A rapid construction method for large-diameter pile foundations in deep-water karst areas

By adopting the design method of linkage components and spiral blades in deep water karst areas, the problems of low pile foundation construction efficiency and poor stability in traditional construction methods have been solved, and the rapid and stable construction of large-diameter pile foundations has been achieved, ensuring the load-bearing capacity of pile foundations. Capacity and service life.

CN118361187BActive Publication Date: 2024-10-22THE 2ND ENG CO LTD MBEC +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410377921.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-10-22
Estimated Expiration
2044-03-29

AI Technical Summary

Technical Problem

When constructing large-diameter pile foundations in deep-water karst areas, traditional construction methods have problems such as the risk of hole collapse, low slag discharge efficiency, poor drilling stability and long construction period, resulting in low construction efficiency and high costs.

Method used

The linkage component is used to make the first drill bit body and the second drill bit body rotate in the same direction synchronously, combined with the spiral blade design, to achieve rapid removal of broken soil and stable support of the pile foundation, ensuring the straightness and verticality of the drilling, and through the positioning component and tension drives improve drilling synchronization and stability.

Benefits of technology

It achieves rapid and stable construction of large-diameter pile foundations, improves soil drainage efficiency, reduces the risk of hole wall collapse, ensures the load-bearing capacity and service life of pile foundations, and improves construction efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118361187B_ABST
    Figure CN118361187B_ABST
Patent Text Reader

Abstract

The invention relates to the field of pile foundation construction, and specifically to a rapid construction method for a large-diameter pile foundation in a deep-water karst area. A rotary drilling bit assembly consists of a first drill bit body, a second drill bit body and a rotating connection piece. The first drill bit body is fixedly connected to the lower end of a steel casing, and the second drill bit body is fixedly connected to the rotating connection piece. The first drill bit body is a tubular structure with a cutting edge at the end, and the second drill bit body is arranged in the first drill bit body. A slide rail and a lifting slider slidably arranged on the slide rail are provided on the rotary drilling rig, and the rotating connection piece is rotatably connected to the lifting slider. A linkage assembly is provided between the first drill bit body and the second drill bit body. The invention realizes that the first drill bit body and the second drill bit body can rotate synchronously and in the same direction through the linkage assembly, which not only helps to more effectively break the formation, but also ensures the straightness and verticality of the borehole, and solves the problem of drilling deviation caused by uneven force on a single drill bit.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of pile foundation construction, and in particular to a rapid construction method for a large-diameter pile foundation in a deep-water karst area. Background Art

[0002] At present, there are often many challenges in the construction of large-diameter pile foundations in deep-water karst areas. Traditional construction methods mainly use single rotary drilling rigs or impact drilling rigs. When facing complex karst geology, this type of drilling rig generally has the following problems: 1. Risk of hole collapse: The stratum structure in the karst area is complex, with many caves and fissures. Hole collapse is prone to occur during the drilling process, which seriously affects the construction progress and safety; 2. Low slag discharge efficiency: After the traditional drill bit breaks the stratum, the discharge of the slag depends on the mud circulation system, but in deep-water environments and karst geology, this process may be greatly affected, resulting in low slag discharge efficiency; 3. Poor drilling stability: There is a lack of sufficient hole wall support facilities, especially when encountering caves or weak interlayers, the stability of the hole wall is difficult to guarantee; 4. Long construction period: Limited by geological conditions and construction technology, existing methods often cannot achieve fast and efficient drilling construction, resulting in a long construction period and high cost.

[0003] The currently disclosed Chinese patent CN216197834U is a lifting and rotary drilling full-casing and full-rotation multifunctional integrated drilling rig, including a rotary drilling machine, a mast is installed on the front surface of the rotary drilling machine, a track frame is welded on the front surface of the mast, a pressurized oil cylinder is installed on the front surface of the track frame, a guide rail connecting plate is provided at the driving end of the pressurized oil cylinder, the cavity parts of two groups of the guide rail connecting plates are fixed to the driving end of the pressurized oil cylinder, one side of the two groups of the guide rail connecting plates is respectively installed with a connecting seat two, and the outer walls of the two groups of the connecting seat two are respectively provided with a rotary drilling power head and a full-rotation drive device.

