A landslide section tunnel reinforcement structure with integrated blocking and supporting functions and its construction method
By arranging soil blocking units and rock mass intersection bearing bodies in the tunnels in the landslide area, an integrated support structure is formed, which solves the problem of the impact of tunnel construction on the landslide body and achieves the effect of reducing landslide risks and construction costs.
Patent Information
- Application Number
- CN202411132547.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2044-08-19
AI Technical Summary
The construction of tunnels in landslide areas has a great impact on the landslide body, which can easily cause creep and instability of the landslide body, leading to tunnel diseases. The existing reinforcement measures are complex and costly.
The tunnel reinforcement structure in the landslide section is adopted with integrated blocking and support. By setting up soil blocking units and rock mass intersecting bearing bodies, an integrated supporting structure is formed to disperse the stress on the tunnel. It also regulates the climate through surface water diversion and water-absorbing sponges, reducing Landslide risk.
It can effectively reduce surface water, block landslides, disperse tunnel stress, reduce the impact of landslides on tunnels, reduce landslide disaster risks, and reduce construction costs.
Smart Images

Figure CN118669147B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tunnel reinforcement, and in particular to a landslide section tunnel reinforcement structure with integrated blocking and support and a construction method thereof. Background Art
[0002] In recent years, with the continuous development of my country's transportation construction, there are more and more highway tunnels. Due to the limitations of terrain conditions, they inevitably have to pass through special strata such as landslides and soft fracture zones.
[0003] Among them, when constructing roads or railways in landslide areas, due to factors such as speed, time saving and high-standard design requirements, and in order to avoid the disturbance of the slope caused by large-scale excavation when building deep road cuttings, tunnel construction has to be adopted. The construction of tunnels in landslide areas has a great impact on the landslide body itself, which is specifically reflected in the following aspects: first, during the excavation process, it is very easy to cause the stress field and displacement field in the landslide body to adjust, and the joints and cracks in the rock body gradually expand, thereby causing long-term creep of the landslide body; secondly, when the original slope body is an old landslide body, the excavation of the tunnel will weaken the supporting force of the landslide body, and at the same time change the stress field and seepage field of the landslide body, which is very likely to cause the old landslide body to revive. For tunnels in active landslide areas, due to the influence of factors such as rainfall and the rise and fall of groundwater levels, the deadweight and sliding force of the landslide body increase, and the anti-sliding force decreases. The instability of the landslide body will directly lead to different degrees of tunnel damage, such as lining cracking, deformation, spalling, collapse, overall movement, etc., which will seriously affect the driving safety and normal operation of the tunnel.
[0004] At present, the commonly used reinforcement measures for tunnels in landslide areas include weight reduction and counter pressure, retaining measures, and tunnel surrounding rock pre-reinforcement, all of which have the characteristics of complex procedures and high construction costs. Summary of the invention
[0005] In order to solve the above problems, the present invention provides a tunnel reinforcement structure for landslide sections with integrated blocking and support and a construction method thereof. By setting up a soil blocking unit, surface water can be reduced and the occurrence of landslides can be blocked. At the same time, a rock intersection bearing body is set up to form an integrated support structure on the outer circumference side of the tunnel, thereby dispersing the force on the tunnel and avoiding the direct impact of the landslide on the tunnel.
[0006] To achieve the above-mentioned objectives, the present invention provides a tunnel reinforcement structure for landslide sections with integrated blocking and support, comprising a rock-interlocking pressure-bearing body arranged between the tunnel and the landslide body and a soil blocking unit arranged on the landslide body, wherein the rock-interlocking pressure-bearing body is an integrated pressure-bearing structure composed of a reinforcement agent injected into the rock through radial injection holes and the rock interlocking.
[0007] Preferably, the soil blocking unit comprises a surface blocking grid laid on the surface of the landslide body and a plurality of blocking pipes arranged between the surface blocking grid and the rock mass intersecting pressure bearing body, and the blocking pipes are perpendicular to the surface of the rock mass intersecting pressure bearing body;
[0008] Intersection points of the surface interception grids are all provided with interception tubes.
[0009] Preferably, the surface blocking grid is a prefabricated concrete structure, the bottom end of the surface blocking grid extends into the landslide body, and the top end of the surface blocking grid extends out of the landslide body to open a surface water diversion trough.
