonable degree evaluation index model, analyzes and issues alarm signals in real time, and realizes real-time cost monitoring. Monitor and manage.

Benefits of technology

Real-time analysis of materials, equipment and planning data during the construction phase of power transmission and transformation projects is realized, abnormal situations are discovered in a timely manner, avoiding significant increases in costs, reducing material expenses, and improving management efficiency and accuracy of construction control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118313630B_ABST
    Figure CN118313630B_ABST
Patent Text Reader

Abstract

The present invention discloses an intelligent cost control platform for power transmission and transformation projects. The intelligent cost control platform for power transmission and transformation projects includes: an acquisition module: used to acquire power transmission and transformation projects, and acquire the construction phase of power transmission and transformation projects according to the progress of power transmission and transformation projects; a division module: used to analyze the construction phase of power transmission and transformation projects to obtain construction sub-phases; a material analysis module: used to analyze the material usage data of the construction sub-phase; an equipment analysis module: used to analyze the equipment arrangement data of the construction sub-phase; a construction analysis module: used to analyze the construction plan data of the construction sub-phase; a comprehensive analysis module: used to analyze the cost of power transmission and transformation projects in combination with material usage data, equipment arrangement data and construction plan data. The present invention timely discovers abnormal situations in the construction sub-phases of power transmission and transformation projects and handles them, thereby avoiding a substantial increase in cost, thereby solving the problem in the prior art that it is difficult to control the cost from the construction aspect of power transmission and transformation projects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of engineering cost, and in particular to an intelligent cost control platform for power transmission and transformation projects. Background Art

[0002] Power transmission and transformation projects refer to projects that transmit the electricity generated by power plants to substations through transmission lines, then use transformers to raise and lower the voltage, and finally distribute it to users. Power transmission and transformation projects have high investment costs, long construction periods, and many links. Therefore, it is very necessary to conduct intelligent cost control of power transmission and transformation projects. In terms of cost control of power transmission and transformation projects, traditional management methods mainly rely on manual budget preparation, review, and control. This method is inefficient, prone to errors, and cannot grasp the progress and cost of the project in real time, making it difficult to achieve effective cost control.

[0003] The existing cost control system realizes the cost control function of the power transmission and transformation project by carefully recording and counting each part of the power transmission and transformation project that requires expenditure, obtaining the overall expenditure, comparing the overall expenditure with the estimated expenditure and controlling it.

[0004] For example, the patent application with publication number: CN111414583A discloses a method for investment estimation and cost analysis and control of power grid technical transformation and maintenance projects, which includes four parts: an indicator management module, a cost estimation module, a project review module and a statistical analysis module; the indicator management module is used to maintain basic data supporting planned funding estimation; the cost estimation module is used to estimate planned funds for production technical transformation and repair projects; the project review module is used to conduct online review of project planned funds; and the statistical analysis module is used to conduct multi-dimensional statistical analysis of cost data.

[0005] For example, the patent application with publication number: CN116756832A discloses a system and method for engineering cost control based on BIM technology, including: a construction control module, which is used to obtain actual construction information; a BIM model building module builds a 5DBIM prediction model according to the input predetermined cost information; an information matching module matches the construction information with the 5DBIM prediction model to obtain a 5DBIM real model and a BIM prediction model for the pre-construction stage; a prediction update module updates the BIM prediction model for the pre-construction stage through the 5DBIM real model using a BP neural network; a dynamic management module obtains model matching information based on the 5DBIM prediction model, the 5DBIM real model and the BIM prediction model for the pre-construction stage; a maintenance management module receives the 5DBIM real model based on the model matching information, and formulates maintenance cycles and analyzes maintenance costs.

[0006] However, in the process of implementing the technical solution of the invention in the embodiments of the present application, the present application found that the above technology has at least the following technical problems:

[0007] In the prior art, the actual construction process of the power transmission and transformation project may be affected by unexpected situations, resulting in problems in construction progress, construction quality, etc., which in turn leads to an increase in the cost of the power transmission and transformation project. It is difficult to control the cost from the construction aspect of the power transmission and transformation project. Summary of the invention

[0008] The embodiment of the present application solves the problem in the prior art that it is difficult to control the cost from the construction aspect of the power transmission and transformation project by providing an intelligent cost control platform for the power transmission and transformation project, and realizes cost control from the construction aspect of the power transmission and transformation project.

