A device for edge cable pulling and fixing suspension and a method of using the same

By using a device for pulling and fixing cables at the edge, using pulleys to reduce friction, and supporting rods to fix and raise the cables, the problems of cable sheath damage and channel occupancy are solved, achieving cable protection and improving construction efficiency.

CN118744782BActive Publication Date: 2025-10-24HUDONG ZHONGHUA SHIPBUILDINGGROUP +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410838090.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2025-10-24
Estimated Expiration
2044-06-26

AI Technical Summary

Technical Problem

During ship outfitting construction, cables rub against the right angles of the outer plate at the top, causing damage to the outer skin. The friction between the cables and the outer plate of the hull damages the paint, and the lack of fixed lifting points occupies the deck passage, affecting the passage efficiency of construction personnel and equipment.

Method used

A device for laying and fixing cables on the edge is used, which includes a main body and a support rod. The pulley is used to reduce friction. The support rod fixes the cable and raises it to provide a stable point, avoiding direct contact between the cable and the outer plate, and ensuring smooth passage.

Benefits of technology

Effectively protect the cable sheath, prevent paint damage, keep the channel unobstructed, improve construction efficiency and reduce costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118744782B_ABST
    Figure CN118744782B_ABST
Patent Text Reader

Abstract

The application discloses a device for edge cable laying and fixing suspension and a using method thereof, and the device comprises a body and a supporting rod, the supporting rod is detachably fixed on the body through a blind hole and a bolt, a pulley is fixed on the front top of the body through a transverse shaft, and a vertical long plate and a vertical cross plate which are arranged in parallel on the back of the body are clamped and fixed at the edge of a ship outer plate through a bolt fastener; in the method, the laying efficiency is improved through the pulley, the cable is fixed and lifted through the supporting rod, the problem that the personnel walking channel is blocked in the process that the ship side cable is loaded on the ship is solved, the safety is improved, meanwhile, the problem that the cable damages the ship outer plate paint and the cable itself in the laying and using process is solved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application belongs to the technical field of shipbuilding, and particularly relates to a device for edge cable laying and fixed suspension and a use method thereof. BACKGROUND

[0002] A large number of cables need to be laid on the ship through the edge of the ship's outer plate during outfitting construction, but due to the continuous adjustment of the ship's berth, the outer plate painting operation and other construction links, the cable path needs to be frequently moved. At present, there are the following three problems in laying the cable:

[0003] 1. Cable outer skin damage problem: During the laying process, the cable rubs at the right angle of the outer plate top steel plate, and due to the sharp edge of the right angle part of the outer plate top steel plate, the cable outer skin is easily damaged, resulting in damage to the cable outer skin during the laying process.

[0004] 2. Outer plate paint damage problem: Due to the high freeboard of the ship, the laid cable is difficult to fix in the middle, so the cable laid along the outer plate of the ship is blown by the wind, thereby rubbing against the outer plate of the ship body, damaging the outer plate paint and affecting the appearance and corrosion resistance of the ship.

[0005] 3. Deck passage obstruction problem: Due to the lack of fixed lifting points on the ship's side, if a railing is used as a lifting point, the disordered cable will occupy the deck passage, affecting the smoothness of the passage, and thus affecting the passing efficiency of the construction personnel and equipment at the deck passage and increasing the moving risk.

[0006] Therefore, there is an urgent need for a device and method to solve the problem of blocking the personnel walking passage during the process of laying the cable on the ship and the problem of damaging the outer plate paint of the ship and the cable itself during the laying and use of the cable. SUMMARY

[0007] In order to solve the above-mentioned problems existing in the prior art, the purpose of the present application is to provide a device for edge cable laying and fixed suspension and a use method thereof, which is beneficial to the laying and protection of the cable by using the device. The device is suitable for the laying and protection of light cables, including but not limited to paint spray gun belts, oxyacetylene belts or water pipe oil pipes. At the same time, by arranging a plurality of the devices along the outer plate, the device can also be suitable for the laying of heavy cables, including but not limited to shore power cables.