[0010] Preferably, the surface blocking grid includes a plurality of vertical flow collecting columns parallel to the sliding direction of the landslide body and a plurality of transverse flow guiding columns perpendicular to the sliding direction of the landslide body, the transverse flow guiding columns are arranged in a wave shape, and the wave low points of the transverse flow guiding columns are connected to the vertical flow collecting columns;
[0011] A surface water diversion trough is provided on the side of the transverse diversion column facing the top of the landslide body. The surface water diversion trough is connected with the confluence trough provided on the vertical confluence column, and the bottom end of the confluence trough leads to the foot of the mountain.
[0012] Preferably, a plug hole is provided in the middle of the transverse guide column, the top end of the blocking pipe is inserted into the plug hole, and the bottom end of the blocking pipe extends into the rock junction bearing body by a set distance, and the set distance is 5m-8m;
[0013] A telescopic blocking component is arranged inside the blocking pipe, and the top of the blocking pipe and the insertion hole are sealed with concrete.
[0014] Preferably, the telescopic blocking assembly rotates a rotating rod disposed inside the blocking tube, a plurality of driving gears fixed to the axial outer circumferential side of the rotating rod, and a telescopic rack meshing with two symmetrical sides of the driving gear, and the telescopic rack is also radially slidably connected to the blocking tube;
[0015] A telescopic hole connected with the telescopic rack is provided on the blocking pipe.
[0016] Preferably, the telescopic rack is a hollow structure, a water-absorbing sponge strip is fixed inside the telescopic rack, and a water-absorbing hole connected to the water-absorbing sponge strip is opened on the telescopic rack.
[0017] Preferably, an intercepting ditch is also opened at the top of the landslide body, the intercepting ditch is perpendicular to the sliding direction of the landslide body, and the intercepting ditch is connected to the top of the drainage ditch located on both sides of the tunnel, and the bottom of the drainage ditch leads to the foot of the mountain.
[0018] Preferably, the tunnel includes an inner wall of the tunnel and anchor bolts fixed between the inner wall of the tunnel and a pressure-bearing body at the junction of the rock mass, and concrete is poured between the anchor bolts and the inner wall of the tunnel.
[0019] The construction method of the tunnel reinforcement structure in a landslide section with integrated blocking and supporting functions comprises the following steps:
[0020] S1. The inner wall of the tunnel is hoisted to a position that fits the inner circumference of the tunnel, and then the inner wall of the tunnel is fixed to the rock using anchor bolts, and then concrete is poured at the connection between the anchor bolts and the inner wall of the tunnel;
[0021] S2, radially drill multiple injection holes along the circumferential direction of the inner wall of the tunnel, and then inject reinforcement into the injection holes. After standing for a set time, the reinforcement and the rock are intertwined to form a rock mass intertwined pressure-bearing body;
[0022] S3, digging intercepting ditches and drainage ditches, embedding surface blocking grids on the surface of the landslide body, and drilling holes aligned with the insertion positions at the intersections of the horizontal diversion columns and the vertical converging columns until the drill enters the rock junction bearing body to a set distance, and withdrawing the drill rod;
[0023] S4, inserting a blocking pipe into the borehole described in step S3, and making the line between the two telescopic holes located on the same horizontal plane of the blocking pipe perpendicular to the sliding direction of the landslide body;
[0024] S5, rotating the rotating rod to drive the driving gear to rotate, thereby driving the telescopic rack to extend through the telescopic hole to the blocking pipe and insert into the soil, and the telescopic rack is perpendicular to the landslide direction of the landslide body;
[0025] S6. Pour concrete to seal the top of the barrier pipe.
[0026] The present invention has the following beneficial effects:
[0027] 1. By setting up soil blocking units, surface water can be reduced and landslides can be prevented. At the same time, by setting up rock mass interlocking bearing bodies, an integrated support structure can be formed on the outer circumference of the tunnel to disperse the force on the tunnel and avoid the direct impact of landslides on the tunnel;
[0028] 2. By opening a surface water diversion trough on the horizontal diversion column of the soil barrier unit, and then diverting the water to the foot of the mountain through the confluence trough opened on the vertical confluence column, the surface runoff is reduced, thereby reducing the risk of landslide disasters;
[0029] 3. By setting a water-absorbing sponge in the telescopic rack and cooperating with the water-absorbing holes, surface water can be absorbed and released in the dry season, which can further reduce the risk of landslide disasters while regulating the climate.
