A ground subsidence monitoring device and its installation and use method

By designing a ground settlement monitoring device, the soil layer settlement is monitored using settlement components and angle detection modules, which solves the problems of detector maintenance difficulties and magnetic field interference in the prior art, and achieves accurate and intuitive soil layer settlement monitoring.

CN118706076BActive Publication Date: 2024-11-013RD CONSTRUCTION (SHENZHEN) CO LTD OF CHINA CONSTRUCTION 5TH ENGINEERING BUREAU
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411187295.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-28
Publication Date
2024-11-01
Estimated Expiration
2044-08-28

AI Technical Summary

Technical Problem

In the existing ground settlement monitoring methods, the tensile detector is difficult to repair or replace, and the magnetic field interference of underground equipment affects the accuracy of the detection results, and the soil layer settlement results cannot be visually reflected.

Method used

A ground settlement monitoring device is designed, including positioning parts, settlement components, fixed brackets and angle detection modules. The connection components are driven to rotate through the settlement components, and the angle detection module is used to monitor the soil layer settlement amount in real time, and the angle detection module is set above the ground. Easy to maintain and avoid interference from underground equipment.

Benefits of technology

It realizes intuitive monitoring of soil layer settlement, with simple structure and convenient operation, and can replace the detector in time to ensure the accuracy and reliability of the detection results and avoid magnetic field interference.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118706076B_ABST
    Figure CN118706076B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of building construction, and discloses a ground settlement monitoring device and its installation and use method. The ground settlement monitoring device includes a positioning member, a settlement component, a fixed bracket, a connecting component and an angle detection module. The positioning member extends vertically and is inserted into the ground, and at least one settlement component is provided, which is movably provided on the positioning member along the vertical direction, and the settlement component is buried underground. The fixed bracket is arranged above the ground. At least one connecting component is provided, one end of which is rotatably connected to the fixed bracket, and the other end is matched with the settlement component. The angle detection module is arranged on the connecting component or the fixed bracket, and is located above the ground. By arranging the settlement component, the connecting component and the angle detection module, the settlement amount of the soil layer at a preset detection depth can be monitored. The angle detection module is arranged above the ground, which can be easily inspected and replaced to ensure the reliability of the detection result.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction, and in particular to a ground subsidence monitoring device and an installation and use method thereof. Background Art

[0002] During construction, ground settlement monitoring is required to obtain accurate ground conditions, help workers assess the impact of construction on the geological environment, and ensure the safety and quality of the project.

[0003] At present, the method for monitoring ground subsidence is to bury a positioning tube below the ground, and set a settlement magnetic ring outside the outer positioning tube. A tension detector is set on the positioning tube, and an elastic rope is connected between the settlement magnetic ring and the tension detector. When the fixation between the settlement magnetic ring and the positioning tube is released, the settlement magnetic ring will move vertically with the soil layer and drive the elastic rope to stretch. The settlement of the soil layer can be indirectly obtained by detecting the tension value on the elastic connector. When using this method to detect the settlement of the soil layer, on the one hand, the tension detector is set underground, and the tension detector cannot be repaired or replaced after being damaged, which causes the entire monitoring device to fail, and the original underground equipment (such as cables) will generate a magnetic field to interfere with the detection results of the tension detector, affecting the accuracy of the settlement; on the other hand, the settlement results of the soil layer cannot be intuitively reflected. Summary of the invention

[0004] The purpose of the present invention is to provide a ground subsidence monitoring device and its installation and use method, which can intuitively reflect the soil settlement results, have a simple structure, and are easy to operate. The detector can be replaced and maintained in time to ensure the normal use of the ground subsidence monitoring device and the accuracy of the settlement detection results.

