Demolition construction method for old inclined pile group high-pile wharf in limited water area deep and thick mud layer
By removing the panels, cutting off and lifting concrete piles on the high-pile wharf, combined with guide sleeves and auger drills to clean up the silt, the difficulties in dismantling the high-pile wharf in deep mud layers and shallow waters have been solved, and efficient construction has been achieved. Process and berth occupancy reduced.
Patent Information
- Application Number
- CN202411115357.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-10-15
AI Technical Summary
In areas with deep mud layers and shallow water levels, it is difficult to dismantle high-pile wharfs because floating cranes and transport ships cannot enter the site for construction, resulting in large port berth occupation and complicated dismantling processes.
The method of removing panels, cutting off and lifting off concrete piles on the high-pile wharf is adopted, cleaning the silt through guide sleeves and auger drills, and using high-pressure water guns and cranes to cut off and lift off, reducing the occupation of berths and the difficulty of construction.
It achieves efficient dismantling of high-pile wharves in deep mud layers and shallow waters, reduces construction difficulty and berth occupation, improves overall disassembly and assembly efficiency, and avoids the need for floating cranes and transport ships to enter the site.
Smart Images

Figure CN118774069A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of dock demolition, and in particular to a construction method for demolishing an old high-pile dock with inclined pile groups in a thick mud layer in a restricted water area. Background Art
[0002] High-pile docks are a common type of water-based building structure in ports, mainly consisting of panels and several pile foundations at the bottom of the panels. The pile foundations include distribution beams and several concrete piles at the bottom of the distribution beams. To improve the bearing capacity of the pile foundations, the concrete piles are driven obliquely into the underwater soil layer.
[0003] At present, the most common methods for dismantling high-pile docks are blasting and mechanical demolition. Since some waters cannot meet the conditions for blasting (such as military ports, etc.), the demolition of high-pile docks can only be carried out through mechanical demolition.
[0004] In the related art, when a high-pile wharf is demolished by mechanical demolition, its panels, distribution beams and concrete piles are first divided and dismantled, and then the dismantled parts are lifted to a transport ship by a floating crane, and finally transported away from the high-pile wharf by the transport ship.
[0005] With regard to the above-mentioned related technologies, the demolition of high-pile docks currently requires the cooperation of floating cranes and transport ships to enter the site for construction. On the one hand, when floating cranes and transport ships enter the site for construction, they need to occupy a large number of berths in the port, which can easily affect the normal operation of the port; on the other hand, the underwater mud layer in some port waters is relatively thick and the water level is relatively shallow, which cannot meet the construction conditions of large engineering vessels such as floating cranes and transport ships, resulting in difficulties in the demolition of high-pile docks. Therefore, there is room for improvement. Summary of the invention
[0006] In order to facilitate the demolition construction of high-pile docks in areas with thick mud layers and shallow water levels, the present application provides a demolition construction method for old high-pile docks with inclined pile groups in thick mud layers in restricted waters.
[0007] This application provides a method for dismantling an old high-pile dock with a thick mud layer in a restricted water area, which adopts the following technical solution: A construction method for dismantling an old high-pile dock with inclined piles in a thick mud layer in a restricted water area comprises the following steps: S1: Panel removal: Cut the panels at the two adjacent pile foundations at the front end of the high-pile wharf and lift them away from the high-pile wharf; S2: Silt removal: Clean the silt around the concrete piles at the bottom of the pile foundation at the forefront of the high-pile wharf until the bottom of the concrete pile to be cut; S3: Concrete pile cutting: cutting off the bottom end of the concrete pile of the pile foundation; S4: Lifting of concrete piles: At the new front end of the high-pile wharf, the distribution beam together with the cut concrete piles are lifted away from the high-pile wharf by a crane; S5: Repeat steps S1 to S4 until the remaining high-pile docks are dismantled.
[0008] By adopting the above technical solution, the demolition construction process can be carried out on the high-pile wharf, without the need for floating cranes and transport ships to enter the site for construction; on the one hand, it reduces the occupation of berths in the port waters during the demolition of the high-pile wharf, and on the other hand, it solves the problem that floating cranes and transport ships cannot enter the site for construction in areas with deep mud layers and shallow water levels, reducing the difficulty of demolition construction of this type of high-pile wharf. By connecting the distribution beam to the cut concrete piles at the bottom and lifting them away together, it is convenient to improve the overall disassembly and assembly efficiency of the high-pile wharf.