[0030] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 A longitudinal cross-sectional view of a landslide tunnel reinforcement structure with integrated blocking and supporting functions according to the present invention;
[0032] Figure 2It is a transverse cross-sectional view of a landslide section tunnel reinforcement structure with integrated blocking and supporting function according to the present invention;
[0033] Figure 3 A surface blocking grid layout diagram of a landslide tunnel reinforcement structure with integrated blocking and supporting functions according to the present invention;
[0034] Figure 4 It is an axial cross-sectional view of a telescopic blocking component of a tunnel reinforcement structure for landslide sections with integrated blocking and support according to the present invention.
[0035] Among them: 1. landslide body; 2. surface blocking grid; 21. vertical confluence column; 211. confluence trough; 22. horizontal diversion column; 221. surface water diversion trough; 222. socket; 3. blocking pipe; 31. telescopic hole; 4. intercepting ditch; 5. rock mass intersection pressure body; 6. injection hole; 7. tunnel; 71. tunnel inner wall; 72. anchor bolt; 8. telescopic blocking assembly; 81. rotating rod; 82. driving gear; 83. telescopic rack. DETAILED DESCRIPTION
[0036] In order to make the purpose, technical scheme and advantages disclosed in the embodiments of the present invention clearer, the embodiments of the present invention are further described in detail in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the embodiments of the present invention and are not intended to limit the embodiments of the present invention. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application. Examples of the embodiments are shown in the accompanying drawings, where the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions.
[0037] It should be noted that the terms "include", "have" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or server comprising a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units not explicitly listed or inherent to these processes, methods, products or devices.
[0038] Like reference numerals and letters denote similar items in the following drawings, and thus, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0039] In the description of the present invention, it should be noted that the terms "upper", "lower", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, or are directions or positional relationships in which the product of the invention is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.
[0040] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "setting", "installation" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0041] like Figure 1-Figure 4 As shown, a tunnel reinforcement structure for landslide sections with integrated blocking and support includes a rock-interlocking pressure-bearing body 5 arranged between the tunnel 7 and the landslide body 1 and a soil blocking unit arranged on the landslide body 1, wherein the rock-interlocking pressure-bearing body 5 is an integrated pressure-bearing structure composed of a reinforcement agent injected into the rock through radial injection holes 6 and the rock interlocking.
[0042] Specifically, the soil barrier unit includes a surface barrier grid 2 laid on the surface of the landslide body 1 and a plurality of barrier pipes 3 arranged between the surface barrier grid 2 and the rock mass intersection pressure bearing body 5, and the barrier pipes 3 are perpendicular to the surface of the rock mass intersection pressure bearing body 5; barrier pipes 3 are arranged at the intersection points of the surface barrier grids 2.
[0043] The surface blocking grid 2 is a prefabricated concrete structure. The bottom end of the surface blocking grid 2 extends into the landslide body 1, and the top end of the surface blocking grid 2 extends out of the landslide body 1 to open a surface water diversion groove 221.
[0044] The surface blocking grid 2 includes a plurality of vertical flow columns 21 parallel to the sliding direction of the landslide body 1 and a plurality of transverse flow columns 22 perpendicular to the sliding direction of the landslide body 1. The transverse flow columns 22 are arranged in a wave shape, and the wave low point of the transverse flow columns 22 is connected to the vertical flow columns 21; a surface water flow channel 221 is provided on the side of the transverse flow columns 22 facing the top of the landslide body 1, and the surface water flow channel 221 is connected to the flow channel 211 provided on the vertical flow columns 21, and the bottom end of the flow channel 211 leads to the foot of the mountain. The wave structure in this embodiment is a bending structure with a high middle and low sides. The transverse flow columns 22 are arranged in a wave shape, and the rainwater collected in this grid can flow along the transverse flow columns 22 to the flow channels 211 on the vertical flow columns 21 on both sides, thereby discharging the surface water.
