Power grid facility waterlogging disaster intelligent prediction method and device based on fluid large model

By combining one-dimensional and two-dimensional hydrodynamic models with large model technology, the problem of insufficient training samples and mutually exclusive calculation accuracy and speed in the prediction of waterlogging disaster in power grid facilities is solved, and high-precision and high-speed prediction of waterlogging distribution is achieved, adapting to meteorological and Changes in the urban environment have improved the timeliness and accuracy of predictions.

CN118735046APending Publication Date: 2024-10-01NORTH CHINA BRANCH OF STATE GRID CORPORATION OF CHINA
View PDF 0 Cites 8 Cited by

Patent Information

Application Number
CN202410763078.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-13
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The existing technology has problems in the prediction of waterlogging disaster in power grid facilities, such as insufficient training samples, mutually exclusive calculation accuracy and speed, and a small amount of true water accumulation data, which cannot support efficient training, and it is difficult to achieve high-precision and high-speed waterlogging forecasting.

Method used

One-dimensional and two-dimensional hydrodynamic models combined with large model technology are used to train a large fluid model through long-term series of precipitation prediction data, conduct model coupling, and use incremental learning to optimize the waterlogging coupling model, and combine operational precipitation prediction and monitoring data for prediction. .

Benefits of technology

It achieves high-precision and high-speed prediction of waterlogging distribution, reduces the complexity of the physical coupling model, improves the timeliness and accuracy of prediction, and adapts to changes in meteorology and urban environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735046A_ABST
    Figure CN118735046A_ABST
Patent Text Reader

Abstract

The invention relates to the field of the power industry, in particular to a power grid facility waterlogging disaster intelligent prediction method and device based on a fluid large model. The method comprises the following steps: acquiring rainfall prediction data of business forecast; inputting rainfall prediction data into the constructed waterlogging model, and outputting waterlogging ponding depth distribution; acquiring parameter data of key facilities of the power grid; and obtaining a waterlogging disaster prediction result of the power grid key facility according to the waterlogging water depth distribution and the parameter data of the power grid key facility. The method can significantly improve the accuracy of waterlogging ponding diffusion prediction, and is of great significance to waterlogging prediction of key facilities of a power grid. According to the improved method, the problem of insufficient true value training samples caused by insufficient ponding monitoring equipment can be solved, and the temporal-spatial resolution and precision of the prediction model are improved through a large model coupling mode, so that more reliable support is provided for operation and planning of key facilities of a power grid.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of the electric power industry, and in particular to an intelligent prediction method and device for waterlogging disasters in power grid facilities based on a large fluid model. Background Art

[0002] Waterlogging poses a direct threat to the safe operation of key grid facilities (such as substations). Globally, with the acceleration of urbanization and the frequent occurrence of extreme climate events, waterlogging disaster prevention and mitigation has received widespread attention in the power industry. Waterlogging may cause damage to key grid equipment, trigger power supply interruptions, and cause significant losses to the society and economy. Therefore, it is necessary to establish an effective waterlogging disaster prevention system to ensure the stable operation of substations and other grid facilities under extreme precipitation events and achieve sustainable development of the power system.

[0003] However, waterlogging risk assessment and early warning for power grid facilities is a complex issue involving multiple factors, including local rainfall, urban drainage capacity, topography, and flood control design of the facilities themselves. The uncertainty and variability of these factors increase the difficulty of waterlogging prediction, thus posing challenges to the disaster prevention and mitigation planning and emergency management of the power grid. In order to meet this challenge, waterlogging disaster prevention prediction has become a key link in the management and operation of power grid facilities. Waterlogging disaster prevention prediction aims to accurately predict the waterlogging risks that power facilities such as substations may face by analyzing historical meteorological data, real-time environmental conditions, and the specific conditions of power grid facilities.

[0004] In recent years, with the rapid development of artificial intelligence and machine learning technologies, the field of waterlogging disaster prevention prediction for power grid facilities has also ushered in new progress. The application of large model technology based on artificial intelligence, such as the new meteorological large model, has greatly improved the accuracy and timeliness of meteorological precipitation forecasts, thereby indirectly improving the accuracy of waterlogging forecasts. It also provides a new solution to the problem of waterlogging and water diffusion. Artificial intelligence large models can process and analyze a large amount of historical meteorological data, real-time monitoring data, and geographic information data, automatically learn the complex relationships between these data, and dynamically adjust and optimize according to real-time environmental changes. For example, by analyzing the rainfall pattern in the surrounding area of ​​the substation, the condition of the drainage system, the geographical location of the substation, and flood control measures, the artificial intelligence model can predict the level of waterlogging risk and potential impact range that the substation may suffer under a specific rainfall event.

[0005] In addition, combined with detailed weather forecast data, such as rainfall forecast, cloud cover, wind direction and speed, the spatiotemporal resolution of waterlogging risk prediction can be further improved, providing more accurate guidance for waterlogging prevention of power facilities such as substations. With real-time updated weather forecast data, the waterlogging prevention system can adjust the warning level and response measures in a timely manner, effectively reducing the risk of power grid facilities under extreme weather conditions.

[0006] Waterlogging disaster prediction is an important means to ensure the safe and stable operation of power grid facilities, especially substations. With the continuous advancement of artificial intelligence and large-scale meteorological model technology, waterlogging disaster prediction methods will become more accurate and reliable, providing strong technical support for disaster prevention and control and emergency management of power systems.

[0007] The waterlogging diffusion model is developed to accurately predict and simulate surface waterlogging caused by precipitation, which is particularly important for disaster prevention planning of cities and power infrastructure. At present, the models used for waterlogging diffusion prediction can be divided into two categories:

[0008] 1. Simulation algorithm based on physical process:

[0009] Hydrodynamic models: These algorithms predict the development and spread of waterlogging by simulating the infiltration of precipitation, surface runoff, and the flow of water through urban streets and drainage systems. The models are usually based on the Saint Venant equation or the Manning equation, combined with detailed information on topography, soil type, and urban drainage systems.

[0010] Surface hydrological models: These models focus on simulating the generation and dissipation of surface water through hydrological cycle processes such as precipitation, evaporation and infiltration. Such models usually require detailed soil properties, land use types and terrain elevation data.

[0011] 2. Data-driven machine learning prediction algorithm:

[0012] Artificial neural network-based methods: Using deep learning frameworks, such as convolutional neural networks (CNN) or recurrent neural networks (RNN), to establish complex nonlinear relationships between inputs (such as precipitation, topographic information) and the spread of waterlogging. This type of method can automatically identify the patterns between precipitation events and waterlogging results, and make effective predictions.

[0013] Support vector machine-based method: By building a support vector machine model, the relationship between historical precipitation events and waterlogging can be learned to predict the waterlogging situation that may be caused by future precipitation events. Support vector machines perform well when processing small sample data and are suitable for waterlogging risk assessment in specific areas.

[0014] Ensemble learning-based methods: Ensemble learning combines the prediction results of multiple single prediction models (such as random forests, gradient boosting trees, etc.) to obtain more accurate and stable predictions of waterlogging spread. These methods improve prediction performance by integrating the prediction advantages of different models.

[0015] In addition, depending on the input characteristics used, waterlogging diffusion models can be further divided into univariate models and multivariate models. Univariate models mainly rely on precipitation data, while multivariate models combine multiple factors such as precipitation, terrain elevation, land cover type, and urban drainage system configuration to improve the accuracy of prediction. Some advanced models also take into account long-term factors such as urbanization and climate change trends to assess waterlogging risks under different scenarios in the future.

