Control method and system of rigid busbar prefabrication production line based on BIM model

Through technologies such as BIM models and multi-agent collaboration frameworks, the problems of low production efficiency and low equipment utilization in the hard busbar prefabricated production line have been solved, real-time status awareness and dynamic optimization control have been achieved, and the intelligence and efficiency of the production line have been improved.

CN118584925BActive Publication Date: 2024-10-18CHINA RAILWAY ELECTRIFICATION ENGINEERING GROUP CO LTD +2
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411063555.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-10-18
Estimated Expiration
2044-08-05

AI Technical Summary

Technical Problem

The traditional hard busbar manufacturing process is complex, the production efficiency is low, and the lack of information technology and intelligent control technology leads to information islands and low equipment utilization, which limits the development of prefabricated production lines.

Method used

Adopting a BIM model-based hard busbar prefabricated production line control method, by building a digital twin BIM model and a virtual-real fusion model, combined with the semantic network, augmented reality, multi-agent collaboration framework, adaptive control algorithm and edge computing, real-time status perception, data Fusion, dynamic optimization control and intelligent scheduling.

Benefits of technology

It improves the visualization, traceability and control accuracy of the production line, maximizes production efficiency and equipment utilization, and improves the intelligence level and product quality of the production line.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118584925B_ABST
    Figure CN118584925B_ABST
Patent Text Reader

Abstract

The present invention provides a control method and system for a hard busbar prefabrication production line based on a BIM model, which relates to the technical field of production control, including: constructing a digital twin BIM model of a hard busbar prefabrication production line, a virtual-real fusion model, performing semantic association and attribute mapping with entities in the production line, generating a first knowledge base, performing registration and fusion display, and obtaining a first production model; constructing a production line intelligent control system comprising multiple layers, collecting real-time status data and generating a high-dimensional feature vector of the production line status, adding it to a control layer, constructing a dynamic optimization control model, generating an optimal control sequence, adjusting the control strategy in real time, and solving a set of candidate scheduling solutions through an optimization layer; constructing an objective function, solving it in combination with a multi-objective optimization algorithm, determining the optimal scheduling solution and deploying an intelligent gateway, receiving the optimal scheduling solution, generating a control action sequence and sending it to production equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of production control, and in particular to a control method and system for a hard busbar prefabrication production line based on a BIM model. Background Art

[0002] Hard busbars are important power transmission and distribution equipment in power systems and are widely used in substations, distribution rooms and other places. Traditional hard busbar manufacturing mainly adopts on-site processing and assembly, which has problems such as complex procedures, low production efficiency, and difficulty in quality control. It is difficult to meet the growing power demand and project progress requirements.

[0003] In order to improve the efficiency and quality of hard busbar manufacturing, the concept of prefabrication production line came into being. Prefabrication production line realizes the industrialization and standardization of hard busbar manufacturing by centralizing the processing and assembly of hard busbar in the factory, greatly improving production efficiency and product quality. However, traditional prefabrication production line mainly relies on manual experience and manual operation, lacks effective information means and intelligent control technology, and the problems of information island, low equipment utilization and unreasonable production plan in the production process are still prominent, which limits the further development and application of prefabrication production line.

[0004] In recent years, the rise of building information modeling technology has provided a new idea for solving the above problems. Through comprehensive and dynamic management and application of building geometry, attribute information, status information, etc., the informatization and intelligence of the entire life cycle of the building have been realized. However, the research on applying BIM technology to the control of rigid busbar prefabrication production line is still relatively rare, and there is still a lack of mature technical solutions and application practices.

[0005] Therefore, there is an urgent need for a solution to apply BIM technology to the rigid busbar prefabrication production line. Summary of the invention

[0006] The embodiments of the present invention provide a control method and system for a hard busbar prefabrication production line based on a BIM model, which can at least solve some of the problems in the prior art.

[0007] A first aspect of an embodiment of the present invention provides a control method for a rigid busbar prefabrication production line based on a BIM model, comprising:

[0008] Construct a digital twin BIM model of the hard busbar prefabrication production line, map the physical information, geometric information and process rules of the prefabrication production line to the virtual space, construct a virtual-reality fusion model, combine semantic web technology and ontology modeling methods to semantically associate and attribute map the digital twin BIM model with entities in the production line, generate a first knowledge base, and combine augmented reality technology to register and fuse the digital twin BIM model and the virtual-reality fusion model to obtain a first production model;

[0009] Based on the first production model, a multi-agent collaborative framework is combined to build a production line intelligent control system containing multiple layers. Real-time status data is collected through multi-source heterogeneous sensors in the perception layer, and a high-dimensional feature vector of the production line status is generated through feature extraction and data fusion technology. The high-dimensional feature vector is added to the control layer, and a dynamic optimization control model is built in combination with process parameters and quality requirements. The optimal control sequence is generated in combination with an adaptive control algorithm, and the control strategy is adjusted in real time in combination with the production line feedback data. A set of candidate scheduling solutions is solved through the optimization layer;

[0010] Based on the set of candidate scheduling schemes, with the goal of maximizing production efficiency and equipment utilization, an objective function is constructed, and a multi-objective optimization algorithm is used to solve it. The optimal scheduling scheme is determined and combined with edge computing and fog computing technologies, an intelligent gateway is deployed on the production line, the optimal scheduling scheme is received in real time, data is processed, and a control action sequence is generated and sent to the production equipment.

[0011] In an optional embodiment,

[0012] Construct a digital twin BIM model of the hard busbar prefabrication production line, map the physical information, geometric information and process rules of the prefabrication production line to the virtual space, construct a virtual-reality fusion model, combine semantic web technology and ontology modeling methods to semantically associate and attribute map the digital twin BIM model with entities in the production line, generate a first knowledge base, combine augmented reality technology to align and fuse the digital twin BIM model with the virtual-reality fusion model, and obtain a first production model including:

[0013] Scan the equipment, site and materials of the hard busbar prefabrication production line through 3D laser scanning technology to obtain point cloud data, denoise and align the point cloud data, generate a 3D point cloud model in combination with 3D modeling software, generate a geometric information model of the production line in combination with the equipment entity, obtain the physical parameters of each device in the hard busbar prefabrication production line, wherein the physical parameters include power, rotation speed, temperature and pressure, establish a physical property database, obtain the material property parameters of each process section of the production line to construct a material property database, associate the physical property database and the material property database with the geometric information model to obtain a physical information model, obtain the process files of the hard busbar prefabrication production line, perform text mining and knowledge extraction on the process knowledge, construct a process knowledge ontology through ontology modeling, map the process knowledge into the process knowledge ontology, construct a process rule knowledge base and associate it with the physical information model to obtain a process rule model, and construct a digital twin BIM model of the hard busbar prefabrication production line based on the process rule model, the physical information model and the geometric information model;

[0014] Based on the digital twin BIM model, the production line status data is collected through sensors, radio frequency identification technology and barcodes, including equipment operating parameters, material location and personnel information, and the collected production line status data is associated with the digital twin BIM model. The virtual model and the physical entity are aggregated through data mapping and data synchronization to build a virtual-real fusion model of the production line;

[0015] The entities in the rigid busbar prefabrication production line are modeled as semantic entities through semantic web technology, entity attributes and relationships are defined, and core concepts are defined in combination with the rigid busbar prefabrication domain ontology to obtain structured domain knowledge. The geometric entities, physical attributes and process rules in the digital twin BIM model are mapped to semantic entities and domain ontology to obtain the first knowledge base;

[0016] The AR system is deployed on site at the hard busbar prefabrication production line through augmented reality technology, and the digital twin BIM model and the virtual-reality fusion model are loaded into the AR system. Real-time alignment and overlay display are performed through visual tracking and feature matching technology to obtain the first production model.

