A power data monitoring system and method based on OCR technology
The power data supervision system based on OCR technology solves the problem of insufficient information support in power equipment testing and testing, realizes intelligent data collection and accurate entry, timely predicts transformer operation and maintenance needs, and improves the efficiency and safety of power equipment. sex.
Patent Information
- Application Number
- CN202311157657.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-08
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2043-09-08
AI Technical Summary
There are weak information support tools in the power equipment test and inspection process, which results in a heavy workload of test preparation and result compilation, error-prone data entry, and difficulty in detecting transformer faults, resulting in high maintenance costs and waste of resources.
Adopt a power data supervision system based on OCR technology, obtain test data through OCR technology, build an operation index prediction model and maintenance model, combine image analysis to predict corrosion conditions, realize intelligent data collection and maintenance reminders, improve data entry efficiency and accuracy, and timely Forecasting transformer maintenance needs.
It realizes the intelligent collection and accurate entry of test data, reduces manual entry errors, improves data entry efficiency, predicts transformer operation and maintenance needs in a timely manner, and avoids equipment failures and high maintenance costs.
Smart Images

Figure CN118411140B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of electric power supervision, and in particular to an electric power data supervision system and method based on OCR technology. Background Art
[0002] With the development of science and technology, artificial intelligence technology has gradually become popular in people's lives. Artificial intelligence is an emerging technical science that aims to study and develop theories, methods, technologies and application systems that can simulate, extend and expand human intelligence. The research fields of artificial intelligence include robots, language recognition, image recognition, natural language processing and expert systems. At present, the test and inspection work of power equipment substation operation and inspection is mainly carried out offline, and the information support tools are weak. There are phenomena that the test preparation relies on experience, the test process relies on memory, and the workload of sorting test results is large. After the test and inspection, the user manually records the receipt on site, manually sorts the receipt into Excel, and finally enters the data into PMS according to the sorted Excel. The workload of test results is large and it is very easy to cause data errors during data entry.
[0003] However, during the power test, due to environmental influences, such as heavy rain followed by exposure to the sun, the transformer may become damp, corroded, and short-circuited, eventually leading to transformer failure. In addition, it is difficult for users to directly know about the transformer failure during each test. As time goes by, the impact gradually increases. Even if users find that the transformer is corroded, if maintenance is carried out in advance, the equipment can still be used. Early replacement will cause a waste of resources. However, if the equipment is completely faulty for maintenance, it will be difficult and costly to repair.
[0004] Therefore, it is necessary to ensure data accuracy, quickly organize test results, predict transformer operation, and conduct predictive analysis on transformer maintenance. Therefore, an OCR-based power data supervision system and method are needed. Summary of the invention
[0005] The purpose of the present invention is to provide an electric power data monitoring system and method based on OCR technology to solve the problems raised in the above background technology.
[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a power data supervision method based on OCR technology, comprising the following steps:
[0007] S1. Obtain the data information recorded by the user when testing the transformer through OCR technology;
[0008] S2. Analyze the performance operation index value of the transformer according to the collected transformer data information, build an operation index prediction model, and predict and analyze the operation index value of the transformer in subsequent tests according to the operation index value of each test in the historical data;
[0009] S3, real-time collection of images inside the transformer equipment, analysis of the internal corrosion of the transformer, prediction of the area of the corrosion region, analysis of the impact index of each test based on the transformer operation conditions analyzed in step S2, construction of an equipment maintenance model, and prediction of the transformer maintenance;
[0010] S4. According to the transformer maintenance situation analyzed in step S3, the user is reminded of the maintenance through the display device and the announcement is made in language.
[0011] Furthermore, in step S1, the code on the transformer is scanned and identified by using a camera through OCR technology to achieve transformer binding, avoid the situation where the receipt does not correspond to the equipment, take a photo of the receipt manually recorded by the user when testing the equipment, and upload the test data into the electronic form of the experimental report template created in the PMS; OCR technology is the abbreviation of optical character recognition, which converts the text of various bills, newspapers, books, manuscripts and other printed materials into image information through optical input methods such as scanning, and then uses text recognition technology to convert the image information into usable computer input technology, supports multiple platforms such as APP, PC, and H5 to call and identify, and has the characteristics of high precision, strong stability, high adaptability, easy to use and wide range of uses; PMS is an engineering production management system that provides specifications and guidelines for enterprise equipment management. The standard content covers the enterprise equipment management policy and objectives, equipment management organizational structure, equipment management planning and equipment life management process, such as equipment demand planning, design, manufacturing, selection, purchase, installation and commissioning, acceptance, use, maintenance, point inspection, inspection and repair, transformation, update, scrapping and disposal.
