A construction design progress supervision system based on big data computing
Through the construction design progress supervision system based on big data calculation, combined with meteorological conditions and material supply factors, the problem of insufficient progress prediction reliability and action guidance in the existing technology is solved, achieving more accurate progress prediction and risk management, ensuring The project was completed on time and with quality.
Patent Information
- Application Number
- CN202411028215.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-30
AI Technical Summary
The existing construction design progress monitoring system ignores meteorological conditions and material supply factors when predicting construction progress, resulting in a lack of reliability and accuracy in prediction results, a lack of clear follow-up action guidance, and the inability to adjust project plans in a timely manner.
Design an architectural design progress supervision system based on big data computing, including a construction project information acquisition module, a current construction stage confirmation module, a predicted completion date analysis module, a progress supervision instruction issuance module, a delay risk reminder module and a rectification demand judgment module. Combine meteorological conditions, construction rate and material supply factors to predict progress, and generate delay risk reminders and rework risk assessments.
By more comprehensively reflecting the progress of construction projects, the accuracy and reliability of forecast results are improved, the level of refinement of project management is enhanced, the project is ensured to be completed on time and with quality, and potential defects are discovered in a timely manner to avoid rework.
Smart Images

Figure CN118552164B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of architectural design progress supervision, and specifically is an architectural design progress supervision system based on big data calculation. Background Art
[0002] With the rapid development of science and technology and the increasing prosperity of the construction industry, the complexity and scale of architectural design projects are constantly increasing. Effective supervision of design progress has become a key factor in ensuring on-time project delivery, controlling costs, and improving quality. Traditional progress supervision methods often rely on manual records and audits, which have problems such as information lag, high error rate, and low efficiency. Therefore, the development of an architectural design progress supervision system has become an inevitable trend in the development of the industry.
[0003] The Chinese patent number is CN2022108808232, which is an invention patent application for a building design progress supervision system based on BIM technology. By collecting and classifying the relevant data of the building design, the average value of the building design is further calculated for various types of building design data, and the average value of the building design is combined with the relevant data of the currently supervised building design for correlation processing, so as to calculate the ratio of the average value to the current data and perform evaluation conversion, and convert various types of data into evaluation values, thereby increasing the intuitiveness of the building progress evaluation, increasing the accuracy of data analysis, saving time and improving work efficiency. However, there are still some shortcomings, which are specifically manifested in the following aspects: First, the scheme mainly relies on construction time data for the progress assessment of construction projects to predict the final progress completion, and ignores the influence of meteorological conditions and material supply factors on the progress of construction. It is not enough to fully reflect the true status and potential risks of the construction project, resulting in a lack of certain reliability and accuracy in the prediction results of the construction project progress.
[0004] 2. After the project progress forecast signal was transmitted to the safety warning unit, the plan failed to provide clear follow-up action guidance or instruction measures. On the one hand, it ignored the consideration of the risk of subsequent rework when the progress was barely qualified or exceeded the target. On the other hand, it failed to further analyze and indicate the specific risk factors and their extent that affect the progress when the progress was insufficient. Even if it was found that the progress was exceeded, barely qualified or insufficient, it meant that the relevant managers lacked specific response strategies and action plans, and were unable to adjust the project implementation plan in a timely and effective manner, which might lead to missing the best time to correct the deviation. Summary of the invention
[0005] In order to overcome the shortcomings of the background technology, an embodiment of the present invention provides a building design progress monitoring system based on big data calculation, which can effectively solve the problems involved in the above-mentioned background technology.
[0006] The purpose of the present invention can be achieved through the following technical solutions: a construction design progress supervision system based on big data calculation, including: a construction project information acquisition module, a current construction stage confirmation module, a predicted completion date analysis module, a progress supervision instruction issuance module, a delay risk warning module, a rectification demand judgment module and a cloud database.
[0007] The construction project information acquisition module is connected to the current construction stage confirmation module, the current construction stage confirmation module is connected to the predicted completion date analysis module, the predicted completion date analysis module is connected to the progress supervision instruction issuance module, the progress supervision instruction issuance module is respectively connected to the delay risk warning module and the rectification demand judgment module, and the cloud database is connected to the predicted completion date analysis module.
