Desulfurizing tower spraying system for cement industry wet desulphurization system
By adopting a combined design of solid cone and hollow cone nozzles in the cement industry wet desulfurization system, combined with an annular panel and an optimized air inlet structure, the problems of high cost and flue gas escape are solved, and the desulfurization efficiency and system stability are improved.
Patent Information
- Application Number
- CN202410996056.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-10-15
AI Technical Summary
The existing wet desulfurization system in the cement industry has problems such as high cost and flue gas escape. The traditional design fails to effectively solve the problems of gypsum accumulation and corrosion of the spray layer support structure, which affects the desulfurization efficiency and service life.
A desulfurization tower spray system including multiple groups of spray layers is designed. The outer ring nozzle is a solid cone and the inner ring nozzle is a hollow cone. It adopts an upper and lower spray structure. An annular panel is set under the spray layer to evenly spray the slurry. Optimize the design of the air inlet to reduce smoke escape.
It effectively reduces flue gas escape, improves desulfurization efficiency and spray coverage, extends the service life of the spray layer and nozzles, and reduces system operating costs.
Smart Images

Figure CN118767654A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of wet desulfurization in cement industry, and more specifically to a desulfurization tower spraying system for a wet desulfurization system in cement industry. Background Art
[0002] The desulfurization tower spray system of the cement industry wet desulfurization system is generally composed of the desulfurization tower spray layer and nozzle, spray layer support structure, enhancement ring and desulfurization circulation pump group.
[0003] For the desulfurization tower slurry pool area, the traditional slurry pool area design only considers conventional technical requirements such as slurry circulation volume and residence time, but does not consider issues such as gypsum accumulation and removal after system operation. If the gypsum accumulation problem is not considered, each time the desulfurization system is shut down for overhaul, a large amount of manpower will be required to physically clean the gypsum in the desulfurization tower slurry pool area.
[0004] As for the air inlet, the air inlet of the desulfurization tower directly affects the flow field of the entire desulfurization system. The unreasonable air inlet design not only causes uneven distribution of airflow in the desulfurization tower and vortex formation, but also directly affects the removal efficiency of SO2. At the same time, there is a dry-wet interface at the air inlet of the desulfurization tower. Conventional air inlets easily cause slurry to gather at the intersection of the air inlet and the desulfurization tower, dry and scale to form gypsum under high temperature environment, which seriously affects the flue flow area. At the same time, when the system is overhauled, it takes a lot of manpower and material resources to clean the gypsum at the air inlet.
[0005] For the spray system, the removal of SO2 in the flue gas at the tail of the kiln is mainly completed by the spray layer and the nozzle. The spray layer support structure is an important component to ensure the normal operation of the spray layer and the nozzle. For the spray layer support beam, due to its long-term exposure to the scouring of high-velocity, high-solid content slurry and the corrosion of strong acid formed by the acid anhydride or gaseous acid dissolved in water in the flue gas, the spray layer support structure is corroded by the slurry, penetrated, broken, collapsed, etc. For the spray layer, an unreasonable spray layer layout can not only increase the escape of flue gas, reduce the SO2 removal rate, but also affect the service life of the spray layer and the nozzle. Therefore, the reasonable design of the spray layer and the spray layer support structure is an important part of the desulfurization tower design.
[0006] In the design of existing wet flue gas desulfurization systems: when designing the spray layer support structure, most spray layer support beams are designed with bidirectional stainless steel, or the spray layer support beams are designed with carbon steel beams + anti-corrosion + gaskets + stainless steel guard plates. These two structures are expensive, and the gaskets and stainless steel guard plates need to be installed after the anti-corrosion is completed, which increases the construction period and labor costs. When designing the spray layer, most spray layers use solid cones + hollow cones to arrange the nozzles, without fully considering the unequal pressure between the nozzles, the relationship between the spray layer and the nozzle, and the problem of flue gas escape.
[0007] In addition, in the existing design, in order to prevent smoke from escaping, more nozzles need to be designed on the outer circle of the spray layer to reduce the smoke from escaping. However, this design increases the cost of the desulfurization system. Summary of the invention
[0008] The invention provides a desulfurization tower spraying system for a wet desulfurization system in cement industry, which is used to solve the problems of high cost and smoke escape of the desulfurization system in the prior art.
[0009] The present invention provides a desulfurization tower spraying system of a cement industry wet desulfurization system, comprising a desulfurization tower, wherein a plurality of spraying layers are arranged in the desulfurization tower, and an air inlet connected to the interior of the desulfurization tower and used for introducing the flue gas to be treated into the desulfurization tower is arranged on the desulfurization tower;
[0010] The spray layer includes a main spray pipe, on which a plurality of branch spray pipes are arranged; the main spray pipe and the branch spray pipes are provided with nozzles;
[0011] The nozzle located in the outer circle of the spray layer is a solid cone, and the nozzle opening of the nozzle is directed toward the bottom of the desulfurization tower; the nozzle located in the inner circle of the spray layer is a hollow cone, and the hollow cone adopts an upper and lower spray structure, and the nozzle opening of the nozzle is directed toward the bottom and the top of the desulfurization tower;
[0012] An annular panel with an outer end face fixed to the inner wall of the desulfurization tower is arranged below each spray layer, the inner end face of the annular panel is inclined toward the bottom of the desulfurization tower, and the angle N between the annular panel and the center of the desulfurization tower is in the range of 50° to 70°; a plurality of annular panel reinforcement plates for supporting the annular panel are evenly distributed around the center of the annular panel at the bottom of the annular panel; the slurry sprayed from the solid cone of the spray layer is sprayed on the annular panel; the inner end of the annular panel close to the center of the desulfurization tower is toothed, so that the water curtain formed when the slurry flows downward from the annular panel is more uniform, thereby increasing the contact area between the water curtain and the flue gas;
[0013] The distance from the end surface of the air inlet located in the desulfurization tower to the inner wall of the desulfurization tower is greater than the distance from the annular panel to the inner wall of the desulfurization tower.
