A monitoring system and method for dry beach length of tailings pond
By collecting and analyzing the soil density, humidity and water level elevation data of tailings ponds, combined with dry beach length and risk analysis, the problem of incomplete assessment of tailings pond status in the existing technology is solved, and the measurement accuracy and risk identification are improved. capability, reducing monitoring costs.
Patent Information
- Application Number
- CN202411107365.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-08-13
AI Technical Summary
The existing dry beach length monitoring method of tailings ponds failed to comprehensively collect and analyze soil density and humidity data, resulting in incomplete assessment of tailings pond status, and the measurement accuracy depends on the drone image resolution and data processing technology, and there are details Missing and high cost maintenance issues.
The monitoring point analysis module is used to collect soil density, humidity and water level elevation data, calculate dry beach length through the dry beach data analysis module, and obtain a comprehensive safety assessment index in combination with the tailings pond risk analysis module, providing early warning terminals to prompt potential risks.
Through detailed soil sample processing and comprehensive evaluation coefficient calculation, the accuracy of dry beach length measurement and tailings pond status judgment ability are improved, ensuring timely identification and prevention of potential risks.
Smart Images

Figure CN118640850B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tailings pond flat beach length monitoring, and in particular to a tailings pond dry beach length monitoring system and method. Background Art
[0002] A tailings pond is a place formed by building a dam to block the valley mouth or enclosing land, used to store tailings or other industrial waste discharged from metal and non-metal mines after ore sorting. A tailings pond is a man-made debris flow hazard source with high potential energy and there is a risk of dam breach. To ensure the safety of the tailings pond, the dry beach is one of the important elements of the tailings pond, and the length of the dry beach is an important indicator of the operation and management of the tailings pond. An accurate and reliable method for measuring the length of the dry beach is very important.
[0003] Prior art, such as the invention patent application with announcement number CN114838709A, discloses an automated monitoring method for the dry beach length of a tailings pond, comprising the following steps: S1. Establishing a high-precision orthophoto and a three-dimensional model of the tailings pond through drone photography and mapping, including a digital orthophoto map DOM and a digital surface model DSM; S2. Based on the digital surface model DSM of the tailings pond, obtaining the overall slope of the dry beach of n sections, taking the average of the overall slopes of the dry beach of multiple sections as the average slope of the dry beach of the dam section, extracting the water level elevations of the n sections and taking the average as the initial water level elevation; using a function expression to fit the functional relationship between the beach elevation of each section and the dry beach length; S3. Collecting the water level elevation, uploading the collected water level elevation data to a cloud platform, the cloud platform calculating the current dry beach length according to the initial dry beach length, the current water level elevation and the functional relationship between the beach elevation and the dry beach length, comparing the calculated dry beach length with the dry beach length warning threshold, and determining whether a warning is required.
[0004] With respect to the above scheme, the applicant of the present invention has found that the above technology has at least the following technical problems: 1. The above method does not mention how to collect and analyze soil density and moisture data on the dry beach of the tailings pond. The density and moisture of the soil directly affect the strength and bearing capacity of the soil, thus resulting in an incomplete assessment of the dry beach status of the tailings pond. It also does not mention how to set up specific monitoring points and analyze the data of the monitoring points, thereby failing to accurately identify potential problems in the dry beach area.
[0005] 2. The accuracy of the digital orthophotos used in the above scheme depends on the resolution of drones or aerial photography. If the image resolution is insufficient, it will lead to missing details and inaccurate measurements. The accuracy of the digital surface model depends on data acquisition and processing technology. Incorrect capture of terrain features or improper data processing will affect the accuracy of the model. In order to maintain the timeliness of the data, regular drone flights and data updates are required, which increases the cost of monitoring and maintenance. Summary of the invention
[0006] The purpose of the present invention is to provide a monitoring system and method for the dry beach length of a tailings pond, which solves the problems existing in the background technology.
[0007] In order to solve the above technical problems, the present invention adopts the following technical solutions: The present invention provides a monitoring system for the dry beach length of a tailings pond, including: a monitoring point analysis module, which is used to set various parameter collection points, collect the monitoring point influencing parameters of the corresponding sedimentation beach of the specified tailings pond, the monitoring point influencing parameters include soil density, soil moisture and water level elevation, and then analyze the comprehensive evaluation coefficient of the specified tailings pond in the corresponding sedimentation beach, thereby analyzing the specific position corresponding to each monitoring point.
