Non-support construction method for large-span spoke type cable-supported roof cover shed
Through the support-free construction method, partitioned symmetrical construction and finite element simulation analysis, the problems of many support frames and long construction period in the traditional method have been solved, and a fast, safe and efficient installation of large-span spoke-type cable-supported roof canopies has been achieved, reducing the cost reduce construction costs and risks of working at heights.
Patent Information
- Application Number
- CN202410653461.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-24
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2044-05-24
AI Technical Summary
The traditional long-span spoke-type cable-supported roof canopy construction method has problems such as a large number of support frames, occupying the construction site, long construction period, many high-altitude operations, and being greatly affected by weather.
Using the support-free construction method, the long-span spoke-type cable-supported roof is divided into areas A, C, B and D in a clockwise direction for simultaneous construction. Hoisting channels and structural assembly sites are set up, and finite element simulation analysis and outer ring are carried out. Beam hoisting, radial cable and hoop cable installation, symmetrical hoisting of the upper tension truss of the prestressed cable, and lifting in sequence until the overall canopy is installed.
Effectively reduce the number of on-site support frames, reduce the amount of high-altitude operations, speed up the construction progress, improve the installation speed and construction quality, reduce cumulative errors, reduce construction costs, and provide more construction sites for the venue.
Smart Images

Figure CN118745790A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a bracket-free construction method of a large-span spoke-type cable-supported roof canopy. Background Art
[0002] The spoke-type cable-supported roof structure system is in a self-balanced tension state under prestressing, has good overall structural stiffness, and can be used for the roof structure of large-span space buildings with internal openings. It is commonly found in large stadiums and football stadiums. Its structure includes: a rigid outer ring beam, which is arranged at the outer edge of the tension structure; a radial string structure, which includes a rigid radial beam, which is arranged at the top of the tension structure and is arranged radially and radially at the top of the tension structure; a middle vertical strut, which is arranged in the middle of the tension structure; a radial cable and ring cable part, which includes a middle ring cable, which is arranged in the middle of the tension structure and below the middle vertical strut; an external radial cable, which is arranged at the bottom of the tension structure; and an internal ring cable, which is arranged at the opening position of the tension structure.
[0003] The traditional large-span spoke-type cable-supported roof canopy construction method is to first install the rigid outer ring beam; then set up the support frame, and install the rigid radial beams and vertical struts from the outside to the inside; finally, lay the annular and radial prestressed cables on the stands of the venue, lift and tension them, remove the internal support frame, and the canopy structure is installed.
[0004] The traditional method has technical problems such as huge amount of support frame measures, occupying construction site, long construction period, many high-altitude operations, and great influence by weather. Summary of the invention
[0005] The technical problem to be solved by the present invention is to provide a bracket-free construction method for a large-span spoke-type cable-supported roof canopy, so as to at least solve some of the above-mentioned technical problems.
[0006] To achieve the above purpose, the technical solution adopted by the present invention is as follows:
[0007] A bracket-free construction method for a large-span spoke-type cable-supported roof canopy is disclosed. The large-span spoke-type cable-supported roof canopy is divided into zone A, zone C, zone B and zone D in a clockwise direction for simultaneous construction. At the same time, hoisting channels and structure assembly sites are set inside and outside the stands. Zone AC and zone BD are constructed symmetrically.
[0008] Furthermore, the basement floor slab is reinforced under the lifting channel.
[0009] Further, the construction includes the following steps:
[0010] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0011] Step 2: hoisting of outer ring beam;
[0012] Step 3: Install the radial cable and the annular cable in place;
[0013] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0014] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0015] Furthermore, in step one, when the prestressed cable structure is tensioned and subjected to finite element simulation analysis, the overall tensioned prestressed cable structure is simulated first, and then the deflection values and cable stresses generated by the radial beams and struts on the upper part of the cable are installed, providing a basis for tensioning the cable structure to the design state at one time.
[0016] Furthermore, in step 2, when the outer ring beam is hoisted, a 400t crawler crane is used for off-site hoisting, and the construction is carried out in a clockwise direction, symmetrically from area A to area C and from area B to area D.
[0017] Furthermore, the outer ring beam is installed by assembling it into unit modules on the ground, then hoisting them one by one, and finally installing the rods between adjacent units.
[0018] Furthermore, in step three, when the radial cables and the annular cables are installed in place, the prestressed cables are tensioned according to the finite element simulation results; a bracket is set up for the annular cables, and the cables are hoisted into place using tooling cables; and the radial cables and the annular cables are connected in the air at the bracket position.
