Construction method of anti-seepage wall separation ditch in tunnel

By pre-embedding arc tubes in the tunnel and welding and fixing them, combined with the laying of a waterproof layer, the problem of leakage risks during the construction of off-wall ditches in the tunnel has been solved, effective water guidance and drainage have been achieved, and the normal operation of the subway station has been ensured. .

CN118757220APending Publication Date: 2024-10-11CHINA RAILWAY SHISIJU GROUP CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411028127.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

The off-wall ditch construction method in the existing tunnel carries the risk of leakage, causing water seepage problems inside the subway station and affecting normal operations.

Method used

Pre-embed the first arc tube in the side wall, and install the second arc tube extending into the side wall at the base of the trench. Connect and fix it by welding, and lay a waterproof layer inside the arc tube to fill the gap between the side wall and the trench. gaps to ensure that water flows into the off-wall ditch without leakage.

Benefits of technology

It effectively fills the gap between the off-wall ditch and the side wall, prevents condensed water or water seepage from entering the subway station, realizes normal drainage function, avoids the risk of water leakage, and ensures the normal operation of the subway station.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118757220A_ABST
    Figure CN118757220A_ABST
Patent Text Reader

Abstract

A construction method for an anti-leakage wall separation ditch in a tunnel is different from a traditional concrete pouring manufacturing method, a round pipe is pre-buried in a side wall when the side wall is manufactured, then a long-strip-shaped groove is formed in the side wall, the lower half portion of the round pipe is cut off to obtain a first arc pipe, and when concrete and a reinforcement cage are used for manufacturing a ditch base subsequently, the long-strip-shaped groove is formed in the side wall; a second arc pipe extending into the side wall is installed at the top, the connecting position of the second arc pipe and the first arc pipe is welded and fixed, a waterproof layer is laid on the inner circumferential face of the arc pipe, the second arc pipe and the first arc pipe are connected into a whole through the construction method, the gap between the side wall and the ditch is completely filled, and the waterproof layer is laid on the inner circumferential face of the second arc pipe. Condensate water or seeping water on the wall can all fall into the wall separation ditch, the phenomenon that the condensate water or seeping water enters the subway station through gaps is avoided, the normal drainage function is achieved, meanwhile, the water leakage risk is avoided, and meanwhile normal operation of an internal subway is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction of drainage ditches in tunnels, in particular to a construction method of an anti-leakage wall ditch in a tunnel. Background Art

[0002] A gutter is a drainage system usually used around the roof and walls of a building. Its function is to collect and discharge rainwater to prevent water from penetrating from the roof and walls into the interior of the building, thereby protecting the structure and walls of the building. The ditch is usually located at the bottom of the wall or wall, which can collect rainwater and direct it into a drainage pipe or a collection tank.

[0003] In existing subway buildings, the wall ditch is a drainage ditch along the subway wall. Generally, after the construction of the inner wall of the subway station is completed, concrete is poured and waterproof material is applied on the surface. That is, the additional construction of the wall ditch is carried out close to the inner side of the subway wall. The wall and the wall ditch are not cast as a whole, and there will be a certain gap between them. Condensation water or seepage on the wall will enter the subway station through the gap. The wall ditch made by the existing construction method still has a certain degree of water leakage risk, which brings trouble to the normal operation of the internal subway. Summary of the invention

[0004] The purpose of the present invention is to provide a construction method for an anti-leakage away from the wall ditch in a tunnel, in which a first arc tube is pre-buried in the wall, and when the ditch base is subsequently constructed, a second arc tube is installed to extend into the wall and connected to the first arc tube to fill the gap between the away from the wall ditch and the side wall, thereby solving the problems in the prior art.