[0008] The dry beach data analysis module is used to analyze the dry beach data corresponding to each monitoring point according to the specific location corresponding to each monitoring point.
[0009] The dry beach length analysis module is used to analyze the dry beach data corresponding to the monitoring point and obtain the dry beach length corresponding to the specified tailings pond.
[0010] The tailings pond risk analysis module is used to calculate the comprehensive safety assessment index corresponding to the designated tailings pond based on the dry beach length corresponding to the designated tailings pond, as well as the downstream slope ratio and infiltration line height of the accumulation dam corresponding to the designated tailings pond, and then analyze whether the comprehensive safety of the designated tailings pond meets the requirements.
[0011] The early warning terminal is used to issue early warning prompts when the comprehensive safety of the designated tailings pond does not meet the requirements.
[0012] Preferably, the acquisition of the influencing parameters of the monitoring points of the designated tailings pond corresponding to the sedimentation beach is carried out in the following specific acquisition process: each monitoring point includes a first monitoring point and a second monitoring point, a first monitoring line and a second monitoring line are set on the sedimentation beach of the designated tailings pond, and each parameter acquisition point includes each first parameter acquisition point and each second parameter acquisition point;
[0013] According to the set monitoring depth, soil sampling is carried out at the set monitoring depth to obtain each soil sample, and then the soil moisture corresponding to each soil sample is monitored using a soil moisture meter, and each soil sample is placed in a container of corresponding known volume to ensure that each soil sample fills each container and there is no gap. The containers filled with each soil sample are placed in an oven for drying, and weighed again after drying to obtain the dry soil mass corresponding to each soil sample. The dry soil mass corresponding to each soil sample is divided by the corresponding volume of each container, and the result obtained is the soil density corresponding to each soil sample. The original ground is used as the reference plane, and the water level elevation is monitored using a water level meter, thereby obtaining the soil moisture, soil density and water level elevation corresponding to the first monitoring line at each first parameter collection point and the second monitoring line at each second parameter collection point.
[0014] In a second aspect, the present invention provides a method for monitoring the dry beach length of a tailings pond, comprising: step one, monitoring point analysis: setting various parameter collection points, collecting monitoring point influencing parameters of the corresponding sedimentation beach of the specified tailings pond, the monitoring point influencing parameters including soil density, soil moisture and water level elevation, and then analyzing the comprehensive evaluation coefficient of the specified tailings pond in the corresponding sedimentation beach, thereby analyzing the specific position corresponding to each monitoring point.
[0015] Step 2: Dry beach data analysis: According to the specific location of each monitoring point, the dry beach data corresponding to each monitoring point is analyzed.
[0016] Step 3: Dry beach length analysis: According to the dry beach data corresponding to the monitoring point, the dry beach length corresponding to the designated tailings pond is analyzed and obtained.
[0017] Step 4. Tailings pond risk analysis: Based on the dry beach length corresponding to the designated tailings pond, as well as the downstream slope ratio and infiltration line height of the pile dam corresponding to the designated tailings pond, the comprehensive safety assessment index corresponding to the designated tailings pond is calculated, and then it is analyzed whether the comprehensive safety of the designated tailings pond meets the requirements.
[0018] Step 5. Early warning: When the comprehensive safety of the designated tailings pond does not meet the requirements, an early warning will be issued.
[0019] The beneficial effects of the present invention are: 1. A monitoring system and method for the dry beach length of a tailings pond provided by the present invention, in the process of collecting soil density and moisture, through detailed soil sample processing, including soil moisture meter monitoring, weighing after drying and density calculation steps, is conducive to accurately understanding the soil characteristics of the tailings pond sedimentation beach, and providing a reliable data basis for further dry beach length and stability analysis. In the process of calculating the comprehensive evaluation coefficient, the specific location of the monitoring point is determined by substituting the soil moisture, density and water level elevation of the monitoring point into the calculation formula, so that the analysis of the dry beach length is more accurate.
[0020] 2. In the dry beach length analysis process of the embodiment of the present invention, by analyzing the dry beach data of each monitoring point, it is beneficial to accurately calculate the dry beach length of the tailings pond. The accurate dry beach length is of great significance for assessing the risks of the tailings pond and formulating emergency measures, ensuring that the measurement results of the dry beach length have high accuracy, thereby improving the ability to judge the status of the tailings pond.
