A metal smelting furnace

By using the cooling ring and temperature sensor to determine the crystallization height in the metal smelting furnace, combined with the lifting rod and sealing mechanism, the problem of complexity of electrode gap control is solved, achieving precise control of the electrode gap and improving cooling efficiency.

CN118565206BActive Publication Date: 2024-10-08BAOJI PENGXIN METAL MATERIALS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411060283.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-10-08
Estimated Expiration
2044-08-05

AI Technical Summary

Technical Problem

The electrode gap control device in the existing vacuum consumable arc furnace is complex, making it difficult to achieve precise control and affecting the quality of the smelting ingot.

Method used

By setting up a cooling ring in the metal smelting furnace, the temperature difference is used to determine the height of the crystallization end face, and combined with the lifting rod and temperature sensor, the electrode height is adjusted to achieve precise control of the electrode gap. At the same time, a sealing mechanism and a pressurization control mechanism are used to improve cooling efficiency. .

Benefits of technology

It achieves precise control of the electrode gap, improves the quality of the melted ingot, enhances the cooling efficiency, and simplifies the complexity of the electrode gap control device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118565206B_ABST
    Figure CN118565206B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of smelting furnaces, and in particular to a metal smelting furnace, which includes a furnace body, a crystallization zone is arranged at the bottom end of the furnace body, a cooling zone is sleeved on the outer surface of the crystallization zone, a vacuum connection port is connected and penetrated above the outer surface of the furnace body, and a cooling ring is sleeved on the outer surface of the crystallization zone in sequence from top to bottom. When detecting the crystallization height, the present invention can press the piston downward through the operation of the lifting rod, so that the medium enters the telescopic sleeve to squeeze the sliding plate to cover the through hole, and the vacuum device is connected to the vacuum exhaust pipe to form a cavity inside the isolation cover, at this time, isothermal cooling water is injected into the cooling ring from the water inlet end, and the cooling ring has a different contact position with the crystallization zone, and the closer the temperature is to the crystallization end face, the more obvious the difference is with the temperature below, and by monitoring the temperature of each cooling ring at the water outlet end, the height of the crystallization end can be determined, so that the signal can be collected for adjusting the electrode height.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of smelting furnaces, and in particular to a metal smelting furnace. Background Art

[0002] The vacuum consumable arc furnace is a type of vacuum metallurgical smelting equipment. The furnace body is a closed container, which is evacuated or filled with inert gas. After the electrodes introduced from the top of the furnace and the water-cooled crystallizer at the bottom of the furnace are energized and arced, an arc is generated, and the metal or alloy is melted by the heat of the arc and solidified in the crystallizer. The electrode is made of the smelted metal, which is called a "consumable electrode vacuum arc furnace". The product has few impurities, low gas content, good ingot structure, and excellent mechanical and physical properties. It is suitable for smelting high-melting-point metals, active metals, special steels and metals, especially titanium metal processing.

[0003] Precise control of the electrode gap (i.e. the distance between the two electrodes) is an important technical guarantee for improving the quality of ingots melted in a vacuum consumable arc furnace. An existing patent CN103045877B for an automatic arc starting device and control method for a vacuum consumable arc furnace discloses that "an auxiliary electrode is arranged above the consumable electrode, and the upper end of the auxiliary electrode is connected to the electrode rod, and the upper end of the electrode rod is connected to the transmission shaft; a differential / reducer is arranged on the upper end of the transmission shaft; the differential / reducer is connected to the feed motor and the fast motor; the programmable controller includes an output module, an input module, a CPU and a communication port; arc voltage measurement leads are respectively led out from the electrode rod and the shell of the furnace chamber, and the other end is connected to the signal transmitter, and then connected to the input module of the programmable controller; the voltmeter is connected in parallel with the signal transmitter; the displacement sensor is also connected to the input module; the output module and the input module are both connected to the motor controller". Through such a setting, the lifting and lowering of the electrode can be controlled, wherein the melting rate is calculated by the electrode weighing device, and the basic speed of the electrode descent is determined by the actual melting rate. In the process of electrode melting, not only the electrode becomes shorter, but also the precipitation height in the crystallizer increases. Therefore, simply controlling the electrode cannot accurately control the electrode gap, and the device for controlling the electrode gap is relatively complicated. Summary of the invention

[0004] In order to solve the problem that the electrode gap control device is relatively complicated, the present invention provides a metal smelting furnace.