[0019] Furthermore, in step 4, the upper prestressed cable chord trusses are hoisted symmetrically in the AC area and the BD area in a clockwise direction, and the lower part of the truss is connected to the cable by a pin; the chord trusses are first assembled on the ground, and radially divided into module 1 and module 2, which are hoisted from the inside and outside of the large-span spoke-type cable-supported roof canopy by a 400t crawler.
[0020] Furthermore, two modules 2 are first hoisted on the outside of the large-span spoke-type cable-supported roof canopy, and then the annular rods between two adjacent modules are supplemented to form a stable structure, and then a module 1 is hoisted from the inside.
[0021] Furthermore, in the step five, the circumferential rods between adjacent modules 1 are hoisted in sequence according to the above construction sequence until the installation of the entire canopy is completed.
[0022] Compared with the prior art, the present invention has the following beneficial effects:
[0023] The present invention is scientifically and reasonably designed, can effectively reduce the number of on-site support frames, reduce the amount of high-altitude operations, and can effectively speed up the progress of on-site construction.
[0024] The invention has the advantages of fast installation, low construction cost, high construction quality, and providing tension compensation through finite element simulation, and can effectively solve the technical problem of downward deformation of the front end of the roof.
[0025] The steel structure part within the outer ring beam of the canopy of the present invention does not need a support frame, which can effectively reduce the amount of measures and provide a large amount of construction space for the stadium stands and internal venues.
[0026] Each radial tensioned truss of the present invention is divided into two modules for hoisting, which can effectively ensure the installation accuracy and accelerate the hoisting speed.
[0027] The present invention adopts zoned symmetrical construction, which can effectively speed up the construction progress, and can also help reduce the cumulative error caused by hoisting, and is closer to the design state. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a schematic diagram of the process of the bracket-free construction method of the large-span spoke-type cable-supported roof canopy of the present invention.
[0029] Figure 2 The present invention divides the large-span spoke-type cable-supported roof canopy into four major construction areas, ABCD.
[0030] Figure 3 This is a diagram showing the hoisting state of the outer ring beam of the present invention.
[0031] Figure 4 The radial cable and the annular cable of the present invention are installed in place. Figure 1 .
[0032] Figure 5 The radial cable and the annular cable of the present invention are installed in place. Figure 2 .
[0033] Figure 6 It is a schematic diagram of the upper tension truss of the symmetrically hoisted prestressed cable of the present invention.
[0034] Figure 7 This is a schematic diagram of the present invention's chord truss being divided into modules 1 and 2 along the radial direction.
[0035] Figure 8 This is a schematic diagram of first hoisting two modules 2 on the outside of the present invention.
[0036] Fig. 9 This is a schematic diagram of the annular rod member installed between two adjacent modules according to the present invention.
[0037] Fig.10 It is a schematic diagram of hoisting a module 1 from the inside after forming a stable structure of the present invention.
[0038] Fig.11 This is a schematic diagram of the overall canopy of the present invention after installation.
[0039] Fig.12 It is a schematic diagram of a large-span spoke-type cable-supported roof canopy of the present invention. DETAILED DESCRIPTION
[0040] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0041] Example 1.
[0042] like Figure 1-12 As shown, the present invention provides a method for constructing a large-span spoke-type cable-supported roof canopy without a bracket, which divides the large-span spoke-type cable-supported roof canopy into zone A, zone C, zone B and zone D in a clockwise direction for simultaneous construction, and at the same time, hoisting passages and structure assembly sites are set inside and outside the stands, the basement floor slab is reinforced under the hoisting passage, and the AC zone and the BD zone are constructed symmetrically.
[0043] The present invention is scientifically and reasonably designed, can effectively reduce the number of on-site support frames, reduce the amount of high-altitude operations, and can effectively speed up the progress of on-site construction.
[0044] Example 2.