[0008] The construction project information acquisition module is used to obtain the basic planning information of each construction stage of the target construction project, including the design model, the planned completion date, the type of construction materials used and their corresponding planned usage.
[0009] The current construction stage confirmation module is used to collect all-round images of the construction site of the target building project on the preset monitoring day, create a current construction scene model of the target building project, compare it with the design models of each construction stage of the target building project, and confirm the current construction stage of the target building project.
[0010] The predicted completion date analysis module is used to screen various historical reference building projects for the target building project, and analyze the predicted completion date of the target building project's current construction stage based on the progress data of the historical reference building projects corresponding to the target building project's current construction stage.
[0011] The progress supervision instruction issuance module is used to compare the predicted completion date with the planned completion date, and issue progress supervision instructions for the current construction stage of the target construction project. The progress supervision instruction is an expected delay instruction or an expected on-time instruction. If the progress supervision instruction is an expected delay instruction, the delay risk warning module is executed, otherwise the rectification demand judgment module is executed.
[0012] The delay risk warning module is used to screen the delay risk factors and their corresponding risk levels of the current construction stage of the target building project, and generate a delay risk warning window for the current construction stage of the target building project for feedback.
[0013] The rectification demand judgment module is used to perform a virtual quality inspection on the current construction scene model of the target building project, evaluate the risk level of rework in the current construction stage of the target building project, and judge whether there is any rectification demand for the current construction scene model of the target building project, and provide feedback on the judgment result.
[0014] The cloud database is used to store construction record documents of various historical building projects and store meteorological parameters suitable for construction projects.
[0015] Compared with the prior art, the embodiments of the present invention have at least the following advantages or beneficial effects: (1) The present invention uses the progress data of each historical reference construction project of the target construction project as the starting point, and combines meteorological conditions, construction rate and material supply dimensions to develop a progress forecast for the current construction stage of the target construction project, thereby helping to more comprehensively reflect the actual progress of the construction project and reduce the risk of prediction deviation caused by ignoring a key factor, thereby ensuring the accuracy and reliability of the construction progress forecast results.
[0016] (2) The present invention conducts a delay risk factor exploration when the target construction project is currently in a construction phase and the progress is expected to be delayed, and generates a delay risk warning window for the target construction project's current construction phase for feedback, thereby helping to significantly improve the level of refinement of project management, thereby enhancing the project's risk resistance and ensuring that the project is completed on time and with quality.
[0017] (3) The present invention conducts a rework risk assessment when the target building project is currently in the construction stage and the estimated progress is on schedule, determines whether there is a need for rectification in the current construction scene model of the target building project and provides feedback, and can promptly discover potential construction defects or non-compliance with specifications, thereby avoiding subsequent rework operations and effectively saving time and costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The present invention is further described using the accompanying drawings, but the embodiments in the accompanying drawings do not constitute any limitation to the present invention. A person skilled in the art can obtain other drawings based on the following drawings without creative work.
[0019] Figure 1 It is a schematic diagram of module connection of the present invention. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0021] Reference Figure 1 As shown, the present invention provides a construction design progress supervision system based on big data calculation, including: a construction project information acquisition module, a current construction stage confirmation module, a predicted completion date analysis module, a progress supervision instruction issuance module, a delay risk warning module, a rectification demand judgment module and a cloud database.
[0022] The construction project information acquisition module is connected to the current construction stage confirmation module, the current construction stage confirmation module is connected to the predicted completion date analysis module, the predicted completion date analysis module is connected to the progress supervision instruction issuance module, the progress supervision instruction issuance module is respectively connected to the delay risk warning module and the rectification demand judgment module, and the cloud database is connected to the predicted completion date analysis module.
[0023] The construction project information acquisition module is used to obtain basic planning information of each construction stage of the target construction project, including design model, planned construction days, planned completion date, construction material usage types and their corresponding planned usage amounts.
