Composite foundation structure of transition section of deep soft foundation railway bridge abutment and construction method

By using cap beams and geogrids and variable length cement mixing piles in the transition section of the deep soft foundation railway abutment to form a soil arch effect, the problem of differential settlement in the transition section of the deep soft foundation railway abutment is solved and the bearing capacity of the foundation is improved. and stability, ensuring the smooth operation of the railway.

CN118745689APending Publication Date: 2024-10-08CCCC FIRST HARBOR ENGINEERING CO LTD +2
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411099039.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-10-08

AI Technical Summary

Technical Problem

Existing technology is difficult to effectively solve the problem of differential settlement in the transition section of a deep soft foundation railway bridge abutment, especially the settlement along and perpendicular to the rail extension direction, which affects the smooth operation and safety of the train.

Method used

The cap beam and the first geogrid are used to form a soil arch effect with variable pile length, two-way cement mixing piles and three-axis cement mixing piles, which evenly distributes stress and reduces local stress concentration. It is optimized through precise pile placement, efficient construction and layer-by-layer backfilling. Pile structure.

Benefits of technology

It significantly improves the bearing capacity and stability of the foundation, ensures the smooth and safe operation of the railway, controls post-construction settlement and the settlement of road shoulders and slopes, and maintains the overall deformation coordination of the railway.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118745689A_ABST
    Figure CN118745689A_ABST
Patent Text Reader

Abstract

The invention relates to a deep soft foundation railway bridge abutment transition section composite foundation structure and a construction method, and belongs to the technical field of geotechnical engineering soft soil foundation treatment.The deep soft foundation railway bridge abutment transition section composite foundation structure comprises variable-pile-length bidirectional cement mixing piles, cap beams, variable-pile-length three-axis cement mixing piles and first geogrids; the pile lengths of the variable-pile-length bidirectional cement mixing piles are gradually reduced in the bridge-road direction; the cap beam is arranged above the variable-pile-length two-way cement mixing pile and is poured in the direction parallel to the extending direction of the railway; the pile lengths of the variable-pile-length three-axis cement mixing piles are gradually reduced in the bridge-road direction; a reinforced soil foundation is arranged above the cap beam, and the first geogrid is laid in the reinforced soil foundation. According to the composite foundation structure of the transition section of the deep soft foundation railway bridge abutment and the construction method, the cap beam and the first geogrid are arranged and form a soil arching effect with the variable-pile-length three-axis cement mixing piles, stress can be evenly distributed on the foundation, and the local stress concentration phenomenon is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of soft soil foundation treatment in geotechnical engineering, and in particular relates to a composite foundation structure of a transition section of a deep soft foundation railway abutment and a construction method. Background Art

[0002] At the junction of the embankment and the bridge of the high-speed railway, due to differences in foundation conditions, roadbed filling materials behind the abutment, the structure of the abutment and the roadbed, and the actual construction quality, as well as the difference in stiffness between the embankment and the bridge, there is generally differential settlement between the abutment and the roadbed. This differential settlement is the settlement along the extension direction of the rails, which will affect the smooth operation of high-speed trains, driving safety, and riding comfort. In addition, in actual projects, due to limitations in funds, resources, and environment, sometimes the roadbeds of two railways are built first, but only one track is laid, and the second track is laid when conditions are ripe; this approach can save costs in the early stage and reserve space for future expansion. Since only one track is laid, the roadbed of the other track may experience different settlement processes during the period of non-use, causing differential settlement of the entire roadbed. This differential settlement is the settlement perpendicular to the extension direction of the rails, which will cause deformation of the rails, aggravate the dynamic interaction between the train and the rails, and affect the smooth operation of the train.

[0003] In the prior art, CN110512598B provides a composite foundation structure of variable diameter high pressure rotary jet piles and variable diameter powder jet piles suitable for deep soft soil and its construction method. The patent improves the bearing capacity of the foundation soil by setting up variable diameter high pressure rotary jet piles. The method adopted in the patent has a certain mitigating effect on the settlement along the extension direction of the rails, but it will cause a new stiffness difference between the transition section foundation and the general section foundation, causing a new differential settlement problem; and the patent does not take into account the settlement of the roadbed perpendicular to the extension direction of the rails, and cannot meet the variable stiffness control settlement and leveling between sections of different properties during the construction and operation of high-speed railways, and it is difficult to ensure the long-term stable operation of trains.

