Water storage and power generation integrated intelligent secondary water supply device
Through intelligent secondary water supply devices in high-rise residences, PLC control boxes and PID algorithms are used to monitor water levels and water quality, store water and generate electricity, solving the problems of waste and water supply pressure caused by peaks and troughs of electricity and water, and improving the efficiency of the water supply system. and stability, achieving sustainable utilization of resources and comprehensive management of energy.
Patent Information
- Application Number
- CN202410867753.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-01
AI Technical Summary
There are peaks and troughs in the electricity and water consumption of residents in high-rise buildings, making it difficult for power generation and water plants to follow accurately, causing waste and water supply pressure problems.
Design an intelligent secondary water supply device that integrates water storage and power generation. It uses PLC control box and PID control algorithm to monitor water level and water quality through water level sensors and water quality sensors. It stores water during the trough of electricity consumption and releases it at the peak. The stored water potential energy generates electricity, realizes the conversion of electrical energy and potential energy, and optimizes water supply and power generation.
It improves the efficiency and stability of the water supply system, achieves sustainable utilization of resources and comprehensive energy management, reduces the pressure on the pipe network during the secondary water supply process, and ensures that users receive tap water supply that meets standards.
Smart Images

Figure CN118756785A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of secondary water supply, and in particular relates to an intelligent secondary water supply device integrating water storage and power generation. Background Art
[0002] High-rise residential buildings are a common type of residential housing for urban residents, and water supply and power supply are basic functions that housing should provide. The water supply pressure of a general water plant can only guarantee the normal water supply of 5-6-story houses. For high-rise residential buildings, additional water supply pressure boosting devices are required to increase the water supply pressure and ensure normal water supply. This type of device is called a secondary water supply device. A common secondary water supply device is a water pump combined with a water tank to supply water at the same time. The principle is to lift water from a multi-stage water pump to a water storage tank installed in the inner mezzanine of a high-rise building. When needed, the water tank is combined with a water pump to supply water to each user in the building. Through observation, it is found that the current urban high-rise residential buildings have the following problems:
[0003] 1. Residential electricity consumption has obvious peaks and troughs, that is, the morning and evening of weekdays are peaks, while noon and early morning are relatively troughs; while the electricity consumption on weekends is relatively even. However, power generation cannot follow the peaks and troughs, resulting in waste in the troughs, so it is necessary to level the electricity.
[0004] 2. Residential water use also has obvious peaks and troughs, that is, the water use peaks in the morning and evening on weekdays, and the troughs at noon and early morning; while the water use on weekends is relatively even. It is also difficult for water plants to produce tap water accurately following the peaks and troughs and adjusting the tap water production plan.
[0005] Taking into account that the peak and trough of residential electricity and water consumption have very similar curves, the present invention proposes an intelligent secondary water supply device that integrates water storage and power generation. The basic principle is to store drinking water in the form of potential energy through electricity consumption when the electricity and water consumption are at the trough; when the electricity and water consumption are at the peak, the stored drinking water is released, and at the same time the generator is driven to generate electricity, releasing the stored drinking water potential energy, thereby realizing the conversion of electrical energy and potential energy through the secondary water supply tank; and an intelligent controller is installed to realize the above functions. Summary of the invention
[0006] The purpose of the present invention is to provide an intelligent secondary water supply device that integrates water storage and power generation to solve the problems raised in the above-mentioned background technology.
[0007] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: an intelligent secondary water supply device with integrated water storage and power generation, comprising a municipal pipeline, a water pump connected to the municipal pipeline, the water pump is used to extract water through the municipal pipeline, one side of the water pump is connected to three check valves of the municipal pipeline, the check valve is used to control the municipal pipeline to turn on and off the water supply, the end of the municipal pipeline is connected to a three-way valve, the other two ends of the three-way valve are respectively connected to a household pipeline and a water storage pipeline, the three-way valve is used to control the water supply to flow to the household pipeline, the water storage pipeline, or to the household pipeline and the water storage pipeline at the same time. A pipeline, the water storage pipeline is connected with an electric valve, the electric valve is used to control the water supply of the water storage pipeline, one side of the electric valve is connected with a turbine generator pump on the water storage pipeline, the turbine generator pump is used to realize the water supply in the water storage pipeline, or to generate electricity through the impact of the water flow in the water storage pipeline, one side of the turbine generator pump is connected with a pressure gauge on the water storage pipeline, the pressure gauge is used to detect the water pressure in the water storage pipeline, the end of the water storage pipeline is connected with a water storage tank, the water storage tank is used to store water when the water consumption of citizens is low, and to provide auxiliary secondary water supply when the water consumption of citizens is peak;
[0008] It also includes a PLC control box, which is electrically connected to the water pump, the electric valve, the turbine generator pump and the pressure gauge respectively. The PLC control box is used to control and adjust the water pump, the electric valve, the turbine generator pump and the pressure gauge. The PLC control box is electrically connected to a water level sensor and a water quality sensor.