[0012] The compilation of test results has been transformed from three steps: on-site record-keeping, manual data compilation into Excel, and data entry into PMS, to one step, achieving the simultaneous completion of the preparation of the test report when the test is completed, while retaining the legal benefits of the user's record of receipts, avoiding the situation where test data is completely dependent on electronic forms, resulting in missing, leaked, and malicious tampering of test data, etc., realizing the intelligent collection of test data, avoiding the tedious process of manual entry, improving the efficiency of data entry, reducing the occurrence of errors in manually entered information, and improving data accuracy.
[0013] Furthermore, in step S2, the following steps are included:
[0014] S201, record the xth transformer tested as w x ;
[0015] According to the data uploaded by OCR scanning, the resistance value between the main winding and the secondary winding of the transformer is obtained as the test resistance value, forming a set A = {a 1 , a 2 , …, a n}, where n is the number of tests, a n It is expressed as the test resistance value obtained in the nth test; the insulation resistance values between the high-voltage winding and the low-voltage winding of the transformer form a set B=
[0016] {b 1 , b 2 , …, b n}, where b n It is expressed as the insulation resistance value obtained in the nth test; the dielectric loss value of the transformer forms a set C = {c 1 , c 2 , …, c n}, where c n It is the dielectric loss value measured at the nth test;
[0017] S202, construct an operation index prediction model, and use the following formula to predict the operation index α of the equipment in the i-th test i Perform calculations
[0018]
[0019] Among them, ln represents the logarithmic function with e as the base, and e represents the natural constant. e is a constant in mathematics, an infinite non-repeating decimal, and a transcendental number. Its value is approximately 2.718281828459045, which is the base of the natural logarithmic function. It is named after the Swiss mathematician Euler, also known as the Napier constant, in honor of the Scottish mathematician John Napier who introduced logarithms; a i It is expressed as the test resistance value obtained in the i-th test, b i It is expressed as the insulation resistance value obtained in the i-th test, c i It is represented by the dielectric loss value measured in the i-th test, i∈[1,n];
[0020] When the test resistance value is low, the insulation resistance value is low, and the dielectric loss value is high, the smaller the operation index is, the more likely it is that the transformer is damp inside. When the coil is short-circuited or open-circuited, the resistance value will be significantly lower than the normal value. When the coil is poorly connected, the resistance value will also be abnormally low, but they are all sudden changes. The dampness inside the equipment will gradually corrode the equipment. As the equipment is used for a long time, it will cause short-circuit leakage when the relevant users have not repaired it, affecting the use of the equipment.
[0021] S203, calculate the operation index of each test to form a set α = {α 1 , α 2 , …, α n}, where α n Expressed as the operating index of the nth test;
[0022] Construct an operation index prediction model and use the following formula to predict the operation index value β at the n+kth test: n+k Perform the calculation:
[0023] β n+k =p+q×k;
[0024]
[0025]
[0026]
[0027] Where k represents the number of pre-tests, k∈[1, k max ],k max It is indicated as the maximum number of predictions, which is set in advance by relevant technical personnel. It is expressed as the exponential smoothing value of the running index of the nth test, The first exponential smoothing value of the operating index of the n-1th test is the predicted value of the operating index of the nth test. It is expressed as the double exponential smoothing value of the running index of the nth test, It is represented by the quadratic exponential smoothing value of the n-1th test, and f is represented by the weighting coefficient, which is pre-set by relevant technical personnel, f∈[0,1], when k=1, the predicted value of the operation index of the n+1th time is obtained;
[0028] S204, setting the threshold to β 阈 , when β n+k >β 阈 When β n+k ≤β 阈 When , it indicates that the transformer operation index is less than the threshold value, there is internal moisture, and the process goes to step S3.
[0029] Furthermore, in step S3, the following steps are included:
[0030] S301, pre-set the time interval t, use the micro high-definition camera to collect the image data inside the transformer equipment in real time, extract the corrosion contour in the image through the OpenCV technology, obtain the area of the corrosion area, and form a set S = {s 1 ,s 2 ,…,s m}, where m represents the number of images collected containing the eroded area, and s m It is expressed as the area of the eroded region in the mth collected image. OpenCV is a cross-platform computer vision and machine learning software library released under the Apache2.0 license. It consists of a series of C functions and a small number of C++ classes. It also provides interfaces for languages such as Python, Ruby, and MATLAB, and implements many common algorithms in image processing and computer vision.