[0005] A metal smelting furnace provided by the present invention adopts the following technical scheme: the metal smelting furnace includes a furnace body, a crystallization zone is arranged at the bottom end of the furnace body, a cooling zone is sleeved on the outer surface of the crystallization zone, a vacuum connection port is connected and penetrated above the outer surface of the furnace body, a group of cooling rings are sleeved on the outer surface of the crystallization zone, which are contacted sequentially from top to bottom, the cooling rings extend to the outside of the cooling zone, the water inlet end of the cooling ring is connected and penetrated by a water inlet sleeve, the water outlet end of the cooling ring is connected and penetrated by a water outlet sleeve, and a temperature sensor is arranged at the water outlet end of the cooling ring. Through such an arrangement, the height of the melting surface can be determined by utilizing the different temperatures of the water outlet end of the cooling ring.

[0006] Optionally, the outer surfaces of the water inlet and outlet ends of the cooling ring are sleeved with spacers, and a partition is fixedly installed in the middle of the spacer. Such an arrangement can reduce the influence of external temperature.

[0007] Optionally, an insulating cover wrapping the cooling ring is provided inside the cooling zone and located on the outer circle of the cooling ring. A through hole is opened on the surface of the insulating cover, and a sealing mechanism covering the through hole is fixedly installed on the outer surface of the insulating cover. The control end of the sealing mechanism is connected to and penetrates a pressurization control mechanism that controls the sealing mechanism to cover the through hole. A vacuum exhaust pipe is sleeved on the bottom end of the insulating cover, and the vacuum exhaust pipe is located at the inner end of the insulating cover. The other end of the vacuum exhaust pipe extends to the outside of the cooling zone. Through such an arrangement, the cooling ring can be located in a vacuum environment, thereby reducing the influence of the external environment.

[0008] Optionally, the sealing mechanism includes a telescopic sleeve, which is slidably connected to a sliding plate inside the telescopic sleeve, and the sliding plate is fixedly connected to the inner wall of the telescopic sleeve by a reset spring. A sealing cover is fixedly installed on the outer surface of the telescopic sleeve, and the sealing cover is fixedly connected to the isolation cover. The sliding plate is slidably sleeved on the outer surface of the sealing cover, and the sealing cover is connected and connected to the pressurization control mechanism. This method has a good sealing effect.

[0009] Optionally, the sealing mechanism includes a connecting sleeve, which is rotatably connected to a sealing plate inside the connecting sleeve, a center axis is fixedly installed in the middle of the sealing plate, an impact sleeve is fixedly installed on the top of the connecting sleeve, the center axis extends to the interior of the impact sleeve, a rotating plate is fixedly installed on the outer surface of the center axis located inside the impact sleeve, a fixed block is fixedly installed inside the impact sleeve, the rotating plate and the fixed block are fixedly connected by an extrusion spring, and the impact sleeve is connected to the pressurization control mechanism at the gap between the rotating plate and the fixed block. Through such an arrangement, the effect of accelerating the heat dissipation of cooling water can be achieved without playing a sealing role.

[0010] Optionally, there are multiple through holes, and the multiple through holes are equidistantly distributed in a ring shape. Such an arrangement can facilitate the flow of cooling water.