[0009] Preferably, the water level sensor is arranged on the side wall of the water storage tank to detect the water level inside the water storage tank, and the water quality sensor is arranged at the bottom of the water storage tank to detect the water quality inside the water storage tank.
[0010] Preferably, the PLC control box adopts a PID control algorithm to control the water storage amount in the water storage tank, collects the liquid level height data in the water storage tank through the water level sensor and sets the liquid level threshold to control the water storage, and then controls the switching condition of the electric valve, and by controlling the water flow rate pumped in and out, the system can operate in various working modes.
[0011] Preferably, the mathematical expression of the PID control algorithm is:
[0012]
[0013] Where K p is the proportional gain, e(t) is the deviation number, U(t) is the controlled output, K I is the integral gain, KD is the differential gain;
[0014] The calculation of e(t) is as follows: e(t)=T1-T2, where T1 is the set water level threshold and T2 is the actual measured water level height.
[0015] Preferably, the working modes include a water storage and supply mode, a water supply and power generation mode, an independent water supply and power generation mode and a water quality monitoring switching mode.
[0016] Preferably, the steps of the water storage and supply mode are as follows:
[0017] The PLC control box starts the turbine generator pump in water pump mode and opens the electric valve to deliver the water supply from the municipal pipeline to the water storage tank at a certain flow rate;
[0018] At the same time, the PLC control box controls the flow rate of water pumped into the water pump and the turbine generator pump, so that part of the tap water flows directly and smoothly to the user's faucet and water-using equipment to meet the user's water needs;
[0019] The water level sensor continuously monitors the water level changes in the water tank. When the water level reaches a preset water level threshold, it indicates that the water tank has stored enough water. The PLC control box closes the electric valve and the turbine generator pump to stop the water supply.
[0020] Preferably, the steps of the water supply power generation mode are as follows:
[0021] The PLC control box opens the electric valve, and the check valve is also in an open state, allowing a portion of tap water to flow directly from the municipal pipeline to the user to meet the user's normal water demand;
[0022] At the same time, the PLC control box supplies water to users through the water storage tank, ensuring the stability of water pressure and water quality.
[0023] The water in the water storage tank serves as a water source and flows into the water storage pipe. When the water flows through the water storage pipe, it drives the power generation structure of the turbine generator pump to work, utilizes the kinetic energy of the water flow to generate electrical energy, and stores the electrical energy, thereby meeting part of the electricity demand during peak hours.
[0024] Preferably, the steps of the independent water supply and power generation mode are as follows:
[0025] When the user's water demand reaches a low point, the check valve is closed and the PLC control box opens the electric valve;
[0026] The water in the water storage tank serves as a water source and flows into the water storage pipe. When the water flows through the water storage pipe, it drives the power generation structure of the turbine generator pump to work, utilizes the kinetic energy of the water flow to generate electrical energy, and stores the electrical energy, thereby meeting part of the electricity demand during peak hours.
[0027] Preferably, the steps of switching the water quality monitoring mode are as follows:
[0028] The PLC control box continuously monitors the water quality sensor data before water supply, and when the water quality does not meet the standard, the PLC control box triggers an alarm;
[0029] The PLC control box automatically closes the electric valve supplying water to the water storage tank, stopping the water supply to the water storage tank;
[0030] At the same time, the system supplies water to the user through the municipal pipeline, the water pump, the check valve, the three-way valve and the household pipeline;
[0031] Switching to the water supply mode of the municipal pipeline, the municipal pipeline starts to supply water to users to ensure that users obtain water sources that meet water quality standards;
[0032] Then the water storage tank discharges the tap water that does not meet the water quality standards through the drainage pipe at the bottom, and the inner wall of the water storage tank is cleaned before storing water.
