Method for hoisting and dismantling cone valve on water conservancy dam
By setting up the main anchor point and pulling anchor point on the water conservancy dam, the conical valve is lifted from the ceiling of the dam to the downstream side and moving along the inclined surface of the dam to the target position, the water conservancy is solved The maintenance problem of conical valves on the dam achieves a safe and effective lifting and disassembly process.
Patent Information
- Application Number
- CN202410701250.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-31
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-05-31
AI Technical Summary
The existing technology is difficult to maintain and replace conical valves on water conservancy dams. The height, inclination and bottom width of the dam make it difficult to safely lift the conical valves during replacement, and common lifting equipment cannot be directly lowered to the target. Location, there is a risk of damage.
The main anchor point is arranged on the upstream side of the middle of the dam top, and the wire rope is guided to the downstream side through the dam top, and a pulling anchor point is set on the downstream side. The conical valve is driven from the large by using a winch device and a lifting device. The dam ceiling is lifted to the hoist lifting point on the downstream side, move along the inclined surface of the dam downstream to the target position, and adjust it in place through the wind rope and guide rail to ensure that the conical valve is connected to the embedded flange to avoid inclination with the dam. Face to touch.
The safety, effective lifting and disassembly of conical valves is achieved, ensuring a 100% success rate, avoiding equipment damage and dam structure damage, and reducing operating costs and time.
Smart Images

Figure CN118561165B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of dam tooling maintenance, and in particular to a hoisting method and a disassembly method of a cone valve on a water conservancy dam. Background Art
[0002] The construction of water conservancy dams is of great significance for flood control and drought relief, and alleviating the environmental impact and resource tension caused by coal-fired power. The downstream side of the dam generally has a wider bottom, making the whole body tilt downward to provide better support.
[0003] Taking the Tanling Reservoir Dam as an example, the width of the dam crest is about 5m, the width of the dam bottom is about 30m, and the height is about 45m. The installation position of the cone valve is about 11m from the dam bottom, about 34m from the dam crest, and about 30m wide from the upstream side of the dam on the downstream side of the dam. Due to factors such as the overall height, inclination, and bottom width of the dam, it is very difficult to replace the cone valve in the middle and lower part of the downstream side of the dam when it needs to be replaced. Secondly, the cone valve body is very heavy. Taking the cone valve on the Tanling Reservoir Dam as an example, the cone valve is about 10.9t, which makes it impossible to use general lifting equipment to directly lower the cone valve to the target position for installation and replacement due to the height and width of the water conservancy dam. At the same time, since the downstream side of the dam is an inclined surface, even if there is a lifting equipment with sufficient lowering height, it is impossible to directly lower the cone valve to the target position, because the cone valve will directly touch the inclined surface of the dam first, which will not only damage the cone valve, but may even damage the structure of the dam. Since the overall site lift during lifting is more than 32m, the horizontal distance from the dam to the cone valve layout is more than 26m, and the bridge deck width on the dam top is small (5.5m), the site restrictions also make it impossible to arrange large-scale lifting equipment that can lift the cone valve (10.9t) with such a large load.
[0004] Therefore, when lowering the conical valve to the target position, it is necessary to consider the height and width of the dam, the load of the lifting equipment, the safety and fault tolerance of the overall technical solution (because of the cost and the stability of the overall structure of the dam, it is necessary to ensure that it is completed in one go, without any possibility of accidents, and to ensure 100% success). At present, there is no lifting method that can completely solve the above-mentioned problems, so it is difficult to achieve the maintenance and replacement of heavy tooling of water conservancy dams, which is a technical problem that needs to be solved urgently. Summary of the invention
[0005] The embodiment of the present invention provides a method for hoisting and disassembling a cone valve on a water conservancy dam, so as to solve the problem that it is difficult to maintain and replace heavy tooling of the water conservancy dam in the prior art.
[0006] According to one aspect of the present invention, there is provided a method for hoisting a cone valve on a water conservancy dam, characterized in that it comprises:
[0007] The main anchor point is arranged on the upstream side of the middle part of the dam crest;
[0008] The two ends of the wire rope are fixed to the main anchor point, guided through the dam top to the downstream side, and a pulley is hung at one end on the downstream side;
[0009] Arrange pulling anchor points on both sides of the mountain on the downstream side of the dam;
[0010] A winch device is arranged at the step on the downstream side of the dam, the winch device includes a first winch unit and a second winch unit, the wire rope of the first winch unit passes around the pulley, and the wire rope of the second winch unit passes around the pulling anchor point;
[0011] A lifting lug and a wind rope are arranged on the conical valve, and a lifting wire rope is arranged at the lifting lug;
[0012] At the same time, the lifting device and the winch device are arranged on the lifting wire rope of the cone valve, and the cone valve is lifted from the dam crest to the winch lifting point on the downstream side of the dam crest by the lifting device;
[0013] Control the winch device to move the cone valve along the downstream slope of the dam about 1 meter to the vicinity of the target position, and use the windlass to stabilize the cone valve;
[0014] Guide the valve sleeve running wheel into the guide rail until the conical valve roughly reaches the target position;
[0015] Coordinate the first winch unit and the second winch unit to adjust and guide the conical valve into position, use the wind rope to guide and adjust the guide bracket above the front end of the conical valve in the correct direction, and apply liquid sealant to the matching surface of the conical valve flange and the embedded part flange;
[0016] Connect the conical valve flange to the embedded part flange and tighten the bolts. After the conical valve and embedded part are securely connected, remove the hook.
