A method for constructing a dark tunnel under shallow geological conditions
Through deep hole grouting and duct grouting technology, combined with regional excavation and support, the problem of insufficient support performance in tunnel construction under shallow geological conditions has been solved, improving the stability and safety of the construction area and reducing construction risks.
Patent Information
- Application Number
- CN202411067259.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-08-06
AI Technical Summary
Under shallow geological conditions, existing tunnel construction methods have insufficient support performance and are difficult to meet construction safety requirements, especially in areas with abundant groundwater, which can easily lead to surface settlement and construction safety accidents.
Deep hole grouting and duct grouting technology are used to provide adequate support around the tunnel face and expel groundwater before construction. Gradual excavation is carried out in different areas and real-time support is provided during the excavation process. Pressure structure and pressure adjustment structure to ensure grouting depth and stability.
It effectively improves the support strength around the tunnel, ensures the stability and safety of the construction area, reduces surface settlement and construction risks, and ensures the safety of the construction process.
Smart Images

Figure CN118582214B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of tunnel construction, and particularly relates to a construction method for a mined tunnel under shallow geological conditions. Background Technique
[0002] With the development of urban subway construction in China, its scale is getting larger and larger, the surrounding environment and various factors restricting construction are becoming more and more demanding. Coupled with the continuous increase in construction projects, the scope of utilization of underground space is continuously shrinking. Under such conditions, when constructing later projects, it is necessary to ensure the stability of other buildings.
[0003] Currently, in the construction of later subway projects, there will inevitably be intersections with previous subway projects or the construction of transfer stations. At this time, when connecting the stations under construction with the stations in the original project, that is, the construction of the crosshead (the crosshead is the junction between the station and the tunnel, the combined part of open and mined construction, with complex structural forces. To ensure the safety of excavating into the tunnel from the shaft wall, it is necessary to take reinforcement measures around the hole, and a strengthening ring is set at the hole if necessary). Only using the existing excavation method will result in surface settlement and construction safety accidents due to insufficient support strength. Especially in shallow geological conditions (the ratio of the cover thickness H of the arch crown to the structural span D, that is, H / D is called the cover-span ratio. When 0.6 < H / D ≤ 1.5, it is all called shallow burial), and in areas with relatively rich groundwater. If dewatering is carried out for convenient excavation, it is easy to cause surface settlement, but without dewatering, it is not convenient for excavation. Therefore, the existing construction methods, especially in areas with more groundwater, cannot meet the construction requirements. It is necessary to provide an improved technical solution for the deficiencies of the above existing technologies. Summary of the Invention
[0004] The purpose of the present invention is to provide a construction method for a mined tunnel under shallow geological conditions to solve the technical problems that the existing construction methods have insufficient support performance and safety performance that cannot meet the construction requirements.
[0005] To achieve the above purpose, the construction method for a mined tunnel under shallow geological conditions of the present invention provides the following technical solutions:
[0006] A construction method for a mined tunnel under shallow geological conditions includes the following steps:
[0007] Step 1, deep-hole grouting. Deep-hole grouting is carried out circumferentially along the contour line of the tunnel face to ensure the support strength around the tunnel. The deep holes are drilled obliquely outwards so that the axial direction of the deep holes has a set angle with the axial direction of the tunnel. At the same time, deep-hole grouting is carried out on the tunnel face.
[0008] Step 2, pipe grouting. Pipes are drilled on the side wall of the tunnel in front of the tunnel face, and pipe grouting is carried out.
[0009] Step 3: Remove the horse head gate, divide the face into multiple construction areas, and excavate each area step by step;
[0010] Step 4, lining construction, after excavating the construction area near the tunnel outline, the conduit is set again on the side wall of the tunnel and grouting is carried out. After grouting, the initial concrete spraying, steel mesh hanging, steel bracket fixing, and re-concrete spraying are carried out in sequence to form a partial support structure of the tunnel;
[0011] Step 5: After the tunnel is excavated to a set distance, repeat steps 1-4 and move forward step by step.