[0024] It should be noted that the basic planning information for each construction stage of the above-mentioned target building project can be extracted from the construction planning plan formulated by the target building project management team.
[0025] The current construction stage confirmation module is used to collect all-round images of the construction site of the target building project on a preset monitoring day, create a current construction scene model of the target building project, compare it with the design models of each construction stage of the target building project, and confirm the current construction stage of the target building project.
[0026] Specifically, the confirmation of the current construction stage of the target building project includes: importing the current construction scene model of the target building project and the design models of its various construction stages into the model software for overlap comparison, and obtaining the matching degree between the design models of each construction stage of the target building project and the current construction scene model.
[0027] It should be noted that the process of obtaining the matching degree between the design model of each construction stage of the target building project and the current construction scene model is as follows: respectively obtain the overlapping volume of the design model of each construction stage of the target building project and the current construction scene model and its own model volume, and take the ratio of the two as the matching degree between the design model of each construction stage of the target building project and the current construction scene model.
[0028] Each construction stage is numbered according to the construction sequence. If the matching degree between the design model of a certain construction stage of the target building project and the current construction scene model is less than the preset matching degree threshold, and the matching degree between the design model of the previous construction stage and the current construction scene model is greater than or equal to the preset matching degree threshold, then the construction stage is confirmed to be the current construction stage of the target building project.
[0029] The predicted completion date analysis module is used to screen various historical reference building projects for the target building project, and analyze the predicted completion date of the target building project's current construction stage based on the progress data of the historical reference building projects corresponding to the target building project's current construction stage.
[0030] Specifically, the method of screening various historical reference building projects for the target building project includes: extracting construction record documents of various historical building projects stored in a cloud database, and screening out various historical building projects that have high similarity with the target building project in terms of construction phase division, construction material supply, and construction structure design according to the construction phase planning content, construction material list content, and construction structure design drawings in the construction record documents as the historical reference building projects for the target building project.
[0031] It should be noted that the screening process of the above-mentioned historical building projects that have high similarity with the target building project in terms of construction phase division, construction material supply, and construction structure design is as follows: compare the planned construction phases and their construction days in the construction phase planning content of each historical building project with the planned construction days of each construction phase of the target building project. If the construction phase division of a certain historical building project is consistent with the construction phase division of the target building project, that is, the construction phases are the same, then the construction deviation days for each construction phase of the historical building project and the target building project are obtained, and the construction deviation days are accumulated and then inverted to obtain the similarity between the historical building project and the target building project in terms of the construction phase division. It is particularly noted that in the process of inverting the denominator, a preset constant is added to exclude the case where the denominator is 0. If the construction phase division of a certain historical building project is inconsistent with the construction phase division of the target building project, the similarity between the historical building project and the target building project in terms of the construction phase division is automatically set to 0, thereby obtaining the similarity between the historical building project and the target building project in terms of the construction phase division, and selecting the historical building projects whose similarity is greater than the preset similarity threshold, and assigning them labels with high similarity to the construction phase division of the target building project.
[0032] The contents of the construction material lists of each historical building project are sorted out to obtain the types of construction materials used in each construction stage of each historical building project and their actual usage, and compared with the types of construction materials used in each construction stage of the target building project and their corresponding planned usage. Taking the deviation in the use of construction materials for each construction stage between the historical building project and the target building project as the starting point, the similarity of the construction material supply between the historical building project and the target building project is obtained in accordance with the similarity analysis process of the above-mentioned historical building projects and the target building project based on the division of construction stages, and the historical building projects with similarities greater than the preset similarity threshold are selected, and labels with high similarity in construction material supply with the target building project are assigned.
[0033] The construction structure design drawings of each historical building project are modeled, and the structural design models of each construction stage of each historical building project are obtained, which are compared with the design models of each construction stage of the target building project. The deviation volume of the design models of the historical building project and the target building project for each construction stage is taken as the starting point. The similarity of the construction structure design of each historical building project and the target building project is obtained in accordance with the similarity analysis process of the above-mentioned historical building projects and the target building project based on the division of construction stages. The historical building projects with similarities greater than the preset similarity threshold are selected, and labels with high similarity to the construction structure design of the target building project are assigned.