[0008] In order to achieve the above-mentioned purposes and other related purposes, the present application adopts the following technical solutions:

[0009] The present application provides a device for edge cable laying and fixed suspension and a use method thereof, comprising the following steps:

[0010] S1, prepare a device for the edge cable laying and fixed suspension device:

[0011] The device comprises a body and a support rod, which is detachably fixed to the body;

[0012] The body comprises a main structure, a pulley, a vertical long plate and a vertical short plate, the main structure comprises a left side plate and a right side plate which are parallel to each other, the pulley is fixed to the top of the front side of the main structure through a transverse shaft; a vertical long plate is vertically fixed between the left side plate and the right side plate, the vertical long plate is close to the back side of the main structure, a vertical short plate is fixed to the back side of the main structure, the vertical short plate is close to the upper end of the main structure and parallel to the vertical long plate, a threaded hole is provided on the vertical short plate, a bolt fastener is threadedly fixed in the threaded hole, the front end of the bolt fastener is provided with a pressing plate for clamping and fixing the outer plate; a longitudinal blind hole is provided on the vertical long plate, the inner diameter of the blind hole is slightly larger than the outer diameter of the support rod, the support rod is sleeved in the blind hole; a latch hole one is provided on the vertical long plate close to the upper end of the vertical long plate, the support rod is provided with a latch hole two corresponding to the latch hole one, the support rod is fixedly connected with the body through the latch; a U-shaped fork with the opening facing upward is fixed to the top of the support rod, a pair of L-shaped hooks with opposite openings are provided on the support rod.

[0013] S2, arrange the prepared cable, and suspend and fix the body at the corresponding edge position of the hull plate, to complete the installation of the body;

[0014] S3, fix the support rod on the body, and lay the cable through the pulley;

[0015] S4, after the cable laying is completed, fix and raise the cable through the support rod;

[0016] S5, after the cable is used up, restore and lower the cable and remove the device.

[0017] As a preferred technical solution, in the step S1, the support rod comprises an upper rod and a lower rod, the upper rod and the lower rod are detachably connected through a threaded sleeve; in the step S3, before the support rod is fixed on the body, the upper rod and the lower rod are fixed through threaded connection to complete the assembly of the support rod; in the step S5, when the device is removed, the support rod is divided into the upper rod and the lower rod.

[0018] As a preferred technical solution, the specific steps of the step S2 comprise:

[0019] S2-1, according to the weight of the cable and the bearing capacity of the support rod, the prepared cable to be laid is arranged into single or multiple bundles;

[0020] S2-2, when the cable is single, the device is installed at the edge of the hull plate, and is located between the on-ship position and the preliminary laying position of the cable;

[0021] When the cable is multiple, the devices are installed side by side along the edge of the hull plate, and the number and position of the devices are determined according to the on-ship position of each cable.

[0022] As a preferred technical solution, in step S2, the installation step of the body includes: placing the device at the edge of the hull plate, suspending the edge by the protrusion of the hull plate, clamping the protrusion of the hull plate between the vertical long plate and the vertical short plate, and clamping and fixing the body and the protrusion of the hull plate by the bolt fastener on the vertical short plate, so that the back side of the vertical long plate is attached to the outer side of the hull plate, thereby fixing the body of the device to the top of the outer edge of the hull plate.

[0023] As a preferred technical solution, the specific steps of step S3 include: after the body is fixed and suspended, a support rod is inserted into the blind hole on the vertical long plate, and the pin hole one and the pin hole two are aligned and locked by inserting the pin; one end of the cable to be laid is placed in the pulley for laying.

[0024] As a preferred technical solution, the specific steps of step S4 include:

[0025] S4-1, winding and fixing the cable between the L-shaped hooks on the same support rod to complete the preliminary fixing of the cable;

[0026] S4-2, lifting and fixing the preliminarily fixed cable by the U-shaped fork at the top of the support rod, so that the lifted cable is higher than the working area of the construction personnel.

[0027] As a further preferred technical solution, step S4-2 further includes the following steps:

[0028] When there is a high support point near the cable, the lifted cable is fixed by the high support point;

[0029] When there is no high support point near the cable, the same device is installed at the protrusion of the opposite edge of the hull plate corresponding to the current device, the cable is passed through the U-shaped fork at the top of the support rod on the opposite side and wound and fixed on the L-shaped hook of the support rod.

[0030] As a further preferred technical solution, the specific steps of step S4 further include: after the cable is preliminarily fixed by the support rod, the cable between the pulley and the support rod is bound and fixed to the nearest on-ship rail.