[0031] S302: The predicted value s of the eroded area collected by the m+1th image is obtained by the following formula: m+1 Perform the calculation:
[0032]
[0033] Among them, g represents the prediction constant, the value of which is pre-set by relevant technical personnel, g∈[0,1], u represents the variable, s m+1-u It is expressed as the area of the eroded region in the image collected at the m+1-uth time, s 1 It is expressed as the area of the eroded region in the first collected image;
[0034] S303, the predicted value s obtained by analysis m+1 Place it in the set S, repeat steps S301-S302, and continuously predict the area of the corrosion region;
[0035] Set the threshold to s 阈 , when s m+1 ≥s 阈 When s m+1 <s 阈 , it indicates that the corrosion area does not exceed the threshold, and then the process goes to step S304;
[0036] Further, in step S3,
[0037] S304, the impact index is calculated by the following formula Perform the calculation:
[0038]
[0039] Among them, s nIt is represented by the corrosion area corresponding to the user's nth test, s n-1 It is represented by the corrosion area corresponding to the user's n-1th test, α n-1 It is represented as the operation index of the user's n-1th test, |α n -α n-1 |It is expressed as the absolute value of the difference between the operation index of the nth test and the n-1th test; in each test, the corresponding impact index is obtained by analyzing the data of the previous test;
[0040] S305. According to the analysis results of steps S301-S304, combined with the transformer operation status analyzed in step S2, according to the analysis results of steps S301-S303, combined with the transformer operation status analyzed in step S2, an equipment maintenance model is constructed, and the transformer maintenance index H is calculated by the following formula:
[0041]
[0042] Where j is a constant, which is set in advance by relevant technical personnel to ensure that the denominator is always not 0, s n+k It is expressed as the predicted value of the corrosion area at the time of the n+kth test; after the nth test, the operation index of the n+1th test is analyzed, and the maintenance index is predicted and analyzed according to the real-time image changes. When the operation index decreases and the corrosion area increases, the maintenance index increases;
[0043] Set the threshold to H 阈 , when H ≥ H 阈 When H <H 阈 When the transformer is operating normally, no reminder will be given to the relevant technical personnel;
[0044] S306. Analyze the transformer maintenance index of all transformer equipment and predict the maintenance status of the transformer.
[0045] Furthermore, in step S4, according to the results of the prediction analysis in step S2 and step S3, when the transformer is predicted to be abnormal, the abnormal transformer information is displayed to relevant technicians through the display device, and a voice alarm is given to relevant technicians through the voice device.
[0046] An electric power data monitoring system based on OCR technology, the electric power data monitoring system comprising: an electric power data analysis module;
[0047] The power data analysis module is used to perform intelligent predictive analysis on the operation and maintenance conditions of the transformer equipment, and includes an equipment operation unit and an internal prediction unit. The equipment operation unit is used to construct an operation index prediction model to perform predictive analysis on the operation conditions of the transformer. The internal prediction unit is used to perform predictive analysis on the corrosion conditions inside the transformer, and comprehensively construct an equipment maintenance model to perform intelligent predictive management on the maintenance of the equipment.
[0048] The power data supervision system also includes: a data monitoring module;
[0049] The output end of the data monitoring module is connected to the input end of the power data analysis module;
[0050] The data monitoring module is used to collect the test data and internal image data of the transformer, including an OCR acquisition unit and an image acquisition unit. The OCR acquisition unit is used to scan and identify the receipt manually recorded by the user when testing the equipment through OCR technology, and upload the test data into the electronic form of the experimental report template created in the PMS, avoiding the tedious process of manual entry, improving the work efficiency of data entry, reducing the occurrence of errors in manually entered information, and improving the accuracy of the data. The image acquisition unit uses a micro high-definition camera to collect the internal image data of the transformer equipment in real time.
[0051] The power data supervision system also includes: a data management module;
[0052] The input end of the data management module is connected to the output end of the data monitoring module, the output end of the data management module is connected to the input end of the power data analysis module, and the input end of the data management module is connected to the output end of the power data analysis module;
[0053] The data management module is used for intelligent encryption management of the collected data and analysis results, including a data storage unit and a security encryption unit. The data storage unit stores the collected data and analysis results through a distributed architecture. A distributed system is a business divided into multiple sub-businesses, which are distributed in different server nodes. The system together is called a distributed system, which has the characteristics of distribution, autonomy, parallelism and globality, which is convenient for managing the data of the transformer and promotes resource sharing. At the same time, it has high reliability and good fault tolerance. The security encryption unit is used to encrypt all stored data through a salted hash encryption algorithm to ensure the security and reliability of the data and avoid information leakage or tampering. Hash, also known as "hash", is a digital computer program that receives any set of input information of arbitrary length and transforms it into a fixed-length data fingerprint output form, such as a combination of letters and numbers, through a hash algorithm. The output is the hash value. The principle of the salted hash encryption algorithm is to mix a random string into the encryption and then perform hash encryption. This random string is the salt value. Even if the password is the same, if the salt value is different, the hash value is also different.