[0034] Specifically, the analysis of the predicted completion date of the current construction stage of the target building project includes: extracting the construction site atlas of each day of the current construction stage of the target building project in the construction record documents of each historical reference building project, constructing the construction site model of each day of the current construction stage of the target building project corresponding to each historical reference building project, comparing it with the current construction scene model of the target building project, obtaining the reference construction date of the current construction scene of the target building project corresponding to each historical reference building project, making an absolute difference with the actual completion date of the current construction stage of the target building project corresponding to each historical reference building project, obtaining the remaining construction days of the current construction scene of the target building project corresponding to each historical reference building project, and obtaining the reference remaining construction days of the current construction scene of the target building project by average calculation. .
[0035] It should be noted that the process of obtaining the reference construction date of the current construction scene of the target building project corresponding to each of the above-mentioned historical reference building projects includes: obtaining the model deviation volume of the construction site model of each day in the current construction phase of the target building project corresponding to each historical reference building project and the current construction scene model of the target building project, and selecting the date corresponding to the day with the smallest model deviation volume as the reference construction date of the current construction scene of the target building project corresponding to each of the historical reference building projects.
[0036] Calculate the construction correction factors of the target construction project affected by meteorological conditions, construction rate, and material supply, respectively, and record them as .
[0037] Get the date of the preset monitoring day , according to the formula Get the predicted completion date of the target building project's current construction phase, is a natural constant.
[0038] The embodiment of the present invention takes the progress data of each historical reference construction project of the target construction project as the starting point, and combines the meteorological conditions, construction rate and material supply dimensions to develop a progress forecast for the current construction stage of the target construction project, so as to help more comprehensively reflect the actual situation of the construction project progress, reduce the risk of prediction deviation due to ignoring a key factor, and thus ensure the accuracy and reliability of the construction progress prediction results.
[0039] Specifically, the The calculation process includes: obtaining the meteorological parameters of each day from the preset monitoring date to the predicted completion date of the current construction stage of the target building project through the meteorological station, including the accumulated precipitation, temperature extremes and wind intensity, and comparing them with the suitable working meteorological parameters of the construction project stored in the cloud database, counting the number of days with abnormal meteorology, and using the ratio of the days with the reference remaining construction days of the current construction scene of the target building project as the construction correction factor affected by meteorological conditions for the target building project .
[0040] It should be noted that the above-mentioned statistical process of abnormal meteorological days includes: the suitable meteorological parameters for construction projects are the permissible precipitation threshold, suitable temperature range and permissible wind intensity threshold under the suitable working environment of construction projects. The days from the preset monitoring date to the predicted completion date of the current construction stage of the target construction project that meet any of the following conditions: the cumulative precipitation is greater than the permissible precipitation threshold under the suitable working environment of the construction project, the temperature extreme value exceeds the suitable temperature range under the suitable working environment of the construction project, and the wind intensity is greater than the permissible wind intensity threshold under the suitable working environment of the construction project are recorded as abnormal meteorological days, and the abnormal meteorological days are counted to obtain the number of abnormal meteorological days.
[0041] The construction site model of each historical reference building project corresponding to the target building project at the current construction stage is compared with the construction site model of the previous day, and the construction rate of each historical reference building project corresponding to the target building project at the current construction stage is calculated. The reference construction rate of the historical reference building project corresponding to the target building project at the current construction stage is obtained by average calculation. .
[0042] Collect the actual completion date of the previous construction stage of the current construction stage of the target building project, make an absolute difference between it and the date of the preset monitoring day, obtain the actual construction days of the current construction stage of the target building project, and obtain the construction rate of the current construction stage of the target building project based on the model difference volume between the current construction scene model of the target building project and the design model of the previous construction stage of the current construction stage .
