A construction technology of drainage ditch connected with floor
By opening a V-shaped groove at the connection between the drainage ditch and the cement floor and injecting flexible caulking agent and protective structural adhesive, the problem of the gap becoming larger was solved and the flatness of the ground and the service life of the drainage ditch were ensured.
Patent Information
- Application Number
- CN202410988353.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-23
AI Technical Summary
The gap between the traditional drainage ditch and the cement floor gradually becomes larger, causing water seepage accidents and affecting the flatness of the ground and the service life of the drainage ditch.
Create a V-shaped groove at the connection between the drainage ditch and the cement floor, inject flexible caulking agent and add protective structural glue to avoid direct contact and ensure the stability and sealing of the gap.
It can effectively prevent gaps from getting larger, ensure the overall smoothness of the road surface, extend the service life of drainage ditches, and improve construction reliability.
Smart Images

Figure CN118531886B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a construction process of a drainage ditch connected to a floor. Background Art
[0002] Floor refers to the surface of the ground, usually refers to the ground after special treatment or laying of special materials. Floor can be used in various places, such as factories and warehouses. In road construction, joint usually refers to the connection between parts of different materials or structures. Drain refers to the linear drainage facility used for drainage, which is usually set up according to the use function and production process needs. It is used to collect and remove road surface water such as sewage and wastewater to keep the ground dry and safe. The drainage ditch jointed with the floor refers to the part where the drainage ditch is connected to the floor, which is usually used to provide effective drainage and sealing between the indoor floor and the drainage ditch.
[0003] The construction process includes several steps: cleaning and leveling the construction site to ensure the cleanliness and levelness of the construction area; marking and measuring the junction of the floor and the drainage ditch to determine the position and size of the drainage ditch; excavating the position of the drainage ditch to ensure that there is enough space and slope at the junction of the drainage ditch and the floor for smooth drainage. The excavation work needs to ensure the safety and cleanliness of the construction site; installing the drainage ditch to ensure that the junction of the drainage ditch and the floor is dense and firm; treating the joints at the junction of the drainage ditch and the floor to ensure that the joints are flat and firm to prevent water seepage and loosening.
[0004] However, in the process of implementing the embodiments of the present invention, the inventors found that there are at least the following defects in the background technology: the traditional drainage ditch is a stainless steel structure embedded in the cement floor. Vehicles transporting goods often pass through factories and warehouses. When the heavier vehicles roll over the floor, the drainage ditch and the cement floor will collide with each other. This state for a long time causes the gap between the two to gradually become larger, thereby causing gaps in the ground to cause water seepage accidents. For some indoor venues with high hygiene requirements, water seepage will breed bacteria and cause production safety risks, while also affecting the overall flatness of the road surface and aggravating the reduction in the service life of the drainage ditch. Therefore, we propose a drainage ditch construction process connected to the floor to solve this problem. Summary of the invention
[0005] The purpose of the present invention is to solve the problems raised in the above background technology and to propose a drainage ditch construction process connected with the floor.
[0006] In order to achieve the above object, the present invention adopts the following technical solutions:
[0007] A construction process for a drainage ditch connected to a floor comprises the following steps:
[0008] Step 1: First, use cleaning tools to thoroughly clean the ground to ensure that the ground is flat, free of debris and dust. After cleaning, use a detergent to treat the ground to ensure that the ground is clean and oil-free. Use a mixer to fully mix cement and water to ensure that the texture of the cement is uniform. Then use cement pouring tools to evenly pour cement on both sides of the drainage ditch to ensure the flatness and fullness of the cement pavement. After pouring, it is necessary to maintain the cement surface to keep it moist to avoid cracks and shrinkage while facilitating subsequent grooving operations;
[0009] Step 2: After pouring and before the cement is completely solidified, make a V-shaped groove on the floor to ensure that the depth and width of the groove meet the design requirements. After the groove is made, it is necessary to use a cleaning tool to clean the debris and debris in the V-shaped groove. This can ensure that the slope of the V-shaped groove is flat and ready for filling with flexible objects;
[0010] Step 3: Inject the flexible caulking agent into the V-shaped groove. The temperature and pressure of the flexible caulking agent need to be monitored to ensure that it meets the production requirements. The injection of the flexible caulking agent should start from one end of the V-shaped groove and gradually move to the other end to ensure that the flexible caulking agent fills the entire V-shaped groove and avoids the generation of bubbles during the filling process. Fill the flexible caulking agent so that its height is 2 cm from the cement floor.