[0016] With the enhancement of computing power and the development of machine learning technology, especially the application of large artificial intelligence models, the accuracy and application scope of urban waterlogging diffusion models have been continuously improved, providing strong technical support for urban planning, power grid facility disaster prevention and mitigation, and emergency management. Summary of the invention

[0017] In order to solve the technical problems of how to establish an effective waterlogging prevention system in the prior art, ensure the stable operation of substations and other power grid facilities under extreme precipitation events, and achieve sustainable development of the power system, the embodiment of the present invention provides a method and device for intelligent prediction of waterlogging disasters in power grid facilities based on a large fluid model. The technical solution is as follows:

[0018] On the one hand, a method for intelligent prediction of waterlogging disasters in power grid facilities based on a large fluid model is provided, the method being implemented by an intelligent prediction device for waterlogging disasters in power grid facilities, the method comprising:

[0019] S1. Obtain precipitation forecast data for operational forecasts.

[0020] S2. Input the precipitation prediction data into the constructed waterlogging model and output the waterlogging depth distribution.

[0021] S3. Obtain parameter data of key power grid facilities.

[0022] S4. Based on the waterlogging depth distribution and parameter data of key grid facilities, the waterlogging disaster prediction results of key grid facilities are obtained.

[0023] Optionally, the construction process of the waterlogging model in S2 includes:

[0024] S21. Obtain long-term series precipitation prediction sample data.

[0025] S22, inputting the precipitation prediction sample data into the one-dimensional hydrodynamic model, outputting the location of the waterlogging overflow point and the overflow volume, and constructing a training sample set of the one-dimensional hydrodynamic model based on the precipitation prediction sample data and the location of the waterlogging overflow point and the overflow volume.

[0026] S23. Train the large model according to the training sample set of the one-dimensional hydrodynamic model to obtain a one-dimensional fluid large model.

[0027] S24, inputting the precipitation prediction sample data into the two-dimensional hydrodynamic model, outputting the two-dimensional water accumulation depth distribution, and constructing a training sample set of the two-dimensional hydrodynamic model according to the precipitation prediction sample data and the two-dimensional water accumulation depth distribution.

[0028] S25. Train the large model according to the training sample set of the two-dimensional hydrodynamic model to obtain a two-dimensional fluid large model.

[0029] S26. Couple the one-dimensional fluid large model and the two-dimensional fluid large model to obtain an urban waterlogging coupling model.

[0030] S27. Obtain waterlogging monitoring data, train a waterlogging coupling model based on the precipitation prediction sample data and the waterlogging monitoring data, and obtain a constructed waterlogging model.

[0031] Optionally, in S27, the waterlogging coupling model is trained according to the precipitation prediction sample data and the waterlogging waterlogging monitoring data to obtain a constructed waterlogging model, including:

[0032] S271. Obtaining precipitation forecast sample data at any time Sample data of precipitation forecast.

[0033] S272, the time The precipitation prediction sample data is input into the one-dimensional fluid model to obtain the time The location and overflow volume of the flood overflow point.

[0034] S273, the time The overflow point position and overflow volume of the flooding are input into the two-dimensional fluid model to obtain the time Two-dimensional water depth distribution.

[0035] S274. Obtaining the precipitation forecast sample data at the time Sample data of precipitation forecast.

[0036] S275, the moment The precipitation prediction sample data is input into the one-dimensional fluid model to obtain the time The location and overflow volume of the flood overflow point.

[0037] S276, time The two-dimensional water depth distribution and time The overflow point position and overflow volume of the flooding are input into the two-dimensional fluid model to obtain the time Two-dimensional water depth distribution.

[0038] S277, according to the time The two-dimensional water depth distribution and time The two-dimensional water depth distribution is used to obtain the water distribution prediction result.

[0039] S278. Train the waterlogging coupling model based on the waterlogging monitoring data and waterlogging distribution prediction results to obtain a constructed waterlogging model.

[0040] Optionally, the step of training the waterlogging coupling model according to the precipitation prediction sample data and the waterlogging monitoring data to obtain the constructed waterlogging model in S27 further includes:

[0041] Based on the precipitation prediction sample data and the waterlogging monitoring data, the waterlogging coupling model is incrementally learned to optimize and correct the key parameters in the waterlogging coupling model to obtain a constructed waterlogging model.

[0042] Optionally, the loss function of the waterlogging model is as follows:

[0043] (1)

[0044] In the formula, represents the loss function of the waterlogging model, Indicates the number of newly acquired waterlogging monitoring data. Indicates that the waterlogging model is based on the weight For The predicted value of each waterlogging monitoring data point, Indicates The actual observation value of each waterlogging monitoring data point.

[0045] Optionally, in the waterlogging model, the one-dimensional fluid large model and the two-dimensional fluid large model are connected through a pipe network node.

[0046] On the other hand, a device for intelligently predicting waterlogging disasters in power grid facilities based on a large fluid model is provided. The device is applied to an intelligent method for predicting waterlogging disasters in power grid facilities based on a large fluid model. The device comprises:

[0047] The first acquisition module is used to obtain precipitation forecast data for operational forecasts.

[0048] The input module is used to input the precipitation prediction data into the constructed waterlogging model and output the distribution of waterlogging depth.

[0049] The second acquisition module is used to acquire data of key facilities of the power grid.

[0050] The output module is used to obtain the prediction results of waterlogging disasters for key power grid facilities based on the distribution of waterlogging depth and data of key power grid facilities.

[0051] Optionally, the input module is further configured to:

[0052] S21. Obtain long-term series precipitation prediction sample data.

[0053] S22, inputting the precipitation prediction sample data into the one-dimensional hydrodynamic model, outputting the location of the waterlogging overflow point and the overflow volume, and constructing a training sample set of the one-dimensional hydrodynamic model based on the precipitation prediction sample data and the location of the waterlogging overflow point and the overflow volume.

[0054] S23. Train the large model according to the training sample set of the one-dimensional hydrodynamic model to obtain a one-dimensional fluid large model.

[0055] S24, inputting the precipitation prediction sample data into the two-dimensional hydrodynamic model, outputting the two-dimensional water accumulation depth distribution, and constructing a training sample set of the two-dimensional hydrodynamic model according to the precipitation prediction sample data and the two-dimensional water accumulation depth distribution.

[0056] S25. Train the large model according to the training sample set of the two-dimensional hydrodynamic model to obtain a two-dimensional fluid large model.

[0057] S26. Couple the one-dimensional fluid large model and the two-dimensional fluid large model to obtain an urban waterlogging coupling model.

[0058] S27. Obtain waterlogging monitoring data, train a waterlogging coupling model based on the precipitation prediction sample data and the waterlogging monitoring data, and obtain a constructed waterlogging model.

[0059] Optionally, the input module is further configured to:

[0060] S271. Obtaining precipitation forecast sample data at any time Sample data of precipitation forecast.

[0061] S272, the time The precipitation prediction sample data is input into the one-dimensional fluid model to obtain the time The location and overflow volume of the flood overflow point.

[0062] S273, the time The overflow point position and overflow volume of the flooding are input into the two-dimensional fluid model to obtain the time Two-dimensional water depth distribution.

[0063] S274. Obtaining the precipitation forecast sample data at the time Sample data of precipitation forecast.

[0064] S275, the moment The precipitation prediction sample data is input into the one-dimensional fluid model to obtain the time The location and overflow volume of the flood overflow point.

[0065] S276, time The two-dimensional water depth distribution and time The overflow point position and overflow volume of the flooding are input into the two-dimensional fluid model to obtain the time Two-dimensional water depth distribution.

[0066] S277, according to the time The two-dimensional water depth distribution and time The two-dimensional water depth distribution is used to obtain the water distribution prediction result.

[0067] S278. Train the waterlogging coupling model based on the waterlogging monitoring data and waterlogging distribution prediction results to obtain a constructed waterlogging model.

[0068] Optionally, the input module is further configured to:

[0069] Based on the precipitation prediction sample data and the waterlogging monitoring data, the waterlogging coupling model is incrementally learned to optimize and correct the key parameters in the waterlogging coupling model to obtain a constructed waterlogging model.