[0017] Adjust the conical valve and tighten it with bolts to the embedded flange to complete the lifting of the conical valve.
[0018] The main anchor point and the pulling anchor point are each provided with at least two anchor points.
[0019] The steel wire rope passing through the top of the dam is composed of two steel wire ropes tied together with a lock.
[0020] The anchoring depth of the main anchor point and the pulling anchor point is not less than 400 mm.
[0021] The main anchor point and the pulling anchor point are both formed by 8 M24×400 chemical anchors and 1 ear plate.
[0022] At least two pulling anchor points are provided.
[0023] The pulling anchor points are set on the mountains on both sides of the downstream side of the dam at a position where the elevation is higher than the installation elevation of the cone valve.
[0024] The second winch assembly includes at least two winches, and each pulling anchor point is wound with a steel wire rope of at least one winch.
[0025] The wind rope is arranged on the screw holes on both sides of the top of the conical valve.
[0026] It also includes testing and verification of the main anchor points and the pulling anchor points, including:
[0027] Use an anchor tension gauge to apply a tensioning force 1.2 times the pull-out force to the anchor to tension it;
[0028] After dismantling the old conical valve, use the winch to lift the old conical valve. When it is fully loaded, lower the old conical valve to about 1 meter at the bottom of the river and keep it there for 10 minutes.
[0029] Another aspect of the present invention provides a method for disassembling a cone valve on a water conservancy dam, comprising:
[0030] The main anchor point is arranged on the upstream side of the middle part of the dam crest;
[0031] The two ends of the wire rope are fixed to the main anchor point, guided through the dam top to the downstream side, and a pulley is hung at one end on the downstream side;
[0032] Arrange pulling anchor points on both sides of the mountain on the downstream side of the dam;
[0033] A winch device is arranged at the step on the downstream side of the dam, the winch device includes a first winch unit and a second winch unit, the wire rope of the first winch unit passes around the pulley, and the wire rope of the second winch unit passes around the pulling anchor point;
[0034] A lifting lug and a wind rope are arranged on the conical valve, and a lifting wire rope is arranged at the lifting lug;
[0035] The cone valve is connected with the first winch unit and the first winch unit is started to bear the weight of the cone valve, and the bolts connecting the cone valve and the embedded part are removed to separate the cone valve from the embedded part;
[0036] Coordinate and control the first winch unit and the second winch unit to move the cone valve about 1 meter along the downstream slope of the dam and rise to the pulley on the downstream side of the dam crest;
[0037] Lower the hook of the lifting device and hang it to the wire rope of the cone valve;
[0038] The hoisting device lifts the conical valve, and at the same time releases the winch device, and uses the hoisting device to lift the conical valve onto the dam transport vehicle, unhooks the pulley and the hook of the hoisting device to complete the removal of the conical valve.
[0039] The hoisting method and disassembly method of the cone valve located on the water conservancy dam of the present invention realizes lifting and lowering of the weight load of the cone valve along an inclined trajectory by using a winch at the main anchor point on the dam top and the pulling anchor point arranged on the mountain outside the downstream side of the dam, so as to ensure that the cone valve can avoid overturning due to an unacceptable hoisting amplitude when lifting with general lifting equipment that can be arranged on the dam top, and by using the winch to bypass the pulling anchor point and pull the cone valve to the downstream side, the cone valve will not touch the inclined surface on the downstream side of the dam during the rising and falling process. In the present invention, in order to ensure the safety of the overall solution, the main anchor point is set on the upstream side of the middle part of the dam crest, and the wire rope connected to the main anchor point bypasses the dam crest, so that part of the load of the main anchor point is shared by the dam crest, and the pulling anchor point is set at the mountain on the downstream side of the dam, which can ensure the outward pulling amplitude of the conical valve when it is lowered, and the cost and safety success rate are combined to ensure that the overall technical solution can be 100% successful. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying any creative work.