[0011] Step 4: Professional workers will use a scraper to flatten the top of the flexible caulking agent until the cured Shore hardness of the flexible caulking agent is 60-70, and fill the top of the flexible caulking agent with protective structural glue to ensure that the protective structural glue is flush with the ground.
[0012] Preferably, a plurality of circular grooves are formed on the inclined surface of the V-shaped groove, and the plurality of circular grooves are arranged in multiple rows and columns. An arc groove is formed on the inner wall of the circular groove, and the circular groove is formed by a groove forming tool.
[0013] Preferably, the flexible sealant comprises polyurethane resin, solvent, functional additive, filler and other additives, and the weight proportions of the flexible sealant are 45 parts of polyurethane resin, 25 parts of solvent, 10 parts of functional additive, 18 parts of filler and 2 parts of other additives.
[0014] Preferably, the functional additives include a dispersant, a thickener and a desiccant, the filler includes silicon dioxide solid particles and aluminum oxide solid particles, and the other additives include a preservative and an antioxidant.
[0015] Preferably, the method for obtaining the flexible caulking agent comprises:
[0016] S1: First, the polyurethane resin is dissolved by a stirring device and a heating device, and the dissolution temperature and time are controlled to ensure that the polyurethane resin can be completely dissolved and to avoid decomposition caused by excessive heating;
[0017] S2: Add the functional additives gradually to avoid adding too much at one time, and control the adding speed and stirring time to ensure that the functional additives can be fully dispersed and dissolved;
[0018] S3: Add filler to ensure that the filler can be evenly dispersed in the solution to avoid agglomeration;
[0019] S4: Add solvent by precise metering, adjust viscosity by gradual addition and stirring to ensure that the viscosity of the product meets the requirements.
[0020] Preferably, the material of the protective structural adhesive is usually epoxy resin structural adhesive, and the epoxy resin structural adhesive includes epoxy resin, curing agent, filler and reinforcing agent.
[0021] Preferably, the filler includes silicon dioxide solid particles and aluminum powder, and the reinforcing agent includes a leveling agent, a modifier and a diluent.
[0022] Preferably, the grooving tool comprises a rotating shaft, a plurality of round rods are fixedly mounted on the outer side of the rotating shaft, an extension shaft is fixedly mounted on the top end of the rotating shaft, and a rotating handle is fixedly sleeved on the outer side of the extension shaft.
[0023] The beneficial effects of the present invention are:
[0024] The structural design of the present invention is reasonable. A V-shaped groove is opened at the connection between the drainage ditch and the cement floor, and a flexible filler is added into the V-shaped groove to avoid direct contact between the drainage ditch body and the cement, reduce the mutual collision between the drainage ditch body and the cement floor, prevent the gap between the two from gradually increasing, ensure the overall flatness of the road surface, improve the service life of the drainage ditch, and have high reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a structural schematic diagram of a drainage ditch construction process connected to the floor proposed by the present invention;
[0026] Figure 2 for Figure 1 A partial enlarged view of part A;
[0027] Figure 3 The present invention is a schematic structural diagram of a grooving tool for a drainage ditch construction process connected to a floor.
[0028] In the figure: 1. Drainage ditch body; 2. Cement floor; 3. Flexible caulking agent; 4. Protective structural adhesive; 5. Circular groove; 6. Arc groove; 7. Rotating shaft; 8. Round rod; 9. Rotating handle. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0030] Reference Figure 1-3 , a drainage ditch construction process connected to the floor, comprising the following steps:
[0031] Step 1: First, use cleaning tools to thoroughly clean the ground to ensure that the ground is flat, free of debris and dust. After cleaning, use a detergent to treat the ground to ensure that the ground is clean and oil-free. Use a mixer to fully mix cement and water to ensure that the texture of the cement is uniform. Then use cement pouring tools to evenly pour cement on both sides of the drainage ditch to ensure the flatness and fullness of the cement pavement. After pouring, it is necessary to maintain the cement surface to keep it moist to avoid cracks and shrinkage while facilitating subsequent grooving operations;
[0032] Step 2: After pouring and before the cement is completely solidified, make a V-shaped groove on the floor to ensure that the depth and width of the groove meet the design requirements. After the groove is made, it is necessary to use a cleaning tool to clean the debris and debris in the V-shaped groove. This can ensure that the slope of the V-shaped groove is flat and ready for filling with flexible objects;
[0033] It should be noted that the material of the drainage ditch body 1 can be set to stainless steel, resin and metal. Stainless steel has excellent corrosion resistance and wear resistance, and has good pressure resistance and high temperature resistance, and is suitable for industrial plants, chemical plants, food processing plants and other environments; resin drainage ditches have the advantages of light weight, easy processing, non-conductive, and rust-proof, and are suitable for chemical plants, laboratories, pharmaceutical plants and other places with strong corrosion; metal drainage ditches are usually made of galvanized steel plates, aluminum alloys and other materials. Metal drainage ditches have high strength, durability and stability, and are suitable for parking lots, warehouses and other places;
[0034] It is further explained that both sides of the top of the gutter body 1 are U-shaped, and the U-shaped edge of the gutter body 1 fits tightly against the floor, and the U-shaped edge extends into the V-shaped groove, ensuring that the gutter body 1 can be firmly grasped on the floor, thereby improving the stability of the installation of the gutter body 1.