[0021] 3. In the process of tailings pond risk analysis, the embodiment of the present invention calculates the comprehensive safety assessment index by obtaining the downstream slope ratio and the infiltration line height, which is conducive to comprehensively assessing the safety of the tailings pond, and then timely identifying potential risks and taking preventive and treatment measures. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0023] Figure 1 It is a schematic diagram of the system structure connection of the present invention.
[0024] Figure 2 It is a schematic flow chart of the implementation steps of the present invention. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0026] See also Figure 1 As shown, the present invention provides a monitoring system for the dry beach length of a tailings pond, the system comprising: a monitoring point analysis module, a dry beach data analysis module, a dry beach length analysis module, a tailings pond risk analysis module, an early warning terminal and a database.
[0027] The monitoring point analysis module is connected to the dry beach data analysis module, the dry beach data analysis module is respectively connected to the database and the dry beach length analysis module, the dry beach length analysis module is connected to the tailings pond risk analysis module, and the tailings pond risk analysis module is respectively connected to the early warning terminal and the database.
[0028] The monitoring point analysis module is used to set various parameter collection points and collect the monitoring point influencing parameters of the designated tailings pond corresponding to the sedimentation beach. The monitoring point influencing parameters include soil density, soil moisture and water level elevation, and then analyze the comprehensive evaluation coefficient of the designated tailings pond in the corresponding sedimentation beach, thereby analyzing the specific location corresponding to each monitoring point.
[0029] It should be noted that the water level elevation refers to the height of the water surface in the tailings pond under specific conditions, and this height is relative to a certain reference plane. This water level elevation reflects the water storage conditions inside the tailings pond.
[0030] In a specific embodiment, the monitoring point influencing parameters of the designated tailings pond corresponding to the sedimentation beach are collected, and the specific collection process is as follows: each monitoring point includes a first monitoring point and a second monitoring point, a first monitoring line and a second monitoring line are set on the sedimentation beach of the designated tailings pond, and each parameter collection point includes each first parameter collection point and each second parameter collection point;
[0031] According to the set monitoring depth, soil sampling is carried out at the set monitoring depth to obtain each soil sample, and then the soil moisture corresponding to each soil sample is monitored using a soil moisture meter, and each soil sample is placed in a container of corresponding known volume to ensure that each soil sample fills each container and there is no gap. The containers filled with each soil sample are placed in an oven for drying, and weighed again after drying to obtain the dry soil mass corresponding to each soil sample. The dry soil mass corresponding to each soil sample is divided by the corresponding volume of each container, and the result obtained is the soil density corresponding to each soil sample. The original ground is used as the reference plane, and the water level elevation is monitored using a water level meter, thereby obtaining the soil moisture, soil density and water level elevation corresponding to the first monitoring line at each first parameter collection point and the second monitoring line at each second parameter collection point.
[0032] It should be noted that the first monitoring line is located at the set advancement length from the last sub-dam, and the second monitoring line is located at the set distance upstream from the first monitoring line. The sub-dam refers to a part of the various stages of the accumulation dam, and is a part of the accumulation dam that is gradually established and raised. The last sub-dam refers to the sub-dam constructed in the last or final stage of the accumulation dam construction.
[0033] In a specific embodiment, the comprehensive evaluation coefficient of the designated tailings pond at the corresponding sedimentation beach is analyzed, and the specific analysis process is as follows: obtaining the standard monitoring point influencing parameters corresponding to the designated tailings pond from the database, the standard monitoring point influencing parameters including standard soil density, standard soil moisture and standard water level elevation;
[0034] By calculating the formula , and obtain the comprehensive evaluation coefficient of the specified tailings pond on the corresponding sedimentation beach ,in , , They are soil density, soil moisture, and water level elevation, respectively. , , They are expressed as standard soil density, standard soil moisture, and standard water level elevation, respectively. , , They are the weight factor corresponding to the set soil density, the weight factor corresponding to the soil moisture, and the weight factor corresponding to the water level elevation;
[0035] The soil moisture, soil density and water level elevation corresponding to the first monitoring line at each first parameter collection point and the second monitoring line at each second parameter collection point are substituted into the calculation formula corresponding to the comprehensive assessment coefficient of the designated tailings pond at the corresponding sedimentation beach, thereby obtaining the comprehensive assessment coefficient corresponding to the first monitoring line at each first parameter collection point and the comprehensive assessment coefficient corresponding to the second monitoring line at each second parameter collection point.