[0033] Preferably, the water storage and supply mode, the water supply and power generation mode, the independent water supply and power generation mode and the water quality monitoring and switching mode are also controlled and adjusted using a PID control algorithm, and the openings of the electric valve, the check valve and the three-way valve are adjusted by monitoring the water level of the water storage tank or the change in water supply demand, and the flow rates of the water pump and the turbine generator pump are also controlled to ensure that the water supply flow rate meets the set requirements;
[0034] At the same time, by optimizing the parameters of the PID control algorithm, the stable control and rapid response of the water supply process are improved to cope with the changing demand during low and peak water consumption periods;
[0035] In terms of power generation function control, a PID control algorithm for turbine speed or power generation is designed, and the openings of the electric valve, the check valve and the three-way valve are adjusted according to the speed or power demand signal monitored in real time, and the water flow is controlled to maintain a stable power generation effect;
[0036] The water flow is adjusted through the PID control algorithm to ensure that the power generation system maintains a stable output power under different loads to improve the energy utilization efficiency of the system.
[0037] Compared with the prior art, the present invention has the following beneficial effects:
[0038] The present invention uses a secondary water supply water storage tank to store water and energy at the trough of electricity and water consumption, releases the stored drinking water at the peak of electricity and water consumption, and converts the stored energy into electrical energy.
[0039] The function of the water storage tank is to store user-side water during the trough of water consumption and supply water to the user-side during the peak of water consumption. The PID control algorithm is designed by comparing the difference between the collected liquid level height data and the expected liquid level height, so as to better control the switching of the electric valve and the check valve. By controlling the water flow rate of the pump in and out, the device can work in different working modes, so as to ensure the water consumption and water supply pressure of the end user;
[0040] The turbine generator pump plays the role of integrating electricity storage and power generation in the system. When the turbine generator pump generates electricity, the turbine converts the potential energy of the water flow into mechanical energy to generate electricity, and at the same time fills the water supply during the peak water consumption period and reduces the pressure of the pipe network during the secondary water supply process. When the turbine generator pump consumes electricity, the turbine generator pump is equivalent to a water pump, assisting the main water pump below to pump water. In addition, the relative flow rate of the water pumped by the two water pumps is controlled by an algorithm, thereby controlling the water flow into the water supply tank or directly into the users on each floor.
[0041] Four intelligent working modes make full use of equipment such as electric valves, check valves, water pumps and turbine generator pumps; through reasonable switching and optimized operation of the four modes, the water supply system can efficiently store water during periods of low water demand, control water flow through electric valves and check valves, and quickly supply water and generate electricity through water pumps during peak water demand periods; at the same time, the water quality monitoring system ensures that users obtain tap water that meets the standards; this flexible operation mode not only improves the efficiency and stability of the water supply system, but also realizes the sustainable use of resources and comprehensive energy management. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 It is a schematic diagram of the system structure of the present invention;
[0043] Figure 2 For the present invention Figure 1 The enlarged schematic diagram at A in the middle;
[0044] Figure 3 For the present invention Figure 1 The enlarged schematic diagram of point B in the middle;
[0045] Figure 4 This is a system block diagram of the water storage and supply mode of the present invention;
[0046] Figure 5 This is a system block diagram of the water supply and power generation mode of the present invention;
[0047] Figure 6This is a system block diagram of the independent water supply and power generation mode of the present invention;
[0048] Figure 7 This is a system block diagram of the water quality monitoring switching mode of the present invention.