[0014] Optionally, the distance from the inner end surface of the air inlet to the inner wall of the desulfurization tower is 0.1 to 0.15 times the distance from the inner wall of the desulfurization tower to the center of the desulfurization tower.
[0015] Optionally,
[0016] The air inlet comprises an upper top plate located at the top, a lower bottom plate located at the bottom, and two side plates connecting the upper top plate and the lower bottom plate; one end of the lower bottom plate that penetrates into the desulfurization tower is inclined toward the bottom of the desulfurization tower;
[0017] A rainproof plate is provided on the upper part of the upper top plate, the size of the rainproof plate in the desulfurization tower is larger than the size of the upper top plate, and the rainproof plate is inclined toward the bottom of the desulfurization tower; sealing plates are provided on both side ends of the rainproof plate, and a first cavity is formed between the two sealing plates, the desulfurization tower and the upper top plate;
[0018] A vertical filler plate is arranged between the side plate and the inner wall of the desulfurization tower in the vertical direction, and an upper filler plate and a lower filler plate are arranged at the upper and lower ends of the vertical filler plate, so that the side plate, the inner wall of the desulfurization tower, the vertical filler plate, the upper filler plate and the lower filler plate form a closed second cavity to prevent the slurry in the desulfurization tower from entering the air inlet along the side plate, so as to reduce the enrichment of flue sediments;
[0019] The upper top plate is also provided with a flushing interface for flushing the inner wall of the air inlet.
[0020] Optionally, it also includes a support beam layer provided inside the desulfurization tower for supporting the spray layer; the support beam layer is in the form of a main beam plus an end beam;
[0021] The end beams are all fixed on the wall of the desulfurization tower, and are used to support the ends of each nozzle in the spray layer; there are two main beams, which are symmetrically arranged on both sides of the center line of the horizontal section of the desulfurization tower, and are used to support the middle part of the spray layer;
[0022] The main beam includes a main beam body, a main beam fixed end for fixing the main beam body, and two secondary beams perpendicular to the main beam; the secondary beams are symmetrically arranged on both sides of the center line of the horizontal cross section of the desulfurization tower, and the main beam fixed end is a rectangular steel, which is arranged through the wall of the desulfurization tower;
[0023] The secondary beam is connected to the main beam via a connecting hole;
[0024] The main beam body is made of rectangular carbon steel, the outer surface of which is wrapped with a stainless steel alloy and is embedded in the outer surface of the fixed end of the main beam;
[0025] The joints of the main beam body wrapped with stainless steel alloy are welded with double layers of sealing.
[0026] Optionally, the outer surface of the fixed end of the main beam and the surface of the end beam are coated with an anti-corrosion coating;
[0027] The outer surface of the fixed end of the main beam and the overlapping section of the main beam body are wrapped with glass cloth.
[0028] Optionally, a drainage hole is provided at a portion of the bottom of the fixed end of the main beam located outside the desulfurization tower, and the drainage hole is connected to the interior of the main beam.
[0029] Optionally, each spray layer is connected to a corresponding liquid supply pipeline, and each of the liquid supply pipelines corresponds to a circulation pump; the circulation pump located at the bottom layer of the desulfurization tower is a variable frequency start circulation pump that can automatically adjust the frequency according to the flue gas concentration at the air inlet, and the remaining circulation pumps are industrial frequency start circulation pumps;
[0030] Each of the liquid supply pipelines is also connected to a first pipeline for flushing the liquid supply pipeline and the pump body of the circulating pump when the circulating pump stops running, and is connected to a second pipeline for flushing the mechanical seal of the circulating pump before starting the circulating pump.
[0031] Optionally, a slurry pool bottom plate is provided at the bottom of the desulfurization tower, and the slurry pool bottom plate includes an angle steel reinforcement mesh and a plate welded to the angle steel reinforcement mesh to form an arc structure with a central bulge in the central cross section.
[0032] Optionally, it further comprises a first supporting structure for supporting the bottom edge of the bottom plate;
[0033] The first supporting structure comprises a shear key arranged vertically and fixed at a first end and a base ring plate arranged horizontally;
[0034] The first end of the base ring plate passes through the second end of the shear key, a bottom plate support plate is horizontally fixed to the second end of the base ring plate, and the top surface height of the base ring plate is greater than the top surface height of the bottom plate support plate; the end surface of the bottom plate is welded to the side surface of the base ring plate, and the edge bottom surface of the bottom plate is welded to the top surface of the bottom plate support plate;
[0035] A gasket is provided at the bottom of the base ring plate, a nut is provided at the second end of the shear key, and the base ring plate is located between the gasket and the nut; the nut is used to make the bottom surface of the base ring plate tightly attached to the top surface of the gasket, so as to ensure that the base ring plate remains horizontal under the pressure of the base plate.
[0036] Optionally, it further comprises a second supporting structure for supporting the middle portion of the bottom plate;
[0037] The lower part of the second supporting structure is fixed, the middle part of the top surface of the second supporting structure is in contact with the middle part of the bottom surface of the bottom plate, and the edge of the second supporting structure is provided with a notch that matches the end surface shape of the bottom plate support plate.
[0038] Optionally, each of the end beams comprises an end beam support plate and two reinforcement plates;
[0039] The support plate is horizontally fixed to the inner wall of the desulfurization tower, and the two reinforcing plates are perpendicular to the bottom of the support plate and are fixedly connected to the bottom surface of the support plate and the desulfurization tower respectively.