[0036] It should be noted that , , The values of are all greater than and less than .
[0037] It should also be noted that the weight factors corresponding to each historical soil density, each historical soil moisture, and each historical water level elevation are obtained from the database, and the medians of the weight factors corresponding to each historical soil density, each historical soil moisture, and each historical water level elevation are selected respectively. The results are the weight factors corresponding to the set soil density, soil moisture, and water level elevation.
[0038] In a specific embodiment, the specific position corresponding to each monitoring point is analyzed, and the specific analysis process is as follows: the comprehensive evaluation coefficients corresponding to the first monitoring line at each first parameter collection point are sorted in order from large to small, and the first parameter collection point corresponding to the first-ranked comprehensive evaluation coefficient is selected as the first monitoring point, and the comprehensive evaluation coefficients corresponding to the second monitoring line at each second parameter collection point are sorted in order from large to small, and the second parameter collection point corresponding to the first-ranked comprehensive evaluation coefficient is selected as the second monitoring point, thereby completing the confirmation of the specific positions corresponding to the first monitoring point and the second monitoring point.
[0039] The dry beach data analysis module is used to analyze the dry beach data corresponding to each monitoring point according to the specific location corresponding to each monitoring point.
[0040] In a specific embodiment, the dry beach data corresponding to each monitoring point are analyzed, and the specific analysis process is as follows: the dry beach data includes the coordinates of the dry beach top and the coordinates of the reservoir water edge, which are respectively recorded as and , drilling work of set installation depth is performed at the first monitoring point and the second monitoring point respectively. After the drilling work is completed, each filter tube is installed in the first monitoring point and the second monitoring point respectively. The filter tubes are connected by threads, and tailings sand is refilled in each filter tube and the borehole. Distributed optical fiber pressure sensors are installed in the filter tubes, and a data collector is installed on the top of the filter tubes;
[0041] According to the set monitoring depths, the pore water pressure and total water and soil pressure corresponding to the first monitoring point and the second monitoring point at each monitoring depth are collected by the distributed optical fiber pressure sensor. When the difference between the pore water pressure and the total water and soil pressure corresponding to a certain monitoring depth is 0, the detection depth is recorded as the beach surface. According to the water level elevation corresponding to the first monitoring point and the second monitoring point, and the data collector installed on the top of the filter tube corresponding to the first monitoring point and the second monitoring point, the coordinates corresponding to the first monitoring point and the second monitoring point are obtained, which are recorded as and , set any point , and then through the straight line equation 1 and the straight line equation 2, the straight line equation 1 and the straight line equation 2 are respectively: and ,in is the slope ratio of the outer slope of the dam crest, is the tailings dam accumulation height, is the length of the sub-dam beach, and a water level gauge is installed in the overflow well of the designated tailings pond to obtain the displayed reservoir water level elevation of the designated tailings pond, which is recorded as By combining linear equation 1 and linear equation 2, the coordinates of the intersection point of linear equation 1 and linear equation 2 are the coordinates of the top of the dry beach. ,Will Substituting into the linear equation 1, we get the coordinates of the reservoir water edge line .
[0042] It should be noted that the equation of the straight line are the coordinates of any point on the line equation 1.
[0043] In the dry beach length analysis process of the embodiment of the present invention, by analyzing the dry beach data of each monitoring point, it is beneficial to accurately calculate the dry beach length of the tailings pond. The accurate dry beach length is of great significance for assessing the risks of the tailings pond and formulating emergency measures, ensuring that the measurement results of the dry beach length have high accuracy, thereby improving the ability to judge the status of the tailings pond.
[0044] The dry beach length analysis module is used to analyze the dry beach data corresponding to the monitoring point and obtain the dry beach length corresponding to the specified tailings pond.
[0045] In a specific embodiment, the analysis obtains the dry beach length corresponding to the specified tailings pond, and the specific analysis process is as follows: according to the coordinates of the top of the dry beach and the coordinates of the water edge of the pond, the distance calculation formula is used: , get the dry beach length corresponding to the specified tailings pond .