[0070] Optionally, the loss function of the waterlogging model is as follows:

[0071] (1)

[0072] In the formula, represents the loss function of the waterlogging model, Indicates the number of newly acquired waterlogging monitoring data. Indicates that the waterlogging model is based on the weight For The predicted value of each waterlogging monitoring data point, Indicates The actual observation value of each waterlogging monitoring data point.

[0073] Optionally, in the waterlogging model, the one-dimensional fluid large model and the two-dimensional fluid large model are connected through a pipe network node.

[0074] On the other hand, a device for intelligently predicting waterlogging disasters in power grid facilities is provided, the device comprising: a processor; a memory, the memory storing computer-readable instructions, and when the computer-readable instructions are executed by the processor, any one of the methods for intelligently predicting waterlogging disasters in power grid facilities based on a large fluid model is implemented.

[0075] On the other hand, a computer-readable storage medium is provided, in which at least one instruction is stored. The at least one instruction is loaded and executed by a processor to implement any one of the above-mentioned intelligent prediction methods for waterlogging disasters in power grid facilities based on a large fluid model.

[0076] The beneficial effects brought about by the technical solution provided by the embodiment of the present invention include at least:

[0077] In the embodiment of the present invention, based on a one-dimensional hydrodynamic model and a two-dimensional hydrodynamic model, a long-term precipitation prediction data is used as input to obtain a long-term waterlogging output, thereby solving the problem of insufficient prediction training samples for the hydrodynamic model AI. Through the AI ​​large model technology, the one-dimensional hydrodynamic model and the two-dimensional hydrodynamic model are replicated to solve the problem that the operation speed and calculation accuracy of the traditional physical model are mutually exclusive, and high precision and high speed are achieved; the two large models are coupled online to simulate the coupling of the physical model, which solves the problem of the difficulty and complexity of physical coupling and reduces the complexity of the coupling model; the precipitation prediction and the real waterlogging monitoring data are used as samples to perform incremental learning training on the large model, solving the problem of small amount of true waterlogging data, small number of samples, and inability to support training; finally, combined with the long-term business precipitation prediction and the trained waterlogging model, the long-term waterlogging distribution is obtained, and the waterlogging risk prediction of the power station equipment is obtained through the location, height and other information of the power station equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0078] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0079] Figure 1 It is a flow chart of an intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model provided by an embodiment of the present invention;

[0080] Figure 2 It is a flow chart of an intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model provided by an embodiment of the present invention;

[0081] Figure 3 It is a flow chart of one-dimensional fluid large model training provided by an embodiment of the present invention;

[0082] Figure 4 It is a Transformer structure diagram in the large model structure provided by an embodiment of the present invention;

[0083] Figure 5 It is a structural diagram of a large model equipped with a Transformer structure provided by an embodiment of the present invention;

[0084] Figure 6 It is a flow chart of training a large two-dimensional fluid model provided by an embodiment of the present invention;

[0085] Figure 7 is a coupling model flow chart provided by an embodiment of the present invention;

[0086] Figure 8 is a flow chart of waterlogging prediction training provided by an embodiment of the present invention;

[0087] Fig. 9 is a flow chart of waterlogging prediction provided by an embodiment of the present invention;

[0088] Fig.10 It is a block diagram of an intelligent prediction device for waterlogging disasters in power grid facilities based on a large fluid model provided by an embodiment of the present invention;

[0089] Fig.11 It is a structural schematic diagram of an intelligent prediction device for waterlogging disasters in power grid facilities provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0090] The technical solution of the present invention is described below in conjunction with the accompanying drawings.

[0091] In the embodiments of the present invention, words such as "exemplarily" and "for example" are used to indicate examples, illustrations or explanations. Any embodiment or design described as "example" in the present invention should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of the word "example" is intended to present the concept in a specific way. In addition, in the embodiments of the present invention, the meaning expressed by "and / or" can be both, or it can be either of the two.

[0092] In the embodiments of the present invention, "image" and "picture" can sometimes be used interchangeably. It should be noted that when the difference between them is not emphasized, the meanings they intend to express are the same. "of", "corresponding, relevant" and "corresponding" can sometimes be used interchangeably. It should be noted that when the difference between them is not emphasized, the meanings they intend to express are the same.

[0093] In the embodiments of the present invention, sometimes a subscript such as W1 may be written as a non-subscript such as W1. When the difference is not emphasized, the meanings to be expressed are the same.

[0094] In order to make the technical problems, technical solutions and advantages to be solved by the present invention more clear, a detailed description will be given below with reference to the accompanying drawings and specific embodiments.

[0095] The embodiment of the present invention provides a method for intelligent prediction of waterlogging disasters in power grid facilities based on a large fluid model. The method can be implemented by an intelligent prediction device for waterlogging disasters in power grid facilities. The intelligent prediction device for waterlogging disasters in power grid facilities can be a terminal or a server. Figure 1The flowchart of the intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model is shown. The processing flow of the method may include the following steps:

[0096] S1. Obtain precipitation forecast data for operational forecasts.

[0097] The present invention takes into account the continuous advancement of domestic power disaster prevention and mitigation, the continuous increase in relevant policy support from the state, global climate change, the continuous increase in social electricity consumption, the continuous increase in pressure on the power grid, and the increasing demand for early warning of disasters such as waterlogging that are likely to affect power facilities. Intelligent disaster prediction is an important development direction for the operation and maintenance of new power systems in the future.

[0098] S2. Input the precipitation prediction data into the constructed waterlogging model and output the waterlogging depth distribution.

[0099] In a feasible implementation, the precipitation forecast data of the business forecast is input into the waterlogging prediction model to obtain the corresponding waterlogging depth distribution.

[0100] Alternatively, if Figure 2 As shown, the construction process of the waterlogging model in S2 may include the following steps S21-S27:

[0101] S21. Obtain long-term series precipitation prediction sample data.

[0102] S22, inputting the precipitation prediction sample data into the one-dimensional hydrodynamic model, outputting the location of the waterlogging overflow point and the overflow volume, and constructing a training sample set of the one-dimensional hydrodynamic model based on the precipitation prediction sample data and the location of the waterlogging overflow point and the overflow volume.

[0103] In a feasible implementation, based on a one-dimensional hydrodynamic model, the long-term precipitation forecast data is used as input to calculate the location and overflow volume of the long-term flood overflow point. This step provides basic data and initial flood risk prediction for the establishment of subsequent models, forming a training sample set for the one-dimensional hydrodynamic model.

[0104] Specifically, a model framework based on one-dimensional hydrodynamics is constructed, which obtains the key locations of waterlogging and their related overflow by inputting long-term precipitation data (such as precipitation in the past few decades). It is also necessary to add a comprehensive analysis of factors such as terrain, drainage network type, and drainage pipe friction to predict the direction and concentration area of ​​water flow in the drainage network, so as to obtain overflow points and overflow volumes.

[0105] Furthermore, when constructing a one-dimensional hydrodynamic model to analyze the urban drainage system, a comprehensive approach is to use the Storm Water Management Model (SWMM). SWMM is a dynamic rainwater, runoff surface flow and pipe network flow model that provides a comprehensive platform for simulating natural rainfall processes and the response of urban drainage systems to rainfall events. The following are the key equations and concepts involved in the model:

[0106] 1. Flow continuity equation

[0107] The flow continuity equation is based on the principle of mass conservation and describes the invariance of mass in fluid flow. For any control volume, the difference between the inflow and outflow flow rates is equal to the rate of change of the fluid mass in the volume:

[0108] (1)

[0109] : The rate of change of flow over time, reflecting the flow changes caused by precipitation events.

[0110] : The flow variation of a fluid in space, taking into account the spatial gradients of cross-sectional area and flow velocity.

[0111] : The difference between the inflow and outflow of water determines the change in storage capacity.

[0112] Dynamic simulation of water flow through an urban drainage network requires the support of the momentum conservation equation:

[0113] (2)

[0114] : The variation of flow rate (and its momentum) with time, taking into account the acceleration of the water.

[0115] : The pressure change caused by the head difference is the main force driving the water flow.