[0004] Therefore, how to provide a composite foundation structure and construction method for the transition section of a deep soft foundation railway abutment is a technical problem that urgently needs to be solved. Summary of the invention

[0005] In view of the shortcomings in the prior art, the present invention provides a composite foundation structure and construction method for a transition section of a deep soft foundation railway abutment. Through the arrangement of a cap beam and a first geogrid, a soil arch effect is formed with variable pile length triaxial cement mixing piles, which helps to evenly distribute stress on the foundation and reduce local stress concentration.

[0006] The present invention provides a composite foundation structure for a transition section of a railway abutment with a deep and soft foundation, comprising:

[0007] Variable-length bidirectional cement mixing piles are arranged in the soft soil foundation below the railway bed parallel to the extension direction of the railway, and are arranged at equal intervals from the center line of the soft soil foundation to the inner side of the shoulder; the length of the variable-length bidirectional cement mixing piles gradually decreases along the bridge-road direction;

[0008] A cap beam is arranged above the variable-length bidirectional cement mixing pile and cast parallel to the extension direction of the railway;

[0009] The variable-length triaxial cement mixing pile is arranged in the soft soil foundation below the railway shoulder parallel to the extension direction of the railway, extending from the inner side of the shoulder to the outer side of the shoulder; the length of the variable-length triaxial cement mixing pile gradually decreases along the bridge-road direction;

[0010] The first geogrid has a reinforced soil foundation above the cap beam, the first geogrid is laid in the reinforced soil foundation, one end of the first geogrid parallel to the extension direction of the railway extends to the abutment, and the two ends of the first geogrid perpendicular to the extension direction of the railway extend to both sides of the shoulder.

[0011] This technical solution forms a soil arch effect with the variable pile length triaxial cement mixing pile through the setting of the cap beam and the first geogrid, which helps to evenly distribute the stress on the foundation and reduce the local stress concentration phenomenon.

[0012] In some embodiments, a variable-length bidirectional cement mixing pile is provided with a top diameter expansion section at the top and a bottom diameter expansion section at the bottom; the top of the top diameter expansion section is on the same horizontal plane as the top surface of the cap. This technical solution enhances the bearing capacity and stability of the pile body by providing the top diameter expansion section and the bottom diameter expansion section, further slows down post-construction settlement, and ensures the stability of the railway structure.

[0013] In some of the embodiments, the variable-length bidirectional cement mixing piles are constructed using powder-sprayed cement mixing piles; the length of the top expansion section is 3.0m, and the pile diameter is 1.0m; the length of the bottom expansion section is 1.0m-3.0m, and the pile diameter is 1.0m; the length of the middle section of the variable-length bidirectional cement mixing piles is calculated based on the thickness of the soft soil foundation combined with the construction specifications, and the pile diameter is 0.6m.

[0014] In some of the embodiments, the variable-length triaxial cement mixing piles are constructed using powder-sprayed cement mixing piles, and the pile diameter is 0.65 m.

[0015] In some of the embodiments, the cap beam is cast with concrete, and basalt composite reinforcement is used as the main reinforcement; the beam section width of the cap beam is 1.0m, and the beam section height is 0.3m.

[0016] In some embodiments, a second geogrid is laid between the variable-length bidirectional cement mixing pile and the cap beam, one end of the second geogrid parallel to the extension direction of the railway extends to the abutment and is partially laid on the cap, and the two ends of the second geogrid perpendicular to the extension direction of the railway extend to both sides of the shoulder. This technical solution increases the integrity of the structure and evenly distributes the stress through the provision of the second geogrid, further mitigates the impact of differential settlement on the railway, and ensures the smooth operation of the railway.

[0017] In some of the embodiments, the first geogrid and the second geogrid are both steel-plastic tri-directional geogrids.

[0018] In addition, the present invention also provides a deep soft foundation railway abutment transition section composite foundation construction method, which is applied to the deep soft foundation railway abutment transition section composite foundation structure as described above, and comprises the following steps:

[0019] S1, determine the pile position in the soft soil foundation area of ​​the transition section, and arrange the variable-length bidirectional cement mixing piles and variable-length triaxial cement mixing piles according to the design;

[0020] S2, construct variable-length bidirectional cement mixing piles, using the "two mixing and one spraying" construction process. The specific construction process is as follows:

[0021] S201, pile driver in place: the mixer reaches the designated pile position and is centered;

[0022] S202, sinking and mixing: start the ash pump to spray cement powder to the soil at the same time, and the two sets of blades rotate forward and reverse at the same time to sink until the bottom surface of the top expansion section has a designed depth;