[0009] Preferably, the specific steps of step S2 are as follows: S2.1: Mud cleaning between piles: Several guide sleeves are driven downwardly into the mud between the piles of the adjacent concrete piles of the pile foundation to be removed. At the new front end of the high-pile wharf, the drill rod of the auger is moved into the guide sleeve, and the drill rod is driven by the auger to drill along the guide sleeve to bring the mud in the guide sleeve out of the guide sleeve; S2.2: Cleaning the silt around the pile: Use an amphibious excavator to remove the silt around the concrete pile.
[0010] By adopting the above technical scheme, the guide sleeve and the spiral drill cooperate with each other to realize the quick and convenient removal of the silt between the concrete piles, effectively solving the problem that the silt between the concrete piles cannot be dug out by an excavator due to space limitations and can only be removed manually; the setting of the guide sleeve, on the one hand, cooperates with the drilling drill rod to realize the rapid guidance of the silt between the concrete piles to the outside of the guide sleeve, and on the other hand, limits the drill rod of the spiral drill to prevent deviation or shaking during the drilling process of the spiral drill rod.
[0011] Preferably, a high-pressure water gun is supported on the outer periphery of the top end of the material guiding sleeve, and the high-pressure water gun is arranged toward the axial direction of the material guiding sleeve.
[0012] By adopting the above technical solution, during the subsequent drilling of the drill rod along the guide sleeve, after the high-pressure water gun is connected to the water source, high-pressure water flow is continuously sprayed toward the spiral blades of the drill rod through the high-pressure water gun, so as to promptly flush the silt brought out during the drilling process of the drill rod from the drill rod, thereby achieving timely cleaning of the drill rod and reducing the safety hazard caused by the falling of silt adhering to the drill rod blades during the subsequent spiral drilling process.
[0013] Preferably, a high-pressure water pump is further arranged on the outer periphery of the material guiding sleeve; the water inlet end and the water outlet end of the high-pressure water pump are respectively connected with a water inlet pipe and a water outlet pipe, and the water outlet pipe is connected with the high-pressure water gun.
[0014] By adopting the above technical solution, during the actual construction process, after the water inlet pipe is placed underwater, a high-pressure water pump is used to draw seawater or river water on-site and pump it into the high-pressure water gun to serve as the water source for the high-pressure water gun, so as to facilitate the subsequent flushing of the drill rod by the high-pressure water gun during the drilling of silt by the drill rod.
[0015] Preferably, the bottom end of the material guiding sleeve is sharpened to form a socket end.
[0016] By adopting the above technical solution and setting the insertion end of the material guide sleeve, the material guide sleeve can be more easily driven into the underwater mud layer when the material guide sleeve is subsequently inserted.
[0017] Preferably, in step S3, before cutting the concrete pile, the crane sling is first connected to the distribution beam to be removed.
[0018] By adopting the above technical solution, the crane is first connected to the distribution beam to be dismantled before cutting the concrete piles, and the crane is used to assist in limiting the distribution beam and the concrete piles at the bottom of the distribution beam, thereby preventing the pile base from becoming unstable or even overturning due to external loads after the concrete piles are subsequently cut off, thereby affecting the safety of underwater construction.
[0019] Preferably, in step S3, when connecting the distribution beam and the crane sling, a number of support beams are evenly arranged at the bottom of the distribution beam, and the two ends of the support beam are respectively extended out of both sides of the distribution beam, and the crane sling is respectively connected to the two ends of the support beam by cables.
[0020] By adopting the above technical solution, when the subsequent crane hoists the distribution beam, the distribution beam can be lifted by several distribution beams, and the overall load of the distribution beam can be evenly distributed on several supporting beams, so that the crane can smoothly hoist the distribution beam.
[0021] Preferably, in step S3, when the support beam is arranged at the bottom of the distribution beam, the hoisting support beam is fixed to the bottom of the distribution beam by expansion bolts.
[0022] By adopting the above technical solution, a reliable connection between the support beam and the distribution beam is achieved. On the one hand, it is convenient to subsequently connect the crane sling and the support beam through cables; on the other hand, it prevents the support beam from slipping during the subsequent crane lifting of the distribution beam, thereby affecting the stability of the lifting.
