Earthwork volume calculation method and device and computer equipment
By obtaining the three-dimensional position of the excavation equipment, calculating the elevation parameters of the excavation site, and directly calculating the amount of earthwork, it solves the timeliness and accuracy problems caused by drone cruise, and achieves efficient and accurate calculation of earthwork volume.
Patent Information
- Application Number
- CN202410862071.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-28
- Publication Date
- 2024-10-08
AI Technical Summary
The existing earthwork volume calculation method relies on multiple drone cruises, resulting in poor timeliness, low accuracy and vulnerability to weather effects.
By obtaining the three-dimensional position of the preset start time and end time on the excavation equipment, determining the elevation parameters of the excavation site, and calculating the change in excavation and filling earthwork, avoiding the use of cruise image data, reducing calculation costs and improving accuracy .
This improves the timeliness and accuracy of earthwork volume calculations, reduces dependence on weather conditions, and simplifies the calculation process.
Smart Images

Figure CN118747253A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of measurement technology, and in particular to a method, device and computer equipment for calculating earthwork volume. Background Art
[0002] Earthwork measurement is an important part of civil engineering and plays an important role in civil engineering projects. With the increasing number of development and construction projects, how to accurately and efficiently measure the volume of excavated earthwork has become one of the most important issues in the early stage of project construction.
[0003] At present, the measurement of earthwork volume generally uses drones to conduct multiple inspections, and then generates two digital elevation models (Digital Orthophoto Map, DOM) and digital surface models (Digital Elevation Model, DSM) based on the previous and subsequent cruise images. Then, based on the features in the two DOMs and the elevation difference in the two DSMs, the excavation and filling volume of the excavation equipment is determined.
[0004] However, calculating the earthwork volume through the results of multiple drone cruises is time-consuming and labor-intensive, with poor timeliness, and is easily affected by weather conditions, resulting in poor accuracy in the calculation of earthwork volume. Summary of the invention
[0005] The purpose of this application is to provide a method, device and computer equipment for calculating earthwork volume in order to improve the accuracy of earthwork volume calculation while improving the timeliness of earthwork volume calculation.
[0006] To achieve the above purpose, the technical solution adopted in the embodiment of the present application is as follows:
[0007] In a first aspect, an embodiment of the present application provides a method for calculating earthwork volume, the method comprising:
[0008] Obtaining a three-dimensional position of a first reference point on the excavation device at a preset start time and a three-dimensional position of a second reference point on an excavation surface of an excavation site in the excavation device at a preset end time;
[0009] Determining a first elevation parameter of the excavation site at the preset starting time according to the three-dimensional position of the first reference point;
[0010] Determining a second elevation parameter of the excavation site at the preset end time according to the three-dimensional position of the second reference point;
[0011] The change amount of excavation and filling of the excavation equipment in the time period from the preset start time to the preset end time is determined according to the first elevation parameter and the second elevation parameter.
[0012] In a possible implementation, determining a first elevation parameter of the excavation site at the preset start time according to the three-dimensional position of the first reference point includes:
[0013] Determining a coordinate value of the first reference point in a preset vertical direction according to the three-dimensional position of the first reference point;
[0014] The first elevation parameter is determined according to the coordinate value of the first reference point in the preset vertical direction.
[0015] In a possible implementation, determining the second elevation parameter of the excavation site at the preset end time according to the three-dimensional position of the second reference point includes:
[0016] Determining the three-dimensional position of the maximum bounding rectangle of the excavation surface according to the three-dimensional position of the second reference point and the size parameters of the excavation surface;
[0017] The second elevation parameter is determined according to the three-dimensional position of the largest enclosing rectangle of the excavation surface.
[0018] In a possible implementation, determining the three-dimensional position of the maximum bounding rectangle of the excavation surface according to the three-dimensional position of the second reference point and the size parameters of the excavation site includes:
[0019] Determine, according to the three-dimensional position of the first point and the three-dimensional position of the second point in the second reference point, normal vectors of two planes perpendicular to each other in the three-dimensional space of a straight line from the first point to the second point;
[0020] According to the size parameters of the excavation surface and the normal vectors of the two planes, the three-dimensional position of the first point is projected onto the two planes to obtain the plane coordinates of two projection points of the first point on the two planes;
[0021] According to the size parameters of the excavation surface and the normal vectors of the two planes, the three-dimensional position of the second point is projected onto the two planes to obtain the plane coordinates of two projection points of the second point on the two planes;
[0022] The plane coordinates of the four projection points are converted into the three-dimensional space to obtain the three-dimensional position of the maximum bounding rectangle.
[0023] In one possible implementation, the method further includes:
[0024] Determine a straight line equation of another plane of the straight line in the three-dimensional space according to the three-dimensional position of the first point and the three-dimensional position of the second point;
[0025] Verifying the three-dimensional position of the maximum enclosing rectangle according to the straight line equation of the straight line in the other plane;
[0026] The step of determining the second elevation parameter according to the three-dimensional position of the maximum bounding rectangle of the excavation surface comprises:
[0027] If the verification is successful, the second elevation parameter is determined according to the three-dimensional position of the largest enclosing rectangle of the excavation surface.
[0028] In a possible implementation, determining the straight line equation of another plane of the straight line in the three-dimensional space according to the three-dimensional position of the first point and the three-dimensional position of the second point includes:
[0029] Determine the slopes of the straight line in the two planes according to the three-dimensional position of the first point and the three-dimensional position of the second point;
[0030] Calculate the slope of another plane of the straight line in the three-dimensional space according to the slopes of the straight line in the two planes;
[0031] The linear equation of the straight line in the other plane of the three-dimensional space is determined according to the slope of the other plane, and the three-dimensional position of the first point and the three-dimensional position of the second point.
[0032] In a possible implementation, determining the change in excavation and filling volume of the excavation equipment within a time period from the preset start time to the preset end time according to the first elevation parameter and the second elevation parameter includes:
[0033] Determine the digital surface model of the preset start time and the preset end time respectively according to the first elevation parameter and the second elevation parameter;
[0034] The change amount of excavation and filling in the time period is determined by using a preset spatial analysis function according to the digital ground surface model of the preset start time and the preset end time.