[0043] It should be noted that the calculation process of the construction rate of the target building project currently in the construction stage corresponding to the above-mentioned historical reference building projects includes: obtaining the added model volume of the construction site model of each day of the current construction stage of the target building project corresponding to each historical reference building project and the construction site model of the previous day, and taking the ratio of the accumulated added value of the added model volume to the actual number of construction days of the current construction stage of the target building project as the construction rate of the target building project currently in the construction stage corresponding to the historical reference building project.
[0044] By computational model Get the construction correction factor of the target building project affected by the construction rate.
[0045] Specifically, the The calculation process includes: collecting the types of construction materials used and their cumulative usage on each day within the actual construction days of the current construction stage of the target building project, importing them into a rectangular coordinate system with date as the horizontal axis and construction material usage as the vertical axis, drawing the cumulative usage change curve of various types of construction materials used in the current construction stage of the target building project and obtaining its corresponding best fitting function.
[0046] Substitute the predicted completion date of the target building project's current construction stage into the best fitting function of the cumulative usage change curve of various types of construction materials used in the target building project's current construction stage to obtain the predicted cumulative usage of various types of construction materials used in the target building project's current construction stage , Numbers for various types of construction materials used. , corresponding to the planned usage of various types of construction materials used in the current construction stage of the target building project Compare and satisfy All kinds of construction materials used under the conditions are recorded as various kinds of excess construction materials, among which In order to preset the allowable deviation usage of construction materials, the excess usage ratio of each type of excess construction material is accumulated to obtain the construction correction factor of the target construction project affected by material supply.
[0047] It should be noted that the calculation formula for the excess proportion of the above-mentioned types of excessive construction materials is: ,in The extracted The predicted cumulative usage and planned usage of such excess construction materials, Numbers for various types of excess construction materials, .
[0048] The progress supervision instruction issuing module is used to compare the predicted completion date with the planned completion date, and issue progress supervision instructions for the current construction stage of the target construction project. The progress supervision instruction is an expected delay instruction or an expected on-time instruction. If the progress supervision instruction is an expected delay instruction, the delay risk warning module is executed, otherwise the rectification demand judgment module is executed.
[0049] Specifically, the issuing of progress supervision instructions for the current construction stage of the target building project includes: if the predicted completion date is less than the planned completion date, issuing an expected extension instruction for the current construction stage of the target building project, otherwise issuing an expected on-time instruction.
[0050] The extension risk warning module is used to screen the extension risk factors and their corresponding risk levels of the current construction stage of the target building project, and generate an extension risk warning window for the current construction stage of the target building project for feedback.
[0051] Specifically, the screening of the delay risk factors and their corresponding risk levels of the current construction stage of the target construction project includes: taking meteorological conditions, construction speed factors, and material supply factors as potential delay risk factors; Normalization processing is performed, and the corresponding factor of the construction correction factor whose value after normalization is greater than the preset delay risk threshold is taken as the delay risk factor, and the corresponding risk level of the delay risk factor is obtained according to the preset value range corresponding to each risk level.
[0052] It should be noted that the delay risk warning window for the current construction stage of the above-mentioned target construction project is obtained by arranging various delay risk factors in order from high to low risk levels to generate a preset size window.
[0053] The embodiment of the present invention conducts a delay risk factor exploration when the target building project is currently in a construction phase and the expected progress is delayed, generates a delay risk warning window for the target building project's current construction phase for feedback, and helps to significantly improve the level of refinement of project management, thereby enhancing the project's risk resistance and ensuring that the project is completed on time and with quality.
[0054] The rectification demand judgment module is used to perform a virtual quality inspection on the current construction scene model of the target building project, evaluate the rework risk level of the current construction stage of the target building project, and thereby determine whether there is a rectification demand for the current construction scene model of the target building project, and provide feedback on the judgment result.
[0055] Specifically, the evaluation of the rework risk level of the current construction stage of the target building project includes: importing the current construction scene model of the target building project into the BIM software, using the BIM software simulation tool to simulate the construction of the remaining models of the current construction stage on the basis of the BIM software, recording the simulated model as the simulation model of the current construction stage of the target building project, performing an appearance difference check with the corresponding design model, collecting the size deviation and position deviation of each key component between the simulation model of the current construction stage of the target building project and the design model, and analyzing the appearance difference coefficient of the simulation model of the current construction stage of the target building project .