[0045] like Figure 1-12 As shown, the present invention provides a large-span spoke-type cable-supported roof canopy without a support frame, and the construction includes the following steps:
[0046] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0047] Step 2: hoisting of outer ring beam;
[0048] Step 3: Install the radial cable and the annular cable in place;
[0049] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0050] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0051] The design of the present invention is scientific and reasonable, which can effectively reduce the number of on-site support frames, reduce the amount of high-altitude operations, and effectively speed up the progress of on-site construction. The present invention has fast installation, low construction cost, high construction quality, and provides tension compensation through finite element simulation, which can effectively solve the technical problem of downward deformation of the front end of the roof. The steel structure part within the outer ring beam of the canopy of the present invention does not require a support frame, which can effectively reduce the amount of measures and provide a large number of construction sites for the stands and internal venues of the venue. In the present invention, each radial tensioned truss is divided into two modules for hoisting, which can effectively ensure installation accuracy and speed up hoisting. The present invention adopts zoned symmetrical construction, which can effectively speed up the construction progress, and can also help reduce the cumulative error caused by hoisting, and is closer to the design state.
[0052] Example 3.
[0053] like Figure 1-12 As shown, the present invention provides a large-span spoke-type cable-supported roof canopy without a support frame, and the construction includes the following steps:
[0054] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0055] Step 2: hoisting of outer ring beam;
[0056] Step 3: Install the radial cable and the annular cable in place;
[0057] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0058] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0059] In the step 1, when the prestressed cable structure is tensioned and subjected to finite element simulation analysis, the overall tensioned prestressed cable structure is simulated first, and then the deflection values and cable stresses generated by the radial beams and struts on the upper part of the cable are installed, providing a basis for tensioning the cable structure to the design state at one time.
[0060] Based on Example 2, this Example 3 provides a more preferred method for finite element simulation analysis of prestressed cable structure tensioning, specifically: when the prestressed cable structure is tensioned and analyzed by finite element simulation, the overall tensioned prestressed cable structure is simulated first, and then the deflection value and cable stress generated by the radial beams and struts on the upper part of the cable are installed, providing a basis for tensioning the cable structure to the design state at one time. The present invention has fast installation, low construction cost, high construction quality, and provides tension compensation through finite element simulation, which can effectively solve the technical problem of downward deformation of the front end of the roof.
[0061] Example 4.
[0062] like Figure 1-12As shown, the present invention provides a large-span spoke-type cable-supported roof canopy without a support frame, and the construction includes the following steps:
[0063] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0064] Step 2: hoisting of outer ring beam;
[0065] Step 3: Install the radial cable and the annular cable in place;
[0066] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0067] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0068] In the step 2, when the outer ring beam is hoisted, a 400t crawler crane is used for off-site hoisting, and the construction is carried out in a clockwise direction, symmetrically from area A to area C and from area B to area D.
[0069] Based on Example 2, this Example 4 provides a more preferred method for hoisting the outer ring beam, specifically: when hoisting the outer ring beam, the 400t crawler crane is used for off-site hoisting, and the construction is carried out in a clockwise direction, from area A to area C, and from area B to area D symmetrically. The steel structure part within the outer ring beam of the canopy of the present invention does not require a support frame, which can effectively reduce the amount of measures and provide a large number of construction sites for the stands and internal venues of the stadium. The present invention adopts symmetrical construction in different zones, which can effectively speed up the construction progress, and can also help reduce the cumulative error caused by hoisting, and is closer to the design state.
[0070] Example 5.
[0071] like Figure 1-12 As shown, the present invention provides a large-span spoke-type cable-supported roof canopy without a support frame, and the construction includes the following steps:
[0072] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0073] Step 2: hoisting of outer ring beam;
[0074] Step 3: Install the radial cable and the annular cable in place;
[0075] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0076] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0077] In the step 2, when the outer ring beam is hoisted, a 400t crawler crane is used for off-site hoisting, and the construction is carried out in a clockwise direction, symmetrically from area A to area C and from area B to area D.
[0078] The outer ring beam is installed by assembling it into unit modules on the ground, then hoisting them one by one, and finally installing the rods between adjacent units.
[0079] Based on Example 4, this Example 5 provides a more preferred method for hoisting the outer ring beam, specifically: the outer ring beam is installed by assembling it into unit modules on the ground, then hoisting them in sequence, and finally installing the rods between adjacent units. The steel structure part within the outer ring beam of the canopy of the present invention does not require a support frame, which can effectively reduce the amount of measures and provide a large number of construction sites for the stands and internal areas of the stadium.
[0080] Example 6.
[0081] like Figure 1-12 As shown, the present invention provides a large-span spoke-type cable-supported roof canopy without a support frame, and the construction includes the following steps:
[0082] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0083] Step 2: hoisting of outer ring beam;
[0084] Step 3: Install the radial cable and the annular cable in place;
[0085] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0086] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0087] In the step three, when the radial cables and the annular cables are installed in place, the prestressed cables are tensioned according to the finite element simulation results; a bracket is set up for the annular cables, and the cables are hoisted into place using tooling cables; and the radial cables and the annular cables are connected in the air at the bracket position.