[0017] In an optional embodiment,

[0018] Based on the process rule model, the physical information model and the geometric information model, a digital twin BIM model of a hard busbar prefabrication production line is constructed as shown in the following formula:

[0019] ;

[0020] in, H Represents the digital twin BIM model, R represents the rotation matrix, P A column vector representing sensor data points, t represents the translation vector, A represents the state transfer matrix, express k The estimated state value at time B represents the control matrix, u k express k The control input at the moment, F i Indicates i The feature vector of the data, F j Indicates j The feature vector of the data, σ represents the activation function, J Representation Node m Neighboring nodes of N ( m ) represents a nodem The set of neighboring nodes of a mn represents the edge weight, W (l) Indicates l The weight matrix of the layer, Indicates l Tier m The feature vector of each node.

[0021] In an optional embodiment,

[0022] Based on the first production model, a production line intelligent control system with multiple layers is constructed in combination with a multi-agent collaborative framework. Real-time status data is collected through multi-source heterogeneous sensors in the perception layer, and a high-dimensional feature vector of the production line status is generated through feature extraction and data fusion technology. The high-dimensional feature vector is added to the control layer, and a dynamic optimization control model is constructed in combination with process parameters and quality requirements. The optimal control sequence is generated in combination with an adaptive control algorithm, and the control strategy is adjusted in real time in combination with the production line feedback data. The candidate scheduling solution set is solved through the optimization layer, including:

[0023] Based on the first production model, a production line intelligent control system including multiple layers is constructed in combination with a multi-agent collaborative framework, wherein the production line intelligent control system includes a perception layer, a control layer and an optimization layer;

[0024] Real-time status data is collected through multi-source heterogeneous sensors in the perception layer, the real-time status data is preprocessed and the data dimension is reduced through independent component analysis to obtain standard status data, frequency domain features are extracted from the standard status data through Fourier transform, time domain features are extracted in combination with statistical features, image processing is performed based on machine vision data, product defects and assembly accuracy are extracted as morphological features, the extracted features are aligned and spliced ​​in the time dimension to generate a high-dimensional feature matrix, local patterns and temporal dependencies in the high-dimensional feature matrix are determined in combination with a pre-set neural network module, high-level feature representations are extracted, corresponding weights are assigned to the high-level feature representations through a self-attention mechanism, and weighted fusion is performed to obtain the high-dimensional feature vector;

[0025] Add the high-dimensional feature vector to the control layer, set state variables and action variables, determine the value range of state variables and action variables in combination with process parameters and quality requirements, obtain state space and action space, construct a reward function, combine to obtain the dynamic optimization control model, perform parameter estimation through an adaptive control algorithm based on the dynamic optimization control model, set an adaptive controller and adjust controller parameters in real time, perform stability analysis on the dynamic optimization control model and the adaptive controller, and obtain a stability value. If the stability value is greater than a preset stability threshold, the current model is considered to be stable, and the optimal control sequence is output through the dynamic optimization control model;

[0026] Based on the optimal control sequence, a simulation application is performed, and the hyperparameters in the dynamic optimization control model are adjusted in real time according to the production line feedback data, and the optimal control sequence is regenerated to obtain the candidate scheduling solution.

[0027] In an optional embodiment,

[0028] Based on the dynamic optimization control model, the parameter estimation is performed by the adaptive control algorithm as shown in the following formula:

[0029] ;

[0030] in, Indicates time k The parameter estimate vector of Indicates time k - 1 The parameter estimate vector of K ( k ) indicates time k The Kalman gain matrix is y ( k ) indicates time k The model output is x ( k ) indicates time k The input vector is x T ( k ) indicates time k The transpose of the input vector.

[0031] In an optional embodiment,

[0032] Based on the candidate scheduling scheme set, with the goal of maximizing production efficiency and equipment utilization, an objective function is constructed, and a multi-objective optimization algorithm is combined to solve it, and the optimal scheduling scheme is determined. In combination with edge computing and fog computing technology, an intelligent gateway is deployed on the production line, and the optimal scheduling scheme is received in real time and data is processed. A control action sequence is generated and sent to the production equipment, including:

[0033] Taking the maximization of production efficiency and equipment utilization as the goal, construct an objective function, set corresponding constraints for the objective function according to equipment specifications and task requirements, determine a search space based on the candidate scheduling solution set, divide the search space into multiple sub-areas, and randomly generate an initial population based on a multi-objective optimization algorithm and the candidate scheduling solution set, wherein each individual in the initial population corresponds to a candidate scheduling solution, and the sub-area is used as a territory;

[0034] The individuals in the initial population are distributed to each territory according to the size of the territory. For the individuals in each territory, the fitness and Pareto level of each individual are calculated according to the production efficiency and equipment utilization rate. Individuals are selected in each territory by a roulette algorithm. For the selected individuals, they are randomly paired and multi-point crossover operations are performed according to a preset crossover probability to generate a first individual. For the first individual, a mutation operation is performed according to a preset mutation probability to obtain offspring individuals and calculate the fitness value. The offspring individuals are sorted in descending order according to the fitness value, and the offspring individuals in the top 10% are selected as excellent individuals and individuals are selected for migration in combination with a preset migration rate to replace the individual with the smallest fitness value in the target territory. The operation is repeated until the preset maximum number of iterations is reached to obtain the optimal scheduling plan.

[0035] Based on edge computing and fog computing methods, an intelligent gateway is deployed on the production line, and the optimal scheduling plan is obtained on the edge server in combination with the industrial communication protocol. The optimal scheduling plan is split into a control action sequence on the edge server and sent to the production equipment. The production equipment performs production activities according to the control action sequence.

[0036] In an optional embodiment,

[0037] The fitness and Pareto level of each individual are calculated based on production efficiency and equipment utilization, and individuals are selected in each territory through the roulette algorithm as shown in the following formula:

[0038] ;

[0039] in, p g Represents an individual x g The probability of being selected, r ( x g ) represents an individual x g The Pareto level of ε represents a small positive number, d ( xg ) represents an individual x g The crowding distance in the same Pareto level is N represents the total number of individuals in the current population, r ( x h ) represents an individual x h The Pareto level of d ( x h ) represents an individual x h The crowding distance within the same Pareto level.

[0040] A second aspect of an embodiment of the present invention provides a control system for a rigid busbar prefabrication production line based on a BIM model, comprising:

[0041] The first unit is used to build a digital twin BIM model of a hard busbar prefabrication production line, map the physical information, geometric information and process rules of the prefabrication production line to a virtual space, build a virtual-reality fusion model, combine semantic web technology and ontology modeling methods to semantically associate and attribute map the digital twin BIM model with entities in the production line, generate a first knowledge base, and combine augmented reality technology to register and fuse the digital twin BIM model with the virtual-reality fusion model to obtain a first production model;

[0042] The second unit is used to build a production line intelligent control system containing multiple layers based on the first production model and in combination with a multi-agent collaborative framework, collect real-time status data through multi-source heterogeneous sensors in the perception layer and generate a high-dimensional feature vector of the production line status through feature extraction and data fusion technology, add the high-dimensional feature vector to the control layer, build a dynamic optimization control model in combination with process parameters and quality requirements, generate an optimal control sequence in combination with an adaptive control algorithm, adjust the control strategy in real time in combination with production line feedback data, and solve a set of candidate scheduling solutions through the optimization layer;

[0043] The third unit is used to construct an objective function based on the candidate scheduling scheme set, with the goal of maximizing production efficiency and maximizing equipment utilization, and solve it in combination with a multi-objective optimization algorithm, determine the optimal scheduling scheme and combine edge computing and fog computing technologies, deploy an intelligent gateway on the production line, receive the optimal scheduling scheme in real time and perform data processing, generate a control action sequence and send it to the production equipment.