[0005] To achieve the above object, the present invention adopts the following technical solutions:

[0006] In a first aspect, a ground subsidence monitoring device is provided, comprising:

[0007] A positioning member extending vertically and configured to be inserted underground;

[0008] A settlement assembly is provided, wherein at least one settlement assembly is movably arranged on the positioning member in a vertical direction and buried underground;

[0009] A fixed support is arranged above the ground;

[0010] A connecting assembly is provided with at least one, one end of which is rotatably connected to the fixed bracket, and the other end of which is matched with the settling assembly, and the settling assembly is used to drive the connecting assembly to rotate relative to the fixed bracket;

[0011] The angle detection module is arranged on the connection component or the fixing bracket and is located above the ground. The angle detection module is used to detect the rotation angle of the connection component relative to the fixing bracket.

[0012] Optionally, the connection assembly comprises a connection rod, a flexible connection member and a first magnet connected in sequence, and one end of the connection rod away from the flexible connection member is rotatably connected to the fixed bracket;

[0013] The sedimentation assembly includes a ring body and a second magnet. The ring body is movably mounted on the positioning member in the vertical direction. The second magnet is arranged on a side of the ring body facing the positioning member. The second magnet is magnetically matched with the first magnet.

[0014] Optionally, the sedimentation assembly further includes a connecting protrusion, which is arranged on the side of the ring body facing the positioning member, the outer wall of the positioning member is recessed with a sliding groove, and the sliding groove extends vertically, and the connecting protrusion can be slidably clamped in the sliding groove.

[0015] Optionally, the sedimentation assembly further includes a rolling member, the rolling member is arranged on a side of the ring body facing the positioning member, and the rolling member and the positioning member are in rolling cooperation.

[0016] Optionally, the fixing bracket comprises a first frame body and an arched plate connected to each other, one end of the first frame body away from the arched plate is installed on the ground, and the inner concave surface of the arched plate faces the positioning member;

[0017] The ground subsidence monitoring device includes a plurality of connecting components and a plurality of settlement components. The plurality of connecting components are arranged in one-to-one correspondence with the plurality of settlement components. The connecting rods of the plurality of connecting components are arranged on the arch plate at intervals along the extension direction of the arch plate, and the distance between two adjacent connecting rods gradually decreases along the direction approaching the positioning member.

[0018] Optionally, the fixing bracket further comprises a second frame body and a positioning ring connected to each other, wherein one end of the second frame body away from the positioning ring is arranged on the first frame body, and the positioning ring is located above the positioning member;

[0019] The flexible connecting piece passes through the positioning ring and is in sliding contact with the ring opening area of ​​the positioning ring.

[0020] Optionally, the positioning member includes a positioning tube, the settlement assembly is vertically movably disposed outside the positioning tube, and the connecting assembly is passed through the positioning tube and cooperates with the settlement assembly.

[0021] Optionally, the sedimentation assembly includes a ring body, a plurality of first fixed arms and a plurality of second fixed arms, the ring body is movably mounted on the positioning member in the vertical direction, the plurality of first fixed arms and the plurality of second fixed arms are circumferentially spaced apart on a side of the ring body away from the positioning member, and the first fixed arms and the second fixed arms extend in different directions respectively.

[0022] Optionally, the first fixed arm and the second fixed arm both include a first arm body, a second arm body and a third arm body that are bent and connected in sequence, one end of the first arm body away from the second arm body is connected to the ring body, the second arm body of the first fixed arm extends upward at an end away from the first arm body, and the second arm body of the second fixed arm extends downward at an end away from the first arm body.

[0023] In a second aspect, a method for installing and using a ground subsidence monitoring device is provided. The ground subsidence monitoring device as described above is used, and the method for installing and using the ground subsidence monitoring device comprises the following steps:

[0024] A monitoring hole is opened at the position to be monitored on the ground, and the positioning member is inserted into the monitoring hole;

[0025] Filling soil between the monitoring hole and the positioning member according to a preset detection depth;

[0026] The sinking assembly is movably arranged on the positioning member in the vertical direction, and the sinking assembly is lowered to the preset detection depth;

[0027] One end of the connecting assembly is rotatably connected to the fixed bracket, and the other end is matched with the settling assembly;

[0028] Filling soil again between the monitoring hole and the positioning member until the monitoring hole is filled;

[0029] The angle detection module is controlled to detect a rotation angle of the connection component relative to the fixing bracket.