[0009] The embodiment of the present application provides an intelligent cost management and control platform for power transmission and transformation projects, including:

[0010] A division module is used to obtain the progress data of the power transmission and transformation project, divide the progress of the power transmission and transformation project, and obtain the construction stage data after division, wherein the construction stage data includes material use parameter data, equipment arrangement parameter data, and construction plan parameter data;

[0011] The material analysis module is used to obtain material usage parameter data, perform data processing and analysis on the material usage parameter data, build a material usage rationality evaluation index model through machine learning, and analyze the material usage data of the construction sub-stage according to the material usage rationality evaluation index model;

[0012] Equipment analysis module: used to obtain equipment arrangement parameter data, process the equipment arrangement parameter data, build an equipment arrangement rationality evaluation index model, and analyze the rationality of equipment arrangement during the construction process through the equipment arrangement rationality evaluation index model;

[0013] The construction analysis module is used to obtain and preprocess the construction plan parameter data, analyze the preprocessed construction plan parameter data to obtain a construction plan rationality evaluation index, and evaluate the rationality of the construction plan during the construction process through the construction plan rationality evaluation index;

[0014] Comprehensive analysis module: used to obtain the output information fed back by the material analysis module, equipment analysis module and construction analysis module, and conduct a comprehensive analysis of the output information to determine the rationality of the cost of the power transmission and transformation project and issue an alarm signal.

[0015] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages:

[0016] 1. By analyzing the construction phase of the power transmission and transformation project, the construction sub-phase is obtained, which is used to analyze the material usage data of the construction sub-phase, the equipment arrangement data of the construction sub-phase, and the construction plan data of the construction sub-phase. In this way, the cost of the power transmission and transformation project is analyzed in combination with the material usage data, equipment arrangement data and construction plan data, thereby realizing timely discovery and processing of abnormal situations in the construction sub-phase of the power transmission and transformation project, avoiding a substantial increase in cost, and effectively solving the problem in the existing technology that it is difficult to control the cost from the construction aspect of the power transmission and transformation project.

[0017] 2. By obtaining material usage parameter data, the material usage parameter data is normalized, and the normalized material usage parameter data is analyzed to obtain the material usage rationality evaluation index, so as to analyze the material usage data of the construction sub-stage according to the material usage rationality evaluation index, thereby realizing timely discovery of unreasonable use of construction materials based on the material usage data, and making rectifications, thereby reducing material cost expenditure and improving the efficiency of material management and control.

[0018] 3. By combining material usage data, equipment arrangement data, and construction plan data to analyze the cost of power transmission and transformation projects, abnormal situations in construction sub-stages can be discovered in a timely manner, and early warning reminders can be issued. This enables staff to quickly discover abnormal situations in the construction process and make corrections, avoiding increases in the cost of power transmission and transformation projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 A schematic diagram of the structure of an intelligent cost management and control platform for power transmission and transformation projects provided in an embodiment of the present application. DETAILED DESCRIPTION

[0020] The embodiment of the present application solves the problem that it is difficult to control the cost from the construction aspect of the power transmission and transformation project in the prior art by providing an intelligent cost control platform for the power transmission and transformation project. The power transmission and transformation project is acquired through an acquisition module, and the construction phase of the power transmission and transformation project is acquired according to the progress of the power transmission and transformation project; the construction phase of the power transmission and transformation project is analyzed through a division module to obtain a construction sub-phase; the material usage data of the construction sub-phase is analyzed through a material analysis module; the equipment arrangement data of the construction sub-phase is analyzed through an equipment analysis module; the construction plan data of the construction sub-phase is analyzed through a construction analysis module; the power transmission and transformation project cost is analyzed by combining the material usage data, equipment arrangement data and construction plan data through a comprehensive analysis module, thereby realizing cost control from the construction aspect of the power transmission and transformation project.

[0021] The technical solution in the embodiment of the present application is to solve the above-mentioned problem that it is difficult to control the cost from the construction aspect of the power transmission and transformation project. The overall idea is as follows:

[0022] By obtaining the power transmission and transformation project, obtaining the construction stage of the power transmission and transformation project according to the progress of the power transmission and transformation project, analyzing the construction stage of the power transmission and transformation project to obtain the construction sub-stage, obtaining the material usage parameter data, analyzing to obtain the material usage rationality evaluation index, analyzing the material usage data of the construction sub-stage according to the material usage rationality evaluation index, obtaining the equipment arrangement parameter data of the construction sub-stage, obtaining the equipment arrangement rationality evaluation index, analyzing the equipment arrangement data of the construction sub-stage according to the equipment arrangement rationality evaluation index, obtaining the construction plan parameter data, analyzing to obtain the construction plan rationality evaluation index, analyzing the construction plan data of the construction sub-stage according to the construction plan rationality evaluation index, combining the material usage data, equipment arrangement data and construction plan data to analyze the power transmission and transformation project cost, thereby achieving the effect of controlling the cost from the construction aspect of the power transmission and transformation project.