[0031] As a preferred technical solution, the specific steps of the step S5 include:

[0032] S5-1, untwist the cable wound on the L-shaped hook, and lower the cable while keeping the cable taut and the cable still in the pulley groove until the cable is restored to the pre-laying state;

[0033] S5-2, after all the cables have been safely lowered away from the ship, remove the positioning pin on the support rod, remove the support rod from the body, and loosen the bolt fastener for fixing between the body and the outer plate, and remove the body from the outer plate.

[0034] As described above, the present application has the following beneficial effects:

[0035] (1) The device for edge cable laying and fixing suspension and the use method thereof of the present application can keep the cable and the outer plate at a certain distance by using the pulley away from the outer plate of the ship body during the laying process, reduce the friction at the right angle between the cable and the top steel plate of the outer plate, and effectively avoid the damage to the cable sheath.

[0036] (2) The device for edge cable laying and fixing suspension and the use method thereof of the present application can effectively avoid the damage caused by the friction between the cable and the outer plate. After the laying is completed, the L-shaped hook oppositely arranged on the support rod is used to wind and fix the cable in the middle, which prevents the cable from falling and avoids the friction between the cable and the outer plate caused by the wind blowing when the cable is laid close to the outer plate of the ship.

[0037] (3) The device for edge cable laying and fixing suspension and the use method thereof of the present application can provide an unobstructed passage after fixing the cable by the method of the present application, which is convenient for the construction personnel to pass through. Specifically, the U-shaped fork on the support rod is used to lift the cable, which avoids the influence of the weight of the cable on the potential lifting point of the railing, thereby keeping the passage unobstructed. Moreover, the height of the cable after being lifted is higher than the height of an ordinary person, which provides sufficient space for the personnel to pass through, and ensures the safety and efficiency of the construction personnel to pass through the deck.

[0038] (4) The device for cable laying and fixing suspension on the edge of the deck and the use method thereof, which is convenient to carry and fast to install, and the carrying weight is considered in the design, and the structure is lightened, and meanwhile, the device is designed as three assembling parts of the body, the upper rod and the lower rod which can be conveniently split, so that the device is convenient to carry on the ship, and the installation process of the device and the deck edge position where the cable is prepared to be laid is simple and fast, the construction efficiency is greatly improved, and the construction cost is reduced. BRIEF DESCRIPTION OF DRAWINGS

[0039] Figure 1 is a perspective structural schematic view of the device for cable laying and fixing suspension on the edge of the deck in the present application.

[0040] Figure 2 is a front view of the device in the present application. Figure 1

[0041] Figure 3 is a left view of the device in the present application. Figure 1

[0042] Figure 4 is a bottom view of the device in the present application. Figure 1

[0043] Figure 5 is a perspective structural schematic view of the upper rod part of the support rod in the present application.

[0044] Figure 6 is a perspective structural schematic view of the lower rod part of the support rod in the present application.

[0045] Figure 7 is a perspective structural schematic view of the body part in the present application.

[0046] Figure 8 is a schematic view of the device in the present application when the cable is laid.

[0047] Figure 9 is a schematic view of the device in the present application when the cable is fixed and lifted after the cable is laid.

[0048] In the drawings, the reference signs are specifically explained as follows: 1, main body structure; 11, transverse reinforcing rib; 12, transverse shaft; 13, vertical short plate; 14, vertical long plate; 141, blind hole; 2, pulley; 3, support rod; 31, U-shaped fork; 32, hook; 33, upper rod; 34, lower rod; 341, bolt hole two; 35, threaded sleeve; 4, bolt fastener; 5, cable; 6, outer plate; 7, deck; 8, high support point. DETAILED DESCRIPTION

[0049] ​​​In order to better understand the purpose, structure and function of the present application, the technical solutions in the embodiments of the present application will be described clearly and completely below in combination with the drawings in the embodiments of the present application. Obviously, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments, a basic appearance of the device and a state of the device when in use, i.e., hanging on the edge of a ship body, and a state of a person when in use are illustrated.

[0050] In the description of the present application, it should be noted that the position relationships indicated in the specification, such as "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer" and the like are based on the position relationships shown in the drawings, and are only for the convenience of describing the embodiments of the present application and simplifying the description, and therefore cannot be understood as indicating or implying that the devices or elements indicated must have a particular orientation, be constructed and operated in a particular direction, and therefore cannot be understood as a limitation on the present application.

