A bridge pier settlement observation device and method

By using components such as large scale plates, limiting frames, and connecting ropes in the bridge pier settlement observation device, accurate observation of the bridge pier inclination angle and direction is achieved, which solves the problem of large errors in tilt settlement data in the existing technology and improves improve the accuracy and quality of settlement observations.

CN118565435BInactive Publication Date: 2024-10-18JINING LUNAN HIGHWAY ENG CO

Patent Information

Application Number
CN202411064619.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

It is difficult for existing bridge pier settlement observation devices to accurately measure the tilted settlement phenomenon of bridge piers, resulting in large errors in settlement observation data and affecting accuracy.

Method used

A bridge pier settlement observation device is designed, which uses components such as a large scale plate, a limit frame, a connecting plate, an installation piece, a T-shaped plug, a connecting rope, a load-bearing column, and a movable connector. The connecting rope and the load-bearing column enable the movable The connector moves to read the position of the digital scale on the small scale plate, enabling effective observation of the inclination angle and direction of the bridge pier, and reducing the probability of automatic movement of the small scale plate through elastic parts and lifting structures.

Benefits of technology

It effectively reduces the error of settlement observation data caused by the tilt of the bridge pier, improves the accuracy of settlement observation, ensures the observation quality of tilt angle data, reduces the probability of the large scale plate itself falling, and improves the quality of observation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118565435B_ABST
    Figure CN118565435B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of measurement technology, and specifically to a device and method for observing the settlement of a bridge pier. The device comprises a large scale plate, a connecting plate is arranged on the right side of the large scale plate, two limit frames are symmetrically installed on the left end of the connecting plate, the two limit frames are slidably connected to the outer end of the large scale plate, a mounting piece is arranged on the right end of the connecting plate, a mounting cylinder is arranged on the upper end of the large scale plate, a T-type plug is threadedly connected to the upper end of the mounting cylinder, the outer end surface of the mounting cylinder is recessed inward to form a plurality of through grooves, a connecting rope is installed in the middle part of the lower end of the T-type plug, a load-bearing column is arranged at the lower end of the connecting rope, a plurality of movable connectors are equidistantly arranged on the outer end of the load-bearing column, and a plurality of small scale plates are respectively arranged toward the outer ends of the plurality of movable connectors. The design realizes effective observation of the inclination angle data and direction of the bridge pier, effectively reduces the error probability of the settlement observation data caused by the inclination of the bridge pier in a certain direction, effectively ensures the observation quality of the inclination angle data, and improves the settlement observation accuracy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a bridge pier settlement observation device and method, belonging to the technical field of measurement. Background Art

[0002] A bridge pier is a building that supports the superstructure of a bridge. A bridge pier is generally built on the ground, which makes it easy for the bridge pier to sink. In order to ensure the safety of the bridge, a bridge pier settlement observation device is generally used to regularly observe and collect the pier settlement data. The existing bridge pier settlement observation device generally consists of a clamping structure and a scale movably installed at the outer end of the clamping structure.

[0003] When in use, first install the clamping structure on the outer end of the pier, and make the ruler fit on the ground. When the pier settles, relative movement will occur between the ruler and the clamping structure, thereby generating movement data. The settlement data can be analyzed based on the movement data to realize the pier settlement observation operation.

[0004] However, the scale mainly observes the settlement data of bridge piers in the vertical direction, and bridge piers are prone to inclined settlement, and the inclination direction of the piers cannot be determined in advance, resulting in a high probability of error in the settlement data observed by the scale, which will affect the accuracy of settlement observation. Summary of the invention

[0005] In view of the problems in the prior art, the present invention provides a pier settlement observation device and method.

[0006] The technical solution adopted by the present invention to solve the technical problem is: a pier abutment settlement observation device, comprising a large scale plate, a connecting plate is arranged on the right side of the large scale plate, and the large scale plate is arranged vertically, two limit frames are symmetrically installed on the left end of the connecting plate, and the two limit frames are slidably connected to the outer end of the large scale plate, a mounting piece is arranged on the right end of the connecting plate, and the mounting piece is sleeved on the outer end of the pier abutment;