[0005] The technical solution adopted by the present invention to solve its technical problem is: a construction method for anti-leakage wall trench in a tunnel, comprising the following steps: ① pre-embed a horizontally arranged circular tube during the casting of the side wall, so that the inner surface of the side wall is tangent to the circular tube; ② after the side wall is manufactured, perform a groove processing at the position of the circular tube to expose the lower half of the circular tube, and open a long strip groove with an arc-shaped cross section on the lower side of the circular tube; ③ after the long strip groove in step ② is opened, the lower half of the circular tube is cut off to obtain a first arc tube with a semicircular cross section; ④ after the circular tube in step ③ is cut off, a trench mold is placed at a position close to the side wall, and a steel cage and a water retaining plate are placed in the trench mold; ⑤ concrete is injected into the trench mold, and the concrete is poured into the trench mold. The concrete and the steel cage form a ditch base, and before the concrete solidifies, a second arc tube is fixedly arranged on the ditch base, so that one side of the second arc tube is tangent to the water retaining plate, and the other side of the second arc tube is connected to one end of the first arc tube, and the opening of the second arc tube corresponds to the opening of the first arc tube; ⑥ After the ditch base is cured and solidified in step ⑤, the ditch mold is removed, and a welding machine is used to weld and fix the second arc tube and the first arc tube at the position where they are connected; ⑦ After the second arc tube and the first arc tube are welded and fixed in step ⑥, a first waterproof layer is laid on the inner surface of the first arc tube, a second waterproof layer is laid on the inner surface of the second arc tube, and a third waterproof layer is laid on the inner side of the water retaining plate on the upper part of the second arc tube, so as to complete the construction of the anti-leakage wall ditch. The water retaining plate is provided with a plurality of L-shaped dowel bars arranged side by side, and the bottom of the L-shaped dowel bars is located in the steel cage. The first arc tube and the second arc tube are both half tubes with semicircular cross-sections, and the center of the first arc tube and the center of the second arc tube are located on the same horizontal straight line. Before placing the second arc tube on the ditch base in step ⑤, a waterproof interface agent is applied in the long groove, and when adjusting the second arc tube to be connected with the first arc tube, a foam filler is added in the gap of the long groove. The length of the water retaining plate above the second arc tube is 15-30cm, the diameter of the round tube is 5-10cm, the width of the ditch base is 80-150cm, and the thickness of the first waterproof layer, the second waterproof layer and the third waterproof layer is 2-5mm. The round tube adopts a polyethylene composite tube. The steel cage includes a plurality of rows of stirrups arranged side by side, and each row of stirrups is provided with connecting bars, which are arranged along the length direction of the wall ditch. The height of the long groove is 2-5 times the diameter of the round tube. The first waterproof layer, the second waterproof layer and the third waterproof layer are all mixed rubbers made of EPDM rubber mixed with additives, fillers and antioxidants. The concrete fragments obtained by the grooving process in step ② are filled into the channel mold together when the concrete is injected in step ⑤.

[0006] The positive effect of the present invention is that the construction method of the anti-leakage wall ditch in the tunnel described in the present invention is different from the traditional concrete pouring method. When the side wall is made, a circular tube is pre-buried inside, and then a long groove is opened in the side wall, and the lower half of the circular tube is cut off to obtain a first arc tube. When the ditch base is subsequently made using concrete and a steel cage, a second arc tube extending into the inside of the side wall is installed on the top, and the connection between the second arc tube and the first arc tube is welded and fixed, and a waterproof layer is laid on the inner circumference of the arc tube. The above construction method allows the second arc tube and the first arc tube to be connected as one, and the gap between the side wall and the ditch is completely filled. The condensation water or seepage water on the wall will all fall into the wall ditch, and will not enter the subway station through the gap. While achieving normal drainage function, the risk of water leakage is avoided, and the normal operation of the internal subway is ensured. BRIEF DESCRIPTION OF THE DRAWINGS

[0007] Figure 1 It is a schematic diagram of the state when step ① of the present invention is completed; Figure 2 It is a schematic diagram of the state when step ② of the present invention is completed; Figure 3 It is a schematic diagram of the state when step ③ of the present invention is completed; Figure 4 It is a schematic diagram of the state when step ④ of the present invention is completed; Figure 5 It is a schematic diagram of the state when step ⑤ of the present invention is completed; Figure 6 It is a schematic diagram of the state when step ⑥ of the present invention is completed; Figure 7 It is a schematic diagram of the state when step ⑦ of the present invention is completed. DETAILED DESCRIPTION

[0008] The invention provides a method for constructing an anti-leakage trench in a tunnel, as follows: Figure 1-7 As shown, the following steps are included: ① When casting the side wall 1, a horizontally arranged round tube 2 is pre-buried so that the inner surface of the side wall 1 is tangent to the round tube 2; ② After the side wall 1 is manufactured, a groove is formed at the position of the circular tube 2 to expose the lower half of the circular tube 2, and a long groove 3 with an arc-shaped cross section is formed on the lower side of the circular tube 2; ③ After the long groove 3 in step ② is opened, the lower half of the circular tube 2 is cut off to obtain a first arc tube 4 with a semicircular cross section; ④ After the round tube 2 in step ③ is cut off, a trench mold 5 is placed near the side wall 1, and a steel cage 6 and a water retaining plate 7 are placed in the trench mold 5; ⑤ Inject concrete into the ditch mold 5, so that the concrete and the steel cage 6 form a ditch base 8, and before the concrete solidifies, fix the second arc tube 9 on the ditch base 8, so that one side of the second arc tube 9 is tangent to the water retaining plate 7, and the other side of the second arc tube 9 is connected to one end of the first arc tube 4, and the opening of the second arc tube 9 corresponds to the opening of the first arc tube 4; ⑥ After the ditch base 8 is cured and solidified in step ⑤, the ditch mold 5 is removed, and a welding machine is used to weld and fix the second arc tube 9 and the first arc tube 4 at the position where they are connected; ⑦ After the second arc tube 9 and the first arc tube 4 are welded and fixed in step ⑥, a first waterproof layer 10 is laid on the inner surface of the first arc tube 4, a second waterproof layer 11 is laid on the inner surface of the second arc tube 9, and a third waterproof layer 12 is laid on the inner side of the water retaining plate 7 on the upper part of the second arc tube 9 to complete the construction of the anti-leakage wall ditch.