[0012] As a further optimized technical solution, in step 1, the deep hole grouting step includes:
[0013] Step 11, hole arrangement, arranging the drilling positions in a plum blossom shape on the tunnel contour and the face;
[0014] Step 12, setting up a grouting platform; setting up a scaffolding close to the face, and installing a supporting formwork on the scaffolding after the setting up is completed, and the supporting formwork and the scaffolding are used to form a grouting platform;
[0015] Step 13, the drilling rig is in place; the drilling rig is installed on the grouting platform, and the drilling rig is adjusted until the drill bit is coaxial with the hole;
[0016] Step 14, drilling a hole; operating a drilling machine to form a grouting deep hole;
[0017] Step 15, backward grouting: after the drilling rig has drilled to the designed depth, a grouting pump is used to perform grouting from the bottom of the hole from the inside out;
[0018] As a further optimized technical solution, the catheter has an equal-diameter section and a tip portion, the side wall of the equal-diameter section is provided with perforations for grouting, and a pressure-maintaining structure is provided in the lumen of the equal-diameter section for maintaining pressure in stages during grouting to ensure the grouting depth.
[0019] As a further optimized technical solution, the pressure maintaining structure includes a slurry baffle, which is arranged perpendicular to the axial direction of the catheter. The slurry baffle is slidably and sealably matched with the tubular cavity of the equal-diameter section. A positioning structure is provided on the slurry baffle, and a locking structure matching the positioning structure is provided at the interval in the tubular cavity corresponding to the equal-diameter section. Within the set pressure, the positioning structure is fixedly connected to the locking structure. When the pressure exceeds the set pressure, the positioning structure disengages from the current locking structure and slides to another locking structure to continue maintaining pressure.
[0020] As a further optimized technical solution, the pulp baffle has an inner cavity, and a plurality of positioning blocks are arranged circumferentially in the inner cavity. The positioning blocks are partially arranged inside the pulp baffle, and partially extend out of the pulp baffle and slideably cooperate with the pulp baffle. An elastic member is fixedly connected to one end of the positioning block located in the inner cavity, and the elastic member is used to drive the positioning block to slide in the inner cavity; the positioning block and the elastic member constitute the locking structure;
[0021] A slot matching the positioning block is provided on the inner side wall of the lumen of the equal-diameter section, and the end away from the operator is defined as the distal end. An inclined guide surface is provided on the side of the slot close to the distal end of the catheter. When the pressure in the lumen exceeds a set value, the positioning block squeezes the guide surface to shrink into the inner cavity to disengage from the current slot. The slot constitutes the positioning structure.
[0022] As a further optimized technical solution, a pressure adjustment structure is further provided in the inner cavity for adjusting the compression degree of the elastic member so as to adjust the pressure holding value of the slurry baffle.
[0023] As a further optimized technical solution, the pressure adjustment structure includes:
[0024] The driving rod comprises a threaded section and a conical section which are integrally fixedly connected. The conical section is in the inner cavity. The threaded section is threadedly connected to the side wall of the inner cavity. The driving rod is rotated to adjust the length of the conical section extending into the inner cavity.
[0025] The adjusting block is arranged along the circumference of the inner cavity and is slidably connected to the side wall of the inner cavity. One end of the adjusting block is fixedly connected to the elastic member, and the other end is slidably matched with the conical section.
[0026] As a further optimized technical solution, one end of the positioning block away from the elastic member is an arc surface.
[0027] As a further optimized technical solution, the slurry baffle is circumferentially provided with guide blocks, and a guide groove is provided on the inner wall of the corresponding lumen; the guide block is arranged on one side of the slurry baffle close to the slurry inlet of the catheter.
[0028] As a further optimized technical solution, in step 3, the tunnel face is divided into nine construction areas, including:
[0029] The first area is located in the upper middle part of the tunnel;
[0030] The second area is located in the middle of the tunnel;
[0031] The third area is located in the lower middle part of the tunnel;
[0032] The fourth area is located in the upper right part of the tunnel;
[0033] The fifth area is located in the middle right part of the tunnel;
[0034] The sixth area is located in the lower right part of the tunnel;
[0035] The seventh area is located in the upper left part of the tunnel;
[0036] The eighth area is located in the middle left part of the tunnel;
[0037] The ninth area is located in the lower left part of the tunnel;
[0038] The first to sixth areas are excavated in sequence through a step construction method, and then the seventh to ninth areas are excavated.