[0004] According to the above-mentioned patent, the positioning shaft on the casing connecting flange is removed to separate the casing and the output flange built into the full-rotation drive device, thereby controlling the operation of the rotary drilling head output sleeve on the rotary drilling head to drive the rotating seat to rotate, wherein the rotating seat is applied to the inner cavity of the rotating sleeve, and the rotary drilling cutter sand scoop installed at the bottom end thereof will remove the soil in the casing. However, the casing of this patent is disassembled and assembled by the positioning shaft, and the soil cannot be removed synchronously during the rotary drilling process, resulting in low construction efficiency. Therefore, there is a need for a construction method that can achieve higher construction efficiency and stability. Summary of the invention

[0005] In view of the problems existing in the prior art, a rapid construction method for large-diameter pile foundations in deep-water karst areas is provided. The present invention realizes that a first drill bit body and a second drill bit body can rotate synchronously and in the same direction through a linkage component, which not only helps to break the stratum more effectively, but also ensures the straightness and verticality of the borehole, solves the problem of drilling deviation caused by uneven force on a single drill bit in the prior art, and is conducive to the rapid removal of the broken soft soil in the steel casing. The design of the spiral blades greatly improves the efficiency of soil discharge, reduces the problem of soil clogging during the drilling process, and ensures the final bearing capacity and service life of the pile foundation.

[0006] In order to solve the problems of the prior art, the present invention provides a rapid construction method for a large-diameter pile foundation in a deep-water karst area, comprising the following steps:

[0007] S1. Construction preparation: Set up a temporary or permanent water construction platform near the predetermined pile position, and transport construction equipment such as rotary drilling rigs to the water construction platform;

[0008] S2. Drilling construction: Design large-diameter pile foundations and rotary drilling bit assemblies suitable for the characteristics of deep-water karst areas, and start the rotary drilling bit assembly through the rotary drilling rig on the water construction platform, so that the steel casing forming the large-diameter pile foundation sinks to the predetermined position;

[0009] S3, discharging soil: during the process of the rotary drilling bit assembly rotating the soil, the rotary drilling bit assembly synchronously pushes the soil upward until the soil is discharged;

[0010] S4. Pile foundation pouring: After the drilling reaches the designed depth, check the hole diameter, hole depth and hole wall quality, leave the steel casing in the hole, remove the rotary drill assembly, then install the steel cage, and pour concrete into the steel casing continuously and quickly to form a solid pile foundation.

[0011] In the drilling construction step of S2, the steel casing is used as the supporting structure of the inner wall of the hole, and the rotary drilling bit assembly is used as the driving source for the rotary drilling movement of the steel casing. The rotary drilling bit assembly consists of a first drill bit body, a second drill bit body and a rotating connection piece. The first drill bit body is fixedly connected to the lower end of the steel casing, and the second drill bit body is fixedly connected to the rotating connection piece. The first drill bit body is a cylindrical structure with a cutting edge at the end, and the second drill bit body is arranged in the first drill bit body. The rotary drilling rig is provided with a slide rail and a lifting slider slidably arranged on the slide rail, the rotating connection piece is rotatably connected to the lifting slider, and a linkage assembly for keeping the first drill bit body and the second drill bit body rotating synchronously and in the same direction is provided between the first drill bit body and the second drill bit body.

[0012] Preferably, in the soil discharge step of S3, the rotary drilling bit assembly is also provided with a rotating inner tube fixedly connected between the rotating connecting piece and the second drill bit body, a fixed inner tube fixedly connected to the lifting slider is coaxially provided in the steel casing, the outer diameter of the fixed inner tube is equal to the inner diameter of the steel casing, the fixed inner tube is coaxial with the rotating inner tube, a spiral blade is provided between the fixed inner tube and the rotating inner tube, the spiral blade is fixedly connected to the rotating inner tube, and the rotating inner tube can rotate around its axial direction relative to the fixed inner tube.

[0013] Preferably, the upper half of the fixed inner tube is provided with a discharge port.

[0014] Preferably, a bearing is provided between the upper end of the steel casing and the fixed inner tube, the inner ring of the bearing is fixedly connected to the fixed inner tube, and a positioning assembly is provided between the outer ring of the bearing and the steel casing.

[0015] Preferably, the linkage assembly is provided with a first shift plate and a second shift plate, the first shift plate is fixedly connected to the lower end of the rotating inner tube, and the second shift plate is fixedly connected to the inner ring of the first drill bit body. When the rotating inner tube rotates, the first shift plate contacts the second shift plate, thereby driving the steel casing to rotate synchronously.

