Control method, processor and control device for arm type high-altitude operation equipment

By acquiring a variety of data on boom-type aerial work equipment, using preset deflection algorithms and deflection determination models to calculate deflection, and using PID controllers for adjustment, the problem of low control accuracy in the existing technology is solved and the stability of the equipment is improved. and security.

CN118754035APending Publication Date: 2024-10-11ZOOMLION INTELLIGENT ACCESS MASCH CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410779586.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-17
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

The control accuracy of arm-type aerial work platforms in the prior art is low, resulting in low deflection calculation accuracy and affecting the stability and safety of the equipment.

Method used

By obtaining the arm length, pitch angle, luffing cylinder position, telescopic cylinder position, load and wind detection data of the boom, the preset deflection algorithm and deflection determination model are used to calculate the deflection, and the PID controller is used to adjust the deflection to achieve accurate control.

Benefits of technology

It improves the position control accuracy of the boom aerial work platform, enhances the stability and safety of the equipment, and reduces the probability of accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118754035A_ABST
    Figure CN118754035A_ABST
Patent Text Reader

Abstract

The invention discloses a control method, a processor and a control device for arm type high-altitude operation equipment, and belongs to the technical field of engineering machinery. The method comprises the steps that the arm length and the pitch angle of a boom, the position of a variable-amplitude oil cylinder, the position of a telescopic oil cylinder, the load of an operation platform and wind power detection data of the arm type high-altitude operation equipment are obtained; through a preset deflection algorithm, the first deflection of the arm support is determined according to the arm length, the pitch angle and the load; determining a second deflection of the boom through a pre-constructed deflection determination model according to the position of the variable-amplitude oil cylinder, the position of the telescopic oil cylinder, the load and the wind power detection data; adding the first deflection and the second deflection to obtain a predicted deflection; adjusting the predicted deflection through a PID controller to obtain a target deflection; and controlling the arm type high-altitude operation equipment to operate according to the target deflection. The control precision of the arm type high-altitude operation equipment can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of engineering machinery, and in particular to a control method, a processor and a control device for arm-type aerial work equipment. Background Art

[0002] A boom-type aerial work platform is a device used to work at high altitudes. Since it needs to bear weight and external forces during use, the stability and safety of its structure need to be considered. Deflection refers to the bending deformation of an object when it is subjected to external forces. If the platform has excessive deflection during operation, it will affect its stability and safety, leading to accidents. In the prior art, the finite element method is usually used to calculate deflection, but the calculation accuracy of this method is affected by the modeling and boundary condition settings, and there is a problem of low accuracy. Summary of the invention

[0003] The purpose of the embodiments of the present application is to provide a control method, processor, control device, arm-type aerial work platform and storage medium for arm-type aerial work equipment, so as to solve the problem of low control accuracy of arm-type aerial work platforms in the prior art.

[0004] In order to achieve the above-mentioned purpose, the first aspect of the present application provides a control method for an arm-type aerial work equipment, the arm-type aerial work equipment comprising an arm frame, a work platform, a variable amplitude cylinder and a telescopic cylinder, the control method comprising:

[0005] Obtain the arm length and pitch angle of the boom, the luffing cylinder position of the luffing cylinder, the telescopic cylinder position of the telescopic cylinder, the load of the work platform, and the wind force detection data of the boom-type aerial work equipment;

[0006] By using a preset deflection algorithm, the first deflection of the boom is determined according to the boom length, the pitch angle and the load;

[0007] The second deflection of the boom is determined by using a pre-built deflection determination model according to the position of the boom cylinder, the position of the telescopic cylinder, the load, and the wind force detection data;

[0008] Adding the first deflection and the second deflection to obtain a predicted deflection;

[0009] The predicted deflection is adjusted by a PID controller to obtain the target deflection;

[0010] The operation of the boom-type aerial work equipment is controlled according to the target deflection.

[0011] In an embodiment of the present application, a first deflection of the boom is determined according to the arm length, the pitch angle and the load by a preset deflection algorithm, including: determining the end bending moment of the boom according to the arm length, the load of the working platform and the predetermined boom weight of the boom by a preset end bending moment algorithm; determining the first deflection of the boom according to the pitch angle, the arm length, the end bending moment and preset parameters of the boom by a preset deflection algorithm; wherein the preset deflection algorithm includes formula (1):

[0012]

[0013] Among them, δ d is the first deflection, M is the end bending moment, θ is the pitch angle, L is the arm length of the boom, E is the material elastic modulus constant in the preset parameters of the boom, and I is the moment of inertia constant of the section in the preset parameters of the boom.