[0023] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0024] like Figure 1 As shown, it is a structural schematic diagram of a cost intelligent management and control platform for a power transmission and transformation project provided in an embodiment of the present application. The cost intelligent management and control platform for a power transmission and transformation project provided in an embodiment of the present application includes: an acquisition module, a division module, a material analysis module, an equipment analysis module, a construction analysis module and a comprehensive analysis module; wherein the material analysis module is used to obtain material usage parameter data, and perform data processing and analysis on the material usage parameter data, construct a material usage rationality evaluation index model through machine learning, and analyze the material usage data of the construction sub-stage according to the material usage rationality evaluation index model; the equipment analysis module: is used to obtain equipment arrangement parameter data, and perform data processing and analysis on the equipment arrangement The parameter data is processed to construct an equipment arrangement rationality evaluation index model, and the rationality of the equipment arrangement during the construction process is analyzed through the equipment arrangement rationality evaluation index model; the construction analysis module is used to obtain the construction plan parameter data and perform preprocessing, analyze the preprocessed construction plan parameter data to obtain the construction plan rationality evaluation index, and evaluate the rationality of the construction plan during the construction process through the construction plan rationality evaluation index; the comprehensive analysis module is used to obtain the output information fed back by the material analysis module, the equipment analysis module and the construction analysis module, and conduct a comprehensive analysis of the output information to determine the rationality of the cost of the power transmission and transformation project and issue an alarm signal.

[0025] In this embodiment, the intelligent management and control platform for the cost of power transmission and transformation projects can realize real-time monitoring and management of the cost of power transmission and transformation projects, improve management efficiency, and reduce costs, which is of great significance for ensuring the safe, efficient and economical construction and operation of power transmission and transformation projects.

[0026] Furthermore, the specific analysis process for obtaining the construction phase of the power transmission and transformation project is as follows: obtaining the power transmission and transformation project; dividing the power transmission and transformation project into the preliminary preparation phase, the construction preparation phase, the construction phase, the commissioning and operation phase, the completion acceptance phase and the operation and maintenance phase according to the progress of the power transmission and transformation project; obtaining the construction phase means obtaining the construction phase of the power transmission and transformation project.

[0027] In this embodiment, the power transmission and transformation project is usually divided into the following stages: Preliminary preparation stage: including feasibility study, planning and site selection, environmental impact assessment, engineering design, bidding and other work. Construction preparation stage: including cleaning of the construction site, construction of temporary facilities, procurement and entry of materials and equipment, training of construction personnel and formulation of construction plans. Construction stage: including tower assembly, line erection, substation construction, equipment installation and other work. Debugging and operation stage: including equipment debugging, system joint debugging, operation test and other work. Completion acceptance stage: including project quality acceptance, environmental protection acceptance, safety acceptance and other work. Operation and maintenance stage: after the power transmission and transformation project is put into operation, regular manual inspection and maintenance are required to ensure the stable operation of the project. At the same time, regular inspection and maintenance of equipment are also required to extend the service life of the equipment.

[0028] Furthermore, the specific analysis process of the construction sub-stages obtained by analyzing the construction stage of the power transmission and transformation project is as follows: the construction stage of the power transmission and transformation project is divided into multiple construction sub-stages according to the construction progress; the construction sub-stages are monitored in real time and data is acquired.

[0029] In this embodiment, the construction phase includes tower assembly, line erection, substation construction, equipment installation and other work. There are significant differences in the main work items carried out at different times during the construction phase. Foundation construction: According to the engineering design, the tower foundation is excavated and poured. Tower assembly: Including the transportation, assembly, welding and other processes of tower materials. Tower assembly is a key step in power transmission and transformation projects. Line erection: After the tower assembly is completed, the transmission line is erected, involving the erection of conductors, the laying of ground wires, etc. Equipment installation: After the transmission and transformation tower assembly and line erection are completed, the substation equipment is installed, including transformers, switchgear, protection devices, etc.

[0030] The materials, equipment and construction arrangements used in each stage are different. When the construction stage is divided into multiple sub-stages, each sub-stage can be analyzed in detail, and abnormal conditions can be discovered in time when they occur, avoiding abnormal conditions for a long time, which will increase the cost of the power transmission and transformation project.

[0031] Furthermore, the specific process of analyzing the material usage data of the construction sub-stage is as follows: obtaining material usage parameter data by real-time monitoring the construction sub-stage and acquiring data; normalizing the material usage parameter data; analyzing the normalized material usage parameter data to obtain a material usage rationality evaluation index, which is used to reflect the rationality of material usage during the construction process; and analyzing the material usage data of the construction sub-stage based on the material usage rationality evaluation index.