[0016] Preferably, the positioning assembly is provided with a positioning shaft and a stretching drive member. There are multiple positioning shafts, which are evenly distributed around the circumferential direction of the steel casing, and the axial direction of the positioning shaft is perpendicular to the axial direction of the steel casing. The outer ring of the bearing is fixedly provided with a ring extending downward and sleeved on the steel casing, and a fixed pin is fixedly connected between the ring and the outer ring of the bearing. The end of the positioning shaft passes through the fixed pin and the ring in turn, and the fixed pin and the ring are provided with guide openings for the positioning shaft to pass through. A positioning opening for the positioning shaft to be inserted therein is provided through the steel casing at the position corresponding to the positioning shaft. The stretching drive member is arranged on the outer ring of the bearing, and all the positioning shafts are connected to the stretching drive member.

[0017] Preferably, a spring sleeved on the positioning shaft is fixedly connected between the positioning shaft and the fixed pin shaft, and the stretching drive member is provided with a fixed electromagnet and a movable electromagnet, both of which are annular structures, the fixed electromagnet is fixedly sleeved on the outer ring of the bearing, and the movable electromagnet is movably sleeved on the outer ring of the bearing, the movable electromagnet can move along the axial direction of the bearing, and a connecting rod is hingedly provided between each positioning shaft and the movable electromagnet.

[0018] Preferably, the second drill bit body is a hollow structure with a hole inside, the rotating inner tube has a flow channel that runs through the upper and lower parts and is connected to the second drill bit body, and the rotating connecting piece has a suction channel that runs through the upper and lower parts and is connected to the flow channel.

[0019] Preferably, the upper end of the first drill bit body has an annular step surrounding the inner wall of the steel casing, and the lower end of the fixed inner tube has a positioning clamping ring extending downward and surrounding the inner wall of the annular step.

[0020] Preferably, the upper end of the steel casing has a docking port which maintains a coaxial connection state with the next steel casing.

[0021] Compared with the prior art, the present invention has the following beneficial effects:

[0022] 1. The present invention realizes synchronous and unidirectional rotation of the first drill bit body and the second drill bit body through a linkage assembly, which not only helps to more effectively break the stratum, but also ensures the straightness and verticality of the borehole, solves the problem of drilling deviation caused by uneven force on a single drill bit in the prior art, and is conducive to quickly removing the broken soft soil in the steel casing. The steel casing supports the hole wall during the drilling process, thereby reducing the safety hazard caused by the instability of the hole wall during construction in karst areas, realizing stable and rapid construction of large-diameter pile foundations, and ensuring the final bearing capacity and service life of the pile foundation.

[0023] 2. The present invention greatly improves the efficiency of soil discharge through the design of spiral blades, reduces the problem of soil clogging during the drilling process, maintains the unobstructed flow of the borehole, and thus speeds up the drilling construction speed. In addition, since the spiral blades can continuously push the broken soil upward, the drilling construction process can be carried out uninterruptedly, thereby effectively improving the construction continuity and stability, achieving the stability of the borehole, and helping to quickly discharge the soil after the broken strata, reducing the internal stress on the hole wall, reducing the risk of hole wall collapse, and ensuring the quality of the borehole.

[0024] 3. The present invention connects the bearing and the steel casing through a positioning assembly, so that the steel casing can rotate relative to the fixed inner tube. Under the action of the linkage assembly, the synchronous and unidirectional rotation of the rotating inner tube and the steel casing is guaranteed, and the synchronous drilling movement of the first drill bit body and the second drill bit body is realized, thereby improving the soil discharge efficiency and drilling quality during the drilling construction process. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 A three-dimensional structural diagram of a rapid construction method for large-diameter pile foundations in deep-water karst areas Figure 1 .

[0026] Figure 2 A three-dimensional structural diagram of a rapid construction method for large-diameter pile foundations in deep-water karst areas Figure 2 .

[0027] Figure 3 It is a partial three-dimensional structural cross-sectional view of a rapid construction method for large-diameter pile foundations in deep-water karst areas.

[0028] Figure 4 It is a plan cross-sectional view of a rapid construction method for large diameter pile foundations in deepwater karst areas.

[0029] Figure 5 yes Figure 4 An enlarged schematic diagram of point A.

[0030] Figure 6 yes Figure 4 A cross-sectional view of the three-dimensional structure at BB.

[0031] Figure 7 yes Figure 6 Enlarged schematic diagram of point C.

[0032] Figure 8 yes Figure 3 Enlarged schematic diagram of point D.

[0033] Fig. 9 yes Figure 4 Plane cross-sectional view at EE.