[0116] : Frictional force does work, is the friction slope, which represents the loss of energy in the flow.

[0117] (3)

[0118] : The inverse of the Manning coefficient, which is related to the pipe material and surface roughness.

[0119] : Reflects the relationship between fluid contact area and hydraulic radius.

[0120] : The square root of the energy slope, which is related to the inclination of the pipeline.

[0121] Based on the input precipitation forecast, the initial conditions are first set based on the terrain and land cover data. The above formula is used in combination with the specific configuration of the drainage network (including pipe diameter, length, slope and node settings) to simulate the dynamic behavior of water flow in the entire system. The focus is on analyzing possible waterlogging areas, predicting water levels at key nodes, and the overall performance of the system under different rainfall scenarios.

[0122] Data preparation: Input detailed data on topography, land cover, drainage network structure, etc.

[0123] Model settings: Adjust SWMM model parameters according to actual conditions, including but not limited to surface permeability, pipe network layout, pipeline characteristics, etc.

[0124] The output of the model is the location and volume of overflow points, which need to be determined by simulating the movement of water in the urban drainage system under different precipitation events. By analyzing the water flow speed and water level, potential overflow points can be identified.

[0125] The long-term precipitation prediction data is input into the one-dimensional hydrodynamic model to obtain the training data set of the one-dimensional fluid model.

[0126] S23. Train the large model according to the training sample set of the one-dimensional hydrodynamic model to obtain a one-dimensional fluid large model.

[0127] In a feasible implementation, based on the large model technology, a one-dimensional fluid large model is trained through a training sample set of a one-dimensional hydrodynamic model.

[0128] Specifically, Figure 3 As shown in the figure, by inputting the training data set of the one-dimensional hydrodynamic model into the big model technology, an artificial intelligence model that can reflect the one-dimensional water flow characteristics is trained. This one-dimensional fluid big model can not only predict the overflow point and flow, but also analyze the overflow change trend under different precipitation conditions and different pipe network facilities.

[0129] Furthermore, AI big model technology is a hot topic in the current deep learning field. It uses large-scale parameters and complex network structures to process massive amounts of data to achieve efficient feature extraction and prediction. Large models usually have billions or even tens of billions of parameters, which enables the model to capture subtle patterns in the data and achieve excellent performance in various tasks.

[0130] 1. Network structure

[0131] The network structure of a large model is often very deep and complex, consisting of multiple stacked neural network modules. Take Transformer as an example. This is a large model structure widely used in the field of NLP. It is composed of multiple encoders and decoders stacked together. Each encoder and decoder contains multiple self-attention mechanisms and feed-forward neural networks.

[0132] The self-attention mechanism is a key component in the large model. It captures the dependencies of the sequence by calculating the correlations between different positions in the input sequence. Specifically, for each position in the input sequence, the self-attention mechanism calculates an attention weight vector that represents the correlation between this position and other positions. Then, these weight vectors are used to perform a weighted summation on the input sequence to obtain the contextual representation of the position.

[0133] Mathematically, the calculation process of the self-attention mechanism can be expressed as:

[0134] (4)

[0135] Among them, Q, K, and V represent query, key, and value matrices, respectively, which are usually obtained by linear transformation of the input sequence. is the dimension of the key vector, which is used to scale the dot product result to prevent the gradient from disappearing. The attention weights are normalized by the softmax function to obtain the final context representation.

[0136] The Transformer structure in the large model structure is as follows Figure 4 As shown, Figure 5 The figure shows the structure of a large model, which is a large model equipped with a Transformer structure.

[0137] 2. Network Depth and Width

[0138] In addition to complex network structures, large models also usually have deeper network depth and wider network width. Network depth refers to the number of neural network layers in the model, while network width refers to the number of neurons in each layer. Increasing network depth and width helps the model capture more complex feature representations, but it also increases computational complexity and the number of parameters.

[0139] 3. Training strategies and techniques

[0140] Due to the huge number of parameters in large models, the training process usually requires a lot of data and computing resources. In order to speed up the training process and prevent overfitting, researchers have proposed a variety of training strategies and techniques. For example, distributed training can use multiple machines to perform parallel computing to speed up training; gradient accumulation can accumulate gradients over multiple small batches before updating parameters to reduce communication overhead; regularization techniques such as dropout and weight decay can help prevent model overfitting.

[0141] Using the large model technology, the one-dimensional training data is substituted into the large model network structure for training, thereby obtaining a one-dimensional fluid large model. The one-dimensional large model simulates the flow of water in the pipe network.

[0142] S24, inputting the precipitation prediction sample data into the two-dimensional hydrodynamic model, outputting the two-dimensional water accumulation depth distribution, and constructing a training sample set of the two-dimensional hydrodynamic model according to the precipitation prediction sample data and the two-dimensional water accumulation depth distribution.

[0143] In a feasible implementation, based on the two-dimensional hydrodynamic model, the long-term precipitation forecast data is used as input to calculate the two-dimensional water depth distribution of the long-term series. This step further refines the flood risk prediction, provides more detailed spatial distribution information, and forms a training sample set for the two-dimensional hydrodynamic model.

[0144] Specifically, a framework based on a two-dimensional hydrodynamic model is constructed to obtain a prediction of the water depth distribution in a two-dimensional plane. It is necessary to consider the influence of urban blocks, building distribution, roads, parks, soil conditions, etc., as well as precipitation, and evaluate the direction and speed of water flow.

[0145] 1. Hydrodynamic model selection

[0146] Select a two-dimensional hydrodynamic model suitable for urban drainage system analysis to describe the water flow dynamics in the urban area. The two-dimensional hydrodynamic model should be able to simulate the water flow movement in the urban area more accurately.

[0147] 2. Equation description

[0148] Considering the planar nature of the urban area, the present invention will use a two-dimensional hydrodynamic equation to describe the movement of water flow. The two-dimensional hydrodynamic equation combines the continuity equation and the momentum conservation equation to describe the flow of water on a two-dimensional plane. Its mathematical expression is as follows:

[0149] (5)

[0150] in, represents the cross-sectional area of ​​water flow, and Respectively indicate that the water flow and Speed ​​in direction, and Represents the amount of water flowing in and out, respectively.

[0151] 3. Meshing and boundary conditions

[0152] The urban area is divided into grid cells of appropriate size, and the initial conditions and boundary conditions of each grid cell are determined. The initial conditions include the water depth distribution at the beginning of precipitation, and the boundary conditions include the water inflow and outflow at the city boundary.

[0153] 4. Parameter setting and simulation operation

[0154] Set various parameters, such as terrain elevation, building height, soil type, pipe drainage capacity, etc. Perform numerical calculations through simulation programs to obtain the distribution of water depth in urban areas under different precipitation conditions.

[0155] Through the above steps, a framework based on a two-dimensional hydrodynamic model is established to accurately predict the two-dimensional surface water depth distribution in urban areas. Based on the long-term precipitation data, a two-dimensional water distribution data set is generated as a training sample for the two-dimensional fluid model.

[0156] S25. Train the large model according to the training sample set of the two-dimensional hydrodynamic model to obtain a two-dimensional fluid large model.

[0157] In a feasible implementation, based on the large model technology, a two-dimensional fluid large model is trained through a training sample set of a two-dimensional hydrodynamic model. The two-dimensional large model simulates the flow of surface water.

[0158] Specifically, Figure 6 As shown in Figure 1, the data from the 2D hydrodynamic model is used to train a 2D fluid model. This model can simulate the process and distribution of water accumulation in detail, provide dynamic changes in flood risk in the spatial dimension, and assess the pressure on the urban drainage system.