[0032] The present embodiment uses an interpolation method to process missing data and abnormal data in the material usage parameter data, and normalizes the processed data; specifically includes: classifying and sorting the material usage parameter data, finding missing data and abnormal data, and filling the missing data by Lagrange interpolation method; and using the Z-score normalization formula to process the filled data to obtain standard data;

[0033] Compare the standard data with the parameter preset data, and eliminate the data with the largest and smallest differences from the standard data.

[0034] The following data processing can be performed using the above method.

[0035] In this embodiment, the following methods can be used to monitor the construction sub-stages of the power transmission and transformation project in real time: drones equipped with high-definition cameras, thermal imagers and other equipment conduct aerial inspections of the construction site, transmit images in real time, and effectively monitor the construction progress and site safety. Install high-definition cameras at the construction site, and transmit video signals to the monitoring center via wired or wireless networks to achieve real-time monitoring. The monitoring center can monitor the construction site around the clock and in all directions to ensure construction progress and safety. Geographic Information System (GIS): Utilize GIS technology to manage the geographical location, line direction, construction progress and other information of the power transmission and transformation project, realize the visualization of the construction process, and help improve the efficiency of construction management. By adopting a variety of monitoring methods and equipment, real-time monitoring of the construction process of the power transmission and transformation project can be achieved to ensure construction progress and safety.

[0036] In the above method, the normalization processing includes: minimum-maximum normalization, normalization, normalization and deviation normalization, etc. After the material use parameter data is normalized, the material use parameter data is in the same dimension and range, which can be compared more fairly and facilitate numerical calculation. Normalization of the material use parameter data is conducive to calculating a more accurate material use rationality evaluation index.

[0037] Furthermore, the specific process of analyzing the equipment arrangement data of the construction sub-stage is as follows: obtaining the equipment arrangement parameter data of the construction sub-stage; performing data processing on the equipment arrangement parameter data; obtaining an equipment arrangement rationality evaluation index based on the equipment arrangement parameter data after data processing, the equipment arrangement rationality evaluation index being used to reflect the rationality of the equipment arrangement during the construction process; and analyzing the equipment arrangement data of the construction sub-stage based on the equipment arrangement rationality evaluation index.

[0038] In this embodiment, the equipment arrangement parameter data is processed, and the data processing includes data cleaning and data conversion. The equipment arrangement parameter data is removed through data cleaning, thereby improving the quality and accuracy of the equipment arrangement parameter data. The equipment arrangement parameter data is converted into a format suitable for analysis through data conversion, such as standardization, normalization or encoding conversion, so as to facilitate subsequent processing. Data processing of the equipment arrangement parameter data is conducive to obtaining a more accurate equipment arrangement rationality evaluation index.

[0039] Furthermore, the specific process of analyzing the construction plan data of the construction sub-stage is: obtaining the construction plan parameter data; preprocessing the construction plan parameter data; analyzing the preprocessed construction plan parameter data to obtain the construction plan rationality evaluation index, and the construction plan rationality evaluation index is used to reflect the rationality of the construction plan during the construction process; analyzing the construction plan data of the construction sub-stage according to the construction plan rationality evaluation index.

[0040] In this embodiment, the construction plan parameter data is preprocessed, and the preprocessing includes normalization, data cleaning and data organization. The accuracy and quality of the construction plan parameter data are improved through the preprocessing, which is conducive to obtaining a more accurate construction plan rationality evaluation index based on the construction plan parameter data.

[0041] Furthermore, the material use rationality evaluation index can be obtained by the following methods, including but not limited to: using computer simulation technology, such as discrete event simulation (DES) or system dynamics (SD), to simulate the construction process, predict material demand and consumption, and evaluate the impact of different strategies on material use; using the material requirement planning (MRP) system to accurately calculate the demand and reduce the situation of excess or shortage of materials. The material use rationality evaluation index can also be calculated. The specific method for obtaining the material use rationality evaluation index is: dividing the construction phase of the power transmission and transformation project into multiple construction sub-phases, obtaining the number of construction sub-phases, and numbering the construction sub-phases; performing multiple data collection on the construction sub-phases, obtaining the number of data collections, and numbering the number of data collections; obtaining the types of materials used in the construction sub-phases, and numbering the types of materials; obtaining material use parameter data; constructing a calculation formula for the material use rationality evaluation index; the specific calculation formula for the material use rationality evaluation index is:

[0042]

[0043] In the formula, Expressed as The material use rationality evaluation index for each construction sub-stage, , Expressed as the total number of construction sub-stages, Expressed as The construction sub-phase is The number of material types used during data collection, , It is expressed as the total number of data collection times, Expressed as The number of material types planned to be used in each construction sub-phase, Expressed as The first construction phase The material in The actual weight of material consumed at the time of data collection, , Expressed as the total number of material types, Expressed as The first construction sub-phase The planned material consumption weight of the material, Expressed as The construction sub-phase is The actual cost of materials during data collection, Expressed as The planned expenditure on materials for each construction sub-phase, It is expressed as the weight ratio of the number of material types used in the material use rationality assessment index. It is expressed as the weight ratio of the actual material consumption weight in the material use rationality evaluation index. It is expressed as the weight ratio of actual material expenditure in the material utilization rationality assessment index.