[0007] The upper end of the large scale plate is provided with a mounting tube, the upper end of the mounting tube is threadedly connected to a T-shaped plug, and the vertical portion of the T-shaped plug extends into the mounting tube, the outer end surface of the mounting tube is inwardly recessed to form a plurality of through grooves, and the through grooves extend into the inner wall of the mounting tube, a connecting rope is installed in the middle of the lower end of the T-shaped plug, a load-bearing column is provided at the lower end of the connecting rope, and a plurality of movable connectors are equidistantly provided at the outer end of the load-bearing column;

[0008] A plurality of small scale plates are respectively arranged at the outer ends of the plurality of movable connectors, and the plurality of small scale plates respectively penetrate a plurality of through slots, and extrusion parts are respectively arranged at the top ends inside the plurality of through slots, and the lower ends of the plurality of extrusion parts are respectively fitted with the upper ends of the plurality of small scale plates, and functional parts are respectively installed at the bottom ends inside the plurality of through slots, and the upper ends of the plurality of functional parts are respectively fitted with the lower ends of the plurality of small scale plates.

[0009] Furthermore, the functional part includes a T-frame, the vertical portion of the T-frame is installed on the bottom end of the through groove, the upper end of the transverse portion of the T-frame is equidistantly provided with fixed portions of multiple first rolling components, and the movable portions of the multiple first rolling components are all rollingly connected to the lower end of the small scale plate.

[0010] Further, the extrusion member includes a first elastic member, the first elastic member is mounted on the top end of the through slot, and a mounting plate is disposed at the lower end of the first elastic member;

[0011] The fixed part of the second rolling member is installed at the lower end of the mounting plate, and the movable part of the second rolling member is rollingly connected to the upper end of the small scale plate. A telescopic rod is arranged between the upper end of the mounting plate and the top end of the through groove, and the telescopic rod is located in the first elastic member.

[0012] Furthermore, the four outer end surfaces of the large scale plate are recessed inward to form grooves, and the grooves are arranged along the length direction of the large scale plate. The four inner wall surfaces of the limit frame are provided with fixed parts of the third rolling member, and the movable part of the third rolling member is rollingly connected to the grooves.

[0013] Furthermore, the front and rear ends of the large scale plate are both fitted with indicator plates, and the indicator plates are arranged horizontally, and the two indicator plates are respectively installed on the front and rear ends of the connecting plate, and the two indicator plates are located between the two limit frames.

[0014] Further, the mounting member includes a mounting clip and a fixing clip, the mounting clip is attached to the left outer end of the pier, the connecting plate is arranged on the middle of the left end of the mounting clip, the fixing clip is attached to the right outer end of the pier, and the fixing clip is located on the right side of the mounting clip;

[0015] T-shaped plates are arranged on both the front and rear sides of the bridge pier, and the vertical part of the T-shaped plate is located between the installation clamp and the fixing clamp, the upper end of the transverse part of the T-shaped plate is in contact with the installation clamp and the fixing clamp, the left end of the vertical part of the T-shaped plate is rotatably connected to the cylinder, and the cylinder passes through the T-shaped plate, and the cylinder is located between the installation clamp and the fixing clamp;

[0016] The left end of the cylinder is threadedly connected to a first bolt, and the rod of the first bolt extends into the cylinder, the first bolt passes through the mounting clamp, and the cap of the first bolt fits on the left end of the mounting clamp, the right end of the cylinder is threadedly connected to a second bolt, and the rod of the second bolt extends into the cylinder, the second bolt is located on the right side of the first bolt, the second bolt passes through the fixing clamp, and the cap of the second bolt fits on the right end of the fixing clamp.

[0017] Furthermore, annular operating plates are symmetrically arranged at the outer end of the cylinder, and the two annular operating plates are located on the left and right sides of the vertical portion of the T-shaped plate, and the annular operating plates are located above the transverse portion of the T-shaped plate.

[0018] A method for using a bridge pier settlement observation device comprises the following steps:

[0019] The first step is assembly. First, fit the installation clamp to the appropriate position of the left outer end of the bridge pier, and make the large scale plate vertical, and fit the fixing clamp to the right outer end of the bridge pier. Then place the two T-shaped plates between the installation clamp and the fixing clamp, and make the two T-shaped plates located on the front and rear sides of the bridge pier. Then, pass the first bolt through the installation clamp and connect it to the cylinder. Then, pass the second bolt through the fixing clamp and connect it to the cylinder. Use the annular operating plate to rotate the cylinder, and then make the cylinder threadedly connected with the first bolt and the second bolt, so that the installation clamp and the fixing clamp are fastened and installed on the outer end of the bridge pier. At this time, the number mark position indicated by the indicator plate on the large scale plate is the straight line reference point, and the zero point of the small scale plate extending from the installation cylinder is the angle reference point.