[0023] S203, retract blades: change the rotation direction of the inner and outer drill rods, retract the mixing blades to a diameter of 500 mm, and the two sets of blades rotate forward and reverse at the same time, and the mixer continues to sink until the top surface of the bottom expansion section reaches the designed depth;

[0024] S204, extending blades: changing the rotation direction of the inner and outer drill rods, extending the mixing blades to a diameter of 900mm-1000mm, the mixer continues to sink, and the two sets of blades rotate forward and reverse at the same time until the mixing of the bottom expansion section is completed;

[0025] S205, lifting and stirring: the ash delivery pump is turned off, and the two sets of blades rotate forward and reverse at the same time to stir to the top surface of the bottom expansion section;

[0026] S206, secondary blade contraction: change the rotation direction of the inner and outer drill rods, contract the mixing blades to a diameter of 500mm, and the two sets of blades rotate forward and reverse at the same time, and the mixer continues to rise until the bottom surface of the top expansion section reaches the designed depth;

[0027] S207, secondary extension of blades: change the rotation direction of the inner and outer drill rods, extend the mixing blades to a diameter of 900mm-1000mm, continue to lift the mixer, and the two sets of blades rotate forward and reverse at the same time until the mixing of the top diameter expansion section is completed, completing the construction of variable pile length bidirectional cement mixing piles;

[0028] S3, construction of variable pile length three-axis cement mixing pile, using the "two mixing and one spraying" construction process, the specific construction process is as follows:

[0029] S301, pile driver in place: the mixer reaches the designated pile position and is centered;

[0030] S302, sinking and mixing: start the high-pressure air pump and the slurry pump at the same time, mix and sink to the designed pile length, and the pile length of the variable pile length triaxial cement mixing pile is consistent with the variable pile length bidirectional cement mixing pile of the same section;

[0031] S303, improve stirring: turn off the slurry delivery pump, continue to turn on the high-pressure air pump, and improve stirring;

[0032] S304, repeating step S302 and step S303 to complete the construction of single-row variable pile long three-axis cement mixing piles;

[0033] S4, leveling the pile heads of the variable-length bidirectional cement-mixed piles and the variable-length triaxial cement-mixed piles and the soft soil foundation site, and laying the second geogrid;

[0034] S5, tie cap beam reinforcement, set up formwork, and pour cap beam concrete;

[0035] S6, backfill the wall backfill layer by layer and lay the first geogrid until backfilling reaches the designed elevation.

[0036] This technical solution effectively solves the problem of differential settlement in the transition section of railway abutments with deep soft foundation through precise pile layout, efficient construction, optimized pile structure, uniform stress distribution and layer-by-layer backfilling, significantly improves the bearing capacity and stability of the foundation, and ensures the smooth and safe operation of the railway.

[0037] In some of the embodiments, in step S2, the construction process parameters of the variable pile length bidirectional cement mixing pile are: 42.5 slag silicate cement is used, the cement addition amount is 25%-40% of the mass of the reinforced wet soil, the drilling speed is 0.8-1.2m / min, the lifting speed is 0.4-0.6m / min, the rotation speed is 30-50 rpm, and the ash spraying pressure during drilling is 0.5-0.7Mpa.

[0038] In some of the embodiments, in step S3, the construction process parameters of the variable pile length triaxial cement mixing pile are: 42.5 slag silicate cement is used, the cement addition amount is 20%-40% of the mass of the reinforced wet soil, the water-cement ratio is 1.50, the drilling speed is 0.4-0.6m / min, and the lifting speed is 0.4-0.6m / min.

[0039] Based on the above scheme, the composite foundation structure and construction method of the transition section of a deep soft foundation railway abutment in the embodiment of the present invention can achieve a smooth transition by gradually reducing the pile length of the variable pile length bidirectional cement mixing pile and the variable pile length triaxial cement mixing pile along the bridge-road direction, and effectively alleviate the differential settlement problem between the rigid-flexible foundation. At the same time, the variable pile length triaxial cement mixing pile can improve the lateral constraint effect of the entire foundation, which is helpful to control the post-construction settlement of the roadbed, and at the same time control the settlement of the shoulder and the slope; further, through the setting of the cap beam and the first geogrid, a soil arch effect is formed with the variable pile length triaxial cement mixing pile, which is helpful to evenly distribute the stress on the foundation and reduce the local stress concentration phenomenon, such as Figure 1 As shown, even if the rails are not fully paved on the roadbed, it is still possible to effectively prevent excessive deformation of the soft soil foundation, improve the overall deformation coordination of the foundation, and maintain the flatness of the railway. The composite foundation structure of the transition section of the deep soft foundation railway abutment provided in the embodiment of the present invention can ensure that the post-construction settlement of the transition section of the abutment on the deep silt foundation is less than 30 mm, the differential settlement between the abutment and the roadbed transition section shall not exceed 5 mm / 20 m, and the angle formed by the settlement of any two sections of the roadbed shall not exceed 1 / 1000. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0041] Figure 1 It is a cross-sectional view of the composite foundation structure of the transition section of a railway abutment on a deep soft foundation when only one rail is laid in an embodiment of the present invention;