[0049] In the figure: 1. Municipal pipeline; 2. Water pump; 3. Check valve; 4. Household pipeline; 5. Water storage pipeline; 6. Three-way valve; 7. Electric valve; 8. Turbine generator pump; 9. Pressure gauge; 10. Water storage tank; 11. Drain pipe. DETAILED DESCRIPTION
[0050] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0051] See also Figure 1-Figure 7 The present invention provides a technical solution: an intelligent secondary water supply device integrating water storage and power generation, comprising a municipal pipeline 1, a water pump 2 is connected to the municipal pipeline 1, the water pump 2 is used to realize water extraction and supply through the municipal pipeline 1, one side of the water pump 2 is connected to the three check valves 3 of the municipal pipeline 1, the check valve 3 is used to control the water supply of the municipal pipeline 1, the end of the municipal pipeline 1 is connected to a three-way valve 6, the other two ends of the three-way valve 6 are respectively connected to the household pipeline 4 and the water storage pipeline 5, the three-way valve 6 is used to control the water supply to flow to the household pipeline 4, the water storage pipeline 5 or to flow to the household pipeline 4 and the water storage pipeline 5 at the same time, The water storage pipeline 5 is connected with an electric valve 7, and the electric valve 7 is used to control the water supply of the water storage pipeline 5. One side of the electric valve 7 is connected with a turbine generator pump 8 on the water storage pipeline 5, and the turbine generator pump 8 is used to realize the water supply in the water storage pipeline 5, or to generate electricity through the impact of the water flow in the water storage pipeline 5. One side of the turbine generator pump 8 is connected with a pressure gauge 9 on the water storage pipeline 5, and the pressure gauge 9 is used to detect the water pressure in the water storage pipeline 5. The end of the water storage pipeline 5 is connected with a water storage tank 10, and the water storage tank 10 is used to store water when the water consumption of citizens is low, and to provide auxiliary secondary water supply during the peak period of the water consumption of citizens;
[0052] It also includes a PLC control box, which is electrically connected to the water pump 2, the electric valve 7, the turbine generator pump 8 and the pressure gauge 9 respectively. The PLC control box is used to control and adjust the water pump 2, the electric valve 7, the turbine generator pump 8 and the pressure gauge 9. The PLC control box is electrically connected to a water level sensor and a water quality sensor.
[0053] The water tank 10 realizes the inflow or outflow of water through a PPR (polypropylene) pipe, in which it is connected to a pressure gauge 9 through the PPR pipe to detect the water pressure flowing through the PPR pipe. The electric valve 7 assists in controlling the flow rate of water pumped into or out of the water tank 10. A water level sensor and a water quality sensor for detecting the age of water are set in the water tank 10. The water level sensor is used to determine the amount of water stored in the water tank 10, and the water quality sensor is used to detect the age of water stored in the water tank 10. Through various sensors, in conjunction with the algorithm in the control cabinet, corresponding control is performed on when water supply is needed and when water supply is needed;
[0054] The turbine generator pump 8 is connected to the electric valve 7 through a PPR pipe and is controlled by a PLC control cabinet. When the water storage tank 10 needs to store water, the turbine generator pump 8 works as a water pump. The turbine generator pump 8 pumps the water pumped from the municipal pipeline 1 to the high-rise water storage tank 10 (water storage and supply mode); when the water storage tank 10 participates in water supply, the water will flow through the turbine generator pump 8, and the kinetic energy of the water will be converted into electrical energy by driving the blades of the turbine generator pump 8 to rotate (water supply and power generation mode, independent water supply and power generation mode);
[0055] The check valve 3 is connected through the PPR pipes on both sides. Placing the check valve 3 on the left side of the bifurcation of the device can ensure that the water pumped from the municipal pipeline 1 cannot flow back into the municipal pipeline 1 through the water pump 2 (some water pumps 2 are not tightly sealed, and if they are not well controlled, water backflow is likely to occur). Due to the one-way flow characteristics of the check valve 3, the water quality of the municipal pipeline 1 can be guaranteed to a certain extent;
[0056] During the secondary water supply process, the electric valve 7 can adjust its opening according to the control of the control cabinet to control the water flow rate;
[0057] In the secondary water supply, water pump 2 plays a key role in pumping water to higher floors; through the relevant algorithms of the PLC control cabinet, the flow of water pump 2 and turbine generator pump 8 and the opening of each valve are controlled, so that water pump 2 can perform corresponding actions in different working modes to realize the relevant functions of on-demand water supply.
[0058] In order to detect the liquid level and water quality in the water tank 10, in this embodiment, preferably, the water level sensor is arranged on the side wall of the water tank 10 to detect the water level inside the water tank 10, and the water quality sensor is arranged at the bottom of the water tank 10 to detect the water quality inside the water tank 10.
[0059] In order to realize algorithmic control of the water storage in the water tank 10, in the present embodiment, preferably, the PLC control box adopts a PID control algorithm to control the water storage amount in the water tank 10, and controls the water storage by collecting the liquid level height data in the water tank 10 through the water level sensor and setting the liquid level threshold, thereby controlling the switching condition of the electric valve 7, and by controlling the water flow rate pumped in and out, the system can operate in various working modes.