[0020] The second step is observation. First, read the position of the number mark indicated by the indicator plate on the scale plate, and compare and calculate it with the straight line reference point, and record the calculated straight line movement data. Then observe the distance of the number marks extending from multiple small scale plates, and compare and calculate it with the angle reference point, and record the calculated inclination angle data and direction. Calculate the settlement distance of the bridge pier based on the straight line movement data, inclination angle data and direction.

[0021] Beneficial effects of the present invention:

[0022] 1. Through the connecting rope and the load-bearing column, the movable connector located in the offset direction will move outward, and then the corresponding small scale plate will move outward along the corresponding through groove, so that the digital position on the small scale plate extending out of the installation tube can be read, so as to realize the effective observation of the inclination angle data and direction of the bridge pier, effectively reduce the error probability of settlement observation data caused by the inclination of the bridge pier in a certain direction, effectively ensure the observation quality of the inclination angle data, and improve the settlement observation accuracy.

[0023] 2. The multiple second bull's eyeballs installed on the upper end of the T-frame will lift the small scale plate, and use the first elastic member and the mounting plate to clamp the small scale plate, effectively reducing the probability of automatic movement of the small scale plate and effectively ensuring the observation quality of the tilt angle data.

[0024] 3. Through the second elastic member and the movable plate, the top rod is used to squeeze the outer end of the pier, so that the structure formed by the installation clamp and the fixing clamp is lifted by the auxiliary structure in an inclined state formed by the straight tube and the top rod, thereby effectively reducing the probability of the structure formed by the installation clamp and the fixing clamp moving down along the surface of the pier, and effectively ensuring the observation quality.

[0025] 4. The lifting structure formed by the base plate and the universal coupling will lift the large scale plate. The design of the base plate increases the contact area between the large scale plate and the ground, effectively reducing the probability of the large scale plate itself falling, effectively ensuring the observation quality, and the universal coupling can make the large scale plate tilt as the bridge pier tilts, effectively ensuring the observation quality of the tilt angle data. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments made with reference to the following drawings:

[0027] Figure 1 It is a schematic structural diagram of an embodiment of a bridge pier settlement observation device of the present invention;

[0028] Figure 2 A cross-sectional view of a bridge pier settlement observation device according to the present invention;

[0029] Figure 3 for Figure 2 Enlarged view of part A in the middle;

[0030] Figure 4 A three-dimensional diagram of an installation tube in a bridge pier settlement observation device of the present invention;

[0031] Figure 5 It is an assembly diagram of a small scale plate, a T-shaped plug, a connecting rope and a load-bearing column in a bridge pier settlement observation device of the present invention;

[0032] Figure 6 It is an assembly diagram of a limit frame and a connection plate in a bridge pier settlement observation device of the present invention;

[0033] Figure 7 It is a schematic diagram of another embodiment of a bridge pier settlement observation device of the present invention;

[0034] Figure 8 A three-dimensional diagram of a T-shaped plate in a bridge pier settlement observation device according to the present invention;

[0035] Fig. 9 It is a front view of a T-shaped plate in a pier settlement observation device of the present invention;

[0036] Fig.10 for Fig. 9 Cross-sectional view along the BB direction;

[0037] Fig.11 for Fig. 9 Sectional view along CC direction;

[0038] Fig.12 for Fig.10 Enlarged view of part D in the middle.

[0039] In the figure: 1, fixing clamp, 2, T-plate, 3, mounting clamp, 4, large scale plate, 5, limiting frame, 6, small scale plate, 7, mounting cylinder, 8, T-type plug, 9, bridge pier, 21, first bolt, 22, straight cylinder, 23, push rod, 24, second bolt, 25, annular operating plate, 26, cylinder, 41, universal coupling, 42, base plate, 43, groove, 51, indicator plate, 52, connecting plate, 53, first bull's eyeball, 61, movable connector, 71, through groove, 72, T-frame, 73, second bull's eyeball, 74, third bull's eyeball, 75, mounting plate, 76, first elastic member, 77, telescopic rod, 81, connecting rope, 82, load-bearing column, 221, second elastic member, 222, movable plate, 223, retaining spring. DETAILED DESCRIPTION

[0040] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.