[0088] Based on Example 2, this Example 6 provides a more preferred method for installing the radial cables and the annular cables in place, specifically: when the radial cables and the annular cables are installed in place, the prestressed cables are tensioned according to the finite element simulation results; a bracket is set up for the annular cables, and the cables are hoisted into place using tooling cables; the radial cables and the annular cables are connected in the air at the bracket position. The design of the present invention is scientific and reasonable, which can effectively reduce the number of on-site support frames, reduce the amount of high-altitude operations, and effectively speed up the progress of on-site construction. The present invention has fast installation, low construction cost, high construction quality, and provides tensioning compensation through finite element simulation, which can effectively solve the technical problem of downward deformation of the front end of the roof. The steel structure part within the outer ring beam of the canopy of the present invention does not require a support frame, which can effectively reduce the amount of measures and provide a large number of construction sites for the stands and internal venues of the stadium.
[0089] Example 7.
[0090] like Figure 1-12 As shown, the present invention provides a large-span spoke-type cable-supported roof canopy without a support frame, and the construction includes the following steps:
[0091] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0092] Step 2: hoisting of outer ring beam;
[0093] Step 3: Install the radial cable and the annular cable in place;
[0094] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0095] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0096] In step 4, the upper prestressed cable chord trusses are hoisted symmetrically in the clockwise direction in the AC area and the BD area, and the lower part of the truss is connected to the cable by a pin; the chord trusses are first assembled on the ground, and radially divided into module 1 and module 2, which are hoisted from the inside and outside of the large-span spoke-type cable-supported roof canopy by a 400t crawler.
[0097] Based on Example 2, this Example 7 provides a more preferred method for symmetrically hoisting the upper prestressed cable string truss in the clockwise direction, specifically: the AC zone and the BD zone are symmetrically hoisted along the clockwise direction. The lower part of the truss is connected to the cable by a pin; the string truss is first assembled on the ground, and is divided into module 1 and module 2 along the radial direction, and is hoisted from the inside and outside of the large-span spoke-type cable-supported roof canopy by a 400t crawler. The present invention has fast installation, low construction cost, high construction quality, and provides tension compensation through finite element simulation, which can effectively solve the technical problem of downward deformation of the front end of the roof. The steel structure part within the outer ring beam of the canopy of the present invention does not require a support frame, which can effectively reduce the amount of measures and provide a large number of construction sites for the stands and internal venues of the stadium. Each radial string truss of the present invention is hoisted in two modules, which can effectively ensure the installation accuracy and speed up the hoisting speed. The present invention adopts symmetrical construction in different zones, which can effectively speed up the construction progress, and can also help reduce the cumulative error caused by hoisting, and is closer to the design state.
[0098] Example 8.
[0099] like Figure 1-12 As shown, the present invention provides a large-span spoke-type cable-supported roof canopy without a support frame, and the construction includes the following steps:
[0100] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0101] Step 2: hoisting of outer ring beam;
[0102] Step 3: Install the radial cable and the annular cable in place;
[0103] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0104] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0105] In step 4, the upper prestressed cable chord trusses are hoisted symmetrically in the clockwise direction in the AC area and the BD area, and the lower part of the truss is connected to the cable by a pin; the chord trusses are first assembled on the ground, and radially divided into module 1 and module 2, which are hoisted from the inside and outside of the large-span spoke-type cable-supported roof canopy by a 400t crawler.
[0106] Based on Example 7, this Example 8 provides a more preferred method for hoisting the upper prestressed cable string truss symmetrically in the clockwise direction, specifically: first hoist two modules 2 on the outside of the large-span spoke-type cable-supported roof canopy, then install the annular rods between the two adjacent modules to form a stable structure, and then hoist a module 1 from the inside. The steel structure part within the outer ring beam of the canopy of the present invention does not require a support frame, which can effectively reduce the amount of measures and provide a large amount of construction space for the stadium stands and internal venues. Each radial string truss of the present invention is hoisted in two modules, which can effectively ensure the installation accuracy and speed up the hoisting speed.
[0107] Example 9.