[0060] In order to realize the calculation and processing of water storage and facilitate the realization of automated water storage control, in this embodiment, preferably, the mathematical expression of the PID control algorithm is:
[0061]
[0062] Where K p is the proportional gain, e(t) is the deviation number, U(t) is the controlled output, K I is the integral gain, K D is the differential gain;
[0063] The calculation of e(t) is as follows: e(t)=T1-T2, where T1 is the set water level threshold and T2 is the actual measured water level height.
[0064] In order to realize multiple modes of operation, in this embodiment, preferably, the working modes include water storage and supply mode, water supply and power generation mode, independent water supply and power generation mode and water quality monitoring switching mode.
[0065] The water supply system will enable this mode during periods of low water demand, such as before dawn and in the afternoon. At this time, most residents are resting or working outside, and the water demand is relatively low. The system uses intelligent control to put the water storage tank 10 into water storage mode. At this time, the turbine generator pump 8 works as a water pump, and cooperates with the municipal pipeline 1 and the water pump 2 to ensure water supply during low periods to meet the user's water demand. The water level change is monitored by a liquid level sensor. Once the water level reaches the preset water level, the control system will promptly shut down the turbine generator pump 8 and the electric valve 7, thereby stopping the water supply to the water storage tank 10. In this embodiment, preferably, the steps of the water storage and supply mode are as follows:
[0066] The PLC control box starts the turbine generator pump 8 in water pump mode and opens the electric valve 7 to deliver the water supply from the municipal pipeline 1 to the water storage tank 10 at a certain flow rate;
[0067] At the same time, the PLC control box controls the flow rate of water pumped into the water pump 2 and the turbine generator pump 8, so that part of the tap water flows directly and smoothly to the user's faucet and water-using equipment to meet the user's water needs;
[0068] The water level sensor continuously monitors the water level change in the water tank 10. When the water level reaches a preset water level threshold, it indicates that the water tank 10 has stored enough water. The PLC control box closes the electric valve 7 and the turbine generator pump 8 to stop the water supply.
[0069] During periods of high water demand, the water supply system adopts a dual water supply strategy to meet the needs of users. On the one hand, the system directly introduces water from the municipal pipeline 1. On the other hand, the system uses the water storage tank 10 to supply water to users and uses the power generation structure of the turbine generator pump 8 to generate electricity to simultaneously meet the water and electricity needs of residents during peak hours. In this embodiment, preferably, the steps of the water supply and power generation mode are as follows:
[0070] The PLC control box opens the electric valve 7, and the check valve 3 is also in an open state, allowing a portion of tap water to flow directly from the municipal pipeline 1 to the user to meet the user's normal water demand;
[0071] At the same time, the PLC control box supplies water to the user through the water storage tank 10, ensuring the stability of water pressure and water quality.
[0072] The water source in the water storage tank 10 serves as a water source and flows into the water storage pipe 5. When the water flows through the water storage pipe 5, it drives the power generation structure of the turbine generator pump 8 to work, utilizes the kinetic energy of the water flow to generate electrical energy, and stores the electrical energy, thereby meeting part of the electricity demand during peak hours.
[0073] When the municipal pipeline 1 bursts or the water in the water tank 10 is old and needs to be used as soon as possible, the water supply from the municipal pipeline 1 is cut off, and only the water in the water tank 10 is supplied; the water supply system uses the power generation structure of the turbine generator pump 8 to generate electricity while continuously supplying water to residents; it not only realizes the stable supply of water, but also utilizes the kinetic energy generated by the water flow to meet the electricity needs of residents, or feeds back to the power grid. In this embodiment, preferably, the steps of the independent water supply and power generation mode are as follows:
[0074] When the user's water demand reaches a low point, the check valve 3 is closed, and the PLC control box opens the electric valve 7;
[0075] The water source in the water storage tank 10 serves as a water source and flows into the water storage pipe 5. When the water flows through the water storage pipe 5, it drives the power generation structure of the turbine generator pump 8 to work, utilizes the kinetic energy of the water flow to generate electrical energy, and stores the electrical energy, thereby meeting part of the electricity demand during peak hours.