[0045] A plug hole 222 is provided in the middle of the transverse guide column 22, and the top of the blocking pipe 3 is inserted into the plug hole 222. The bottom of the blocking pipe 3 extends to the inside of the rock junction bearing body by a set distance, and the set distance is 5m-8m. A telescopic blocking assembly 8 is provided inside the blocking pipe 3, and the top of the blocking pipe 3 and the plug hole 222 are sealed by concrete. The telescopic blocking assembly 8 is rotatably provided with a rotating rod 81 inside the blocking pipe 3, a plurality of driving gears 82 fixed to the axial outer circumference of the rotating rod 81, and a telescopic rack 83 meshed with the symmetrical sides of the driving gear 82, and the telescopic rack 83 is also radially slidably connected with the blocking pipe 3; a telescopic hole 31 is provided on the blocking pipe 3 to be connected with the telescopic rack 83. In this embodiment, the telescopic rack 83 passing through the telescopic hole 31 is perpendicular to the direction of the landslide of the landslide body 1, thereby playing a role in blocking the soil from sliding down, thereby playing a role in reducing the possibility of landslide disasters.
[0046] The telescopic rack 83 is a hollow structure, and a water-absorbing sponge strip is fixed inside the telescopic rack 83. A water-absorbing hole connected to the water-absorbing sponge strip is opened on the telescopic rack 83. The moisture in the soil penetrates into the water-absorbing sponge strip along the water-absorbing hole, reducing the possibility of forming surface runoff, thereby reducing the possibility of landslide disasters.
[0047] A diversion ditch 4 is also provided at the top of the landslide body 1. The diversion ditch 4 is perpendicular to the sliding direction of the landslide body 1 and is connected to the tops of the drainage ditches on both sides of the tunnel 7. The bottom of the drainage ditch leads to the foot of the mountain. A large amount of rainwater can be guided to the foot of the mountain through the diversion ditch 4 and the drainage ditch, thereby avoiding the occurrence of landslide disasters caused by a large amount of rainwater impacting the landslide body 1.
[0048] The tunnel 7 includes a tunnel inner wall 71 and anchor bolts 72 fixed between the tunnel inner wall 71 and the rock mass bearing body 5 , and concrete is poured between the anchor bolts 72 and the tunnel inner wall 71 .
[0049] The method for constructing a landslide tunnel reinforcement structure comprises the following steps:
[0050] S1, hoisting the tunnel inner wall 71 to a position that fits the inner circumference of the tunnel 7, then fixing the tunnel inner wall 71 to the rock with anchor bolts 72, and then pouring concrete at the connection between the anchor bolts 72 and the tunnel inner wall 71;
[0051] S2, radially drill a plurality of injection holes 6 along the circumferential direction of the tunnel inner wall 71, and then inject a reinforcing agent into the injection holes 6. After standing for a set time, the reinforcing agent and the rock are intertwined to form a rock mass intertwined pressure-bearing body 5;
[0052] S3, digging intercepting ditches 4 and drainage ditches, embedding surface blocking grids 2 on the surface of the landslide body 1, and drilling holes aligned with the insertion holes 222 at the intersection of the horizontal guide column 22 and the vertical converging column 21 until drilling into the rock junction bearing body to a set distance, and withdrawing the drill rod;
[0053] S4, inserting the blocking tube 3 into the borehole described in step S3, and making the connecting line between the two telescopic holes 31 located on the same horizontal plane of the blocking tube 3 perpendicular to the sliding direction of the landslide body 1;
[0054] S5, rotating the rotating rod 81, driving the driving gear 82 to rotate, thereby driving the telescopic rack 83 to extend through the telescopic hole to the blocking pipe 3 and insert into the soil, and the telescopic rack 83 is perpendicular to the landslide direction of the landslide body 1;
[0055] S6. Pour concrete to seal the top of the barrier pipe 3.
[0056] Therefore, the present invention adopts the above-mentioned integrated blocking and supporting landslide section tunnel reinforcement structure and its construction method. By setting up a soil blocking unit, surface water can be reduced and the occurrence of landslides can be blocked. At the same time, a rock intersection bearing body is set to form an integrated support structure on the outer circumference side of the tunnel, disperse the force on the tunnel, and avoid the direct impact of the landslide on the tunnel.
[0057] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.