[0039] Beneficial effects: When using this construction method, deep hole grouting and duct grouting are used for full support before excavation, and the face needs to be fully grouted, which can fully ensure the stability of the horse head gate position, and the face grouting can expel groundwater, so that excavation can be facilitated while ensuring the stability of the excavation position. After that, the face is divided into multiple areas, excavation is carried out in different areas, and support is provided while excavating, which can effectively control surface settlement, ensure the geological stability of the construction area, ensure safety during construction, reduce disturbance to the surrounding rock, and thus reduce construction risks. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. Among them:
[0041] Figure 1 This is a schematic diagram of a tunnel face structure according to an embodiment of the present invention;
[0042] Figure 2 A side view of a tunnel according to an embodiment of the present invention;
[0043] Figure 3 A schematic diagram of the overall structure of a catheter according to an embodiment of the present invention;
[0044] Figure 4 A schematic cross-sectional view of a catheter according to an embodiment of the present invention;
[0045] Figure 5 for Figure 4 The enlarged schematic diagram of part A in the middle;
[0046] Figure 6 A side view of a catheter according to an embodiment of the present invention;
[0047] Figure 7 The figure is a schematic diagram of the internal structure of a slurry guard plate according to an embodiment of the present invention.
[0048] In the figure: 1, tunnel; 11, first area; 12, second area; 13, third area; 14, fourth area; 15, fifth area; 16, sixth area; 17, seventh area; 18, eighth area; 19, ninth area; 2, deep hole; 3, catheter; 31, equal diameter section; 311, guide groove; 32, tip part; 33, perforation; 34, pressure maintaining structure; 340, slideway; 341, slurry baffle; 342, inner cavity; 343, positioning block; 344, elastic member; 345, slot; 346, guide surface; 347, drive rod; 3471, threaded section; 3472, conical section; 3473, cross groove; 348, adjustment block; 349, guide block. DETAILED DESCRIPTION
[0049] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention belong to the scope of protection of the present invention.
[0050] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixed connections or detachable connections; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0051] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.
[0052] The present invention provides a dark tunnel construction method under shallow geological conditions, which ensures stability and safety during the excavation process by fully supporting and expelling groundwater before construction.
[0053] Specifically, Figure 1 , Figure 2 As shown, a dark excavation tunnel construction method under shallow geological conditions comprises the following steps:
[0054] Step 1, deep hole 2 grouting, deep hole 2 grouting is performed in the circumferential direction of the tunnel face contour line of the tunnel 1 to ensure the support strength around the tunnel 1; the deep hole 2 outside the tunnel face contour line is tilted outward so that the axial direction of the deep hole 2 has a set angle with the axial direction of the tunnel 1, and deep hole 2 grouting is performed on the tunnel face at the same time to expel groundwater.
[0055] The step of grouting the deep hole 2 comprises:
[0056] Step 11, hole arrangement, the drilling positions are arranged in a plum blossom shape on the tunnel 1 contour and the tunnel face, the hole spacing is 600mm, the row spacing is 800mm, the deep holes 2 outside the tunnel face contour line are tilted outward, the tilt angle is 5°-13°, and the deep holes 2 on the tunnel face are drilled perpendicular to the tunnel face;
[0057] Step 12, setting up a grouting platform; setting up a scaffolding close to the face, and installing a supporting formwork on the scaffolding after the setting up is completed, and the supporting formwork and the scaffolding are used to form a grouting platform;
[0058] Step 13, the drilling rig is in place; the drilling rig is installed on the grouting platform, and the drilling rig is adjusted until the drill bit is coaxial with the hole;
[0059] Step 14, drilling a hole; operating a drilling machine to form a grouting deep hole 2;
[0060] Step 15, backward grouting; after the drilling rig drills to the designed depth, a grouting pump is used to perform grouting from the bottom of the hole from the inside to the outside; wherein, the slurry injected into the deep hole 2 outside the contour line of the face is concrete with fine aggregate, which is used to form the protective structure of the tunnel 1, and the slurry injected into the face is mortar, which is used to remove groundwater and solidify the part to be excavated with a higher water content, thereby facilitating excavation.
[0061] Step 2, grouting of the conduit 3, a conduit 3 is set on the side wall of the tunnel 1 on the front side of the tunnel face, and grouting of the conduit 3 is performed to enhance the support strength near the tunnel face, thereby ensuring the stability of the excavation.