[0034] Fig.10 yes Figure 4 Cross-sectional view of the three-dimensional structure at EE.

[0035] The numbers in the figure are: 1. water construction platform; 2. rotary drilling drill bit assembly; 21. first drill bit body; 211. fixed inner tube; 2111. discharge port; 212. annular step; 2121. positioning clamp ring; 22. second drill bit body; 221. rotating inner tube; 2211. spiral blade; 222. flow channel; 23. rotating connector; 231. suction channel; 3. steel casing; 31. bearing; 311. sleeve; 312. fixed pin shaft; 32. ramp; 33. docking port; 4. slide rail; 41. lifting slider; 411. ring sleeve; 412. block; 4121. bolt; 5. linkage assembly; 51. first dial plate; 52. second dial plate; 6. positioning assembly; 61. positioning shaft; 611. spring; 62. stretching drive; 621. fixed electromagnet; 622. movable electromagnet; 623. connecting rod. DETAILED DESCRIPTION

[0036] In order to further understand the features, technical means, specific objectives and functions of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0037] A rapid construction method for large-diameter pile foundations in deep-water karst areas comprises the following steps:

[0038] S1. Construction preparation: a temporary or permanent water construction platform 1 is set up near the predetermined pile position, and construction equipment such as rotary drilling rigs are transported to the water construction platform 1;

[0039] S2, drilling construction: design a large-diameter pile foundation and a rotary drilling bit assembly 2 suitable for the characteristics of deep-water karst areas, start the rotary drilling bit assembly 2 through the rotary drilling rig on the water construction platform 1, so that the steel casing 3 forming the large-diameter pile foundation sinks to a predetermined position;

[0040] S3, discharging soil: during the process of rotary drilling of soil by the rotary drilling bit assembly 2, the rotary drilling bit assembly 2 synchronously pushes the soil upward until the soil is discharged;

[0041] S4. Pile foundation pouring: After the drilling reaches the designed depth, check the hole diameter, hole depth and hole wall quality, leave the steel casing 3 in the hole, remove the rotary drill assembly 2, then install the steel cage, and pour concrete into the steel casing 3 continuously and quickly to form a solid pile foundation.

[0042] See also Figure 1-Figure 4 As shown, in the drilling construction step of S2, the steel casing 3 is used as the supporting structure of the inner wall of the hole, and the rotary drilling bit assembly 2 is used as the driving source for the rotary drilling movement of the steel casing 3. The rotary drilling bit assembly 2 is composed of a first drill bit body 21, a second drill bit body 22 and a rotating connection member 23. The first drill bit body 21 is fixedly connected to the lower end of the steel casing 3, and the second drill bit body 22 is fixedly connected to the rotating connection member 23. The first drill bit body 21 is a cylindrical structure with a cutting edge at the end, and the second drill bit body 22 is arranged in the first drill bit body 21. A slide rail 4 and a lifting slider 41 slidably arranged on the slide rail 4 are provided on the rotary drilling rig, and the rotating connection member 23 is rotatably connected to the lifting slider 41. A linkage assembly 5 for keeping the first drill bit body 21 and the second drill bit body 22 rotating synchronously and in the same direction is provided between the first drill bit body 21 and the second drill bit body 22.

[0043] A guide port for guiding the sinking direction of the steel casing 3 is opened on the water construction platform 1, and the steel casing 3 with the first drill bit body 21 is accurately placed to ensure that it sinks vertically along the guide port. The steel casing 3 is slowly rotated and released by the lifting device of the rotary drilling rig, so that it gradually drills into a predetermined depth under the movement of the lifting slider 41 and the action of the rotating force. The rotating connector 23 is driven by the rotating device to drive the second drill bit body 22 to rotate in the first drill bit body 21. The second drill bit body 22 is connected to the inside of the first drill bit body 21 through the linkage assembly 5 to ensure that the two can rotate synchronously in the same direction. The cutting edge of the first drill bit body 21 contacts and breaks the stratum, and at the same time drives the entire steel casing 3 to rotate together, thereby forming a borehole and digging downward, and the second drill bit body 22 further breaks the soil and rock stratum inside the steel casing 3, which is conducive to discharging the soil, and the sinking speed and rotation force of the rotary drilling bit assembly 2 are monitored and adjusted in real time to ensure that the drilling depth and aperture meet the specified standards. At the same time, the steel casing 3 plays a role in stabilizing the hole wall during the sinking process to prevent the hole from collapsing.