[0044] According to a third aspect of the embodiments of the present invention,

[0045] An electronic device is provided, comprising:

[0046] processor;

[0047] a memory for storing processor-executable instructions;

[0048] The processor is configured to call the instructions stored in the memory to execute the aforementioned method.

[0049] According to a fourth aspect of the embodiments of the present invention,

[0050] A computer-readable storage medium is provided, on which computer program instructions are stored. When the computer program instructions are executed by a processor, the aforementioned method is implemented.

[0051] In the present invention, by constructing a digital twin BIM model of the hard busbar prefabrication production line, physical information, geometric information and process rules are mapped to the virtual space, and the semantic web technology and ontology modeling method are combined to realize virtual-real mapping and association, and a virtual-real integrated production line model is constructed, which improves the visualization, traceability and diagnosability of the production line. By deploying multi-source heterogeneous sensors in the production line, real-time perception and data collection of the production line status are realized, and high-dimensional feature vectors are generated through feature extraction and data fusion technology, which provides data support for intelligent control and optimization decision-making. In combination with process parameters, quality requirements and production line status characteristics, a dynamic optimization control model is constructed, and adaptive control is adopted. The algorithm generates the optimal control sequence, realizes real-time feedback control and strategy adjustment of the production line, improves the control accuracy and stability of the production line, constructs a multi-objective optimization model with the goal of maximizing production efficiency and equipment utilization, and combines the intelligent optimization algorithm to solve the candidate scheduling schemes, obtains the optimal scheduling scheme, and realizes intelligent scheduling and optimal resource allocation of the production line. In summary, the present invention realizes digital modeling, intelligent perception, adaptive control, multi-objective optimization and distributed collaboration of the production line, improves the intelligence level, production efficiency and product quality of the production line, and provides a new solution and implementation path for the intelligent upgrade and technological advancement of the hard busbar prefabrication production line. BRIEF DESCRIPTION OF THE DRAWINGS

[0052] Figure 1 It is a flow chart of a control method of a hard busbar prefabrication production line based on a BIM model according to an embodiment of the present invention;

[0053] Figure 2 It is a structural schematic diagram of a control system of a hard busbar prefabrication production line based on a BIM model according to an embodiment of the present invention. DETAILED DESCRIPTION

[0054] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0055] The technical solution of the present invention is described in detail with specific embodiments below. The following specific embodiments can be combined with each other, and the same or similar concepts or processes may not be described in detail in some embodiments.

[0056] Figure 1 FIG. 1 is a flow chart of a control method for a hard busbar prefabrication production line based on a BIM model according to an embodiment of the present invention. Figure 1 As shown, the method includes:

[0057] S1. Construct a digital twin BIM model of the hard busbar prefabrication production line, map the physical information, geometric information and process rules of the prefabrication production line to the virtual space, construct a virtual-reality fusion model, combine the semantic web technology and ontology modeling method to semantically associate and attribute map the digital twin BIM model with the entities in the production line, generate a first knowledge base, and combine the augmented reality technology to register and fuse the digital twin BIM model and the virtual-reality fusion model to obtain a first production model;

[0058] The hard bus refers to a high-current conductor used to transmit electric energy in an electric power system. The hard bus prefabrication production line refers to an industrial production line specifically used to manufacture hard bus. The virtual space is a three-dimensional virtual environment created through computer technology and simulation technology, which can simulate scenes, objects and events in the real world. The virtual-reality fusion model refers to a technical method that closely integrates virtual space with the physical world. The semantic web technology is a technology that improves the information processing capabilities of the Internet by giving data and information clear semantic descriptions. The ontology modeling method refers to a technical method that constructs a knowledge model by defining concepts and the relationship between concepts.

[0059] In an optional embodiment,

[0060] Construct a digital twin BIM model of the hard busbar prefabrication production line, map the physical information, geometric information and process rules of the prefabrication production line to the virtual space, construct a virtual-reality fusion model, combine semantic web technology and ontology modeling methods to semantically associate and attribute map the digital twin BIM model with entities in the production line, generate a first knowledge base, combine augmented reality technology to align and fuse the digital twin BIM model with the virtual-reality fusion model, and obtain a first production model including:

[0061] Scan the equipment, site and materials of the hard busbar prefabrication production line through 3D laser scanning technology to obtain point cloud data, denoise and align the point cloud data, generate a 3D point cloud model in combination with 3D modeling software, generate a geometric information model of the production line in combination with the equipment entity, obtain the physical parameters of each device in the hard busbar prefabrication production line, wherein the physical parameters include power, rotation speed, temperature and pressure, establish a physical property database, obtain the material property parameters of each process section of the production line to construct a material property database, associate the physical property database and the material property database with the geometric information model to obtain a physical information model, obtain the process files of the hard busbar prefabrication production line, perform text mining and knowledge extraction on the process knowledge, construct a process knowledge ontology through ontology modeling, map the process knowledge into the process knowledge ontology, construct a process rule knowledge base and associate it with the physical information model to obtain a process rule model, and construct a digital twin BIM model of the hard busbar prefabrication production line based on the process rule model, the physical information model and the geometric information model;

[0062] Based on the digital twin BIM model, the production line status data is collected through sensors, radio frequency identification technology and barcodes, including equipment operating parameters, material location and personnel information, and the collected production line status data is associated with the digital twin BIM model. The virtual model and the physical entity are aggregated through data mapping and data synchronization to build a virtual-real fusion model of the production line;

[0063] The entities in the rigid busbar prefabrication production line are modeled as semantic entities through semantic web technology, entity attributes and relationships are defined, and core concepts are defined in combination with the rigid busbar prefabrication domain ontology to obtain structured domain knowledge. The geometric entities, physical attributes and process rules in the digital twin BIM model are mapped to semantic entities and domain ontology to obtain the first knowledge base;

[0064] The AR system is deployed on site at the hard busbar prefabrication production line through augmented reality technology, and the digital twin BIM model and the virtual-reality fusion model are loaded into the AR system. Real-time alignment and overlay display are performed through visual tracking and feature matching technology to obtain the first production model.

[0065] The three-dimensional point cloud model is a collection of points on the surface of an object in space obtained by three-dimensional scanning technology. The equipment entity refers to the three-dimensional model of each specific equipment in the production line and its attribute description. The geometric information model is a mathematical model that describes the geometric shape and spatial relationship of the object. The physical property database is a database that stores the physical property information of the object, including material properties (such as density, conductivity, strength, etc.), thermodynamic properties (such as temperature, pressure, etc.) and mechanical properties (such as stiffness, elasticity, etc.). The physical information model is a digital representation of comprehensive geometric information and physical properties, which is used to describe and simulate the behavior and performance of the object under actual working conditions. The text mining is a technology that extracts useful information and knowledge from a large amount of text data, including natural language processing, information retrieval and data mining. The knowledge extraction is the process of identifying and extracting structured knowledge from data, including entity recognition, relationship extraction and rule generation. The process knowledge ontology is a systematic representation of knowledge related to the production process, including process flow, process parameters, equipment operation and quality control. The process rule model is a model that describes various rules and constraints in the production process, including operating specifications, quality standards and safety regulations. The digital twin BIM model is a digital twin of the actual production line, including information such as equipment, process, operation and environment. The radio frequency identification technology is a technology that uses radio frequency signals for non-contact information transmission and identification. The semantic entity is a concept or object with a clear semantic description, which is used for semantic web and ontology modeling. The hard busbar prefabrication domain ontology is an ontology model specifically constructed for the hard busbar prefabrication production process, including knowledge such as production equipment, process flow, operating specifications and quality standards. The augmented reality technology is a technology that superimposes virtual information on the real world, and presents virtual images, text and other information in the user's field of vision through a display device.