[0030] Beneficial effects of the present invention:

[0031] The present invention provides a ground settlement monitoring device and its installation and use method, including a positioning member, a settlement component, a fixed bracket, a connecting component and an angle detection module. When performing ground settlement monitoring, the fixed bracket is set above the ground, and a monitoring hole is opened at the position to be measured. Then, the positioning member is inserted into the monitoring hole, the positioning member is kept vertical, and soil is filled between the monitoring hole and the positioning tube to a preset detection depth. Then, the settlement component is set on the positioning member, and the settlement component is lowered to the depth to be measured. Then, one end of the connecting component is rotatably connected to the fixed bracket, and the other end is matched with the settlement component. Soil is filled between the monitoring hole and the positioning member again until the monitoring hole is filled. The angle detection module is controlled to monitor the rotation angle of the connecting component relative to the fixed bracket in real time. When the soil layer settles, the soil layer will drive the settlement component to move downward, thereby driving the connecting component to rotate relative to the fixed bracket. The settlement amount of the soil layer can be known by the rotation angle of the connecting component relative to the fixed bracket detected by the angle detection module.

[0032] By setting up a settlement component, a connection component and an angle detection module, the settlement of the soil layer at a preset detection depth can be monitored. In addition, multiple settlement components and multiple connection components can be set up to simultaneously monitor the settlement of soil layers at different preset detection depths, comprehensively obtain soil layer information, and help staff accurately assess the construction site conditions. Setting the angle detection module above the ground can facilitate staff to promptly inspect and replace the angle detection module to ensure the normal use of the monitoring device. At the same time, it can also avoid the magnetic field generated by the original underground equipment from interfering with the detection results, ensuring the reliability of the detection results. In addition, the settlement of the soil layer can drive the rotation of the connection component, so that the staff can intuitively know the settlement degree of the soil layer. The structure is simple and easy to operate. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 is a first view of the land subsidence monitoring device provided by an embodiment of the present invention;

[0034] Figure 2 is a second view of the land subsidence monitoring device provided by an embodiment of the present invention;

[0035] Figure 3 is a cross-sectional view of a land subsidence monitoring device provided by an embodiment of the present invention;

[0036] Figure 4 yes Figure 3 The enlarged view of point A in the middle;

[0037] Figure 5 It is a schematic diagram of the structure of the sedimentation assembly provided in an embodiment of the present invention.

[0038] In the figure:

[0039] 1. Positioning piece; 11. Sliding groove;

[0040] 2. Sedimentation assembly; 21. Ring body; 22. Second magnet; 23. Connecting protrusion; 24. Rolling member; 25. First fixed arm; 251. First arm body; 252. Second arm body; 253. Third arm body; 26. Second fixed arm;

[0041] 3. Fixed bracket; 31. First frame; 32. Arched plate; 33. Second frame; 34. Positioning ring;

[0042] 4. Connecting assembly; 41. Connecting rod; 42. Flexible connecting member; 43. First magnet. DETAILED DESCRIPTION

[0043] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.

[0044] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0045] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0046] In the description of this embodiment, the terms "upper", "lower", "left", "right" and other directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplification of operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operate in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.

[0047] Embodiment 1

[0048] This embodiment provides a ground subsidence monitoring device, such as Figures 1 to 3 As shown, the ground subsidence monitoring device includes a positioning member 1, a subsidence component 2, a fixing bracket 3, a connecting component 4 and an angle detection module (not shown in the figure). The ground subsidence monitoring device can be used to monitor the subsidence of the soil layer in real time, so as to obtain the ground situation more accurately, help the staff to evaluate the impact of the construction on the geological environment, and ensure the safety and quality of the project.