[0040] The present invention has at least the following beneficial effects:
[0041] The present invention provides a desulfurization tower spray system for a wet desulfurization system in the cement industry. The nozzles of the outer circle of the spray layer adopt a solid cone to effectively prevent the smoke from escaping from a position close to the tower wall. The inner circle adopts a hollow cone, and the hollow cone adopts an upper and lower spray structure, which increases the contact time between the smoke and the slurry while also increasing the spray coverage rate. In addition, an annular panel with one end fixed to the tower wall is arranged under each spray layer, and the desulfurization slurry sprayed from the outermost nozzle is sprayed on the annular panel, which effectively prevents the desulfurization slurry from scouring and corroding the tower wall; and the inner end of the annular panel is toothed, and the desulfurization slurry sprayed on the annular panel flows through the toothed structure to the slurry pool at the bottom of the desulfurization tower, forming a relatively uniform water curtain. In addition, the distance from the end face of the air inlet located inside the desulfurization tower to the inner wall of the desulfurization tower is greater than the distance from the inner end face of the annular panel to the inner wall of the desulfurization tower, ensuring that the flue gas entering the desulfurization tower from the air inlet is confined in the rain curtain formed by the annular panel. The water curtain increases the contact area between the sprayed desulfurization slurry and the flue gas, further preventing the escape of the flue gas. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0043] Figure 1 A schematic diagram of a desulfurization system provided in an embodiment of the present invention;
[0044] Figure 2 A schematic diagram of a spray layer provided for an embodiment of the invention;
[0045] Figure 3 A schematic cross-sectional view of an annular panel provided in an embodiment of the present invention;
[0046] Figure 4 A schematic diagram of the structure of the annular panel AA provided in an embodiment of the present invention;
[0047] Figure 5 A schematic diagram of the inner end of an annular panel provided in an embodiment of the present invention;
[0048] Figure 6 A schematic diagram of a top view of an air inlet provided in an embodiment of the present invention;
[0049] Figure 7 A schematic diagram of a second cavity provided in an embodiment of the present invention;
[0050] Figure 8 A schematic diagram of the cross section of the air inlet BB provided in an embodiment of the present invention;
[0051] Fig. 9 A schematic diagram of a support beam layer provided by an embodiment of the present invention;
[0052] Fig.10 A schematic diagram of a cross section of a main beam provided in an embodiment of the present invention;
[0053] Fig.11 A schematic diagram of the relationship between the fixed end of the main beam and the desulfurization tower provided in an embodiment of the present invention;
[0054] Fig.12 A schematic diagram of a drainage hole provided in an embodiment of the present invention;
[0055] Fig.13 A schematic diagram of a slurry pool bottom plate provided in an embodiment of the present invention;
[0056] Fig.14 A schematic diagram of an angle steel reinforcement mesh provided in an embodiment of the present invention;
[0057] Fig.15 A schematic diagram of a first supporting structure provided by an embodiment of the present invention;
[0058] Fig.16 A schematic diagram of a second supporting structure provided by an embodiment of the present invention;
[0059] Fig.17 A schematic diagram of the cross section of an end beam provided in an embodiment of the present invention.
[0060] Reference numerals:
[0061] 1. Desulfurization tower; 2. Spray layer; 201. Main spray pipe; 202. Branch spray pipe; 203. Hollow cone; 204. Solid cone; 3. Annular panel; 301. Annular panel reinforcement plate; 4. Air inlet; 401. Upper top plate; 402. Lower bottom plate; 403. Side plate; 404. Rainproof plate; 405. First vertical patch plate; 406. First cavity; 407. Second cavity; 408. Flushing interface; 409. Second vertical patch plate; 5. Main beam; 501. Main beam fixed end; 50 2. Drain hole; 6. Secondary beam; 7. End beam; 701. End beam support plate; 702. End beam reinforcement plate; 8. Stainless steel alloy; 9. Liquid supply pipeline; 901. First pipeline; 902. Second pipeline; 10. Variable frequency starting circulation pump; 11. Power frequency starting circulation pump; 12. Slurry pool bottom plate; 1201. Angle steel reinforcement mesh; 13. First supporting structure; 1301. Shear key; 1302. Foundation ring plate; 1303. Bottom plate support plate; 1304. Gasket; 14. Second supporting structure. DETAILED DESCRIPTION
[0062] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0063] The present invention provides a spray system for a desulfurization tower 1 of a wet desulfurization system in cement industry, comprising a desulfurization tower 1, wherein a plurality of spray layers 2 are arranged in the desulfurization tower 1, and an air inlet 4 connected to the inside of the desulfurization tower 1 and used for introducing flue gas to be treated into the desulfurization tower 1 is arranged on the desulfurization tower 1, wherein the spray layer 2 comprises a main spray pipe 201, and a plurality of branch spray pipes 202 are arranged on the main spray pipe 201; nozzles are arranged on the main spray pipe 201 and the branch spray pipes 202;
[0064] The outer ring nozzle of the spray layer 2 is a solid cone 204, and the nozzle is directed toward the bottom of the desulfurization tower 1; the inner ring nozzle of the spray layer 2 is a hollow cone 203, and the hollow cone 203 adopts an up-and-down spray structure, and is directed toward the bottom and the top of the desulfurization tower 1;
[0065] An annular panel 3 whose outer end face is fixed to the inner wall of the desulfurization tower 1 is arranged below each spray layer 2, and the inner end face of the annular panel 3 is inclined toward the bottom of the desulfurization tower 1, and the angle N between the annular panel and the center of the desulfurization tower 1 is in the range of 50° to 70°; a plurality of annular panel reinforcement plates 301 for supporting the annular panel 3 are evenly distributed around the center of the annular panel 3 at the bottom of the annular panel 3; the slurry sprayed from the solid cone 204 of the spray layer 2 is sprayed on the annular panel 3; the inner end of the annular panel 3 close to the center of the desulfurization tower 1 is toothed, so that the water curtain formed when the slurry flows downward from the annular panel 3 is more uniform, thereby increasing the contact area between the water curtain and the flue gas;
[0066] The distance from the end surface of the air inlet 4 located in the desulfurization tower 1 to the inner wall of the desulfurization tower 1 is greater than the distance from the annular panel 3 to the inner wall of the desulfurization tower 1 .