[0054] The power data supervision system also includes: a maintenance prompt module;
[0055] The input end of the maintenance prompt module is connected to the output end of the power data analysis module;
[0056] The maintenance prompt module is used to prompt relevant technical personnel when an abnormal transformer appears according to the analysis results, and includes a data display unit and a voice alarm unit. The data display unit is used to display abnormal transformer information to relevant technical personnel through a display device when an abnormal transformer is predicted to appear. The voice alarm unit is used to issue a voice alarm to relevant technical personnel through a voice device, so that relevant technical personnel can repair the transformer equipment in time to avoid gradual failure of the equipment due to internal moisture or even leakage, thereby ensuring the user's electricity safety.
[0057] Compared with the prior art, the beneficial effects achieved by the present invention are:
[0058] The present invention enters test and inspection receipts through OCR technology, and converts the organization of test results from three steps of on-site record-keeping, manual data organization into Excel and data entry into PMS into one step, so that the preparation of the test report is completed simultaneously with the completion of the test, and the legal benefits of the user's record of receipts are retained, avoiding the situation of complete reliance on electronic forms, which leads to the loss, leakage and malicious tampering of test data, realizing the intelligent collection of test data, avoiding the tedious process of manual entry, improving the work efficiency of data entry, reducing the occurrence of errors in manually entered information, and improving the accuracy of data.
[0059] Based on historical test data, an operation index prediction model is constructed to predict and analyze the operation of the transformer. Combined with internal images, the corrosion situation inside the transformer is predicted and analyzed. An equipment maintenance model is constructed to comprehensively predict equipment maintenance, ensuring the accuracy of data entry, making it easier for users to repair damp equipment in a timely manner, avoiding situations where equipment gradually fails over time and users fail to discover the problem in time, maximizing the use value of the equipment, reducing the cost of repairing the equipment after it has completely failed, improving the user's maintenance efficiency, and ensuring the user's electricity safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0060] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0061] Figure 1 It is a flow chart of the steps of a power data supervision method based on OCR technology of the present invention;
[0062] Figure 2 This is a schematic diagram of the module composition of an electric power data monitoring system based on OCR technology of the present invention; DETAILED DESCRIPTION
[0063] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0064] The present invention provides a technical solution: a power data supervision method based on OCR technology, Figure 1 It is a step flow chart, characterized in that it includes the following steps:
[0065] S1. Obtain the data information recorded by the user when testing the transformer through OCR technology;
[0066] In step S1, OCR technology is used to obtain the image of the camera, such as a mobile phone APP or Hanvon V700 scanner, etc., scan and identify the code on the transformer, including barcode or QR code, etc., to achieve transformer binding, avoid the situation that the receipt does not correspond to the equipment, take a photo of the receipt manually recorded by the user when testing the equipment, and upload the test data into the electronic form of the experimental report template created in PMS; OCR technology is the abbreviation of optical character recognition, which converts the text of various bills, newspapers, books, manuscripts and other printed materials into image information through optical input methods such as scanning, and then uses text recognition technology to convert the image information into usable computer input technology, supports APP, PC, H5 and multiple platforms to call and identify, with high precision, strong stability, high adaptability, easy to use and wide range of uses; PMS is an engineering production management system, which provides specifications and guidelines for enterprise equipment management. The standard content covers the enterprise equipment management policy and objectives, equipment management organizational structure, equipment management planning and equipment life management process, such as equipment demand planning, design, manufacturing, selection, purchase, installation and commissioning, acceptance, use, maintenance, point inspection, inspection and repair, transformation, update, scrapping and disposal.
[0067] The compilation of test results has been transformed from three steps: on-site record-keeping, manual data compilation into Excel, and data entry into PMS, to one step, achieving the simultaneous completion of the preparation of the test report when the test is completed, while retaining the legal benefits of the user's record of receipts, avoiding the situation where test data is completely dependent on electronic forms, resulting in missing, leaked, and malicious tampering of test data, etc., realizing the intelligent collection of test data, avoiding the tedious process of manual entry, improving the efficiency of data entry, reducing the occurrence of errors in manually entered information, and improving data accuracy.