[0062] Step 3: Remove the horse head gate, divide the face into multiple construction areas, and excavate the area step by step. The face is divided into nine construction areas, including:
[0063] The first area 11 is located in the upper middle position of the tunnel 1, the second area 12 is located in the middle position of the tunnel 1, the third area 13 is located in the lower middle position of the tunnel 1, the fourth area 14 is located in the upper right position of the tunnel 1, the fifth area 15 is located in the right middle position of the tunnel 1, the sixth area 16 is located in the lower right position of the tunnel 1, the seventh area 17 is located in the upper left position of the tunnel 1, the eighth area 18 is located in the left middle position of the tunnel 1, and the ninth area 19 is located in the lower left position of the tunnel 1.
[0064] The step-by-step excavation of each area includes the following steps:
[0065] Step 31, grouting is performed in deep holes 2 to reinforce the stratum. The first area 11 is opened by staggering the distance of one time of the hole diameter in front and back, and initial support is performed as the excavation progresses; the initial support is grouting performed behind the closed ring in time.
[0066] Step 32, continue to excavate the second area 12 by using the step method with a staggered interval of one time of the hole diameter, adopt the full section grouting water-stopping measure in case of groundwater entering the excavation section, and carry out initial support as the excavation progresses. Grouting is carried out behind the initial support in time after the ring is closed.
[0067] Step 33, continue to excavate the third area 13 by staggering the distance of one hole diameter, adopt the full section grouting water-stopping measure to deal with the situation that groundwater enters the excavation section, and carry out initial support as the excavation progresses. Grouting is carried out behind the initial support in time after the ring is closed.
[0068] Step 34, stagger the distance of one time before and after the tunnel diameter and continue to use the step method to excavate the fourth area 14, the fifth area 15, and the sixth area 16 of the cave in sequence. During the excavation process, the arch needs to be reinforced with deep hole grouting. In case of groundwater entering the excavation section, the full section grouting water-stopping measures are adopted, and initial support is applied as the excavation progresses. Grouting behind the initial support is carried out in time after the ring is closed.
[0069] Step 35, continue to excavate the seventh area 17, the eighth area 18, and the ninth area 19 by using the step method with a staggered interval of one time. During the excavation of the cavern, the vault needs to be reinforced with deep hole 2 grouting. In case of groundwater entering the excavation section, full section grouting water-stopping measures are adopted, and initial support is applied as the excavation progresses. Grouting behind the initial support is carried out in time after the ring is closed.
[0070] Step 4, lining construction, after excavating the construction area near the outline of tunnel 1, the conduit 3 is set again on the side wall of tunnel 1 and grouting is carried out. After grouting, initial concrete spraying, steel mesh hanging, steel support fixing, and re-concrete spraying are carried out in sequence to form a partial enclosure structure of tunnel 1.
[0071] Step 5: After tunnel 1 has been excavated to a set distance, steps 1-4 are repeated to gradually advance forward.
[0072] When grouting the traditional catheter 3, due to the long lumen of the catheter 3, after the slurry is injected into the lumen, pressure loss will inevitably occur, that is, the grouting pressure gradually decreases from the end close to the grouting equipment to the end far away from the grouting equipment. Although there are measures for pressure-maintaining grouting in the final stage of grouting, the initial setting state of the slurry injected into the surrounding rock formation during the early grouting process will prevent the continued injection of the later slurry. In the present invention, the end far away from the operator is defined as the distal end, and the end close to the operator is defined as the proximal end. The slurry inlet of the catheter 3 is set at the proximal end, which is convenient for injecting slurry from the proximal end and gradually flowing into the distal end along the catheter 3. Therefore, when grouting directly into the lumen, the grouting degree at the distal end will be less than that at the proximal end. In this way, the stability of the support at the distal position cannot be guaranteed, especially for key construction projects, such as cross-construction. If the support strength cannot be guaranteed, once settlement occurs during construction, huge losses will occur.
[0073] In order to solve the above technical problems, Figure 3 As shown, the catheter 3 is a tubular structure with a lumen for grouting inside. The catheter 3 has an equal-diameter section 31 and a tip portion 32. The tip portion is used to facilitate driving the catheter 3 into the rock formation of the tunnel side wall. In order to ensure the stability of the tip portion 32 during the driving process, in this embodiment, the tip portion 32 is a solid structure.