[0067] Specifically, the flue gas at the tail of the cement industry kiln is pressurized by the tail exhaust fan and enters the desulfurization tower 1 through the air inlet 4 of the desulfurization tower 1. The desulfurization slurry is sent into the spray system through a circulating pump and sprayed out by the nozzle. The flue gas moves upward in the desulfurization tower 1 and is intercepted by the slurry moving downward. In the wet desulfurization technology of the cement industry, a multi-layer spray layer 2 for spraying desulfurization slurry is set in the desulfurization tower 1. The air inlet 4 is connected to the flue. The flue gas generated during the cement production process enters the air inlet 4 connected to the desulfurization tower 1 from the flue, and then enters the desulfurization tower 1 from the air inlet 4. The flue gas contacts the desulfurization slurry sprayed from the spray layer 2 and the flue gas, achieving the purpose of desulfurization. The desulfurized flue gas enters the chimney at the tail of the kiln.
[0068] The spray layer 2 adopts the form of a main spray pipe plus a branch spray pipe. In this application, each spray layer 2 adopts a main spray pipe 201 plus 6 branch spray pipes 202. Nozzles are set on the main spray pipe 201 and the branch spray pipe 202. In the spray layer 2, the relationship between the main pipe flow rate, the nozzle flow rate and the branch pipe flow rate is: nozzle flow rate> branch pipe flow rate> main pipe flow rate, which can reduce system blockage. The outer ring nozzle of the spray layer 2 is a solid cone 204 with a spray angle of 90°, which can effectively reduce smoke escape and reduce scouring of the inner wall of the tower. The inner ring nozzle of the spray layer 2 adopts an upper and lower spray hollow cone 203 with a spray angle of 120°, which increases the system coverage rate and is particularly suitable for ultra-low emission desulfurization projects.
[0069] The desulfurization slurry sprayed from the solid cone 204 of the outer circle is sprayed on the annular panel 3. On the one hand, it can prevent the outer nozzle from spraying onto the inner wall of the desulfurization tower 1 and scouring the desulfurization tower 1. On the other hand, the desulfurization slurry sprayed onto the annular panel 3 flows from the inner end surface of the annular panel 3 to the bottom of the desulfurization tower 1 along the inclination angle of the annular panel 3. The angle N between the annular panel 3 and the center of the desulfurization tower is in the range of 50° to 70°, preferably 60°. Around the center of the annular panel 3, a plurality of annular panel reinforcement plates 301 are evenly distributed on the bottom circumference of the annular panel 3. In the present application, the number of annular panel reinforcement plates 301 is 30, and other numbers may be used in other embodiments to further enhance the stability of the annular panel 3. The desulfurization slurry flows from the inner end of the annular panel 3 to the bottom of the desulfurization tower to form a water curtain. In addition, Figure 5 yes Figure 4 The top view of the enlarged view of the G area in the middle is as follows: Figure 5 As shown, the inner end of the annular panel 3 is toothed, so that the formed water curtain is more uniform, further reducing the amount of flue gas escaping from the wall of the desulfurization tower 1, improving the utilization rate of the desulfurization slurry, and improving the desulfurization efficiency. The air inlet 4 is located below the annular panel 3, and the distance from the end face of the air inlet 4 located in the desulfurization tower 1 to the inner wall of the desulfurization tower 1 is greater than the distance from the annular panel 3 to the inner wall of the desulfurization tower 1. In this way, after the flue gas enters the desulfurization tower from the outlet of the air inlet, it enters the rain curtain formed by the annular panel 3, reducing the flue gas escape rate and further improving the utilization rate of the desulfurization slurry.
[0070] The bottom of the annular panel 3 is supported by an annular panel reinforcement plate 301 .
[0071] In a possible implementation manner, the distance from the inner end surface of the air inlet 4 to the inner wall of the desulfurization tower 1 is 0.1 to 0.15 times the distance from the inner wall of the desulfurization tower 1 to the center of the desulfurization tower 1 .
[0072] In one possible implementation,
[0073] The air inlet 4 includes an upper top plate 401 located at the top, a lower bottom plate 402 located at the bottom, and two side plates 403 connecting the upper top plate 401 and the lower bottom plate 402; one end of the lower bottom plate 402 that penetrates into the desulfurization tower 1 is inclined toward the bottom of the desulfurization tower 1;
[0074] A rainproof plate 404 is provided on the upper part of the upper top plate 401. The size of the rainproof plate 404 in the desulfurization tower 1 is larger than that of the upper top plate 401. The rainproof plate 404 is inclined toward the bottom of the desulfurization tower 1. A sealing plate is provided on the side end of the rainproof plate 404. A first cavity 406 is formed between the sealing plate, the desulfurization tower 1 and the upper top plate 401.
[0075] A vertical filler plate is arranged between the side plate 403 and the inner wall of the desulfurization tower 1 in the vertical direction, and an upper filler plate and a lower filler plate are arranged at the upper and lower ends of the vertical filler plate, so that the side plate 403, the inner wall of the desulfurization tower 1, the vertical filler plate, the upper filler plate and the lower filler plate form a closed second cavity 407 to prevent the slurry in the desulfurization tower 1 from entering the air inlet along the side plate 403, so as to reduce the enrichment of flue sediments;
[0076] The upper top plate 401 is also provided with a flushing interface 408 for flushing the inner wall of the air inlet 4 .