[0066] Use 3D laser scanners to comprehensively scan the equipment, sites and materials of the production line to obtain high-precision point cloud data, pre-process the collected point cloud data, including removing noise points and isolated points, etc., to improve data quality, align and splice the point cloud data obtained from multiple perspectives and scenes to form a complete point cloud model, and use 3D modeling software such as AutoCAD, SolidWorks etc., convert the point cloud model into a three-dimensional solid model, build a geometric information model of the production line, collect the power, speed, temperature, pressure and other physical parameters of each device in the production line through sensors, instruments and other monitoring means, organize and store the collected physical parameters according to the equipment type, timestamp, etc., establish a physical property database of the equipment, obtain the property parameters of the materials (such as steel, welding materials, insulating materials, etc.) used in each process section of the production line, such as size, material, electrical properties, etc., classify and store the material property parameters according to category, specification, etc., build a material property database, create a unique identifier (such as ID, code, etc.) for each device and material entity in the geometric information model, map and associate the device parameters in the physical property database with the corresponding device entity to form a device physical information model, map and associate the material parameters in the material property database with the corresponding material entity to form a material physical information model, integrate the physical information models of equipment and materials, build an overall physical information model of the production line, collect the hard busbar prefabrication production line The process documents, including process flow, operating procedures, quality standards, etc., are mined and knowledge extracted from the process documents to extract key process parameters, operating steps, constraints, etc. The ontology modeling method is used to define the core concepts, relationships and attributes in the field of hard busbar prefabrication, and the process knowledge ontology is constructed. The extracted process knowledge is mapped into the process knowledge ontology to form a structured and semantic process rule knowledge base. The process rule knowledge base is associated with the physical information model, and process attributes and constraints are added to equipment and material entities. The physical information model and the process rule knowledge base are integrated to construct the process rule model of the production line. The geometric information model is used as the basis of the digital twin model to provide a three-dimensional visualization scene of the production line. The equipment and material parameters in the physical information model are bound to the corresponding geometric entities to realize parameter visualization. The process constraints and logical relationships in the process rule model are associated with the relevant geometric entities and physical parameters. The geometric model, physical parameters and process rules are integrated in the digital twin platform to construct a digital twin BIM model of the production line.

[0067] Deploy sensors, RFID readers, barcode scanners and other data collection equipment on the production line to collect equipment operating parameters (such as current, voltage, speed, etc.), material locations (such as inventory, delivery information, etc.) and personnel information (such as operator location, operating behavior, etc.) in real time, transmit the collected status data to the digital twin platform, and associate the data with the corresponding virtual entities in the digital twin BIM model. Through data mapping and synchronization mechanisms, the real-time synchronization update of physical entity status changes and virtual models is achieved. Integrate physical entities, virtual models and real-time data in the digital twin platform to build a virtual-real fusion model of the production line;

[0068] Use ontology languages ​​(such as OWL, RDF, etc.) to semantically model entities such as equipment, materials, and personnel in the production line, define the types, attributes, and relationships of entities, combine expert knowledge and industry standards in the field of hard busbar prefabrication, build domain ontology, define core concepts, terms, and logical rules, and form a structured domain knowledge representation. Map and associate the geometric entities, physical properties, and process rules in the digital twin BIM model with the semantic entities in the domain ontology. Through semantic reasoning and knowledge fusion, integrate implicit domain knowledge with explicit model knowledge to obtain a semantically rich first knowledge base.

[0069] An augmented reality system is deployed at the production site, including AR glasses, mobile terminals, edge servers, etc. The digital twin BIM model and the virtual-reality fusion model are loaded into the AR system as virtual content for superimposed display. Through visual tracking and feature matching technology, the equipment, materials and personnel at the production site are identified in real time and aligned with the virtual model. The virtual information (such as equipment parameters, material properties, process guidance, etc.) is superimposed on the physical objects on site to provide an intuitive and interactive augmented reality experience, thereby obtaining the first production model.

[0070] In this embodiment, a geometric information model of the production line is constructed by three-dimensional laser scanning technology, and high-precision digital reconstruction of the production environment is achieved, which provides basic scenes and spatial coordinate references for subsequent physical modeling, virtual-real mapping and visual management and control, and improves the accuracy and intuitiveness of digital management and control. Based on geometric, physical and process models, a digital twin BIM model of the production line is constructed to achieve digital mapping and simulation of all elements and processes of the production line, providing a digital testing ground and decision-making space for production management, and improving the predictability and operability of management and control. The semantic web technology is used to construct a knowledge base in the field of hard busbar prefabrication, and it is mapped with the digital twin model to form a semantically rich knowledge base, which realizes the structured representation and semantic association of knowledge in the fields of equipment, process, materials, etc. of the production line, provides comprehensive semantic information and reasoning basis for intelligent decision-making, and improves the knowledge density and intelligence level of management and control. In summary, this embodiment realizes the comprehensive collection of production data, real-time monitoring of production status, intelligent optimization of production process and visualization of production management, significantly improving the digitalization, networking and intelligence level of the production line, and providing technical support and innovation power for the high-quality development of hard busbar prefabrication enterprises.

[0071] In an optional embodiment,

[0072] Based on the process rule model, the physical information model and the geometric information model, a digital twin BIM model of a hard busbar prefabrication production line is constructed as shown in the following formula:

[0073] ;

[0074] in, H Represents the digital twin BIM model, R represents the rotation matrix, P A column vector representing sensor data points, t represents the translation vector, A represents the state transfer matrix, express k The estimated state value at time B represents the control matrix, u k express k The control input at the moment, F i Indicates i The feature vector of the data, F j Indicates j The feature vector of the data, σ represents the activation function, J Representation Node m The neighboring nodes of N ( m ) represents a nodem The set of neighboring nodes of a mn represents the edge weight, W (l) Indicates l The weight matrix of the layer, Indicates l Tier m The feature vector of each node.

[0075] In this embodiment, coordinate transformation is performed through rotation matrix and translation vector to achieve alignment and fusion of point cloud data and BIM model, improve the geometric accuracy of the model and the accuracy of physical property description, and lay a solid data foundation for subsequent simulation analysis, virtual-reality interaction and other applications. By calculating the cosine of the angle between different data feature vectors, the similarity of the data is measured, and the semantic association and fusion of multi-source data are achieved, which improves the semantic consistency and knowledge density of the model, establishes semantic association and knowledge fusion between data, realizes cross-domain and cross-system information integration and sharing, and improves the intelligence level and application value of the model. The introduction of graph neural network improves the model's modeling and reasoning capabilities for complex production systems, and expands the scope and scenarios of digital twin technology. In summary, this embodiment realizes comprehensive digital mapping and intelligent control of the hard busbar prefabrication production line, greatly improves the efficiency of production management and the scientific nature of decision-making, and provides strong technical support for the industry's digital transformation and intelligent manufacturing upgrades.