[0159] Firstly, the present invention uses precipitation data and one-dimensional and two-dimensional hydrodynamic equations to supplement the long-time series data samples of waterlogging overflow points, overflow volume, and two-dimensional water accumulation distribution, so as to make up for the short time series of real waterlogging monitoring data. Secondly, the large model technology is used to train based on data samples to obtain a large fluid model related to waterlogging, which makes up for the problem that the calculation accuracy and calculation time of the traditional waterlogging prediction model are mutually exclusive. This will improve the spatiotemporal resolution and accuracy of waterlogging forecasts, and provide necessary data support for subsequent disaster prevention and mitigation of key power grid facilities. It can improve the problem of insufficient training samples for waterlogging predictions.

[0160] S26. Couple the one-dimensional fluid large model and the two-dimensional fluid large model to obtain an urban waterlogging coupling model.

[0161] In one possible implementation, one-dimensional and two-dimensional fluid models are efficiently coupled through technical means to create a comprehensive flood prediction model that can simultaneously consider the location of overflow points and the distribution of water depth. This coupled model provides a comprehensive perspective for understanding flood risks.

[0162] The present invention adopts large model coupling technology to couple a one-dimensional fluid large model with a two-dimensional fluid large model, and simultaneously considers the flow of accumulated water in the pipe network and the distribution of accumulated water on the surface, so as to obtain a model with accurate extrapolation prediction of the distribution of urban waterlogging. The advantages of the large model are utilized to solve the problems of the traditional coupling model and improve the timeliness of the prediction.

[0163] Urban drainage mainly refers to the runoff generated by rainfall on the surface through infiltration, evaporation and depression storage loss. It enters the underground pipe network through the node where the pipe network connects to the surface through the surface confluence, and the pipe network finally discharges into the urban water body, or part of the runoff converges into the combined rainwater and sewage pipe and enters the sewage treatment plant. If the rainfall intensity is too high, the pipe network is overloaded, and the drainage capacity is insufficient, the water in the pipe network will overflow to the surface through the pipe network node connected to the surface, forming surface waterlogging or even waterlogging disasters; after the rainfall ends, the drainage pressure of the pipe network gradually decreases, and the surface water around the pipe network node can re-enter the pipe network and finally be discharged into the urban water body. However, there is no way to automatically eliminate the waterlogging in low-lying areas without pipe network nodes, and serious cases require manual active drainage. It can be seen from this that the process of urban surface runoff and pipe network drainage is quite complicated, involving surface runoff generation and confluence, pipe network drainage, and water exchange between the surface and the pipe network.

[0164] The two-dimensional fluid model can accurately calculate the physical process of surface runoff by inputting high-precision surface terrain data, land use type, and corresponding infiltration values ​​and Manning values; it can calculate the rainfall runoff process with different flow directions and complex terrain, but it requires high-precision terrain data, and the calculation efficiency is low and the calculation process is complicated. For the calculation of the one-dimensional fluid model, since its flow direction is relatively single and has obvious one-dimensional flow properties; therefore, the one-dimensional model is selected for the pipe network drainage process, which can not only meet the calculation accuracy requirements, but also has great advantages in calculation efficiency and basic data of pipe network modeling. According to the previous description, the runoff process of the two-dimensional fluid model is actually based on the dynamic wave method to solve the complete two-dimensional Saint-Venant equation, with high simulation accuracy; the one-dimensional fluid model also learns the calculation of the dynamic wave method, which not only ensures accuracy, but also has high efficiency.

[0165] The coupling of the waterlogging model mainly needs to solve the water interaction problem between the two-dimensional surface model and the one-dimensional pipe network model, that is, the coupling of the one-dimensional fluid model and the two-dimensional fluid model; in the model, the pipe network node connects the two-dimensional surface with the one-dimensional pipe network, and is the only channel for the water interaction between the two. Usually, in the actual water interaction between the surface and the pipe network, there are three situations. One is that the drainage capacity of the pipe network is insufficient, overload occurs, and the water in the pipe network overflows to the surface through the pipe network node; another situation is that the drainage capacity of the pipe network is sufficient, there is no overload, and the surface water enters the pipe network through the node; the last situation is that there is no water on the surface, and there is no water in the pipe network node or there is water in the pipe network node but the water depth does not exceed the surface elevation. At this time, there is no water interaction between the surface and the pipe network. However, in the actual simulation calculation, according to the relationship between the node head elevation, the surface water surface elevation and the surface elevation, there are four different calculation situations. Assume that the surface elevation is Z, the surface grid water level is Z2D, and the node water level is Z1D. Case 1: When the node water level Z1D is less than the surface grid water level Z2D, the surface water enters the pipe network system through the node, that is, the water in the surface two-dimensional model enters the pipe network one-dimensional model. Case 2: When the node water level Z1D is greater than the surface elevation Z but less than the surface grid water level Z2D, the surface water enters the pipe network under the action of the water head, that is, the water in the surface two-dimensional model enters the pipe network one-dimensional model. Case 3: When the node water level Z1D is greater than the surface grid water level Z2D, the water in the pipe network system overflows into the surface; that is, the water in the pipe network one-dimensional model enters the surface two-dimensional model. Case 4: When the surface grid water level Z2D is equal to the surface elevation Z, that is, there is no water on the surface, the pipe network node water level Z1D is less than the ground elevation Z or there is no water at the pipe network node, at this time, there is no water interaction between the pipe network system and the surface, that is, there is no water interaction between the two-dimensional model and the one-dimensional model of the pipe network. In case 4, no water interaction occurs during calculation, so the coupling model mainly considers the first three cases for the water interaction between the surface and the pipe network. When the grid water level Z2D of the surface two-dimensional model is greater than the corresponding node water level Z1D of the pipe network one-dimensional model, the runoff generated by rainfall in the surface two-dimensional model enters the urban underground pipe network system through the pipe network node, and node inflow occurs; when the pipe network drainage capacity is insufficient and overload occurs, the water in the pipe network system overflows to the surface water through the pipe network node, and returns to the pipe network system after the pipe network drainage capacity is restored, and node backflow occurs.

[0166] S27. Obtain waterlogging monitoring data, train a waterlogging coupling model based on the precipitation prediction sample data and the waterlogging monitoring data, and obtain a constructed waterlogging model.

[0167] In a feasible implementation, precipitation prediction data and waterlogging monitoring data are used as samples to perform incremental learning on the waterlogging coupling model, thereby correcting the parameters of the waterlogging coupling model to obtain an accurate waterlogging prediction model.

[0168] Optionally, in S27, training the waterlogging coupling model according to the precipitation prediction sample data and the waterlogging waterlogging monitoring data to obtain the constructed waterlogging model may include the following steps S271-S278:

[0169] S271. Obtaining precipitation forecast sample data at any time Sample data of precipitation forecast.

[0170] S272, the time The precipitation prediction sample data is input into the one-dimensional fluid model to obtain the time The location and overflow volume of the flood overflow point.

[0171] S273, the time The overflow point position and overflow volume of the flooding are input into the two-dimensional fluid model to obtain the time Two-dimensional water depth distribution.

[0172] S274. Obtaining the precipitation forecast sample data at the time Sample data of precipitation forecast.

[0173] S275, the moment The precipitation prediction sample data is input into the one-dimensional fluid model to obtain the time The location and overflow volume of the flood overflow point.

[0174] S276, time The two-dimensional water depth distribution and time The overflow point position and overflow volume of the flooding are input into the two-dimensional fluid model to obtain the time Two-dimensional water depth distribution.

[0175] S277, according to the time The two-dimensional water depth distribution and time The two-dimensional water depth distribution is used to obtain the water distribution prediction result.

[0176] S278. Train the waterlogging coupling model based on the waterlogging monitoring data and waterlogging distribution prediction results to obtain a constructed waterlogging model.

[0177] like Figure 7 As can be seen from the flowchart, the model decomposes the long-term precipitation sequence, and performs a one-dimensional process and a two-dimensional process at each step, converting the pipe network flow and the two-dimensional surface flow on the entire timeline into a one-dimensional and two-dimensional alternating coupled flow. In this way, two large fluid models are coupled, avoiding the complexity and low computational efficiency of the coupling of ordinary physical models.

