Transformation method for heightening existing reinforced concrete pier
Through the jacking device and pier formwork technology, concrete cutting is reduced, the efficiency and quality of bridge pier reconstruction are improved, the problems of resource waste and environmental pollution in traditional methods are solved, and the efficiency, safety and aesthetics of bridge reconstruction are improved.
Patent Information
- Application Number
- CN202411064877.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-10-11
AI Technical Summary
The traditional bridge pier reconstruction method results in a large amount of concrete removal, a long construction period, high costs, and may damage the structure and pollute the environment. The demolition and reconstruction of old bridges results in a waste of resources.
A jacking device is used to cut the piers into upper and lower parts, and then cut into bamboo-shaped columns respectively. Concrete is poured through the pier column formwork and wedge-shaped pouring opening formwork, which reduces concrete chipping and improves splicing quality and aesthetics.
The amount of concrete removal is reduced, the construction period is shortened, the cost is reduced, the safety and durability of the bridge are improved, and resource waste is avoided.
Smart Images

Figure CN118756607A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for modifying an existing reinforced concrete bridge pier to increase its height. Background Art
[0002] As the service life of bridges increases, some piers may have problems such as structural aging and damage, and need to be reinforced or renovated. Traditional pier renovation methods often involve a lot of concrete chiseling work, which not only has a long construction period and high construction cost, but also easily causes structural damage and environmental pollution to existing bridges. In addition, a large number of highway bridges or urban cross-line flyovers in operation have insufficient clearance under the bridge due to bridge settlement, improved navigation grade, improved underpass grade or route modification. The use function of the bridge within the normal service life cannot meet the transportation requirements, and poses a hidden danger to the operational safety of itself and the underpass. In order to make the bridge meet the transportation requirements, it is usually chosen to demolish the old bridge and rebuild a new bridge. This method causes the old bridge to be abandoned, resulting in a huge waste of resources. How to reduce the waste of resources in the process of renovating old bridges has become an urgent problem that needs to be solved in the industry. Summary of the invention
[0003] The purpose of the present invention is to overcome the defects of the prior art and provide a method for increasing the height of an existing reinforced concrete pier, which can reduce the amount of concrete removed, facilitate the pouring operation and improve the quality of the reconstruction.
[0004] The object of the present invention is achieved by: a method for improving the height of an existing reinforced concrete bridge pier, comprising the following steps:
[0005] Step 1: installing a jacking device between the top surface of the pedestal of the existing bridge and the bottom surface of the main beam of the existing bridge and between the top surface of the pedestal and the bottom surface of the pier tie beam of the existing bridge;
[0006] Step 2: First, accurately measure and design the piers of the existing bridge, determine the cutting position and shape, and then use special cutting equipment to cut the piers of the existing bridge horizontally at the cutting position to form upper piers and lower piers;
[0007] Step 3: First, all the lifting devices are alternately lifted to lift the main beam of the existing bridge, the main beam support of the existing bridge, the pier tie beam of the existing bridge and the upper pier, so that the top elevation of the main beam of the existing bridge meets the requirements of the reconstruction design, and then the lower concrete of the upper pier is cut from the outside to the inside in a manner of high outside and low inside into an upper bamboo shoot-shaped column in the shape of an inverted cone column, so that the lower part of the steel bars of the upper pier is exposed, and the upper concrete of the lower pier is cut from the outside to the inside in a manner of low outside and high inside into a lower bamboo shoot-shaped column in the shape of a cone column, so that the upper part of the steel bars of the lower pier is exposed;
[0008] Step 4: first insert an upper sleeve into the lower end of the steel bar of the upper pier, and insert a lower sleeve into the upper end of the steel bar of the lower pier, and then insert the extended steel bar between the upper sleeve and the lower sleeve;
[0009] Step 5: Install a pier column template between the upper pier and the lower pier, the length of which should cover the upper and lower bamboo-shaped columns; open a casting notch on the top of the pier column template, and install a wedge-shaped casting port template on the outer surface of the pier column template corresponding to the casting notch;
[0010] Step six, pouring concrete into the inner cavity of the pier column template through the wedge-shaped pouring port template, and after the concrete strength reaches the designed strength, removing the wedge-shaped pouring port template and the pier column template to form a wedge-shaped pouring port concrete and a new pier column splicing section;
[0011] Step seven: first cut and level the wedge-shaped pouring mouth concrete, then remove all jacking devices.
[0012] In the above-mentioned reconstruction method for raising the height of an existing reinforced concrete bridge pier, before carrying out step one, the pier of the existing bridge must first be widened, and then a jacking device must be installed on the widened pier.