[0035] Step 3: Inject the flexible caulking agent into the V-shaped groove. The temperature and pressure of the flexible caulking agent need to be monitored to ensure that it meets the production requirements. The injection of the flexible caulking agent should start from one end of the V-shaped groove and gradually move to the other end to ensure that the flexible caulking agent fills the entire V-shaped groove and avoids the generation of bubbles during the filling process. Fill the flexible caulking agent so that its height is 2 cm from the cement floor.
[0036] It should be noted that a thermometer is installed at the outlet of the flexible sealant injection equipment or near the flexible sealant pipeline to monitor the temperature of the flexible sealant, and a pressure sensor is installed on the flexible sealant injection equipment or the flexible sealant pipeline. The pressure data of the flexible sealant is collected by the sensor, and the pressure of the flexible sealant is monitored in real time. By monitoring the temperature and pressure of the flexible sealant, the parameters of the injection equipment can be adjusted in time to ensure the quality and construction effect of the flexible sealant.
[0037] Step 4: Professional workers will use a scraper to flatten the top of the flexible caulking agent until the cured Shore hardness of the flexible caulking agent is 60-70, and fill the top of the flexible caulking agent with protective structural glue to ensure that the protective structural glue is flush with the ground.
[0038] It should be noted that the flexible caulking agent needs a certain amount of time to cure after construction to ensure that the flexible caulking agent can fully solidify and bond. If the epoxy resin protective glue is applied before the flexible caulking agent is completely cured, it may affect the curing process of the flexible caulking agent, resulting in the flexible caulking agent failing to fully enter the circular groove and the annular groove, thereby reducing the adhesion of the flexible caulking agent to the V-shaped groove. After the flexible caulking agent is cured, the application of epoxy resin protective glue can better adhere to the surface of the flexible caulking agent, improve the adhesion and stability of the coating, thereby increasing the protective effect of the caulking, and thus ensuring the quality and durability of the overall construction.
[0039] In a specific embodiment of the present scheme, a plurality of circular grooves are formed on the inclined surface of the V-shaped groove, the plurality of circular grooves are arranged in multiple rows and columns, an arc groove is formed on the inner wall of the circular groove, and the circular groove is formed by a groove forming tool.
[0040] It should be noted that, in the specific construction process, workers hold the grooving tool and insert the shaft part into the inclined surface of the V-shaped groove. After inserting to a certain depth, they rotate it to a certain angle, then reverse it to a certain angle to return to the insertion angle, and then pull the shaft part out of the V-shaped groove, thereby forming a circular groove. A plurality of arc grooves extend on the inner wall of the circular groove. When the flexible caulking agent is filled into the circular groove and the arc groove, the stability of the connection between the flexible caulking agent and the V-shaped groove is improved.
[0041] In a specific embodiment of the present scheme, a flexible filler includes a polyurethane resin, a solvent, a functional additive, a filler and other additives. The weight proportions of the flexible filler are 45 parts of the polyurethane resin, 25 parts of the solvent, 10 parts of the functional additive, 18 parts of the filler and 2 parts of the other additives.
[0042] Specifically, the functional additives include dispersants, thickeners and desiccants, the fillers include silicon dioxide solid particles and aluminum oxide solid particles, and other additives include preservatives and antioxidants.