[0042] Figure 2 It is a cross-sectional view of the composite foundation structure of the transition section of a railway abutment on a deep soft foundation when two rails are laid in an embodiment of the present invention;

[0043] Figure 3 It is a plan layout diagram of the composite foundation structure of the transition section of a deep soft foundation railway abutment in an embodiment of the present invention;

[0044] Figure 4 It is a side view of the composite foundation structure of the transition section of a deep soft foundation railway abutment in an embodiment of the present invention.

[0045] In the figure:

[0046] 1. Variable-length bidirectional cement mixing pile; 101. Top diameter expansion section; 102. Bottom diameter expansion section;

[0047] 2. Variable-length three-axis cement-mixed pile; 3. Cap beam; 4. Reinforced soil foundation; 5. First geogrid; 6. Second geogrid; 7. Soft soil foundation; 8. Abutment; 9. Cap; 10. Rail. DETAILED DESCRIPTION

[0048] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0049] In the description of the present invention, it should be understood that the terms "center", "lateral", "longitudinal", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0050] The terms "first", "second", and "third" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the technical features indicated. Thus, a feature defined as "first", "second", and "third" may explicitly or implicitly include one or more of the features.

[0051] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0052] The terms "system", "unit" and "module" used in this document are a method for distinguishing different components, elements, parts, portions or assemblies at different levels, and these terms may be replaced by other expressions that can achieve the same purpose.

[0053] like Figure 1-Figure 4As shown, in one embodiment of the composite foundation structure and construction method of the transition section of a deep soft foundation railway abutment of the present invention, the composite foundation structure of the transition section of a deep soft foundation railway abutment includes a variable-length bidirectional cement mixing pile 1, a cap beam 3, a variable-length triaxial cement mixing pile 2, and a first geogrid 5; wherein the variable-length bidirectional cement mixing pile 1 is arranged in parallel with the extension direction of the railway in the soft soil foundation 7 below the railway bed, and is arranged at equal intervals from the center line of the soft soil foundation 7 to the inside of the shoulder; the pile length of the variable-length bidirectional cement mixing pile 1 gradually decreases along the bridge-road direction; the cap beam 3 is arranged above the variable-length bidirectional cement mixing pile 1, and is cast parallel to the extension direction of the railway; as shown in FIG. Figure 3 As shown, the variable pile length triaxial cement mixing pile 2 is arranged in parallel with the extension direction of the railway in the soft soil foundation 7 below the railway shoulder, extending from the inner side of the shoulder to the outer side of the shoulder; the pile length of the variable pile length triaxial cement mixing pile 2 gradually decreases along the bridge-road direction; a reinforced soil foundation 4 is provided above the cap beam 3, and the first geogrid 5 is laid in the reinforced soil foundation 4, and one end of the first geogrid 5 parallel to the extension direction of the railway extends to the abutment 8, and the two ends of the first geogrid 5 perpendicular to the extension direction of the railway extend to both sides of the shoulder.

[0054] In the above-mentioned schematic embodiment, the composite foundation structure of the transition section of the deep soft foundation railway abutment can achieve a smooth transition by gradually reducing the pile length of the variable-pile-length bidirectional cement mixing pile 1 and the variable-pile-length triaxial cement mixing pile 2 along the bridge-road direction, effectively alleviating the differential settlement problem between the rigid-flexible foundation. At the same time, the variable-pile-length triaxial cement mixing pile 2 can improve the lateral constraint effect of the entire foundation, help control the post-construction settlement of the roadbed, and control the settlement of the shoulder and the slope at the same time; further, through the arrangement of the cap beam 3 and the first geogrid 5, a soil arch effect is formed with the variable-pile-length triaxial cement mixing pile 2, which helps to evenly distribute the stress on the foundation and reduce the local stress concentration phenomenon, such as Figure 1 As shown, even if the rails 10 are not fully paved on the roadbed, the excessive deformation of the soft soil foundation 7 can be effectively prevented, the overall deformation coordination of the foundation can be improved, and the flatness of the railway can be maintained. The composite foundation structure of the transition section of the deep soft foundation railway abutment provided in the embodiment of the present invention can ensure that the post-construction settlement of the transition section of the abutment 8 on the deep silt foundation is less than 30 mm, the differential settlement between the abutment 8 and the roadbed transition section shall not exceed 5 mm / 20 m, and the angle formed by the settlement of any two sections of the roadbed shall not exceed 1 / 1000.