[0178] Optionally, the step of training the waterlogging coupling model according to the precipitation prediction sample data and the waterlogging monitoring data to obtain the constructed waterlogging model in S27 further includes:

[0179] Based on the precipitation prediction sample data and the waterlogging monitoring data, the waterlogging coupling model is incrementally learned to optimize and correct the key parameters in the waterlogging coupling model to obtain a constructed waterlogging model.

[0180] In a feasible implementation, Figure 8 As shown in the figure, the coupled model is incrementally learned using actual precipitation forecast data and on-site monitored waterlogging data, and the key parameters in the model are continuously optimized and corrected. This process ensures that the forecast model can adapt to the changing meteorological conditions and urban environment, improves the accuracy of waterlogging forecasts, and ensures the rational use of a small amount of real observation data.

[0181] Incremental learning is a machine learning method that allows a model to gradually learn from new data without having to be retrained from scratch. This is particularly important for flood prediction models, as meteorological conditions and urban environments are constantly changing and real-time waterlogging monitoring data is relatively limited.

[0182] The present invention uses an incremental learning method to optimize and calibrate the trained waterlogging model, so that it can be continuously adjusted according to new precipitation forecast data and on-site monitored waterlogging data to improve the accuracy of the prediction. Incremental learning is particularly suitable for situations where the amount of data gradually increases, especially when new observation data becomes available, and the model can be updated without retraining the entire model.

[0183] Incremental learning methods are used to optimize and calibrate the trained waterlogging model so that it can be continuously adjusted according to new precipitation forecast data and on-site monitored waterlogging data to improve the accuracy of the prediction. Incremental learning is particularly suitable for situations where the amount of data gradually increases, especially when new observational data becomes available, and the model can be updated without retraining the entire model.

[0184] First, define the weight before model update as , the weight updated by incremental learning is The goal of model updating is to minimize the loss of new data on model predictions. The loss function can be defined as the observed water depth Prediction of water depth with model The difference between , for example using the mean squared error (MSE):

[0185] (6)

[0186] in, is the number of newly acquired observations, The model is based on weights For The predicted value of the observed data point, are the corresponding actual observed values.

[0187] The key to incremental learning is how to update weights based on new data This can be done using gradient descent or its variants, and the update rule can be expressed as:

[0188] (7)

[0189] in, is the learning rate, which determines the step size of the weight update; is the loss function About weight The gradient of , indicates the direction in which the loss is minimized.

[0190] (8)

[0191] in, is the regularization coefficient, which controls the strength of the regularization term; Represents the L2 norm of the weight vector.

[0192] In this way, whenever new precipitation forecast data and field-monitored waterlogging data become available, the above process can be applied to fine-tune the model, ensuring that the model can continuously adapt to changing meteorological conditions and urban environments. This not only improves the accuracy of waterlogging predictions, but also ensures that these data can be fully utilized even when real observation data are scarce.

[0193] In practical applications, it may be necessary to consider regularization terms to prevent overfitting, especially when the amount of data is small. For example, L2 regularization can be introduced.

[0194] The present invention applies the incremental learning method, using a small amount of real waterlogging observation data and precipitation forecast data to form true value sample pairs, to optimize and improve the trained waterlogging coupling model, thereby also giving play to the advantages of a large model, and still being able to simulate the real physical mechanism when the sample size is small. This process ensures that the prediction model can adapt to the ever-changing meteorological conditions and urban environment, improves the accuracy of waterlogging prediction, and ensures the rational use of a small amount of real observation data.

[0195] Optionally, in the waterlogging model, the one-dimensional fluid large model and the two-dimensional fluid large model are connected through a pipe network node.

[0196] like Fig. 9As shown in the figure, by inputting operational precipitation forecast data into the waterlogging prediction model, the model can quickly generate a prediction map of waterlogging depth, providing scientific guidance for disaster prevention and mitigation plans for key power grid facilities.

[0197] Establish an efficient data interface to ensure the real-time acquisition of the latest operational precipitation forecast data. These data include information such as expected precipitation, precipitation intensity, and precipitation duration, which are the basis for waterlogging risk prediction. The data interface needs to support multiple meteorological data formats and sources to ensure the timeliness and accuracy of the data.

[0198] The received precipitation forecast data is preprocessed, including data cleaning, format conversion and standardization, to adapt to the input requirements of the waterlogging prediction model. The spatial resolution and temporal resolution of the data must also be considered during the preprocessing process to ensure that it can reflect the actual precipitation conditions in the specific prediction area.

[0199] The pre-processed precipitation forecast data is input into the trained waterlogging prediction model. This model is based on advanced hydrological principles and hydrodynamic simulation technology, and can comprehensively consider factors such as topography, land use type, and urban drainage system to simulate surface runoff and waterlogging caused by precipitation. The result of the model operation is a detailed waterlogging depth prediction map, which shows the distribution of waterlogging in the areas surrounding key power grid facilities under different precipitation scenarios.

[0200] S3. Obtain parameter data of key power grid facilities.

[0201] S4. Based on the waterlogging depth distribution and parameter data of key grid facilities, the waterlogging disaster prediction results of key grid facilities are obtained.

[0202] In a feasible implementation, the flooding risk level faced by each facility is assessed based on the distribution of waterlogging depth output by the flooding prediction model, combined with the hardware information, equipment location and height of power grid-related facilities. This step provides targeted disaster prevention suggestions and measures for power grid operation and maintenance and emergency management.

[0203] Based on the waterlogging depth distribution data provided by the waterlogging prediction model, the system will conduct a detailed assessment of the waterlogging risk of each key facility in the power grid. This assessment process takes into account multiple factors such as the facility's geographical location, terrain characteristics, surrounding environmental conditions, historical waterlogging experience, and the equipment's flood resistance capabilities to ensure the comprehensiveness and accuracy of the assessment results.

[0204] By using GIS (geographic information system) technology, the location information of key power grid facilities is combined with the output of the waterlogging prediction model to visualize the facilities that may be threatened by waterlogging and their risk levels, helping decision makers to intuitively understand the risk distribution and facilitating the rapid identification of high-risk areas and facilities so that disaster prevention resources can be deployed in a prioritized manner.

[0205] Develop corresponding disaster prevention and mitigation measures for facilities with different risk levels. For high-risk facilities, emergency protection measures may need to be taken, such as reinforcing flood walls and installing temporary drainage pumps. At the same time, conduct detailed safety inspections on these facilities to ensure that all key systems and equipment are in optimal condition before the flood arrives. For facilities with medium and low risk levels, focus on monitoring and early warning to ensure rapid response if the situation deteriorates. Develop an emergency response plan to clarify various emergency measures, division of responsibilities, material allocation and information communication channels when waterlogging occurs. Through simulation exercises, improve the familiarity and execution capabilities of power grid operation and maintenance personnel with emergency plans.

[0206] Based on the results of urban flood risk assessments, disaster prevention and mitigation strategies for key power grid facilities are regularly updated, including long-term measures such as strengthening the flood control capabilities of facility hardware, optimizing drainage system design, and improving surrounding topography, in order to improve the overall resilience of the power grid and its ability to resist urban flood disasters.

[0207] Through the above steps, the present invention not only significantly improves the accuracy and efficiency of urban flood disaster prediction, but also provides strong data support and scientific guidance for disaster protection of power grid facilities, which helps to ensure the safe and stable operation of the power grid and reduce the losses caused by natural disasters.

