A slab collapse construction method for tunnel karst cave

By drilling and installing I-steel blind holes and installing steel arch frame structures on the tunnel construction platform, a temporary crossing platform is formed, which solves the construction problems of vertical development caves, improves construction safety and efficiency, and ensures structural stability and water flow. The passage is smooth.

CN118423083BActive Publication Date: 2024-11-01HUNAN PROVINCIAL COMM PLANNING SURVEY & DESIGN INST CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410879948.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-02
Publication Date
2024-11-01
Estimated Expiration
2044-07-02

AI Technical Summary

Technical Problem

During the tunnel construction process, when encountering large vertically developed caves, the existing technology is difficult to provide effective support, resulting in high construction difficulty, low efficiency and safety hazards. In particular, the cave wall is vertically smooth and has no construction surface, making it difficult to install concrete The slag or bridge deck, and the slag excavated in front of the blasting and excavation can easily block the bottom water passage, affecting the water passing capacity of the dissolution chamber.

Method used

The construction platform is excavated downward at the excavated tunnel section near the target tunnel cave. A drilling device is used to drill I-steel blind holes on the cave wall to form a temporary crossing platform, and the outer and inner steel are installed on it. The arch frame and the intermediate buffer layer overlap the reinforced concrete span, and is used as a formwork as a cross-platform and a overlapping platform, solving the support problems and the problem of water passage blockage.

Benefits of technology

It improves construction safety and efficiency, can effectively support the casting of reinforced concrete with larger thickness, solves the load problem in the air-to-air situation of the bottom, and ensures construction convenience and structural stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118423083B_ABST
    Figure CN118423083B_ABST
Patent Text Reader

Abstract

The present invention provides a slab collapse construction method for a tunnel karst cave, wherein a construction platform is excavated downward near the target tunnel karst cave position in the excavated tunnel section, a blind hole row for I-beam installation is drilled on the karst cave wall of the target tunnel karst cave away from the construction platform by using a drilling device on the construction platform, one end of each I-beam is pushed into the corresponding overlapping blind hole in turn, the other end of each I-beam is overlapped on the construction platform to form a temporary spanning platform, a protective scaffold composed of an outer steel arch frame, an inner steel arch frame and an intermediate buffer layer is installed above the temporary spanning platform, a lap platform for overlapping reinforced concrete spanning slabs is excavated on the karst cave wall of the target tunnel karst cave away from the construction platform along the tunnel excavation direction, and the temporary spanning platform is used as a template to construct the reinforced concrete spanning slab. The present application can solve the problems of rockfall on the top, water overflow at the bottom and vertical and smooth karst cave wall without construction working surface during tunnel construction, and has high safety and construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, in particular to a slab collapse construction method of a tunnel karst cave. Background Art

[0002] Nowadays, during the construction of highway karst tunnels, the face often reveals large vertically developed karst caves (the height of the tunnel arch is greater than 10m, the depth of the arch bottom is greater than 10m, and the longitudinal length is less than 10m), which brings great safety hazards to tunnel construction and operation. For the karst caves encountered during tunnel excavation and construction, when the scale of the karst cave is small, it is generally treated by backfilling with cave slag and mortar-laid stone. However, it cannot be well treated for terrain with large karst cave space, and the backfilling method will greatly weaken the water-passing capacity of the karst cavity. In the event of heavy rain or floods, the water in the karst cavity cannot be discharged in time, which poses a great risk to tunnel safety.

[0003] In order not to affect the smooth flow of water through the bottom of the karst cavity, the existing technology usually uses bridges or concrete slabs to cross larger karst caves. However, the karst cavity wall in front is basically in a vertical state, and the karst cave wall is vertical and smooth without a construction working surface, which makes it difficult to provide support for the concrete slab or bridge deck. In addition, the debris produced by the blasting and excavation in front is also easy to block the bottom water through channel. In addition, due to the small space in the tunnel, large machinery is difficult to play a role, the construction efficiency of the bridge in the cave is low, and the falling rocks caused by the blasting vibration of the front face can easily injure the construction workers, resulting in the difficulty of construction of traditional construction methods, great safety hazards, and low efficiency.

[0004] In view of this, it is necessary to propose a slab collapse construction method for tunnel karst caves to solve or at least alleviate the above defects. Summary of the invention

[0005] The main purpose of the present invention is to provide a slab collapse construction method for a tunnel karst cave, so as to solve the technical problem that in the prior art, when a vertically developed tunnel karst cave is constructed and a bridge or a concrete slab is used to cross it, there is a vertical and smooth karst cave wall with no construction working surface, it is difficult to provide support for the concrete slab or the bridge deck, and the construction is difficult and inefficient.