[0068] S2. Analyze the performance operation index value of the transformer according to the collected transformer data information, build an operation index prediction model, and predict and analyze the operation index value of the transformer in subsequent tests according to the operation index value of each test in the historical data;
[0069] In step S2, the following steps are included:
[0070] S201, record the xth transformer tested as w x ;
[0071] According to the data uploaded by OCR scanning, the resistance value between the main winding and the secondary winding of the transformer is obtained as the test resistance value, forming a set A = {a 1 , a 2 , …, a n}, where n is the number of tests, a nIt is represented by the test resistance value obtained in the nth test; the insulation resistance value between the high-voltage winding and the low-voltage winding of the transformer forms a set B = {b 1 , b 2 , …, b n}, where b n It is expressed as the insulation resistance value obtained in the nth test; the dielectric loss value of the transformer forms a set C = {c 1 , c 2 , …, c n}, where c n It is the dielectric loss value measured at the nth test;
[0072] S202, construct an operation index prediction model, and use the following formula to predict the operation index α of the equipment in the i-th test i Perform calculations
[0073]
[0074] Among them, ln represents the logarithmic function with e as the base, e represents the natural constant, which is a constant in mathematics, an infinite non-repeating decimal, and a transcendental number. Its value is approximately 2.718281828459045, which is the base of the natural logarithmic function. It is named after the Swiss mathematician Euler, also known as the Napier constant, in memory of the Scottish mathematician John Napier who introduced logarithms; ai represents the test resistance value obtained in the i-th test, b i It is expressed as the insulation resistance value obtained in the i-th test, c i It is represented by the dielectric loss value measured in the i-th test, i∈[1,n];
[0075] When the test resistance value is low, the insulation resistance value is low, and the dielectric loss value is high, the smaller the operation index is, the more likely it is that the transformer is damp inside. When the coil is short-circuited or open-circuited, the resistance value will be significantly lower than the normal value. When the coil is poorly connected, the resistance value will also be abnormally low, but they are all sudden changes. The dampness inside the equipment will gradually corrode the equipment. As the equipment is used for a long time, it will cause short-circuit leakage when the relevant users have not repaired it, affecting the use of the equipment.
[0076] S203, calculate the operation index of each test to form a set α = {α 1 , α 2 , …, α n}, where α n Expressed as the operating index of the nth test;
[0077] Construct an operation index prediction model and use the following formula to predict the operation index value β at the n+kth test: n+k Perform the calculation:
[0078] β n+k =p+q×k;
[0079]
[0080]
[0081]
[0082] Where k represents the number of pre-tests, k∈[1, k max ],k max It is indicated as the maximum number of predictions, which is set in advance by relevant technical personnel. It is expressed as the exponential smoothing value of the running index of the nth test, The first exponential smoothing value of the operating index of the n-1th test is the predicted value of the operating index of the nth test. It is expressed as the double exponential smoothing value of the running index of the nth test, It is represented by the quadratic exponential smoothing value of the n-1th test, and f is represented by the weighting coefficient, which is pre-set by relevant technical personnel, f∈[0,1], when k=1, the predicted value of the operation index of the n+1th time is obtained;
[0083] S204, setting the threshold to β 阈 , when β n+k >β 阈 When β n+k ≤β 阈 When , it indicates that the transformer operation index is less than the threshold value, there is internal moisture, and the process goes to step S3.
[0084] S3, real-time collection of images inside the transformer equipment, analysis of the internal corrosion of the transformer, prediction of the area of the corrosion region, analysis of the impact index of each test based on the transformer operation conditions analyzed in step S2, construction of an equipment maintenance model, and prediction of the transformer maintenance;
[0085] In step S3, the following steps are included:
[0086] S301, pre-set the time interval t, use the micro high-definition camera to collect the image data inside the transformer equipment in real time, extract the corrosion contour in the image through the OpenCV technology, obtain the area of the corrosion area, and form a set S = {s 1 ,s 2 ,…,s m}, where m represents the number of images collected containing the eroded area, and s mIt is expressed as the area of the eroded region in the mth collected image. OpenCV is a cross-platform computer vision and machine learning software library released under the Apache2.0 license. It consists of a series of C functions and a small number of C++ classes. It also provides interfaces for languages such as Python, Ruby, and MATLAB, and implements many common algorithms in image processing and computer vision.