[0055] In some embodiments, the spacing between the variable-length bidirectional cement mixing piles 1 is determined according to the high fill roadbed and the upper use load, and the maximum pile length of the variable-length bidirectional cement mixing piles 1 is determined according to the thickness of the soft soil foundation 7; through the differential settlement calculation results and the railway slope requirements, the layout range of the variable-length bidirectional cement mixing piles 1 in the direction away from the abutment 8 is determined, and the shortening amount of the length of each pile is determined.

[0056] In some embodiments, Figure 1 or Figure 2 As shown, a first geogrid 5 is laid every 1-3 m in the reinforced soil foundation 4, the width of the first geogrid 5 does not exceed the shoulder, and the first geogrid 5 at the lower layer is 3-5 m shorter than the first geogrid 5 at the upper layer. By arranging multiple layers of the first geogrid 5, the overall stability of the foundation is enhanced, the stress is evenly distributed, and the deformation of the foundation is reduced.

[0057] In some embodiments, Figure 4 As shown, the top of the variable-length bidirectional cement mixing pile 1 is provided with a top diameter expansion section 101, and the bottom is provided with a bottom diameter expansion section 102; the top of the top diameter expansion section 101 is on the same horizontal plane as the top surface of the cap 9. By providing the top diameter expansion section 101 and the bottom diameter expansion section 102, the bearing capacity and stability of the pile body are enhanced, the post-construction settlement is further slowed down, and the stability of the railway structure is ensured.

[0058] Furthermore, the variable-length bidirectional cement mixing pile 1 is constructed using powder-sprayed cement mixing piles; the length of the top expansion section 101 is 3.0 m, and the pile diameter is 1.0 m; the length of the bottom expansion section 102 is 1.0 m-3.0 m, and the pile diameter is 1.0 m; the length of the middle section of the variable-length bidirectional cement mixing pile 1 is calculated based on the thickness of the soft soil foundation 7 combined with the construction specifications, and the pile diameter is 0.6 m.

[0059] In some embodiments, the variable-length three-axis cement mixing pile 2 is constructed using powder-sprayed cement mixing piles, and the pile diameter is 0.65m.

[0060] Furthermore, the interlocking overlap length of the variable pile long triaxial cement mixing pile 2 is 0.2 m, the number of the single-row variable pile long triaxial cement mixing pile 2 is determined according to the width of the shoulder slope, and the row spacing is 6 m.

[0061] In some embodiments, the cap beam 3 is cast with concrete, and basalt composite bars are used as main bars; the beam section width of the cap beam 3 is 1.0m, and the beam section height is 0.3m. The force-bearing bars are basalt composite bars, which effectively give play to the advantages of basalt composite bars such as high tensile strength and light weight.

[0062] In some embodiments, Figure 4 As shown, a second geogrid 6 is laid between the variable-length bidirectional cement mixing pile 1 and the cap beam 3. One end of the second geogrid 6 parallel to the extension direction of the railway extends to the abutment 8 and is partially laid on the cap 9. The second geogrid 6 extends to both sides of the shoulder perpendicular to the extension direction of the railway. The second geogrid 6 is provided to increase the integrity of the structure, evenly distribute stress, further mitigate the impact of differential settlement on the railway, and ensure the smooth operation of the railway.

[0063] In some embodiments, the first geogrid 5 and the second geogrid 6 are both made of steel-plastic triaxial geogrids. The steel-plastic triaxial geogrids have the advantages of high strength and good durability, and can ensure the long-term safety and reliability of the railway foundation structure.