Claims
1. A tunnel reinforcement structure for landslide sections with integrated blocking and support, characterized in that: It includes a rock mass interlocking pressure-bearing body arranged between the tunnel and the landslide body and a soil blocking unit arranged on the landslide body, wherein the rock mass interlocking pressure-bearing body is an integrated pressure-bearing structure composed of a reinforcement agent injected into the rock through a radial injection hole and the rock interlocking; The soil blocking unit includes a surface blocking grid laid on the surface of the landslide body and a plurality of blocking pipes arranged between the surface blocking grid and the rock mass intersecting pressure bearing body, and the blocking pipes are perpendicular to the surface of the rock mass intersecting pressure bearing body; The intersections of the surface blocking grids are all provided with blocking tubes; The surface blocking grid is a prefabricated concrete structure. The bottom of the surface blocking grid extends into the landslide body, and the top of the surface blocking grid extends out of the landslide body to open a surface water diversion channel. The surface blocking grid includes a plurality of vertical flow collecting columns parallel to the sliding direction of the landslide body and a plurality of transverse flow guiding columns perpendicular to the sliding direction of the landslide body. The transverse flow guiding columns are arranged in a wave shape, and the wave low points of the transverse flow guiding columns are connected to the vertical flow collecting columns. A surface water diversion trough is provided on the side of the transverse diversion column facing the top of the landslide body. The surface water diversion trough is connected to the confluence trough provided on the vertical confluence column. The bottom of the confluence trough leads to the foot of the mountain. The water is diverted to the foot of the mountain through the confluence trough provided on the vertical confluence column, thereby reducing surface runoff and thus reducing the risk of landslide disasters. A plug hole is provided in the middle of the transverse guide column, the top end of the barrier pipe is inserted into the plug hole, and the bottom end of the barrier pipe extends into the rock junction bearing body by a set distance, which is 5m-8m; A telescopic blocking component is arranged inside the blocking pipe, and the top of the blocking pipe and the insertion hole are sealed with concrete; The telescopic blocking assembly rotates a rotating rod disposed inside the blocking tube, a plurality of driving gears fixed to the axial outer circumference of the rotating rod, and a telescopic rack meshing with the symmetrical sides of the driving gear, and the telescopic rack is also radially slidably connected to the blocking tube; A telescopic hole connected with the telescopic rack is provided on the blocking pipe.
2. The landslide section tunnel reinforcement structure with integrated blocking and supporting function according to claim 1, characterized in that: The telescopic rack is a hollow structure, a water-absorbing sponge strip is fixed inside the telescopic rack, and a water-absorbing hole connected with the water-absorbing sponge strip is opened on the telescopic rack.
3. The landslide section tunnel reinforcement structure with integrated blocking and supporting function according to claim 2 is characterized by: An interception ditch is also opened at the top of the landslide body. The interception ditch is perpendicular to the sliding direction of the landslide body, and the interception ditch is connected to the top of the drainage ditch located on both sides of the tunnel. The bottom of the drainage ditch leads to the foot of the mountain.
4. The landslide section tunnel reinforcement structure with integrated blocking and supporting function according to claim 3 is characterized by: The tunnel includes an inner wall of the tunnel and anchor bolts fixed between the inner wall of the tunnel and a bearing body at the junction of the rock mass, and concrete is poured between the anchor bolts and the inner wall of the tunnel.
5. The construction method of a tunnel reinforcement structure in a landslide section with integrated blocking and supporting function as claimed in claim 4, characterized in that: The following steps are involved: S1. The inner wall of the tunnel is hoisted to a position that fits the inner circumference of the tunnel, and then the inner wall of the tunnel is fixed to the rock using anchor bolts, and then concrete is poured at the connection between the anchor bolts and the inner wall of the tunnel; S2, radially drill multiple injection holes along the circumferential direction of the inner wall of the tunnel, and then inject reinforcement into the injection holes. After standing for a set time, the reinforcement and the rock are intertwined to form a rock mass intertwined pressure-bearing body; S3, digging intercepting ditches and drainage ditches, embedding surface blocking grids on the surface of the landslide body, and drilling holes aligned with the insertion positions at the intersections of the horizontal diversion columns and the vertical converging columns until the drill enters the rock junction bearing body to a set distance, and withdrawing the drill rod; S4, inserting a blocking pipe into the borehole described in step S3, and making the line between the two telescopic holes located on the same horizontal plane of the blocking pipe perpendicular to the sliding direction of the landslide body; S5, rotating the rotating rod to drive the driving gear to rotate, thereby driving the telescopic rack to extend through the telescopic hole to the blocking pipe and insert into the soil, and the telescopic rack is perpendicular to the landslide direction of the landslide body; S6. Pour concrete to seal the top of the barrier pipe.