[0044] See also Figure 1-Figure 8 As shown, in the soil discharge step of S3, the rotary drilling bit assembly 2 is also provided with a rotating inner tube 221 fixedly connected between the rotating connecting piece 23 and the second drill bit body 22, and a fixed inner tube 211 fixedly connected to the lifting slider 41 is coaxially provided in the steel casing 3, the outer diameter of the fixed inner tube 211 is equal to the inner diameter of the steel casing 3, the fixed inner tube 211 is coaxial with the rotating inner tube 221, a spiral blade 2211 is provided between the fixed inner tube 211 and the rotating inner tube 221, the spiral blade 2211 is fixedly connected to the rotating inner tube 221, and the rotating inner tube 221 can rotate around its axial direction relative to the fixed inner tube 211.

[0045] A ring sleeve 411 is fixedly provided on the lifting slide block 41, and a block 412 is extended outward from the edges of the ring sleeve 411. A slot corresponding to the block 412 is provided on the upper end of the fixed inner tube 211. The block 412 and the fixed inner tube 211 are fixedly connected by bolts 4121, which ensures the stability of the fixed inner tube 211 and ensures that when the fixed inner tube 211 is stationary, the rotating movement of the rotating inner tube 221 can push the soil upward along the inner wall of the fixed inner tube 211 through the spiral blades 2211. The specific pushing process is as follows: The first drill bit body 21 and the second drill bit body 22 rotate synchronously under the action of the linkage assembly 5 to break the stratum. The broken soil is gradually pushed by the spiral blades 2211 on the rotating inner tube 221 coaxially arranged in the second drill bit body 22. The rotating inner tube 221 rotates around its axis relative to the fixed inner tube 211 under the drive of the rotating connecting piece 23. Since the spiral blades 2211 are arranged between the fixed inner tube 211 and the rotating inner tube 221, the soil moves toward the top of the steel casing 3 along the spiral blades 2211 under the squeezing and pushing action of the spiral blades 2211.

[0046] See also Figure 1-Figure 4 As shown, the upper half of the fixed inner tube 211 is provided with a discharge port 2111 .

[0047] As the spiral blades 2211 continuously push the crushed soil upward, the soil reaches the discharge port 2111 opened at the upper half of the fixed inner tube 211 , and is finally discharged from the discharge port 2111 .

[0048] See also Figure 3-Figure 5 As shown, a bearing 31 is provided between the upper end of the steel casing 3 and the fixed inner tube 211 , the inner ring of the bearing 31 is fixedly connected to the fixed inner tube 211 , and a positioning assembly 6 is provided between the outer ring of the bearing 31 and the steel casing 3 .

[0049] The setting of the bearing 31 enables the rotating inner tube 221 to drive the fixed inner tube 211 to rotate synchronously when rotating and under the action of the linkage assembly 5, while the fixed inner tube 211 remains stationary, which not only ensures that the spiral blade 2211 can smoothly push the soil upward, but also ensures that the first drill bit body 21 and the second drill bit body 22 drill the soil synchronously, thereby improving the drilling efficiency. When the bearing 31 is connected to the steel casing 3, the steel casing 3 is firstly sleeved on the fixed inner tube 211, and the steel casing The end of 3 contacts the lower end of the bearing 31, and then the outer ring of the bearing 31 is fixed to the steel casing 3 by the positioning assembly 6, thereby completing the rotational connection between the steel casing 3 and the fixed inner tube 211, ensuring that the first drill bit body 21 follows the second drill bit body 22 to perform synchronous rotational movement. After the steel casing 3 is drilled into place, the rotary drilling drill bit assembly 2 needs to be pulled out of the steel casing 3 as a whole. At this time, the fixed connection state with the steel casing 3 is released by the positioning assembly 6, and then the inside of the steel casing 3 is cast.

[0050] See also Figure 3 , Fig. 9 and Fig.10 As shown, the linkage assembly 5 is provided with a first shift plate 51 and a second shift plate 52. The first shift plate 51 is fixedly connected to the lower end of the rotating inner tube 221, and the second shift plate 52 is fixedly connected to the inner ring of the first drill bit body 21. When the rotating inner tube 221 rotates, the first shift plate 51 contacts the second shift plate 52, thereby driving the steel casing 3 to rotate synchronously.