[0208] The present invention applies a large model to the prediction field of the power industry. First, based on a one-dimensional hydrodynamic model, the precipitation prediction data is used as input to obtain the location of the waterlogging overflow point and the overflow volume. Then, based on a two-dimensional hydrodynamic model, the precipitation prediction data is used as input to obtain the two-dimensional water accumulation depth distribution. Using the precipitation prediction data of a long time series, the one-dimensional hydrodynamic model is used to obtain the location of the waterlogging overflow point and the overflow volume of the long time series, and a sample set of the long time series is formed. The sample set is used to train the large model to obtain a one-dimensional fluid large model. Using the precipitation prediction data of a long time series, the two-dimensional water accumulation distribution of the long time series is obtained through a two-dimensional hydrodynamic model to form a sample set of the long time series. The sample set is used to train the large model to obtain a two-dimensional fluid large model. Through the one-dimensional-two-dimensional coupling of two fluid large models, a waterlogging coupling model is obtained. Using the precipitation prediction data and the waterlogging water monitoring data as samples, the waterlogging coupling model is incrementally learned, and the model parameters in the coupling model are corrected to obtain the final waterlogging model. Finally, by using the real operational forecast precipitation data as input, the waterlogging model can output the corresponding waterlogging depth distribution. Combined with the hardware information, equipment location and height of power grid-related facilities, the waterlogging disaster prediction of key power grid equipment and facilities can be obtained.

[0209] In the embodiment of the present invention, based on a one-dimensional hydrodynamic model and a two-dimensional hydrodynamic model, long-term precipitation prediction data is used as input to obtain a long-term output of waterlogging, thereby solving the problem of insufficient prediction training samples for the hydrodynamic model AI. Through the AI ​​large model technology, the one-dimensional hydrodynamic model and the two-dimensional hydrodynamic model are replicated to solve the problem of the mutual exclusion between the operation speed and calculation accuracy of the traditional physical model, achieving high precision and high speed; the two large models are coupled online to simulate the coupling of the physical model, solving the difficult and complex problem of physical coupling and reducing the complexity of the coupling model; using precipitation predictions and real waterlogging monitoring data as samples, the large model is incrementally trained to solve the problem of small amount of true waterlogging data, small number of samples, and inability to support training; finally, combined with the long-term business precipitation prediction and the trained waterlogging model, the long-term distribution of waterlogging is obtained, and the waterlogging risk prediction of the power station equipment is obtained through the location, height and other information of the power station equipment.

[0210] Fig.10 The block diagram of a device for intelligently predicting waterlogging disasters in power grid facilities based on a large fluid model according to an exemplary embodiment is shown. The device is used in an intelligent method for predicting waterlogging disasters in power grid facilities based on a large fluid model. Fig.10 The device includes a first acquisition module 310, an input module 320, a second acquisition module 330 and an output module 340. Wherein:

[0211] The first acquisition module 310 is used to acquire precipitation prediction data for operational forecasting.

[0212] The input module 320 is used to input the precipitation prediction data into the constructed waterlogging model and output the waterlogging depth distribution.

[0213] The second acquisition module 330 is used to acquire data of key facilities of the power grid.

[0214] The output module 340 is used to obtain the prediction results of waterlogging disasters of key power grid facilities based on the distribution of waterlogging depth and the data of key power grid facilities.

[0215] In the embodiment of the present invention, based on a one-dimensional hydrodynamic model and a two-dimensional hydrodynamic model, a long-term precipitation prediction data is used as input to obtain a long-term waterlogging output, thereby solving the problem of insufficient prediction training samples for the hydrodynamic model AI. Through the AI ​​large model technology, the one-dimensional hydrodynamic model and the two-dimensional hydrodynamic model are replicated to solve the problem that the operation speed and calculation accuracy of the traditional physical model are mutually exclusive, and high precision and high speed are achieved; the two large models are coupled online to simulate the coupling of the physical model, which solves the problem of the difficulty and complexity of physical coupling and reduces the complexity of the coupling model; the precipitation prediction and the real waterlogging monitoring data are used as samples to perform incremental learning training on the large model, solving the problem of small amount of true waterlogging data, small number of samples, and inability to support training; finally, combined with the long-term business precipitation prediction and the trained waterlogging model, the long-term waterlogging distribution is obtained, and the waterlogging risk prediction of the power station equipment is obtained through the location, height and other information of the power station equipment.

[0216] Fig.11 is a schematic diagram of a structure of an intelligent prediction device for waterlogging disasters in power grid facilities provided by an embodiment of the present invention. Fig.11 As shown, the intelligent prediction equipment for waterlogging disasters in power grid facilities may include the above Fig.10 The power grid facility waterlogging disaster intelligent prediction device based on the fluid large model is shown. Optionally, the power grid facility waterlogging disaster intelligent prediction device 410 may include a first processor 2001.

[0217] Optionally, the intelligent prediction device 410 for waterlogging disasters in power grid facilities may also include a memory 2002 and a transceiver 2003 .

[0218] The first processor 2001, the memory 2002 and the transceiver 2003 may be connected via a communication bus.

[0219] Combine the following Fig.11 The components of the intelligent prediction device 410 for waterlogging disasters in power grid facilities are specifically introduced:

[0220] The first processor 2001 is the control center of the intelligent prediction device 410 for waterlogging disasters in power grid facilities, and can be a processor or a general term for multiple processing elements. For example, the first processor 2001 is one or more central processing units (CPUs), or an application specific integrated circuit (ASIC), or one or more integrated circuits configured to implement the embodiments of the present invention, such as one or more microprocessors (digital signal processors, DSPs), or one or more field programmable gate arrays (FPGAs).

[0221] Optionally, the first processor 2001 can perform various functions of the power grid facility waterlogging disaster intelligent prediction device 410 by running or executing a software program stored in the memory 2002 and calling data stored in the memory 2002.

[0222] In a specific implementation, as an embodiment, the first processor 2001 may include one or more CPUs, such as Fig.11 CPU0 and CPU1 are shown in FIG.

[0223] In a specific implementation, as an embodiment, the intelligent prediction device 410 for waterlogging disasters in power grid facilities may also include multiple processors, such as Fig.11 The first processor 2001 and the second processor 2004 are shown in FIG. Each of these processors may be a single-core processor (single-CPU) or a multi-core processor (multi-CPU). The processor here may refer to one or more devices, circuits, and / or processing cores for processing data (e.g., computer program instructions).

[0224] The memory 2002 is used to store the software program for executing the solution of the present invention, and is controlled to be executed by the first processor 2001. The specific implementation method can refer to the above method embodiment, which will not be repeated here.

[0225] Optionally, the memory 2002 may be a read-only memory (ROM) or other types of static storage devices that can store static information and instructions, a random access memory (RAM) or other types of dynamic storage devices that can store information and instructions, or an electrically erasable programmable read-only memory (EEPROM), a compact disc read-only memory (CD-ROM) or other optical disc storage, optical disc storage (including compressed optical disc, laser disc, optical disc, digital versatile disc, Blu-ray disc, etc.), a magnetic disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited thereto. The memory 2002 may be integrated with the first processor 2001, or may exist independently, and may be connected to the first processor 2001 through the interface circuit ( Fig.11 (not shown) is coupled to the first processor 2001, which is not specifically limited in this embodiment of the present invention.

[0226] The transceiver 2003 is used to communicate with a network device or a terminal device.

[0227] Optionally, the transceiver 2003 may include a receiver and a transmitter ( Fig.11 The receiver is used to implement a receiving function, and the transmitter is used to implement a sending function.

[0228] Optionally, the transceiver 2003 may be integrated with the first processor 2001, or may exist independently, and communicate with the first processor 2001 through the interface circuit ( Fig.11 (not shown) is coupled to the first processor 2001, which is not specifically limited in this embodiment of the present invention.

[0229] It should be noted that Fig.11 The structure of the power grid facility waterlogging disaster intelligent prediction device 410 shown in the figure does not constitute a limitation on the router, and the actual knowledge structure identification device may include more or fewer components than shown in the figure, or combine certain components, or arrange the components differently.

[0230] In addition, the technical effects of the intelligent prediction device 410 for waterlogging disasters in power grid facilities can refer to the technical effects of the intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model described in the above method embodiment, and will not be repeated here.

[0231] It should be understood that the first processor 2001 in the embodiment of the present invention may be a central processing unit (CPU), and the processor may also be other general-purpose processors, digital signal processors (DSP), application specific integrated circuits (ASIC), field programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc.