[0046] The tailings pond risk analysis module is used to calculate the comprehensive safety assessment index corresponding to the designated tailings pond based on the dry beach length corresponding to the designated tailings pond, as well as the downstream slope ratio and infiltration line height of the accumulation dam corresponding to the designated tailings pond, and then analyze whether the comprehensive safety of the designated tailings pond meets the requirements.
[0047] In a specific embodiment, the downstream slope ratio and infiltration line height of the dam corresponding to the specified tailings pond are obtained, and the specific acquisition process is as follows: the horizontal slope length and the vertical height from the dam base to the slope top corresponding to the specified tailings pond are measured by a total station, and the measured vertical height from the dam base to the slope top is divided by the horizontal slope length. The result obtained is the downstream slope ratio of the dam corresponding to the specified tailings pond, and each infiltration line monitoring point is set in the flat beach area of the specified tailings pond. The infiltration line corresponding to each infiltration line monitoring point is obtained by monitoring with a water level meter, and the infiltration line corresponding to each infiltration line monitoring point is calculated by the mean, and the result obtained is the infiltration line height of the dam corresponding to the specified tailings pond.
[0048] It should be noted that the increase in the height of the infiltration line means that the water or liquid in the designated tailings pond penetrates into the tailings accumulation body to a higher height, thereby reducing the strength of the tailings, increasing the fluidity of the tailings, and affecting the stability of the dam body. The downstream slope ratio of the accumulation dam directly affects the stability of the dam body. The smaller the slope ratio, that is, the gentler the slope, the less likely it is to slip the tailings accumulation body and improve the stability of the dam body. On the contrary, the larger the slope ratio and the steeper the slope, the greater the risk of tailings landslide.
[0049] In a specific embodiment, the calculation obtains the comprehensive safety assessment index corresponding to the specified tailings pond, and the specific calculation process is as follows: obtaining the safe flat beach length, the safe downstream slope ratio of the dam and the safe infiltration line height corresponding to the specified tailings pond from the database;
[0050] By calculating the formula , get the comprehensive safety assessment index corresponding to the specified tailings pond , , It is expressed as the downstream slope ratio and the height of the infiltration line of the dam corresponding to the specified tailings pond. , , They are respectively represented by the safe flat beach length, the safe downstream slope ratio of the dam, and the safe infiltration line height. , , They are the weight factor corresponding to the set dry beach length, the weight factor corresponding to the downstream slope ratio of the accumulation dam, and the weight factor corresponding to the height of the infiltration line.
[0051] It should be noted that , , The values of are all greater than and less than .
[0052] It should also be noted that the number of times the comprehensive safety does not meet the requirements due to the flat beach length, the number of times the comprehensive safety does not meet the requirements due to the downstream slope ratio of the accumulation dam, and the number of times the comprehensive safety does not meet the requirements due to the height of the infiltration line are obtained from the database when the comprehensive safety of the specified tailings pond does not meet the requirements, and the total number of times is accumulated, and the number of times the comprehensive safety does not meet the requirements due to the flat beach length, the number of times the comprehensive safety does not meet the requirements due to the downstream slope ratio of the accumulation dam, and the number of times the comprehensive safety does not meet the requirements due to the height of the infiltration line are divided by the total number of times respectively, and the result obtained is the weight factor corresponding to the set dry beach length, the weight factor corresponding to the downstream slope ratio of the accumulation dam, and the weight factor corresponding to the height of the infiltration line.
[0053] In a specific embodiment, the analysis determines whether the comprehensive safety of the designated tailings pond meets the requirements. The specific analysis process is as follows: the comprehensive safety assessment index corresponding to the designated tailings pond is compared with the set comprehensive safety assessment index. If the comprehensive safety assessment index corresponding to the designated tailings pond belongs to the set comprehensive safety assessment index interval, then it is determined that the comprehensive safety of the designated tailings pond meets the requirements. If the comprehensive safety assessment index corresponding to the designated tailings pond does not belong to the set comprehensive safety assessment index interval, then it is determined that the comprehensive safety of the designated tailings pond does not meet the requirements.