[0006] To achieve the above object, the present invention provides a slab collapse construction method for a tunnel karst cave, comprising the steps of: S1, excavating a construction platform downward near a target tunnel karst cave position in an excavated tunnel section; wherein the target tunnel karst cave is located in front of the excavated tunnel section, and the target tunnel karst cave is developed vertically;

[0007] S2, using a drilling device on the construction platform to drill a row of blind holes for installing I-beams on the wall of the target tunnel cave away from the construction platform; wherein the row of blind holes includes a plurality of overlapping blind holes arranged transversely along the tunnel;

[0008] S3, sequentially pushing one end of each I-beam into the corresponding overlapping blind hole, overlapping the other end of each I-beam on the construction platform, and welding and fixing two adjacent I-beams through connecting ribs to form a temporary spanning platform;

[0009] S4, installing a plurality of outer steel arch frames arranged at intervals along the extension direction of the temporary spanning platform above the temporary spanning platform, hanging a first double-layer steel mesh between two adjacent outer steel arch frames, and spraying concrete toward the first double-layer steel mesh to obtain an outer steel arch frame structure layer;

[0010] S5, installing a plurality of inner steel arch frames arranged at intervals along the extension direction of the temporary spanning platform above the temporary spanning platform, and hanging a second double-layer steel mesh between two adjacent inner steel arch frames, reserving a blowing and filling pipe, and then spraying concrete toward the second double-layer steel mesh to obtain an inner steel arch frame structure layer; wherein the inner steel arch frame is arranged on the inner side of the outer steel arch frame, the blowing and filling pipe is connected to the inner steel arch frame through connecting ribs, and the outlet of the blowing and filling pipe faces the outer steel arch frame;

[0011] S6, blowing sand into the space between the outer steel arch structure layer and the inner steel arch structure layer through the filling pipe to obtain an intermediate buffer layer;

[0012] S7, excavating a lap joint platform for lap joint of reinforced concrete span slabs on the karst cave wall of the target tunnel far away from the construction platform along the tunnel excavation direction;

[0013] S8, using the temporary spanning platform as a template to construct a reinforced concrete spanning slab spanning the construction platform and the overlapping platform, and reserving connecting steel bars for the lining structure;

[0014] S9, using the inner steel arch structure layer as a template to sequentially construct a waterproof layer and a reinforced concrete open hole structure, and then construct an internal auxiliary structure of the tunnel.

[0015] Preferably, the temporary crossing platform in step S3 is specifically determined by the following steps:

[0016] S31, according to the formula Determine the resultant vertical uniform load on the temporary crossing platform ;in, is the design value of the deadweight load of the construction machinery, It is the sum of the self-weight loads of the outer steel arch structure layer, the inner steel arch structure layer and the middle buffer layer. is the self-weight load of the reinforced concrete slab, is the deadweight load of the temporary spanning platform;

[0017] S32, according to the formula Determine the length of the overlap required at both ends of the temporary spanning platform ;in, is the sum of the required lap lengths at both ends of the temporary spanning platform, f is the design value of the foundation bearing capacity, The width of the temporary spanning platform;

[0018] S33, according to the formula Determine the cross-sectional area required for the temporary spanning platform to resist shear ;in, The shear stress of steel;

[0019] S34, determining the maximum mid-span bending moment of the temporary spanning platform ;

[0020] S35, according to the formula Determine the section inertia moment I required for the temporary spanning platform to resist bending; wherein, is the tensile stress of the steel, y is the distance from the maximum stress point to the centroid of the section of the temporary spanning platform;

[0021] S36, according to the cross-sectional area The cross-sectional size and cross-sectional shape of the temporary spanning platform are determined by the cross-sectional moment of inertia I, thereby determining the model of the I-beam of the temporary spanning platform.

[0022] Preferably, the reinforced concrete span slab in step S8 is determined by the following steps:

[0023] S81, according to the formula Determine the resultant vertical load on the reinforced concrete span ;in, It is the sum of the self-weight loads of the outer steel arch structure layer, the inner steel arch structure layer and the middle buffer layer. It is the self-weight load of the reinforced concrete open hole structure and its internal auxiliary structures. The larger value is the deadweight load of the construction machinery during construction and the vehicle load during operation. is the self-weight load of the reinforced concrete span slab;

[0024] S82, according to the formula Determine the sum of the required overlap lengths at both ends of the reinforced concrete span ;in, is the width of the reinforced concrete slab;

[0025] S83, according to the formula Determine the shear force on the reinforced concrete slab ;