[0043] It should be noted that the proportion of polyurethane resin is relatively high because it is the main component of the flexible sealant and is responsible for providing flexibility and adhesion properties. The proportion of solvent is relatively high, which can help the polyurethane resin maintain fluidity during preparation and complete volatilization after curing, so that the flexible sealant can achieve flexibility. Functional additives are used to adjust the rheological properties and other properties of the flexible sealant. Fillers are used to increase the volume of the flexible sealant and improve its mechanical properties. Other additives may be used to adjust the specific properties of the flexible sealant, such as anti-aging properties, weather resistance, etc.
[0044] It is further explained that the dispersant is used to disperse fillers and other additives to ensure that they are evenly distributed in the flexible sealant, the thickener is used to adjust the viscosity and rheological properties of the flexible sealant to ensure that the flexible sealant is easy to construct and apply, the desiccant helps the flexible sealant to dry quickly during the curing process and speeds up the construction speed, the silica solid particles and the alumina solid particles are used as fillers to increase the volume of the flexible sealant and improve its mechanical properties, the preservative is used to prevent the flexible sealant from being invaded by microorganisms during storage and use and extend its service life, and the antioxidant is used to improve the aging resistance of the flexible sealant and delay its oxidation and degradation process.
[0045] Specifically, the method for obtaining the flexible sealant includes:
[0046] S1: First, the polyurethane resin is dissolved by a stirring device and a heating device, and the dissolution temperature and time are controlled to ensure that the polyurethane resin can be completely dissolved and to avoid decomposition caused by excessive heating;
[0047] S2: Add the functional additives gradually to avoid adding too much at one time, and control the adding speed and stirring time to ensure that the functional additives can be fully dispersed and dissolved;
[0048] S3: Add filler to ensure that the filler can be evenly dispersed in the solution to avoid agglomeration;
[0049] S4: Add solvent by precise metering, adjust viscosity by gradual addition and stirring to ensure that the viscosity of the product meets the requirements.
[0050] It should also be noted that there are environmental requirements when using flexible sealants. The construction and curing temperature of polyurethane sealants is generally between 5°C and 40°C. Make sure to carry out construction within this temperature range to ensure that the sealant can cure normally. If the temperature is too low, it will affect the fluidity and curing speed of the sealant. If the temperature is too high, the sealant may cure too quickly, affecting the construction effect. The relative humidity should generally be controlled between 40% and 70%. Too high humidity may affect the curing speed and curing effect of the sealant, and too low humidity may cause uneven curing of the sealant.
[0051] Furthermore, the best curing temperature of the caulking agent is generally between 20°C and 25°C, and the best curing humidity is generally between 50% and 60%. Within this temperature and humidity range, the curing speed and curing effect of the caulking agent are the best. Within 24 hours after construction, the caulking area should be avoided from external interference to ensure that the caulking agent can be fully cured.
[0052] In a specific embodiment of the present solution, the material of the protective structural adhesive is usually epoxy resin structural adhesive, and the epoxy resin structural adhesive includes epoxy resin, curing agent, filler and reinforcing agent.
[0053] Specifically, the filler includes silicon dioxide solid particles and aluminum powder, and the reinforcing agent includes a leveling agent, a modifier and a diluent.
[0054] It should be noted that epoxy resin structural adhesive has excellent chemical resistance, can resist the erosion of chemical substances such as acids, alkalis, and solvents, and protect the caulking parts from the influence of the external environment; epoxy resin structural adhesive has good heat resistance, can maintain stability in high temperature environment, is not easy to soften or deform, and protects the caulking parts from the influence of high temperature; epoxy resin structural adhesive has good weather resistance, can resist the influence of environmental factors such as ultraviolet rays, oxygen, and moisture, and protects the caulking parts from damage by ultraviolet rays, oxidation and other factors; epoxy resin structural adhesive has high wear resistance, can resist external physical friction and impact, and protects the caulking parts from wear; epoxy resin structural adhesive has good aging resistance, is not easy to decompose, crack and other phenomena, and protects the caulking parts to maintain good performance for a long time; epoxy resin structural adhesive has good adhesion performance, can firmly adhere to the caulking surface to form a solid protective layer.
[0055] In a specific embodiment of the present scheme, a slotting tool includes a rotating shaft, a plurality of round rods are fixedly mounted on the outer side of the rotating shaft, an extension shaft is fixedly mounted on the top end of the rotating shaft, and a rotating handle is fixedly sleeved on the outer side of the extension shaft.