[0051] Embodiments

[0052] As shown in Figures 1-9 , the present embodiment provides a device for edge cable pulling and fixing suspension and a use method thereof, which is suitable for use in a shipyard mooring stage, and the method comprises the following steps,

[0053] S1, as shown in Figures 1-7 , a device for edge cable 5 pulling and fixing suspension is prepared.

[0054] The device comprises a body and a support rod 3; the body comprises a main structure 1, the main structure 1 comprises left and right side plates which are parallel to each other, a front top of the main structure 1 is fixed with a pulley 2 through a transverse shaft 12, two ends of the transverse shaft 12 are fixedly connected with the left and right side plates respectively, a vertical long plate 14 is vertically fixed between the left and right side plates, the vertical long plate 14 is close to a back side of the main structure 1, a vertical short plate 13 is fixed to the back side of the main structure 1, the vertical short plate 13 is close to an upper end of the main structure 1 and is parallel to the vertical long plate 14, and a threaded through hole is arranged on the vertical short plate 13, a bolt fastener 4 is threadedly fixed in the threaded through hole, a pressing plate is arranged on a front end of the bolt fastener 4, and the bolt fastener 4 can clampingly fix a ship body outer plate 6 between the vertical short plate 13 and the vertical long plate 14; a longitudinal blind hole 141 is arranged on the vertical long plate 14, and a bolt hole one is arranged on the vertical long plate 14, the bolt hole one is close to an upper end of the vertical long plate 14 and transversely penetrates the blind hole 141, an inner diameter of the blind hole 141 is slightly larger than an outer diameter of the support rod 3, the support rod 3 is sleeved in the blind hole 141, a bolt hole two 341 is arranged on the support rod 3, and the bolt hole two 341 is arranged at a position corresponding to the bolt hole one, so that a bolt is inserted and locked.

[0055] In the embodiment, the left and right side plates are both stamping thin plates, and a plurality of lightening holes are arranged on the left and right side plates, so that the overall weight of the device is effectively reduced while the stability of the main structure 1 is maintained, and the manufacturing cost of the device is reduced; a plurality of transverse reinforcing ribs 11 are further arranged between the left and right side plates, the number of the transverse reinforcing ribs 11 is three, and the transverse reinforcing ribs 11 are all circular tubes, the left and right side plates are fixedly connected with two ends of the transverse reinforcing ribs 11 respectively, so that the main structure 1 is more stable and shaking during the process of pulling and covering is avoided; the vertical long plate 14 and the vertical short plate 13 are both reinforcing plates, so as to ensure the clamping force between the vertical long plate 14 and the vertical short plate 13.

[0056] The support rod 3 is detachably fixed to the body through the blind hole 141 and the bolt, a top of the support rod 3 is fixed with a U-shaped fork 31 with an opening facing upward, the lowest point of the opening of the U-shaped fork 31 is higher than the maximum height of a construction worker, and a pair of L-shaped hooks 32 with openings facing opposite directions are fixed on the rod of the support rod 3.

[0057] In the embodiment, the support rod 3 comprises an upper rod 33 and a lower rod 34, the upper rod 33 and the lower rod 34 are detachably connected through a threaded sleeve 35, the top of the lower rod 34 is provided with an internal thread, the bottom of the upper rod 33 is provided with an external thread matched with the internal thread, and the upper rod 33 and the lower rod 34 are fixedly connected through the internal and external threads; the U-shaped fork 31 and the L-shaped hook 32 are located on the rod body of the upper rod 33, and the bolt hole two 341 is located on the rod body of the lower rod 34; the bolt hole one and the bolt hole two 341 have shapes matched with the shape of the bolt.

[0058] S2, arrange the prepared cable 5, and install the device body at the edge position of the corresponding ship outer plate 6 to complete the fixed suspension of the device body.

[0059] S2-1, generally, the cable 5 is pulled and arranged by manpower, and the weight of the pulled and arranged cable 5 and the weight of the cable 5 suspended and fixed on the support rod 3 after the pulling and arranging are considered to prevent the deformation of the support rod 3, so that in the embodiment, when the cable 5 is arranged, the prepared cable 5 to be pulled and arranged is straightened in the wharf area, and according to the weight of the cable 5 itself and the bearing capacity of the support rod 3, the prepared cable 5 to be pulled and arranged is arranged into single cable 5 or multiple cables 5 in a bundle to prevent the winding of the cable 5 in the pulling and arranging process and prevent the deformation of the support rod 3.