[0049] Among them, the positioning member 1 extends vertically and is configured to be inserted into the ground, which can provide positioning support for the entire monitoring device. At least one settlement component 2 is provided, and the settlement component 2 is movably arranged on the positioning member 1 along the vertical direction, and the settlement component 2 is buried underground. The fixed bracket 3 is arranged above the ground. At least one connecting component 4 is provided, one end of the connecting component 4 is rotatably connected to the fixed bracket 3, and the other end is matched with the settlement component 2. When the soil layer settles, the soil layer will drive the settlement component 2 to move downward together, so that the settlement component 2 drives the connecting component 4 to rotate relative to the fixed bracket 3. The angle detection module is arranged on the connecting component 4 or the fixed bracket 3, and is located above the ground. When the connecting component 4 rotates relative to the fixed bracket 3, the angle detection module can detect the rotation angle of the connecting component 4 relative to the fixed bracket 3, so as to know the settlement amount of the soil layer.

[0050] By setting the settlement component 2, the connection component 4 and the angle detection module, the settlement of the soil layer at the preset detection depth can be monitored, and multiple settlement components 2 and multiple connection components 4 can be set to monitor the settlement of soil layers at different preset detection depths at the same time, and comprehensively obtain soil layer information to help staff accurately evaluate the construction site conditions. Setting the angle detection module above the ground can facilitate staff to timely inspect and replace the angle detection module to ensure the normal use of the monitoring device, and at the same time avoid the magnetic field generated by the original underground equipment from interfering with the detection results, ensuring the reliability of the detection results. In addition, the settlement of the soil layer can drive the connection component 4 to rotate, so that the staff can intuitively know the settlement degree of the soil layer, with a simple structure and easy operation.

[0051] Optionally, the angle detection module includes an angle sensor. In other embodiments, the angle detection module also includes a rotary encoder and the like.

[0052] Exemplarily, three settling assemblies 2 and three connecting assemblies 4 are provided. In other embodiments, one, two or more than three settling assemblies 2 and connecting assemblies 4 may be provided according to actual needs, which is not limited here.

[0053] It should be noted that the number of the settlement components 2 is the same as the number of the connection components 4, and each settlement component 2 is provided with a corresponding connection component 4. In addition, the number of settlement components 2 to be provided is determined according to the actual need to detect the settlement of soil layers at several depths.

[0054] Alternatively, if Figure 1 , Figure 3 and Figure 4 As shown, the connection assembly 4 includes a connection rod 41, a flexible connection member 42 and a first magnet 43 connected in sequence. One end of the connection rod 41 away from the flexible connection member 42 is rotatably connected to the fixed bracket 3. The sedimentation assembly 2 includes a ring body 21 and a second magnet 22, and the ring body 21 is movably sleeved on the positioning member 1 in the vertical direction. The second magnet 22 is arranged on the side of the ring body 21 facing the positioning member 1, and the second magnet 22 is magnetically matched with the first magnet 43.

[0055] Since the settlement component 2 is buried underground, when the soil layer settles, the soil layer will drive the ring body 21 to move downward along the positioning member 1. During the downward movement, due to the magnetic attraction between the second magnet 22 and the first magnet 43, the settlement component 2 will drive the first magnet 43 to move downward, thereby pulling the connecting rod 41 through the flexible connecting member 42, causing the connecting rod 41 to rotate relative to the fixed bracket 3. The angle detection module can detect the rotation angle of the connecting rod 41 relative to the fixed bracket 3, thereby knowing the settlement amount of the soil layer.

[0056] In addition, the rotation of the connecting rod 41 enables the staff to intuitively know the degree of settlement of the soil layer. The structure is simple and easy to operate. The ring body 21 is sleeved on the positioning member 1, and the positioning member 1 can provide a guiding effect for the ring body 21, so that the ring body 21 can always move along the positioning member 1, preventing the ring body 21 from tilting and shifting under the drive of the soil, thereby avoiding affecting the detection results.

[0057] Exemplarily, the flexible connector 42 includes a steel wire rope. In other embodiments, flexible materials such as nylon rope, polyester fiber rope, etc. can also be selected as the flexible connector 42 according to actual needs, which is not limited here.

[0058] It should be noted that each sedimentation assembly 2 is correspondingly provided with a second magnet 22 .