[0056] In the description of the present invention, it is necessary to understand that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0057] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0058] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, an electrical connection, or a communication; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0059] The preferred embodiments of the present invention disclosed above are only used to help illustrate the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. A drainage ditch construction process connected to the floor. It is characterized in that The following steps are involved: Step 1: First, use cleaning tools to thoroughly clean the ground to ensure that the ground is flat, free of debris and dust. After cleaning, use a detergent to treat the ground to ensure that the ground is clean and oil-free. Use a mixer to fully mix cement and water to ensure that the texture of the cement is uniform. Then use cement pouring tools to evenly pour cement on both sides of the drainage ditch to ensure the flatness and fullness of the cement pavement. After pouring, it is necessary to maintain the cement surface to keep it moist to avoid cracks and shrinkage while facilitating subsequent grooving operations; Step 2: After pouring and before the cement is completely solidified, make a V-shaped groove on the floor to ensure that the depth and width of the groove meet the design requirements. After the groove is made, it is necessary to use a cleaning tool to clean the debris and debris in the V-shaped groove. This can ensure that the slope of the V-shaped groove is flat and ready for filling with flexible objects; Step 3: Inject the flexible caulking agent into the V-shaped groove. The temperature and pressure of the flexible caulking agent need to be monitored to ensure that it meets the production requirements. The injection of the flexible caulking agent should start from one end of the V-shaped groove and gradually move to the other end to ensure that the flexible caulking agent fills the entire V-shaped groove and avoids the generation of bubbles during the filling process. Fill the flexible caulking agent so that its height is 2 cm from the cement floor. Step 4: Professional workers will use a scraper to flatten the top of the flexible caulking agent until the cured Shore hardness of the flexible caulking agent is 60-70, and fill the top of the flexible caulking agent with protective structural glue to ensure that the protective structural glue is flush with the ground.
2. A drainage ditch construction process connected to the floor according to claim 1, It is characterized in that A plurality of circular grooves are formed on the inclined surface of the V-shaped groove, and the plurality of circular grooves are arranged in multiple rows and columns. An arc groove is formed on the inner wall of the circular groove, and the circular groove is formed by a groove forming tool.
3. A construction process for drainage ditch connected to the floor according to claim 1, It is characterized in that The flexible sealant comprises polyurethane resin, solvent, functional additive, filler and other additives. The weight proportions of the flexible sealant are 45 parts of polyurethane resin, 25 parts of solvent, 10 parts of functional additive, 18 parts of filler and 2 parts of other additives.
4. A construction process for drainage ditch connected to the floor according to claim 3, It is characterized in that The functional additives include dispersants, thickeners and desiccants, the fillers include silicon dioxide solid particles and aluminum oxide solid particles, and the other additives include preservatives and antioxidants.
5. A construction process for drainage ditch connected to the floor according to claim 3, It is characterized in that Ways to obtain flexible caulk include: S1: First, the polyurethane resin is dissolved by a stirring device and a heating device, and the dissolution temperature and time are controlled to ensure that the polyurethane resin can be completely dissolved and to avoid decomposition caused by excessive heating; S2: Add the functional additives gradually to avoid adding too much at one time, and control the adding speed and stirring time to ensure that the functional additives can be fully dispersed and dissolved; S3: Add filler to ensure that the filler can be evenly dispersed in the solution to avoid agglomeration; S4: Add solvent by precise metering, adjust viscosity by gradual addition and stirring to ensure that the viscosity of the product meets the requirements.
6. A construction process for drainage ditch connected to the floor according to claim 1, It is characterized in that The material of the protective structural adhesive is epoxy resin structural adhesive, and the epoxy resin structural adhesive includes epoxy resin, curing agent, filler and reinforcing agent.
7. A construction process for drainage ditch connected to the floor according to claim 6, It is characterized in that The filler includes silicon dioxide solid particles and aluminum powder, and the reinforcing agent includes a leveling agent, a modifier and a diluent.
8. A construction process for drainage ditch connected to the floor according to claim 2, It is characterized in that The slotting tool comprises a rotating shaft, a plurality of round rods are fixedly mounted on the outer side of the rotating shaft, an extension shaft is fixedly mounted on the top end of the rotating shaft, and a rotating handle is fixedly sleeved on the outer side of the extension shaft.