A method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles
Through real-time monitoring and automatic adjustment of the rotation speed of the rotary excavation equipment according to the gear temperature, the performance reduction and mechanical failure problems caused by gear heating in traditional square foundation pit excavation equipment are solved, the reliability and working life of the equipment are improved, and the cost is reduced. Energy consumption and maintenance costs.
Patent Information
- Application Number
- CN202410556429.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-07
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-05-07
AI Technical Summary
During the operation of traditional square foundation pit excavation equipment, due to the eccentric rotation of the driving shaft and the driven shaft that are not on the same axis, the gear pair loses a lot, the efficiency decreases, and the potential risk of mechanical failure occurs, especially in long-term, high-load working environments. There are problems with mechanical failures and high maintenance costs.
By monitoring the gear temperature in real time and using the temperature as a feedback signal, the speed of the rotary excavation equipment is automatically adjusted to optimize the working condition of the gear, reduce the mechanical failure rate caused by overheating, and improve the reliability and working life of the equipment.
It effectively reduces the mechanical failure rate and maintenance costs, improves the reliability and working life of the equipment, and at the same time reduces energy consumption and improves engineering efficiency.
Smart Images

Figure CN118327450B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for controlling the rotary excavation speed of electric pole square foundation pit excavation equipment, which is applicable to the field of electric power engineering construction. Background Art
[0002] During the operation of traditional square foundation pit excavation equipment, the main consideration is the rotation speed and torque balance point for different soil conditions. However, based on the Leroy triangle principle, the driving shaft and the driven shaft are not on the same axis. The eccentric rotation caused by the wheelbase makes the gear pair between the driving shaft and the driven shaft a relatively weak link. During the operation of the equipment, the gear pair has a relatively large loss.
[0003] In view of the above situation, and taking into full consideration the performance degradation and potential damage risk caused by gear heating during operation, it is of great significance to develop a new method for rotating drilling equipment speed control based on real-time monitoring and control of gear heating. This method uses the heat generated by the gear during operation as a feedback signal, and controls the maximum speed of the rotary drilling equipment by finely adjusting the working state of the gear, aiming to reduce the mechanical failure rate caused by overheating and improve the reliability and service life of the equipment.
[0004] By using sensors to monitor the temperature of the gears in real time and comparing it with the set safety temperature threshold, the system can automatically adjust the speed when an over-temperature is detected, thereby optimizing the performance of the equipment while ensuring the integrity of the mechanical structure and operational safety. This temperature-controlled speed-limiting method provides a new idea for the long-term stable operation and fault prevention of rotary drilling equipment, especially for long-term, high-load excavation environments. In addition, it also helps to reduce energy consumption and maintenance costs, thereby achieving a dual improvement in economic benefits and engineering efficiency. Summary of the invention
[0005] The purpose of the present invention is to solve the problem of performance degradation and potential damage risk caused by gear heating during the operation of the equipment, to improve the reliability and service life of the equipment, and to provide a speed control method for square foundation pit excavation equipment for power poles in a distribution network. The method is suitable for the field of power engineering construction, has the advantages of achieving dual improvements in economic benefits and engineering efficiency, and can be widely used in the field of power engineering construction.
[0006] The purpose of the present invention can be achieved by taking the following methods:
[0007] 1) Assess soil conditions;
[0008] The soil condition assessment includes the on-site personnel assessing the soil type based on the soil particle size, wetness, and degree of breakage after being held in a ball and then releasing it, and assessing the static friction coefficient μ between the soil and the drill bit of the excavation equipment in combination with the soil type and geotechnical test data to obtain the static friction coefficient μ;
[0009] 2) Evaluate excavation torque;
[0010] The excavation torque evaluation includes the on-site personnel evaluating the torque M (N) required for foundation pit excavation according to the static friction coefficient μ according to the evaluation calculation formula (1).