[0051] When the rotating inner tube 221 rotates, the first dial plate 51 rotates accordingly, and the second dial plate 52 is on the same horizontal plane as the first dial plate 51, so that the first dial plate 51 contacts the second dial plate 52, and the contact force is transmitted to the first drill bit body 21 through the second dial plate 52, thereby realizing the synchronous rotation of the first drill bit body 21 and the second drill bit body 22, that is, the synchronous rotation of the steel casing 3 and the rotating inner tube 221, so that during the drilling process, the first drill bit body 21 and the second drill bit body 22 can work together to improve the efficiency of crushing and drilling the formation, enhance the stability and continuity of the drilling, prevent the problem of drilling deviation or hole wall collapse caused by the rotation of a single drill bit, play a good protective role on the drilling structure, ensure the straightness and verticality of the drilling, and improve the overall quality of the pile foundation.

[0052] See also Figure 3-Figure 5As shown, the positioning assembly 6 is provided with a positioning shaft 61 and a stretching drive member 62. There are multiple positioning shafts 61, and the multiple positioning shafts 61 are evenly distributed around the circumferential direction of the steel casing 3. The axial direction of the positioning shaft 61 is perpendicular to the axial direction of the steel casing 3. The outer ring of the bearing 31 is fixedly provided with a ring 311 extending downward and sleeved on the steel casing 3. A fixing pin 312 is fixedly connected between the ring 311 and the outer ring of the bearing 31. The end of the positioning shaft 61 passes through the fixing pin 312 and the ring 311 in sequence. The fixing pin 312 and the ring 311 are provided with guide openings for the positioning shaft 61 to pass through. A positioning opening for the positioning shaft 61 to be inserted therein is provided through the steel casing 3 at the position corresponding to the positioning shaft 61. The stretching drive member 62 is arranged on the outer ring of the bearing 31, and all the positioning shafts 61 are connected to the stretching drive member 62.

[0053] Insert the positioning shafts 61 one by one into the positioning holes pre-opened in the steel casing 3, ensuring that the ends of the positioning shafts 61 are accurately inserted into the positioning holes, thereby realizing the radial and axial dual positioning between the steel casing 3 and the outer ring of the bearing 31. By manipulating the stretching drive 62, the position of the positioning shaft 61 in the guide hole can be accurately controlled to further ensure the positioning accuracy. The connection state between the bearing 31 and the steel casing 3 is realized through the positioning shaft 61. The positioning assembly 6 increases the stability of the structure through the uniform distribution of multiple positioning shafts 61, reduces the risk of vibration and deviation during the drilling process, and effectively improves the construction quality and efficiency. In addition, due to the use of the stretching drive 62, there is no need for manual operation when operating the positioning shaft 61, thereby improving safety.

[0054] See also Figure 3-Figure 5 As shown, a spring 611 sleeved on the positioning shaft 61 is fixedly connected between the positioning shaft 61 and the fixed pin shaft 312, and the stretching drive member 62 is provided with a fixed electromagnet 621 and a movable electromagnet 622. The fixed electromagnet 621 and the movable electromagnet 622 are both annular structures. The fixed electromagnet 621 is fixedly sleeved on the outer ring of the bearing 31, and the movable electromagnet 622 is movably sleeved on the outer ring of the bearing 31. The movable electromagnet 622 can move along the axial direction of the bearing 31, and a connecting rod 623 is hingedly provided between each positioning shaft 61 and the movable electromagnet 622.

[0055] The outer ring of the bearing 31 has a slope 32 that shields the top of the bearing 31, which can prevent soil from entering the bearing 31. The positioning shaft 61 is connected to the fixed pin shaft 312 through a spring 611. The spring 611 provides an initial positioning force for the positioning shaft 61 under normal conditions to ensure that the positioning shaft 61 can maintain the positioning effect on the steel casing 3 even in an uncontrolled state. When the position of the positioning shaft 61 needs to be precisely adjusted, the fixed electromagnet 621 and the movable electromagnet 622 in the stretching drive 62 work. When power is turned on, an attractive force is generated, and the movable electromagnet 622 drives the positioning shaft 61 to move along the guide port through the connecting rod 623. At this time, the positioning shaft 61 is close to the steel casing 3, and when a repulsive force is generated after power is turned on, the positioning shaft 61 is away from the steel casing 3.

[0056] See also Figure 3 and Figure 4 As shown, the second drill bit body 22 is a hollow structure with a hole inside, the rotating inner tube 221 has a flow channel 222 that runs through the upper and lower parts and is connected to the second drill bit body 22, and the rotating connecting member 23 has a suction channel 231 that runs through the upper and lower parts and is connected to the flow channel 222.