[0044] In this embodiment, , and The value range of is between 0 and 1, and satisfies . By consulting the procurement contract and construction plan, the types, quantities, quality standards, delivery time and prices of materials used in the construction sub-stage are clarified, and the planned types and quantities of materials, the planned consumption weight of materials and the planned expenditure of materials are obtained. By manually counting the types of materials used in the construction sub-stage, the consumption of each material and the amount of material expenditure, the types and quantities of materials used, the actual consumption weight of materials and the actual expenditure of materials are obtained.

[0045] By taking square root, the curve of the material utilization rationality assessment index becomes smoother, which is conducive to observing the changes of the material utilization rationality assessment index.

[0046] Furthermore, the equipment arrangement rationality evaluation index can be obtained through a variety of methods, including: using risk assessment methods, such as expected losses, confidence intervals, etc., to clarify the risk level of the leasing arrangement; conducting sensitivity analysis on key parameters (such as leasing price, usage time, demand, etc.) to clarify the qualification level of the leasing arrangement. The equipment arrangement rationality evaluation index can also be calculated. The specific method for obtaining the equipment arrangement rationality evaluation index is: dividing the construction phase of the power transmission and transformation project into multiple construction sub-phases, obtaining the number of construction sub-phases, and numbering the construction sub-phases; performing multiple data collection on the construction sub-phases, obtaining the number of data collection times, and numbering the number of data collection times; obtaining the number of construction equipment used in the construction sub-phases, and numbering the construction equipment; obtaining equipment arrangement parameter data; constructing a calculation formula for the equipment arrangement rationality evaluation index; the specific equipment arrangement rationality evaluation index calculation formula is: In the formula, Expressed as The equipment arrangement rationality evaluation index for each construction sub-stage, , Expressed as the total number of construction sub-stages, Expressed as The first construction sub-phase Construction equipment in The actual power consumption of the construction equipment during the data collection. , It is expressed as the total number of data collection times, , Expressed as the total number of construction equipment, Expressed as The first construction sub-phase Expected power consumption of construction equipment for each construction equipment, Expressed as The first construction sub-phase Construction equipment in The construction equipment rental expenses during the data collection, Expressed as The first construction sub-phase Expected rental expenses for construction equipment for each construction equipment, Expressed as The construction sub-phase is The actual number of leased equipment at the time of data collection, Expressed as Expected number of rental equipment for each construction sub-phase, It is expressed as the weight ratio of the actual power consumption of construction equipment in the evaluation index of the rationality of equipment arrangement. It is expressed as the weight ratio of construction equipment leasing expenditure in the equipment arrangement rationality evaluation index. It is expressed as the weight ratio of the actual number of leased equipment in the evaluation index of the rationality of equipment arrangement. Expressed as a natural constant.

[0047] In this embodiment, , and All values ​​are in the range of 0-1 and satisfy , and The sum is equal to 1. The equipment usage time and the planned number of leased equipment arranged in the construction sub-phase are checked from the financial statements and schedules of the power transmission and transformation project to obtain the expected rental expenditure of the construction equipment and the expected number of leased equipment. The expected power consumption of the construction equipment is obtained by checking the planned usage time of the equipment and the equipment operating power. The rental equipment cost and the number of leased equipment are obtained from the construction log and construction record sheet to obtain the rental expenditure of the construction equipment and the actual number of leased equipment. The actual usage time of the construction equipment is obtained by statistics and multiplied by the equipment operating power to obtain the actual power consumption of the construction equipment.

[0048] By using the logarithmic function, the fitting curve of the equipment arrangement rationality evaluation index changes slowly, which is conducive to the detailed analysis of the changes in the equipment arrangement rationality evaluation index.