[0011] M=k1Fe+k2μQD (1)
[0012] Where, k1 is the torque correction coefficient of the driven shaft around the driving shaft, F is the side pressure of the drill bit (N), e is the horizontal distance between the driving shaft and the driven shaft axis (m), k2 is the friction torque correction coefficient of the spiral drill teeth, D is the side length of the Leroy triangle of the spiral drill teeth (m), and Q is the drilling pressure (N);
[0013] 3) Evaluate the maximum rotary speed;
[0014] The maximum rotation speed of rotary drilling is evaluated by the on-site personnel according to the torque M required for the foundation pit excavation, and the maximum rotation speed ω of the gear during the foundation pit rotary drilling process is evaluated. max (rad / s) is evaluated according to the evaluation formula (2),
[0015]
[0016] In the formula, η is the conversion efficiency of the excavation equipment, and P is the power of the excavation equipment (W);
[0017] 4) Monitor gear temperature;
[0018] The monitoring of the gear temperature includes using a temperature monitoring device to monitor the gear temperature in real time, and recording and feeding back the local maximum temperature of the gear every Δt time;
[0019] 5) Control the rotary drilling speed;
[0020] The controlling of the rotary drilling speed includes comparing the real-time monitoring data results of the local maximum temperature of the gear. When the local maximum temperature of the gear is less than T and the local maximum temperatures of the previous n gears are also less than T, the rotary drilling speed can be increased, and the rotary drilling speed after the increase is not greater than the maximum rotary drilling speed; when the local maximum temperature of the gear is less than T and the local maximum temperatures of the previous n gears are greater than or equal to T, the rotary drilling speed is maintained; when the local maximum temperature of the gear is greater than or equal to T, the rotary drilling speed must be reduced.
[0021] Furthermore, the foundation pit excavation equipment adopts a drill bit based on the Leroy triangle principle, and the drill bit includes a driving shaft directly connected to the drill rod of the rotary drilling rig, a driven shaft connected to the driving shaft through a pair of bevel gear pairs of the same specifications, and a spiral drill tooth directly connected to the driven shaft. The gear is a gear on the driving shaft in the pair of bevel gear pairs of the same specifications.
[0022] Furthermore, in the above 1), the geotechnical test data includes the values of the static friction coefficient between the drill bit material of the excavation equipment and the soil under different soil conditions.
[0023] Furthermore, in the above 4), the temperature monitoring device is a non-contact temperature measuring device, and the measurement accuracy of the measuring device is determined according to the measurement interval time.
[0024] Furthermore, in the above 5), the comparison result of the real-time monitoring data is fed back by the temperature monitoring device. After comparing the measured local maximum temperature of the gear with the local maximum temperature of the gear for the previous n times, the temperature monitoring device feeds back to the on-site personnel, who then comprehensively decide whether to increase, maintain or reduce the speed of the equipment.
[0025] The beneficial effects of the present invention are:
[0026] The beneficial effects of the present invention are: solving the problem of performance degradation and potential damage risk caused by gear heating during equipment operation, improving the reliability and service life of the equipment; providing a method for controlling the rotary drilling speed of square foundation pit excavation equipment for electric poles, which has the advantages of achieving dual improvements in economic benefits and engineering efficiency, and can be widely used in the field of power engineering construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 : Flow chart of a method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles of the present invention.
[0028] Figure 2 : The drill bit structure of an excavation equipment for a square foundation pit of an electric pole and a method for controlling the rotary excavation speed of the excavation equipment. In the figure: 1, driving shaft; 2, gear 1; 3, gear 2; 4, driven shaft; 5, drill teeth.
[0029] Figure 3 : A top view of the drill teeth of a method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles according to the present invention. DETAILED DESCRIPTION
[0030] The specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings; it should be understood that the specific embodiments given here are only used to illustrate and explain the present invention and cannot be used to limit the present invention.
[0031] The following is a specific embodiment of a method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles.
[0032] like Figure 1 The figure shows a flow chart of a method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles according to the present invention.