[0087] S302: The predicted value s of the eroded area collected by the m+1th image is obtained by the following formula: m+1 Perform the calculation:
[0088]
[0089] Among them, g represents the prediction constant, the value of which is pre-set by relevant technical personnel, g∈[0,1], u represents the variable, s m+1-u It is expressed as the area of the eroded region in the image collected at the m+1-uth time, s 1 It is expressed as the area of the eroded region in the first collected image;
[0090] S303, the predicted value s obtained by analysis m+1 Place it in the set S, repeat steps S301-S302, and continuously predict the area of the corrosion region;
[0091] Set the threshold to s 阈 , when s m+1 ≥s 阈 When S m+1 <s 阈 , it indicates that the corrosion area does not exceed the threshold, and then the process goes to step S304;
[0092] S304, the impact index is calculated by the following formula Perform the calculation:
[0093]
[0094] Among them, s n It is represented by the corrosion area corresponding to the user's nth test, s n-1 It is represented by the corrosion area corresponding to the user's n-1th test, α n-1 It is represented as the operation index of the user's n-1th test, |α n -α n-1 |It is expressed as the absolute value of the difference between the operation index of the nth test and the n-1th test; in each test, the corresponding impact index is obtained by analyzing the data of the previous test;
[0095] S304: Based on the analysis results of steps S301-S304, combined with the transformer operation status analyzed in step S2, and based on the analysis results of steps S301-S303, combined with the transformer operation status analyzed in step S2, an equipment maintenance model is constructed, and the transformer maintenance index H is calculated by the following formula:
[0096]
[0097] Where j is a constant, which is set in advance by relevant technical personnel to ensure that the denominator is always not 0, s n+k It is expressed as the predicted value of the corrosion area at the time of the n+kth test. After the nth test, the operation index of the n+1th test is analyzed. At the same time, the maintenance index is predicted and analyzed according to the real-time image changes. When the operation index decreases and the corrosion area increases, the maintenance index increases.
[0098] Set the threshold to H 阈 , when H ≥ H 阈 When H<H 阈 When the transformer is operating normally, no reminder will be given to the relevant technical personnel;
[0099] S305. Analyze the transformer maintenance index of all transformer equipment and predict the maintenance status of the transformer.
[0100] S4. According to the transformer maintenance situation analyzed in step S3, the user is reminded of the maintenance through the display device and the announcement is made in language.
[0101] In step S4, according to the results of the predictive analysis in step S2 and step S3, when the transformer is predicted to be abnormal, the abnormal transformer information, including the transformer location, analysis results and test data, is displayed to the relevant technicians through a display device such as a mobile phone, a computer or a central control display screen, and a voice alarm is given to the relevant technicians through a voice device such as a broadcast or AI voice.
[0102] An electric power data supervision system based on OCR technology. Figure 2 The schematic diagram of the module composition is shown in FIG. 1 , wherein the power data supervision system includes: a power data analysis module;
[0103] The power data analysis module is used to perform intelligent predictive analysis on the operation and maintenance conditions of the transformer equipment, and includes an equipment operation unit and an internal prediction unit. The equipment operation unit is used to construct an operation index prediction model to perform predictive analysis on the operation conditions of the transformer. The internal prediction unit is used to perform predictive analysis on the corrosion conditions inside the transformer, and comprehensively construct an equipment maintenance model to perform intelligent predictive management on the maintenance of the equipment.
[0104] The power data supervision system also includes: a data monitoring module;
[0105] The output end of the data monitoring module is connected to the input end of the power data analysis module;
[0106] The data monitoring module is used to collect the test data and internal image data of the transformer, including an OCR acquisition unit and an image acquisition unit. The OCR acquisition unit is used to scan and identify the receipt manually recorded by the user when testing the equipment through OCR technology, and upload the test data into the electronic form of the experimental report template created in the PMS, avoiding the tedious process of manual entry, improving the work efficiency of data entry, reducing the occurrence of errors in manually entered information, and improving the accuracy of the data. The image acquisition unit uses a micro high-definition camera to collect the internal image data of the transformer equipment in real time.
[0107] The power data supervision system also includes: a data management module;
[0108] The input end of the data management module is connected to the output end of the data monitoring module, the output end of the data management module is connected to the input end of the power data analysis module, and the input end of the data management module is connected to the output end of the power data analysis module;
[0109] The data management module is used for intelligent encryption management of the collected data and analysis results, including a data storage unit and a security encryption unit. The data storage unit stores the collected data and analysis results through a distributed architecture. A distributed system is a business divided into multiple sub-businesses, which are distributed in different server nodes. The system together is called a distributed system, which has the characteristics of distribution, autonomy, parallelism and globality, which is convenient for managing the data of the transformer and promotes resource sharing. At the same time, it has high reliability and good fault tolerance. The security encryption unit is used to encrypt all stored data through a salted hash encryption algorithm to ensure the security and reliability of the data and avoid information leakage or tampering. Hash, also known as "hash", is a digital computer program that receives any set of input information of arbitrary length and transforms it into a fixed-length data fingerprint output form, such as a combination of letters and numbers, through a hash algorithm. The output is the hash value. The principle of the salted hash encryption algorithm is to mix a random string into the encryption and then perform hash encryption. This random string is the salt value. Even if the password is the same, if the salt value is different, the hash value is also different.