[0035] In one possible implementation, the method further includes:
[0036] Acquire a first digital elevation model of a preset area at the preset start time, and a second digital elevation model of the preset area at the preset end time;
[0037] Obtaining a digital image map at the preset starting time according to the first digital elevation model and the digital surface model at the preset starting time;
[0038] A digital image map for the preset end time is obtained according to the second digital elevation model and the digital surface model for the preset end time.
[0039] In a second aspect, another embodiment of the present application provides a device for calculating earthwork volume, the device comprising:
[0040] An acquisition module, used to acquire the three-dimensional position of a first reference point on the excavation device at a preset start time and the three-dimensional position of a second reference point on the excavation surface of the excavation part of the excavation device at a preset end time;
[0041] A first determination module, configured to determine a first elevation parameter of the excavation site at the preset start time according to the three-dimensional position of the first reference point;
[0042] A first determination module, configured to determine a second elevation parameter of the excavation site at the preset end time according to the three-dimensional position of the second reference point;
[0043] The comparison module is used to determine the change in excavation and filling of the excavation equipment within the time period from the preset start time to the preset end time according to the first elevation parameter and the second elevation parameter.
[0044] In the third aspect, another embodiment of the present application provides a computer device, comprising: a processor, a storage medium and a bus, wherein the storage medium stores machine-readable instructions executable by the processor, and when the computer device is running, the processor communicates with the storage medium through the bus, and the processor executes the machine-readable instructions to perform the steps of any method described in the first aspect above.
[0045] The present application provides a method, device and computer equipment for calculating earthwork volume. The method can obtain the three-dimensional position of a first reference point on an excavation device at a preset start time and the three-dimensional position of a second reference point on the excavation surface of an excavation site in the excavation device at a preset end time; determine a first elevation parameter of the excavation site at a preset start time based on the three-dimensional position of the first reference point; determine a second elevation parameter of the excavation site at a preset end time based on the three-dimensional position of the second reference point; and determine a change in excavation and filling earthwork of the excavation device during a time period from the preset start time to the preset end time based on the first elevation parameter and the second elevation parameter. The present application can determine the front and rear elevation parameters of the excavation site at a preset start time and a preset end time respectively according to the three-dimensional position of the first reference point at the preset start time and the three-dimensional position of the second reference point at the preset end time, and then calculate the amount of excavation and filling in the corresponding time period according to the front and rear elevation parameters. In the process of calculating the amount of excavation and filling, only the three-dimensional coordinates of each reference point are required, and no cruise image data is required. Therefore, there is no need to perform multiple cruises, which reduces the calculation cost and ensures timeliness. Moreover, since no drone cruise image is required, the calculated amount of excavation and filling will not be affected by weather conditions, thereby improving the accuracy of the calculation of the earthwork volume. BRIEF DESCRIPTION OF THE DRAWINGS
[0046] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0047] Figure 1 A schematic diagram of a flow chart of a method for calculating earthwork volume provided in an embodiment of the present application;
[0048] Figure 2 A flowchart of a method for determining a first elevation parameter provided in an embodiment of the present application;
[0049] Figure 3 A flowchart of a method for determining a second elevation parameter provided in an embodiment of the present application;
[0050] Figure 4 A schematic flow chart of a method for determining a maximum enclosing rectangle is provided for an embodiment of the present application;
[0051] Figure 5 A schematic diagram of a projection of a second reference point provided in an embodiment of the present application;
[0052] Figure 6A schematic diagram of the plane coordinates of a projection point of a second reference point provided in an embodiment of the present application;
[0053] Figure 7 A schematic flow chart of a method for verifying a three-dimensional coordinate point obtained is provided for an embodiment of the present application;
[0054] Figure 8 A schematic flow chart of a method for calculating a straight line equation is provided for an embodiment of the present application;
[0055] Fig. 9 A schematic flow chart of a method for calculating the change in excavation and filling earthwork is provided for an embodiment of the present application;
[0056] Fig.10 A schematic flow chart of a method for obtaining a digital image is provided for an embodiment of the present application;
[0057] Fig.11 A schematic diagram of an earthwork volume calculation device provided in Embodiment 5 of the present application;
[0058] Fig.12 A schematic diagram of the structure of a computer device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0059] To make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. It should be understood that the drawings in the present application only serve the purpose of explanation and description and are not used to limit the scope of protection of the present application. In addition, it should be understood that the schematic drawings are not drawn in real proportion. The flowchart used in this application shows the operations implemented according to some embodiments of the present application. It should be understood that the operations of the flowchart can be implemented out of sequence, and the steps without logical context can be reversed in order or implemented simultaneously. In addition, those skilled in the art can add one or more other operations to the flowchart under the guidance of the content of the present application, or remove one or more operations from the flowchart.
[0060] In addition, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various configurations. Therefore, the following detailed description of the embodiments of the present application provided in the drawings is not intended to limit the scope of the application claimed for protection, but merely represents the selected embodiments of the present application. Based on the embodiments of the present application, all other embodiments obtained by those skilled in the art without making creative work belong to the scope of protection of the present application.
[0061] It should be noted that the term "comprising" will be used in the embodiments of the present application to indicate the existence of the features declared thereafter, but does not exclude the addition of other features.
[0062] In order to clearly describe the methods provided by the embodiments of the present application, the earthwork volume calculation method provided by the embodiments of the present application is described in detail below through multiple embodiments in combination with the accompanying drawings. Figure 1 A flow chart of a method for calculating earthwork volume provided in an embodiment of the present application. The method for calculating earthwork volume can be executed by a computer device connected to multiple sensor devices installed on an excavation device. An excavation device can also be called an excavator, a digging machine, or a shovel machine. The excavation part of the excavation device can be called a bucket, and the excavation surface of the excavation part is the support surface where the tip of the bucket is located. Figure 1 As shown in FIG. 1 , the earthwork volume calculation method includes:
[0063] S101, obtaining a three-dimensional position of a first reference point on an excavation device at a preset start time and a three-dimensional position of a second reference point on an excavation surface of an excavation site in the excavation device at a preset end time.
[0064] The first reference point is the center point of the excavation equipment, and the second reference point of the excavation surface is the midline point of the two sides of the support surface where the shovel tip on the excavation surface is located that are parallel to the working direction. Before executing the solution of the present application, corresponding sensing devices can be deployed in advance at the first reference point and the second reference point, respectively, to collect the three-dimensional position of the corresponding reference point. The sensing device can be, for example, a three-dimensional space sensor or a spatial positioning sensor. Among them, the preset start time and the preset end time are the start time and end time of the corresponding monitoring time period of the excavation equipment pre-selected by the user.