[0026] S84, determining the maximum bending moment value at the mid-span of the reinforced concrete span slab ;

[0027] S85, according to the formula and formula Determine the minimum cross-sectional thickness of reinforced concrete slab per unit width and the cross-sectional area of ​​the longitudinal tensile reinforcement ;in, is the bending calculation coefficient of the positive section, is the design value of concrete axial compressive strength, b is the width of the reinforced concrete span per unit width, is the height of the concrete compression zone, is the design value of steel bar tensile strength;

[0028] S86, according to the minimum section thickness Determine the thickness of the reinforced concrete span slab according to the cross-sectional area of ​​the longitudinal tensile reinforcement Determine the reinforcement method of the reinforced concrete span slab.

[0029] Preferably, the first double-layer steel mesh includes a first steel mesh and a second steel mesh respectively arranged on both sides of the outer steel arch frame, the first steel mesh is connected to the outer wall of the outer steel arch frame, and the second steel mesh is connected to the inner wall of the outer steel arch frame, and the spacing distance between the first steel mesh and the second steel mesh matches the thickness of the outer steel arch frame.

[0030] Preferably, the second double-layer steel mesh includes a third steel mesh and a fourth steel mesh respectively arranged on both sides of the inner steel arch frame, the third steel mesh is connected to the outer wall of the inner steel arch frame, and the fourth steel mesh is connected to the inner wall of the inner steel arch frame, and the spacing distance between the third steel mesh and the fourth steel mesh matches the thickness of the inner steel arch frame.

[0031] Preferably, the sand in step S6 is medium-grained sand, and the particle size of the medium-grained sand is set between 0.25 and 0.5 mm.

[0032] Preferably, the overlapping length of the I-beam at the overlapping blind hole is not less than 3m, and the overlapping length of the I-beam at the construction platform is not less than 3m.

[0033] Preferably, the reinforced concrete open hole structure adopts a 60 cm thick reinforced concrete structure.

[0034] Preferably, the mesh size of the first steel mesh and the second steel mesh is set to 5cm×5cm, and the mesh size of the third steel mesh and the fourth steel mesh is set to 10cm×10cm.

[0035] Preferably, the spacing distance between the outer steel arch structure layer and the inner steel arch structure layer is set to 30 cm.

[0036] Compared with the prior art, the present invention has the following beneficial effects:

[0037] The present invention provides a slab collapse construction method for a tunnel karst cave, which comprises the following steps: a construction platform is excavated downwards from an excavated tunnel section near a target tunnel karst cave position, a blind hole row for installing I-beams is drilled on a karst cave wall of the target tunnel karst cave far away from the construction platform by using a drilling device on the construction platform, one end of each I-beam is sequentially pushed into a corresponding overlapping blind hole, the other end of each I-beam is overlapped on the construction platform to form a temporary spanning platform, a protective scaffold consisting of an outer steel arch frame, an inner steel arch frame and an intermediate buffer layer is installed above the temporary spanning platform, a overlapping platform for overlapping reinforced concrete spanning slabs is excavated on a karst cave wall of the target tunnel karst cave far away from the construction platform along a tunnel excavation direction, and a reinforced concrete spanning slab spanning the construction platform and the overlapping platform is constructed by using the temporary spanning platform as a template. The present application can solve the problems of rockfall on the top, water overflow at the bottom, and vertical and smooth cave walls with no construction working surface during tunnel construction, with high safety and construction efficiency; the temporary crossing platform of the present application can also serve as the bottom formwork support of the reinforced concrete span, which can solve the problem that the general formwork cannot withstand the load when pouring thick reinforced concrete span when the bottom is exposed to the air. In addition, the present application also provides a specific design method for the temporary crossing platform and the reinforced concrete span, so that the temporary crossing platform determined can meet the structural requirements and can improve the convenience of construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.

[0039] Figure 1 is a schematic diagram of a flow chart in one embodiment of the present invention;

[0040] Figure 2 It is a schematic diagram of the overall structure of one embodiment of the present invention;

[0041] Figure 3for Figure 2 A is an enlarged schematic diagram;

[0042] Figure 4 It is a schematic diagram of the combined structure of the outer steel arch structure layer, the inner steel arch structure layer and the intermediate buffer layer in one embodiment of the present invention;

[0043] Figure 5 It is a schematic diagram of the structure after the construction platform is excavated in one embodiment of the present invention;

[0044] Figure 6 It is a schematic diagram of the structure after the overlapping blind holes are drilled in one embodiment of the present invention;

[0045] Figure 7 It is a schematic diagram of the structure after the temporary spanning platform is overlapped in one embodiment of the present invention;

[0046] Figure 8 It is a schematic elevation diagram of a complete structure in one embodiment of the present invention;

[0047] Fig. 9 It is a schematic longitudinal section diagram of a complete structure in one embodiment of the present invention.