[0041] Embodiment 1: Figure 1 , Figure 2 , Figure 6 , Figure 8 , Fig. 9 and Fig.11 As shown, a settlement observation device for a bridge pier 9 is provided, comprising a large scale plate 4 arranged vertically, two limit frames 5 slidably connected to the outer ends of the large scale plate 4 are symmetrically installed on the left end of a connecting plate 52 located on the right side of the large scale plate 4, the two limit frames 5 are used in conjunction with each other to guide the movement of the large scale plate 4, and a mounting carrier is provided for the limit frames 5 through the connecting plate 52;

[0042] The four outer end surfaces of the large scale plate 4 are all recessed inward to form grooves 43 arranged along the length direction of the large scale plate 4. The grooves 43 are used to guide the movement of the third rolling member. The fixed parts of the third rolling member whose four movable parts are rollingly connected with the grooves 43 are respectively arranged on the four inner wall surfaces of the limit frame 5. The third rolling member assists the relative movement between the limit frame 5 and the large scale plate 4. The third rolling member can adopt the first bull's eyeball 53.

[0043] Two indicator plates 51 installed at the front and rear ends of the connecting plate 52 and arranged transversely and located between the two limit frames 5 are respectively attached to the front and rear ends of the large scale plate 4. The indicator plates 51 are used to indicate the position of the numbers on the large scale plate 4 for easy observation. The connecting plate 52 is set on the middle part of the left end of the installation clip 3 attached to the left outer end of the pier 9. The installation clip 3 provides an installation carrier for the connecting plate 52.

[0044] The fixing clamp 1 located on the right side of the installation clamp 3 is attached to the outer end of the right part of the bridge pier 9. The installation clamp 3 is used in conjunction with the fixing clamp 1 to fasten the connection plate 52 and the bridge pier 9. The T-shaped plate 2 with two vertical parts located between the installation clamp 3 and the fixing clamp 1 and the upper end of the horizontal part attached to the installation clamp 3 and the fixing clamp 1 is respectively arranged on the front and rear sides of the bridge pier 9. The T-shaped plate 2 is used to provide an installation carrier for the cylinder 26 on the one hand, and to position and install the installation clamp 3 and the fixing clamp 1 on the other hand.

[0045] The cylinder 26 that penetrates the T-shaped plate 2 and is located between the mounting clamp 3 and the fixing clamp 1 is rotatably connected to the left end of the vertical portion of the T-shaped plate 2. The cylinder 26 provides a mounting carrier for the annular operating plate 25 and other components. Two annular operating plates 25 located on the left and right sides of the vertical portion of the T-shaped plate 2 and above the horizontal portion of the T-shaped plate 2 are symmetrically arranged on the outer end of the cylinder 26. The cylinder 26 can be rotated by the annular operating plate 25.

[0046] The first bolt 21, whose rod portion extends into the cylinder 26 and passes through the mounting clamp 3 and whose cap portion fits the left end of the mounting clamp 3, is threadedly connected to the left end of the cylinder 26, and the second bolt 24, whose rod portion extends into the cylinder 26 and is located on the right side of the first bolt 21 and passes through the fixing clamp 1 and whose cap portion fits the right end of the fixing clamp 1, is threadedly connected to the right end of the cylinder 26. The first bolt 21, the second bolt 24 and the cylinder 26 are used in combination to securely install the mounting clamp 3 and the fixing clamp 1 on the bridge pier 9.

[0047] When in use, firstly attach the installation clip 3 to the appropriate position of the left outer end of the bridge pier 9, and make the large scale plate 4 in a vertical state, then attach the fixing clip 1 to the right outer end of the bridge pier 9, and then place the two T-shaped plates 2 between the installation clip 3 and the fixing clip 1, so that the two T-shaped plates 2 are located on the front and rear sides of the bridge pier 9, and make the installation clip 3 and the fixing clip 1 both attach to the upper end of the horizontal part of the T-shaped plate 2, so as to position and install the installation clip 3 and the fixing clip 1;

[0048] Then the first bolt 21 passes through the mounting clamp 3 and is in contact with the cylinder 26, and then the second bolt 24 passes through the fixing clamp 1 and is in contact with the cylinder 26. Then the annular operating plate 25 is rotated to rotate the cylinder 26. Since the cylinder 26 is threadedly connected with the first bolt 21 and the second bolt 24 respectively, the rotation of the cylinder 26 simultaneously moves the first bolt 21 and the second bolt 24 inward.