[0056] It should be noted that the above It is obtained by accumulating the product of the size deviation and position deviation of each key component between the simulation model and the design model of the target building project at the current construction stage.
[0057] Through the stability performance detection tool and conflict detection tool of BIM software, the structural instability coefficient of the simulation model of the target building project at the current construction stage is obtained. and conflict degree coefficient .
[0058] It should be noted that the above The acquisition process is as follows: through the stability performance detection tool of the BIM software, based on the set parameters, simulate the response of the target building project under various loads and collect the corresponding response parameters, including the structural stress limit value and the overall structural deformation, refer to the design rated structural stress value under various loads in the construction planning plan of the target building project, calculate the structural load anomaly of the target building project under various loads, further multiply it with the overall structural deformation of the target building project under the corresponding type of load, and obtain the foundation structure instability coefficient of the target building project under various loads, and multiply it with the preset weight of the corresponding type of load to obtain the structural instability coefficient of the simulation model of the current construction stage of the target building project.
[0059] Exemplarily, the above-mentioned various types of load effects include but are not limited to wind loads, snow loads, earthquake loads, etc.
[0060] It should be noted that the above The acquisition process is: using the conflict detection tool of the BIM software to automatically find the conflict events and their conflict parameters in the target building project, including the conflict type, the volume of the conflict affected area, and the and conflict resolution difficulty , based on the preset weight ratios of various conflict impacts, obtain the weight ratios of each conflict event ,in is the number of each conflict event, , according to the formula Get the conflict degree coefficient of the simulation model of the current construction stage of the target building project, where The total volume of the model of the target building project is preset as recorded in the construction planning scheme content of the target building project.
[0061] Will , , The rework risk assessment index of the current construction stage of the target building project is obtained by accumulating the products of the corresponding preset weights.
[0062] Specifically, the judgment condition that the current construction scenario model of the target building project has rectification needs includes: the rework risk level assessment index of the current construction stage of the target building project is greater than a preset rework risk level assessment index compliance threshold.
[0063] The embodiment of the present invention carries out a rework risk assessment when the estimated progress of the current construction stage of the target building project is on schedule, determines whether there is a need for rectification in the current construction scene model of the target building project and provides feedback, and can promptly discover potential construction defects or non-compliance with specifications, thereby avoiding subsequent rework operations and effectively saving time and costs.
[0064] The cloud database is used to store construction record documents of various historical building projects and store meteorological parameters suitable for construction work.
[0065] The data sources in the cloud database of this embodiment are shown in Table 1 below.
[0066] Table 1 Detailed description of data sources in cloud database
[0067]
[0068] The above contents are merely examples and explanations of the structure of the present invention. The technicians in this technical field may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the structure of the invention or exceed the scope defined by the present invention, they should all fall within the protection scope of the present invention.