[0009] In step ① of the above construction method, the side wall 1 is the wall of the subway station, and the round tube 2 can be an existing plastic tube, which has a certain strength. The side wall 1 is pre-buried inside when it is made, and there is no filler such as concrete inside the round tube 2, which is a cavity space. In step ②, the side wall 1 is grooved, and a long groove 3 with an arc-shaped cross section is opened in the length direction of the side wall 1, and the lower half of the round tube 2 is exposed. In step ③, the lower half of the round tube 2 is cut off to obtain a first arc tube 4 with a semicircular cross section.

[0010] Step ④ is to use the ditch mold 5 to make the ditch base 8 at the side of the side wall 1. The steel cage 6 is placed in the ditch mold 5 to enhance the strength of the overall ditch base 8. The water retaining plate 7 is placed on one side of the mold to increase the height of the ditch away from the wall, so that the water inside the ditch will not overflow and ensure normal drainage. Step ⑤ is to fix the second arc tube 9 on the ditch base 8 before pouring concrete into the mold and solidifying, and let the second arc tube 9 be connected to the first arc tube 4 to fill the gap between the side wall 1 and the ditch away from the wall, wherein the unsolidified ditch base 8 can form an arc groove that matches the bottom surface of the second arc tube 9 under the downward pressure of the second arc tube 9, thereby realizing the positioning and installation of the second arc tube 9 on the ditch base 8.

[0011] Step ⑥ is to maintain and shape the ditch base 8, and weld and fix the second arc tube 9 and the first arc tube 4 at the position where they meet, which can improve the integrity and strength while preventing water leakage. Step ⑦ is to lay a waterproof layer on the inner circumference of the first arc tube 4, the second arc tube 9 and the water retaining plate 7 in order to increase the service life of the entire wall ditch and further prevent water leakage.

[0012] Compared with the traditional manufacturing method, the wall ditch manufactured by the above method effectively fills the gap between the wall ditch and the side wall. The first arc tube 4 and the second arc tube 9 can form a guide for the leakage water. The leakage water flowing down through the side wall 1 will eventually drip onto the second arc tube 9 under the action of gravity and completely enter the wall ditch, thereby realizing the corresponding drainage operation, avoiding the leakage water from entering the gap between the wall ditch and the side wall, and reducing the impact of the leakage water on the normal operation inside the station.

[0013] Furthermore, in order to enhance the connection performance between the water retaining plate 7 and the ditch base 8 and improve the strength of the water retaining plate 7 itself to withstand the scouring of drainage in the ditch, a plurality of L-shaped dowel bars 13 arranged side by side are provided in the water retaining plate 7, and the bottom of the L-shaped dowel bar 13 is located in the steel cage 6.

[0014] Furthermore, the first arc tube 4 and the second arc tube 9 are both half tubes with semicircular cross-sections, and the center of the first arc tube 4 and the center of the second arc tube 9 are located on the same horizontal straight line. The above position setting can facilitate the installation and fixation of the second arc tube 9, so that the two arc tubes form a whole, and the leaking water can completely enter the wall groove under the guidance of the arc tube, avoiding the seepage water from entering the subway station and affecting the subsequent normal operation.

[0015] Furthermore, in order to improve the waterproof performance and installation adaptability between the second arc tube 9 and the long groove 3 during installation and ensure that the second arc tube 9 can form a stable sealed connection with the first arc tube 4, before placing the second arc tube 9 on the ditch base 8 in step ⑤, a waterproof interface agent is coated in the long groove 3, and when adjusting the second arc tube 9 to be connected with the first arc tube 4, a foam filler is added to the gap of the long groove 3.

[0016] Furthermore, with regard to the overall structural size of the above-mentioned wall-free ditch, the sizes of each structure are preferably as follows: the length of the water retaining plate 7 above the second arc tube 9 is 15-30 cm, the diameter of the circular tube 2 is 5-10 cm, the width of the ditch base 8 is 80-150 cm, and the thickness of the first waterproof layer 10, the second waterproof layer 11 and the third waterproof layer 12 are 2-5 mm.