[0077] Specifically, the air inlet 4 is a through-hole structure surrounded by an upper top plate 401, a lower bottom plate 402, and two side plates 403. The upper top plate 401 is installed perpendicular to the center line of the desulfurization tower. In the present application, the lower bottom plate 402 is inclined downward at an angle X toward the pulp pool area, and the angle Y between the end face of the two side plates 403 located in the desulfurization tower 1 and the line connecting the center line of the desulfurization tower 1, X in the present invention is 15°, and Y is 90°, so that the actual air inlet area of the desulfurization tower 1 is much larger than the area of the air inlet 4. After the high-velocity flue gas enters the absorption tower, the flue gas flow rate can be quickly reduced. At the same time, the lower bottom plate 402 has a diversion effect, which can increase the residence time of the flue gas in the desulfurization tower 1 and avoid flue gas vortex. The top of the upper top plate 401 is continuously welded with a rainproof plate 404, one end face of the rainproof plate 404 is in contact with the inner wall of the desulfurization tower 1, and the other end face of the rainproof plate 404 is inclined to the bottom of the desulfurization tower 1. A first cavity 406 with a triangular cross-section is formed between the intersection line of the upper top plate 401 and the rainproof plate 404 and the tower wall. The two open end faces of the first cavity 406 are sealed by sealing plates to prevent the spray slurry from entering the flue from the top of the upper top plate 401.
[0078] A sealed second cavity 407 is provided between the outer surface of the side plate 403 of the air inlet 4 in the desulfurization tower 1 and the inner wall of the desulfurization tower 1. A first vertical patch plate 405 constituting the second cavity 407 forms an angle with the outer surface of the side plate 403, and the angle is sealed. The second vertical patch plate 409 in the second cavity 407 forms a cavity with a triangular cross section with the angle. The top and bottom openings of the cavity are sealed by the upper patch plate and the lower patch plate. The second cavity 407 serves as a vertical retaining wall to prevent the slurry in the wall of the desulfurization tower 1 from entering the flue of the desulfurization tower 1 along the outer surface of the side plate 403, thereby reducing the accumulation of flue sediments. At the same time, the upper top plate 401 has a flushing interface 408, which can spray water to flush the air inlet 4 regularly to further reduce the risk of sediment enrichment. The air inlet 4 of the desulfurization tower 1 is a dry-wet interface. The conventional air inlet 4 easily causes the slurry to accumulate in the flue, dry and scale to form gypsum under high temperature environment, and seriously affect the flow area of the flue. The air inlet 4 of the present invention can solve the problem of slurry accumulation in the flue.
[0079] In a possible implementation, it also includes a support beam layer disposed inside the desulfurization tower 1 for supporting the spray layer 2; the support beam layer is in the form of a main beam 5 plus an end beam 7;
[0080] The end beams 7 are all fixed on the wall of the desulfurization tower 1, and are used to support the ends of each spray pipe in the spray layer 2; there are two main beams 5, which are symmetrically arranged on both sides of the center line of the horizontal section of the desulfurization tower 1, and are used to support the middle part of the spray layer 2;
[0081] The main beam 5 includes a main beam body, a main beam fixed end 501 for fixing the main beam body, and two secondary beams 6 perpendicular to the main beam 5; the secondary beams 6 are symmetrically arranged on both sides of the center line of the horizontal cross section of the desulfurization tower 1, and the main beam fixed end 501 is a rectangular steel and is arranged through the tower wall of the desulfurization tower 1;
[0082] The secondary beam 6 is connected to the main beam 5 via a connecting hole.
[0083] The main beam body is made of rectangular carbon steel, and the outer surface is wrapped by stainless steel alloy 8, which is embedded in the outer surface of the fixed end 501 of the main beam;
[0084] The joints of the main beam body wrapped with stainless steel alloy 8 are welded with double layers of sealing.
[0085] Specifically, the supporting beam layer correspondingly arranged below each spray layer 2 is in the form of an end beam 7 plus a main beam 5. Among them, there are two main beams 5, and the main beams 5 are used to support the middle part of the spray layer 2 and are symmetrically arranged on both sides of the center line of the horizontal section of the desulfurization tower 1. The two main beams 5 are connected by two parallel secondary beams 6, and the two secondary beams 6 are perpendicular to the two main beams 5, which play a role in strengthening the stability of the main beams 5. The secondary beam 6 is embedded in the connecting hole of the main beam 5 and is connected to the main beam 5. The top surface height of the secondary beam 6 is lower than the top surface height of the main beam 5, and the bottom surface of the secondary beam 6 is located at the same horizontal plane as the bottom surface of the main beam 5. The fixed end 501 of the main beam is fixed on the tower wall and is a rectangular steel structure. The end beam 7 is fixed on the inner wall of the desulfurization tower 1 and is used for the ends of the main pipe and branch pipe in the spray layer 2. The end beam 7 and the main beam 5 jointly support the spray layer 2. The top surfaces of the end beam 7 and the main beam 5 are displaced at the same horizontal height, which is convenient for system squaring and installation of the spray layer 2.
[0086] The main beam body is a rectangular carbon steel structure, and the outer surface is wrapped with stainless steel alloy 8 to prevent corrosion of the main beam 5. There is an overlap section at the joint of the stainless steel plate, and the overlap section is located on the two sides of the main beam body. Each end face of the overlap section is spot welded. A layer of stainless steel alloy 8 is also welded on the outer surface of the overlap section to ensure the sealing of the joint. Preferably, in this application, the overlap length a is 5mm, and the length b of the covered stainless steel alloy 8 is about 40mm.
[0087] It should be noted that the hollow cones 203 in the area between the two main beams 5 all adopt a sinking mode to prevent scouring of the main beam 5 and the secondary beam 6.
[0088] Compared with the traditional spray layer 2 support structure of beam + anti-corrosion layer + rubber gasket 1304 + stainless steel cover, it can reduce the one-time investment cost of the system and shorten the system construction period. Compared with the traditional four main beams 5, it reduces the steel consumption of the system. The spray layer 2 of the invention has a simple structure, low investment and operation cost, and stable operation of the desulfurization system. It is particularly suitable for wet desulfurization technology of flue gas at the tail of cement kiln.
[0089] In a possible implementation, the outer surface of the main beam fixed end 501 and the surface of the end beam 7 are both coated with an anti-corrosion coating;
[0090] The outer surface of the main beam fixed end 501 and the part overlapping with the main beam body are wrapped with glass cloth.