[0049] Then the installation clamp 3 and the fixing clamp 1 are moved inwards and the bridge pier 9 is clamped, so that the structure formed by the installation clamp 3 and the fixing clamp 1 is fastened and installed on the outer end of the bridge pier 9, and then the large scale plate 4 is connected with the bridge pier 9, so that the large scale plate 4 and the bridge pier 9 are conveniently disassembled and assembled, and at this time, the large scale plate 4 is in contact with the ground;

[0050] When the pier 9 sinks, the structure formed by the mounting clamp 3, the fixing clamp 1 and the connecting plate 52 will drop, and then the two limit frames 5 and the two indicator plates 51 will move down along the large scale plate 4. At this time, the indicator plate 51 is at the numerical position indicated on the large scale plate 4, and the linear movement data caused by the settlement of the pier 9 can be obtained.

[0051] like Figure 1-Figure 5 As shown, the mounting tube 7 is arranged on the upper end of the large scale plate 4, and a mounting carrier is provided for components such as the T-shaped plug 8 through the mounting tube 7, and the T-shaped plug 8 whose vertical portion extends into the mounting tube 7 is threadedly connected to the upper end of the mounting tube 7, and a mounting carrier is provided for the connecting rope 81 through the T-shaped plug 8;

[0052] The outer end surface of the installation tube 7 is inwardly recessed to form a plurality of through grooves 71 extending into the inner wall of the installation tube 7. The through grooves 71 are used to extend the small scale plate 6 out of the installation tube 7. The connecting rope 81 is installed on the middle part of the lower end of the T-shaped plug 8. The load-bearing column 82 is connected to the T-shaped plug 8 through the connecting rope 81. The load-bearing column 82 is set on the lower end of the connecting rope 81. The small scale plate 6 is moved through the load-bearing column 82.

[0053] A plurality of movable connectors 61 are equidistantly arranged on the outer end of the load-bearing column 82, and the load-bearing column 82 and the small scale plate 6 are movably connected through the movable connector 61. A plurality of small scale plates 6 penetrating the through grooves 71 are respectively arranged on the outer ends of the plurality of movable connectors 61, and the small scale plates 6 are used to observe the inclination angle and direction of the bridge pier 9.

[0054] When the bridge pier 9 sinks obliquely, the structure formed by the mounting clamp 3, the fixing clamp 1 and the connecting plate 52 will tilt, and the load-bearing column 82 will deviate and become vertical under the weight of the load-bearing column 82.

[0055] During the displacement process, the load-bearing column 82 causes the movable connector 61 located in the displacement direction to move outward, thereby causing the corresponding small scale plate 6 to move outward along the corresponding through slot 71, so that the digital position on the small scale plate 6 extending out of the mounting tube 7 can be read;

[0056] It realizes effective observation of the inclination angle data and direction of the bridge pier 9, effectively reduces the error probability of settlement observation data caused by the inclination of the bridge pier 9 in a certain direction, effectively ensures the observation quality of the inclination angle data, and improves the settlement observation accuracy.

[0057] like Figure 2 and Figure 3As shown, a plurality of first elastic members 76 are respectively mounted on the top ends of the inner parts of the plurality of through slots 71, and a plurality of mounting plates 75 located in the through slots 71 are respectively arranged on the lower ends of the plurality of first elastic members 76, and the mounting plates 75 are movably mounted in the through slots 71 through the first elastic members 76. The first elastic members 76 can be springs, and the mounting plates 75 are used to provide mounting carriers for the second rolling members;

[0058] The fixed part of the second rolling member whose movable part is rollingly connected to the upper end of the small scale plate 6 is installed on the lower end of the mounting plate 75, and the mounting plate 75 and the small scale plate 6 are movably connected through the second rolling member. The second rolling member can be a third bull's eye 74, and the telescopic rod 77 located in the first elastic member 76 is arranged between the upper end of the mounting plate 75 and the top end of the through groove 71, and the movement of the mounting plate 75 is guided by the telescopic rod 77;

[0059] The vertical parts of multiple T-frames 72 are respectively installed on the inner bottom ends of multiple through grooves 71. Through the T-frames 72, a mounting carrier is provided for the first rolling member, and the fixed parts of the first rolling members whose multiple movable parts are rollingly connected to the lower ends of the small scale plates 6 are equidistantly arranged on the upper ends of the transverse parts of the T-frames 72. Through the first rolling member, on the one hand, the small scale plate 6 is lifted, and on the other hand, the small scale plate 6 is assisted to move. The first rolling member can use a second bull's eye 73.