[0048] The purpose, features and advantages of the present invention will be further described with reference to the accompanying drawings in conjunction with the embodiments.

[0049] Description of Figure Numbers:

[0050] 10. Excavated tunnel section; 20. Target tunnel cave; 210. Overlap blind hole; 220. Construction platform; 230. Overlap platform; 30. Temporary crossing platform; 310. I-beam; 40. Outer steel arch structure layer; 410. Outer steel arch; 420. First double-layer steel mesh; 50. Inner steel arch structure layer; 510. Inner steel arch; 520. Second double-layer steel mesh; 60. Intermediate buffer layer; 70. Reinforced concrete span slab; 80. Reinforced concrete open hole structure; 90. Internal auxiliary structure. DETAILED DESCRIPTION

[0051] It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not used to limit the present invention.

[0052] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0053] It should be noted that all directional indications (such as up, down, left, right, front, back, etc.) in the embodiments of the present invention are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0054] In addition, the descriptions of "right part", "middle part" and the like in the present invention are only for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "right part" and "middle part" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0055] Please see attached Figures 1 to 9 In one embodiment of the present invention, a slab collapse construction method for a tunnel karst cave comprises the following steps:

[0056] S1, excavate a construction platform 220 downwards near the target tunnel cave 20 in the excavated tunnel section 10; wherein, the target tunnel cave 20 is located in front of the excavated tunnel section 10, and the target tunnel cave 20 is vertically developed; it should be noted that in the face of vertically developed tunnel caves, especially vertically developed large caves with a height greater than 10m and a depth greater than 10m, the tunnel will face problems such as rockfall from the top (this section of the tunnel structure will be completely exposed in the huge cavity), water overflow from the bottom, and vertical and smooth cave walls without construction work surfaces during construction. Figure 5 As shown, a construction platform 220 is excavated downwards in the excavated tunnel section 10 near the target tunnel cave 20. The construction platform 220 can be used for temporary construction machinery operations, such as drilling equipment, etc., and can also be used for overlapping the I-beams 310 of the temporary crossing platform 30 described later.

[0057] S2, using a drilling device (not shown) on the construction platform 220 to drill a blind hole row (not shown) for installing the I-beam 310 on the karst cave wall of the target tunnel karst cave 20 away from the construction platform 220; wherein the blind hole row includes a plurality of overlapping blind holes 210 arranged transversely along the tunnel; Figure 6 As shown, a drilling device is used on a construction platform 220 to drill the blind hole row on the opposite side wall of the target tunnel cave 20. Preferably, the drilling device uses a down-the-hole drill, which has precise positioning capabilities and rapid construction capabilities, and can quickly and accurately drill the overlapping blind holes 210.

[0058] S3, push one end of each I-beam 310 into the corresponding overlapping blind hole 210 in turn, overlap the other end of each I-beam 310 on the construction platform 220, and weld and fix two adjacent I-beams 310 through connecting ribs to form a temporary spanning platform 30; drill holes and grooves on the opposite cave wall by using a drilling device, and push a row of I-beams 310 into the opposite overlapping blind holes 210 to form a temporary spanning platform 30. Considering the problem of pouring a large volume of reinforced concrete span slab 70 in a suspended state, the temporary spanning platform 30 of the present application can also serve as the bottom formwork support of the reinforced concrete span slab 70, which can solve the problem that the general formwork cannot withstand the load when pouring the reinforced concrete span slab 70 with a large thickness (for example, 1m) when the bottom is exposed to the air.

[0059] S4, installing a plurality of outer steel arch frames 410 arranged at intervals along the extension direction of the temporary spanning platform 30 above the temporary spanning platform 30, and hanging a first double-layer steel mesh 420 between two adjacent outer steel arch frames 410, and then spraying concrete toward the first double-layer steel mesh 420 to obtain an outer steel arch frame structure layer 40;

[0060] Technical personnel in this field should note that the cavity wall is temporarily stable when not disturbed. However, the falling rocks from the cavity wall caused by the blasting vibration at the front face can easily injure construction workers. Therefore, it is crucial to construct a protective scaffolding inside the cavity before the blasting at the face.