[0041] Figure 1 It is a schematic diagram of the structure of a cone valve required to be hoisted in a method for hoisting a cone valve located on a water conservancy dam according to an embodiment of the present invention;
[0042] Figure 2 It is a structural schematic diagram of a scenario (Tanling Reservoir Dam) in which a method for hoisting a cone valve on a water conservancy dam according to an embodiment of the present invention is applied;
[0043] Figure 3 It is a flow chart of a method for hoisting a cone valve on a water conservancy dam according to an embodiment of the present invention;
[0044] Figure 4 The arrangement of the overall lifting system in the lifting method of the cone valve located on the water conservancy dam according to one embodiment of the present invention is schematically shown;
[0045] Figure 5 It is a structural schematic diagram of the arrangement of the main anchor points in a method for hoisting a cone valve on a water conservancy dam according to an embodiment of the present invention;
[0046] Figure 6 It is a schematic diagram of the dam top structure after the main anchor point is arranged in the method for hoisting a cone valve on a water conservancy dam according to one embodiment of the present invention;
[0047] Figure 7 It is a structural schematic diagram of the arrangement of the pulling anchor points in the method for hoisting a cone valve on a water conservancy dam according to one embodiment of the present invention;
[0048] Figure 8 A simplified force diagram of a method for hoisting a cone valve on a water conservancy dam according to an embodiment of the present invention during hoisting;
[0049] Fig. 9 It is a schematic diagram of the dam top structure after a hanging ladder is added when carrying out the relay arrangement of the lifting points in a method for lifting a cone valve located on a water conservancy dam according to one embodiment of the present invention;
[0050] Fig.10 The present invention is a flowchart of a method for disassembling a cone valve located on a water conservancy dam according to an embodiment of the present invention.
[0051] Explanation of the reference numerals in the accompanying drawings: 1. conical valve; 21. dam top; 22. dam bottom; 23. mountain; 24. hanging ladder; 31. main anchor point; 32. pulling anchor point; 33. screw; 34. nut; 35. lifting ear plate; 36. corner guard; 4. pulley; 5. winch; 6. lifting device. DETAILED DESCRIPTION
[0052] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0053] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application may be combined with each other.
[0054] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include" and "comprise" include not only those elements, but also other elements that are not explicitly listed, or also include elements inherent to such processes, methods, articles or equipment. In the absence of further restrictions, the elements defined by the statement "include..." do not exclude the existence of other identical elements in the process, method, article or equipment that includes the elements.
[0055] The present invention is further described in detail below by taking the hoisting and installation of the cone valve 1 for the Tanling Reservoir Dam as an example.
[0056] Specifically, in this example, the parameters of the conical valve 1 are that the single piece weighs about 10.9 tons, is about 3.6 meters long, about 2.6 meters wide, and about 2.6 meters high. Its structure is as follows: Figure 1 The total height of the Tanling Reservoir Dam is about 45m, the width of the dam crest 21 is about 5m, the width of the dam bottom 22 is about 30m, there is a step in the middle of the downstream side of the dam, the step is located about 15m away from the dam crest 21, and the width is about 1.5m. The installation position of the cone valve 1 is located at a height of about 11m from the dam bottom 22 on the downstream side of the dam, about 34m from the dam crest 21, and about 30m wide on the upstream side of the dam. Its structure is as follows Figure 2 shown.
[0057] In this hoisting process, the heaviest part is the valve body of the cone valve 1. Now the layout parameters of the truck crane and winch are calculated based on the hoisting of the cone valve 1. The weight of the movable pulley is 0.13t, the wire rope is 0.152t / 100m, the longest wire of the suspended part is about 450m, and the weight = 4.5×0.152=0.684(t).
[0058] The total weight of the wire rope, the movable pulley and the hoisting weight of the cone valve 1 is used as the calculated load = 10.9 + 0.13 + 0.684 = 11.7t. To simplify the calculation, 12t is used as the lifting point load.
[0059] The technical difficulty of hoisting and installing the cone valve 1 mainly lies in the fact that the cone valve 1 itself is heavy. At the same time, due to the high height of its installation position on the dam, it is difficult for the existing general lifting equipment to lift the cone valve 1 of such size to this height. At the same time, the road condition at the bottom 22 of the dam is poor, and it is difficult for general lifting equipment to be directly installed at the bottom 22 of the dam. Therefore, basically only the technical solution of lowering the cone valve 1 from the dam crest 21 to the target position can be considered. However, since there is an inclined surface on the downstream side of the dam, and the installation position of the cone valve 1 is about 30m wide from the upstream side of the dam and about 34m from the dam crest 21, the cone valve 1 cannot touch the inclined surface on the downstream side of the dam when it is lowered. Due to safety factors and fault tolerance factors such as installation cost and dam body structure, it is necessary to ensure that the hoisting and installation can be 100% successful at one time. Therefore, when designing the hoisting and installation technical solution, many factors need to be considered to ensure that it is completed at one time, without any possibility of accidents, and to ensure 100% success.