[0064] Based on the above-mentioned deep soft foundation railway abutment transition section composite foundation structure, the present invention also provides a deep soft foundation railway abutment transition section composite foundation construction method, the construction method is applied to the above-mentioned deep soft foundation railway abutment transition section composite foundation structure, comprising the following steps:

[0065] S1, determine the pile position in the soft soil foundation 7 area of ​​the transition section, and arrange the variable-length bidirectional cement mixing pile 1 and the variable-length triaxial cement mixing pile 2 according to the design;

[0066] S2, construct variable-length bidirectional cement mixing pile 1, using the "two mixing and one spraying" construction process. The specific construction process is as follows:

[0067] S201, pile driver in place: the mixer reaches the designated pile position and is centered;

[0068] S202, sinking and mixing: start the ash pump to spray cement powder to the soil at the same time, and the two sets of blades rotate forward and reverse at the same time to sink until the bottom surface of the top expansion section 101 is at the designed depth;

[0069] S203, retract the blades: change the rotation direction of the inner and outer drill rods, retract the mixing blades to a diameter of 500 mm, and the two sets of blades rotate forward and reverse at the same time, and the mixer continues to sink until the top surface of the bottom expansion section 102 reaches the designed depth;

[0070] S204, extending blades: changing the rotation direction of the inner and outer drill rods, extending the mixing blades to a diameter of 900mm-1000mm, the mixer continues to sink, and the two sets of blades rotate forward and reverse at the same time until the mixing is completed in the bottom expansion section 102;

[0071] S205, lifting and stirring: the ash delivery pump is turned off, and the two sets of blades rotate forward and reverse at the same time to stir to the top surface of the bottom expansion section 102;

[0072] S206, secondary blade contraction: change the rotation direction of the inner and outer drill rods, contract the mixing blades to a diameter of 500 mm, and the two sets of blades rotate forward and reverse at the same time, and the mixer is continuously lifted until the bottom surface of the top expansion section 101 reaches the designed depth;

[0073] S207, secondary extension of blades: change the rotation direction of the inner and outer drill pipes, extend the mixing blades to a diameter of 900mm-1000mm, continue to lift the mixer, and rotate the two sets of blades in the forward and reverse directions at the same time until the mixing of the top diameter expansion section 101 is completed, and the construction of the variable-length bidirectional cement mixing pile 1 is completed;

[0074] S3, construct variable pile length three-axis cement mixing pile 2, using the "two mixing and one spraying" construction process. The specific construction process is as follows:

[0075] S301, pile driver in place: the mixer reaches the designated pile position and is centered;

[0076] S302, sinking and mixing: start the high-pressure air pump and the slurry pump at the same time, mix and sink until the designed pile length is reached. The length of the variable pile length triaxial cement mixing pile 2 is consistent with the variable pile length bidirectional cement mixing pile 1 of the same section;

[0077] S303, improve stirring: turn off the slurry delivery pump, continue to turn on the high-pressure air pump, and improve stirring;

[0078] S304, repeating step S302 and step S303 to complete the construction of single-row variable pile long three-axis cement mixing pile 2;

[0079] S4, leveling the pile heads of the variable-length bidirectional cement-mixed pile 1 and the variable-length triaxial cement-mixed pile 2 and the soft soil foundation 7, and laying the second geogrid 6;

[0080] S5, tie the steel bars of cap beam 3, set up the formwork, and pour the concrete of cap beam 3;

[0081] S6, backfill the wall backfill material layer by layer, and lay the first geogrid 5 until backfilling reaches the designed elevation.

[0082] In the above-mentioned exemplary embodiment, the problem of differential settlement in the transition section of a railway abutment with deep soft foundation is effectively solved through precise pile layout, efficient construction, optimized pile structure, uniform stress distribution and layer-by-layer backfilling, which significantly improves the bearing capacity and stability of the foundation and ensures the smooth and safe operation of the railway.

[0083] In some embodiments, in step S2, the construction process parameters of the variable pile length bidirectional cement mixing pile 1 are: 42.5 slag silicate cement is used, the cement addition amount is 25%-40% of the mass of the reinforced wet soil, the drilling speed is 0.8-1.2m / min, the lifting speed is 0.4-0.6m / min, the rotation speed is 30-50 rpm, and the ash spraying pressure during drilling is 0.5-0.7Mpa.

[0084] In some embodiments, in step S3, the construction process parameters of the variable pile length triaxial cement mixing pile 2 are: the cement is 42.5 slag silicate cement, the cement addition amount is 20%-40% of the mass of the reinforced wet soil, the water-cement ratio is 1.50, the drilling speed is 0.4-0.6m / min, and the lifting speed is 0.4-0.6m / min.