Claims
1. A construction design progress monitoring system based on big data computing, characterized in that: The system includes: The construction project information acquisition module is used to obtain the basic planning information of each construction stage of the target construction project, including the design model, the planned completion date, the type of construction materials used and their corresponding planned usage; The current construction stage confirmation module is used to collect all-round images of the construction site of the target building project on the preset monitoring day, create a current construction scene model of the target building project, compare it with the design models of each construction stage of the target building project, and confirm the current construction stage of the target building project; The predicted completion date analysis module is used to screen various historical reference building projects for the target building project, and analyze the predicted completion date of the target building project at the current construction stage according to the progress data of the historical reference building projects corresponding to the target building project at the current construction stage; The progress supervision instruction issuing module is used to compare the predicted completion date with the planned completion date, and issue progress supervision instructions for the current construction stage of the target building project. The progress supervision instruction is an expected delay instruction or an expected on-time instruction. If the progress supervision instruction is an expected delay instruction, the delay risk warning module is executed, otherwise the rectification demand judgment module is executed; The delay risk warning module is used to screen the delay risk factors and their corresponding risk levels of the current construction stage of the target building project, and generate a delay risk warning window for the current construction stage of the target building project for feedback; The rectification demand judgment module is used to perform a virtual quality inspection on the current construction scene model of the target building project, evaluate the rework risk level of the current construction stage of the target building project, and judge whether there is a rectification demand for the current construction scene model of the target building project, and provide feedback on the judgment result; Cloud database, used to store construction record documents of various historical building projects and store weather parameters suitable for construction projects; The analysis of the predicted completion date of the current construction stage of the target building project includes: extracting the construction site atlas of each day of the current construction stage of the target building project corresponding to each historical reference building project in the construction record document, constructing the construction site model of each day of the current construction stage of the target building project corresponding to each historical reference building project, comparing with the current construction scene model of the target building project, obtaining the reference construction date of the current construction scene of the target building project corresponding to each historical reference building project, making an absolute difference with the actual completion date of the current construction stage of the target building project corresponding to each historical reference building project, obtaining the remaining construction days of the current construction scene of the target building project corresponding to each historical reference building project, and obtaining the reference remaining construction days of the current construction scene of the target building project by average calculation. ; Calculate the construction correction factors of the target construction project affected by meteorological conditions, construction rate, and material supply, respectively, and record them as ; Get the date of the preset monitoring day , according to the formula Get the predicted completion date of the target building project's current construction phase, is a natural constant; The method for evaluating the rework risk level of the current construction stage of the target building project includes: importing the current construction scene model of the target building project into the BIM software, using the BIM software simulation tool to simulate the construction of the remaining models of the current construction stage on the basis of the BIM software, recording the simulated model as the simulation model of the current construction stage of the target building project, performing an appearance difference check with the corresponding design model, collecting the size deviation and position deviation of each key component between the simulation model of the current construction stage of the target building project and the design model, and analyzing the appearance difference coefficient of the simulation model of the current construction stage of the target building project ; The product of the size deviation and position deviation of each key component between the simulation model of the target building project at the current construction stage and the design model is accumulated to obtain the appearance difference coefficient of the simulation model of the target building project at the current construction stage ; Through the stability performance detection tool and conflict detection tool of BIM software, the structural instability coefficient of the simulation model of the target building project at the current construction stage is obtained. and conflict degree coefficient ; Above The acquisition process is as follows: using the stability performance detection tool of the BIM software to simulate the response of the target building project under various loads based on the set parameters and collect the corresponding response parameters, including the structural stress limit value and the overall structural deformation, referring to the design rated structural stress value under various loads in the construction planning scheme of the target building project, calculating the structural load anomaly of the target building project under various loads, further multiplying it with the overall structural deformation of the target building project under the corresponding type of load, obtaining the foundation structure instability coefficient of the target building project under various loads, multiplying it with the preset weight of the corresponding type of load, and obtaining the structural instability coefficient of the simulation model of the target building project at the current construction stage; Above The acquisition process is: using the conflict detection tool of the BIM software to automatically find the conflict events and their conflict parameters in the target building project, including the conflict type, the volume of the conflict affected area, and the and conflict resolution difficulty , based on the preset weight ratios of various conflict impacts, obtain the weight ratios of each conflict event ,in is the number of each conflict event, , according to the formula Get the conflict degree coefficient of the simulation model of the current construction stage of the target building project, where The total volume of the preset model of the target building project recorded in the construction planning scheme of the target building project; Will , , The rework risk assessment index of the current construction stage of the target building project is obtained by accumulating the products of the corresponding preset weights.
2. The architectural design progress monitoring system based on big data calculation according to claim 1 is characterized by: The confirmation of the current construction stage of the target building project includes: importing the current construction scene model of the target building project and the design models of each construction stage into the model software for overlap comparison, and obtaining the matching degree between the design models of each construction stage of the target building project and the current construction scene model; Each construction stage is numbered according to the construction sequence. If the matching degree between the design model of a certain construction stage of the target building project and the current construction scene model is less than the preset matching degree threshold, and the matching degree between the design model of the previous construction stage and the current construction scene model is greater than or equal to the preset matching degree threshold, then the construction stage is confirmed to be the current construction stage of the target building project.