[0033] This embodiment relies on the square foundation pit excavation process of a certain section of a 10kV transmission line project of a certain power grid, and the specific implementation process is as follows:
[0034] 1) Assess soil conditions;
[0035] On-site personnel assessed the soil type as silty clay based on the particle size, wetness, and degree of breakage after being held in a ball and then released. In geotechnical test data, the static friction coefficient between silty clay and the drill bit of the excavation equipment is μ = 0.7;
[0036] 2) Evaluate excavation torque;
[0037] The model was built to calculate the torque required for gear rotation under different conditions of bit side pressure, horizontal distance between the driving shaft and the driven shaft, side length of the spiral drill tooth Leroy triangle, and drilling pressure. Based on the calculation results, the multivariate regression analysis method was used to obtain the torque correction coefficient k1 of the driven shaft around the driving shaft, which was 1.12, and the torque correction coefficient k2 of the spiral drill tooth friction resistance was 2.15.
[0038] In this embodiment, the drill side pressure F = 12 kN, the horizontal distance between the driving shaft and the driven shaft axis e = 0.4 m, the side length of the spiral drill tooth Leroy triangle D = 0.5 m, the drilling pressure Q = 30 kN, combined with the static friction coefficient μ, the torque M required for foundation pit excavation is evaluated according to the evaluation calculation formula (1):
[0039] M=k1Fe+k2μQD (1)
[0040] The torque required for foundation pit excavation is M=27.95kN;
[0041] 3) Evaluate the maximum rotary speed;
[0042] The pair of gears between the driving shaft and the driven shaft have the same specifications, and the force form and speed are equal and opposite. Therefore, it is appropriate to take gear 1 on the driving shaft as the reference target, and the subsequent gears are all referred to as gear 1. The power of the excavation equipment P = 120kW. Under the condition of drilling pressure of 15kN, the conversion efficiency of the excavation equipment η = 0.75. Combined with the torque M required for foundation pit excavation, the maximum speed ω of the gear during the foundation pit rotary excavation process is calculated. max (rad / s) is evaluated according to the evaluation formula (2),
[0043]
[0044] The maximum speed of the gear during the foundation pit rotary excavation process ω max =3.22rad / s. The speed in the engineering field is generally expressed in revolutions per minute (r / min). Therefore, the maximum speed of the gear during the foundation pit excavation process is ω max =31r / min;
[0045] 4) Monitor gear temperature;
[0046] The monitoring of the gear temperature includes using a temperature monitoring device to monitor the gear temperature in real time, recording and feeding back the local maximum temperature of the gear every Δt=10s, and using an infrared thermometer with an accuracy of 1°C;
[0047] 5) Control the rotary drilling speed;
[0048] Gears are made of steel. Generally, when the temperature of steel reaches 200°C, the various mechanical properties of the steel begin to change. Therefore, the local maximum temperature limit of the gear is T = 200°C.
[0049] With reference to the real-time monitoring data results of the local maximum temperature of the gear and the degree of proximity of the local maximum temperature of the gear to 200°C, the rotary drilling speed is controlled according to the following rule: when the local maximum temperature of the gear is less than 200°C and the previous two local maximum temperatures of the gear are also less than 200°C, the rotary drilling speed can be increased, and the rotary drilling speed after increase is not greater than the maximum rotary drilling speed; when the local maximum temperature of the gear is less than 200°C and the previous two local maximum temperatures of the gear are greater than or equal to 200°C, the rotary drilling speed is maintained; when the local maximum temperature of the gear is greater than or equal to 200°C, the rotary drilling speed must be reduced.
[0050] The actual control method of rotary drilling speed in the 150-200s stage is shown in the following table:
[0051] Table 1 Actual control method of rotary drilling speed
[0052] t(s) 150 160 170 180 190 200 Maximum local temperature of gear 180℃ 196℃ 201℃ 195℃ 196℃ 198℃ Control method Increase the speed Increase the speed Reduce the speed Maintain speed Maintain speed Maintain speed Current speed (r / min) 24 26 28 26 26 26
[0053] In the above embodiments, the present invention discloses a method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles, including evaluating soil conditions, evaluating excavation torque, evaluating the maximum rotary excavation speed, monitoring gear temperature and controlling the rotary excavation speed; the method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles proposed in the present invention solves the problems of performance degradation and potential damage risks caused by gear heating during equipment operation, has the advantages of achieving dual improvements in economic benefits and engineering efficiency, and can be widely used in the field of power engineering construction.