[0074] The side wall of the equal diameter section 31 is provided with a perforation 33 for grouting. The slurry is injected into the rock formation from the tube cavity through the perforation 33. A pressure retaining structure 34 is provided in the tube cavity of the equal diameter section 31. In this way, during grouting, the pressure retaining structure first stays at a set position of the equal diameter section 31. The distance from this position to the grouting port is short, which can ensure the grouting effect. Grouting is first performed on this section of the tube cavity. After the grouting is completed, the pressure retaining structure 34 automatically slides to the next set position, and then grouting is performed on the tube cavity. Since the rock formation near one end of the grouting equipment has been grouted in the early stage, the grouting pressure at this stage is The force influence is very small, so as to ensure the smooth grouting in this stage, and it is repeated in sequence until the pressure-maintaining structure 34 slides to the end of the tube cavity, that is, the pressure-maintaining structure 34 slides to one end connected to the tip part 32, and the grouting is completed. In this way, the pressure-maintaining structure 34 realizes stage-by-stage pressure maintenance during grouting, which can ensure the grouting depth during the initial grouting, and in the subsequent staged grouting, the previous grouting is strengthened, thereby ensuring the grouting depth. Compared with the existing one-time grouting, the overall grouting depth is deeper and more uniform, thereby ensuring the support strength and further ensuring the stability of the construction.
[0075] like Figure 4 , Figure 5 , Figure 6 , Figure 7As shown, the specific pressure-maintaining structure 34 includes a slurry baffle 341, the shape of which is adapted to the cross-section of the lumen, the slurry baffle 341 is arranged axially perpendicular to the catheter 3, the slurry baffle 341 is slidably sealed with the lumen of the equal-diameter section 31, a positioning structure is provided on the slurry baffle 341, and a locking structure cooperating with the positioning structure is provided at the interval in the lumen of the corresponding equal-diameter section 31. Within the set pressure, the positioning structure is fixedly connected to the locking structure, and when the set pressure is exceeded, the positioning structure is pushed by the slurry to separate from the current locking structure and slide to another locking structure close to the tip portion 32 to continue maintaining the pressure.
[0076] The slurry retaining plate 341 has an inner cavity 342, and a plurality of positioning blocks 343 are arranged circumferentially in the inner cavity 342. The positioning blocks 343 are partially arranged inside the slurry retaining plate 341, and partially extend out of the slurry retaining plate 341 and slideably cooperate with the slurry retaining plate 341. A coil spring as an elastic member 344 is fixedly connected to one end of the positioning block 343 located in the inner cavity 342, and the elastic member 344 is used to drive the positioning block 343 to slide in the inner cavity 342; the positioning block 343 and the elastic member 344 constitute the above-mentioned locking structure;
[0077] A plurality of groups of slots 345 adapted to the positioning blocks 343 are provided on the inner wall of the tubular cavity of the equal-diameter section 31. Each group of slots 345 is used to adapt all the positioning blocks 343 at one position. In the present embodiment, two positioning blocks 343 are symmetrically provided, and there are three groups of slots. Each group of slots 345 has two slots. The two slots 345 are respectively used to adapt to one positioning block 343. In this way, at one position, the two positioning blocks 343 in the pressing structure 34 extend into one slot 345 respectively.
[0078] An inclined guide surface 346 is provided on one side of the slot 345 near the distal end of the catheter 3. When the pressure in the lumen exceeds a set value, the slurry pushes the slurry retaining plate 341 to move toward the side near the tip portion 32. At this time, the positioning block 343 squeezes the guide surface 346 to shrink into the inner cavity 342 to disengage from the current slot 345. The slot 345 constitutes the above-mentioned positioning structure. In this embodiment, in order to ensure smooth cooperation between the positioning block 343 and the guide surface 346, the end of the positioning block 343 away from the elastic member 344 is an arc surface.
[0079] Under different construction conditions, the required grouting pressure is different. In order to reduce the processing difficulty and improve the processing efficiency, all of them are directly processed into the same structure. However, a pressure adjustment structure is provided in the inner cavity 342 to adjust the compression degree of the elastic member 344 to adjust the pressure holding value of the slurry baffle 341. According to the specific construction requirements, the corresponding pressure adjustment structure is adjusted during assembly to meet the actual needs.
[0080] The pressure adjustment structure specifically includes a driving rod 347 and an adjustment block 348 .