[0061] At present, pipe sheds are usually constructed outside the tunnel contour to form a protective scaffolding. However, constructing a pipe shed inside the tunnel requires expanding a pipe shed room and requires an arc-shaped arrangement of drilling holes. The construction is extremely inconvenient, the drilling positioning is difficult, and the pipe shed protective scaffolding cannot effectively resist the impact of falling rocks.

[0062] In order to avoid workers being injured by falling rocks from the cavity wall during blasting of the tunnel face ahead, and to prevent damage to the subsequent main structure lining caused by falling rocks during operation, the present application needs to construct a protective scaffolding on the temporary crossing platform 30. Specifically, a plurality of outer steel arch frames 410 arranged at intervals along the extension direction of the temporary crossing platform 30 are first installed above the temporary crossing platform 30, and a first double-layer steel mesh 420 is hung between two adjacent outer steel arch frames 410, and then concrete is sprayed toward the first double-layer steel mesh 420 to obtain an outer steel arch structure layer 40, which includes an outer steel arch 410, a first double-layer steel mesh 420 and correspondingly sprayed concrete.

[0063] It should be noted that, in order to effectively adhere the shotcrete, in a preferred embodiment, the first double-layer steel mesh 420 includes a first steel mesh (not shown) and a second steel mesh (not shown) respectively arranged on both sides of the outer steel arch frame 410, the first steel mesh is connected to the outer side wall of the outer steel arch frame 410, the second steel mesh is connected to the inner side wall of the outer steel arch frame 410, and the spacing between the first steel mesh and the second steel mesh matches the thickness of the outer steel arch frame 410. The mesh size of the first steel mesh and the second steel mesh is set to 5cm×5cm. In other embodiments, those skilled in the art can also set the mesh size to a shape or other value, as long as it is convenient for the shotcrete to adhere.

[0064] S5, install multiple inner steel arch frames 510 arranged at intervals along the extension direction of the temporary crossing platform 30 above the temporary crossing platform 30, and hang a second double-layer steel mesh 520 between two adjacent inner steel arch frames 510, reserve a blowing and filling pipe, and then spray concrete toward the second double-layer steel mesh 520 to obtain an inner steel arch frame structure layer 50; the inner steel arch frame structure layer 50 includes an inner steel arch frame 510, a second double-layer steel mesh 520, and corresponding sprayed concrete. The inner steel arch frame 510 is arranged on the inner side of the outer steel arch frame 410, the blowing and filling pipe is connected to the inner steel arch frame 510 through connecting ribs, and the outlet of the blowing and filling pipe faces the outer steel arch frame 410;

[0065] In a preferred embodiment, the second double-layer steel mesh 520 includes a third steel mesh (not shown) and a fourth steel mesh (not shown) respectively arranged on both sides of the inner steel arch frame 510, the third steel mesh is connected to the outer wall of the inner steel arch frame 510, the fourth steel mesh is connected to the inner wall of the inner steel arch frame 510, and the spacing between the third steel mesh and the fourth steel mesh matches the thickness of the inner steel arch frame 510. The mesh size of the third steel mesh and the fourth steel mesh is set to 10cm×10cm. In other embodiments, those skilled in the art can also set the mesh size to a shape or other value, as long as it is convenient for sprayed concrete to adhere.

[0066] In addition, the use of double-layer steel arch frames can also ensure the thickness and density of shotcrete when it is surrounded by air.

[0067] S6, blowing sand into the space between the outer steel arch structure layer 40 and the inner steel arch structure layer 50 through the blowing filling pipe to obtain the intermediate buffer layer 60; it is worth noting that a blowing filling pipe (not shown) is reserved before the inner steel arch 510 is sprayed with concrete, and the blowing filling pipe is fixed to the inner steel arch 510 through the connecting ribs, the outlet of the blowing filling pipe is toward the outer steel arch 410, and the inlet of the blowing filling pipe is toward the inner side of the inner steel arch 510. After the upper and lower arches are sprayed with concrete, in the preferred example In the middle, medium-grained sand is blown into the space between the outer steel arch structure layer 40 and the inner steel arch structure layer 50 through a filling pipe as an intermediate buffer layer 60. The particle size of the medium-grained sand ranges from 0.5 to 0.25 mm. The intermediate buffer layer 60 can unload most of the impact load when the outer steel arch structure layer 40 is impacted by falling rocks, which significantly improves the ability of the protective scaffolding to resist the impact of falling rocks. It can prevent workers from being injured by falling rocks from the cavity wall during construction, and can serve as an arch protection buffer layer during operation to prevent damage to the tunnel structure caused by falling rocks from the cave roof.