[0054] The above description is a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles, characterized in that: The following steps are involved: 1) Assess soil conditions; The soil condition assessment includes the on-site personnel assessing the soil type based on the soil particle size, wetness, and degree of breakage after being held in a ball and then releasing it, and assessing the static friction coefficient μ between the soil and the drill bit of the excavation equipment in combination with the soil type and geotechnical test data to obtain the static friction coefficient μ; 2) Evaluate excavation torque; The excavation torque evaluation includes the on-site personnel evaluating the torque M (N·m) required for foundation pit excavation according to the static friction coefficient μ according to the evaluation calculation formula (1). M=k1Fe+k2μQD (1) Where, k1 is the torque correction coefficient of the driven shaft around the driving shaft, F is the side pressure of the drill bit (N), e is the horizontal distance between the driving shaft and the driven shaft axis (m), k2 is the friction torque correction coefficient of the drill tooth, D is the side length of the drill tooth Leroy triangle (m), and Q is the drilling pressure (N); 3) Evaluate the maximum rotary speed; The evaluation of the maximum rotary excavation speed includes the on-site personnel evaluating the maximum speed ωmax (rad / s) of the gear during the rotary excavation of the foundation pit according to the torque M required for the foundation pit excavation according to the evaluation calculation formula (2), and the gear is the first gear at the lower part of the driving shaft; In the formula, η is the conversion efficiency of the excavation equipment, and P is the power of the excavation equipment (W); 4) Monitor gear temperature; The monitoring of the gear temperature includes using a temperature monitoring device to monitor the gear temperature in real time, and recording and feeding back the local maximum temperature of the gear every Δt time; 5) Control the rotary drilling speed; The controlling of the rotary drilling speed includes comparing the real-time monitoring data results of the local maximum temperature of the gear, and when the local maximum temperature of the gear is less than T and the local maximum temperatures of the previous n gears are also less than T, increasing the rotary drilling speed, and the rotary drilling speed after the increase is not greater than the maximum rotary drilling speed; when the local maximum temperature of the gear is less than T and the local maximum temperatures of the previous n gears are greater than or equal to T, maintaining the rotary drilling speed; when the local maximum temperature of the gear is greater than or equal to T, the rotary drilling speed must be reduced.
2. The method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles according to claim 1 is characterized in that: The foundation pit excavation equipment adopts a drill bit based on the Lerowert triangle principle. The drill bit includes a driving shaft directly connected to the drill rod of the rotary drilling rig, a driven shaft connected to the driving shaft through a pair of bevel gear pairs of the same specifications, and drill teeth directly connected to the driven shaft.
3. The method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles according to claim 1, characterized in that: In 1), the geotechnical test data include the static friction coefficient values between the drill bit material of the excavation equipment and the soil under different soil conditions.
4. The method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles according to claim 1, characterized in that: In the above 4), the temperature monitoring device is a non-contact temperature measuring device, and the measurement accuracy of the measuring device is determined according to the measurement interval time.
5. The method for controlling the rotary excavation speed of a square foundation pit excavation equipment for electric poles according to claim 1, characterized in that: In 5), the comparison result of the real-time monitoring data is fed back by the temperature monitoring device. The temperature monitoring device compares the measured local maximum temperature of the gear with the local maximum temperature of the previous n times, and then feeds back to the on-site personnel, who then comprehensively decide whether to increase, maintain or reduce the speed of the equipment.
Citation Information
Patent Citations
Device for the cutting and mixing of soils
CN102037190A
Cast-in-situ tubular pile rotary drilling rig capable of forming annular hole and piling method
CN102182404A