[0081] like Figure 5 , Figure 6 As shown, the driving rod 347 has a threaded section 3471 and a conical section 3472 that are integrally fixedly connected. The conical section 3472 is in the inner cavity 342. The threaded section 3471 is threadedly connected to the side wall of the inner cavity 342 that faces away from the tip portion 32. By rotating the driving rod 347, the length of the conical section 3472 extending into the inner cavity 342 can be adjusted. In order to facilitate the rotation of the driving rod 347, a cross groove 3473 is provided on the end surface of the driving rod 347, which is convenient for screwing using a tool with a cross head.
[0082] The adjustment block 348 is arranged along the circumference of the inner cavity 342 and is slidably connected to the side wall of the inner cavity 342. One end of the adjustment block 348 is fixedly connected to the elastic member 344, and the other end is slidably matched with the conical section 3472. Specifically, a slideway 340 is provided on the side wall of the inner cavity 342, so that the adjustment block 348 slides along the slideway 340 to ensure stable compression of the elastic member 344. In order to ensure smooth cooperation between the adjustment block 348 and the driving rod 347, the side of the adjustment block 348 facing the conical section 3472 is preferably processed to have an inclination that matches the taper of the conical section 3472. At the same time, it is best to open an arc groove on the side that matches the arc surface of the conical section 3472.
[0083] Furthermore, if the thickness of the slurry baffle 341 is not designed reasonably, especially when it is too thin, the slurry baffle 341 is prone to tilt when moving along the lumen. However, thickening the slurry baffle 341 will, firstly, consume more production materials, and secondly, in the final grouting stage, the slurry baffle 341 is at the end of the lumen. The slurry baffle 341 will block the end portion of the perforation 33, resulting in a reduction in the grouting length of the catheter 3. In order to ensure that the slurry baffle 341 can both stably slide with the lumen and minimize the impact on the grouting length, a guide block 349 is circumferentially arranged on the slurry baffle 341, and a guide groove 311 is arranged on the corresponding inner wall of the lumen; the length of the guide block 349 only needs to be greater than the thickness of the slurry baffle 341, and the guide block 349 needs to be arranged on the side of the slurry baffle 341 close to the slurry inlet of the catheter 3 to avoid affecting the grouting length.
[0084] It should be understood that the above description is merely exemplary and the embodiments of the present application do not limit this.
[0085] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are within the scope of protection of the pending claims of the present invention.
Claims
1. A method for constructing a dark tunnel under shallow geological conditions, characterized in that: The following steps are involved: Step 1, deep hole (2) grouting, deep hole (2) grouting is performed in the circumferential direction of the tunnel face contour line of the tunnel (1) to ensure the support strength around the tunnel (1); the deep hole (2) is tilted outward so that the axial direction of the deep hole (2) and the axial direction of the tunnel (1) have a set angle, and deep hole (2) grouting is performed on the tunnel face at the same time to expel groundwater; Step 2, grouting of the conduit (3), setting a conduit (3) on the side wall of the tunnel (1) on the front side of the tunnel face, and grouting the conduit (3); Step 3: Remove the horse head gate, divide the face into multiple construction areas, and excavate each area step by step; Step 4, lining construction, after excavating the construction area near the outline of the tunnel (1), the conduit (3) is again set on the side wall of the tunnel (1) and grouting is performed. After grouting, initial concrete spraying, steel mesh hanging, steel support fixing, and re-concrete spraying are performed in sequence to form a partial support structure of the tunnel (1); Step 5, after the tunnel (1) is excavated to a set distance, steps 1 to 4 are repeated to gradually advance forward; In step 1, the step of grouting the deep hole (2) comprises: Step 11, hole arrangement, arranging the drilling positions in a plum blossom shape on the tunnel (1) contour and the tunnel face; Step 12, setting up a grouting platform; setting up a scaffolding close to the face, and installing a supporting formwork on the scaffolding after the setting up is completed, and the supporting formwork and the scaffolding are used to form a grouting platform; Step 13, the drilling rig is in place; the drilling rig is installed on the grouting platform, and the drilling rig is adjusted until the drill bit is coaxial with the hole; Step 14, drilling a hole; operating a drilling machine to form a grouting deep hole (2); Step 15, backward grouting: after the drilling rig has drilled to the designed depth, a grouting pump is used to perform grouting from the bottom of the hole from the inside out; The conduit (3) comprises a constant diameter section (31) and a tip portion (32); a perforation (33) for grouting is arranged on the side wall of the constant diameter section (31); a pressure-maintaining structure (34) is arranged in the lumen of the constant diameter