[0076] During the water supply process, when the water quality sensor detects that the water quality in the water storage tank 10 does not meet the standard, this mode will be entered, the electric valve 7 will be closed, and the system will draw water from the municipal pipeline 1 through the water pump 2 and supply water to the residents on the floor to ensure that the users obtain water sources that meet the water quality standards; at the same time, the substandard water will be drained away through the drain pipe 11 or the filtration system, and the water storage tank 10 will be cleaned or repaired. In this embodiment, preferably, the steps of switching the water quality monitoring mode are as follows:
[0077] The PLC control box continuously monitors the water quality sensor data before water supply, and when the water quality does not meet the standard, the PLC control box triggers an alarm;
[0078] The PLC control box automatically closes the electric valve 7 for supplying water to the water storage tank 10, thereby stopping the water supply to the water storage tank 10;
[0079] At the same time, the system supplies water to the user through the municipal pipeline 1, the water pump 2, the check valve 3, the three-way valve 6 and the household pipeline 4;
[0080] Switching to the water supply mode of the municipal pipeline 1, the municipal pipeline 1 starts to supply water to the user to ensure that the user obtains water that meets the water quality standards;
[0081] Then, the water storage tank 10 discharges the tap water that does not meet the water quality standards through the drainage pipe 11 at the bottom, and cleans the inner wall of the water storage tank 10 before storing water.
[0082] In order to realize precise control and adjustment of the entire system and achieve the effect of high automation control, in this embodiment, preferably, the water storage and supply mode, the water supply and power generation mode, the independent water supply and power generation mode and the water quality monitoring switching mode are also controlled and adjusted by the PID control algorithm, and the opening of the electric valve 7, the check valve 3 and the three-way valve 6 is adjusted by monitoring the water level of the water storage tank 10 or the change of water supply demand, and the flow rate of the water pump 2 and the turbine generator pump 8 is also controlled to ensure that the water supply flow rate meets the set requirements;
[0083] At the same time, by optimizing the parameters of the PID control algorithm, the stable control and rapid response of the water supply process are improved to cope with the changing demand during low and peak water consumption periods;
[0084] In terms of power generation function control, a PID control algorithm for turbine speed or power generation is designed. According to the speed or power demand signal monitored in real time, the opening of the electric valve 7, the check valve 3 and the three-way valve 6 is adjusted to control the water flow to maintain a stable power generation effect.
[0085] The water flow is adjusted through the PID control algorithm to ensure that the power generation system maintains a stable output power under different loads to improve the energy utilization efficiency of the system.
[0086] The working principle and use process of the present invention:
[0087] The steps of water storage and supply mode are as follows:
[0088] The PLC control box starts the turbine generator pump 8 in water pump mode and opens the electric valve 7 to deliver the water supply from the municipal pipeline 1 to the water storage tank 10 at a certain flow rate;
[0089] At the same time, the PLC control box controls the flow rate of water pumped into the water pump 2 and the turbine generator pump 8, so that part of the tap water flows directly and smoothly to the user's faucet and water-using equipment to meet the user's water needs;
[0090] The water level sensor continuously monitors the water level change in the water storage tank 10. When the water level reaches a preset water level threshold, it indicates that the water storage tank 10 has stored enough water. The PLC control box closes the electric valve 7 and the turbine generator pump 8 to stop the water supply.
[0091] The steps of the water supply and power generation mode are as follows:
[0092] The PLC control box opens the electric valve 7, and the check valve 3 is also in an open state, allowing a portion of tap water to flow directly from the municipal pipeline 1 to the user to meet the user's normal water demand;
[0093] At the same time, the PLC control box supplies water to the user through the water storage tank 10, ensuring the stability of water pressure and water quality.
[0094] The water source in the water storage tank 10 is used as a water source and flows into the water storage pipe 5. When the water flows through the water storage pipe 5, it drives the power generation structure of the turbine generator pump 8 to work, uses the kinetic energy of the water flow to generate electrical energy, and stores the electrical energy, thereby meeting part of the electricity demand during peak hours.
[0095] The steps of independent water supply and power generation mode are as follows:
[0096] When the user's water demand reaches a low point, the check valve 3 is closed, and the PLC control box opens the electric valve 7;
[0097] The water source in the water storage tank 10 is used as a water source and flows into the water storage pipe 5. When the water flows through the water storage pipe 5, it drives the power generation structure of the turbine generator pump 8 to work, uses the kinetic energy of the water flow to generate electrical energy, and stores the electrical energy, thereby meeting part of the electricity demand during peak hours.