[0049] The construction plan rationality evaluation index can be obtained through a variety of methods, including: using computer simulation technology to predict the future progress of the project, evaluate the rationality of the current schedule, and predict possible delays; agile methods use short-cycle construction iterations (called "sprints") to evaluate and adjust the progress to ensure that the project can quickly adapt to changes on site. The construction plan rationality evaluation index can also be calculated. The specific calculation formula for the construction plan rationality evaluation index is:

[0050]

[0051] In the formula, Expressed as The construction plan rationality evaluation index of each construction sub-stage, Expressed as The construction sub-phase is The actual construction time at the time of data collection, Expressed as The construction planning duration of each construction sub-phase, Expressed as The permitted extension period for each construction phase is: Expressed as The construction sub-phase is The duration of extreme weather during the data collection period, Expressed as The construction sub-phase is The duration of the accident at the time of data collection, Expressed as The construction sub-phase is The actual construction expenditure at the time of data collection, Expressed as The construction planning expenditure for each construction sub-phase, It is expressed as the weight ratio of the actual construction duration in the construction plan rationality evaluation index. It is expressed as the weight ratio of extreme weather duration in the construction plan rationality evaluation index. It is expressed as the weight ratio of the accident duration in the construction plan rationality evaluation index. It is expressed as the weight ratio of the actual construction expenditure in the construction plan rationality evaluation index. , , and The value range of is between 0 and 1, and satisfies .

[0052] Extreme weather phenomena, such as storms, floods, typhoons, tornadoes, etc., will threaten the safety of the construction site and will also affect the construction progress. In some areas, climate change may lead to more extreme weather, which will increase the uncertainty and difficulty of power transmission and transformation project construction. Therefore, the specific construction arrangements need to take meteorological aspects into consideration.

[0053] Obtain the scheduled construction time and the planned construction cost on the construction schedule, obtain the planned construction time and planned construction expenditure, and obtain the actual construction time, extreme weather time, accident time and actual construction expenditure by monitoring and counting the construction sub-stages.

[0054] Furthermore, the specific analysis process of material usage data is as follows: obtaining an evaluation index of material usage rationality, obtaining a first material threshold and a second material threshold; when the evaluation index of material usage rationality is greater than the first material threshold and the evaluation index of material usage rationality is less than the second material threshold, it indicates that construction materials are used reasonably; when in other situations, it indicates that construction materials are not used reasonably; the specific analysis process of equipment arrangement data is as follows: obtaining an evaluation index of equipment arrangement rationality, obtaining a first equipment threshold and a second equipment threshold; when the evaluation index of equipment arrangement rationality is greater than the first equipment threshold and the evaluation index of equipment arrangement rationality is less than the second equipment threshold, it indicates that the equipment arrangement is reasonable; when in other situations, it indicates that the equipment arrangement is unreasonable; the specific analysis process of construction plan data is as follows: obtaining an evaluation index of construction plan rationality, obtaining a first construction threshold and a second construction threshold; when the evaluation index of construction plan rationality is greater than the first construction threshold and the evaluation index of construction plan rationality is less than the second construction threshold, it indicates that the construction plan is reasonable; when in other situations, it indicates that the construction plan is unreasonable.

[0055] In this embodiment, the material use rationality evaluation index is obtained, and the material use rationality evaluation index is analyzed to obtain the material first threshold value and the material second threshold value. The material first threshold value is , the second threshold of the material is , when the material use reasonable degree evaluation index is greater than the material first threshold and the material use reasonable degree evaluation index is less than the material second threshold, that is When , it indicates that the construction materials are used reasonably.

[0056] Obtain the equipment arrangement rationality evaluation index, analyze the equipment arrangement rationality evaluation index to obtain the equipment first threshold and the equipment second threshold. The equipment first threshold is , the second threshold of the device is , when the equipment arrangement rationality evaluation index is greater than the equipment first threshold and the equipment arrangement rationality evaluation index is less than the equipment second threshold, that is , it indicates that the equipment arrangement is reasonable.

[0057] Obtain the construction plan rationality evaluation index, analyze the construction plan rationality evaluation index to obtain the first construction threshold and the second construction threshold. The first construction threshold is , the second construction threshold is , when the construction plan rationality evaluation index is greater than the first construction threshold and the construction plan rationality evaluation index is less than the second construction threshold, that is , it indicates that the construction plan is reasonable.

[0058] Furthermore, the specific analysis process of analyzing the transmission and transformation project cost by combining material usage data, equipment arrangement data and construction plan data is as follows: when two or more of the material usage data in the construction sub-stage indicate that the construction materials are not used reasonably, the equipment arrangement data indicate that the equipment arrangement is unreasonable, and the construction plan data indicate that the construction plan is unreasonable, it indicates that an abnormal situation has occurred in the construction sub-stage, and an early warning reminder is issued; when it is in other situations, it indicates that the construction sub-stage is in normal situation.

[0059] In order to more intuitively and accurately judge the rationality of the cost of the power transmission and transformation project, this embodiment adopts the image analysis method for comparative analysis, specifically:

[0060] Collect data on the output information fed back by the material analysis module and the equipment analysis module;

[0061] Classify the collected data and draw curve images through machine learning;

[0062] Analyze the curve image, output unreasonable cost data of the power transmission and transformation project, and issue early warning reminders.