[0060] Based on such technical difficulties, the hoisting technical solutions that can be generally envisioned include the technical solution of arranging a slideway on the outer side of the downstream side of the inclined dam and the technical solution of directly opening a road from the side mountain to the downstream river channel. However, in fact, in the technical solution of arranging the slideway, the construction of the slideway itself is highly risky, and the slideway itself is also a source of risk, which has certain safety hazards. At the same time, when arranging the slideway rail, the workload of arranging the rail is large, and after the conical valve reaches the safe position, it is still necessary to carry out secondary hoisting before the conical valve can be installed. The construction of the secondary lifting system is still very difficult and the operation convenience is poor. The disassembly and assembly time of the slideway rail is long, the construction period is long, and the slide rail part is a consumable, and the cost effect is high. In the technical solution of directly opening a road from the side mountain to the downstream river channel, it is necessary for the design institute and the civil engineering unit to jointly determine the construction road for transportation to the downstream and the on-site hoisting platform. The project volume is large, the overall cost is high, and the environmental damage is great, so the actual operation possibility is small. Therefore, the technical aspects of the present invention are considered in many aspects, and the following technical solution is formed.
[0061] Figure 3 The flow chart of a method for hoisting a cone valve on a water conservancy dam according to an embodiment of the present invention is schematically shown. Figure 5 The arrangement of the overall lifting system in the lifting method of the cone valve on the water conservancy dam according to one embodiment of the present invention is schematically shown, referring to Figure 4 and Figure 5 As shown, the method comprises the following steps:
[0062] Step S11: arranging the main anchor point 31 on the upstream side of the middle part of the dam crest 21;
[0063] Step S12: The two ends of the wire rope are fixed to the main anchor point 31, and guided to the downstream side through the dam crest 21, and a pulley 4 is hung at one end of the downstream side;
[0064] Step S13: Arrange the pulling anchor points 32 at the mountains 23 on both sides of the downstream side of the dam;
[0065] Step S14: Arrange a hoisting device 5 at the step on the downstream side of the dam, the hoisting device 5 includes a first hoisting unit and a second hoisting unit, the wire rope of the first hoisting unit passes around the pulley 4, and the wire rope of the second hoisting unit passes around the pulling anchor point 32;
[0066] Step S15: a lifting lug and a wind rope are arranged on the conical valve 1, and a lifting wire rope is arranged at the lifting lug;
[0067] Step S16: Use the lifting device 6 to lift the cone valve 1 from the dam crest 21 to the pulley 4 on the downstream side of the dam crest 21, and switch to the hoisting device 5 to lift the cone valve 1;
[0068] Step S17: coordinate and control the first hoisting unit and the second hoisting unit of the hoisting device 5 to move the cone valve 1 obliquely about 1 meter along the downstream slope of the dam and drop it to the vicinity of the target position, and use the wind rope to stabilize the cone valve 1;
[0069] Step S18: coordinate the first winch unit and the second winch unit to adjust and guide the conical valve 1 to the conical valve installation position, use the wind rope to guide and adjust the guide bracket above the front end of the conical valve 1 in the correct direction, and apply liquid sealant to the matching surface between the flange of the conical valve 1 and the embedded flange;
[0070] Step S19: guiding the valve sleeve running wheel into the guide rail until the conical valve 1 roughly reaches the target position;
[0071] Step S110: The flange of the conical valve 1 is connected to the flange of the embedded part and bolted, and after the conical valve 1 is reliably connected to the embedded part, the hook is released;
[0072] Step S111: adjust the conical valve 1 and fasten it to the embedded flange with bolts to complete the hoisting of the conical valve 1.
[0073] Among them, the overall specific technical solution proposes to use three winches as winch devices 5, one of which is used as the first winch unit, and the other two winches are used as the second winch unit. A 35t truck crane is installed on the top of the dam, which is used as a lifting device 6 for unloading and auxiliary lifting of the conical valve 1.
[0074] When executing step S11, the main anchor point 31 is arranged on the upstream side of the middle part of the dam crest 21, the arranged main anchor point 31 is a double anchor point, each anchor point is formed by 8 M24×400 chemical anchors and 1 lug plate 35. Specifically, refer to Figure 5 As shown, in Figure 5 In the figure, a cross-sectional view and a front view of the main anchor point 31 in the anchored state are shown. The lug plate 35 of the main anchor point 31 is chemically anchored by an M24 screw 33 and an M24 nut 34. Then, step S12 is performed to fix the two ends of a single Φ34 steel wire rope with a length of about 14m on the two anchor points respectively, and bypass the dam crest 21 to guide it to the downstream side of the dam to be hung with a pulley 4. The pulley 4 specifically uses a 32t pulley 4. In order to ensure a higher safety factor for the main anchor point 31, the two steel wire ropes can also be combined with a lock at the dam crest 21. Specifically, the arrangement and position of the main anchor point 31 can refer to Figure 6 As shown, in Figure 6 In the figure, the main anchor point 31 is set on the upstream side of the dam crest 21, the wire rope bypasses the dam crest and is on the downstream side of the dam crest 21, and corner guards 36 are respectively provided at the two corners of the dam crest 21 to protect the wire rope from being damaged by the corner tip, thereby ensuring the safety of the overall technical solution during implementation.