[0098] The steps to switch the water quality monitoring mode are as follows:
[0099] The PLC control box continuously monitors the water quality sensor data before water supply, and when the water quality does not meet the standard, the PLC control box triggers an alarm;
[0100] The PLC control box automatically closes the electric valve 7 for supplying water to the water storage tank 10, thereby stopping the water supply to the water storage tank 10;
[0101] At the same time, the system supplies water to the user through the municipal pipeline 1, the water pump 2, the check valve 3, the three-way valve 6 and the household pipeline 4;
[0102] Switching to the water supply mode of the municipal pipeline 1, the municipal pipeline 1 starts to supply water to the user to ensure that the user obtains water that meets the water quality standards;
[0103] Then, the water storage tank 10 discharges the tap water that does not meet the water quality standards through the drainage pipe 11 at the bottom, and cleans the inner wall of the water storage tank 10 before storing water.
[0104] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An intelligent secondary water supply device integrating water storage and power generation, comprising a municipal pipeline (1), characterized in that: The municipal pipeline (1) is connected to a water pump (2), and the water pump (2) is used to extract water through the municipal pipeline (1). One side of the water pump (2) is connected to a check valve (3) at three ends of the municipal pipeline (1), and the check valve (3) is used to control the water supply of the municipal pipeline (1). The end of the municipal pipeline (1) is connected to a three-way valve (6), and the other two ends of the three-way valve (6) are respectively connected to the household pipeline (4) and the water storage pipeline (5). The three-way valve (6) is used to control the water supply to flow to the household pipeline (4), the water storage pipeline (5), or to flow to the household pipeline (4) and the water storage pipeline (5) at the same time. The water storage pipeline (5) is connected to an electric valve (7). The electric valve (7) is used to control the water supply of the water storage pipe (5). One side of the electric valve (7) is connected to a turbine generator pump (8) on the water storage pipe (5). The turbine generator pump (8) is used to realize the water supply in the water storage pipe (5), or to generate electricity through the impact of the water flow in the water storage pipe (5). One side of the turbine generator pump (8) is connected to a pressure gauge (9) on the water storage pipe (5). The pressure gauge (9) is used to detect the water pressure in the water storage pipe (5). The end of the water storage pipe (5) is connected to a water storage tank (10). The water storage tank (10) is used to store water when the water consumption of citizens is low, and to provide auxiliary secondary water supply when the water consumption of citizens is peak. The invention also comprises a PLC control box, which is electrically connected to the water pump (2), the electric valve (7), the turbine generator pump (8) and the pressure gauge (9) respectively, and is used to control and adjust the water pump (2), the electric valve (7), the turbine generator pump (8) and the pressure gauge (9). The PLC control box is electrically connected to a water level sensor and a water quality sensor.
2. According to claim 1, the intelligent secondary water supply device integrating water storage and power generation is characterized in that: The water level sensor is arranged on the side wall of the water storage tank (10) and is used to detect the water level inside the water storage tank (10); the water quality sensor is arranged at the bottom of the water storage tank (10) and is used to detect the water quality inside the water storage tank (10).
3. The intelligent secondary water supply device integrating water storage and power generation according to claim 2, characterized in that: The PLC control box uses a PID control algorithm to control the amount of water stored in the water tank (10), collects liquid level height data in the water tank (10) through the water level sensor and sets a liquid level threshold to control water storage, thereby controlling the switching status of the electric valve (7), and controlling the flow rate of water pumped in and out, so that the system can operate in various different working modes.
4. The intelligent secondary water supply device integrating water storage and power generation according to claim 3 is characterized in that: The mathematical expression of the PID control algorithm is: Where K p is the proportional gain, e(t) is the deviation number, U(t) is the controlled output, K I is the integral gain, K D is the differential gain; The calculation of e(t) is as follows: e(t)=T1-T2, where T1 is the set water level threshold and T2 is the actually measured water level height.
5. The intelligent secondary water supply device integrating water storage and power generation according to claim 3 is characterized in that: The working modes include a water storage and supply mode, a water supply and power generation mode, an independent water supply and power generation mode and a water quality monitoring switching mode.