[0065] In a possible implementation, multiple three-dimensional positions of the first reference point and multiple three-dimensional positions of the second reference point are obtained according to a preset time interval, and the multiple three-dimensional positions of the first reference point and the multiple three-dimensional positions of the second reference point are stored in a preset message queue. In response to a trigger operation for earthwork volume calculation at a preset start time and a preset end time, the three-dimensional position of the first reference point at the preset start time and the three-dimensional position of the second reference point at the preset end time are obtained from the preset message queue. The preset time interval may be, for example, 10s. The preset message queue may be, for example, a message queue telemetry transport protocol (Message Queuing Telemetry Transport, MQTT).
[0066] In the case where multiple three-dimensional positions of the first reference point are obtained, the multiple three-dimensional positions of the first reference point can be filtered, and after filtering, the three-dimensional positions are stored in a preset message queue. For the multiple three-dimensional positions of the first reference point, it can be: filtering out abnormal data that is too large or too small in the data of the multiple three-dimensional positions of the first reference point, and the position data of the mining equipment in the shutdown state.
[0067] In the case where multiple three-dimensional positions of the second reference point are obtained, the multiple three-dimensional positions of the second reference point can be filtered, and after filtering, the three-dimensional positions are stored in a preset message queue. For the multiple three-dimensional positions of the second reference point, it can be: filtering out abnormal data that is too large or too small in the data of the multiple three-dimensional positions of the second reference point, and position data that exceeds the corresponding range of the mining equipment.
[0068] The three-dimensional position of the first reference point can be expressed as (x0, y0, z0), for example. The second reference points include two reference points, point A and point B. The three-dimensional positions of the two second reference points can be expressed as A(x1, y1, z1) and B(x2, y2, z2), respectively.
[0069] S102: Determine a first elevation parameter of the excavation site at a preset starting time according to the three-dimensional position of the first reference point.
[0070] Whether it is the three-dimensional position of the first reference point or the three-dimensional position of the second reference point, it is the position coordinates of the first reference point and the second reference point in a preset three-dimensional coordinate system. The three-dimensional coordinate system includes: a three-dimensional coordinate system consisting of a longitude coordinate axis, a latitude coordinate axis and an elevation coordinate axis, wherein the longitude coordinate axis can be represented as an x-axis, the latitude coordinate axis can be represented as a y-axis, and the elevation coordinate axis can be represented as a z-axis.
[0071] At the preset start time, the excavation equipment has not yet performed the excavation and filling operation, that is, at this time, the excavation site is in a preset non-operation state, therefore, the first elevation parameter can be determined according to the three-dimensional position of the first reference point as the initial elevation parameter of the excavation site at the preset start time. The first elevation parameter can be expressed as (x0, y0, z0).
[0072] S103: Determine a second elevation parameter of the excavation site at a preset end time according to the three-dimensional position of the second reference point.
[0073] Since the posture of the excavation site will change during the excavation and filling operation of the excavation equipment, that is, the three-dimensional position of the second reference point on the excavation surface of the excavation site will change, therefore, in this embodiment, the second elevation parameter of the excavation site at the preset end time can be determined based on the three-dimensional position of the second reference point at the preset end time.
[0074] In a possible implementation, the three-dimensional position of the excavation surface can be determined based on the three-dimensional position of the second reference point, and then the second elevation parameter can be determined based on the three-dimensional positions of multiple endpoints on the excavation surface, that is, the second elevation parameter includes at least: the three-dimensional positions of four endpoints on the excavation surface, which can be expressed as (x3, y3, z3), (x4, y4, z4), (x5, y5, z5), and (x6, y6, z6), respectively.
[0075] S104. Determine, based on the first elevation parameter and the second elevation parameter, a change in the amount of earthwork cut and filled by the excavation equipment within a time period from a preset start time to a preset end time.
[0076] In a possible implementation, the amount of change in the digital surface within a time period from a preset start time to a preset end time can be determined based on the first elevation parameter and the second elevation parameter, and then the amount of change in excavation and filling within the time period can be calculated.
[0077] The present application provides a method for calculating earthwork volume, which can obtain the three-dimensional position of a first reference point on an excavation device at a preset start time and the three-dimensional position of a second reference point on the excavation surface of an excavation part in the excavation device at a preset end time; determine a first elevation parameter of the excavation part at the preset start time based on the three-dimensional position of the first reference point; determine a second elevation parameter of the excavation part at the preset end time based on the three-dimensional position of the second reference point; and determine a change in excavation and filling earthwork of the excavation device within a time period from the preset start time to the preset end time based on the first elevation parameter and the second elevation parameter. The present application can determine the front and rear elevation parameters of the excavation site at a preset start time and a preset end time respectively according to the three-dimensional position of the first reference point at the preset start time and the three-dimensional position of the second reference point at the preset end time, and then calculate the amount of excavation and filling in the corresponding time period according to the front and rear elevation parameters. In the process of calculating the amount of excavation and filling, only the three-dimensional coordinates of each reference point are required, and no cruise image data is required. Therefore, there is no need to perform multiple cruises, which reduces the calculation cost and ensures timeliness. Moreover, since no drone cruise image is required, the calculated amount of excavation and filling will not be affected by weather conditions, thereby improving the accuracy of the calculation of the earthwork volume.
[0078] Based on the above embodiments of the present application, a method for determining a first elevation parameter at a preset starting time is also provided. Figure 2 A flowchart of a method for determining a first elevation parameter provided in an embodiment of the present application. As in S102 of the above embodiment, determining a first elevation parameter of an excavation site at a preset start time according to the three-dimensional position of the first reference point includes:
[0079] S201. Determine a coordinate value of the first reference point in a preset vertical direction according to the three-dimensional position of the first reference point.
[0080] The three-dimensional position of the first reference point can be the three-dimensional coordinates of the first reference point under the preset three-dimensional coordinates, that is, (x0, y0, z0). Therefore, based on the three-dimensional position of the first reference point, the coordinate value of the first reference point in the preset vertical direction, that is, on the elevation coordinate axis, that is, z0, can be determined.
[0081] S202. Determine a first elevation parameter according to a coordinate value of a first reference point in a preset vertical direction.