[0075] When executing step S13 to arrange the pulling anchor point 32, no less than two pulling anchor points 32 can be set, and they are respectively set at positions on the mountains 23 on both sides of the downstream side of the dam at an elevation higher than the installation elevation of the cone valve (about 620m (i.e., 18m from the height of the dam bottom, and about 55m from the axis of the dam), so as to select a suitable point at the position to embed anchor bars and set the pulling anchor point 32. Similar to the main anchor point 31, the pulling anchor point 32 is also formed by 8 M24×400 chemical anchors and 1 ear plate 35. And, similarly, the pulling anchor point 32 can also be set as a double anchor point set in the front and back, and the rear anchor point serves as a backup anchor point for the front anchor point, and the rear anchor point is connected to the front anchor point with a wire rope. After the anchor point is arranged, a pulley is arranged on the ear plate 35 of the pulling anchor point 32 for the wire rope of the winch to pass around. For details, refer to Figure 7 As shown, in Figure 7 , a cross-sectional view and a front view of the pulling anchor point 32 in the anchored state are shown, and the ear plate 35 of the pulling anchor point 32 is chemically anchored by an M24 screw 33 and an M24 nut 34.
[0076] Figure 8 The simplified force diagram of the hoisting method of the present invention is shown in the figure below. The left figure shows the force condition in a side view, and the right figure shows the force condition in a top view. Figure 8 Calculate each component force, and the results are shown in the following table:
[0077] Force calculation table
[0078]
[0079] From the table above, we can see that the maximum force of the pulley 4 is 160kN, and the maximum pulling force of the two pulling anchor points 32 is 77kN. Therefore, the 32t main pulley 4 (6 wheels and 12 ropes) is arranged on the dam top, and the 16t anchor point (single wheel and double rope) is arranged at the pulling anchor point 32 to complete the lifting.
[0080] When executing step S14 to arrange the winch 5, considering the geographical conditions of the dam bottom 22 and the small number of platforms on the downstream side of the dam, the winch 5 is arranged at the steps downstream of the dam, and the tunnel entrance is selected for fixed arrangement of the winch, so that the space of the tunnel entrance can be combined to form the space required for the winch to be operated, so that the operator can better operate the winch. Specifically, the steps on the downstream side of the Tanling Reservoir Dam are 1.5m wide, and the tunnel entrance is 1.5m wide, forming a space of 1.5m wide and 3m long, while the winch size is 1.3m×1.5m, so the arrangement at this position can meet the requirements of the size of the operating space. The hoisting device 5 includes a first hoisting unit and a second hoisting unit. The first hoisting unit corresponds to the main anchor point 31, and its wire rope passes around the pulley 4 hung on the main anchor point 31 to bear the main load of the cone valve 1. The second hoisting unit corresponds to the pulling anchor point 32, and its wire rope passes around the pulley set on the pulling anchor point 32 to bear the load of pulling the cone valve 1 to the downstream side to prevent the cone valve 1 from touching the inclined surface on the downstream side of the dam when lowering.
[0081] Since the arrangement of the hoisting device 5 and the main anchor point 31 and the pulling anchor point 32 is directly related to the success and safety of the replacement of the conical valve 1, and the arrangement of the hoisting device 5 and the main anchor point 31 and the pulling anchor point 32 is also related to the actual installation environment conditions on site, there is a lot of uncertainty. Therefore, after the hoisting device 5 and the main anchor point 31 and the pulling anchor point 32 are arranged, it is best to verify the stability and load of this part first, including the pull-out resistance verification of the anchor rod and the load confirmation of the hoisting device 5, the main anchor point 31 and the pulling anchor point 32.
[0082] When verifying the tensile strength of anchor rods, an anchor rod tensioning machine is used to tension the anchor rods. The tensioning force is 1.2 times (73.08 kN) of the designed tensile strength. If the result shows that the anchor rod is not damaged, it is qualified, otherwise, it is unqualified.
[0083] According to calculation, when the cone valve 1 is in the installation position (i.e., the lowest lifting position), the load of the entire system is the largest, and when the load of the hoisting device 5, the main anchor point 31 and the pulling anchor point is confirmed, the load confirmation needs to be carried out based on this load. Specifically, after the old cone valve 1 is disassembled, the old cone valve 1 can be used to confirm the load of the hoisting device 5, the main anchor point 31 and the pulling anchor point 32.