[0076] S2. Based on the first production model, a multi-agent collaborative framework is combined to build a production line intelligent control system containing multiple layers, collect real-time status data through multi-source heterogeneous sensors in the perception layer, and generate a high-dimensional feature vector of the production line status through feature extraction and data fusion technology, add the high-dimensional feature vector to the control layer, build a dynamic optimization control model in combination with process parameters and quality requirements, generate the optimal control sequence in combination with the adaptive control algorithm, adjust the control strategy in real time in combination with the production line feedback data, and solve the candidate scheduling solution set through the optimization layer;

[0077] The multi-agent collaborative framework refers to a framework in which multiple agents (or robots, agents, etc.) interact and collaborate with each other to complete complex tasks together. The production line intelligent control system uses advanced control algorithms, sensor technology and information processing methods to monitor the production line in real time, make intelligent decisions and optimize control. The data fusion technology refers to the technology of integrating and analyzing data from multiple sources and types. The high-dimensional feature vector refers to a data vector with a large number of feature dimensions. The dynamic optimization control model is a mathematical model that optimizes the control strategy in real time under a changing environment. The adaptive control algorithm is a type of algorithm that can adjust the control strategy according to changes in the system itself and changes in the external environment. The optimal control sequence is a series of control operations obtained by solving the optimization problem given the system dynamic model and performance indicators.

[0078] In an optional embodiment,

[0079] Based on the first production model, a production line intelligent control system with multiple layers is constructed in combination with a multi-agent collaborative framework. Real-time status data is collected through multi-source heterogeneous sensors in the perception layer, and a high-dimensional feature vector of the production line status is generated through feature extraction and data fusion technology. The high-dimensional feature vector is added to the control layer, and a dynamic optimization control model is constructed in combination with process parameters and quality requirements. The optimal control sequence is generated in combination with an adaptive control algorithm, and the control strategy is adjusted in real time in combination with the production line feedback data. The candidate scheduling solution set is solved through the optimization layer, including:

[0080] Based on the first production model, a production line intelligent control system including multiple layers is constructed in combination with a multi-agent collaborative framework, wherein the production line intelligent control system includes a perception layer, a control layer and an optimization layer;

[0081] Real-time status data is collected through multi-source heterogeneous sensors in the perception layer, the real-time status data is preprocessed and the data dimension is reduced through independent component analysis to obtain standard status data, frequency domain features are extracted from the standard status data through Fourier transform, time domain features are extracted in combination with statistical features, image processing is performed based on machine vision data, product defects and assembly accuracy are extracted as morphological features, the extracted features are aligned and spliced ​​in the time dimension to generate a high-dimensional feature matrix, local patterns and temporal dependencies in the high-dimensional feature matrix are determined in combination with a pre-set neural network module, high-level feature representations are extracted, corresponding weights are assigned to the high-level feature representations through a self-attention mechanism, and weighted fusion is performed to obtain the high-dimensional feature vector;

[0082] Add the high-dimensional feature vector to the control layer, set state variables and action variables, determine the value range of state variables and action variables in combination with process parameters and quality requirements, obtain state space and action space, construct a reward function, combine to obtain the dynamic optimization control model, perform parameter estimation through an adaptive control algorithm based on the dynamic optimization control model, set an adaptive controller and adjust controller parameters in real time, perform stability analysis on the dynamic optimization control model and the adaptive controller, and obtain a stability value. If the stability value is greater than a preset stability threshold, the current model is considered to be stable, and the optimal control sequence is output through the dynamic optimization control model;

[0083] Based on the optimal control sequence, a simulation application is performed, and the hyperparameters in the dynamic optimization control model are adjusted in real time according to the production line feedback data, and the optimal control sequence is regenerated to obtain the candidate scheduling solution.

[0084] The independent component analysis is a technique that decomposes a mixed signal into independent components through statistical methods. The Fourier transform is a mathematical method used to convert a function (or signal) from the time domain to the frequency domain. The assembly accuracy refers to the ability to correctly assemble various parts or components together during the product manufacturing process to ensure that they meet the design requirements. The high-dimensional feature matrix refers to a data matrix with a large number of feature dimensions. The local pattern refers to the characteristics or patterns of local areas or parts in the data. The temporal dependency refers to the causal or correlation relationship between various time points in the time series data. The state variable is a variable that describes the state of a dynamic system. The value of the state variable changes with time. The action variable is a variable determined and adjusted by the controller in the control system. The value of the action variable directly affects the behavior and response of the system. The state space refers to the set of all state values ​​that may exist in a dynamic system within a certain time range. The action space is the set of all possible actions or control input values ​​in the control system. The stability analysis refers to the process of analyzing and evaluating the stability of a dynamic system.

[0085] Based on the multi-agent collaborative framework and the first production model, a hierarchical structure of the production line intelligent control system is constructed, including the perception layer, the control layer and the optimization layer. In the perception layer, multi-source heterogeneous sensors (such as temperature sensors, pressure sensors, visual sensors, etc.) are deployed to collect real-time status data of the production line. The collected real-time status data is preprocessed, including data cleaning, denoising, standardization and other operations to improve data quality. The independent component analysis algorithm is used to reduce the dimension of the preprocessed data, remove redundant information, and obtain standard status data. Feature extraction is performed on the standard status data, including time domain features and frequency domain features. The time domain data is converted to the frequency domain through Fourier transform to extract the frequency domain. Domain features, calculate the statistical features of time domain data, such as mean, variance, peak, etc., extract time domain features, use machine vision technology to process and analyze product images, extract morphological features such as product defects and assembly accuracy, align and splice the extracted time domain features, frequency domain features and morphological features in the time dimension, generate a high-dimensional feature matrix, use pre-set neural network modules (such as convolutional neural networks, recursive neural networks, etc.) to learn and extract local patterns and temporal dependencies of the high-dimensional feature matrix, obtain high-level feature representation, introduce self-attention mechanism, assign different weights to high-level feature representation, and perform weighted fusion to obtain the final high-dimensional feature vector;

[0086] The high-dimensional feature vector is passed to the control layer as the input of the control decision. In the control layer, the state variables and action variables are defined, and the value range of the state variables and action variables is determined in combination with the process parameters and quality requirements. The state space and action space are obtained, and the reward function is constructed to evaluate the pros and cons of the control decision. The reward function considers multiple goals such as production efficiency, quality, and energy consumption, assigns weights to different goals, forms a comprehensive evaluation index, combines the state space, action space, and reward function, and constructs a dynamic optimization control model. The dynamic optimization control model takes state variables as input, action variables as output, and reward function as optimization target, and establishes a mapping relationship between state, action, and reward. Based on the dynamic optimization control model, an adaptive control algorithm (such as adaptive dynamic programming, adaptive model predictive control, etc.) is used for parameter estimation and controller design. An adaptive controller is set to adjust controller parameters in real time to adapt to the dynamic changes of the production line. The controller calculates the optimal control action according to the current state and optimization target, and sends it to the execution layer. The dynamic optimization control model and the adaptive controller are subjected to stability analysis, and the stability value is calculated to determine whether the stability value is greater than the preset stability threshold. If so, the current model is considered stable and continues to be executed. Otherwise, the model structure or parameters need to be adjusted until the stability requirements are met. Through the dynamic optimization control model, combined with the adaptive controller, the optimal control sequence is output to guide the real-time scheduling and optimization of the production line.

[0087] The optimal control sequence is applied to the simulation environment of the production line to evaluate its actual effect. According to the real-time data fed back by the production line, the hyperparameters in the control model (such as learning rate, decay factor, etc.) are dynamically adjusted, and the optimal control sequence is regenerated. After multiple iterations of optimization, the candidate scheduling scheme that meets the production requirements is obtained as the final output of the intelligent control of the production line.