[0091] Specifically, the anti-corrosion coating is an anti-corrosion coating containing glass flakes. The outer surface of the main beam fixed end 501 and the portion of the main beam body overlapping the width c are wrapped with glass cloth.
[0092] The glass cloth winding method can increase the structural strength of the end of the main beam 5 and the main beam fixed end 501. This method of strengthening the structure enables the main beam 5 to withstand greater loads and stresses, thereby improving the safety and stability of the entire desulfurization tower 1. In a possible embodiment, the bottom of the main beam fixed end 501 located outside the desulfurization tower 1 is provided with a drainage hole 502, and the drainage hole 502 is connected to the inside of the main beam 5.
[0093] Specifically, Fig.11 yes Fig.10 The CC cross-sectional diagram is as follows: Fig.10 and Fig.11 As shown, the fixed end 501 of the main beam is connected to the main beam body. During the operation of the desulfurization system, if the main beam 5 is punctured, the slurry enters the inside of the main beam 5 and then flows to the outside of the desulfurization tower 1 from the drainage hole 502, which makes it convenient for production personnel to discover the situation in time and determine the corresponding damaged main beam 5 according to the drainage hole 502, which is convenient for maintenance.
[0094] In one possible implementation,
[0095] Each spray layer 2 is connected to a corresponding liquid supply pipeline 9, and each of the liquid supply pipelines 9 corresponds to a circulation pump; the circulation pump at the bottom layer of the desulfurization tower 1 is a variable frequency start circulation pump 10 that can automatically adjust the frequency according to the flue gas concentration at the air inlet, and the remaining circulation pumps are power frequency start circulation pumps 11;
[0096] Each of the liquid supply pipelines 9 is also connected to a first pipeline 901 for flushing the liquid supply pipeline 9 and the pump body of the circulating pump when the circulating pump stops running, and is connected to a second pipeline 902 for flushing the mechanical seal of the circulating pump before starting the circulating pump.
[0097] Specifically, the variable frequency starting circulation pump 10 can control the starting and running speed of the motor through the frequency converter to achieve precise control of the motor speed. The industrial frequency starting circulation pump 11 starts and runs at a fixed frequency. The liquid supply pipeline 9 of the bottom spray layer 2 corresponds to the variable frequency starting circulation pump 10, and the liquid supply pipelines 9 corresponding to the other spray layers 2 are connected to the industrial frequency starting circulation pump 11. Since the raw mill switch of the cement industrial production line affects the change of SO2 in the flue gas at the inlet of the desulfurization tower 1, the number of circulating pumps can be selectively started according to the change of SO2 in the inlet flue gas, and the frequency of the circulating pump can also be selectively started according to the change of SO2 in the inlet, which can effectively reduce the energy consumption of system operation.
[0098] Each liquid supply pipeline 9 is also connected to a first pipeline 901 for flushing the liquid supply pipeline 9 and the pump body of the circulating pump when the circulating pump stops running, so as to prevent the desulfurization slurry from clogging the liquid supply pipeline 9. Each liquid supply pipeline 9 is also connected to a second pipeline 902 for flushing the mechanical seal of the circulating pump before starting the circulating pump. Before starting the circulating pump, the sealing of the circulating pump is flushed to remove the residual medium and debris in the circulating pump to avoid damage to the pump during the startup process. The water source of the first pipeline 901 is process flushing water, and the water source of the second pipeline 902 is production line circulating water.
[0099] The mechanical seal cooling water of the three circulating pumps is discharged into the ditch.
[0100] In a possible embodiment, a slurry pool bottom plate 12 is provided at the bottom of the desulfurization tower 1, and the slurry pool bottom plate 12 includes an angle steel reinforcement mesh 1201 and a plate welded on the angle steel reinforcement mesh 1201 to form an arc-shaped structure with a central convex central cross section.
[0101] Specifically, the desulfurization tower 1 slurry pool bottom plate 12 is divided into blocks and welded to the angle steel reinforcement mesh 1201 to ensure the strength of the desulfurization tower 1 slurry pool bottom plate 12. Compared with the traditional H-shaped steel reinforcement mesh, the system steel consumption is reduced. After the slurry pool bottom plate 12 is pre-assembled and qualified, it is necessary to repeatedly apply anti-rust paint twice on the lower surface of the slurry pool bottom plate 12 as required to prevent the bottom of the slurry pool bottom plate 12 from rusting.
[0102] The slurry pool bottom plate 12 of the desulfurization tower 1 has a certain slope around the center of the slurry pool bottom plate 12. When the disturbance system in the slurry pool area is disturbed, the slurry on the slurry pool bottom plate 12 in the slurry pool area will flow around with the slurry to prevent gypsum slurry from accumulating on the slurry pool bottom plate 12.
[0103] In a possible embodiment, it further includes a first supporting structure 13 for supporting the bottom edge of the slurry pool bottom plate 12;
[0104] The first supporting structure 13 includes a shear key 1301 which is vertically arranged and fixed at a first end, and a base ring plate 1302 which is horizontally arranged;
[0105] The first end of the base ring plate 1302 passes through the second end of the anti-shear key 1301, and a bottom plate support plate 1303 is horizontally fixed to the second end of the base ring plate 1302. The top surface height of the base ring plate 1302 is greater than the top surface height of the bottom plate support plate 1303; the end surface of the slurry pool bottom plate 12 is welded to the side surface of the base ring plate 1302, and the edge bottom surface of the slurry pool bottom plate 12 is welded to the top surface of the bottom plate support plate 1303;
[0106] A gasket 1304 is provided at the bottom of the base ring plate 1302, and a nut is provided at the second end of the shear key 1301, and the base ring plate 1302 is located between the gasket 1304 and the nut; the nut is used to make the bottom surface of the base ring plate 1302 tightly attached to the top surface of the gasket 1304, so as to ensure that the base ring plate 1302 remains horizontal under the pressure of the slurry pool bottom plate 12.