[0084] Use an anchor tension gauge to apply a tensioning force 1.2 times the pull-out force to the anchor to tension it;
[0085] After disassembling the old conical valve 1, the winch device 5 is used to lift the old conical valve 1. When the load is fully borne, the old conical valve 1 is lowered to about 1 meter below the river bottom and stays there for 10 minutes. A safety person checks the main anchor point 31 and the pulling anchor point 32. If the result shows that there is no deformation at each anchor point, it is qualified, otherwise it is unqualified.
[0086] After completing the verification of the stability and load of the hoisting device 5 and the main anchor point 31 and the pulling anchor point 32, during the subsequent hoisting and installation of the cone valve 1, it is necessary to arrange a dedicated person to monitor each anchor point to ensure that each anchor point works normally.
[0087] When executing step S15, it is necessary to set a lifting lug and a wind rope on the conical valve 1. The function of the wind rope is to stabilize the valve body of the conical valve 1 during lifting, hook replacement, and in place, thereby facilitating the operation of the operator. The installation position of the wind rope can be specifically set to be tied to the bolt holes on both sides of the top of the conical valve 1. The lifting lug can be temporarily welded on the conical valve 1, and it can be set 3m away from the end that is farther away, or the screw hole on the valve body can be directly used as the lifting lug during lifting. After the lifting lug is set, a lifting wire rope is set at the lifting lug for connecting with the first winch unit and the second winch unit to lift and lower the conical valve 1.
[0088] When executing step S16, it is necessary to simultaneously connect the automobile crane and each winch to the lifting wire rope of the cone valve 1, so as to save the operator's operation when switching between the automobile crane and the winch. Specifically, first use the automobile crane to unload the cone valve 1 from the transport vehicle on the ceiling, and use the automobile crane to lift the cone valve 1 from the dam top to the downstream side of the dam top and close to the dam body, so that the cone valve 1 is at the hoisting point of the winch. Then start the winch device 5 to make the winch device 5 bear the weight of the cone valve 1. After the main pulley 4 bears the weight of the cone valve 1, use the wind rope to stabilize the cone valve 1. The operator goes down to the cone valve 1 to remove the automobile hook and complete the relay of the lifting point. Among them, since the operating position is located on the downstream side of the dam top, a hanging ladder 24 can be hung on the downstream side of the dam top. Specifically, refer to Fig. 9 As shown, the length of the hanging ladder 24 is about 2m. The manufacture of the hanging ladder 24 needs to comply with GB4053.1-2009 "Safety Requirements for Fixed Steel Ladders and Platforms", and the relay of the hanging point is performed by an operator wearing a fall arrester to change the hook.
[0089] Then continue to perform the subsequent steps. Start the hoisting device 5. The first hoisting unit is responsible for the vertical load. The two hoists of the second hoisting unit cooperate to control the horizontal movement of the cone valve 1. Move the cone valve 1 along the downstream slope of the dam at a distance of about 1m, and lower it to the front of the valve chamber of the cone valve 1. Use the wind rope to stabilize the cone valve 1. Guide the valve sleeve running wheel to enter the horizontal I-shaped guide rail on the dam for installing the cone valve 1 until the cone valve 1 reaches the target position. Coordinate the first hoisting unit and the second hoisting unit to adjust and guide the cone valve 1 into place. Use the wind rope to guide and adjust the guide bracket above the front end of the cone valve 1 in the correct direction. Apply liquid sealant to the matching surface of the cone valve 1 flange and the embedded part flange. Connect the cone valve 1 flange to the embedded part flange and bring bolts. After the cone valve 1 is reliably connected to the embedded part, release the hook. Adjust the cone valve 1 and tighten it with bolts to complete the hoisting of the cone valve 1.