[0014] In an embodiment of the present application, construction of a deflection determination model includes: acquiring multiple sets of environmental data of the boom during amplitude variation and telescopic movement; constructing a training set based on the multiple sets of environmental data through a pre-constructed forward kinematics model; and training the target model through the training set to obtain the deflection determination model.

[0015] In an embodiment of the present application, the environmental data includes the position of the boom cylinder, the position of the telescopic cylinder, wind detection data, the actual position of the end of the boom and the load of the work platform. A training set is constructed according to multiple groups of environmental data through a pre-constructed positive kinematic model, including: determining the expected position of the end of the boom corresponding to each group of environmental data according to the position of the boom cylinder and the telescopic cylinder through a pre-constructed positive kinematic model; determining the actual deflection according to the actual position of the end and the corresponding expected position of the end; determining the deflection error corresponding to each group of environmental data according to the actual deflection and the corresponding first deflection; and constructing a training set according to each group of environmental data and the corresponding deflection error.

[0016] In an embodiment of the present application, the control parameters of the PID controller include a proportional coefficient, an integral coefficient and a differential coefficient. The predicted deflection is adjusted by the PID controller to obtain a target deflection, including: determining the initial control parameters of the PID controller; respectively determining the partial derivative values ​​of the predicted deflection with respect to the initial control parameters; updating the control parameters of the PID controller according to the partial derivative values, the initial control parameters and a preset learning rate through a gradient descent algorithm; and adjusting the predicted deflection according to the updated control parameters to obtain the target deflection.

[0017] In an embodiment of the present application, the initial control parameters of the PID controller are determined, including: setting the integral coefficient and the differential coefficient to 0; increasing the proportional coefficient according to a preset rule until the PID controller produces continuous oscillation, and recording the proportional coefficient value and the oscillation period when the PID controller produces continuous oscillation; determining the initial control parameters of the PID controller according to the proportional coefficient value and the oscillation period.

[0018] A second aspect of the present application provides a processor configured to execute the control method for arm-type aerial work equipment according to the above-mentioned method.

[0019] The third aspect of the present application provides a control device for arm-type aerial work equipment, including: an acquisition module, used to obtain the arm length and pitch angle of the boom, the boom cylinder position of the boom cylinder, the telescopic cylinder position of the telescopic cylinder, the load of the work platform and the wind detection data of the arm-type aerial work equipment; a first deflection determination module, used to determine the first deflection of the boom according to the arm length, pitch angle and load through a preset deflection algorithm; a second deflection determination module, used to determine the second deflection of the boom according to the boom cylinder position, telescopic cylinder position, load and wind detection data through a pre-built deflection determination model; a predicted deflection determination module, used to add the first deflection and the second deflection to obtain a predicted deflection; an adjustment module, used to adjust the predicted deflection through a PID controller to obtain a target deflection; and a control module, used to control the operation of the arm-type aerial work equipment according to the target deflection.

[0020] A fourth aspect of the present application provides an arm-type aerial work platform, comprising a processor according to the above or a control device for an arm-type aerial work equipment.

[0021] A fifth aspect of the present application provides a machine-readable storage medium having instructions stored thereon, the instructions being used to enable a machine to execute the above-mentioned control method for arm-type aerial work equipment.

[0022] Through the above technical scheme, the arm length and pitch angle of the boom, the position of the boom cylinder of the boom cylinder, the position of the telescopic cylinder of the telescopic cylinder, the load of the work platform and the wind detection data of the boom-type aerial work equipment are first obtained, and then the first deflection of the boom is determined according to the arm length, pitch angle and load through a preset deflection algorithm, and the second deflection of the boom is determined according to the position of the boom cylinder, the position of the telescopic cylinder, the load and the wind detection data through a pre-constructed deflection determination model, and then the first deflection and the second deflection are added to obtain a predicted deflection, and finally the predicted deflection is adjusted by a PID controller to obtain a target deflection, and the operation of the boom-type aerial work equipment is controlled according to the target deflection. The present application can accurately predict the deflection of the boom, thereby improving the position control accuracy of the aerial work platform.