[0017] Furthermore, the circular tube is made of polyethylene composite tube, which has excellent mechanical properties and excellent waterproofness. Furthermore, in order to improve the strength of the ditch base 8, the steel cage 6 includes a plurality of rows of stirrups arranged side by side, each row of stirrups is provided with connecting ribs, and the connecting ribs are arranged along the length direction of the wall ditch. Furthermore, in order to facilitate the cutting operation of the lower half of the circular tube 2, sufficient cutting operation space is reserved, and the height of the long groove 3 is 2-5 times the diameter of the circular tube 2. Furthermore, the first waterproof layer 10, the second waterproof layer 11 and the third waterproof layer 12 are all made of mixed rubber made of EPDM rubber mixed with additives, fillers and antioxidants. The above structure has good aging resistance, heat resistance and elongation, and has strong bonding performance, and the construction operation is simple. Furthermore, the concrete fragments obtained by the slotting process in step ② are filled into the channel mold (5) together when the concrete is injected in step ⑤. The above operation can reuse the waste materials in the operation process, and can effectively reduce the overall production cost while ensuring the corresponding strength.

[0018] The technical solution of the present invention is not limited to the scope of the embodiments described in the present invention. The technical contents not described in detail in the present invention are all well-known technologies.

Claims

1. A method for constructing an anti-leakage trench in a tunnel, characterized by: The method comprises the following steps: ① pre-embedding a horizontally arranged circular tube (2) during casting of the side wall (1), so that the inner surface of the side wall (1) is tangent to the circular tube (2); ② After the side wall (1) is manufactured, a groove is formed at the position of the circular tube (2) to expose the lower half of the circular tube (2), and a long groove (3) with an arc-shaped cross section is formed on the lower side of the circular tube (2); ③ After the long groove (3) in step ② is formed, the lower half of the circular tube (2) is cut off to obtain a first arc tube (4) with a semicircular cross section; ④ After the circular tube (2) in step ③ is cut off, a trench mold (5) is placed near the side wall (1), and a steel cage (6) and a water retaining plate (7) are placed in the trench mold (5); ⑤ injecting concrete into the ditch mold (5) so that the concrete and the steel cage (6) form a ditch base (8), and before the concrete solidifies, fixing a second arc tube (9) on the ditch base (8), so that one side of the second arc tube (9) is tangent to the water retaining plate (7), the other side of the second arc tube (9) is connected to one end of the first arc tube (4), and the opening of the second arc tube (9) corresponds to the opening of the first arc tube (4); ⑥ After the ditch base (8) in step ⑤ is cured and solidified, the ditch mold (5) is removed, and a welding machine is used to weld and fix the second arc tube (9) and the first arc tube (4) at the position where they are connected; ⑦ After the second arc tube (9) and the first arc tube (4) are welded and fixed in step ⑥, a first waterproof layer (10) is laid on the inner surface of the first arc tube (4), a second waterproof layer (11) is laid on the inner surface of the second arc tube (9), and a third waterproof layer (12) is laid on the inner side of the water retaining plate (7) above the second arc tube (9), thereby completing the construction of the anti-leakage wall trench.

2. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: A plurality of L-shaped inserted bars (13) arranged side by side are provided in the water retaining plate (7), and the bottoms of the L-shaped inserted bars (13) are located in the steel cage (6).

3. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: The first arc tube (4) and the second arc tube (9) are both half tubes with semicircular cross-sections, and the center of the first arc tube (4) and the center of the second arc tube (9) are located on the same horizontal straight line.

4. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: Before placing the second arc tube (9) on the ditch base (8) in step ⑤, a waterproof interface agent is applied in the long groove (3), and when adjusting the second arc tube (9) to be connected with the first arc tube (4), a foam filler is added in the gap of the long groove (3).

5. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: The water retaining plate (7) is 15-30 cm higher than the second arc tube (9), the diameter of the circular tube (2) is 5-10 cm, the width of the ditch base (8) is 80-150 cm, and the thicknesses of the first waterproof layer (10), the second waterproof layer (11) and the third waterproof layer (12) are 2-5 mm.

6. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: The circular tube (2) is a polyethylene composite tube.

7. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: The steel cage (6) comprises a plurality of rows of stirrups arranged side by side, each row of stirrups is provided with connecting bars, and the connecting bars are arranged along the length direction of the wall trench.

8. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: The height of the long groove (3) is 2-5 times the diameter of the circular tube (2).

9. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: The first waterproof layer (10), the second waterproof layer (11) and the third waterproof layer (12) are all made of mixed rubber made of EPDM rubber mixed with additives, fillers and antioxidants.

10. The method for constructing an anti-leakage trench in a tunnel according to claim 1, characterized in that: The concrete fragments obtained by the grooving process in step ② are filled into the channel mold (5) together with the concrete when pouring in step ⑤.