[0068] S7, excavating a lap platform 230 for lap connection of reinforced concrete span slab 70 in the lap wall of the target tunnel 20 away from the construction platform 220 along the tunnel excavation direction; Fig. 9 As shown, the overlapping length from the opposite cave wall to the reinforced concrete span slab 70 is excavated for overlapping use of the reinforced concrete span slab 70 .

[0069] S8, using the temporary spanning platform 30 as a template to construct a reinforced concrete spanning plate 70 spanning the construction platform 220 and the overlapping platform 230, and reserving lining structure connecting steel bars (not shown);

[0070] S9, the inner steel arch structure layer 50 is used as a template to sequentially apply a waterproof layer (not shown) and a reinforced concrete open hole structure 80, and then an internal tunnel auxiliary structure 90 is applied. As a preferred example, considering the impact of rockfall in a large cave and the local instability and collapse of the surrounding rock of the cave during the 100-year operation of the tunnel, the reinforced concrete open hole structure 80 adopts a 60cm thick C35 reinforced concrete structure, which can better resist the impact of rockfall and the collapse load of the surrounding rock. The internal tunnel auxiliary structure 90 is a conventional auxiliary structure of the tunnel, such as a pavement layer, a drainage system and other conventional structures, which will not be described here.

[0071] As a preferred implementation, the temporary crossing platform 30 in step S3 is specifically determined by the following steps:

[0072] S31, according to the formula Determine the resultant vertical uniform load on the temporary crossing platform 30 , unit kN; where, is the design value of the deadweight load of the construction machinery, in kN. It is the sum of the deadweight loads of the outer steel arch structure layer 40, the inner steel arch structure layer 50 and the intermediate buffer layer 60, in kN. is the self-weight load of the reinforced concrete span 70, in kN, is the deadweight load of the temporary spanning platform 30, in kN;

[0073] S32, according to the formula Determine the length of the two ends of the temporary spanning platform 30 that need to be overlapped , unit is m; where, is the sum of the lap lengths required at both ends of the temporary spanning platform 30, in kN, and f is the design value of the foundation bearing capacity, in kPa. is the width of the temporary spanning platform 30, in m;

[0074] S33, according to the formula Determine the cross-sectional area required for the temporary spanning platform 30 to resist shear , unit m 2 ;in, is the shear stress of steel, unit is kPa;

[0075] S34, determining the maximum mid-span bending moment of the temporary spanning platform 30 ,unit ;

[0076] S35, according to the formula Determine the section inertia moment I required for the temporary spanning platform 30 to resist bending, in m 4 ;in, is the tensile stress of steel, in kPa, y is the distance from the maximum stress point to the centroid of the section of the temporary spanning platform 30, in m;

[0077] S36, according to the cross-sectional area The cross-sectional size and cross-sectional shape of the temporary spanning platform 30 are determined by the cross-sectional moment of inertia I, thereby determining the model of the I-beam 310 of the temporary spanning platform 30 .

[0078] This embodiment provides a specific design method for a temporary spanning platform 30, which is designed according to the most unfavorable load situation of the temporary spanning platform 30, and the cross-sectional area of ​​the temporary spanning platform 30 required by the above calculation is The cross-sectional moment of inertia I required for the I-beam 310 to resist bending can be used to determine the cross-sectional size and cross-sectional shape of the selected I-beam 310. In a preferred example, according to the cross-sectional size and cross-sectional shape, force calculation is performed to determine that the temporary spanning platform 30 is fully paved with I22b I-beams 310, and the I-beams 310 are welded into a whole through connecting ribs. The two ends of the I-beam 310 are overlapped on the stable bedrock for a length of not less than 3m, and the bedrock needs to provide a foundation bearing capacity of not less than 300kPa. The temporary spanning platform 30 determined in this way can meet the structural requirements.

[0079] As a preferred embodiment, the reinforced concrete span slab 70 in step S8 is specifically determined by the following steps:

[0080] S81, according to the formula Determine the resultant vertical load on the reinforced concrete span 70 , unit kN; where, It is the sum of the deadweight loads of the outer steel arch structure layer 40, the inner steel arch structure layer 50 and the intermediate buffer layer 60, in kN. is the deadweight load of the reinforced concrete open hole structure 80 and the internal auxiliary structure 90, in kN. It is the larger value of the deadweight load of the construction machinery during construction and the vehicle load during operation, in kN. is the self-weight load of the reinforced concrete span 70, in kN;

[0081] S82, according to the formula Determine the sum of the lengths required to overlap the two ends of the reinforced concrete span 70 , unit is m; where, is the width of the reinforced concrete span 70, in m;