[0059] Alternatively, if Figure 1 and Figure 5As shown, the settlement assembly 2 also includes a connecting protrusion 23, and the connecting protrusion 23 is arranged on the side of the ring body 21 facing the positioning member 1. The outer wall of the positioning member 1 is recessed with a sliding groove 11, and the sliding groove 11 extends vertically. The connecting protrusion 23 is slidably clamped in the sliding groove 11. When the soil layer settles, the ring body 21 will drive the connecting protrusion 23 to move downward in the sliding groove 11. Through the cooperation of the connecting protrusion 23 and the sliding groove 11, the ring body 21 can be further limited to prevent the ring body 21 from detaching from the positioning member 1, and the sliding groove 11 can provide a guiding effect for the ring body 21, so that the ring body 21 always moves along the positioning member 1, preventing the ring body 21 from tilting and shifting, and avoiding affecting the detection result.

[0060] Alternatively, if Figure 1 and Figure 5 As shown, the settlement assembly 2 also includes a rolling member 24. The rolling member 24 is arranged on the side of the ring body 21 facing the positioning member 1, and the rolling member 24 and the positioning member 1 are rollingly matched. When the soil layer settles, the soil layer will drive the ring body 21 to move downward, and at the same time, the rolling member 24 and the positioning member 1 are rollingly matched. With the assistance of the rolling member 24, the ring body 21 moves smoothly along the positioning member 1. By setting the rolling member 24, the friction between the ring body 21 and the positioning member 1 can be reduced, so that the ring body 21 can move downward smoothly, and it is prevented that the ring body 21 cannot move downward with the soil layer due to excessive friction, so as to avoid affecting the detection result. In addition, it can also make the ring body 21 more stable when moving along the positioning member 1, reduce shaking and jitter, and improve the overall stability of the monitoring device.

[0061] Exemplarily, the rolling element 24 includes a ball. In other embodiments, the rolling element 24 also includes a rollable structure such as a roller, which is not limited here.

[0062] In this embodiment, each sedimentation assembly 2 is provided with two rolling members 24. The connecting protrusion 23 is provided with a receiving cavity, the rolling member 24 is provided in the receiving cavity, and the second magnet 22 is provided between the two rolling members 24. In other embodiments, each sedimentation assembly 2 can also be provided with one or more rolling members 24 according to actual needs, and the rolling member 24 and the second magnet 22 are both provided in the receiving cavity, and the number of the rolling members 24 is not limited here.

[0063] In some embodiments, the rolling element 24 and the second magnet 22 may be disposed on the side of the ring body 21 facing the positioning element 1 and outside the accommodating cavity. The number of the rolling elements 24 includes one, two or more than two, and the number of the rolling elements 24 is not limited. When there are multiple rolling elements 24, the multiple rolling elements 24 are disposed at intervals along the circumference of the ring body 21.

[0064] In other embodiments, multiple rolling elements 24 may be disposed simultaneously on the side of the ring body 21 facing the positioning element 1 and in the accommodating cavity. The positions and numbers of the rolling elements 24 are not limited here.

[0065] Alternatively, if Figure 1 and Figure 2 As shown, the fixed bracket 3 includes a first frame 31 and an arch plate 32 connected to each other. One end of the first frame 31 away from the arch plate 32 is installed on the ground, and the inner concave surface of the arch plate 32 faces the positioning member 1. The ground settlement monitoring device includes a plurality of connecting components 4 and a plurality of settlement components 2, and the plurality of connecting components 4 are arranged one by one with the plurality of settlement components 2. The connecting rods 41 of the plurality of connecting components 4 are arranged on the arch plate 32 at intervals along the extension direction of the arch plate 32, and the spacing between two adjacent connecting rods 41 gradually decreases along the direction close to the positioning member 1. When the soil layer settles, the plurality of settlement components 2 will drive the connecting rods 41 of the plurality of connecting components 4 to rotate relative to the fixed bracket 3 at the same time. By setting the arch plate 32, a fixed installation foundation can be provided for the connecting rod 41, and the inner concave surface of the arch plate 32 faces the positioning member 1, so that the plurality of connecting rods 41 are arranged circumferentially along the positioning member 1, which can intuitively reflect the settlement difference of soil layers at different depths, and facilitate the staff to obtain the geological information of the site.