[0023] Other features and advantages of the embodiments of the present application will be described in detail in the subsequent specific implementation section. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] The accompanying drawings are used to provide a further understanding of the embodiments of the present application and constitute a part of the specification. Together with the following specific implementations, they are used to explain the embodiments of the present application, but do not constitute a limitation on the embodiments of the present application. In the accompanying drawings:

[0025] Figure 1 A flow chart schematically shows a control method for an arm-type aerial work equipment according to an embodiment of the present application;

[0026] Figure 2 A coordinate system modeling diagram of an arm-type aerial work equipment according to an embodiment of the present application is schematically shown;

[0027] Figure 3 The structure of a control device for an arm-type aerial work equipment according to an embodiment of the present application is schematically shown.

[0028] Description of Reference Numerals

[0029] 301 Acquisition module 302 First deflection determination module

[0030] 303 Second deflection determination module 304 Predicted deflection determination module

[0031] 305 Adjustment module 306 Control module DETAILED DESCRIPTION

[0032] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. It should be understood that the specific implementation methods described herein are only used to illustrate and explain the embodiments of the present application, and are not used to limit the embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0033] It should be noted that if the embodiments of the present application involve directional indications (such as up, down, left, right, front, back...), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0034] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present application, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or suggesting their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such combination of technical solutions does not exist and is not within the scope of protection required by this application.

[0035] Figure 1 The flowchart of a control method for an arm-type aerial work equipment according to an embodiment of the present application is schematically shown. Figure 1 As shown, the embodiment of the present application provides a control method for an arm-type aerial work equipment, the arm-type aerial work equipment includes an arm frame, a work platform, a variable amplitude cylinder and a telescopic cylinder. Taking the method applied to a processor as an example, the method may include the following steps:

[0036] Step S101: Acquire the arm length and pitch angle of the boom, the luffing cylinder position of the luffing cylinder, the telescopic cylinder position of the telescopic cylinder, the load of the work platform, and the wind force detection data of the boom-type aerial work equipment.

[0037] Step S102: Determine the first deflection of the boom according to the arm length, pitch angle and load using a preset deflection algorithm.

[0038] Step S103: Determine the second deflection of the boom by using the pre-constructed deflection determination model and according to the position of the boom cylinder, the position of the telescopic cylinder, the load and the wind force detection data.

[0039] Step S104: Add the first deflection and the second deflection to obtain the predicted deflection.

[0040] Step S105: adjusting the predicted deflection by a PID controller to obtain a target deflection.

[0041] Step S106: Controlling the operation of the boom-type aerial work equipment according to the target deflection.

[0042] It can be understood that the deflection of the boom can be divided into a deterministic part and an uncertain part. Among them, the deterministic deflection is the deflection generated based on the deterministic load, and the deterministic load includes the load of the working platform of the arm-type aerial work equipment and the deadweight of the boom. In addition to the deterministic load, the deflection of the boom is also affected by a variety of uncertain factors. The deflection caused by uncertain factors is uncertain deflection, also known as deflection error. Uncertain factors include material properties, geometric dimensions, fatigue and damage, wind loads, etc. In an embodiment of the present application, the first deflection is a deterministic deflection, and the second deflection is an uncertain deflection.

[0043] Specifically, the processor obtains the arm length and pitch angle of the boom, the boom cylinder position of the boom cylinder, the telescopic cylinder position of the telescopic cylinder, the load of the work platform, and the wind detection data of the arm-type aerial work equipment in real time, wherein the work platform load includes the sum of the work platform's own weight and other loads on the work platform. The end bending moment M of the boom is a key parameter in the calculation process of the deterministic deflection. Therefore, the processor first calculates the end bending moment according to the acquired parameters, and then calculates the deterministic deflection of the boom according to the arm length, pitch angle and load through the preset deflection algorithm, that is, the first deflection. Then, in order to deal with the deflection calculation error caused by uncertain factors, a machine learning method can be used to calculate the deflection compensation amount, that is, the second deflection, that is, the current boom cylinder position, telescopic cylinder position, load and wind detection data are input into the pre-built deflection determination model, and the output is the uncertain deflection, that is, the second deflection. The predicted deflection is obtained by adding the first deflection and the second deflection, and the formula is δ=δ d +δ e Among them, δ d is the first deflection, δ e is the second deflection, and δ is the predicted deflection. In order to compensate for the deformation of the boom, after the predicted deflection is calculated, a PID controller is used to adjust it, with the predicted deflection as input and the target deflection as output. The boom operation is controlled according to the output target deflection, which can improve the control accuracy of the boom.