[0107] In a possible embodiment, it further includes a second supporting structure 14 for supporting the middle portion of the slurry pool bottom plate 12;
[0108] The lower part of the second support structure 14 is fixed, the middle part of the top surface of the second support structure 14 fits with the middle part of the bottom surface of the slurry pool bottom plate 12, and the edge of the second support structure 14 is provided with a notch that matches the end surface shape of the bottom support plate 1303.
[0109] The installation and construction sequence of desulfurization tower 1 is as follows:
[0110] Step 1: Pour the concrete surface at one time, pour area A of the tower bottom, and reserve space area B for placing the shear key 1301.
[0111] Step 2: Install the tower body foundation ring plate 1302, connect the foundation ring plate 1302 with the shear key 1301 and install it in place, and place the leveling gasket 1304 under the foundation ring plate 1302 to level the foundation ring plate 1302. The bottom plate support plate 1303 is welded to the foundation ring plate 1302, and the bottom plate support plate 1303 is also horizontally set to facilitate the slurry pool bottom plate 12 to be fixed in place.
[0112] The third step: carry out steel structure construction and install the tower slurry pool bottom plate 12 fixing frame, that is, the second supporting structure 14. During installation, the top curvature of the second supporting structure 14 is close to the bottom curvature of the slurry pool bottom plate 12 to ensure the straightness and flatness of the angle steel.
[0113] Step 4: pour concrete for the second time. The second concrete pouring tower slurry pool bottom plate 12 is fixed to the frame. The top of the concrete is poured to be flush with the top surface of the second support structure 14. The space B area reserved for placing the shear key 1301 on the first concrete pouring surface is poured to ensure the stability of the shear key 1301.
[0114] Step 5: Install the slurry pool bottom plate 12 of the desulfurization tower 1. Before installing the slurry pool bottom plate 12, grind the foundation surface flat. The slurry pool bottom plate 12 is welded to the angle steel mesh frame, and the slurry pool bottom plate 12 and the foundation ring plate 1302 are welded to each other, and the weld is polished flat after welding.
[0115] Step 6: Three pourings of concrete. After two layers of the desulfurization tower 1 are installed, adjust the verticality of the desulfurization tower 1, pour it with non-shrinkage high-strength grouting material, and then tighten the anchor nuts. Finally, weld the nuts to the gasket 1304 and the pad to the bolt seat firmly, and then pour the bottom surface of the foundation ring plate 1302 to the C area between the A area and the B area.
[0116] Step 7: Install other structures of the desulfurization tower.
[0117] In a possible implementation manner, each of the end beams 7 includes an end beam support plate 701 and two reinforcement plates;
[0118] The support plate is horizontally fixed to the inner wall of the desulfurization tower 1 , and the two reinforcing plates are perpendicular to the bottom of the support plate and are fixedly connected to the bottom surface of the support plate and the desulfurization tower 1 respectively.
[0119] Specifically, the end beam support plate 701 is horizontally fixed on the inner wall of the desulfurization tower 1, and the end surface of the end beam support plate 701 fixed on the inner wall of the desulfurization tower 1 is in contact with the inner wall of the desulfurization tower 1. The end of the spray pipe in the spray layer 2 is placed on the surface of the end beam 7 to achieve support. In addition, the two end beam reinforcement plates 702 arranged at the bottom of the end beam support plate 701 further support the end beam 7 and improve the stability of the end beam 7. In this application, the distance Z between the two end beam reinforcement plates 702 is 150 mm, which is convenient for anti-corrosion construction and inspection.
[0120] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.
[0121] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A desulfurization tower spraying system for a cement industry wet desulfurization system, comprising a desulfurization tower, wherein a plurality of spraying layers are arranged in the desulfurization tower, and an air inlet connected to the interior of the desulfurization tower for introducing the flue gas to be treated into the desulfurization tower is arranged on the desulfurization tower, characterized in that: The spray layer includes a main spray pipe, on which a plurality of branch spray pipes are arranged; the main spray pipe and the branch spray pipes are provided with nozzles; The nozzle located at the outer circle of the spray layer is a solid cone, and the nozzle opening faces the bottom of the desulfurization tower; The nozzle located in the inner circle of the spray layer is a hollow cone, and the hollow cone adopts an upper and lower spray structure, and the nozzle opening faces the bottom and the top of the desulfurization tower; An annular panel with an outer end face fixed to the inner wall of the desulfurization tower is arranged below each spray layer, the inner end face of the annular panel is inclined toward the bottom of the desulfurization tower, and the angle N between the annular panel and the center of the desulfurization tower is in the range of 50° to 70°; a plurality of annular panel reinforcement plates for supporting the annular panel are evenly distributed around the center of the annular panel at the bottom of the annular panel; the slurry sprayed from the solid cone of the spray layer is sprayed on the annular panel; the inner end of the annular panel close to the center of the desulfurization tower is toothed, so that the water curtain formed when the slurry flows downward from the annular panel is more uniform, thereby increasing the contact area between the water curtain and the flue gas; The distance from the end surface of the air inlet located in the desulfurization tower to the inner wall of the desulfurization tower is greater than the distance from the annular panel to the inner wall of the desulfurization tower.
2. The desulfurization tower spray system of the cement industry wet desulfurization system according to claim 1 is characterized in that: The distance from the inner end surface of the air inlet to the inner wall of the desulfurization tower is 0.1 to 0.15 times the distance from the inner wall of the desulfurization tower to the center of the desulfurization tower.