[0054] In the process of tailings pond risk analysis, the embodiment of the present invention calculates the comprehensive safety assessment index by obtaining the downstream slope ratio and the infiltration line height, which is conducive to comprehensively evaluating the safety of the tailings pond, and then timely identifying potential risks and taking preventive and treatment measures.
[0055] The early warning terminal is used to issue early warning prompts when the comprehensive safety of the designated tailings pond does not meet the requirements.
[0056] The database is used to store the influencing parameters of the standard monitoring points corresponding to the specified tailings pond, which include standard soil density, standard soil moisture and standard water level elevation. It also stores the safe flat beach length, safe downstream slope ratio of the dam and safe infiltration line height corresponding to the specified tailings pond, and also stores the weight factors corresponding to each historical soil density, each historical soil moisture and each historical water level. When the comprehensive safety of the specified tailings pond does not meet the requirements, the number of times the comprehensive safety does not meet the requirements due to the corresponding flat beach length, the number of times the comprehensive safety does not meet the requirements due to the downstream slope ratio of the dam, and the number of times the comprehensive safety does not meet the requirements due to the infiltration line height.
[0057] See also Figure 2A monitoring method for the dry beach length of a tailings pond is shown, comprising the following steps: Step 1, monitoring point analysis: setting various parameter collection points, collecting monitoring point influencing parameters of the corresponding sedimentation beach of the specified tailings pond, the monitoring point influencing parameters including soil density, soil moisture and water level elevation, and then analyzing the comprehensive evaluation coefficient of the specified tailings pond in the corresponding sedimentation beach, thereby analyzing the specific location corresponding to each monitoring point.
[0058] Step 2: Dry beach data analysis: According to the specific location of each monitoring point, the dry beach data corresponding to each monitoring point is analyzed.
[0059] Step 3: Dry beach length analysis: According to the dry beach data corresponding to the monitoring point, the dry beach length corresponding to the designated tailings pond is analyzed and obtained.
[0060] Step 4. Tailings pond risk analysis: Based on the dry beach length corresponding to the designated tailings pond, as well as the downstream slope ratio and infiltration line height of the pile dam corresponding to the designated tailings pond, the comprehensive safety assessment index corresponding to the designated tailings pond is calculated, and then it is analyzed whether the comprehensive safety of the designated tailings pond meets the requirements.
[0061] Step 5. Early warning: When the comprehensive safety of the designated tailings pond does not meet the requirements, an early warning will be issued.
[0062] The present invention provides a monitoring system and method for the dry beach length of a tailings pond. In the process of collecting soil density and moisture, detailed soil sample processing, including soil moisture meter monitoring, weighing after drying and density calculation steps, is conducive to accurately understanding the soil characteristics of the tailings pond sedimentation beach, and provides a reliable data basis for further dry beach length and stability analysis. In the process of calculating the comprehensive evaluation coefficient, the specific location of the monitoring point is determined by substituting the soil moisture, density and water level elevation of the monitoring point into the calculation formula, so that the analysis of the dry beach length is more accurate.
[0063] The above contents are merely examples and explanations of the concept of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the concept of the invention or exceed the scope defined in this specification, they shall all fall within the protection scope of the present invention.
