The invention relates to the field of mining area
subsidence reduction and filling mining, in particular to a
coal mining method for controlling
ground subsidence through bottom plate isolation grouting filling. Comprising the steps that a rock stratum with a certain thickness is selected below a bottom plate
damage zone to serve as a bottom
plate pressure-bearing
protection layer, the bottom
plate pressure-bearing
protection layer arches upwards under the grouting pressure, but cracks for conducting the upper bottom plate
damage zone are not generated; the bottom interface of the pressure-bearing
protection layer of the bottom plate serves as a grouting layer, and grouting
drill holes are constructed to communicate with the grouting layer; and when grouting filling can be carried out, filling
grout is injected into the grouting layer position from the grouting
drill hole. The filling
slurry lifts a bottom plate grouting pressure-bearing layer and a bottom plate
damage zone under the action of
high pressure, and finally the whole goaf is filled, the fracture degree of a
coal seam roof is reduced, the settlement amplitude of an overlying rock layer is controlled, and then the surface
subsidence amplitude is reduced. The
coal mining process and the grouting filling process are separated, the influence of grouting filling operation on working face
stoping is avoided, and the method is particularly suitable for coal mine areas with dense buildings.