[0085] Through the description of multiple embodiments of the composite foundation structure and construction method of the transition section of a deep soft foundation railway abutment of the present invention, it can be seen that the embodiments of the composite foundation structure and construction method of the transition section of a deep soft foundation railway abutment of the present invention have at least one or more of the following advantages:

[0086] 1. The composite foundation structure of the transition section of a deep soft foundation railway abutment provided by the present invention can achieve a smooth transition by gradually reducing the pile length of the variable-pile-length bidirectional cement mixing pile 1 and the variable-pile-length triaxial cement mixing pile 2 along the bridge-road direction, thereby effectively alleviating the differential settlement problem between the rigid and flexible foundations;

[0087] 2. The composite foundation structure of the transition section of a deep soft foundation railway abutment provided by the present invention, the variable pile length triaxial cement mixing pile 2 can improve the lateral restraint effect of the entire foundation, help control the post-construction settlement of the roadbed, and control the settlement of the shoulder and slope at the same time;

[0088] 3. The composite foundation structure of the transition section of a deep soft foundation railway abutment provided by the present invention forms a soil arch effect with the variable pile length triaxial cement mixing pile 2 through the arrangement of the cap beam 3 and the first geogrid 5, which helps to evenly distribute the stress on the foundation and reduce the local stress concentration phenomenon;

[0089] 4. The composite foundation construction method for the transition section of a railway abutment with deep soft foundation provided by the present invention effectively solves the problem of differential settlement of the transition section of a railway abutment with deep soft foundation through precise pile layout, efficient construction, optimization of pile structure, uniform stress distribution and layer-by-layer backfilling, significantly improves the bearing capacity and stability of the foundation, and ensures the smooth and safe operation of the railway.

[0090] Finally, it should be noted that: the various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0091] The above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the present invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.

Claims

1. A composite foundation structure for the transition section of a railway abutment with a thick soft foundation. It is characterized in that include: The variable-length bidirectional cement-mixed piles are arranged in the soft soil foundation below the railway bed in parallel with the extension direction of the railway, and are arranged at equal intervals from the center line of the soft soil foundation to the inner side of the shoulder; the length of the variable-length bidirectional cement-mixed piles gradually decreases along the bridge-road direction; A cap beam is arranged above the variable-length bidirectional cement mixing pile and is cast parallel to the extension direction of the railway; The variable-length triaxial cement mixing pile is arranged in the soft soil foundation below the railway shoulder in parallel with the extension direction of the railway, extending from the inner side of the shoulder to the outer side of the shoulder; the length of the variable-length triaxial cement mixing pile gradually decreases along the bridge-road direction; A first geogrid, a reinforced soil foundation is provided above the cap beam, the first geogrid is laid in the reinforced soil foundation, one end of the first geogrid parallel to the extension direction of the railway extends to the abutment, and the two ends of the first geogrid perpendicular to the extension direction of the railway extend to both sides of the shoulder.

2. The composite foundation structure of the transition section of a railway abutment with deep soft foundation according to claim 1, It is characterized in that The variable-length bidirectional cement-mixed pile has a top diameter expansion section at the top and a bottom diameter expansion section at the bottom; the top end of the top diameter expansion section is on the same horizontal plane as the top surface of the bearing platform.

3. The composite foundation structure of the transition section of a railway abutment with deep soft foundation according to claim 2, It is characterized in that The variable-length bidirectional cement mixing pile is constructed using powder-sprayed cement mixing piles; the length of the top expansion section is 3.0m, and the pile diameter is 1.0m; the length of the bottom expansion section is 1.0m-3.0m, and the pile diameter is 1.0m; the length of the middle section of the variable-length bidirectional cement mixing pile is calculated based on the thickness of the soft soil foundation and the construction specifications, and the pile diameter is 0.6m.

4. The composite foundation structure for transition section of a railway abutment with deep soft foundation according to claim 1, It is characterized in that The variable pile length three-axis cement mixing pile is constructed using powder spray cement mixing piles, and the pile diameter is 0.65m.

5. The composite foundation structure of the transition section of a railway abutment with deep soft foundation according to claim 1, It is characterized in that The cap beam is cast with concrete, and basalt composite reinforcement is used as the main reinforcement; the beam section width of the cap beam is 1.0m, and the beam section height is 0.3m.