Claims
1. A monitoring system for the dry beach length of a tailings pond, characterized in that: include: The monitoring point analysis module is used to set various parameter collection points and collect the monitoring point influencing parameters of the designated tailings pond corresponding to the sedimentation beach. The monitoring point influencing parameters include soil density, soil moisture and water level elevation, and then analyze the comprehensive evaluation coefficient of the designated tailings pond in the corresponding sedimentation beach, thereby analyzing the specific location corresponding to each monitoring point; The analysis specifies the comprehensive assessment coefficient of the tailings pond at the corresponding sedimentation beach. The specific analysis process is as follows: Obtain the standard monitoring point influencing parameters corresponding to the specified tailings pond from the database, the standard monitoring point influencing parameters including standard soil density, standard soil moisture and standard water level elevation; By calculating the formula , and obtain the comprehensive evaluation coefficient of the specified tailings pond on the corresponding sedimentation beach ,in , , They are soil density, soil moisture, and water level elevation, respectively. , , They are expressed as standard soil density, standard soil moisture, and standard water level elevation, respectively. , , They are the weight factor corresponding to the set soil density, the weight factor corresponding to the soil moisture, and the weight factor corresponding to the water level elevation; Substitute the soil moisture, soil density and water level elevation corresponding to the first monitoring line at each first parameter collection point and the second monitoring line at each second parameter collection point into the calculation formula corresponding to the comprehensive assessment coefficient of the designated tailings pond at the corresponding sedimentation beach, and then obtain the comprehensive assessment coefficient corresponding to the first monitoring line at each first parameter collection point and the comprehensive assessment coefficient corresponding to the second monitoring line at each second parameter collection point; The specific location corresponding to each monitoring point is analyzed, and the specific analysis process is as follows: The comprehensive evaluation coefficients corresponding to the first parameter collection points of the first monitoring line are sorted in order from large to small, and the first parameter collection point corresponding to the first-ranked comprehensive evaluation coefficient is selected as the first monitoring point. The comprehensive evaluation coefficients corresponding to the second parameter collection points of the second monitoring line are sorted in order from large to small, and the second parameter collection point corresponding to the first-ranked comprehensive evaluation coefficient is selected as the second monitoring point, thereby completing the confirmation of the specific positions corresponding to the first monitoring point and the second monitoring point; The dry beach data analysis module is used to analyze the dry beach data corresponding to each monitoring point according to the specific location of each monitoring point; The specific analysis process of analyzing the dry beach data corresponding to each monitoring point is as follows: The dry beach data include the dry beach top coordinates and the reservoir water edge coordinates, which are recorded as and , drilling work of set installation depth is performed at the first monitoring point and the second monitoring point respectively. After the drilling work is completed, each filter tube is installed in the first monitoring point and the second monitoring point respectively. The filter tubes are connected by threads, and tailings sand is refilled in each filter tube and the borehole. Distributed optical fiber pressure sensors are installed in the filter tubes, and a data collector is installed on the top of the filter tubes; According to the set monitoring depths, the pore water pressure and total water and soil pressure corresponding to the first monitoring point and the second monitoring point at each monitoring depth are collected by the distributed optical fiber pressure sensor. When the difference between the pore water pressure and the total water and soil pressure corresponding to a certain monitoring depth is 0, the monitoring depth is recorded as the beach surface. According to the water level elevation corresponding to the first monitoring point and the second monitoring point, and the data collector installed on the top of the filter tube corresponding to the first monitoring point and the second monitoring point, the coordinates corresponding to the first monitoring point and the second monitoring point are obtained, which are recorded as and , set any point , and then through the straight line equation 1 and the straight line equation 2, the straight line equation 1 and the straight line equation 2 are respectively: and ,in is the slope ratio of the outer slope of the dam crest, is the tailings dam accumulation height, is the length of the sub-dam beach, and a water level gauge is installed in the overflow well of the designated tailings pond to obtain the displayed reservoir water level elevation of the designated tailings pond, which is recorded as By combining linear equation 1 and linear equation 2, the coordinates of the intersection point of linear equation 1 and linear equation 2 are the coordinates of the top of the dry beach. ,Will Substituting into the linear equation 1, we get the coordinates of the reservoir water edge line ; The dry beach length analysis module is used to analyze the dry beach data corresponding to the monitoring point and obtain the dry beach length corresponding to the specified tailings pond; The analysis obtains the dry beach length corresponding to the specified tailings pond. The specific analysis process is as follows: According to the coordinates of the top of the dry beach and the water edge of the reservoir, the distance is calculated using the formula: , get the dry beach length corresponding to the specified tailings pond ; The tailings pond risk analysis module is used to calculate the comprehensive safety assessment index corresponding to the designated tailings pond based on the dry beach length corresponding to the designated tailings pond, as well as the downstream slope ratio and infiltration