[0088] In this embodiment, multi-source heterogeneous sensors are deployed to collect multi-dimensional real-time status data of the production line, realize comprehensive perception and monitoring of the production process, provide a data basis for subsequent modeling and optimization, and use independent component analysis, Fourier transform, statistical analysis, machine vision and other technologies to extract key features from the original data, including time domain features, frequency domain features and morphological features, effectively compress data dimensions, highlight key information, improve data quality and availability, use neural network modules to perform deep learning on high-dimensional feature matrices, extract implicit local patterns and temporal dependencies, obtain higher-level feature representations, enhance the expressiveness of data and semantic information, and provide intelligent decision-making. The system provides support for the production line strategy and adopts an adaptive control algorithm to estimate the model parameters in real time and adjust the controller parameters so that the control system can adapt to the dynamic changes of the production line, improve the control accuracy and stability, and ensure the smooth operation of the production line. The multi-agent collaborative framework is adopted to divide the production line into multiple agents, each of which is responsible for different tasks and functions. Through communication, negotiation and cooperation among agents, the collaborative optimization and intelligent decision-making of the entire production line are realized. In summary, this embodiment realizes comprehensive perception, intelligent modeling, dynamic optimization and adaptive control of the production line, which significantly improves the automation, intelligence and optimization level of the production line and provides key technical support for intelligent manufacturing.

[0089] In an optional embodiment,

[0090] Based on the dynamic optimization control model, the parameter estimation is performed by the adaptive control algorithm as shown in the following formula:

[0091] ;

[0092] in, Indicates time k The parameter estimate vector of Indicates time k - 1 The parameter estimate vector of K ( k ) indicates time k The Kalman gain matrix is y ( k ) indicates time k The model output is x ( k ) indicates time kThe input vector is x T ( k ) indicates time k The transpose of the input vector.

[0093] In this embodiment, through the recursive estimation formula, the online estimation and real-time update of the model parameters are realized, without the need for offline training or re-fitting, which reduces the computational overhead and time cost, improves the efficiency and real-time performance of parameter estimation, and dynamically adjusts the model parameters according to the real-time input and output data of the production line so that the model can adapt to the changes in the operating conditions, interference disturbances and uncertain factors of the production line, improves the adaptability and robustness of the model, introduces the Kalman gain matrix, performs filtering optimization on the parameter estimation, reduces the influence of measurement noise and process noise, and improves the accuracy and stability of parameter estimation. In summary, this embodiment improves the adaptability, robustness and predictive ability of the dynamic optimization control model, provides strong technical support for realizing intelligent control and optimization decision-making of the production line, and has important practical application value.

[0094] S3. Based on the set of candidate scheduling solutions, with the goal of maximizing production efficiency and equipment utilization, construct an objective function, combine it with a multi-objective optimization algorithm to solve it, determine the optimal scheduling solution, and combine it with edge computing and fog computing technology. Deploy an intelligent gateway on the production line, receive the optimal scheduling solution in real time and perform data processing, generate a control action sequence and send it to the production equipment.

[0095] The edge computing is a distributed computing paradigm, the core idea of ​​which is to store computing resources and data close to the data source and end user, i.e., edge devices or edge nodes. The fog computing is a computing model between cloud computing and edge computing. The multi-objective optimization algorithm is an algorithm for solving optimization problems with multiple conflicting objectives. The control action sequence refers to adjusting the system state through a series of continuous control actions in the control system according to the current system state and the expected goal, so as to achieve the desired control effect.

[0096] In an optional embodiment,

[0097] Based on the candidate scheduling scheme set, with the goal of maximizing production efficiency and equipment utilization, an objective function is constructed, and a multi-objective optimization algorithm is combined to solve it, and the optimal scheduling scheme is determined. In combination with edge computing and fog computing technology, an intelligent gateway is deployed on the production line, and the optimal scheduling scheme is received in real time and data is processed. A control action sequence is generated and sent to the production equipment, including:

[0098] Taking the maximization of production efficiency and equipment utilization as the goal, construct an objective function, set corresponding constraints for the objective function according to equipment specifications and task requirements, determine a search space based on the candidate scheduling solution set, divide the search space into multiple sub-areas, and randomly generate an initial population based on a multi-objective optimization algorithm and the candidate scheduling solution set, wherein each individual in the initial population corresponds to a candidate scheduling solution, and the sub-area is used as a territory;

[0099] The individuals in the initial population are distributed to each territory according to the size of the territory. For the individuals in each territory, the fitness and Pareto level of each individual are calculated according to the production efficiency and equipment utilization rate. Individuals are selected in each territory by a roulette algorithm. For the selected individuals, they are randomly paired and multi-point crossover operations are performed according to a preset crossover probability to generate a first individual. For the first individual, a mutation operation is performed according to a preset mutation probability to obtain offspring individuals and calculate the fitness value. The offspring individuals are sorted in descending order according to the fitness value, and the offspring individuals in the top 10% are selected as excellent individuals and individuals are selected for migration in combination with a preset migration rate to replace the individual with the smallest fitness value in the target territory. The operation is repeated until the preset maximum number of iterations is reached to obtain the optimal scheduling plan.

[0100] Based on edge computing and fog computing methods, an intelligent gateway is deployed on the production line, and the optimal scheduling plan is obtained on the edge server in combination with the industrial communication protocol. The optimal scheduling plan is split into a control action sequence on the edge server and sent to the production equipment. The production equipment performs production activities according to the control action sequence.

[0101] The search space refers to the set of all possible values ​​that may contain solutions in optimization or search problems, the territory refers to the area of ​​solutions or local optimal solutions that have been found during the search process, the Pareto level refers to one of the criteria used to measure the quality of solutions in multi-objective optimization problems, the roulette algorithm is a selection algorithm, commonly used in genetic algorithms and evolutionary algorithms, the multi-point crossover operation is a crossover operation in genetic algorithms, used to generate new individuals, and the fitness refers to a metric used to evaluate the quality of individual solutions in optimization or evolutionary algorithms.

[0102] Taking the maximization of production efficiency and equipment utilization as the optimization goals, the corresponding objective function is constructed. According to the specifications and task requirements of the equipment in the production line, the corresponding constraints are set for the objective function, such as equipment processing capacity, task priority, process sequence, etc. Based on the set of candidate scheduling solutions, the search space of the optimization problem is determined, that is, the solution space composed of all feasible scheduling solutions, and the search space is divided into multiple sub-areas, each of which represents an independent optimization territory, so as to facilitate parallel search and optimization;

[0103] Based on multi-objective optimization algorithms (such as NSGA-II, MOEA / D, etc.) and a set of candidate scheduling schemes, the initial population is randomly generated, in which each individual corresponds to a candidate scheduling scheme. According to the size of the territory, the individuals in the initial population are allocated to each territory to ensure the balance of the number of individuals in each territory. For the individuals in each territory, their fitness values ​​are calculated based on production efficiency and equipment utilization, and their Pareto levels are determined based on the Pareto dominance relationship. In each territory, a part of individuals with higher fitness are selected through the roulette algorithm as the parent individuals of subsequent genetic operations. For the selected individuals, they are randomly paired to form multiple parent combinations. A multi-point crossover operation is performed according to a preset crossover probability to generate the first individual. For the first individual, a mutation operation is performed according to a preset mutation probability to introduce new genetic information and improve the diversity of the population. For the mutated offspring individuals, their fitness values ​​are calculated to evaluate their quality. The offspring individuals are sorted in descending order according to their fitness values, and the individuals in the top 10% are selected as excellent individuals for random migration. Combined with the preset migration rate, a part of the individuals are selected from the excellent individuals for cross-territory migration to replace the individuals with the lowest fitness in the target territory. The operation is repeated until the preset maximum number of iterations is reached to obtain the optimal scheduling plan.