[0082] In a possible implementation example, when determining the coordinate value z0 of the first reference point in a preset vertical direction, z0 can be directly used as the first elevation parameter. Of course, in some other possible implementation examples, z0 can also be fine-tuned, and the coordinate value after fine-tuning can be determined as the first elevation parameter.
[0083] In this embodiment, the first elevation parameter can be automatically determined based on the three-dimensional coordinates of the first reference point of the excavation equipment. There is no need to determine the first elevation parameter based on the cruise data of the drone, which simplifies the calculation method, reduces the calculation cost, and ensures the calculation accuracy.
[0084] Based on the above embodiment of the present application, a method for determining a second elevation parameter at a preset end time is also provided. Figure 3 A flowchart of a method for determining a second elevation parameter provided in an embodiment of the present application. As in S103 of the above embodiment, determining the second elevation parameter of the excavation site at a preset end time according to the three-dimensional position of the second reference point includes:
[0085] S301. Determine the three-dimensional position of the maximum bounding rectangle of the excavation surface according to the three-dimensional position of the second reference point and the size parameters of the excavation surface.
[0086] The size parameters of the excavation surface include the length and width of the excavation surface. The length of the excavation surface is the size of the excavation surface in the preset working direction, which can be expressed as L, and the width of the excavation surface is the size parallel to the preset working direction, which can be expressed as W.
[0087] In a possible implementation example, the second reference points A (x1, y1, z1) and B (x2, y2, z2) are known, where the distance between point A and point B is the length L of the shovel, and the side width W of the excavation surface where points A and B are located. The three-dimensional position of the maximum enclosing rectangle of the excavation surface can be calculated based on the coordinates of the second reference point in the preset three-dimensional coordinate system and the length and width of the excavation surface.
[0088] The three-dimensional coordinates of the maximum enclosing rectangle may include at least: the three-dimensional coordinates of the four endpoints of the maximum enclosing rectangle: (x3, y3, z3), (x4, y4, z4), (x5, y5, z5), (x6, y6, z6).
[0089] S302: Determine a second elevation parameter according to the three-dimensional position of the largest enclosing rectangle of the excavation surface.
[0090] In a possible implementation example, the coordinate value of each endpoint of the maximum enclosing rectangle in the preset vertical direction, that is, the value of the maximum enclosing rectangle in the z-axis direction in the preset three-dimensional coordinate system, is used as the second elevation parameter. For example, the three-dimensional position of the maximum enclosing rectangle includes: (x3, y3, z3), (x4, y4, z4), (x5, y5, z5), (x6, y6, z6), then it can be determined that the second elevation parameters include z3, z4, z5, z6.
[0091] In this embodiment, the second elevation parameter can be automatically determined based on the three-dimensional coordinates of the second reference point of the excavation surface. There is no need to determine the second elevation parameter based on the cruise data of the drone, which simplifies the calculation method, reduces the calculation cost, and ensures the calculation accuracy.
[0092] Based on the above embodiments of the present application, a method for determining a maximum enclosing rectangle is also provided. Figure 4 A schematic flow chart of a method for determining a maximum enclosing rectangle is provided for an embodiment of the present application. Figure 4 As shown, in S302 of the above embodiment, the second elevation parameter is determined according to the three-dimensional position of the largest enclosing rectangle of the excavation surface, including:
[0093] S401. Determine normal vectors of two planes perpendicular to each other in the three-dimensional space from the first point to the second point according to the three-dimensional position of the first point and the three-dimensional position of the second point in the second reference point.
[0094] The three-dimensional space can be the three-dimensional space where the three-dimensional coordinate system composed of the longitude coordinate axis, the latitude coordinate axis and the elevation coordinate axis is located, that is, the three-dimensional space composed of the x-coordinate axis, the y-coordinate axis and the z-coordinate axis, wherein the two mutually perpendicular planes are the xy plane composed of the longitude coordinate axis and the latitude coordinate axis and the xz plane composed of the longitude coordinate axis and the elevation coordinate axis.
[0095] Among them, when the second reference points are A (x1, y1, z1) and B (x2, y2, z2), the normal vector of the point is first calculated according to the slope formula based on the slopes of two mutually perpendicular planes of A and B in three-dimensional space.
[0096] In a possible implementation example, the slope of the straight line between the first point and the second point in the three-dimensional space is calculated by the three-dimensional positions of the first point and the second point in the second reference point at the preset end time, and the normal vectors of two planes perpendicular to each other in the three-dimensional space are calculated by the slope of the straight line.
[0097] In a possible implementation example, taking the xy plane and the xz plane as examples, the second reference points are A(x1, y1, z1) and B(x2, y2, z2). First, the slopes of the two points in the xy plane can be calculated. Slope in the xz plane The normal vector in the xy plane is The normal vector in the xz plane is
[0098] S402. Project the three-dimensional position of the first point onto the two planes according to the size parameters of the excavation surface and the normal vectors of the two planes to obtain the plane coordinates of two projection points of the first point on the two planes.
[0099] In a possible implementation example, based on the length L and width W of the excavation surface and the normal vector calculated above, the first point in the second reference point is projected to two planes to obtain the plane coordinates of the two projection points of the first point on the two planes.
[0100] In a possible implementation example, taking the xy plane and the xz plane as examples, when the slope of the first point in the xy plane is Normal vector in the xy plane Slope in the xz plane The normal vector in the xz plane is It can be calculated that the equation of the line at the first point A in the xy plane is y=y1-k1×(x-x1), the equation of the line at the xz plane is z=z1-k2×(x-x1), and the equation of the line normal to the first point A in the xy plane is The equation of the line with the normal vector of the xz plane at point A is According to the shovel tip width W of the shovel, the projection points of the first point on the two planes can be obtained: (x3, y3), (x3, z3) and (x4, y4), (x4, z4).
[0101] S403. Project the three-dimensional position of the second point onto the two planes according to the size parameters of the excavation surface and the normal vectors of the two planes to obtain the plane coordinates of two projection points of the second point on the two planes.
[0102] In a possible implementation example, according to the length L and width W of the excavation surface and the calculated normal vector, the second point in the second reference point is projected onto two planes to obtain the plane coordinates of two projection points of the second point on the two planes.