[0013] In the above-mentioned reconstruction method for increasing the height of an existing reinforced concrete bridge pier, the jacking device adopts a jacking jack.
[0014] In the above-mentioned reconstruction method for increasing the height of an existing reinforced concrete bridge pier, during step six, after the concrete is poured into the inner cavity of the pier column formwork, it is necessary to vibrate to ensure that the concrete is fully filled into the wedge-shaped casting port formwork.
[0015] The characteristics of the existing reinforced concrete bridge pier heightening reconstruction method of the present invention are:
[0016] 1. Reduce concrete chiseling: By cutting off the damaged section of the pier to form the upper pier and the lower pier, the upper pier is lifted by the jacking device, and then the butt ends of the upper and lower piers are cut into bamboo shoot-shaped columns, which avoids a lot of concrete chiseling work in the traditional method, reduces construction costs, and shortens the construction period.
[0017] 2. Improve the quality of splicing: By setting a wedge-shaped pouring port template on the pier column template, the spliced bridge piers have better integrity and stability, which improves the safety and durability of the bridge; the bamboo shoot column can enhance the shear resistance of the connection between the newly poured concrete and the original concrete.
[0018] 3. Improve aesthetics: By leveling the concrete at the wedge-shaped casting mouth, the surface of the pier column concrete is ensured to be flat and smooth, thereby improving the overall aesthetics. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a perspective view of the existing reinforced concrete bridge before renovation;
[0020] Figure 2 is a perspective view of step 1 of the method for reconstructing an existing reinforced concrete bridge pier of the present invention;
[0021] Figure 3 is a perspective view of step 2 of the method for reconstructing an existing reinforced concrete bridge pier of the present invention;
[0022] Figure 4 is a perspective view of step three of the method for reconstructing an existing reinforced concrete bridge pier of the present invention;
[0023] Figure 5 is a perspective view of step 4 of the method for reconstructing an existing reinforced concrete bridge pier of the present invention;
[0024] Figure 6 is a perspective view of step five of the method for reconstructing an existing reinforced concrete bridge pier of the present invention;
[0025] Figure 7 is a perspective view of step six of the method for reconstructing an existing reinforced concrete bridge pier of the present invention;
[0026] Figure 8 It is a perspective view of step seven of the method for reconstructing an existing reinforced concrete bridge pier of the present invention. DETAILED DESCRIPTION
[0027] The present invention will be further described below in conjunction with the accompanying drawings.
[0028] Please refer to Figure 1 The existing reinforced concrete bridge before the reconstruction includes a main beam 1 of the existing bridge, a main beam support 2 of the existing bridge, a pier tie beam 3 of the existing bridge, a pier 4 of the existing bridge, a cap 5 of the existing bridge and a pile foundation 6 of the existing bridge.
[0029] Please see again Figures 2 to 8 The method for reconstructing an existing reinforced concrete bridge pier of the present invention comprises the following steps:
[0030] Step 1: First, widen the cap 5 of the existing bridge, and then install a jacking device 7 between the top surface of the widened cap 50 and the bottom surface of the main beam 1 of the existing bridge and between the top surface of the widened cap 50 and the bottom surface of the pier tie beam 3 of the existing bridge. The jacking device 7 supports the main beam 1 of the existing bridge; the jacking device 7 uses a jacking jack;
[0031] Step 2: First, accurately measure and design the damaged pier 4 of the existing bridge, determine the cutting position and shape, and then use a dedicated cutting device to cut the pier 4 of the existing bridge horizontally at the cutting position to form an upper pier 41 and a lower pier 42;
[0032] Step 3: First, control the jacking device 7 to jack up alternately, lift the main beam 1 of the existing bridge, the main beam support 2 of the existing bridge, the pier tie beam 3 of the existing bridge and the upper pier 41, so that the top elevation of the main beam 1 of the existing bridge meets the requirements of the reconstruction design, and then cut the lower concrete of the upper pier 41 from the outside to the inside and in a manner of high outside and low inside into an inverted cone-shaped upper bamboo shoot-shaped column 410, so that the lower part of the steel bar 81 of the upper pier 41 is exposed, and cut the upper concrete of the lower pier 42 from the outside to the inside and in a manner of low outside and high inside into a cone-shaped lower bamboo shoot-shaped column 420, so that the upper part of the steel bar 82 of the lower pier 42 is exposed;
[0033] Step 4: first insert the upper sleeve 83 into the lower end of the steel bar 81 of the upper bridge pier 41, and insert the lower sleeve 84 into the upper end of the steel bar 82 of the lower bridge pier 41, and then insert the extended steel bar 80 between the upper sleeve 83 and the lower sleeve 84;
[0034] Step 5: Install the pier column template 9 between the upper pier 41 and the lower pier 42. The length of the pier column template 13 should cover the upper bamboo-shaped column 410 and the lower bamboo-shaped column 420. A casting notch is opened on the top of the pier column template 9, and a wedge-shaped casting notch template 10 is installed on the outer surface of the pier column template 9 corresponding to the casting notch. The shape, size and position of the casting notch should be accurately calculated and designed according to the actual situation and design requirements of the piers to ensure that the spliced piers have good integrity and stability.