6. The composite foundation structure for transition section of a railway abutment with deep soft foundation according to claim 1, It is characterized in that A second geogrid is laid between the variable-length bidirectional cement-mixed pile and the cap beam, one end of the second geogrid parallel to the extension direction of the railway extends to the abutment and is partially laid on the pedestal, and the two ends of the second geogrid perpendicular to the extension direction of the railway extend to both sides of the shoulder.

7. The composite foundation structure for the transition section of a railway abutment with deep soft foundation according to claim 6, It is characterized in that The first geogrid and the second geogrid are both steel-plastic three-dimensional geogrids.

8. A composite foundation construction method for the transition section of a railway abutment with a thick soft foundation. It is characterized in that The composite foundation structure for the transition section of a railway abutment with a deep soft foundation as claimed in any one of claims 1 to 7 comprises the following steps: S1, determine the pile position in the soft soil foundation area of ​​the transition section, and arrange the variable-length bidirectional cement mixing piles and variable-length triaxial cement mixing piles according to the design; S2, construct variable-length bidirectional cement mixing piles, using the "two mixing and one spraying" construction process. The specific construction process is as follows: S201, pile driver in place: the mixer reaches the designated pile position and is centered; S202, sinking and mixing: start the ash pump to spray cement powder to the soil at the same time, and the two sets of blades rotate forward and reverse at the same time to sink until the bottom surface of the top expansion section has a designed depth; S203, retract blades: change the rotation direction of the inner and outer drill rods, retract the mixing blades to a diameter of 500 mm, and the two sets of blades rotate forward and reverse at the same time, and the mixer continues to sink until the top surface of the bottom expansion section reaches the designed depth; S204, extending blades: changing the rotation direction of the inner and outer drill rods, extending the mixing blades to a diameter of 900mm-1000mm, the mixer continues to sink, and the two sets of blades rotate forward and reverse at the same time until the mixing of the bottom expansion section is completed; S205, lifting and stirring: the ash delivery pump is turned off, and the two sets of blades rotate forward and reverse at the same time to stir to the top surface of the bottom expansion section; S206, secondary blade contraction: change the rotation direction of the inner and outer drill rods, contract the mixing blades to a diameter of 500mm, and the two sets of blades rotate forward and reverse at the same time, and the mixer continues to rise until the bottom surface of the top expansion section reaches the designed depth; S207, secondary extension of blades: change the rotation direction of the inner and outer drill rods, extend the mixing blades to a diameter of 900mm-1000mm, continue to lift the mixer, and the two sets of blades rotate forward and reverse at the same time until the mixing of the top diameter expansion section is completed, completing the construction of variable pile length bidirectional cement mixing piles; S3, the construction of variable pile length three-axis cement mixing pile adopts the "two mixing and one spraying" construction process. The specific construction process is as follows: S301, pile driver in place: the mixer reaches the designated pile position and is centered; S302, sinking and mixing: start the high-pressure air pump and the slurry pump at the same time, mix and sink to the designed pile length, and the pile length of the variable pile length triaxial cement mixing pile is consistent with the variable pile length bidirectional cement mixing pile of the same section; S303, improve stirring: turn off the slurry delivery pump, continue to turn on the high-pressure air pump, and improve stirring; S304, repeating step S302 and step S303 to complete the construction of single-row variable pile long three-axis cement mixing piles; S4, leveling the pile heads of the variable-length bidirectional cement-mixed piles and the variable-length triaxial cement-mixed piles and the soft soil foundation site, and laying the second geogrid; S5, tie cap beam reinforcement, set up formwork, and pour cap beam concrete; S6, backfill the wall backfill layer by layer and lay the first geogrid until backfilling reaches the designed elevation.

9. The method for constructing a composite foundation for a transition section of a thick soft foundation railway abutment according to claim 8, It is characterized in that In step S2, the construction process parameters of the variable-length bidirectional cement-mixed piles are: 42.5 slag silicate cement is used, the cement addition amount is 25%-40% of the mass of the reinforced wet soil, the drilling speed is 0.8-1.2m / min, the lifting speed is 0.4-0.6m / min, the rotation speed is 30-50 rpm, and the ash spraying pressure during drilling is 0.5-0.7Mpa.

10. The method for constructing a composite foundation for a transition section of a thick soft foundation railway abutment according to claim 8, It is characterized in that In step S3, the construction process parameters of the variable pile length triaxial cement mixing pile are: 42.5 slag silicate cement is used, the cement addition amount is 20%-40% of the mass of the reinforced wet soil, the water-cement ratio is 1.50, the drilling speed is 0.4-0.6m / min, and the lifting speed is 0.4-0.6m / min.