[0104] Based on edge computing and fog computing methods, intelligent gateways are deployed on the production line as a communication bridge between edge servers and production equipment. Through industrial communication protocols (such as OPC UA, MQTT, etc.), the optimal scheduling solution is optimized on the edge server. The optimal scheduling solution is split into specific control action sequences on the edge server, such as equipment start and stop, parameter setting, material scheduling, etc. The control action sequence is sent to each production equipment through the intelligent gateway to guide it to perform corresponding production activities. The production equipment performs corresponding production operations such as processing, assembly, logistics, etc. according to the received control action sequence, thereby realizing the automation and intelligence of the production process.

[0105] In this embodiment, by constructing objective functions of maximizing production efficiency and maximizing equipment utilization and setting corresponding constraints, multi-objective optimization of production scheduling problems is achieved, the contradiction between production efficiency and equipment utilization is balanced, and the overall performance of the production system is improved. A territory division strategy is adopted to divide the search space into multiple sub-areas, and each sub-area performs optimization search independently, which improves search efficiency and parallelism, speeds up the optimization speed, and shortens the generation time of scheduling schemes. By randomly generating the initial population and adopting genetic operations such as crossover and mutation, new genetic information is introduced to maintain the diversity of the population, avoid premature convergence, and improve the global search ability of the optimization algorithm. Through fitness calculation and Pareto rank evaluation, excellent individuals are selected for retention and migration, which accelerates the optimization convergence speed. At the same time, information exchange between territories is realized through migration operations, and the robustness and generalization ability of the algorithm are improved. In summary, this embodiment realizes intelligent optimization and efficient execution of production scheduling schemes, improves production efficiency, equipment utilization and production flexibility, and provides key technical support for the realization of intelligent manufacturing.

[0106] In an optional embodiment,

[0107] The fitness and Pareto level of each individual are calculated based on production efficiency and equipment utilization, and individuals are selected in each territory through the roulette algorithm as shown in the following formula:

[0108] ;

[0109] in, p g Represents an individual x g The probability of being selected, r ( x g ) represents an individual x g The Pareto level of ε represents a small positive number, d ( x g ) represents an individual x g The crowding distance in the same Pareto level is N represents the total number of individuals in the current population, r ( x h ) represents an individual x h The Pareto level of d ( x h ) represents an individual x h The crowding distance within the same Pareto level.

[0110] In this embodiment, the individuals in the population are non-dominated and sorted by calculating the Pareto level of the individuals, and the individuals are divided into different levels. The smaller the level, the higher the superiority of the individual, so that the non-dominated individuals are selected first, which improves the convergence speed and optimization quality of the population. By calculating the crowding distance of individuals in the same Pareto level, selecting individuals with large crowding distance helps to maintain the diversity and extensiveness of the population and avoid premature convergence and local optimality. Through the roulette algorithm, random selection is performed according to the selection probability of the individual, which not only takes into account the superiority of the individual, but also introduces a certain degree of randomness, thereby enhancing the diversity and exploration ability of the population. In summary, this embodiment realizes the diversity and uniformity of individual selection, maintains the diversity and extensiveness of the population while ensuring the convergence of the population, improves the efficiency and quality of multi-objective optimization, and provides an effective technical means for solving production scheduling problems.

[0111] Figure 2 FIG. 1 is a schematic diagram of a control system of a rigid busbar prefabrication production line based on a BIM model according to an embodiment of the present invention. Figure 2 As shown, the system comprises:

[0112] The first unit is used to build a digital twin BIM model of a hard busbar prefabrication production line, map the physical information, geometric information and process rules of the prefabrication production line to a virtual space, build a virtual-reality fusion model, combine semantic web technology and ontology modeling methods to semantically associate and attribute map the digital twin BIM model with entities in the production line, generate a first knowledge base, and combine augmented reality technology to register and fuse the digital twin BIM model with the virtual-reality fusion model to obtain a first production model;

[0113] The second unit is used to build a production line intelligent control system containing multiple layers based on the first production model and in combination with a multi-agent collaborative framework, collect real-time status data through multi-source heterogeneous sensors in the perception layer and generate a high-dimensional feature vector of the production line status through feature extraction and data fusion technology, add the high-dimensional feature vector to the control layer, build a dynamic optimization control model in combination with process parameters and quality requirements, generate an optimal control sequence in combination with an adaptive control algorithm, adjust the control strategy in real time in combination with production line feedback data, and solve a set of candidate scheduling solutions through the optimization layer;

[0114] The third unit is used to construct an objective function based on the candidate scheduling scheme set, with the goal of maximizing production efficiency and maximizing equipment utilization, and solve it in combination with a multi-objective optimization algorithm, determine the optimal scheduling scheme and combine edge computing and fog computing technologies, deploy an intelligent gateway on the production line, receive the optimal scheduling scheme in real time and perform data processing, generate a control action sequence and send it to the production equipment.

[0115] According to a third aspect of the embodiments of the present invention,

[0116] An electronic device is provided, comprising:

[0117] processor;

[0118] a memory for storing processor-executable instructions;

[0119] The processor is configured to call the instructions stored in the memory to execute the aforementioned method.

[0120] According to a fourth aspect of the embodiments of the present invention,

[0121] A computer-readable storage medium is provided, on which computer program instructions are stored. When the computer program instructions are executed by a processor, the aforementioned method is implemented.

[0122] The present invention may be a method, an apparatus, a system and / or a computer program product. The computer program product may include a computer-readable storage medium carrying computer-readable program instructions for executing various aspects of the present invention.