[0090] The present invention also provides a method for disassembling a cone valve located on a water conservancy dam. Fig.10 The process of disassembling a cone valve on a water conservancy dam according to an embodiment of the present invention is schematically shown. Fig.10 As shown, the method specifically includes: a method for disassembling a cone valve located on a water conservancy dam, comprising:
[0091] Step S21: arranging the main anchor point 31 on the upstream side of the middle part of the dam crest 21;
[0092] Step S22: The two ends of the wire rope are fixed to the main anchor point 31, and the wire rope is guided to the downstream side through the dam crest 21, and a pulley 4 is hung at one end of the downstream side;
[0093] Step S23: Arrange the pulling anchor points 32 at the mountains 23 on both sides of the downstream side of the dam;
[0094] Step S24: Arrange a hoisting device 5 at the step on the downstream side of the dam, the hoisting device 5 includes a first hoisting unit and a second hoisting unit, the wire rope of the first hoisting unit passes around the pulley 4, and the wire rope of the second hoisting unit passes around the pulling anchor point 32;
[0095] Step S25: a lifting lug and a wind rope are arranged on the conical valve 1, and a lifting wire rope is arranged at the lifting lug;
[0096] Step S26: using the first hoisting unit to connect the conical valve 1 and start the first hoisting unit to bear the weight of the conical valve 1, and removing the bolts connecting the conical valve 1 and the embedded parts to separate the conical valve 1 from the embedded parts;
[0097] Step S27: Coordinate and control the first hoisting unit and the second hoisting unit to move the conical valve 1 along the downstream slope of the dam by about 1 meter and rise to the pulley 4 on the downstream side of the dam crest 21;
[0098] Step S28: lower the hook of the lifting device 6 and hang it on the wire rope of the cone valve 1;
[0099] Step S29: The lifting device 6 lifts the conical valve 1, and at the same time, the hoisting device 5 is released, and the conical valve 1 is lifted onto the dam transport vehicle by the lifting device 6, and the hooks of the pulley 4 and the lifting device 6 are unhooked to complete the disassembly of the conical valve 1.
[0100] Among them, steps S21 to S25 are the same as steps S11 to S15, and the specific operations can refer to the relevant description of steps S11 to S15 in the above text. It can be understood that before the cone valve 1 is hoisted, the cone valve 1 generally needs to be disassembled first. Therefore, the hoisting and disassembly of the cone valve 1 can actually use the same hoisting system for lowering or pulling up the cone valve 1. After the main anchor point 31, the pulling anchor point 32, the hoisting device 5, etc. are arranged on and near the dam, the cone valve 1 can be disassembled and the cone valve 1 can be hoisted and installed using these arranged main anchor points 31, the pulling anchor point 32 and the hoisting device 5.
[0101] Afterwards, step S26 is executed. When executing step S26, the first hoisting unit is required to lift the conical valve 1 to bear the weight of the conical valve 1, and then the connection between the conical valve 1 and the embedded part is disassembled. After the first hoisting unit bears the weight of the conical valve 1, the connection between the conical valve 1 and the embedded part is disassembled, which can reduce the compression of the bolts by the deadweight of the conical valve 1 and reduce the difficulty of disassembly. At the same time, it can also ensure that the conical valve 1 will not fall after being disassembled, ensuring the safety of the working environment.
[0102] Then, step S27 is continued to be executed, so as to pull up the removed conical valve 1 obliquely by coordinating the first winch unit and the second winch unit of the winch device 5, so that the conical valve 1 can move along the inclined surface at a distance of about 1m on the downstream side of the dam, thereby avoiding collision with the dam, and finally pulling up the conical valve 1 to the highest point, that is, the position where the pulley 4 is set on the downstream side of the dam crest 21.
[0103] Then continue to perform subsequent steps. At this time, it is necessary to switch the cone valve 1 from the hanging of the first hoisting unit to the hanging of the lifting device 6, and use the lifting device 6 to lift the cone valve 1 to the transport vehicle on the dam crest 21 to complete the disassembly of the cone valve 1. Specifically, first lower the hook of the lifting device 6 to the pulley 4, and the operator goes down to the cone valve 1 through the hanging ladder 24 hanging on the downstream side of the dam crest, and hangs the hook of the lifting device 6 on the cone valve 1. After that, the lifting device 6 lifts the cone valve 1 so that the lifting device 6 bears the weight of the cone valve 1. During this process, it is necessary to proceed slowly to ensure the safety of the lifting device 6 when bearing the weight of the cone valve 1, and then relax the winch device 5 at the same time to complete the relay of the lifting point. Finally, use the lifting device 6 to lift the cone valve 1 to the dam transport vehicle, unhook the pulley 4 and the hook of the lifting device 6, and the disassembly of the cone valve 1 can be completed.
[0104] The hoisting method and disassembly method of the conical valve located on the water conservancy dam of the present invention realizes lifting and lowering of the weight load of the conical valve 1 along an inclined trajectory by using a winch device 5 at a main anchor point 31 on the dam top 21 and a pulling anchor point 32 arranged on the mountain 23 outside the downstream side of the dam, so as to ensure that an unacceptable lifting amplitude overturning situation can be avoided when lifting with general lifting equipment that can be arranged on the dam top 21. In addition, the winch device 5 is used to bypass the pulling anchor point 32 and pull the conical valve 1 to the downstream side, so that the conical valve 1 will not touch the inclined surface on the downstream side of the dam during the descent. In the hoisting method of the present invention, in order to ensure the safety of the overall solution, the main anchor point 31 is set on the upstream side of the middle part of the dam crest 21, and the wire rope connected to the main anchor point 31 bypasses the dam crest 21, so that part of the load of the main anchor point 31 is shared by the dam crest 21, and the pulling anchor point 32 is set at the mountain 23 on the downstream side of the dam, which can ensure the outward pulling amplitude of the conical valve 1 when it is lowered, and the cost and safety success rate are combined to ensure that the overall technical solution can be 100% successful.