6. The intelligent secondary water supply device integrating water storage and power generation according to claim 5, characterized in that: The steps of the water storage and supply mode are as follows: The PLC control box starts the turbine generator pump (8) in water pump mode and opens the electric valve (7) to transport the water supply from the municipal pipeline (1) to the water storage tank (10) at a certain flow rate; At the same time, the PLC control box controls the flow rate of water pumped by the water pump (2) and the turbine generator pump (8), so that part of the tap water flows directly and smoothly to the user's faucet and water-using equipment to meet the user's water demand; The water level sensor continuously monitors the water level change in the water storage tank (10). When the water level reaches a preset water level threshold, it indicates that the water storage tank (10) has stored enough water. The PLC control box closes the electric valve (7) and the turbine generator pump (8) to stop the water supply.
7. The intelligent secondary water supply device integrating water storage and power generation according to claim 5, characterized in that: The steps of the water supply and power generation mode are as follows: The PLC control box opens the electric valve (7), and the check valve (3) is also in an open state, allowing a portion of tap water to flow directly from the municipal pipeline (1) to the user to meet the user's normal water demand; At the same time, the PLC control box supplies water to the user through the water storage tank (10), thereby ensuring the stability of water pressure and the compliance of water quality; The water source in the water storage tank (10) is used as a water source and flows into the water storage pipe (5). When the water flows through the water storage pipe (5), it drives the power generation structure of the turbine generator pump (8) to work, utilizes the kinetic energy of the water flow to generate electrical energy, and stores the electrical energy, thereby meeting part of the electricity demand during peak hours.
8. The intelligent secondary water supply device integrating water storage and power generation according to claim 5, characterized in that: The steps of the independent water supply and power generation mode are as follows: When the user's water demand reaches a low point, the check valve (3) is closed, and the PLC control box opens the electric valve (7); The water source in the water storage tank (10) is used as a water source and flows into the water storage pipe (5). When the water flows through the water storage pipe (5), it drives the power generation structure of the turbine generator pump (8) to work, utilizes the kinetic energy of the water flow to generate electrical energy, and stores the electrical energy, thereby meeting part of the electricity demand during peak hours.
9. The intelligent secondary water supply device integrating water storage and power generation according to claim 5, characterized in that: The steps of switching the water quality monitoring mode are as follows: The PLC control box continuously monitors the water quality sensor data before water supply, and when the water quality does not meet the standard, the PLC control box triggers an alarm; The PLC control box automatically closes the electric valve (7) supplying water to the water storage tank (10), thereby stopping the water supply to the water storage tank (10); At the same time, the system supplies water to the user through the municipal pipeline (1), the water pump (2), the check valve (3), the three-way valve (6) and the household pipeline (4); Switching to the water supply mode of the municipal pipeline (1), the municipal pipeline (1) starts to supply water to the user, so as to ensure that the user obtains water that meets the water quality standards; Then, the water storage tank (10) discharges the tap water that does not meet the water quality standards through the drainage pipe (11) at the bottom, and cleans the inner wall of the water storage tank (10) before storing water.
10. The intelligent secondary water supply device integrating water storage and power generation according to claim 5, characterized in that: The water storage and supply mode, the water supply and power generation mode, the independent water supply and power generation mode and the water quality monitoring and switching mode are also controlled and regulated by a PID control algorithm, and the openings of the electric valve (7), the check valve (3) and the three-way valve (6) are regulated by monitoring the water level of the water storage tank (10) or the change in water supply demand, and the flow rates of the water pump (2) and the turbine generator pump (8) are also controlled to ensure that the water supply flow rate meets the set requirements; At the same time, by optimizing the parameters of the PID control algorithm, the stable control and rapid response of the water supply process are improved to cope with the changing demand during low and peak water consumption periods; In terms of power generation function control, a PID control algorithm for turbine speed or power generation is designed, and the openings of the electric valve (7), the check valve (3) and the three-way valve (6) are adjusted according to the speed or power demand signal monitored in real time, so as to control the water flow to maintain a stable power generation effect; The water flow is adjusted through the PID control algorithm to ensure that the power generation system maintains a stable output power under different loads to improve the energy utilization efficiency of the system.
Citation Information
Patent Citations
Photovoltaic direct current side energy storage based power grid intelligent regulation and control system
CN105932704A
High-rise building pumped storage scenery intelligent micro-grid system and control method
CN106356888A
Building energy saving system
CN106555421A
Cooperative operation system and method for wind power generation, pumped storage power generation and hydraulic supply
CN108979939A
Clean energy system for residential community and operation method of system
CN109861627A