[0060] The multiple second bull's eyeballs 73 installed on the upper end of the T-shaped frame 72 will lift the small scale plate 6, and the first elastic member 76 is in a compressed state, so that the first elastic member 76 itself has an elastic force, and the elastic force of the first elastic member 76 will exert a downward force on the mounting plate 75, thereby clamping the small scale plate 6, effectively reducing the probability of automatic movement of the small scale plate 6, and effectively ensuring the observation quality of the tilt angle data.

[0061] Embodiment 2: A mounting tube 7 and other components are arranged on the upper end of the large scale plate 4 to realize observation of the inclination angle data and direction of the bridge pier 9. However, the large scale plate 4 is easily inserted into the ground due to the weight of the mounting tube 7 and other components, resulting in a high probability that the large scale plate 4 itself falls, affecting the observation quality. In addition, a clamping structure formed by the mounting clamp 3 and the fixing clamp 1 is clamped to the outer end of the bridge pier 9 to realize a movable connection between the large scale plate 4 and the bridge pier 9. However, the clamping structure is prone to downward movement when in a clamped state for a long time, which affects the observation quality.

[0062] In order to solve the above problems, Figure 7-Figure 12As shown, a plurality of straight tubes 22 located between the fixing clamp 1 and the installation clamp 3 and arranged in an inclined manner with a high outside and a low inside are equidistantly arranged on the inner end of the T-shaped plate 2, and the straight tubes 22 are used to provide installation space for components such as the mandrel 23, and the mandrel 23 which is attached to the outer end of the bridge pier 9 and extends into the straight tube 22 and is arranged in an inclined manner with a high outside and a low inside is movably arranged on the inner end of the straight tube 22, and the outer end of the bridge pier 9 is squeezed by the mandrel 23;

[0063] The movable plate 222 installed at the outer end of the push rod 23 is slidably connected in the straight tube 22, and the movable plate 222 is used to provide a mounting carrier for the push rod 23 and other components, and the second elastic member 221 is arranged between the outer end of the movable plate 222 and the inner outer wall of the straight tube 22, and the push rod 23 can be pushed inward by the second elastic member 221, and the second elastic member 221 can be a spring;

[0064] The inner wall of the straight tube 22 is recessed outward to form a slot, and the slot provides an installation space for the clamping spring 223. The clamping spring 223 located outside the push rod 23 and inside the movable plate 222 is assembled on the slot. The clamping spring 223 is used to restrict the installation between the movable plate 222 and the straight tube 22, so that the push rod 23 and the straight tube 22 can be easily disassembled.

[0065] The universal coupling 41 is set at the lower end of the large scale plate 4. The large scale plate 4 and the base plate 42 are movably connected through the universal coupling 41, and the base plate 42 located outside the pier 9 is installed on the other end of the universal coupling 41. The large scale plate 4 can be lifted through the base plate 42.

[0066] When the structure formed by the installation clamp 3 and the fixing clamp 1 is fastened to the outer end of the pier 9, the second elastic member 221 is in a compressed state, so that the second elastic member 221 itself has elastic force, and the elastic force of the second elastic member 221 exerts an inward force on the movable plate 222 and the top rod 23, so that the top rod 23 squeezes the outer end of the pier 9;

[0067] The structure formed by the installation clamp 3 and the fixing clamp 1 is lifted by using the auxiliary structure in an inclined state formed by the straight tube 22 and the top rod 23, which effectively reduces the probability that the structure formed by the installation clamp 3 and the fixing clamp 1 moves downward along the surface of the bridge pier 9, and effectively ensures the observation quality;

[0068] When in use, first place the base plate 42 on the ground close to the bridge pier 9. At this time, the lifting structure formed by the base plate 42 and the universal coupling 41 will lift the large scale plate 4. The design of the base plate 42 increases the contact area between the large scale plate 4 and the ground, effectively reducing the probability of the large scale plate 4 itself falling, effectively ensuring the observation quality, and the universal coupling 41 can make the large scale plate 4 tilt as the bridge pier 9 tilts, effectively ensuring the observation quality of the tilt angle data.