[0044] Through the above technical scheme, the arm length and pitch angle of the boom, the position of the boom cylinder of the boom cylinder, the position of the telescopic cylinder of the telescopic cylinder, the load of the work platform and the wind detection data of the boom-type aerial work equipment are first obtained, and then the first deflection of the boom is determined according to the arm length, pitch angle and load through a preset deflection algorithm, and the second deflection of the boom is determined according to the position of the boom cylinder, the position of the telescopic cylinder, the load and the wind detection data through a pre-constructed deflection determination model, and then the first deflection and the second deflection are added to obtain a predicted deflection, and finally the predicted deflection is adjusted by a PID controller to obtain a target deflection, and the operation of the boom-type aerial work equipment is controlled according to the target deflection. The present application can accurately predict the deflection of the boom, thereby improving the position control accuracy of the aerial work platform.

[0045] In the embodiment of the present application, step S102: determining the first deflection of the boom according to the arm length, the pitch angle and the load by using a preset deflection algorithm may include: determining the end bending moment of the boom according to the arm length, the load of the working platform and the predetermined boom weight of the boom by using a preset end bending moment algorithm; determining the first deflection of the boom according to the pitch angle, the arm length, the end bending moment and preset parameters of the boom by using a preset deflection algorithm; wherein the preset deflection algorithm includes formula (1):

[0046]

[0047] Among them, δ d is the first deflection, M is the end bending moment, θ is the pitch angle, L is the arm length of the boom, E is the material elastic modulus constant in the preset parameters of the boom, and I is the moment of inertia constant of the section in the preset parameters of the boom.

[0048] Specifically, the first deflection is the deterministic deflection caused by the deterministic load, and the deterministic load includes the load of the working platform and the deadweight of the boom. Among them, the load of the working platform refers to the sum of the weight of the working platform and other loads on the working platform. The load P of the working platform can be obtained by a weighing sensor. In practical applications, the cross-sectional shape of the boom is a rectangular hollow structure. In order to calculate the deadweight G of the boom, the cross-sectional area must be determined first. Let B be the width of the outer rectangle of the cross-section, T be the height of the outer rectangle of the cross-section, b be the width of the inner rectangle of the cross-section, and t be the height of the inner rectangle of the cross-section. Then the cross-sectional area A of the outer rectangle is outer =B×T, the cross-sectional area of ​​the inner rectangle is A inner = b × t, the actual area of ​​the hollow rectangular interface of the arm is A = A outer -A inner . Since the boom will be extended and retracted during the operation of the boom-type aerial work equipment, the boom length L includes the initial length L0 of the boom and the extension amount ΔL. The volume of the boom V = A × (L0 + ΔL), and the deadweight of the boom G = ρ × g × V. The end bending moment M of the boom is a key parameter in the calculation process of the deterministic deflection, and its calculation formula is: M = P × L + G × L / 2. After calculating the above parameters, the deterministic deflection of the boom, that is, the first deflection, can be calculated according to the preset deflection algorithm, wherein the preset deflection algorithm is shown in formula (1), which establishes the relationship between the bending moment and the vertical deflection according to the Euler-Bernoulli beam theory.

[0049] In an embodiment of the present application, the environmental data includes the position of the boom cylinder, the position of the telescopic cylinder, wind detection data, the actual position of the end of the boom and the load of the work platform. A training set is constructed according to multiple groups of environmental data through a pre-constructed positive kinematic model, including: determining the expected position of the end of the boom corresponding to each group of environmental data according to the position of the boom cylinder and the telescopic cylinder through a pre-constructed positive kinematic model; determining the actual deflection according to the actual position of the end and the corresponding expected position of the end; determining the deflection error corresponding to each group of environmental data according to the actual deflection and the corresponding first deflection; and constructing a training set according to each group of environmental data and the corresponding deflection error.

[0050] It can be understood that material properties refer to the elastic modulus, Poisson's ratio and density of the material, which may have a certain range of variation, and these changes will affect the stiffness and deflection of the boom; geometric dimensions refer to the tolerances and errors in the manufacturing process that may cause the geometric dimensions of the boom to differ from the design values, and these differences will affect the calculation of the section moment of inertia and deflection; fatigue and damage refer to the possibility of fatigue or damage to the boom during long-term operation, resulting in increased deflection. Wind load refers to the influence of wind load on the deflection when the aerial work platform is working in a high wind speed environment.