[0060] S2-2, the installation steps of the device include: placing the device at the edge of the ship outer plate 6, suspending the outer edge by the protrusion of the edge of the ship outer plate 6, clamping the protrusion at the edge of the ship outer plate 6 between the vertical long plate 14 and the vertical short plate 13, and clamping and fixing the body and the protrusion at the edge of the outer plate 6 by the bolt fastener 4 on the vertical short plate 13, so that the back side of the vertical long plate 14 is attached to the outer side of the ship outer plate 6, thereby firmly fixing and suspending the device body at the top of the outer edge of the ship outer plate 6.

[0061] When the number of the cable 5 is single, the device is installed at the edge of the ship outer plate 6 between the cable 5 on the ship and the prepared laying position; when the number of the cable 5 is multiple in a bundle, that is, when a large number of cables 5 need to be on the ship, such as shore power cable 5, since the shore power cable 5 needs to be connected with the ship by single cable 5, a plurality of cables 5 need to be laid to be on the ship when connected with the shore power cable 5, at this time, according to the position of each cable 5 on the ship, a plurality of devices are arranged side by side along the edge of the ship outer plate 6, which is beneficial to the grouped use of the outer edge of the ship, so that the cables 5 can be laid without winding, interference, and the outer skin of the cable 5 can be prevented from being damaged by friction with the ship edge, and the damage of the paint of the outer plate 6 is also avoided.

[0062] S3, fix the support rod 3 on the body, and pull the cable 5 through the pulley 2 on the device.

[0063] After the body is fixed and hung, the lower end of the upper rod 33 and the upper end of the lower rod 34 are fixed by screw connection to complete the assembly of the support rod 3. The support rod 3 is inserted into the blind hole 141 on the vertical long plate 14 of the body, and the pin hole one and the pin hole two 341 are aligned and locked by inserting the pin to fix, so that the support rod 3 is vertically fixed on the body, and the assembly between the body and the support rod 3 is completed. As shown in Figure 8 The end of the cable 5 to be pulled is placed in the groove of the pulley 2 for pulling, which can realize labor-saving manual pulling. The pulley 2 rotates with the dragging of the cable 5, so that the friction is reduced, and the pulling process is more relaxed. At the same time, the cable 5 and the outer plate 6 are kept at a certain distance through the pulley 2, which avoids the damage of the cable 5 outer skin at the right angle of the outer plate 6 during the pulling process, and also avoids the damage of the paint of the outer plate 6 when the cable 5 directly rubs against the outer plate 6 under the influence of wind. Whether the support rod 3 needs to be removed can be determined according to the actual situation during manual pulling.

[0064] S4, as Figure 9 shown, after the cable 5 is pulled, the cable 5 is fixed and lifted through the support rod 3.

[0065] S4-1, the end of the cable 5 on the ship is wound and fixed on the pair of L-shaped hooks 32 on the same support rod 3, and the preliminary fixing of the cable 5 is realized by winding between the L-shaped hooks 32 oppositely arranged in the middle of the support rod 3, so as to prevent the cable 5 from falling.

[0066] S4-2, then, the preliminarily fixed cable 5 is lifted through the U-shaped fork 31 at the top of the support rod 3, so that the lifted cable 5 is higher than the working area of the construction personnel, and the lifted cable 5 is fixed through the high support point 8 on the ship near the cable 5. The cable 5 is arranged above the head of the construction personnel, and due to the limited width of the channel, the cable 5 will not have too much falling, so that an unobstructed deck 7 channel can be left for the smooth passage of the construction personnel, thereby improving the safety of the construction personnel during construction. The support point includes but is not limited to a bracket, a support frame or other existing fixed objects on the ship. Since the fixed objects are not involved in the patent, they will not be described here. In another embodiment, when there is no high support point 8 on the ship near the cable 5, the same device is installed on the corresponding edge protrusion of the ship body outer plate 6 on the opposite side of the current device through steps S2 and S3, the cable 5 is passed through the U-shaped fork 31 at the top end of the support rod 3 arranged on the opposite side and wound and fixed on the L-shaped hook 32 of the support rod 3, so as to ensure that the cable 5 does not bend when passing through the oppositely arranged U-shaped fork 31 at the top end of the support rod 3.