[0011] Optionally, the pressurization control mechanism includes an extrusion sleeve, which is slidably connected to the inside of the extrusion sleeve, and a lifting rod is fixedly installed on the top of the extrusion sleeve. The free end of the lifting rod extends to the inside of the extrusion sleeve and is fixedly connected to the piston. The input end of the extrusion sleeve is connected to and penetrated by a main pipe, which extends to the inner side of the cooling zone. The main pipe is connected and penetrated by a branch pipe to the sealing mechanism. Through such an arrangement, multiple gaps can be adapted.

[0012] Optionally, the cross-sectional shape of the sealing plate is a "Z" shape, and the shape of the connecting sleeve is adapted to the sealing plate. Such a configuration can achieve a sealing effect.

[0013] Optionally, the water inlet and outlet of the cooling ring are located in the same horizontal plane, and adjacent cooling rings are offset at the same angle in sequence. This arrangement can avoid the positions that cannot be cooled from being concentrated in the same vertical position.

[0014] In summary, the present invention includes the following beneficial technical effects:

[0015] 1. When the crystallization height needs to be detected in the metal smelting furnace, the piston is pressed down by the lifting rod, so that the medium enters the telescopic sleeve to squeeze the sliding plate to cover the through hole, and the vacuum device is connected to the vacuum exhaust pipe to form a cavity inside the isolation cover. At this time, isothermal cooling water is injected into the cooling ring from the water inlet end. Due to the different contact positions of the cooling ring with the crystallization zone, the closer the temperature is to the crystallization end face and the temperature below, the more obvious the difference is. By monitoring the temperature of each cooling ring at the water outlet end, the height of the crystallization end can be determined, so that the signal can be collected for adjusting the electrode height.

[0016] 2. The metal smelting furnace, the sealing mechanism includes a connecting sleeve, the internal rotation of the connecting sleeve is connected to a sealing plate, the middle of the sealing plate is fixedly installed with a central axis, the top of the connecting sleeve is fixedly installed with an impact sleeve, the central axis extends to the inside of the impact sleeve, the outer surface of the central axis located inside the impact sleeve is fixedly installed with a rotating plate, the inside of the impact sleeve is fixedly installed with a fixed block, the rotating plate and the fixed block are fixedly connected by an extrusion spring, and the impact sleeve is connected to the pressure control mechanism at the gap between the rotating plate and the fixed block. Through such an arrangement, when the central axis is squeezed by the medium, the rotating plate and the sealing plate can both rotate, thereby opening the through hole, and when the medium is extracted, it is reset under the action of the extrusion spring, and the action is repeated, and the sealing plate can swing periodically, thereby stirring the coolant, thereby improving the cooling efficiency.

[0017] 3. In the metal smelting furnace, the water inlet and outlet of the cooling ring are located in the same horizontal plane, and adjacent cooling rings are displaced at the same angle in sequence. This arrangement ensures that the position where the cooling ring cannot contact the crystallization zone is not on the same vertical line, thereby improving the cooling effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the structure of the present invention;

[0019] Figure 2 It is a half-section schematic diagram of the present invention;

[0020] Figure 3 It is a schematic diagram of the cooling zone of the present invention;

[0021] Figure 4 This is a schematic diagram of the cooling ring connection of the present invention;

[0022] Figure 5 A schematic diagram of the isolation cover of the present invention;

[0023] Figure 6 This is a schematic diagram of the connection of the telescopic sleeve of the present invention;

[0024] Figure 7 This is a schematic diagram of the connection of the pressurization control mechanism of the present invention;

[0025] Figure 8 Another schematic diagram of the isolation cover of the present invention;

[0026] Fig. 9 This is a schematic diagram of the sealing plate connection of the present invention.