line height of the pile dam corresponding to the designated tailings pond, and then analyze whether the comprehensive safety of the designated tailings pond meets the requirements; The specific acquisition process of obtaining the downstream slope ratio and the height of the infiltration line of the pile dam corresponding to the specified tailings pond is as follows: The horizontal slope length and the vertical height from the dam base to the top of the slope corresponding to the designated tailings pond are measured by a total station. The vertical height from the dam base to the top of the slope measured is divided by the horizontal slope length. The result obtained is the downstream slope ratio of the pile dam corresponding to the designated tailings pond. Each infiltration line monitoring point is set in the flat beach area of the designated tailings pond. The infiltration line corresponding to each infiltration line monitoring point is obtained by monitoring with a water level meter. The infiltration line corresponding to each infiltration line monitoring point is calculated by the mean value. The result obtained is the infiltration line height of the pile dam corresponding to the designated tailings pond. The calculation obtains the comprehensive safety assessment index corresponding to the specified tailings pond, and the specific calculation process is as follows: Obtain the safe flat beach length, safe downstream slope ratio and safe infiltration line height corresponding to the specified tailings pond from the database; By calculating the formula , get the comprehensive safety assessment index corresponding to the specified tailings pond , , It is expressed as the downstream slope ratio and the height of the infiltration line of the dam corresponding to the specified tailings pond. , , They are respectively represented by the safe flat beach length, the safe downstream slope ratio of the dam, and the safe infiltration line height. , , They are the weight factor corresponding to the set dry beach length, the weight factor corresponding to the downstream slope ratio of the accumulation dam, and the weight factor corresponding to the height of the infiltration line; The analysis specifies whether the comprehensive safety of the tailings pond meets the requirements. The specific analysis process is as follows: Compare the comprehensive safety assessment index corresponding to the designated tailings pond with the set comprehensive safety assessment index. If the comprehensive safety assessment index corresponding to the designated tailings pond is within the set comprehensive safety assessment index interval, it is determined that the comprehensive safety of the designated tailings pond meets the requirements. If the comprehensive safety assessment index corresponding to the designated tailings pond does not fall within the set comprehensive safety assessment index interval, it is determined that the comprehensive safety of the designated tailings pond does not meet the requirements. The early warning terminal is used to issue early warning prompts when the comprehensive safety of the designated tailings pond does not meet the requirements.
2. A monitoring system for the dry beach length of a tailings pond according to claim 1, characterized in that: The specific collection process of the monitoring point influencing parameters of the designated tailings pond corresponding to the sedimentation beach is as follows: Each monitoring point includes a first monitoring point and a second monitoring point, a first monitoring line and a second monitoring line are set on the sedimentation beach of the designated tailings pond, and each parameter collection point includes each first parameter collection point and each second parameter collection point; According to the set monitoring depth, soil sampling is carried out at the set monitoring depth to obtain each soil sample, and then the soil moisture corresponding to each soil sample is monitored using a soil moisture meter, and each soil sample is placed in a container of corresponding known volume to ensure that each soil sample fills each container and there is no gap. The containers filled with each soil sample are placed in an oven for drying, and weighed again after drying to obtain the dry soil mass corresponding to each soil sample. The dry soil mass corresponding to each soil sample is divided by the corresponding volume of each container, and the result obtained is the soil density corresponding to each soil sample. The original ground is used as the reference plane, and the water level elevation is monitored using a water level meter, thereby obtaining the soil moisture, soil density and water level elevation corresponding to the first monitoring line at each first parameter collection point and the second monitoring line at each second parameter collection point.
3. A method for monitoring the dry beach length of a tailings pond using the monitoring system for the dry beach length of a tailings pond according to any one of claims 1 to 2, characterized in that: The steps include: Step 1: Monitoring point analysis: Set up various parameter collection points to collect the monitoring point influencing parameters of the designated tailings pond corresponding to the sedimentation beach. The monitoring point influencing parameters include soil density, soil moisture and water level elevation, and then analyze the comprehensive assessment coefficient of the designated tailings pond in the corresponding sedimentation beach, thereby analyzing the specific location corresponding to each monitoring point; Step 2: Dry beach data analysis: According to the specific location of each monitoring point, the dry beach data corresponding to each monitoring point is analyzed; Step 3: Dry beach length analysis: According to the dry beach data corresponding to the monitoring point, the dry beach length corresponding to the specified tailings pond is analyzed; Step 4. Tailings pond risk analysis: Based on the dry beach length corresponding to the designated tailings pond, as well as the downstream slope ratio and infiltration line height of the pile dam corresponding to the designated tailings pond, the comprehensive safety assessment index corresponding to the designated tailings pond is calculated, and then the comprehensive safety of the designated tailings pond is analyzed to see whether it meets the requirements; Step 5. Early warning: When the comprehensive safety of the designated tailings pond does not meet the requirements, an early warning will be issued.