[0066] In this embodiment, if Figures 2 to 4 As shown, the fixed bracket 3 also includes a second frame 33 and a positioning ring 34 connected to each other. One end of the second frame 33 away from the positioning ring 34 is arranged on the first frame 31, and the positioning ring 34 is located above the positioning member 1. When setting the connecting component 4, the flexible connecting member 42 of the connecting component 4 is passed through the positioning ring 34, and then the first magnet 43 and the second magnet 22 are magnetically matched, and the flexible connecting member 42 is in sliding contact with the ring opening area of ​​the positioning ring 34. By setting the positioning ring 34, the flexible connecting members 42 of multiple connecting components 4 can be gathered together to prevent the flexible connecting members 42 of multiple connecting components 4 from tangling and interfering with each other, thereby avoiding affecting the detection results.

[0067] In addition, the upper end surface of the positioning ring 34 and the inner wall of the positioning ring 34 are connected by an arc transition, so that the positioning ring 34 and the flexible connector 42 are in smooth contact, which can reduce the friction between the flexible connector 42 and the positioning ring 34, prevent the settlement component 2 from being hindered from moving downward due to excessive friction, and prevent the flexible connector 42 from being damaged or broken due to the positioning ring 34 being too sharp, thereby avoiding affecting the detection results.

[0068] Optionally, the positioning member 1 includes a positioning tube. The settlement component 2 is movably arranged outside the positioning tube in the vertical direction, and the connecting component 4 is inserted into the positioning tube and cooperates with the settlement component 2. By setting the positioning tube as the positioning member 1, the connecting component 4 can be inserted into the positioning tube, and the positioning tube can protect the connecting component 4, isolate the contact between the soil layer and the connecting component 4, prevent the soil layer from affecting the cooperation between the connecting component 4 and the settlement component 2, and ensure the accuracy of the detection result.

[0069] like Figures 1 to 3As shown, the settlement assembly 2 includes a plurality of first fixed arms 25 and a plurality of second fixed arms 26. The plurality of first fixed arms 25 and the plurality of second fixed arms 26 are all arranged at intervals along the circumference on the side of the ring body 21 away from the positioning member 1, and the first fixed arm 25 and the second fixed arm 26 extend in different directions respectively. Since the settlement assembly 2 is buried underground, the first fixed arm 25 and the second fixed arm 26 arranged thereon will be inserted into the soil layer. When the soil layer settles, the soil layer will drive the ring body 21, the first fixed arm 25 and the second fixed arm 26 to move synchronously. By setting the first fixed arm 25 and the second fixed arm 26, the connection strength between the ring body 21 and the soil layer can be strengthened, the movement consistency between the ring body 21 and the soil layer can be improved, and it is ensured that the soil layer can drive the ring body 21 to move downward, thereby ensuring the accuracy of the detection structure. In addition, the first fixed arm 25 and the second fixed arm 26 extend in different directions respectively, so that the first fixed arm 25 and the second fixed arm 26 can be stuck in the soil layer in multiple directions, making the connection between the ring body 21 and the soil layer tighter and more reliable.

[0070] Alternatively, if Figure 1 and Figure 2 As shown, the first fixed arm 25 and the second fixed arm 26 each include a first arm body 251, a second arm body 252 and a third arm body 253 which are bent and connected in sequence. One end of the first arm body 251 away from the second arm body 252 is connected to the ring body 21. The bent first arm body 251, the second arm body 252 and the third arm body 253 are inserted into the soil layer, so that a contact surface with a more complex shape can be formed between the fixed arm and the soil layer, thereby increasing the friction between the fixed arm and the soil layer and improving the stability of the fixed arm. In addition, the bent fixed arm can better adapt to different geological conditions due to the variability of its shape, ensuring that the fixed arm can be smoothly inserted and reach the expected depth, and ensuring that the soil layer can drive the ring body 21 to move downward.