[0057] The second drill bit body 22 has a hole inside and a hollow structure designed so that the mud generated during the drilling process can be discharged through the inside of the second drill bit body 22, and the mud is discharged along the flow channel 222. The suction channel 231 provided on the rotating connecting piece 23 is connected to an external suction device or a mud circulation system. The mud in the drilling process is quickly extracted by the suction force to keep the borehole unobstructed and the drilling process continuous, thereby achieving efficient discharge of the mud during the drilling process and improving construction efficiency.

[0058] See also Figure 4 , Figure 6 and Figure 8 As shown, the upper end of the first drill bit body 21 has an annular step 212 surrounding the inner wall of the steel casing 3 , and the lower end of the fixed inner tube 211 has a positioning clamping ring 2121 extending downward and surrounding the inner wall of the annular step 212 .

[0059] The annular step 212 at the upper end of the first drill bit body 21 and the positioning clamping ring 2121 at the lower end of the fixed inner tube 211 engage with each other to form a stable connection structure, ensuring the concentricity and verticality between the fixed inner tube 211 and the first drill bit body 21, and further enhancing the stability during drilling.

[0060] See also Figure 5 As shown, the upper end of the steel casing 3 has a docking port 33 which maintains a coaxial connection state with the next steel casing 3 .

[0061] The end of the next steel casing 3 has a docking block that is clamped with the docking port 33 on the end of the previous steel casing 3. The purpose of the docking port 33 is to ensure that when the steel casing 3 is lowered section by section, each section of the steel casing 3 can be accurately and tightly connected to each other, maintaining axial consistency throughout the drilling process, ensuring that the steel casings 3 are coaxial with each other, and the rotary drill bit assembly 2 is connected to the next steel casing 3, thereby continuously pushing the previous steel casing 3 to sink until it reaches a preset depth.

[0062] The present invention realizes that the first drill bit body 21 and the second drill bit body 22 can rotate synchronously and in the same direction through the linkage component 5, which not only helps to break the stratum more effectively, but also ensures the straightness and verticality of the borehole, solves the drilling deviation problem caused by uneven force on a single drill bit in the prior art, and is conducive to the rapid removal of the broken soft soil in the steel casing 3. The design of the spiral blade 2211 greatly improves the efficiency of soil discharge, reduces the problem of soil clogging during the drilling process, and ensures the final bearing capacity and service life of the pile foundation.

[0063] The above embodiments only express one or several implementation modes of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the present invention. It should be pointed out that, for those of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the attached claims.