[0232] It should also be understood that the memory in the embodiments of the present invention may be a volatile memory or a non-volatile memory, or may include both volatile and non-volatile memories. Among them, the non-volatile memory may be a read-only memory (ROM), a programmable read-only memory (PROM), an erasable programmable read-only memory (EPROM), an electrically erasable programmable read-only memory (EEPROM), or a flash memory. The volatile memory may be a random access memory (RAM), which is used as an external cache. By way of example and not limitation, many forms of random access memory (RAM) are available, such as static RAM (SRAM), dynamic random access memory (DRAM), synchronous DRAM (SDRAM), double data rate synchronous dynamic random access memory (DDR SDRAM), enhanced synchronous dynamic random access memory (ESDRAM), synchronous link DRAM (SLDRAM), and direct rambus RAM (DR RAM).

[0233] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.

[0234] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the above-described equipment, devices and units can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0235] In the several embodiments provided by the present invention, it should be understood that the disclosed devices, apparatuses and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another device, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.

[0236] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0237] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.

[0238] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for enabling a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the methods described in various embodiments of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk, and other media that can store program codes.

[0239] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. An intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model, characterized in that: The method comprises: S1. Obtaining precipitation forecast data for operational forecast; S2, inputting the precipitation prediction data into the constructed waterlogging model, and outputting the waterlogging depth distribution; S3, obtaining parameter data of key facilities of the power grid; S4. Obtain waterlogging disaster prediction results for key power grid facilities based on the waterlogging depth distribution and parameter data of key power grid facilities.

2. The intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model according to claim 1 is characterized in that: The construction process of the waterlogging model in S2 includes: S21. Obtaining long-term series precipitation forecast sample data; S22, inputting the precipitation prediction sample data into a one-dimensional hydrodynamic model, outputting the location of the waterlogging overflow point and the overflow amount, and constructing a training sample set of the one-dimensional hydrodynamic model based on the precipitation prediction sample data and the location of the waterlogging overflow point and the overflow amount; S23, training a large model according to the training sample set of the one-dimensional hydrodynamic model to obtain a one-dimensional fluid large model; S24, inputting the precipitation prediction sample data into a two-dimensional hydrodynamic model, outputting a two-dimensional water accumulation depth distribution, and constructing a training sample set of the two-dimensional hydrodynamic model according to the precipitation prediction sample data and the two-dimensional water accumulation depth distribution; S25, training a large model according to the training sample set of the two-dimensional hydrodynamic model to obtain a two-dimensional fluid large model; S26, coupling the one-dimensional fluid large model and the two-dimensional fluid large model to obtain a waterlogging coupling model; S27, obtaining waterlogging monitoring data, and training the waterlogging coupling model according to the precipitation prediction sample data and the waterlogging monitoring data to obtain a constructed waterlogging model.

3. The intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model according to claim 2 is characterized in that: The step S27 of training the waterlogging coupling model according to the precipitation prediction sample data and the waterlogging monitoring data to obtain a constructed waterlogging model includes: S271. Obtaining precipitation forecast sample data at any time Sample data of precipitation forecast; S272, the time The precipitation prediction sample data is input into the one-dimensional fluid model to obtain the time The location and amount of waterlogging overflow points; S273, the time The location of the flood overflow point and the overflow volume are input into the two-dimensional fluid model to obtain the time 2D water depth distribution; S274. Obtaining the precipitation forecast sample data at the time Sample data of precipitation forecast; S275, the time The precipitation prediction sample data is input into the one-dimensional fluid model to obtain the time The location and amount of waterlogging overflow points; S276, the time The two-dimensional water depth distribution and time The location of the flood overflow point and the overflow volume are input into the two-dimensional fluid model to obtain the time 2D water depth distribution; S277, according to the time The two-dimensional water depth distribution and time The two-dimensional water depth distribution is used to obtain the water distribution prediction result; S278. Train the waterlogging coupling model according to the waterlogging monitoring data and waterlogging distribution prediction results to obtain a constructed waterlogging model.

4. The intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model according to claim 2 is characterized in that: The step S27 of training the waterlogging coupling model according to the precipitation prediction sample data and the waterlogging monitoring data to obtain a constructed waterlogging model further includes: The waterlogging coupling model is incrementally learned according to the precipitation prediction sample data and the waterlogging waterlogging monitoring data, and the key parameters in the waterlogging coupling model are optimized and corrected to obtain a constructed waterlogging model.

5. The intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model according to claim 2 is characterized in that: The loss function of the waterlogging model is shown in the following formula (1): (1) In the formula, represents the loss function of the waterlogging model, Indicates the number of newly acquired waterlogging monitoring data. Indicates that the waterlogging model is based on the weight For The predicted value of each waterlogging monitoring data point, Indicates The actual observation value of each waterlogging monitoring data point.

6. The intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model according to claim 2 is characterized in that: In the waterlogging model, the one-dimensional fluid large model is connected to the two-dimensional fluid large model through a pipe network node.

7. An intelligent prediction device for waterlogging disasters in power grid facilities based on a large fluid model, the intelligent prediction device for waterlogging disasters in power grid facilities based on a large fluid model is used to implement the intelligent prediction method for waterlogging disasters in power grid facilities based on a large fluid model as claimed in any one of claims 1 to 6, characterized in that: The device comprises: The first acquisition module is used to obtain precipitation forecast data for operational forecast; An input module, used to input the precipitation prediction data into the constructed waterlogging model and output the waterlogging depth distribution; The second acquisition module is used to acquire data of key facilities of the power grid; The output module is used to obtain the waterlogging disaster prediction results of the key facilities of the power grid according to the waterlogging depth distribution and the data of the key facilities of the power grid.

8. The intelligent prediction device for waterlogging disasters in power grid facilities based on a large fluid model according to claim 7 is characterized in that: The construction process of the waterlogging model includes: S21. Obtaining long-term series precipitation forecast sample data; S22, inputting the precipitation prediction sample data into a one-dimensional hydrodynamic model, outputting the location of the waterlogging overflow point and the overflow amount, and constructing a training sample set of the one-dimensional hydrodynamic model based on the precipitation prediction sample data and the location of the waterlogging overflow point and the overflow amount; S23, training a large model according to the training sample set of the one-dimensional hydrodynamic model to obtain a one-dimensional fluid large model; S24, inputting the precipitation prediction sample data into a two-dimensional hydrodynamic model, outputting a two-dimensional water accumulation depth distribution, and constructing a training sample set of the two-dimensional hydrodynamic model according to the precipitation prediction sample data and the two-dimensional water accumulation depth distribution; S25, training a large model according to the training sample set of the two-dimensional hydrodynamic model to obtain a two-dimensional fluid large model; S26, coupling the one-dimensional fluid large model and the two-dimensional fluid large model to obtain a waterlogging coupling model; S27, obtaining waterlogging monitoring data, and training the waterlogging coupling model according to the precipitation prediction sample data and the waterlogging monitoring data to obtain a constructed waterlogging model.

9. An intelligent prediction device for waterlogging disasters in power grid facilities, characterized in that: The intelligent prediction equipment for waterlogging disasters in power grid facilities includes: processor; A memory having computer-readable instructions stored thereon, wherein when the computer-readable instructions are executed by the processor, the method according to any one of claims 1 to 6 is implemented.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores program codes, which can be called by a processor to execute the method according to any one of claims 1 to 6.

Citation Information

Cited By

  • Flood early warning information acquisition method and system based on geographic information

    CN119169218A

  • SWMM simulation model approximation method based on sparse attention and physical embedding

    CN119416667A

  • Method and device for generating flood risk map and nonvolatile storage medium

    CN119600781A

  • Real-time calculation and visualization method and device for SWMM model

    CN119903487A

  • Waterlogging prediction method based on behavior thermodynamic diagram and infiltration dynamic modeling

    CN120354750A