[0071] Alternatively, if Figure 2 and Figure 3 As shown, the second arm 252 of the first fixed arm 25 extends upwardly at an end away from the first arm 251, and the second arm 252 of the second fixed arm 26 extends downwardly at an end away from the first arm 251. By arranging the second arm 252 to extend obliquely in different directions, the first fixed arm 25 and the second fixed arm 26 can clamp the soil layer vertically, strengthen the connection strength between the ring body 21 and the soil layer, and ensure the overall stability of the monitoring device.

[0072] Embodiment 2

[0073] This embodiment provides a method for installing and using a ground subsidence monitoring device. Using the ground subsidence monitoring device as described above, the method for installing and using the ground subsidence monitoring device includes the following steps:

[0074] S1. Open a monitoring hole at the location to be monitored on the ground, and insert the positioning member 1 into the monitoring hole;

[0075] S2, filling soil between the monitoring hole and the positioning member 1 according to the preset detection depth;

[0076] S3, vertically movably arrange the sedimentation assembly 2 on the positioning member 1, and lower the sedimentation assembly 2 to a preset detection depth;

[0077] S4, one end of the connecting component 4 is rotatably connected to the fixed bracket 3, and the other end is matched with the settling component 2;

[0078] S5, filling the space between the monitoring hole and the positioning member 1 again until the monitoring hole is filled;

[0079] S6 , controlling the angle detection module to detect the rotation angle of the connecting component 4 relative to the fixed bracket 3 .

[0080] When monitoring ground subsidence, the fixed support 3 is set above the ground, and a monitoring hole is opened at the position to be tested. Then, the positioning member 1 is inserted into the monitoring hole, and the positioning member 1 is kept vertical. The soil is filled between the monitoring hole and the positioning tube to the preset detection depth. Then, the settlement component 2 is set on the positioning member 1, and the settlement component 2 is lowered to the depth to be measured. Then, one end of the connecting component 4 is rotatably connected to the fixed support 3, and the other end is matched with the settlement component 2. The soil is filled between the monitoring hole and the positioning member 1 again until the monitoring hole is filled. The angle detection module is controlled to monitor the rotation angle of the connecting component 4 relative to the fixed support 3 in real time. When the soil layer settles, the soil layer will drive the settlement component 2 to move downward, thereby driving the connecting component 4 to rotate relative to the fixed support 3. The amount of soil layer settlement can be known by the rotation angle of the connecting component 4 relative to the fixed support 3 detected by the angle detection module.

[0081] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the protection scope of the present invention. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.

Claims

1. A ground subsidence monitoring device, characterized in that: include: A positioning member (1), the positioning member (1) extending vertically and configured to be inserted underground; A settlement component (2) is provided with at least one, the settlement component (2) being movably arranged on the positioning member (1) in a vertical direction, and the settlement component (2) being buried underground; A fixed support (3) is arranged above the ground; A connecting assembly (4) is provided with at least one, one end of the connecting assembly (4) is rotatably connected to the fixed bracket (3), and the other end is matched with the settling assembly (2), and the settling assembly (2) is used to drive the connecting assembly (4) to rotate relative to the fixed bracket (3); an angle detection module, arranged on the connection component (4) or the fixed bracket (3) and located above the ground, the angle detection module being used to detect the rotation angle of the connection component (4) relative to the fixed bracket (3); The connecting assembly (4) comprises a connecting rod (41), a flexible connecting member (42) and a first magnet (43) which are connected in sequence, and an end of the connecting rod (41) away from the flexible connecting member (42) is rotatably connected to the fixed bracket (3); The sedimentation assembly (2) comprises a ring body (21) and a second magnet (22); the ring body (21) is movably sleeved on the positioning member (1) in the vertical direction; the second magnet (22) is arranged on a side of the ring body (21) facing the positioning member (1); the second magnet (22) is magnetically engaged with the first magnet (43); The fixed bracket (3) comprises a first frame body (31) and an arched plate (32) connected to each other, wherein one end of the first frame body (31) away from the arched plate (32) is mounted on the ground, and the inner concave surface of the arched plate (32) faces the positioning member (1); The ground subsidence monitoring device comprises a plurality of the connecting assemblies (4) and a plurality of the subsidence assemblies (2), wherein the plurality of the connecting assemblies (4) are arranged in a one-to-one correspondence with the plurality of the subsidence assemblies (2), and the connecting rods (41) of the plurality of the connecting assemblies (4) are arranged on the arch plate (32) at intervals along the extension direction of the arch plate (32), and the spacing between two adjacent connecting rods (41) gradually decreases in a direction approaching the positioning member (1).