[0051] Specifically, in order to deal with the deflection calculation error caused by uncertain factors, a machine learning method can be used to calculate the deflection compensation amount, that is, the second deflection. In order to train the machine learning deflection determination model, it is first necessary to collect environmental data to construct a training set. Among them, the environmental data includes the position of the boom cylinder, the position of the telescopic cylinder, wind force detection data (wind speed and wind direction), the actual position of the end of the boom, and the load of the working platform. The boom is controlled online to perform variable amplitude and telescopic movements, and the position of the boom cylinder x1, the position of the telescopic cylinder x2, the load P of the working platform, and the wind speed v w With wind direction w , the actual position of the end of the boom x real Among them, the position of the boom cylinder and the telescopic cylinder can be obtained through the pull-wire sensors of the boom cylinder and the telescopic cylinder respectively; the load of the working platform can be obtained through the weighing sensor; the wind speed and wind direction can be obtained by the anemometer installed on the working platform; the actual position of the boom end can be obtained by the total station electronic distance meter. Through the pre-established positive kinematic model, combined with the position of the boom cylinder x1 and the position of the telescopic cylinder x2, the expected position x of the end of the boom can be obtained. d , and compare it with the actual position x at the end of the boom real By subtracting, we can get the actual deflection δ of the boom. real , the actual deflection δ real and the deterministic flexibility δ d The deflection error δ can be obtained by subtracting e , that is, δ e =xreal -x d -δ d In this way, multiple sets of environmental data and their corresponding deflection errors are obtained. According to the environmental data and the corresponding deflection errors, a training set can be constructed to train the target model. During the training process, the model input is X = (x1, x2, P, v w , d w ), the model output is δ e .

[0052] Figure 2 A coordinate system modeling diagram of an arm-type aerial work equipment according to an embodiment of the present application is schematically shown. Figure 2 As shown, in the embodiment of the present application, the DH method is used to model the coordinate system of the boom-type aerial work platform, thereby obtaining the kinematic model of the top of the boom. Among them, the positive kinematic equation of the top of the boom is as follows:

[0053]

[0054] Among them, c i is cosθ i ,s i is sinθ i , i is the joint, w is the distance from the boom root hinge to the rotation center, h is the distance from the boom root hinge to the ground, L E is the distance between the two connecting rods. In the embodiment of the present application, only the deflection in the vertical direction is considered, so the expected position of the end of the boom satisfies the following formula:

[0055] x d =L E s2+h=(L0+ΔL)sinθ2+h

[0056] In an embodiment of the present application, construction of a deflection determination model may include: obtaining multiple sets of environmental data of the boom during amplitude change and telescopic movement; constructing a training set based on the multiple sets of environmental data through a pre-constructed forward kinematics model; and training the target model through the training set to obtain the deflection determination model.

[0057] In the embodiment of the present application, a multi-layer neural network model is used as the target model for training, including an input layer, a hidden layer and an output layer. The input layer contains the number of neurons related to the input data, such as the position of the variable-length oil cylinder, the position of the telescopic oil cylinder, etc. The hidden layer is one or more layers with an appropriate number of neurons. The output layer contains one neuron, which represents the predicted deflection error δ eDuring the training process, the training parameters such as learning rate, batch size, training rounds, etc. are constantly adjusted to obtain the best performance. Then the model performance is evaluated on the validation set to avoid overfitting, and the performance of the neural network model is evaluated on the test set. According to the evaluation results and actual needs, the model is adjusted, such as increasing / decreasing the number of hidden layers, neurons, changing the learning rate, etc., so as to ensure that the model has good generalization performance.

[0058] In an embodiment of the present application, the control parameters of the PID controller include a proportional coefficient, an integral coefficient and a differential coefficient. Step S105: adjusting the predicted deflection by the PID controller to obtain the target deflection may include: determining the initial control parameters of the PID controller; respectively determining the partial derivative values ​​of the predicted deflection with respect to the initial control parameters; updating the control parameters of the PID controller according to the partial derivative values, the initial control parameters and a preset learning rate through a gradient descent algorithm; and adjusting the predicted deflection according to the updated control parameters to obtain the target deflection.