[0103] In one possible implementation example, when the slope of the second point in the xy plane The normal vector in the xy plane is Slope in the xz plane The normal vector in the xz plane is It can be calculated that the equation of the line at the second point B in the xy plane is y=y1-k1×(x-x1), the equation of the line at the xz plane is z=z1-k2×(x-x1), and the equation of the line normal to the second point B in the xy plane is The equation of the line with the normal vector of the second point B in the xz plane is According to the shovel tip width W of the shovel, the projection points of the second point on the two planes (x5, y5), (x5, z5) and (x6, y6), (x6, z6) can be obtained.
[0104] The following is an example of obtaining the maximum bounding rectangle through the second reference point in conjunction with the accompanying drawings: Figure 5 A schematic diagram of the projection of a second reference point provided in an embodiment of the present application. Figure 5 As shown, point A and point B are projected onto the xy axis and xz axis respectively according to their spatial positions to obtain the projected coordinate points. Figure 6 A schematic diagram of the plane coordinates of a projection point of a second reference point provided in an embodiment of the present application. Figure 6 As shown, Figure 6 -(a), project point A and point B on the xy axis, and translate the projection point left and right in the direction of the normal vector according to the width of the shovel tip, to obtain (x3, y3), (x4, y4), (x5, y5), (x6, y6). Figure 6 -As shown in (b), point A and point B are projected on the xz axis. According to the width of the shovel tip, the projection point is translated left and right in the direction of the normal vector to obtain (x3, z3), (x4, z4), (x5, z5), and (x6, z6).
[0105] S404: Convert the plane coordinates of the four projection points into three-dimensional space to obtain the three-dimensional position of the maximum bounding rectangle.
[0106] In a possible implementation example, the coordinate points in the above plane are regressed into the three-dimensional space to obtain the three-dimensional position of the maximum bounding rectangle.
[0107] In a possible implementation example, taking the xy plane and the xz plane as examples, after obtaining the projection points of the first point on the two planes (x3, y3), (x3, z3) and (x4, y4), (x4, z4), and the projection points of the second point on the two planes (x5, y5), (x5, z5) and (x6, y6), (x6, z6), the two-dimensional coordinates are converted into three-dimensional space to obtain the three-dimensional position of the maximum enclosing rectangle: (x3, y3, z3), (x4, y4, z4), (x5, y5, z5), (x6, y6, z6).
[0108] In this embodiment, the maximum enclosing rectangle is calculated by the width and length of the excavation surface, and the maximum excavation area within a preset time period and the height change value within the preset time period can be obtained. The process of obtaining data is simpler and the data obtained is more accurate and timely.
[0109] Based on the above embodiments of the present application, a method for verifying the acquired three-dimensional coordinate points is also provided. Figure 7 A flowchart of a method for verifying a three-dimensional coordinate point obtained is provided for an embodiment of the present application. Figure 7 As shown, in S404 of the above embodiment, the plane coordinates of the four projection points are converted into three-dimensional space to obtain the three-dimensional position of the maximum bounding rectangle, and further includes:
[0110] S501. Determine a straight line equation of another plane in the three-dimensional space according to the three-dimensional position of the first point and the three-dimensional position of the second point.
[0111] Among them, the other plane is a plane not involved in the above steps. In the embodiment of the present application, the other plane is the zy plane composed of the elevation coordinate axis and the latitude coordinate axis.
[0112] In a possible implementation example, after obtaining the calculated slope k1 of the xy plane and the slope k2 of the xz plane, the slope k1 of the xy plane and the slope k2 of the xz plane can be obtained by The value of the slope k3 of the yz plane is calculated. Based on k3, A(x1,y1,z1) and B(x2,y2,z2), it can be calculated that the equation of the straight line between points AB in the zy plane is y=y1-k3×(z-z1).
[0113] S502: Verify the three-dimensional position of the maximum enclosing rectangle according to the straight line equation of the straight line in another plane.
[0114] The verification refers to substituting the values of the four endpoints of the largest enclosing rectangle that have been obtained into the straight line equation in the zy plane to observe whether the straight line equation is valid after the substitution.
[0115] In a possible implementation example, the endpoints of the maximum enclosing rectangle of the second reference point corresponding to the end time are substituted into the straight line equation of another plane for verification.
[0116] In a possible implementation example, the three-dimensional coordinate points (x3, y3, z3), (x4, y4, z4), (x5, y5, z5), and (x6, y6, z6) of the maximum enclosing rectangle that have been obtained are substituted into the straight line equation of the zy plane y = y1-k3×(z-z1). If the left and right sides are equal, the endpoints of the maximum enclosing rectangle are verified.
[0117] As shown in S302 above, the second elevation parameter is determined according to the three-dimensional position of the largest enclosing rectangle of the excavation surface, including:
[0118] S503: If the verification is successful, determine the second elevation parameter according to the three-dimensional position of the largest enclosing rectangle of the excavation surface.
[0119] In a possible implementation example, when the endpoints of the maximum enclosing rectangle corresponding to the second reference point corresponding to the end time are substituted into the straight line equation of another plane and verified, the coordinates of the maximum enclosing rectangle in the vertical direction are recorded as the second elevation parameter.
[0120] In a possible implementation example, the three-dimensional coordinates of the largest enclosing rectangle of the rectangle are (x3, y3, z3), (x4, y4, z4), (x5, y5, z5), and (x6, y6, z6). The four points are substituted into the straight line equation of the zy plane y = y1-k3×(z-z1). If the equality of the left and right sides is verified, the vertical coordinates z3, z4, z5, and z6 of the four points are used as the second elevation parameters.
[0121] In this embodiment, by verifying the endpoints of the maximum enclosing rectangle according to the straight line equation of another plane, the accuracy of the data is ensured, the validity of the second elevation parameter obtained by the maximum enclosing rectangle is guaranteed, and the calculation result is more accurate.
[0122] Based on the above embodiments of the present application, a method for calculating the equation of a plane line is also provided. Figure 8 A schematic flow chart of a method for calculating a plane straight line equation is provided for an embodiment of the present application. Figure 8 As shown, in the above embodiment, in S501, according to the three-dimensional position of the first point and the three-dimensional position of the second point, the straight line equation of another plane in the three-dimensional space is determined, including:
[0123] S601. Determine the slopes of the straight line in two planes according to the three-dimensional position of the first point and the three-dimensional position of the second point.
[0124] The slopes of the first point and the second point in different planes can be obtained using the slope formula and the coordinates of the first point and the second point.