Claims

1. A rapid construction method for large-diameter pile foundations in deep-water karst areas. It is characterized in that The following steps are involved: S1. Construction preparation: a temporary or permanent water construction platform (1) is set up near the predetermined pile position, and construction equipment such as rotary drilling rigs are transported to the water construction platform (1); S2, drilling construction: designing a large-diameter pile foundation and a rotary drilling bit assembly (2) suitable for the characteristics of the deep-water karst area, and starting the rotary drilling bit assembly (2) by means of a rotary drilling rig on the above-water construction platform (1), so that the steel casing (3) forming the large-diameter pile foundation sinks to a predetermined position; S3, discharging soil: during the process of the rotary drilling bit assembly (2) rotary drilling the soil, the rotary drilling bit assembly (2) synchronously pushes the soil upwards until the soil is discharged; S4, pouring the pile foundation: after the drilling reaches the designed depth, the hole diameter, hole depth and hole wall quality are checked, the steel casing (3) is left in the hole, the rotary drilling drill assembly (2) is removed, and then the steel cage is installed, and concrete is continuously and quickly poured into the steel casing (3) to form a solid pile foundation; In the drilling construction step S2, the steel casing (3) is used as a supporting structure for the inner wall of the hole, and the rotary drilling drill bit assembly (2) is used as a driving source for the rotary drilling movement of the steel casing (3). The rotary drilling drill bit assembly (2) is composed of a first drill bit body (21), a second drill bit body (22) and a rotary connecting piece (23). The first drill bit body (21) is fixedly connected to the lower end of the steel casing (3), the second drill bit body (22) is fixedly connected to the rotary connecting piece (23), and the first drill bit body ( 21) is a cylindrical structure with a cutting edge at the end, the second drill bit body (22) is arranged in the first drill bit body (21), the rotary drilling rig is provided with a slide rail (4) and a lifting slider (41) slidably arranged on the slide rail (4), the rotating connecting member (23) is rotatably connected to the lifting slider (41), and a linkage component (5) is provided between the first drill bit body (21) and the second drill bit body (22) for keeping the first drill bit body (21) and the second drill bit body (22) rotating synchronously and in the same direction; In the soil discharge step of S3, the rotary drilling bit assembly (2) is further provided with a rotating inner tube (221) fixedly connected between the rotating connector (23) and the second drill bit body (22); a fixed inner tube (211) fixedly connected to the lifting slider (41) is coaxially provided in the steel casing (3); the outer diameter of the fixed inner tube (211) is equal to the inner diameter of the steel casing (3); the fixed inner tube (211) and the rotating inner tube (221) are coaxial; a spiral blade (2211) is provided between the fixed inner tube (211) and the rotating inner tube (221); the spiral blade (2211) is fixedly connected to the rotating inner tube (221); and the rotating inner tube (221) can rotate relative to the fixed inner tube (211) around its axis direction; A bearing (31) is provided between the upper end of the steel casing (3) and the fixed inner tube (211); the inner ring of the bearing (31) is fixedly connected to the fixed inner tube (211); and a positioning assembly (6) is provided between the outer ring of the bearing (31) and the steel casing (3); The linkage assembly (5) is provided with a first shift plate (51) and a second shift plate (52), wherein the first shift plate (51) is fixedly connected to the lower end of the rotating inner tube (221), and the second shift plate (52) is fixedly connected to the inner ring of the first drill bit body (21); when the rotating inner tube (221) rotates, the first shift plate (51) contacts the second shift plate (52), thereby driving the steel casing (3) to rotate synchronously; The positioning assembly (6) is provided with a positioning shaft (61) and a stretching driving member (62); There are a plurality of positioning shafts (61), and the plurality of positioning shafts (61) are evenly distributed in the circumferential direction of the steel casing (3). The axial direction of the positioning shaft (61) is perpendicular to the axial direction of the steel casing (3). The outer ring of the bearing (31) is fixedly provided with a sleeve (311) extending downward and sleeved on the steel casing (3). A fixing pin (312) is fixedly connected between the sleeve (311) and the outer ring of the bearing (31). The end of the positioning shaft (61) passes through the fixing pin (312) and the sleeve (311) in sequence. The fixing pin (312) and the sleeve (311) are provided with guide openings for the positioning shaft (61) to pass through. A positioning opening for the positioning shaft (61) to be inserted into is provided through the steel casing (3) at a position corresponding to the positioning shaft (61). The stretching driving member (62) is arranged on the outer ring of the bearing (31), and all the positioning shafts (61) are connected to the stretching driving member (62); A spring (611) sleeved on the positioning shaft (61) is fixedly connected between the positioning shaft (61) and the fixed pin shaft (312). The stretching drive member (62) is provided with a fixed electromagnet (621) and a movable electromagnet (622). Both the fixed electromagnet (621) and the movable electromagnet (622) are annular structures. The fixed electromagnet (621) is fixedly sleeved on the outer ring of the bearing (31). The movable electromagnet (622) is movably sleeved on the outer ring of the bearing (31). The movable electromagnet (622) can move along the axial direction of the bearing (31). A connecting rod (623) is hingedly provided between each positioning shaft (61) and the movable electromagnet (622).

2. A rapid construction method for large-diameter pile foundations in deep-water karst areas according to claim 1, It is characterized in that The upper half of the fixed inner tube (211) is provided with a discharge outlet (2111).

3. A rapid construction method for large-diameter pile foundations in deep-water karst areas according to claim 1, It is characterized in that The second drill bit body (22) is a hollow structure having a hole inside, the rotating inner tube (221) has a flow channel (222) that passes through from top to bottom and is connected to the second drill bit body (22), and the rotating connecting piece (23) has a suction channel (231) that passes through from top to bottom and is connected to the flow channel (222).

4. A rapid construction method for large-diameter pile foundations in deep-water karst areas according to claim 1, It is characterized in that The upper end of the first drill bit body (21) has an annular step (212) surrounding the inner wall of the steel casing (3), and the lower end of the fixed inner tube (211) has a positioning clamping ring (2121) extending downward and surrounding the inner wall of the annular step (212).

5. A rapid construction method for large-diameter pile foundations in deep-water karst areas according to claim 4, It is characterized in that The upper end of the steel casing (3) has a docking port (33) which maintains a coaxial connection with the next steel casing (3).