[0067] At this time, the device can be more firmly attached to the top of the outer edge of the outer plate 6 under the combined action of the gravity of the cable 5 and the clamping force at the bolt fastener 4; at the same time, since the cable 5 is also in the groove of the pulley 2, even if the cable 5 is blown by the wind, it will have a certain extension outside, thereby avoiding the friction between the cable 5 and the outer plate 6; according to the rise and fall of the tide, the other end of the cable 5 is fixed to the fixed point in the wharf area, so that the cable 5 is taut, which can further avoid the friction between the cable 5 and the outer plate 6. When the weight of the cable 5 is large, additional binding operation is performed on the cable 5. Specifically, after the cable 5 is preliminarily fixed by the support rod 3 and it is ensured that no displacement occurs, the cable 5 between the pulley 2 and the support rod 3 is fixed and bound to the nearest ship side rail, so that the cable 5 weight borne by the support rod 3 is dispersed through the structure of the ship body itself.

[0068] S5, after the cable 5 is used up, the cable 5 is restored and lowered and the device is removed.

[0069] S5-1, the cable 5 wound on the L-shaped hook 32 is unwound, and the cable 5 is lowered while keeping the cable 5 taut and the cable 5 still in the groove of the pulley 2. At this time, the cable 5 is slowly lowered by using the self-weight of the cable 5 and artificially controlling the lowering speed until the cable 5 is restored to the state before laying. This method avoids the friction between the outer skin of the cable 5 and the fast port of the outer edge of the ship body, effectively protecting the cable 5 and the paint of the outer plate 6.

[0070] S5-2, after all the cables 5 are safely lowered away from the ship, the positioning pin on the support rod 3 is removed, the support rod 3 is removed from the body, then the support rod 3 is split into the upper rod 33 and the lower rod 34; after the bolt fastener 4 used for fixing the body and the outer plate 6 is loosened, the body is removed from the outer plate 6 of the ship body.

[0071] The above only describes the preferred embodiments of the present application and is not intended to limit the present application. Any person skilled in the art can make various changes or equivalent replacements to the features and embodiments without departing from the spirit and scope of the present application. In addition, the features and embodiments can be modified to adapt to specific conditions and materials under the guidance of the present application without departing from the spirit and scope of the present application. Therefore, the present application is not limited by the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of the present application are within the scope of the present application.

Claims

1. A method for using a device for laying and fixing cables on the edge, characterized in that: The method comprises the following steps: S1, preparing a device for edge cable (5) laying and fixing suspension device: The device comprises a body and a support rod (3), and the support rod (3) is detachably fixed on the body; The body comprises a main structure (1), a pulley (2), a vertical long plate (14) and a vertical short plate (13), the main structure (1) comprises left and right side plates which are parallel to each other, the pulley (2) is fixed on the top of the front side of the main structure (1) through a transverse shaft (12); a vertical long plate (14) is vertically fixed between the left and right side plates, the vertical long plate (14) is close to the back side of the main structure (1), a vertical short plate (13) is fixed on the back side of the main structure (1), the vertical short plate (13) is close to the upper end of the main structure (1) and parallel to the vertical long plate (14), a threaded hole is arranged on the vertical short plate (13), a bolt fastener (4) is threadedly fixed in the threaded hole, and a pressing plate for clamping and fixing an outer plate (6) is arranged on the front end of the bolt fastener (4); a longitudinal blind hole (141) is arranged on the vertical long plate (14), the inner diameter of the blind hole (141) is slightly larger than the outer diameter of the support rod (3), and the support rod (3) is sleeved in the blind hole (141); a latch hole one is arranged on the vertical long plate (14) close to the upper end and penetrating the blind hole (141), a latch hole two (341) corresponding to the latch hole one is arranged on the support rod (3), and the support rod (3) is fixedly connected with the body through the latch holes; a U-shaped fork (31) with an opening facing upward is fixed on the top of the support rod (3), a pair of L-shaped hooks (32) with opposite openings are arranged on the rod body of the support rod (3), S2, arranging the cable (5) to be laid, suspending and fixing the body at the corresponding edge position of the hull outer plate (6), and completing the installation of the body; S3, fixing the support rod (3) on the body and laying the cable (5) through the pulley (2); S4, after the cable (5) is laid, fixing and lifting the cable (5) through the support rod (3); S5, after the cable (5) is used, restoring and lowering the cable (5) and removing the device.