[0125] The slope k1 of the xy plane can be calculated by using the coordinates x1 and x2 of point A and point B on the x-axis and the coordinates y1 and y2 of point A and point B on the y-axis. Calculated The slope of the xz plane, k2, can be calculated by using the coordinates x1 and x2 of point A and point B on the x-axis and the coordinates z1 and z2 of point A and point B on the z-axis. Calculated
[0126] In a possible implementation example, the slope of a straight line formed by projecting the second reference point on two planes is determined by presetting the three-dimensional positions of the first point and the second point of the second reference point at the end time.
[0127] In a possible implementation example, taking the xy plane and the xz plane as examples, when the second reference points are A(x1, y1, z1) and B(x2, y2, z2), firstly, it can be calculated that the slopes of the two points in the xy plane are Slope in the xz plane
[0128] S602. Calculate the slope of the straight line in another plane in the three-dimensional space according to the slopes of the straight line in two planes.
[0129] Among them, if the coordinates of two points and the slopes of two planes in three-dimensional space are known, the slope of another plane in three-dimensional space can be calculated. In the three-dimensional coordinate system, if the slopes k1 and k2 of the other two planes are known, the formula for calculating the slope can be Calculate the slope k3 of the other plane.
[0130] In a possible implementation example, the slope of a straight line on another plane in the three-dimensional position is calculated based on the slope of a straight line formed by projecting the second reference point on two planes.
[0131] In a possible implementation example, after obtaining the calculated slope k1 of the xy plane and the slope k2 of the xz plane, the slope k1 of the xy plane and the slope k2 of the xz plane can be obtained by The slope k3 of the yz plane can also be calculated by The value of the slope k3 is calculated.
[0132] S603: Determine a line equation of the line in another plane of the three-dimensional space according to the slope of another plane and the three-dimensional position of the first point and the three-dimensional position of the second point.
[0133] Among them, the straight line equation of the line segment can be easily obtained by knowing the slope of the straight line and the positions of any two points.
[0134] In a possible implementation example, the straight line equation of another plane in the three-dimensional space is determined based on the slope of the straight line equation of another plane in the three-dimensional position obtained above and the three-dimensional position of the first point and the second point in the second reference point.
[0135] In a possible implementation example, based on k3, A(x1, y1, z1) and B(x2, y2, z2), it can be calculated that the equation of the straight line between points AB in the zy plane is y=y1-k3×(z-z1).
[0136] In this embodiment, by calculating the straight line equation of another plane in the three-dimensional space, the endpoint coordinates of the obtained maximum enclosing rectangle can be verified, making the endpoints of the calculated maximum enclosing rectangle more accurate, making the subsequent calculation of earthwork excavation and filling volume more accurate.
[0137] Based on the above embodiments of the present application, a method for calculating the change in excavation and filling earthwork is also provided. Fig. 9 A flow chart of a method for calculating the change in excavation and filling volume is provided for an embodiment of the present application. Fig. 9 As shown, in the above embodiment, S104 determines the change amount of excavation and filling of the excavation equipment in the time period from the preset start time to the preset end time according to the first elevation parameter and the second elevation parameter, including:
[0138] S701. Determine a digital surface model with a preset start time and a preset end time according to a first elevation parameter and a second elevation parameter.
[0139] Among them, before the earth excavation work is carried out, the initial digital surface model data is generated by cruising using a drone. After obtaining the first elevation parameter and the second elevation parameter, the first elevation parameter of the preset start time and the second elevation parameter of the preset end time are input into the initial digital surface model to obtain a new digital surface model corresponding to the elevation.
[0140] In a possible implementation example, a first elevation parameter of a preset start time is obtained, and after the first elevation parameter is input into an initial digital surface model, a digital surface model corresponding to the first elevation parameter is obtained, and a second elevation parameter of a preset end time is obtained, and after the second elevation parameter is input into the initial digital surface model, a digital surface model corresponding to the second elevation parameter is obtained.
[0141] In a possible implementation example, the first elevation parameter z0 obtained based on the center coordinates of the shovel is calculated, and z0 is input into the initial digital surface model to obtain the digital surface model corresponding to z0. The second elevation parameters z3, z4, z5, and z6 in the vertical direction of the maximum enclosing rectangle are calculated, and z3, z4, z5, and z6 are input into the initial digital surface model to obtain the digital surface models corresponding to z3, z4, z5, and z6.
[0142] S702: Determine the amount of earthwork change within a time period by using a preset spatial analysis function based on a digital ground surface model with a preset start time and a preset end time.
[0143] In a possible embodiment, the digital surface models of the start time and the end time are respectively inputted through a preset spatial analysis function, and the change amount of excavation and filling in the unit of time is obtained by calculation.
[0144] Among them, the spatial analysis function in this specific embodiment is CutFill(in_before_surface, in_after_surface, {z_factor}). In actual applications, the spatial analysis function may be other functions, and the embodiment of the present application does not limit this.
[0145] In a possible implementation example, the digital surface model corresponding to the first elevation parameter obtained at the preset initial time and the digital surface model corresponding to the second elevation parameter obtained at the preset end time are input into the value CutFill(in_before_surface, in_after_surface, {z_factor}), and the change in earth filling and excavation by the shovel within a certain period of time is calculated based on the function return value.
[0146] In this embodiment, it is only necessary to obtain the first elevation parameter of the preset initial time and the second elevation parameter of the preset end time. The change in earthwork excavation and filling within a certain period of time can be obtained by calculation. There is no need to use drones for multiple cruises, which saves manpower and material resources. The change in earthwork excavation and filling can also be obtained in real time through the calculation method of the maximum outer bounding rectangle. Computer programming can be used to quickly display the amount of excavated earthwork on the front end, and the transmission speed is fast, which optimizes the process of solving the earthwork volume.
[0147] Before excavating and filling earthwork, the embodiment of the present application needs to use drone cruising to obtain the digital elevation model and digital surface model within the range to be excavated and filled, and obtain the initial digital elevation model and initial digital surface model before excavating and filling earthwork. During the excavation and filling process, the message queue telemetry transport protocol (Message Queuing Telemetry Transport, MQTT) and Threejs's (MESH) grid technology are also used to obtain and render the transmission data every 10 seconds, and the obtained data is input into the initial digital elevation model and the initial digital surface model to obtain a new digital elevation model and a new digital surface model, and the excavation situation of the shovel is displayed in real time on the front end.