[0069] A method for using a bridge pier 9 settlement observation device comprises the following steps:

[0070] The first step is assembly. First, fit the installation clamp 3 to the appropriate position of the left outer end of the bridge pier 9, and make the large scale plate 4 vertical, and fit the fixing clamp 1 to the right outer end of the bridge pier 9, then place the two T-shaped plates 2 between the installation clamp 3 and the fixing clamp 1, and make the two T-shaped plates 2 located on the front and rear sides of the bridge pier 9, then penetrate the first bolt 21 through the installation clamp 3 and connect it to the cylinder 26, then penetrate the second bolt 24 through the fixing clamp 1 and connect it to the cylinder 26, and use the annular operating plate 25 to rotate the cylinder 26, so that the cylinder 26 is threadedly connected with the first bolt 21 and the second bolt 24, so that the installation clamp 3 and the fixing clamp 1 are fastened and installed on the outer end of the bridge pier 9. At this time, the numerical position indicated by the indicator plate 51 on the large scale plate 4 is the straight line reference point, and the zero point of the small scale plate 6 extending from the installation cylinder 7 is the angle reference point;

[0071] The second step is observation. First, read the digital position indicated by the indicator plate 51 on the scale plate, and compare and calculate it with the straight line reference point, and record the linear movement data calculated by comparison. Then observe the digital distances extending from multiple small scale plates 6, and compare and calculate it with the angle reference point, and record the inclination angle data and direction calculated by comparison. Finally, calculate the settlement distance of the pier 9 based on the straight line movement data, inclination angle data and direction.

[0072] Although this specification is described according to implementation modes, not every implementation mode includes only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A bridge pier settlement observation device, characterized in that: It comprises a large scale plate (4), a connecting plate (52) is arranged on the right side of the large scale plate (4), and the large scale plate (4) is arranged vertically, two limit frames (5) are symmetrically installed on the left end of the connecting plate (52), and the two limit frames (5) are both slidably connected to the outer end of the large scale plate (4), and a mounting piece is arranged on the right end of the connecting plate (52), and the mounting piece is sleeved on the outer end of the bridge pier (9); A mounting tube (7) is arranged at the upper end of the large scale plate (4), the upper end of the mounting tube (7) is threadedly connected to a T-shaped plug (8), and the vertical portion of the T-shaped plug (8) extends into the mounting tube (7), the outer end surface of the mounting tube (7) is inwardly recessed to form a plurality of through grooves (71), and the through grooves (71) extend into the inner wall of the mounting tube (7), a connecting rope (81) is installed at the middle of the lower end of the T-shaped plug (8), a bearing column (82) is arranged at the lower end of the connecting rope (81), and a plurality of movable connectors (61) are equidistantly arranged at the outer end of the bearing column (82); A plurality of small scale plates (6) are respectively arranged at the outer ends of the plurality of movable connectors (61), and the plurality of small scale plates (6) respectively penetrate a plurality of through slots (71). An extrusion piece is arranged at the top of the inner part of the plurality of through slots (71), and the lower ends of the plurality of extrusion pieces are respectively fitted with the upper ends of the plurality of small scale plates (6). Functional parts are installed at the bottom ends of the inner part of the plurality of through slots (71), and the upper ends of the plurality of functional parts are respectively fitted with the lower ends of the plurality of small scale plates (6); The functional part comprises a T-shaped frame (72), the vertical portion of the T-shaped frame (72) being mounted on the inner bottom end of the through groove (71), the upper end of the transverse portion of the T-shaped frame (72) being equidistantly provided with a plurality of fixed portions of first rolling members, and the movable portions of the plurality of first rolling members being all rollingly connected to the lower end of the small scale plate (6); The extrusion member comprises a first elastic member (76), the first elastic member (76) being mounted on the inner top end of the through slot (71), a mounting plate (75) being arranged at the lower end of the first elastic member (76), a fixed portion of a second rolling member being mounted at the lower end of the mounting plate (75), and a movable portion of the second rolling member being rollingly connected to the upper end of the small scale plate (6), a telescopic rod (77) being arranged between the upper end of the mounting plate (75) and the inner top end of the through slot (71), and the telescopic rod (77) being located in the first elastic member (76).

2. The pier settlement observation device according to claim 1 is characterized in that: The four outer end surfaces of the large scale plate (4) are all recessed inwards to form grooves (43), and the grooves (43) are arranged along the length direction of the large scale plate (4). The four inner wall surfaces of the limiting frame (5) are all provided with fixed parts of the third rolling member, and the movable part of the third rolling member is rollingly connected to the grooves (43).