[0059] In an embodiment of the present application, determining the initial control parameters of the PID controller may include: setting the integral coefficient and the differential coefficient to 0; increasing the proportional coefficient according to a preset rule until the PID controller produces continuous oscillation, and recording the proportional coefficient value and the oscillation period when the PID controller produces continuous oscillation; determining the initial control parameters of the PID controller based on the proportional coefficient value and the oscillation period.

[0060] Specifically, in order to compensate for the deformation of the boom, after the predicted deflection is calculated, a PID controller is used to adjust it, with the predicted deflection as input and the target deflection as output. The boom operation is controlled according to the output target deflection to improve the control accuracy of the boom. The output calculation formula of the PID controller is as follows:

[0061]

[0062] Among them, U(t) is the controller output, i.e., the target deflection, e(t) is the predicted deflection, and Kp, Ki, and Kd are the proportional, integral, and differential coefficients of the PID controller, respectively.

[0063] To use a PID controller to adjust the predicted deflection, it is first necessary to determine the initial control parameters of the PID controller. In an embodiment of the present application, the Ziegler-Nichols method is used to determine the initial control parameters of the PID controller. First, set Ki and Kd to 0, starting from a smaller Kp value, and gradually increase the Kp value until the PID controller produces continuous oscillations in the vertical direction. Continuous oscillation means that the boom deflection error changes periodically within a fixed amplitude range. Therefore, the parameters at this time are critical parameters. The Kp value that causes the PID controller to produce continuous oscillations is recorded as Ku, and the oscillation period is recorded as Tu. Based on Ku and Tu, the initial parameters of the PID controller can be calculated as follows:

[0064] Kp=0.6*Ku

[0065] Ki=2*Kp / Tu

[0066] Kd=Kp*Tu / 8

[0067] In the embodiment of the present application, in order to achieve adaptive control, the gradient descent method is used as the adaptive control strategy of the PID control parameter dynamic adjustment algorithm. That is, after the predicted deflection is calculated, the predicted deflection is first adjusted using the initial control parameters, and then the PID control parameters are dynamically updated, and the updated PID control parameters are used for control. First, the partial derivatives of the predicted deflection with respect to the initial control parameters are calculated respectively, that is, for Kp, the calculation For Ki, calculate For Kd, calculate Then update each control parameter according to the following formula:

[0068]

[0069] Among them, η is the learning rate, which is used to control the parameter update speed. The above method can realize online adaptive control.

[0070] An embodiment of the present application provides a processor configured to execute the control method for arm-type aerial work equipment according to the above-mentioned method.

[0071] Specifically, in an embodiment of the present application, the processor can be configured to: obtain the arm length and pitch angle of the boom, the boom cylinder position of the boom cylinder, the telescopic cylinder position of the telescopic cylinder, the load of the work platform, and the wind detection data of the arm-type aerial work equipment; determine the first deflection of the boom according to the arm length, pitch angle and load through a preset deflection algorithm; determine the second deflection of the boom according to the boom cylinder position, telescopic cylinder position, load and wind detection data through a pre-built deflection determination model; add the first deflection and the second deflection to obtain a predicted deflection; adjust the predicted deflection through a PID controller to obtain a target deflection; and control the operation of the arm-type aerial work equipment according to the target deflection.

[0072] In the embodiment of the present application, the processor may also be configured to: determine the end bending moment of the boom according to the boom length, the load of the working platform and the predetermined boom weight of the boom by using a preset end bending moment algorithm; determine the first deflection of the boom according to the pitch angle, the boom length, the end bending moment and the preset parameters of the boom by using a preset deflection algorithm; wherein the preset deflection algorithm includes formula (1):

[0073]

[0074] Among them, δ d is the first deflection, M is the end bending moment, θ is the pitch angle, L is the arm length of the boom, E is the material elastic modulus constant in the preset parameters of the boom, and I is the moment of inertia constant of the section in the preset parameters of the boom.

[0075] In an embodiment of the present application, the processor can also be configured to: obtain multiple sets of environmental data of the boom during amplitude change and telescopic movement; construct a training set based on the multiple sets of environmental data through a pre-built forward kinematics model; and train the target model through the training set to obtain a deflection determination model.