[0082] S83, according to the formula Determine the shear force on the reinforced concrete span 70 , unit kN;

[0083] S84, determining the maximum mid-span bending moment value of the reinforced concrete span slab 70 ,unit ;

[0084] S85, according to the formula and formula Determine the minimum cross-sectional thickness of the reinforced concrete span 70 per unit width and the cross-sectional area of ​​the longitudinal tensile reinforcement ;in, is the bending calculation coefficient of the positive section, dimensionless, is the design value of concrete axial compressive strength, unit kPa, b is the width of the unit width reinforced concrete span slab 70, unit m, is the height of the concrete compression zone, in m, is the design value of steel bar tensile strength, unit is kPa;

[0085] S86, according to the minimum section thickness Determine the thickness of the reinforced concrete span 70 according to the cross-sectional area of ​​the longitudinal tensile reinforcement The reinforcement method of the reinforced concrete span slab 70 is determined.

[0086] This embodiment provides a specific design method for a reinforced concrete span slab 70, which is designed according to the most unfavorable load condition of the reinforced concrete span slab 70, and the minimum cross-sectional thickness of the reinforced concrete span slab 70 is Determine the thickness of the reinforced concrete span 70 according to the cross-sectional area of ​​the longitudinal tensile reinforcement Determine the reinforcement method of the reinforced concrete span 70. In a preferred example, after the force calculation and reinforcement calculation of the above formula, it is determined that the thickness of the reinforced concrete span 70 is 1m, the longitudinal tensile reinforcement is Ф28 HRB400 reinforcement with a spacing of 150mm, and the length of the two ends overlapped on the stable bedrock at the edge of the cavity is not less than 3m, and the bedrock needs to provide a foundation bearing capacity of not less than 300kPa.

[0087] As a preferred example, the length of the I-beam 310 overlapped on the overlapping blind hole 210 is not less than 3 m, and the length of the I-beam 310 overlapped on the construction platform 220 is not less than 3 m.

[0088] As a preferred example, the spacing distance between the outer steel arch structure layer 40 and the inner steel arch structure layer 50 is set to 30 cm.