section (31) for maintaining pressure in stages during grouting to ensure the grouting depth; The pressure-maintaining structure (34) comprises a slurry retaining plate (341), the slurry retaining plate (341) being arranged axially perpendicular to the conduit (3), the slurry retaining plate (341) being slidably sealed with the lumen of the equal-diameter section (31), a positioning structure being arranged on the slurry retaining plate (341), and a locking structure cooperating with the positioning structure being arranged at intervals in the lumen of the corresponding equal-diameter section (31); within a set pressure, the positioning structure is fixedly connected to the locking structure; when the pressure exceeds the set pressure, the positioning structure is separated from the current locking structure to slide to another locking structure to continue to maintain the pressure; The pulp baffle plate (341) has an inner cavity (342), a plurality of positioning blocks (343) are arranged in a circumferential direction within the inner cavity (342), the positioning blocks (343) are partially arranged inside the pulp baffle plate (341), and partially extend out of the pulp baffle plate (341) and slidably cooperate with the pulp baffle plate (341), one end of the positioning block (343) located in the inner cavity (342) is fixedly connected to an elastic member (344), and the elastic member (344) is used to drive the positioning block (343) to slide within the inner cavity (342); the positioning block (343) and the elastic member (344) constitute the locking structure; A slot (345) adapted to the positioning block (343) is provided on the inner side wall of the lumen of the equal diameter section (31), and the end away from the operator is defined as the distal end. An inclined guide surface (346) is provided on the side of the slot (345) close to the distal end of the catheter (3). When the pressure in the lumen exceeds a set value, the positioning block (343) squeezes the guide surface (346) to shrink into the inner lumen (342) to detach from the current slot (345). The slot (345) constitutes the positioning structure. A pressure adjustment structure is also provided in the inner cavity (342) for adjusting the degree of compression of the elastic member (344) so as to adjust the pressure holding value of the pulp baffle plate (341); The pressure adjustment structure comprises: A driving rod (347), the driving rod (347) comprising a threaded section (3471) and a conical section (3472) which are integrally fixedly connected, the conical section (3472) being located in the inner cavity (342), the threaded section (3471) being threadedly connected to a side wall of the inner cavity (342), and the driving rod (347) being rotated to adjust the length of the conical section (3472) extending into the inner cavity (342); An adjustment block (348) is arranged along the circumference of the inner cavity (342) and is slidably connected to the side wall of the inner cavity (342); one end of the adjustment block (348) is fixedly connected to the elastic member (344), and the other end is slidably matched with the conical section (3472).
2. The method for constructing a dark tunnel under shallow geological conditions according to claim 1, characterized in that: One end of the positioning block (343) away from the elastic member (344) is an arc surface.
3. The method for constructing a dark tunnel under shallow geological conditions according to claim 1, characterized in that: The slurry retaining plate (341) is provided with a guide block (349) in the circumferential direction, and a guide groove (311) is provided on the inner wall of the corresponding lumen; the guide block (349) is provided on one side of the slurry retaining plate (341) close to the slurry inlet of the catheter (3).
4. The method for constructing a dark tunnel under shallow geological conditions according to claim 1, characterized in that: In step 3, the tunnel face is divided into nine construction areas, including: The first area (11) is located in the upper middle part of the tunnel (1); The second area (12) is located in the middle of the tunnel (1); The third area (13) is located in the middle and lower part of the tunnel (1); The fourth area (14) is located at the upper right position of the tunnel (1); The fifth area (15) is located in the middle right portion of the tunnel (1); The sixth area (16) is located at the lower right portion of the tunnel (1); The seventh area (17) is located at the upper left portion of the tunnel (1); The eighth area (18) is located in the middle left portion of the tunnel (1); The ninth area (19) is located at the lower left part of the tunnel (1); The first area (11) to the sixth area (16) are excavated in sequence by a step construction method, and then the seventh area (17) to the ninth area are excavated.
Citation Information
Patent Citations
Underground excavation construction deformation control method for three-hole small clear distance tunnel underpass trunk railway
CN103375170A
Construction method of shallow-buried subsurface-excavated cross-shaped cross-strut tunnel
CN105443132A
Deep-hole backward grouting and water-blocking construction method for igneous rock water-rich fault
CN110735653A
Construction method of large-span section underground excavation tunnel influenced by underground water
CN114542086A
Construction method for subway crossing riverway
CN115450221A