[0063] In this embodiment, when an abnormal situation occurs in a construction sub-stage, an early warning reminder is issued, so that the staff can immediately notice the situation in the construction sub-stage, inspect the construction sub-stage, promptly discover the cause of the abnormal situation in the construction sub-stage, and rectify the subsequent construction sub-stages to avoid the same problem and cause additional economic losses.

[0064] The technical scheme in the above-mentioned embodiment of the present application has at least the following technical effects or advantages: the embodiment of the present application obtains material usage parameter data, normalizes the material usage parameter data, analyzes the normalized material usage parameter data to obtain a material usage rationality evaluation index, and analyzes the material usage data of the construction sub-stage according to the material usage rationality evaluation index, thereby realizing timely discovery of unreasonable use of construction materials based on the material usage data, and making rectifications, thereby reducing material cost expenditures and improving the efficiency of material management and control; the embodiment of the present application analyzes the cost of power transmission and transformation projects by combining material usage data, equipment arrangement data and construction plan data, thereby timely discovering abnormal situations in the construction sub-stages, and issuing early warning reminders, thereby realizing that the staff can quickly discover abnormal situations in the construction process and make rectifications, thereby avoiding the increase in the cost of power transmission and transformation projects.

[0065] It will be appreciated by those skilled in the art that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Furthermore, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0066] The present invention is described with reference to flowcharts and / or block diagrams of systems, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0067] These computer program instructions may also be stored in a computer readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer readable memory produce an article of manufacture including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0068] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 A step that specifies a function in one or more boxes.

[0069] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.

[0070] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. An intelligent cost control platform for power transmission and transformation projects, characterized in that: include: A division module is used to obtain the progress data of the power transmission and transformation project, divide the progress of the power transmission and transformation project, and obtain the construction stage data after division, wherein the construction stage data includes material use parameter data, equipment arrangement parameter data, and construction plan parameter data; The material analysis module is used to obtain material usage parameter data, perform data processing and analysis on the material usage parameter data, build a material usage rationality evaluation index model through machine learning, and analyze the material usage data of the construction sub-stage according to the material usage rationality evaluation index model; The material use rationality evaluation index model adopts the following formula: In the formula, Expressed as The material use rationality evaluation index for each construction sub-stage, , Expressed as the total number of construction sub-stages, Expressed as The construction sub-phase is The number of material types used during data collection, , It is expressed as the total number of data collection times, Expressed as The number of types of materials planned to be used in each construction sub-phase, Expressed as The first construction sub-phase The material in The actual weight of material consumed at the time of data collection, , Expressed as the total number of material types, Expressed as The first construction phase The planned material consumption weight of the material, Expressed as The construction sub-phase is The actual cost of materials during data collection, Expressed as The planned expenditure on materials for each construction sub-phase, It is expressed as the weight ratio of the number of material types used in the material use rationality assessment index. It is expressed as the weight ratio of the actual material consumption weight in the material use rationality evaluation index. It is expressed as the weight ratio of the actual material expenditure in the material use rationality evaluation index; Equipment analysis module: used to obtain equipment arrangement parameter data, process the equipment arrangement parameter data, build an equipment arrangement rationality evaluation index model, and analyze the rationality of equipment arrangement during the construction process through the equipment arrangement rationality evaluation index model; Among them, the calculation formula of the equipment arrangement rationality evaluation index model is: In the formula, Expressed as The equipment arrangement rationality evaluation index for each construction sub-stage, , Expressed as the total number of construction sub-stages, Expressed as The first construction phase Construction equipment in The actual power consumption of the construction equipment during the data collection. , It is expressed as the total number of data collection times, , Expressed as the total number of construction equipment, Expressed as The first construction phase Expected power consumption of construction equipment for each construction equipment, Expressed as The first construction phase Construction equipment in The construction equipment rental expenses during the data collection, Expressed as The first construction phase Expected rental expenses for construction equipment for each construction equipment, Expressed as The construction sub-phase is The actual number of leased equipment at the time of data collection, Expressed as Expected number of rental equipment for each construction sub-phase, It is expressed as the weight ratio of the actual power consumption of construction equipment in the evaluation index of the rationality of equipment arrangement. It is expressed as the weight ratio of construction equipment leasing expenditure in the equipment arrangement rationality evaluation index. It is expressed as the weight ratio of the actual number of leased equipment in the evaluation index of the rationality of equipment arrangement. Expressed as a natural constant; Comprehensive analysis module: used to obtain the output information fed back by the material analysis module and the equipment analysis module, and conduct a comprehensive analysis of the output information to determine the rationality of the cost of the power transmission and transformation project and issue an alarm signal.