[0076] In an embodiment of the present application, the processor can also be configured to: determine the expected position of the end of the boom corresponding to each set of environmental data according to the position of the boom cylinder and the telescopic cylinder through a pre-constructed forward kinematics model; determine the actual deflection according to the actual position of the end and the corresponding expected position of the end; determine the deflection error corresponding to each set of environmental data according to the actual deflection and the corresponding first deflection; and construct a training set according to each set of environmental data and the corresponding deflection error.

[0077] In an embodiment of the present application, the processor can also be configured to: determine the initial control parameters of the PID controller; determine the partial derivative values ​​of the predicted deflection with respect to the initial control parameters respectively; update the control parameters of the PID controller according to the partial derivative values, the initial control parameters and the preset learning rate through the gradient descent algorithm; and adjust the predicted deflection according to the updated control parameters to obtain the target deflection.

[0078] In an embodiment of the present application, the processor can also be configured to: set the integral coefficient and the differential coefficient to 0; increase the proportional coefficient according to a preset rule until the PID controller produces continuous oscillation, and record the proportional coefficient value and the oscillation period when the PID controller produces continuous oscillation; determine the initial control parameters of the PID controller based on the proportional coefficient value and the oscillation period.

[0079] Through the above technical scheme, the arm length and pitch angle of the boom, the position of the boom cylinder of the boom cylinder, the position of the telescopic cylinder of the telescopic cylinder, the load of the work platform and the wind detection data of the boom-type aerial work equipment are first obtained, and then the first deflection of the boom is determined according to the arm length, pitch angle and load through a preset deflection algorithm, and the second deflection of the boom is determined according to the position of the boom cylinder, the position of the telescopic cylinder, the load and the wind detection data through a pre-constructed deflection determination model, and then the first deflection and the second deflection are added to obtain a predicted deflection, and finally the predicted deflection is adjusted by a PID controller to obtain a target deflection, and the operation of the boom-type aerial work equipment is controlled according to the target deflection. The present application can accurately predict the deflection of the boom, thereby improving the position control accuracy of the aerial work platform.

[0080] Figure 2 The structure diagram of a control device for an arm-type aerial work equipment according to an embodiment of the present application is schematically shown. Figure 2 As shown, the embodiment of the present application also provides a control device for an arm-type aerial work equipment, which may include:

[0081] An acquisition module 301 is used to acquire the arm length and pitch angle of the boom, the luffing cylinder position of the luffing cylinder, the telescopic cylinder position of the telescopic cylinder, the load of the work platform, and the wind force detection data of the boom-type aerial work equipment;

[0082] A first deflection determination module 302 is used to determine a first deflection of the boom according to the boom length, the pitch angle and the load by using a preset deflection algorithm;

[0083] The second deflection determination module 303 is used to determine the second deflection of the boom according to the position of the luffing cylinder, the position of the telescopic cylinder, the load and the wind force detection data through a pre-built deflection determination model;

[0084] A predicted deflection determination module 304, configured to add the first deflection and the second deflection to obtain a predicted deflection;

[0085] An adjustment module 305 is used to adjust the predicted deflection by a PID controller to obtain a target deflection;

[0086] The control module 306 is used to control the operation of the boom-type aerial work equipment according to the target deflection.

[0087] An embodiment of the present application also provides an arm-type aerial work platform, which may include the above-mentioned processor or a control device for an arm-type aerial work equipment.

[0088] An embodiment of the present application also provides a machine-readable storage medium, on which instructions are stored, and the instructions are used to enable a machine to execute the above-mentioned control method for arm-type aerial work equipment.

[0089] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0090] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0091] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0092] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0093] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0094] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.

[0095] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.

[0096] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0097] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.

Claims

1. A control method for an arm-type aerial work equipment, characterized in that: The arm-type aerial work equipment includes an arm frame, an operating platform, a boom cylinder and a telescopic cylinder, and the control method includes: Acquire the arm length and pitch angle of the boom, the luffing cylinder position of the luffing cylinder, the telescopic cylinder position of the telescopic cylinder, the load of the work platform, and the wind force detection data of the boom-type aerial work equipment; Determine the first deflection of the boom according to the arm length, the pitch angle and the load by using a preset deflection algorithm; Determine the second deflection of the boom by using a pre-built deflection determination model according to the position of the luffing cylinder, the position of the telescopic cylinder, the load and the wind force detection data; adding the first deflection and the second deflection to obtain a predicted deflection; The predicted deflection is adjusted by a PID controller to obtain a target deflection; The operation of the arm-type aerial work equipment is controlled according to the target deflection.