2. The ground subsidence monitoring device according to claim 1, characterized in that: The sedimentation assembly (2) further comprises a connecting protrusion (23), wherein the connecting protrusion (23) is arranged on a side of the ring body (21) facing the positioning member (1), and a sliding groove (11) is recessed on an outer wall of the positioning member (1), and the sliding groove (11) extends vertically, and the connecting protrusion (23) can be slidably clamped in the sliding groove (11).

3. The ground subsidence monitoring device according to claim 1, characterized in that: The sedimentation assembly (2) further comprises a rolling member (24), wherein the rolling member (24) is arranged on a side of the ring body (21) facing the positioning member (1), and the rolling member (24) and the positioning member (1) are in rolling cooperation.

4. The ground subsidence monitoring device according to claim 1, characterized in that: The fixing bracket (3) further comprises a second frame body (33) and a positioning ring (34) connected to each other, wherein one end of the second frame body (33) away from the positioning ring (34) is arranged on the first frame body (31), and the positioning ring (34) is located above the positioning member (1); The flexible connecting piece (42) passes through the positioning ring (34) and is in sliding contact with the ring opening area of ​​the positioning ring (34).

5. The land subsidence monitoring device according to any one of claims 1 to 4, characterized in that: The positioning member (1) comprises a positioning tube, the settling assembly (2) is arranged outside the positioning tube in a vertically movably manner, and the connecting assembly (4) is inserted into the positioning tube and cooperates with the settling assembly (2).

6. The land subsidence monitoring device according to any one of claims 1 to 4, characterized in that: The sedimentation assembly (2) comprises a ring body (21), a plurality of first fixed arms (25) and a plurality of second fixed arms (26); the ring body (21) is movably sleeved on the positioning member (1) in the vertical direction; the plurality of first fixed arms (25) and the plurality of second fixed arms (26) are circumferentially spaced apart and arranged on a side of the ring body (21) away from the positioning member (1); the first fixed arms (25) and the second fixed arms (26) extend in different directions respectively.

7. The ground subsidence monitoring device according to claim 6, characterized in that: The first fixed support arm (25) and the second fixed support arm (26) both comprise a first arm body (251), a second arm body (252) and a third arm body (253) which are bent and connected in sequence; one end of the first arm body (251) away from the second arm body (252) is connected to the ring body (21); one end of the second arm body (252) of the first fixed support arm (25) away from the first arm body (251) extends upwardly at an angle; and one end of the second arm body (252) of the second fixed support arm (26) away from the first arm body (251) extends downwardly at an angle.

8. A method for installing and using a land subsidence monitoring device, using the land subsidence monitoring device according to any one of claims 1 to 7, characterized in that: The method for installing and using the ground subsidence monitoring device comprises the following steps: A monitoring hole is opened at the position to be monitored on the ground, and the positioning member (1) is inserted into the monitoring hole; Filling soil between the monitoring hole and the positioning member (1) according to a preset detection depth; The sedimentation component (2) is arranged on the positioning member (1) in a vertically movably manner, and the sedimentation component (2) is lowered to the preset detection depth; One end of the connecting component (4) is rotatably connected to the fixed bracket (3), and the other end is matched with the settling component (2); Filling soil again between the monitoring hole and the positioning member (1) until the monitoring hole is filled; The angle detection module is controlled to detect the rotation angle of the connection component (4) relative to the fixed bracket (3).

Citation Information

Patent Citations

  • Side adhesion type tunnel top wall settlement monitoring mechanism and tunnel top wall settlement monitoring method

    CN113532383A

  • Foundation pit settlement monitoring device

    CN115162429A

  • Embedded land subsidence monitoring device

    CN115420255A

  • Device for detecting settlement of soil around pipe pile

    CN116105677A