[0089] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A slab collapse construction method for a tunnel karst cave, characterized in that: The following steps are involved: S1, excavating a construction platform downward near the target tunnel cave in the excavated tunnel section; wherein the target tunnel cave is located in front of the excavated tunnel section, and the target tunnel cave is developed vertically; S2, using a drilling device on the construction platform to drill a row of blind holes for installing I-beams on the wall of the target tunnel karst cave away from the construction platform; wherein the row of blind holes includes a plurality of overlapping blind holes arranged transversely along the tunnel; and the drilling device is a down-the-hole drill; S3, sequentially pushing one end of each I-beam into the corresponding overlapping blind hole, overlapping the other end of each I-beam on the construction platform, and welding and fixing two adjacent I-beams through connecting ribs to form a temporary spanning platform; S4, installing a plurality of outer steel arch frames arranged at intervals along the extension direction of the temporary spanning platform above the temporary spanning platform, hanging a first double-layer steel mesh between two adjacent outer steel arch frames, and spraying concrete toward the first double-layer steel mesh to obtain an outer steel arch frame structure layer; S5, installing a plurality of inner steel arch frames arranged at intervals along the extension direction of the temporary spanning platform above the temporary spanning platform, and hanging a second double-layer steel mesh between two adjacent inner steel arch frames, reserving a blowing and filling pipe, and then spraying concrete toward the second double-layer steel mesh to obtain an inner steel arch frame structure layer; wherein the inner steel arch frame is arranged on the inner side of the outer steel arch frame, the blowing and filling pipe is connected to the inner steel arch frame through connecting ribs, and the outlet of the blowing and filling pipe faces the outer steel arch frame; S6, blowing sand into the space between the outer steel arch structure layer and the inner steel arch structure layer through the filling pipe to obtain an intermediate buffer layer; S7, excavating a lap joint platform for lap joint of reinforced concrete span slabs on the karst cave wall of the target tunnel far away from the construction platform along the tunnel excavation direction; S8, using the temporary spanning platform as a template to construct a reinforced concrete spanning slab spanning the construction platform and the overlapping platform, and reserving connecting steel bars for the lining structure; S9, using the inner steel arch structure layer as a template to sequentially construct a waterproof layer and a reinforced concrete open hole structure, and then construct an internal auxiliary structure of the tunnel; The temporary crossing platform in step S3 is specifically determined by the following steps: S31, according to the formula Determine the resultant vertical uniform load on the temporary crossing platform , unit kN; where, is the design value of the deadweight load of the construction machinery, in kN. It is the sum of the self-weight loads of the outer steel arch structure layer, the inner steel arch structure layer and the intermediate buffer layer, in kN. is the self-weight load of the reinforced concrete span slab, in kN, is the deadweight load of the temporary crossing platform, in kN; S32, according to the formula Determine the sum of the lengths required to be overlapped at both ends of the temporary spanning platform , unit is m; where f is the design value of foundation bearing capacity, unit is kPa, is the width of the temporary spanning platform, in m; S33, according to the formula Determine the cross-sectional area required for the temporary spanning platform to resist shear , unit m 2 ;in, is the shear stress of steel, unit is kPa; S34, determining the maximum mid-span bending moment of the temporary spanning platform ,unit ; S35, according to the formula Determine the section inertia moment I required for the temporary spanning platform to resist bending, in m 4 ;in, is the tensile stress of steel, in kPa, y is the distance from the maximum stress point to the centroid of the temporary spanning platform, in m; S36, according to the cross-sectional area and the moment of inertia I of the section to determine the cross-sectional size and cross-sectional shape of the temporary spanning platform, thereby determining the model of the I-beam of the temporary spanning platform; The reinforced concrete span slab in step S8 is specifically determined by the following steps: S81, according to the formula Determine the resultant vertical load on the reinforced concrete span , unit kN; where, It is the sum of the self-weight loads of the outer steel arch structure layer, the inner steel arch structure layer and the intermediate buffer layer, in kN. is the self-weight load of the reinforced concrete open hole structure and its internal auxiliary structures, in kN. It is the larger value of the deadweight load of the construction machinery during construction and the vehicle load during operation, in kN. is the self-weight load of the reinforced concrete span slab, in kN; S82, according to the formula Determine the sum of the required overlap lengths at both ends of the reinforced concrete span , unit is m; where, is the width of the reinforced concrete slab, in m; S83, according to the formula Determine the shear force on the reinforced concrete slab , unit kN; S84, determining the maximum bending moment value at the mid-span of the reinforced concrete span slab ,unit ; S85, according to the formula and formula Determine the minimum cross-sectional thickness of reinforced concrete slab per unit width and the cross-sectional area of ​​the longitudinal tensile reinforcement ;in, is the bending calculation coefficient of the positive section, dimensionless, is the design value of concrete axial compressive strength, unit is kPa, b is the width of the unit width reinforced concrete span, unit is m, is the height of the concrete compression zone, in m, is the design value of steel bar tensile strength, unit is kPa; S86, according to the minimum section thickness Determine the thickness of the reinforced concrete span slab according to the cross-sectional area of ​​the longitudinal tensile reinforcement Determine the reinforcement method of the reinforced concrete span slab.

2. The slab collapse construction method of a tunnel karst cave according to claim 1, characterized in that: The first double-layer steel mesh includes a first steel mesh and a second steel mesh respectively arranged on both sides of the outer steel arch frame, the first steel mesh is connected to the outer wall of the outer steel arch frame, and the second steel mesh is connected to the inner wall of the outer steel arch frame, and the spacing distance between the first steel mesh and the second steel mesh matches the thickness of the outer steel arch frame.

3. The slab collapse construction method of a tunnel karst cave according to claim 2, characterized in that: The second double-layer steel mesh includes a third steel mesh and a fourth steel mesh respectively arranged on both sides of the inner steel arch frame, the third steel mesh is connected to the outer wall of the inner steel arch frame, and the fourth steel mesh is connected to the inner wall of the inner steel arch frame. The spacing distance between the third steel mesh and the fourth steel mesh matches the thickness of the inner steel arch frame.

4. The slab collapse construction method of a tunnel karst cave according to claim 3 is characterized in that: The sand in step S6 is medium-grained sand, and the particle size of the medium-grained sand is set between 0.25 and 0.5 mm.

5. The slab collapse construction method of a tunnel karst cave according to claim 3, characterized in that: The overlapping length of the I-beam at the overlapping blind hole is not less than 3m, and the overlapping length of the I-beam at the construction platform is not less than 3m.

6. The slab collapse construction method of a tunnel karst cave according to claim 1, characterized in that: The reinforced concrete open hole structure adopts a 60cm thick reinforced concrete structure.

7. The slab collapse construction method of a tunnel karst cave according to claim 3, characterized in that: The mesh size of the third steel mesh and the fourth steel mesh is set to 10 cm×10 cm.

8. The slab collapse construction method of a tunnel karst cave according to claim 1, characterized in that: The spacing distance between the outer steel arch structure layer and the inner steel arch structure layer is set to 30 cm.