[0105] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A method for hoisting a cone valve on a water conservancy dam, characterized in that: include: Arrange the main anchor point on the upstream side of the middle part of the dam crest; The two ends of the wire rope are fixed to the main anchor point, guided through the dam crest to the downstream side, and a pulley is hung at one end on the downstream side; Arrange pulling anchor points on both sides of the mountain on the downstream side of the dam; A winch device is arranged at the step on the downstream side of the dam, the winch device includes a first winch unit and a second winch unit, the wire rope of the first winch unit passes around the pulley, and the wire rope of the second winch unit passes around the pulling anchor point; A lifting lug and a wind rope are arranged on the conical valve, and a lifting wire rope is arranged at the lifting lug; Use a lifting device to lift the cone valve from the dam crest to the pulley on the downstream side of the dam crest, and switch to the hoisting device to lift the cone valve; Coordinate and control the first and second winch units of the winch device to move the cone valve obliquely about 1 meter along the downstream slope of the dam to the vicinity of the target position, and use the windlass to stabilize the cone valve; Coordinate the first winch unit and the second winch unit to adjust and guide the cone valve to the cone valve installation position, use the wind rope to guide and adjust the guide bracket above the front end of the cone valve to the correct direction, and apply liquid sealant to the matching surface of the cone valve flange and the embedded part flange; Guide the valve sleeve running wheel into the guide rail until the conical valve roughly reaches the target position; Connect the conical valve flange to the embedded part flange and tighten the bolts. After the conical valve and embedded part are reliably connected, remove the hook. Adjust the conical valve and tighten it with bolts to the embedded flange to complete the lifting of the conical valve.
2. The hoisting method according to claim 1, characterized in that: The main anchor point and the pulling anchor point are each provided with at least two anchor points.
3. The hoisting method according to claim 1, characterized in that: The steel wire rope passing through the top of the dam is composed of two steel wire ropes tied together with a lock.
4. The hoisting method according to claim 1, characterized in that: The anchoring depth of the main anchor point and the pulling anchor point is not less than 400 mm.
5. The hoisting method according to claim 4, characterized in that: The main anchor point and the pulling anchor point are both formed by 8 M24×400 chemical anchors and 1 ear plate.
6. The hoisting method according to claim 1, characterized in that: At least two pulling anchor points are provided.
7. The hoisting method according to claim 6, characterized in that: The pulling anchor points are arranged on the mountains on both sides of the downstream side of the dam at a position where the elevation is higher than the installation elevation of the cone valve.
8. The hoisting method according to claim 6, characterized in that: The second hoisting machine assembly includes at least two hoists, and each pulling anchor point is wound with a steel wire rope of at least one hoisting machine.
9. The hoisting method according to claim 1, characterized in that: The wind rope is arranged on screw holes on both sides of the top of the conical valve.
10. The hoisting method according to claim 1, characterized in that: It also includes testing and verification of the main anchor points and the pulling anchor points, including: Use an anchor tension gauge to apply a tensioning force 1.2 times the pull-out force to the anchor to tension it; After dismantling the old conical valve, use the winch to lift the old conical valve. When it is fully loaded, lower the old conical valve to about 1 meter at the bottom of the river and keep it there for 10 minutes.
11. A method for disassembling a cone valve located on a water conservancy dam, characterized in that: include: Arrange the main anchor point on the upstream side of the middle part of the dam crest; The two ends of the wire rope are fixed to the main anchor point, guided through the dam top to the downstream side, and a pulley is hung at one end on the downstream side; Arrange pulling anchor points on both sides of the mountain on the downstream side of the dam; A winch device is arranged at the step on the downstream side of the dam, the winch device includes a first winch unit and a second winch unit, the wire rope of the first winch unit passes around the pulley, and the wire rope of the second winch unit passes around the pulling anchor point; A lifting lug and a wind rope are arranged on the conical valve, and a lifting wire rope is arranged at the lifting lug; The cone valve is connected with the first winch unit and the first winch unit is started to bear the weight of the cone valve, and the bolts connecting the cone valve and the embedded part are removed to separate the cone valve from the embedded part; Coordinate and control the first winch unit and the second winch unit to move the cone valve about 1 meter along the downstream slope of the dam and rise to the pulley on the downstream side of the dam crest; Lower the hook of the lifting device and hang it to the wire rope of the cone valve; The hoisting device lifts the conical valve, and at the same time releases the winch device, and uses the hoisting device to lift the conical valve onto the dam transport vehicle, unhooks the pulley and the hook of the hoisting device to complete the removal of the conical valve.