[0110] The power data supervision system also includes: a maintenance prompt module;
[0111] The input end of the maintenance prompt module is connected to the output end of the power data analysis module;
[0112] The maintenance prompt module is used to prompt relevant technical personnel when an abnormal transformer appears according to the analysis results, and includes a data display unit and a voice alarm unit. The data display unit is used to display abnormal transformer information to relevant technical personnel through display devices such as mobile phones, computers or central control display screens when it is predicted that the transformer will be abnormal, including transformer location, analysis results and test data. The voice alarm unit is used to issue voice alarms to relevant technical personnel through voice devices such as broadcasting or AI voice, so that relevant technical personnel can repair the transformer equipment in time to avoid gradual failure of the equipment due to internal moisture or even leakage, thereby ensuring the safety of users' electricity use.
[0113] Embodiment 1:
[0114] If the weighting coefficient f = 0.8, the first exponential smoothing value of the operating index of the nth test is 62, and the second exponential smoothing value of the operating index of the nth test is 60.
[0115]
[0116] β n+k =p+q×k=64+8k;
[0117] Then βn+1 =64+8×1=72;
[0118] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0119] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A power data supervision method based on OCR technology, characterized by: The following steps are involved: S1. Obtain the data information recorded by the user when testing the transformer through OCR technology; S2. Analyze the performance operation index value of the transformer according to the collected transformer data information, build an operation index prediction model, and predict and analyze the operation index value of the transformer in subsequent tests according to the operation index value of each test in the historical data; S3, real-time collection of images inside the transformer equipment, analysis of the internal corrosion of the transformer, prediction of the area of the corrosion region, analysis of the impact index of each test based on the transformer operation conditions analyzed in step S2, construction of an equipment maintenance model, and prediction of the transformer maintenance; S4. According to the transformer maintenance situation analyzed in step S3, the user is reminded of the maintenance through the display device and the announcement is made in language; In step S3, the following steps are included: S301, pre-set the time interval t, use the micro high-definition camera to collect the internal image data of the transformer equipment in real time, extract the corrosion contour in the image through the OpenCV technology, obtain the area of the corrosion area, and form a set S = {s1, s2, ..., s m }, where m represents the number of images collected containing the eroded area, and s m It is expressed as the area of the eroded region in the mth acquisition image; S302: The predicted value s of the eroded area collected by the m+1th image is obtained by the following formula: m+1 Perform the calculation: Among them, g represents the prediction constant, u represents the variable, and s m+1-u It is represented by the area of the eroded region in the image collected at the m+1-uth time, and s1 is represented by the area of the eroded region in the image collected at the first time; S303, the predicted value s obtained by analysis m+1 Place it in the set S, repeat steps S301-S302, and continuously predict the area of the corrosion region; Set the threshold to s 阈 , when s m+1 ≥s 阈 When s m+1 阈 , it indicates that the corrosion area does not exceed the threshold, and then the process goes to step S304; S304, the impact index is calculated by the following formula Perform the calculation: Among them, s n It is represented by the corrosion area corresponding to the user's nth test, s n-1 It is represented by the corrosion area corresponding to the user's n-1th test, α n-1 It is represented as the operation index of the user's n-1th test, |α n -α n-1 It is expressed as the absolute value of the difference between the operating index of the nth test and the n-1th test; S305. According to the analysis results of steps S301-S304 and the transformer operation status analyzed in step S2, an equipment maintenance model is constructed, and the transformer maintenance index H is calculated by the following formula: Where j is a constant, s n+k It is expressed as the predicted value of corrosion area at the time of the n+kth test, β n+k is the predicted value of the operation index at the n+kth test; Set the threshold to H 阈 , when H ≥ H 阈 When H <H 阈 When the relevant technical personnel are not reminded; S306. Analyze the transformer maintenance index of all transformer equipment and predict the maintenance status of the transformer.
2. The power data supervision method based on OCR technology according to claim 1 is characterized in that: In step S1, the code on the transformer is scanned and identified using a camera through OCR technology, the receipt manually recorded by the user when testing the equipment is photographed and identified, and the test data is uploaded and entered into the electronic form of the experimental report template created in the PMS.