[0123] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A control method for a rigid busbar prefabrication production line based on a BIM model, characterized in that: include: Construct a digital twin BIM model of the hard busbar prefabrication production line, map the physical information, geometric information and process rules of the prefabrication production line to the virtual space, construct a virtual-reality fusion model, combine semantic web technology and ontology modeling methods to semantically associate and attribute map the digital twin BIM model with entities in the production line, generate a first knowledge base, combine augmented reality technology to align and fuse the digital twin BIM model and the virtual-reality fusion model, and obtain a first production model, including: Scan the equipment, site and materials of the hard busbar prefabrication production line through 3D laser scanning technology to obtain point cloud data, denoise and align the point cloud data, generate a 3D point cloud model in combination with 3D modeling software, generate a geometric information model of the production line in combination with the equipment entity, obtain the physical parameters of each device in the hard busbar prefabrication production line, wherein the physical parameters include power, rotation speed, temperature and pressure, establish a physical property database, obtain the material property parameters of each process section of the production line to construct a material property database, associate the physical property database and the material property database with the geometric information model to obtain a physical information model, obtain the process files of the hard busbar prefabrication production line, perform text mining and knowledge extraction on the process knowledge, construct a process knowledge ontology through ontology modeling, map the process knowledge into the process knowledge ontology, construct a process rule knowledge base and associate it with the physical information model to obtain a process rule model, and construct a digital twin BIM model of the hard busbar prefabrication production line based on the process rule model, the physical information model and the geometric information model; Based on the digital twin BIM model, the production line status data is collected through sensors, radio frequency identification technology and barcodes, including equipment operating parameters, material location and personnel information, and the collected production line status data is associated with the digital twin BIM model. The virtual model and the physical entity are aggregated through data mapping and data synchronization to build a virtual-real fusion model of the production line; The entities in the rigid busbar prefabrication production line are modeled as semantic entities through semantic web technology, entity attributes and relationships are defined, and core concepts are defined in combination with the rigid busbar prefabrication domain ontology to obtain structured domain knowledge. The geometric entities, physical attributes and process rules in the digital twin BIM model are mapped to semantic entities and domain ontology to obtain the first knowledge base; Deploy an AR system on-site at the hard busbar prefabrication production line through augmented reality technology and load the digital twin BIM model and the virtual-reality fusion model into the AR system, and perform real-time registration and superimposed display through visual tracking and feature matching technology to obtain the first production model; Based on the first production model, a production line intelligent control system with multiple layers is constructed in combination with a multi-agent collaborative framework. Real-time status data is collected through multi-source heterogeneous sensors in the perception layer, and a high-dimensional feature vector of the production line status is generated through feature extraction and data fusion technology. The high-dimensional feature vector is added to the control layer, and a dynamic optimization control model is constructed in combination with process parameters and quality requirements. The optimal control sequence is generated in combination with an adaptive control algorithm, and the control strategy is adjusted in real time in combination with production line feedback data. A set of candidate scheduling solutions is solved through the optimization layer, including: Based on the first production model, a production line intelligent control system including multiple layers is constructed in combination with a multi-agent collaborative framework, wherein the production line intelligent control system includes a perception layer, a control layer and an optimization layer; Real-time status data is collected through multi-source heterogeneous sensors in the perception layer, the real-time status data is preprocessed and the data dimension is reduced through independent component analysis to obtain standard status data, frequency domain features are extracted from the standard status data through Fourier transform, time domain features are extracted in combination with statistical features, image processing is performed based on machine vision data, product defects and assembly accuracy are extracted as morphological features, the extracted features are aligned and spliced ​​in the time dimension to generate a high-dimensional feature matrix, local patterns and temporal dependencies in the high-dimensional feature matrix are determined in combination with a pre-set neural network module, high-level feature representations are extracted, corresponding weights are assigned to the high-level feature representations through a self-attention mechanism, and weighted fusion is performed to obtain the high-dimensional feature vector; Add the high-dimensional feature vector to the control layer, set state variables and action variables, determine the value range of state variables and action variables in combination with process parameters and quality requirements, obtain state space and action space, construct a reward function, combine to obtain the dynamic optimization control model, perform parameter estimation through an adaptive control algorithm based on the dynamic optimization control model, set an adaptive controller and adjust controller parameters in real time, perform stability analysis on the dynamic optimization control model and the adaptive controller, and obtain a stability value. If the stability value is greater than a preset stability threshold, the current model is considered to be stable, and the optimal control sequence is output through the dynamic optimization control model; Perform simulation application based on the optimal control sequence, adjust the hyperparameters in the dynamic optimization control model in real time according to the production line feedback data and regenerate the optimal control sequence to obtain the candidate scheduling solution; Based on the candidate scheduling scheme set, with the goal of maximizing production efficiency and equipment utilization, an objective function is constructed, and a multi-objective optimization algorithm is combined to solve it, and the optimal scheduling scheme is determined. In combination with edge computing and fog computing technology, an intelligent gateway is deployed on the production line to receive the optimal scheduling scheme in real time and perform data processing, generate a control action sequence and send it to the production equipment, including: Taking the maximization of production efficiency and equipment utilization as the goal, construct an objective function, set corresponding constraints for the objective function according to equipment specifications and task requirements, determine a search space based on the candidate scheduling solution set, divide the search space into multiple sub-areas, and randomly generate an initial population based on a multi-objective optimization algorithm and the candidate scheduling solution set, wherein each individual in the initial population corresponds to a candidate scheduling solution, and the sub-area is used as a territory; The individuals in the initial population are distributed to each territory according to the size of the territory. For the individuals in each territory, the fitness and Pareto level of each individual are calculated according to the production efficiency and equipment utilization rate. Individuals are selected in each territory by a roulette algorithm. For the selected individuals, they are randomly paired and multi-point crossover operations are performed according to a preset crossover probability to generate a first individual. For the first individual, a mutation operation is performed according to a preset mutation probability to obtain offspring individuals and calculate the fitness value. The offspring individuals are sorted in descending order according to the fitness value, and the offspring individuals in the top 10% are selected as excellent individuals and individuals are selected for migration in combination with a preset migration rate to replace the individual with the smallest fitness value in the target territory. The operation is repeated until the preset maximum number of iterations is reached to obtain the optimal scheduling plan. Based on edge computing and fog computing methods, an intelligent gateway is deployed on the production line, and the optimal scheduling plan is obtained on the edge server in combination with the industrial communication protocol. The optimal scheduling plan is split into a control action sequence on the edge server and sent to the production equipment. The production equipment performs production activities according to the control action sequence.

2. The method according to claim 1, characterized in that: Based on the process rule model, the physical information model and the geometric information model, a digital twin BIM model of a hard busbar prefabrication production line is constructed as shown in the following formula: ; in, H Represents the digital twin BIM model, R represents the rotation matrix, P A column vector representing sensor data points, t represents the translation vector, A represents the state transfer matrix, express k The estimated state value at time B represents the control matrix, express k The control input at the moment, Indicates i The feature vector of the data, Indicates j The feature vector of the data, represents the activation function, Representation Node m The neighboring nodes of Representation Node m The set of neighboring nodes of represents the edge weight, Indicates The weight matrix of the layer, Indicates Tier m The feature vector of each node.

3. The method according to claim 1, characterized in that Based on the dynamic optimization control model, the parameter estimation is performed by the adaptive control algorithm as shown in the following formula: ; in, Indicates time k The parameter estimate vector of Indicates time k - 1 The parameter estimate vector of K ( k ) indicates time k The Kalman gain matrix is y ( k ) indicates time k The model output is x ( k ) indicates time k The input vector is Indicates time k The transpose of the input vector.

4. The method according to claim 1, characterized in that: The fitness and Pareto level of each individual are calculated based on production efficiency and equipment utilization, and individuals are selected in each territory through the roulette algorithm as shown in the following formula: ; in, Represents an individual x g The probability of being selected, Represents an individual x g The Pareto level of represents a small positive number, Represents an individual x g The crowding distance in the same Pareto level is N represents the total number of individuals in the current population, Represents an individual x h The Pareto level of Represents an individual x h The crowding distance within the same Pareto level.

5. A hard busbar prefabrication production line control system based on a BIM model, used to implement the method described in any one of claims 1 to 4, characterized in that: include: The first unit is used to build a digital twin BIM model of a hard busbar prefabrication production line, map the physical information, geometric information and process rules of the prefabrication production line to a virtual space, build a virtual-reality fusion model, combine semantic web technology and ontology modeling methods to semantically associate and attribute map the digital twin BIM model with entities in the production line, generate a first knowledge base, and combine augmented reality technology to register and fuse the digital twin BIM model with the virtual-reality fusion model to obtain a first production model; The second unit is used to build a production line intelligent control system containing multiple layers based on the first production model and in combination with a multi-agent collaborative framework, collect real-time status data through multi-source heterogeneous sensors in the perception layer and generate a high-dimensional feature vector of the production line status through feature extraction and data fusion technology, add the high-dimensional feature vector to the control layer, build a dynamic optimization control model in combination with process parameters and quality requirements, generate an optimal control sequence in combination with an adaptive control algorithm, adjust the control strategy in real time in combination with production line feedback data, and solve a set of candidate scheduling solutions through the optimization layer; The third unit is used to construct an objective function based on the candidate scheduling scheme set, with the goal of maximizing production efficiency and maximizing equipment utilization, and solve it in combination with a multi-objective optimization algorithm, determine the optimal scheduling scheme and combine edge computing and fog computing technologies, deploy an intelligent gateway on the production line, receive the optimal scheduling scheme in real time and perform data processing, generate a control action sequence and send it to the production equipment.

6. An electronic device, characterized in that: include: processor; a memory for storing processor-executable instructions; The processor is configured to call the instructions stored in the memory to execute the method described in any one of claims 1 to 4.

7. A computer-readable storage medium having computer program instructions stored thereon, characterized in that: When the computer program instructions are executed by a processor, the method according to any one of claims 1 to 4 is implemented.

Citation Information