[0027] 1. The furnace body; 2. The crystallization zone; 3. The cooling zone; 4. The vacuum connection port; 5. The cooling ring; 6. The temperature sensor; 7. The sealing mechanism; 8. The pressurization control mechanism; 9. The insulating cover; 10. The through hole; 11. The spacer; 12. The partition; 13. The vacuum exhaust pipe; 14. The water inlet sleeve; 15. The water outlet sleeve; 711. The telescopic sleeve; 712. The sliding plate; 713. The reset spring; 714. The sealing cover; 721. The connecting sleeve; 722. The sealing plate; 723. The center axis; 724. The impact sleeve; 725. The rotating plate; 726. The fixed block; 727. The extrusion spring; 801. The extrusion sleeve; 802. The piston; 803. The lifting rod; 804. The main pipe; 805. The branch pipe. DETAILED DESCRIPTION

[0028] The following combination Figure 1-Figure 9 The present invention is described in further detail.

[0029] An embodiment of the present invention discloses a metal smelting furnace, including a furnace body 1, a crystallization zone 2 is arranged at the bottom end of the furnace body 1, a cooling zone 3 is sleeved on the outer surface of the crystallization zone 2, a vacuum connection port 4 is connected and penetrated above the outer surface of the furnace body 1, a group of cooling rings 5 ​​are sleeved on the outer surface of the crystallization zone 2, which are contacted sequentially from top to bottom, the cooling ring 5 extends to the outside of the cooling zone 3, the water inlet end of the cooling ring 5 is connected and penetrated by a water inlet sleeve 14, the water outlet end of the cooling ring 5 is connected and penetrated by a water outlet sleeve 15, and a temperature sensor 6 is arranged at the water outlet end of the cooling ring 5.

[0030] The outer surfaces of the water inlet and outlet ends of the cooling ring 5 are sleeved with spacers 11 , and a partition plate 12 is fixedly installed in the middle of the spacer 11 . This arrangement can reduce the influence of the outer cooling water on the cooling ring 5 .

[0031] An insulating cover 9 wrapping the cooling ring 5 is arranged inside the cooling zone 3 and located on the outer circle of the cooling ring 5. A through hole 10 is opened on the surface of the insulating cover 9. A sealing mechanism 7 covering the through hole 10 is fixedly installed on the outer surface of the insulating cover 9. The control end of the sealing mechanism 7 is connected to and penetrates a pressurization control mechanism 8 which controls the sealing mechanism 7 to cover the through hole 10. A vacuum exhaust pipe 13 is sleeved on the bottom end of the insulating cover 9. The vacuum exhaust pipe 13 is located at the inner end of the insulating cover 9. The other end of the vacuum exhaust pipe 13 extends to the outside of the cooling zone 3. By setting the vacuum exhaust pipe 13, the internal water can be pumped out. By setting the insulating cover 9 and the sealing mechanism 7, a cavity can be formed between the insulating cover 9 and the crystallization zone 2, so that the cooling ring 5 is not affected by external cooling water.

[0032] The sealing mechanism 7 includes a telescopic sleeve 711, which is internally slidably connected to a sliding plate 712. The sliding plate 712 is fixedly connected to the inner wall of the telescopic sleeve 711 via a reset spring 713. A sealing cover 714 is fixedly installed on the outer surface of the telescopic sleeve 711. The sealing cover 714 is fixedly connected to the isolation cover 9. The sliding plate 712 is slidably sleeved on the outer surface of the sealing cover 714. The sealing cover 714 is connected to and penetrates the pressurization control mechanism 8. Through such an arrangement, the expansion and contraction of the sliding plate 712 can be utilized to control the opening and closing of the through hole 10. At the same time, such an arrangement can achieve a good sealing effect.

[0033] There are multiple through holes 10 , which are equidistantly distributed in a ring shape. This arrangement allows the multiple through holes 10 to facilitate the flow of cooling water.