[0148] Based on the above embodiments of the present application, a method for obtaining a digital image is also provided. Fig.10 The present invention provides a flowchart of a method for obtaining a digital image. Fig.10 As shown, in the above embodiment, in S701, the digital surface model of the preset start time and the preset end time are determined according to the first elevation parameter and the second elevation parameter, and further includes:
[0149] S801: Acquire a first digital elevation model of a preset area at a preset start time, and a second digital elevation model of a preset area at a preset end time.
[0150] Among them, the digital elevation model is the initial data model obtained by drone cruising before earthwork excavation operations.
[0151] In a possible implementation example, a first digital orthoimage impact model corresponding to the first elevation parameter and a second digital orthoimage impact model corresponding to the second elevation parameter are obtained by inputting the first elevation parameter and the second high-level parameter into an initial numerical elevation model according to a first elevation parameter z0 of a start time and second elevation parameters z3, z4, z5, and z6 of an end time.
[0152] S802: Obtain a digital image map at a preset starting time according to the first digital elevation model and the digital surface model at a preset starting time.
[0153] In a possible implementation example, the digital elevation model and the digital surface model corresponding to the first elevation parameter z0 are combined to obtain a digital image map at the start time.
[0154] S803: Obtain a digital image map of the preset end time according to the second digital elevation model and the digital surface model of the preset end time. In a possible implementation example, the orthophoto influence model corresponding to the second elevation parameter and the digital surface model are combined to obtain a digital image map of the start time.
[0155] In a possible implementation example, the orthophoto influence model and the digital surface model corresponding to the first elevation parameters z3, z4, z5, and z6 corresponding to the preset end time are combined to obtain a digital image map of the start time.
[0156] In this embodiment, by displaying the excavation situation in real time, it is convenient to monitor the operating efficiency of the excavation equipment in real time during the construction process, provide timely feedback on abnormal conditions of the excavation equipment, and visualize the earth excavation and filling situation, so as to facilitate the observation of the earth excavation situation.
[0157] Based on the same inventive concept, an earthwork volume calculation device corresponding to the earthwork volume calculation method is also provided in the embodiment of the present application. Since the principle of solving the problem by the device in the embodiment of the present application is similar to the above-mentioned earthwork volume calculation method in the embodiment of the present application, the implementation of the device can refer to the implementation of the method, and the repeated parts will not be repeated.
[0158] Reference Fig.11 As shown, Fig.11 A schematic diagram of a device for calculating earthwork volume provided in an embodiment of the present application is shown in FIG. Fig. 9 The earthwork volume calculation device shown includes:
[0159] An acquisition module 91 is used to acquire the three-dimensional position of a first reference point on the excavation device at a preset start time and the three-dimensional position of a second reference point on the excavation surface of the excavation part of the excavation device at a preset end time;
[0160] A first determination module 92, for determining a first elevation parameter of the excavation site at a preset start time according to the three-dimensional position of the first reference point;
[0161] A second determination module 93, for determining a second elevation parameter of the excavation site at a preset end time according to the three-dimensional position of the second reference point;
[0162] The comparison module 94 is used to determine the change in the excavation and filling volume of the excavation equipment within a time period from a preset start time to a preset end time according to the first elevation parameter and the second elevation parameter.
[0163] In a possible implementation, the first determination module 92 is specifically used to: determine the coordinate value of the first reference point in a preset vertical direction according to the three-dimensional position of the first reference point; determine the first elevation parameter according to the coordinate value of the first reference point in the preset vertical direction.
[0164] In a possible implementation, the second determination module 93 is specifically used to: determine the three-dimensional position of the maximum enclosing rectangle of the excavation surface according to the three-dimensional position of the second reference point and the size parameters of the excavation surface; determine the second elevation parameter according to the three-dimensional position of the maximum enclosing rectangle of the excavation surface.
[0165] In one possible implementation, the second determination module 93 is specifically used to: determine the normal vectors of two planes perpendicular to each other in the three-dimensional space of the straight line from the first point to the second point based on the three-dimensional position of the first point and the three-dimensional position of the second point in the second reference point; project the three-dimensional position of the first point into the two planes based on the size parameters of the excavation surface and the normal vectors of the two planes to obtain the plane coordinates of two projection points of the first point on the two planes; project the three-dimensional position of the second point onto the two planes based on the size parameters of the excavation surface and the normal vectors of the two planes to obtain the plane coordinates of the two projection points of the second point on the two planes; convert the plane coordinates of the four projection points into the three-dimensional space to obtain the three-dimensional position of the maximum enclosing rectangle.
[0166] In a possible implementation, the second determination module 93 is also used to: determine the linear equation of the straight line in another plane in the three-dimensional space based on the three-dimensional position of the first point and the three-dimensional position of the second point; verify the three-dimensional position of the maximum enclosing rectangle based on the linear equation of the straight line in another plane; if the verification passes, determine the second elevation parameter based on the three-dimensional position of the maximum enclosing rectangle of the excavation surface.
[0167] In a possible implementation, the second determination module 93 is specifically used to: determine the slopes of the straight line in two planes based on the three-dimensional position of the first point and the three-dimensional position of the second point; calculate the slope of the straight line in another plane in the three-dimensional space based on the slope of the straight line in the two planes; determine the straight line equation of the straight line in another plane in the three-dimensional space based on the slope of the other plane, and the three-dimensional position of the first point and the three-dimensional position of the second point.
[0168] In a possible implementation, the comparison module 94 is specifically used to: determine the digital surface model of the preset start time and the preset end time respectively according to the first elevation parameter and the second elevation parameter; and determine the change in excavation and filling within the time period using a preset spatial analysis function based on the digital surface model of the preset start time and the preset end time.
[0169] In a possible implementation, the comparison module 94 is further used to: obtain a first digital elevation model of a preset area at a preset start time, and a second digital elevation model of the preset area at a preset end time; obtain a digital image map at the preset start time based on the first digital elevation model and the digital surface model at the preset start time; obtain a digital image map at the preset end time based on the second digital elevation model and the digital surface model at the preset end time.
[0170] For descriptions of the processing flow of each module in the device and the interaction flow between each module, reference may be made to the relevant descriptions in the above method embodiment, which will not be described in detail here.