3. The power data supervision method based on OCR technology according to claim 2 is characterized in that: In step S2, the following steps are included: S201, record the xth transformer tested as w x ; According to the data uploaded by OCR scanning, the resistance value between the main winding and the secondary winding of the transformer is obtained as the test resistance value, forming a set A = {a1, a2, ..., a n }, where n is the number of tests, a n It is represented by the test resistance value obtained in the nth test; the insulation resistance value between the high-voltage winding and the low-voltage winding of the transformer forms a set B = {b1, b2, ..., b n }, where b n It is expressed as the insulation resistance value obtained in the nth test; the dielectric loss value of the transformer forms a set C = {c1, c2, ..., c n }, where c n It is the dielectric loss value measured at the nth test; S202, construct an operation index prediction model, and use the following formula to predict the operation index α of the equipment in the i-th test i Perform the calculation: Where ln is a logarithmic function with e as the base, e is a natural constant; a i It is expressed as the test resistance value obtained in the i-th test, b i It is expressed as the insulation resistance value obtained in the i-th test, c i It is represented by the dielectric loss value measured in the i-th test; S203, calculate the operation index of each test to form a set α = {α1, α2, ..., α n }, where α n Expressed as the operation index of the nth test; Construct an operation index prediction model and use the following formula to predict the operation index value β at the n+kth test: n+k Perform the calculation: b n+k =p+q×k; Where k represents the number of pre-tests. It is expressed as the exponential smoothing value of the running index of the nth test, It is expressed as the exponential smoothing value of the running index of the n-1th test, It is expressed as the double exponential smoothing value of the running index of the nth test, It is represented by the quadratic exponential smoothing value of the n-1th test, and f is represented by the weighting coefficient; S204, setting the threshold to β 阈 , when β n+k >β 阈 When β n+k ≤β 阈 , proceed to step S3.
4. The power data supervision method based on OCR technology according to claim 1 is characterized in that: In step S4, according to the results of the prediction analysis in step S2 and step S3, when the transformer is predicted to be abnormal, the abnormal transformer information is displayed to the relevant technicians through the display device, and a voice alarm is given to the relevant technicians through the voice device.
5. A power data supervision system based on OCR technology, the system executing the power data supervision method based on OCR technology as claimed in claim 1, characterized in that: The power data supervision system includes: a power data analysis module; The power data analysis module is used to perform intelligent predictive analysis on the operation and maintenance conditions of the transformer equipment, and includes an equipment operation unit and an internal prediction unit. The equipment operation unit is used to construct an operation index prediction model to perform predictive analysis on the operation conditions of the transformer. The internal prediction unit is used to perform predictive analysis on the corrosion conditions inside the transformer, and comprehensively construct an equipment maintenance model to perform intelligent predictive management on the maintenance of the equipment.
6. The power data monitoring system based on OCR technology according to claim 5 is characterized in that: The power data supervision system also includes: a data monitoring module; The output end of the data monitoring module is connected to the input end of the power data analysis module; The data monitoring module is used to collect the test data and internal image data of the transformer, including an OCR acquisition unit and an image acquisition unit. The OCR acquisition unit is used to scan and identify the receipt manually recorded by the user when testing the equipment through OCR technology, and upload the test data into the electronic form of the experimental report template created in the PMS. The image acquisition unit uses a micro high-definition camera to collect the internal image data of the transformer equipment in real time.
7. The power data monitoring system based on OCR technology according to claim 6 is characterized by: The power data supervision system also includes: a data management module; The input end of the data management module is connected to the output end of the data monitoring module, the output end of the data management module is connected to the input end of the power data analysis module, and the input end of the data management module is connected to the output end of the power data analysis module; The data management module is used to perform intelligent encryption management on the collected data and analysis results, and includes a data storage unit and a security encryption unit. The data storage unit stores the collected data and analysis results through a distributed architecture, and the security encryption unit is used to encrypt all stored data through a salted hash encryption algorithm.
8. The power data monitoring system based on OCR technology according to claim 5 is characterized by: The power data supervision system also includes: a maintenance prompt module; The input end of the maintenance prompt module is connected to the output end of the power data analysis module; The maintenance prompt module is used to prompt relevant technicians when an abnormal transformer appears according to the analysis results, and includes a data display unit and a voice alarm unit. The data display unit is used to display abnormal transformer information to relevant technicians through a display device when an abnormal transformer is predicted to appear. The voice alarm unit is used to issue a voice alarm to relevant technicians through a voice device.
Citation Information
Patent Citations
Intelligent monitoring and operation and maintenance system for transformer
CN113689013A
Digital tuning equipment early warning supervision system and method based on Internet of Things
CN116016119A