[0034] The pressurization control mechanism 8 includes an extrusion sleeve 801, which is slidably connected to a piston 802 inside. A lifting rod 803 is fixedly installed on the top of the extrusion sleeve 801. The free end of the lifting rod 803 extends to the inside of the extrusion sleeve 801 and is fixedly connected to the piston 802. The input end of the extrusion sleeve 801 is connected to and penetrated by a main pipe 804. The main pipe 804 extends to the inner side of the cooling zone 3. The main pipe 804 is connected and penetrated by the sealing mechanism 7 through a branch pipe 805. Through such an arrangement, the piston 802 can be driven by the lifting rod 803 to extrude the internal medium to the outside, thereby driving the sealing mechanism 7 to work, so that the gap can be covered.

[0035] The water inlet and outlet ends of the cooling ring 5 are located in the same horizontal plane, and adjacent cooling rings 5 ​​are offset at the same angle. This arrangement ensures that the positions where the cooling ring 5 cannot contact the crystallization area 2 are not on the same vertical line, thereby improving the cooling effect.

[0036] The sealing mechanism 7 can also be replaced, where the sealing mechanism 7 includes a connecting sleeve 721, the interior of the connecting sleeve 721 is rotatably connected to a sealing plate 722, the middle of the sealing plate 722 is fixedly installed with a center shaft 723, the top of the connecting sleeve 721 is fixedly installed with an impact sleeve 724, the center shaft 723 extends to the interior of the impact sleeve 724, a rotating plate 725 is fixedly installed on the outer surface of the center shaft 723 located inside the impact sleeve 724, and a fixed block 726 is fixedly installed inside the impact sleeve 724.

[0037] The rotating plate 725 and the fixed block 726 are fixedly connected by the extrusion spring 727, and the impact sleeve 724 is connected to the pressure control mechanism 8 at the gap between the rotating plate 725 and the fixed block 726. With such an arrangement, when the central shaft 723 is squeezed by the medium, the rotating plate 725 and the sealing plate 722 can both rotate, so that the through hole 10 can be opened. At the same time, when the medium is extracted, it is reset under the action of the extrusion spring 727, and the action is repeated. The sealing plate 722 can swing periodically, thereby stirring the coolant, thereby improving the cooling efficiency.

[0038] The cross-sectional shape of the sealing plate 722 is a “Z” shape, and the shape of the connecting sleeve 721 is adapted to the sealing plate 722 . Such an arrangement can provide a better sealing effect.

[0039] The implementation principle of one embodiment of the present invention is as follows: the self-melting electrode melts in the crystallization zone 2 and cools and crystallizes. The discharge zone of the self-melting electrode has a higher temperature than the crystallization zone 2. When in use, the cooling liquid is circulated in the cooling ring 5 and in the cooling zone 3 to cool the crystallization zone 2. When the crystallization height needs to be detected, the piston 802 is pressed down by the lifting rod 803, so that the medium enters the telescopic sleeve 711 to squeeze the sliding plate 712 to cover the through hole 10, and the vacuum device is connected to the vacuum exhaust pipe 13 to form a cavity inside the isolation cover 9. At this time Isothermal cooling water is injected into the cooling ring 5 from the water inlet end. Since the cooling ring 5 has a different contact position with the crystallization zone 2, the temperature difference between the temperature at the crystallization end face and the temperature below is more obvious. By monitoring the temperature of each cooling ring 5 at the water outlet end, the height of the crystallization end can be determined, so that the signal can be collected for adjusting the electrode height. At the same time, through long-term detection, by determining the change rate of the cooling ring 5 corresponding to the crystallization end face, the melting speed of the electrode can be calculated, and then the signal is collected for adjusting the electrode height. After the detection is completed, the device is reset.