[0171] The present application also provides a computer device, such as Fig.12 As shown, Fig.12 A schematic diagram of the structure of a computer device provided in an embodiment of the present application includes: a processor 101, a memory 102, and optionally, a bus 103. The memory 102 stores machine-readable instructions executable by the processor 101. When the computer device is running, the processor 101 communicates with the memory 102 through the bus 103. When the machine-readable instructions are executed by the processor 101, the steps of the earthwork volume calculation method provided in any of the above embodiments are performed.
[0172] Those skilled in the art can clearly understand that, for the convenience and simplicity of description, the specific working process of the system and device described above can refer to the corresponding process in the method embodiment, and will not be repeated in this application. In the several embodiments provided in this application, it should be understood that the disclosed system, device and method can be implemented in other ways. The device embodiments described above are merely schematic. For example, the division of the modules is only a logical function division. There may be other division methods in actual implementation. For example, multiple modules or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some communication interfaces, indirect coupling or communication connection of devices or modules, which can be electrical, mechanical or other forms.
[0173] In addition, each functional unit in each embodiment of the present application may be integrated into a processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. If the function is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product, which is stored in a storage medium and includes a number of instructions for a computer device (which may be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention.
[0174] The above are only specific implementation methods of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be covered by the protection scope of the present application.
Claims
1. A method for calculating earthwork volume, characterized in that: The method comprises: Obtaining a three-dimensional position of a first reference point on the excavation device at a preset start time and a three-dimensional position of a second reference point on an excavation surface of an excavation site in the excavation device at a preset end time; Determining a first elevation parameter of the excavation site at the preset starting time according to the three-dimensional position of the first reference point; Determining a second elevation parameter of the excavation site at the preset end time according to the three-dimensional position of the second reference point; The change amount of excavation and filling of the excavation equipment in the time period from the preset start time to the preset end time is determined according to the first elevation parameter and the second elevation parameter.
2. The method according to claim 1, characterized in that Determining a first elevation parameter of the excavation site at the preset starting time according to the three-dimensional position of the first reference point includes: Determining a coordinate value of the first reference point in a preset vertical direction according to the three-dimensional position of the first reference point; The first elevation parameter is determined according to the coordinate value of the first reference point in the preset vertical direction.
3. The method according to claim 1, characterized in that The step of determining a second elevation parameter of the excavation site at the preset end time according to the three-dimensional position of the second reference point includes: Determining the three-dimensional position of the maximum bounding rectangle of the excavation surface according to the three-dimensional position of the second reference point and the size parameters of the excavation surface; The second elevation parameter is determined according to the three-dimensional position of the largest enclosing rectangle of the excavation surface.
4. The method according to claim 3, characterized in that: Determining the three-dimensional position of the maximum bounding rectangle of the excavation surface according to the three-dimensional position of the second reference point and the size parameters of the excavation site includes: Determine, according to the three-dimensional position of the first point and the three-dimensional position of the second point in the second reference point, normal vectors of two planes perpendicular to each other in the three-dimensional space of a straight line from the first point to the second point; According to the size parameters of the excavation surface and the normal vectors of the two planes, the three-dimensional position of the first point is projected onto the two planes to obtain the plane coordinates of two projection points of the first point on the two planes; According to the size parameters of the excavation surface and the normal vectors of the two planes, the three-dimensional position of the second point is projected onto the two planes to obtain the plane coordinates of two projection points of the second point on the two planes; The plane coordinates of the four projection points are converted into the three-dimensional space to obtain the three-dimensional position of the maximum bounding rectangle.
5. The method according to claim 4, characterized in that The method further comprises: Determine a straight line equation of another plane of the straight line in the three-dimensional space according to the three-dimensional position of the first point and the three-dimensional position of the second point; Verifying the three-dimensional position of the maximum enclosing rectangle according to the straight line equation of the straight line in the other plane; The step of determining the second elevation parameter according to the three-dimensional position of the maximum bounding rectangle of the excavation surface comprises: If the verification is successful, the second elevation parameter is determined according to the three-dimensional position of the largest enclosing rectangle of the excavation surface.
6. The method according to claim 5, characterized in that Determining the straight line equation of another plane of the straight line in the three-dimensional space according to the three-dimensional position of the first point and the three-dimensional position of the second point includes: Determine the slopes of the straight line in the two planes according to the three-dimensional position of the first point and the three-dimensional position of the second point; Calculate the slope of another plane of the straight line in the three-dimensional space according to the slopes of the straight line in the two planes; The linear equation of the straight line in the other plane of the three-dimensional space is determined according to the slope of the other plane, and the three-dimensional position of the first point and the three-dimensional position of the second point.
7. The method according to claim 1, characterized in that The step of determining the change in the amount of earthwork cut and filled by the excavation equipment within a time period from the preset start time to the preset end time according to the first elevation parameter and the second elevation parameter includes: Determining a digital surface model of the preset start time and the preset end time respectively according to the first elevation parameter and the second elevation parameter; The change amount of excavation and filling in the time period is determined by using a preset spatial analysis function according to the digital ground surface model of the preset start time and the preset end time.
8. The method according to claim 7, characterized in that The method further comprises: Acquire a first digital elevation model of a preset area at the preset start time, and a second digital elevation model of the preset area at the preset end time; Obtaining a digital image map at the preset starting time according to the first digital elevation model and the digital surface model at the preset starting time; A digital image map for the preset end time is obtained according to the second digital elevation model and the digital surface model for the preset end time.
9. A method and device for calculating earthwork volume, characterized in that: include: An acquisition module, used to acquire the three-dimensional position of a first reference point on the excavation device at a preset start time and the three-dimensional position of a second reference point on the excavation surface of the excavation part of the excavation device at a preset end time; A first determination module, configured to determine a first elevation parameter of the excavation site at the preset start time according to the three-dimensional position of the first reference point; A second determination module, configured to determine a second elevation parameter of the excavation site at the preset end time according to the three-dimensional position of the second reference point; The comparison module is used to determine the change in excavation and filling of the excavation equipment within the time period from the preset start time to the preset end time according to the first elevation parameter and the second elevation parameter.
10. A computer device, characterized in that: include: A processor and a memory, wherein the memory stores machine-readable instructions executable by the processor, and when the computer device is running, the processor executes the machine-readable instructions to perform the steps of the earthwork volume calculation method as described in any one of claims 1 to 8.