2. The control method according to claim 1, characterized in that: The method of determining the first deflection of the boom according to the arm length, the pitch angle and the load by using a preset deflection algorithm includes: Determine the end bending moment of the boom according to the boom length, the load of the working platform and the predetermined boom weight of the boom by using a preset end bending moment algorithm; Determine a first deflection of the boom by a preset deflection algorithm according to the pitch angle, the boom length, the end bending moment and preset parameters of the boom; The preset deflection algorithm includes formula (1): Among them, δ d is the first deflection, M is the end bending moment, θ is the pitch angle, L is the arm length of the boom, E is the material elastic modulus constant in the preset parameters of the boom, and I is the moment of inertia constant of the section in the preset parameters of the boom.

3. The control method according to claim 1, characterized in that: The construction of the deflection determination model includes: Acquire multiple sets of environmental data of the boom during the luffing and telescopic movements; Building a training set according to the multiple sets of environmental data by using a pre-built forward kinematics model; The deflection determination model is obtained by training the target model through the training set.

4. The control method according to claim 3, characterized in that: The environmental data includes the position of the luffing cylinder, the position of the telescopic cylinder, the wind force detection data, the actual position of the end of the boom and the load of the working platform. The pre-constructed forward kinematics model is used to construct a training set according to the multiple sets of environmental data, including: Determining the expected end position of the boom corresponding to each set of the environmental data according to the position of the luffing cylinder and the position of the telescopic cylinder through a pre-constructed forward kinematics model; determining an actual deflection according to the actual position of the end and the corresponding expected position of the end; Determine a deflection error corresponding to each set of the environmental data according to the actual deflection and the corresponding first deflection; A training set is constructed according to each group of the environmental data and the corresponding deflection error.

5. The control method according to claim 1, characterized in that: The control parameters of the PID controller include a proportional coefficient, an integral coefficient and a differential coefficient. The method of adjusting the predicted deflection by the PID controller to obtain a target deflection includes: Determining initial control parameters of the PID controller; respectively determining partial derivatives of the predicted deflection with respect to the initial control parameters; By means of a gradient descent algorithm, the control parameters of the PID controller are updated according to the partial derivative value, the initial control parameter and a preset learning rate; The predicted deflection is adjusted according to the updated control parameters to obtain a target deflection.

6. The control method according to claim 5, characterized in that: The determining of the initial control parameters of the PID controller comprises: Setting the integral coefficient and the differential coefficient to 0; Increase the proportional coefficient according to a preset rule until the PID controller generates continuous oscillation, and record the proportional coefficient value and oscillation period when the PID controller generates continuous oscillation; The initial control parameters of the PID controller are determined according to the proportional coefficient value and the oscillation period.

7. A processor, characterized in that: The device is configured to execute the control method for boom-type aerial work equipment according to any one of claims 1 to 6.

8. A control device for boom-type aerial work equipment, characterized in that: include: An acquisition module, used to acquire the arm length and pitch angle of the boom, the luffing cylinder position of the luffing cylinder, the telescopic cylinder position of the telescopic cylinder, the load of the work platform and the wind force detection data of the boom-type aerial work equipment; A first deflection determination module, configured to determine a first deflection of the boom according to the boom length, the pitch angle and the load by using a preset deflection algorithm; A second deflection determination module, configured to determine a second deflection of the boom according to a position of the boom cylinder, a position of the telescopic cylinder, the load, and the wind force detection data by using a pre-built deflection determination model; A predicted deflection determination module, configured to add the first deflection and the second deflection to obtain a predicted deflection; An adjustment module, used for adjusting the predicted deflection by a PID controller to obtain a target deflection; A control module is used to control the operation of the arm-type aerial work equipment according to the target deflection.

9. An arm-type aerial work platform, characterized in that: It comprises the processor according to claim 7 or the control device for boom-type aerial work equipment according to claim 8.

10. A machine-readable storage medium, characterized in that: The machine-readable storage medium stores instructions for causing a machine to execute a control method for an arm-type aerial work equipment according to any one of claims 1 to 6.

Citation Information

Cited By

  • Risk early warning method and system in hoisting operation process of crane

    CN119320104A

  • Axle load leveling method for working machine and working machine

    CN119502617A