[0108] like Figure 1-12 As shown, the present invention provides a large-span spoke-type cable-supported roof canopy without a support frame, and the construction includes the following steps:
[0109] Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure;
[0110] Step 2: hoisting of outer ring beam;
[0111] Step 3: Install the radial cable and the annular cable in place;
[0112] Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction;
[0113] Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
[0114] In step 4, the upper prestressed cable chord trusses are hoisted symmetrically in the clockwise direction in the AC area and the BD area, and the lower part of the truss is connected to the cable by a pin; the chord trusses are first assembled on the ground, and radially divided into module 1 and module 2, which are hoisted from the inside and outside of the large-span spoke-type cable-supported roof canopy by a 400t crawler.
[0115] In step five, the circumferential rods between adjacent modules 1 are hoisted in sequence according to the above construction sequence until the overall canopy is installed.
[0116] Based on Example 8, this Example 9 provides a more preferred method of sequentially hoisting along the above construction sequence until the overall canopy is installed, specifically: sequentially hoisting along the above construction sequence, supplementing the annular rods between adjacent modules 1, until the overall canopy is installed. The present invention adopts partitioned symmetrical construction, which can effectively speed up the construction progress, and can also help reduce the cumulative error caused by hoisting, and is closer to the design state.
[0117] The present invention provides a method for constructing a large-span spoke-type cable-supported roof canopy without a support frame, which reduces the number of on-site support frames, reduces high-altitude operations, and speeds up on-site progress. This method uses "crawler crane + truck crane" for hoisting. The large-span spoke-type cable-supported roof canopy is generally divided into four major construction areas, such as ABCD. Figure 2 As shown. The AC area and the BD area are constructed symmetrically. At the same time, hoisting channels (the basement floor needs to be reinforced under the channel) and structural assembly sites are set up inside and outside the stands.
[0118] The construction method of the present invention is as follows:
[0119] Step 1: Conduct finite element simulation analysis to first simulate the overall tensioned prestressed cable structure, and then install the radial beams and struts on the upper part of the cable to generate the deflection value and cable stress, providing a basis for tensioning the cable structure to the design state at one time.
[0120] Step 2: Hoisting of the outer ring beam. Hoisting is done by a 400t crawler crane outside the site. Construction direction: clockwise, symmetrical hoisting from area A to area C, and from area B to area D. The outer ring beam is installed by assembling it into unit modules on the ground, then hoisting them one by one, and finally installing the rods between adjacent units. Figure 3 shown.
[0121] Step 3: Install the radial and annular cables in place, and tension the prestressed cables according to the finite element simulation results. The annular cables need to be supported by a bracket, and the cables are hoisted into place using a tooling cable. The radial and annular cables are connected in the air at the bracket position. Figure 4 and Figure 5 shown.
[0122] Step 4: In the AB area, symmetrically hoist the upper string truss of the prestressed cable in the clockwise direction. The lower part of the truss is connected to the cable with a pin. Figure 6 The string truss (radial steel beam + vertical strut) is first assembled on the ground and divided into module 1 and module 2 along the radial direction. Figure 7 As shown, 400t crawler cranes were used to lift the equipment from inside and outside the stadium.
[0123] Among them, Figure 8 As shown, two modules 2 are hoisted on the outside first, and then the annular rods between the two adjacent modules are installed to form a stable structure, such as Fig. 9 As shown; then hoist a module 1 from the inside, as shown Fig.10 shown.
[0124] Step 5: Install the annular rods between adjacent modules 1 in the order mentioned above until the whole canopy is installed. Fig.11 shown.
[0125] The present invention is scientifically and reasonably designed, can effectively reduce the number of on-site support frames, reduce the amount of high-altitude operations, and can effectively speed up the progress of on-site construction.
[0126] The invention has the advantages of fast installation, low construction cost, high construction quality, and providing tension compensation through finite element simulation, and can effectively solve the technical problem of downward deformation of the front end of the roof.
[0127] The steel structure part within the outer ring beam of the canopy of the present invention does not need a support frame, which can effectively reduce the amount of measures and provide a large amount of construction space for the stadium stands and internal venues.
[0128] Each radial tensioned truss of the present invention is divided into two modules for hoisting, which can effectively ensure the installation accuracy and accelerate the hoisting speed.
[0129] The present invention adopts zoned symmetrical construction, which can effectively speed up the construction progress, and can also help reduce the cumulative error caused by hoisting, and is closer to the design state.