[0035] Step 6: pour concrete into the inner cavity of the pier column template 9 through the wedge-shaped pouring port template 10, and vibrate the concrete while pouring it. Strictly control the pouring speed and vibration time of the concrete to ensure that the concrete is fully filled into the wedge-shaped pouring port template 10; after the concrete strength reaches the designed strength, remove the wedge-shaped pouring port template 10 and the pier column template 9 to form the wedge-shaped pouring port concrete 100 and the new pier column splicing section 40;
[0036] Step seven, first use professional grinding equipment or hand tools to cut and level the wedge-shaped pouring mouth concrete 100 to ensure that the concrete surface at the wedge mouth is flat and smooth, coordinated with the surrounding concrete surface, to improve the overall aesthetics and stability, and then remove all the jacking devices 7 to complete the reconstruction construction of the bridge pier height increase.
[0037] The above embodiments are only used to illustrate the present invention, rather than to limit the present invention. Those skilled in the relevant technical field may make various changes or modifications without departing from the spirit and scope of the present invention. Therefore, all equivalent technical solutions should also belong to the scope of the present invention and should be defined by the claims.
Claims
1. A method for increasing the height of an existing reinforced concrete bridge pier, characterized in that: The transformation method comprises the following steps: Step 1: installing a jacking device between the top surface of the pedestal of the existing bridge and the bottom surface of the main beam of the existing bridge and between the top surface of the pedestal and the bottom surface of the pier tie beam of the existing bridge; Step 2: First, accurately measure and design the piers of the existing bridge, determine the cutting position and shape, and then use special cutting equipment to cut the piers of the existing bridge horizontally at the cutting position to form upper piers and lower piers; Step 3: First, all the lifting devices are alternately lifted to lift the main beam of the existing bridge, the main beam support of the existing bridge, the pier tie beam of the existing bridge and the upper pier, so that the top elevation of the main beam of the existing bridge meets the requirements of the reconstruction design, and then the lower concrete of the upper pier is cut from the outside to the inside in a manner of high outside and low inside into an upper bamboo shoot-shaped column in the shape of an inverted cone column, so that the lower part of the steel bars of the upper pier is exposed, and the upper concrete of the lower pier is cut from the outside to the inside in a manner of low outside and high inside into a lower bamboo shoot-shaped column in the shape of a cone column, so that the upper part of the steel bars of the lower pier is exposed; Step 4: first insert an upper sleeve into the lower end of the steel bar of the upper pier, and insert a lower sleeve into the upper end of the steel bar of the lower pier, and then insert the extended steel bar between the upper sleeve and the lower sleeve; Step 5: Install a pier column template between the upper pier and the lower pier, the length of which should cover the upper and lower bamboo-shaped columns; open a casting notch on the top of the pier column template, and install a wedge-shaped casting port template on the outer surface of the pier column template corresponding to the casting notch; Step six, pouring concrete into the inner cavity of the pier column template through the wedge-shaped pouring port template, and after the concrete strength reaches the designed strength, removing the wedge-shaped pouring port template and the pier column template to form a wedge-shaped pouring port concrete and a new pier column splicing section; Step seven: first cut and level the wedge-shaped pouring mouth concrete, then remove all jacking devices.
2. The method for increasing the height of an existing reinforced concrete bridge pier according to claim 1, characterized in that: Before proceeding to step one, the existing bridge's pier must be widened first, and then a lifting device must be installed on the widened pier.
3. The method for increasing the height of an existing reinforced concrete bridge pier according to claim 1 or 2, characterized in that: The jacking device adopts a jacking jack.
4. The method for improving the height of an existing reinforced concrete bridge pier according to claim 1, characterized in that: During step six, after the concrete is poured into the inner cavity of the pier formwork, it is necessary to vibrate it to ensure that the concrete is fully filled into the wedge-shaped pouring port formwork.
Citation Information
Patent Citations
Continuous splicing construction method of pier column for jacking broken beam of bridge
CN103015328A
Uneven jacking system and uneven jacking construction method for existing bridge superstructure
CN111236089A
Elongation method for bridge pier
JP2009228301A