3. The architectural design progress monitoring system based on big data calculation according to claim 1 is characterized by: The method of screening various historical reference building projects for the target building project includes: extracting construction record documents of various historical building projects stored in a cloud database, and screening out various historical building projects that have high similarity with the target building project in terms of construction phase division, construction material supply, and construction structure design according to the construction phase planning content, construction material list content, and construction structure design drawings in the construction record documents as various historical reference building projects for the target building project.
4. The architectural design progress monitoring system based on big data calculation according to claim 1 is characterized by: Said The calculation process includes: obtaining the meteorological parameters of each day from the preset monitoring date to the predicted completion date of the current construction stage of the target building project through the meteorological station, including the accumulated precipitation, temperature extremes and wind intensity, and comparing them with the suitable working meteorological parameters of the construction project stored in the cloud database, counting the number of days with abnormal meteorology, and using the ratio of the days with the reference remaining construction days of the current construction scene of the target building project as the construction correction factor affected by meteorological conditions for the target building project ; The construction site model of each historical reference building project corresponding to the target building project at the current construction stage is compared with the construction site model of the previous day, and the construction rate of each historical reference building project corresponding to the target building project at the current construction stage is calculated. The reference construction rate of the historical reference building project corresponding to the target building project at the current construction stage is obtained by average calculation. ; Collect the actual completion date of the previous construction stage of the current construction stage of the target building project, make an absolute difference between it and the date of the preset monitoring day, obtain the actual construction days of the current construction stage of the target building project, and obtain the construction rate of the current construction stage of the target building project based on the model difference volume between the current construction scene model of the target building project and the design model of the previous construction stage of the current construction stage ; By computational model Get the construction correction factor of the target building project affected by the construction rate.
5. The architectural design progress monitoring system based on big data calculation according to claim 4 is characterized by: Said The calculation process includes: collecting the types of construction materials used and their cumulative usage on each day within the actual construction days of the current construction stage of the target building project, importing them into a rectangular coordinate system with the date as the horizontal axis and the amount of construction materials used as the vertical axis, drawing the cumulative usage change curve of various types of construction materials used in the current construction stage of the target building project and obtaining the corresponding best fitting function; Substitute the predicted completion date of the target building project's current construction stage into the best fitting function of the cumulative usage change curve of various types of construction materials used in the target building project's current construction stage to obtain the predicted cumulative usage of various types of construction materials used in the target building project's current construction stage , Numbers for various types of construction materials used. , corresponding to the planned usage of various types of construction materials used in the current construction stage of the target building project Compare and satisfy All kinds of construction materials used under the conditions are recorded as various kinds of excess construction materials, among which In order to preset the allowable deviation usage of construction materials, the excess usage ratio of each type of excess construction material is accumulated to obtain the construction correction factor of the target construction project affected by material supply.
6. The architectural design progress monitoring system based on big data calculation according to claim 1 is characterized by: The issuing of progress supervision instructions for the current construction stage of the target construction project includes: if the predicted completion date is less than the planned completion date, issuing an estimated extension instruction for the current construction stage of the target construction project, otherwise issuing an estimated on-time instruction.
7. The architectural design progress monitoring system based on big data calculation according to claim 1 is characterized by: The screening target construction project's current construction phase's delay risk factors and their corresponding risk levels include: taking weather conditions, construction rate, and material supply factors as potential delay risk factors; Normalization processing is performed, and the corresponding factor of the construction correction factor whose value after normalization is greater than the preset delay risk threshold is taken as the delay risk factor, and the corresponding risk level of the delay risk factor is obtained according to the preset value range corresponding to each risk level.
8. The architectural design progress monitoring system based on big data calculation according to claim 1 is characterized by: The judgment condition that the current construction scenario model of the target building project has rectification needs includes: the rework risk level assessment index of the current construction stage of the target building project is greater than a preset rework risk level assessment index compliance threshold.