[0040] The above are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A metal smelting furnace, comprising a furnace body (1), wherein a crystallization zone (2) is arranged at the bottom end of the furnace body (1), a cooling zone (3) is sleeved on the outer surface of the crystallization zone (2), and a vacuum connection port (4) is connected and penetrated above the outer surface of the furnace body (1), characterized in that: The outer surface of the crystallization zone (2) is sleeved with a group of cooling rings (5) that are in contact with the crystallization zone (2) from top to bottom, and the cooling rings (5) extend to the outside of the cooling zone (3); The water inlet end of the cooling ring (5) is connected and penetrated by a water inlet sleeve (14), the water outlet end of the cooling ring (5) is connected and penetrated by a water outlet sleeve (15), and the water outlet end of the cooling ring (5) is provided with a temperature sensor (6); An insulating cover (9) wrapping the cooling ring (5) is arranged inside the cooling zone (3) and located on the outer ring of the cooling ring (5); a through hole (10) is opened on the surface of the insulating cover (9); a sealing mechanism (7) covering the through hole (10) is fixedly installed on the outer surface of the insulating cover (9); a control end of the sealing mechanism (7) is connected to and penetrates a pressurizing control mechanism (8) controlling the sealing mechanism (7) to cover the through hole (10); a vacuum exhaust pipe (13) is sleeved on the bottom end of the insulating cover (9); the vacuum exhaust pipe (13) is located at the inner end of the insulating cover (9); and the other end of the vacuum exhaust pipe (13) extends to the outside of the cooling zone (3).

2. A metal smelting furnace according to claim 1, characterized in that: The outer surfaces of the water inlet and water outlet ends of the cooling ring (5) are sleeved with spacers (11), and a partition plate (12) is fixedly mounted in the middle of the spacer (11).

3. A metal smelting furnace according to claim 1, characterized in that: The sealing mechanism (7) comprises a telescopic sleeve (711), a sliding plate (712) is slidably connected inside the telescopic sleeve (711), the sliding plate (712) is fixedly connected to the inner wall of the telescopic sleeve (711) via a return spring (713), a sealing cover (714) is fixedly installed inside the telescopic sleeve (711), the sealing cover (714) is fixedly connected to the isolation cover (9), the sliding plate (712) is slidably connected inside the sealing cover (714), and the telescopic sleeve (711) is connected to and communicates with the pressurization control mechanism (8).

4. A metal smelting furnace according to claim 1, characterized in that: The sealing mechanism (7) comprises a connecting sleeve (721), the interior of which is rotatably connected to a sealing plate (722), a central shaft (723) being fixedly mounted in the middle of the sealing plate (722), an impact sleeve (724) being fixedly mounted at the top of the connecting sleeve (721), the central shaft (723) extending into the interior of the impact sleeve (724), a rotating plate (725) being fixedly mounted on the outer surface of the central shaft (723) located inside the impact sleeve (724), a fixed block (726) being fixedly mounted inside the impact sleeve (724), the rotating plate (725) and the fixed block (726) being fixedly mounted between the rotating plate (725) and the fixed block (726) via a compression spring (727), and the impact sleeve (724) and the pressurization control mechanism (8) being connected at a gap between the rotating plate (725) and the fixed block (726).

5. A metal smelting furnace according to claim 3 or 4, characterized in that: The number of the through holes (10) is multiple, and the multiple through holes (10) are equidistantly distributed in an annular pattern.

6. A metal smelting furnace according to claim 4, characterized in that: The pressurization control mechanism (8) comprises an extrusion sleeve (801), the interior of the extrusion sleeve (801) is slidably connected to a piston (802), a lifting rod (803) is fixedly mounted on the top of the extrusion sleeve (801), the free end of the lifting rod (803) extends into the interior of the extrusion sleeve (801) and is fixedly connected to the piston (802), the input end of the extrusion sleeve (801) is connected to and penetrated by a main pipe (804), the main pipe (804) extends to the inside of the cooling zone (3), and the main pipe (804) and the sealing mechanism (7) are connected and penetrated by a branch pipe (805).

7. A metal smelting furnace according to claim 6, characterized in that: The cross-sectional shape of the sealing plate (722) is a "Z" shape, and the shape of the connecting sleeve (721) is compatible with the sealing plate (722).