3. The pier abutment settlement observation device according to claim 1, characterized in that: The front and rear ends of the large scale plate (4) are both fitted with an indicator plate (51), and the indicator plates (51) are arranged in a transverse manner. The two indicator plates (51) are respectively mounted on the front and rear ends of the connecting plate (52), and the two indicator plates (51) are located between the two limit frames (5).

4. The pier settlement observation device according to claim 1, characterized in that: The mounting member comprises a mounting clip (3) and a fixing clip (1), wherein the mounting clip (3) is attached to the left outer end of the bridge pier (9), the connecting plate (52) is arranged on the middle of the left end of the mounting clip (3), the fixing clip (1) is attached to the right outer end of the bridge pier (9), and the fixing clip (1) is located directly to the right of the mounting clip (3); T-shaped plates (2) are arranged on both the front and rear sides of the bridge pier (9), and the vertical portion of the T-shaped plate (2) is located between the mounting clamp (3) and the fixing clamp (1), the upper end of the transverse portion of the T-shaped plate (2) is in contact with the mounting clamp (3) and the fixing clamp (1), the left end of the vertical portion of the T-shaped plate (2) is rotatably connected to a cylinder (26), and the cylinder (26) passes through the T-shaped plate (2), and the cylinder (26) is located between the mounting clamp (3) and the fixing clamp (1); The left end of the cylinder (26) is threadedly connected to the first bolt (21), and the rod of the first bolt (21) extends into the cylinder (26); the first bolt (21) passes through the mounting clamp (3), and the cap of the first bolt (21) fits on the left end of the mounting clamp (3); the right end of the cylinder (26) is threadedly connected to the second bolt (24), and the rod of the second bolt (24) extends into the cylinder (26); the second bolt (24) is located on the right side of the first bolt (21); the second bolt (24) passes through the fixing clamp (1), and the cap of the second bolt (24) fits on the right end of the fixing clamp (1).

5. The bridge pier settlement observation device according to claim 4 is characterized in that: An annular operating plate (25) is symmetrically arranged at the outer end of the cylinder (26), and the two annular operating plates (25) are located on the left and right sides of the vertical portion of the T-shaped plate (2), and the annular operating plates (25) are located above the horizontal portion of the T-shaped plate (2).

6. The method for using the pier settlement observation device according to any one of claims 1 to 5, characterized in that: The following steps are involved: The first step is assembly. First, fit the mounting clamp (3) to the appropriate position of the left outer end of the bridge pier (9), and make the large scale plate (4) vertical. Then fit the fixing clamp (1) to the right outer end of the bridge pier (9). Then, place the two T-shaped plates (2) between the mounting clamp (3) and the fixing clamp (1), and make the two T-shaped plates (2) located on the front and rear sides of the bridge pier (9). Then, insert the first bolt (21) through the mounting clamp (3) and make it contact with the cylinder (26). Then, insert the second bolt (24 ) penetrates the fixing clamp (1) and contacts and connects with the cylinder (26), and uses the annular operating plate (25) to rotate the cylinder (26), thereby threading the cylinder (26) with the first bolt (21) and the second bolt (24), so that the mounting clamp (3) and the fixing clamp (1) are fastened and installed on the outer end of the bridge pier (9), at which time the numerical position indicated by the indicator plate (51) on the large scale plate (4) is the straight line reference point, and the zero point of the small scale plate (6) extending from the mounting cylinder (7) is the angle reference point; The second step is observation. First, read the numerical position indicated by the indicator plate (51) on the scale plate, and compare and calculate it with the straight line reference point, and record the linear movement data calculated by comparison. Then observe the numerical distance extended from the multiple small scale plates (6), and compare and calculate it with the angle reference point, and record the inclination angle data and direction calculated by comparison. Then, calculate the settlement distance of the bridge pier (9) based on the straight line movement data, inclination angle data and direction.

Citation Information

Patent Citations

  • Inclined drill hole water level measuring device

    CN110318738A

  • Bridge pier appearance detection device and bridge pier detection method

    CN113984012A

  • Large-span bridge abutment settlement observation device and method

    CN117723021A

  • Steel pipe truss node steel pipe butt joint measuring device

    CN216694819U

  • Method and apparatus for measuring thickness

    GB791382A

Cited By

  • Bridge pier settlement monitoring device and use method thereof

    CN120576718A