2. The intelligent cost control platform for power transmission and transformation projects according to claim 1, characterized in that: Also includes construction analysis module, The construction analysis module is used to obtain and preprocess the construction plan parameter data, analyze the preprocessed construction plan parameter data to obtain a construction plan rationality evaluation index, and evaluate the rationality of the construction plan during the construction process through the construction plan rationality evaluation index.

3. The intelligent cost control platform for power transmission and transformation projects according to claim 2, characterized in that: The material uses parameter data for data processing and analysis specifically as follows: The interpolation method is used to process the missing data and abnormal data in the material usage parameter data, and the processed data is normalized.

4. The intelligent cost control platform for power transmission and transformation projects as claimed in claim 3, characterized in that: The interpolation method is used to process the missing data and abnormal data in the material usage parameter data, and the processed data is normalized, specifically including: Classify and sort the material usage parameter data, find missing data and abnormal data, and fill in the missing data through Lagrange interpolation method; And use the Z-score normalization formula to process the filled data to obtain standard data; Compare the standard data with the parameter preset data, and eliminate the data with the largest and smallest differences from the standard data.

5. The intelligent cost control platform for power transmission and transformation projects as claimed in claim 4, characterized in that: The specific construction method of the material use rationality evaluation index model is as follows: Divide the construction phase of the power transmission and transformation project into multiple construction sub-phases, obtain the number of construction sub-phases, and number the construction sub-phases; Conduct multiple data collections for the construction sub-stages, obtain the number of data collections, and number the number of data collections; Obtain the types of materials used in the construction sub-stages and number the material types; Obtain material usage parameter data and construct a material usage rationality assessment index model through machine learning.

6. The intelligent cost control platform for power transmission and transformation projects as claimed in claim 5, characterized in that: The specific construction method of the equipment arrangement rationality evaluation index model is: Divide the construction phase of the power transmission and transformation project into multiple construction sub-phases, obtain the number of construction sub-phases, Perform multiple data collection on the construction sub-stages to obtain the number of data collections, and obtain the number of construction equipment used in the construction sub-stages and equipment arrangement parameter data; The equipment arrangement rationality evaluation index model is constructed through machine learning and the calculation formula is given.

7. The intelligent cost control platform for power transmission and transformation projects according to claim 1, characterized in that: The material usage data of the construction sub-stage is analyzed according to the material usage rationality evaluation index model, specifically: The first material threshold and the second material threshold are obtained. When the material utilization rationality evaluation index is greater than the first material threshold and the material utilization rationality evaluation index is less than the second material threshold, the construction materials are used reasonably; otherwise, the construction materials are not used reasonably.

8. The intelligent cost control platform for power transmission and transformation projects as claimed in claim 7, characterized in that: The equipment arrangement rationality evaluation index model is used to analyze the rationality of equipment arrangement during the construction process, specifically: The first threshold value and the second threshold value of the equipment are obtained. When the equipment arrangement rationality evaluation index is greater than the first threshold value and the equipment arrangement rationality evaluation index is less than the second threshold value, it indicates that the equipment arrangement is reasonable, otherwise the equipment arrangement is unreasonable.

9. The intelligent cost control platform for power transmission and transformation projects as claimed in claim 2, characterized in that: The rationality of the construction plan during the construction process is evaluated by the construction plan rationality evaluation index, specifically: The first construction threshold and the second construction threshold are obtained. When the construction plan rationality evaluation index is greater than the first construction threshold and the construction plan rationality evaluation index is less than the second construction threshold, it indicates that the construction plan is reasonable, otherwise it indicates that the construction plan is unreasonable.

10. The intelligent cost control platform for power transmission and transformation projects according to claim 1, characterized in that: The method is used to obtain the output information fed back by the material analysis module and the equipment analysis module, and to conduct a comprehensive analysis on the output information, judge the rationality of the cost of the power transmission and transformation project and issue an alarm signal, specifically: Collect data on the output information fed back by the material analysis module and the equipment analysis module; Classify the collected data and draw curve images through machine learning; Analyze the curve image, output unreasonable cost data of the power transmission and transformation project, and issue early warning reminders.

Citation Information

Patent Citations

  • Investment estimation and cost analysis management and control method for power grid technical improvement and maintenance engineering

    CN111414583A

  • Engineering cost management and control system and method based on BIM technology

    CN116756832A

  • Engineering cost intelligent management system and method based on cloud computing and big data

    CN115392676A

  • Construction site material fine management system based on data analysis

    CN116757458A

  • Building curtain wall construction management system based on BIM technology

    CN117172414A