3. The desulfurization tower spray system of the cement industry wet desulfurization system according to claim 2 is characterized in that: The air inlet comprises an upper top plate located at the top, a lower bottom plate located at the bottom, and two side plates connecting the upper top plate and the lower bottom plate; one end of the lower bottom plate that penetrates into the desulfurization tower is inclined toward the bottom of the desulfurization tower; A rainproof plate is provided on the upper part of the upper top plate, the size of the rainproof plate in the desulfurization tower is larger than the size of the upper top plate, and the rainproof plate is inclined toward the bottom of the desulfurization tower; sealing plates are provided on both side ends of the rainproof plate, and a first cavity is formed between the two sealing plates, the desulfurization tower and the upper top plate; A vertical filler plate is arranged between the side plate and the inner wall of the desulfurization tower in the vertical direction, and an upper filler plate and a lower filler plate are arranged at the upper and lower ends of the vertical filler plate, so that the side plate, the inner wall of the desulfurization tower, the vertical filler plate, the upper filler plate and the lower filler plate form a closed second cavity to prevent the slurry in the desulfurization tower from entering the air inlet along the side plate, so as to reduce the enrichment of flue sediments; The upper top plate is also provided with a flushing interface for flushing the inner wall of the air inlet.
4. The desulfurization tower spraying system of the cement industry wet desulfurization system according to claim 1 is characterized in that: It also includes a support beam layer arranged inside the desulfurization tower for supporting the spray layer; the support beam layer is in the form of a main beam plus an end beam; The end beams are all fixed on the wall of the desulfurization tower, and are used to support the ends of each nozzle in the spray layer; there are two main beams, which are symmetrically arranged on both sides of the center line of the horizontal section of the desulfurization tower, and are used to support the middle part of the spray layer; The main beam includes a main beam body, a main beam fixed end for fixing the main beam body, and two secondary beams perpendicular to the main beam; the secondary beams are symmetrically arranged on both sides of the center line of the horizontal cross section of the desulfurization tower, and the main beam fixed end is a rectangular steel, which is arranged through the wall of the desulfurization tower; The secondary beam is connected to the main beam via a connecting hole; The main beam body is made of rectangular carbon steel, the outer surface of which is wrapped with a stainless steel alloy and is embedded in the outer surface of the fixed end of the main beam; The joints of the main beam body wrapped with stainless steel alloy are welded with double layers of sealing.
5. The desulfurization tower spraying system of the cement industry wet desulfurization system according to claim 4 is characterized in that: The outer surface of the fixed end of the main beam and the surface of the end beam are coated with an anti-corrosion coating; The outer surface of the fixed end of the main beam and the overlapping section of the main beam body are wrapped with glass cloth.
6. The desulfurization tower spraying system of the cement industry wet desulfurization system according to claim 4 is characterized in that: A drainage hole is provided at a portion of the bottom of the fixed end of the main beam located outside the desulfurization tower, and the drainage hole is communicated with the interior of the main beam.
7. The desulfurization tower spraying system of the cement industry wet desulfurization system according to claim 1 is characterized in that: Each spray layer is connected to a corresponding liquid supply pipeline, and each of the liquid supply pipelines corresponds to a circulation pump; the circulation pump located at the bottom layer of the desulfurization tower is a variable frequency start circulation pump that can automatically adjust the frequency according to the flue gas concentration at the air inlet, and the remaining circulation pumps are power frequency start circulation pumps; Each of the liquid supply pipelines is also connected to a first pipeline for flushing the liquid supply pipeline and the pump body of the circulating pump when the circulating pump stops running, and is connected to a second pipeline for flushing the mechanical seal of the circulating pump before starting the circulating pump.
8. The desulfurization tower spraying system of the cement industry wet desulfurization system according to claim 1 is characterized in that: A slurry pool bottom plate is arranged at the bottom of the desulfurization tower. The slurry pool bottom plate includes an angle steel reinforcement mesh and a plate welded on the angle steel reinforcement mesh to form an arc structure with a central bulge in the central cross section.
9. The desulfurization tower spraying system of the cement industry wet desulfurization system according to claim 8, characterized in that: Also included is a first support structure for supporting a bottom edge of the base plate; The first supporting structure comprises a shear key arranged vertically and fixed at a first end and a base ring plate arranged horizontally; The first end of the base ring plate passes through the second end of the shear key, a bottom plate support plate is horizontally fixed to the second end of the base ring plate, and the top surface height of the base ring plate is greater than the top surface height of the bottom plate support plate; the end surface of the bottom plate is welded to the side surface of the base ring plate, and the edge bottom surface of the bottom plate is welded to the top surface of the bottom plate support plate; A gasket is provided at the bottom of the base ring plate, a nut is provided at the second end of the shear key, and the base ring plate is located between the gasket and the nut; the nut is used to make the bottom surface of the base ring plate tightly attached to the top surface of the gasket, so as to ensure that the base ring plate remains horizontal under the pressure of the base plate.
10. The desulfurization tower spraying system of the cement industry wet desulfurization system according to claim 9, characterized in that: Also included is a second support structure for supporting the middle portion of the bottom plate; The lower part of the second supporting structure is fixed, the middle part of the top surface of the second supporting structure is in contact with the middle part of the bottom surface of the bottom plate, and the edge of the second supporting structure is provided with a notch that matches the end surface shape of the bottom plate support plate.
11. The desulfurization tower spraying system of the cement industry wet desulfurization system according to claim 4, characterized in that: Each of the end beams comprises an end beam support plate and two reinforcement plates; The support plate is horizontally fixed to the inner wall of the desulfurization tower, and the two reinforcing plates are perpendicular to the bottom of the support plate and are fixedly connected to the bottom surface of the support plate and the desulfurization tower respectively.
Citation Information
Patent Citations
Slurry spraying system in adsorption tower
CN101164670A
Anticorrosion and leak detection structure of thermal insulation type absorbing tower
CN105067196A
Desulfurizing tower inlet anti-blocking device and desulfurizing tower comprising same
CN117861420A
Efficient spray absorber tower adopting wet desulphurization process
CN201357047Y
Anti-blocking device for inlet of original flue of desulfurizing tower
CN214973044U