[0130] Finally, it should be noted that the above embodiments are only preferred embodiments of the present invention to illustrate the technical solution of the present invention, but not to limit it, and certainly not to limit the patent scope of the present invention. Any changes or modifications that are made to the main design concept and spirit of the present invention without any substantial meaning, and the technical problems they solve are still consistent with the present invention, should be included in the protection scope of the present invention; in addition, the direct or indirect application of the technical solution of the present invention in other related technical fields is also included in the patent protection scope of the present invention.
Claims
1. A construction method for a large-span spoke-type cable-supported roof canopy without a support frame. It is characterized in that The large-span spoke-type cable-supported roof canopy is divided into Area A, Area C, Area B and Area D in a clockwise direction and constructed simultaneously. At the same time, hoisting passages and structural assembly sites are set up inside and outside the stands. Area AC and Area BD are constructed symmetrically.
2. A method for constructing a large-span spoke-type cable-supported roof canopy without a support according to claim 1, It is characterized in that The basement floor is reinforced under the lifting channel.
3. A method for constructing a large-span spoke-type cable-supported roof canopy without a support according to claim 1, It is characterized in that The construction process includes the following steps: Step 1: Conduct finite element simulation analysis on the tensioning of the prestressed cable structure; Step 2: hoisting of outer ring beam; Step 3: Install the radial cable and the annular cable in place; Step 4: hoist the upper chord truss of the prestressed cable symmetrically in a clockwise direction; Step 5: Lift in sequence according to the above construction sequence until the entire canopy is installed.
4. A method for constructing a large-span spoke-type cable-supported roof canopy without a support according to claim 3, It is characterized in that In the step 1, when the prestressed cable structure is tensioned and subjected to finite element simulation analysis, the overall tensioned prestressed cable structure is simulated first, and then the deflection values and cable stresses generated by the radial beams and struts on the upper part of the cable are installed, providing a basis for tensioning the cable structure to the design state at one time.
5. A method for constructing a large-span spoke-type cable-supported roof canopy without a support according to claim 3, It is characterized in that In the step 2, when the outer ring beam is hoisted, a 400t crawler crane is used for off-site hoisting, and the construction is carried out in a clockwise direction, symmetrically from area A to area C and from area B to area D.
6. A method for constructing a large-span spoke-type cable-supported roof canopy without a support according to claim 5, It is characterized in that The outer ring beam is installed by assembling it into unit modules on the ground, then hoisting them one by one, and finally installing the rods between adjacent units.
7. A method for constructing a large-span spoke-type cable-supported roof canopy without a support according to claim 3, It is characterized in that In the step 3, when the radial cables and the annular cables are installed in place, the prestressed cables are tensioned according to the finite element simulation results; a bracket is set up for the annular cables, and the cables are hoisted into place using tooling cables; The radial cables and the annular cables are connected at high altitude at the support position.
8. A method for constructing a large-span spoke-type cable-supported roof canopy without a support according to claim 3, It is characterized in that In the step 4, the upper string trusses of the prestressed cables are hoisted symmetrically in the AC area and the BD area in a clockwise direction, and the lower part of the truss is connected to the cables by a pin shaft; The string truss is first assembled on the ground and radially divided into module 1 and module 2, which are respectively hoisted from the inside and outside of the large-span spoke-type cable-supported roof canopy using a 400t crawler hoist.
9. A method for constructing a large-span spoke-type cable-supported roof canopy without a support according to claim 8, It is characterized in that First, two modules 2 are hoisted on the outside of the large-span spoke-type cable-supported roof canopy, and then the annular rods between the two adjacent modules are installed to form a stable structure, and then a module 1 is hoisted from the inside.
10. A bracket-free construction method for a large-span spoke-type cable-supported roof canopy according to claim 9, It is characterized in that In step five, the circumferential rods between adjacent modules 1 are hoisted in sequence according to the above construction sequence until the installation of the entire canopy is completed.
Citation Information
Patent Citations
Unsupported construction method of circular rope-supported grid structure
CN107246153A
Large-span arc-shaped steel structure without support in middle and construction method
CN111733978A
Installation method of middle pressing ring spoke type tensioning structure
CN112814247A
Inverse construction method for spoke type cable-supported grid structure
CN113700308A
Full-flexible spoke type cable net structure and tire-free overhead deformation integral lifting method thereof
CN114991305A
Cited By
Spoke type cable-supported grid roof support-free construction method
CN119332944A
A construction method without support for spoke-type cable-supported grid roof
CN119332944B