2. The use of a device for edge cable pulling and fixing suspension according to claim 1, characterized in that, In the step S1, the support rod (3) comprises an upper rod (33) and a lower rod (34), and the upper rod (33) and the lower rod (34) are detachably connected through a threaded sleeve (35); in the step S3, before the support rod (3) is fixed on the body, the upper rod (33) and the lower rod (34) are fixed through threaded connection, and the assembly of the support rod (3) is completed; in the step S5, when the device is removed, the support rod (3) is divided into the upper rod (33) and the lower rod (34).

3. The method of using a device for edge cable pulling and securing suspension of claim 1, wherein, The specific steps of the step S2 comprise: S2-1, according to the weight of the cable (5) and the bearing capacity of the support rod (3), the cable (5) to be laid is arranged into single or multiple cables in bundles; S2-2, when the cable (5) is single, the device is installed at the edge of the hull outer plate (6) and located between the upper ship position and the prepared laying position of the cable (5); When the cable (5) is a plurality of bundled, the device is installed side by side along the hull plate (6) edge, the number and position of the device is determined according to the on-board position of each cable (5).

4. The use of a device for edge cable pulling and fixing suspension according to claim 1 or 3, characterized in that, In step S2, the mounting step of the body includes: placing the device at the edge of the hull plate (6), suspending the edge with the protrusion of the outer plate (6), clamping the protrusion of the outer plate (6) between the vertical long plate (14) and the vertical short plate (13), and clamping and fixing the body and the protrusion of the outer plate (6) edge with the bolt fastener (4) on the vertical short plate (13), so that the back side of the vertical long plate (14) is attached to the outer side of the outer plate (6), so that the body of the device is fixed and suspended on the top of the outer edge of the outer plate (6).

5. The method of using a device for edge cable pulling and securing suspension as claimed in claim 1, wherein, The specific steps of step S3 include: after the body is fixed and suspended, the support rod (3) is inserted into the blind hole (141) on the vertical long plate (14) of the body, and the bolt is locked and fixed by inserting the bolt after the bolt hole one and the bolt hole two (341) are aligned; one end of the cable (5) to be laid is put into the pulley (2) for laying.

6. The method of using a device for edge cable pulling and securing suspension of claim 1, wherein, The specific steps of step S4 include: S4-1, winding the fixed cable (5) between the L-shaped hooks (32) on the same support rod (3) to complete the preliminary fixing of the cable (5); S4-2, the preliminarily fixed cable (5) is lifted and fixed by the U-shaped fork (31) located at the top of the support rod (3), so that the lifted cable (5) is higher than the working area of the construction personnel.

7. The method of using a device for edge cable pulling and securing suspension of claim 6, wherein, The step S4-2 further includes the following steps: When there is a high support point (8) near the cable (5), the lifted cable (5) is fixed through the high support point (8); When there is no high support point (8) near the cable (5), repeat steps S2 and S3 to install the same device on the corresponding protrusion of the hull plate (6) edge on the opposite side of the current device, pass the cable (5) through the U-shaped fork (31) at the top of the support rod (3) arranged on the opposite side and wind it on the L-shaped hook (32) of the support rod (3).

8. The method of using a device for edge cable pulling and securing suspension according to any one of claims 1 or 6 or 7, wherein, The specific steps of step S4 further include: after the cable (5) is preliminarily fixed by the support rod (3), the cable (5) between the pulley (2) and the support rod (3) is fixed to the nearest ship rail on the ship.

9. The method of using a device for edge cable pulling and securing suspension of claim 1, wherein, The specific steps of step S5 include: S5-1, untwist the cable (5) wound on the L-shaped hook (32), and lower the cable (5) while keeping it tight and still in the groove of the pulley (2) until the cable (5) is restored to the state before laying; S5-2, after all the cables (5) have been safely lowered away from the ship, remove the positioning pin on the support rod (3), remove the support rod (3) from the body, and loosen the bolt fastener (4) for fixing the body and the outer plate (6), and remove the body from the outer plate (6).

Citation Information

Patent Citations

  • Laying method of ship shore power cable

    CN110212456A

  • Cable pulling and laying device and use method thereof

    CN116014632A