[0023] In summary, the present application includes at least one of the following beneficial technical effects: 1. Start construction from the front end of the high-pile wharf, first dismantle the panel part of the high-pile wharf, then cut off the concrete piles of the front end pile foundation of the high-pile wharf, and finally lift the distribution beam together with the cut concrete piles away from the high-pile wharf by crane at the new front end of the high-pile wharf; during the demolition construction process, the deployment and operation of related equipment can be carried out on the high-pile wharf, and there is no need for large engineering ships such as floating cranes and transport ships to enter the site for construction, which solves the problem that floating cranes and transport ships cannot enter the site for construction when facing thick mud layers and shallow water levels, affecting the demolition construction of the high-pile wharf.
[0024] 2. When cleaning the silt between concrete piles, first drive several guide sleeves downwardly into the silt between the concrete piles at an angle, and at the new front end of the high-pile wharf, insert the drill rod of the spiral drill into the guide sleeve and drill downward along the guide sleeve. The silt between the concrete piles is directed out of the guide sleeve by the drill rod, which facilitates the cleaning of the silt between the concrete piles and reduces the difficulty of cleaning the silt between the concrete piles.
[0025] 3. A high-pressure water gun is supported on the outer periphery of the top end of the guide sleeve and is arranged toward the axial direction of the guide sleeve; when the subsequent spiral drill drives the drill rod to drill along the guide sleeve to drill the silt of the concrete pile, the high-pressure water flow is continuously sprayed toward the drill rod through the high-pressure water gun, and the silt brought out of the drill rod by the sprayed high-pressure water flow is blown off from the drill rod blades, thereby cleaning the spiral drill rod and reducing the situation where silt adheres to the drill rod and the drill rod blades. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the state of the embodiment of the present application when being used to clean the silt between concrete piles.
[0027] Figure 2 It is a structural schematic diagram used to illustrate the material guide sleeve in an embodiment of the present application.
[0028] Figure 3 yes Figure 2 Enlarged schematic diagram of part A in the middle.
[0029] Figure 4 yes Figure 2 Enlarged schematic diagram of part B in the middle.
[0030] Figure 5 It is a schematic diagram of an embodiment of the present application used to illustrate the state of supporting the installation support beam at the bottom of the redistribution beam.
[0031] Figure 6 yes Figure 5 Enlarged schematic diagram of part C in the middle.
[0032] Description of reference numerals: 1. Panel; 2. Distribution beam; 3. Concrete pile; 4. Material guide sleeve; 41. High-pressure water gun; 42. High-pressure water pump; 43. Water inlet pipe; 44. Water outlet pipe; 5. Auger drilling rig; 6. Support beam; 61. Lifting ring. DETAILED DESCRIPTION
[0033] The following is combined with Figure 1-6 This application is described in further detail.
[0034] The present application embodiment discloses a method for dismantling an old high-pile dock with inclined piles in a thick mud layer in a restricted water area, comprising the following steps: S1: Panel 1 removal: Refer to Figure 1 , the specific steps are as follows: S1.1: Cut the panel 1 at two adjacent pile foundations at the front end of the high-pile wharf in sections by using a rope saw cutter; S1.2: On the high-pile wharf, the panel 1 cut off by the rope saw cutting machine is lifted off the high-pile wharf by a crane; S1.3: Repeat steps S1.1-S1.2 until the panel 1 at the two adjacent pile foundations at the front end of the high-pile wharf is removed; S2: Sludge removal: Refer to Figure 1 and Figure 2 , the specific steps are as follows, S2.1: Cleaning of silt between piles: S2.1.1: Use a vibrating hammer to drive a plurality of guide sleeves 4 obliquely downward into the mud layer between the adjacent concrete piles 3 of the pile foundation to be removed; S2.1.2: The auger drill 5 is positioned: the auger drill 5 is moved to the new front end of the high-pile wharf and the drill rod of the auger drill 5 is controlled to penetrate into the guide sleeve 4; S2.1.3: Drilling out the silt between piles: The auger 5 is used to control the drill rod to drill downward along the guide sleeve 4 to drill out the silt in the guide sleeve 4, thereby cleaning most of the silt between the adjacent concrete piles 3; S2.1.4: The auger 5 keeps the drill rod rotating and controls the drill rod to move out of the guide sleeve 4; S2.1.5: Repeat steps S2.1.2 to S2.1.4 until the drilling of the sludge in the remaining material guide sleeves 4 is completed.
[0035] S2.1.6: Pull the guide sleeve 4 out of the underwater mud layer by a vibrating hammer.
[0036] S2.2: Cleaning the silt around the pile: remove the silt around the concrete pile 3 by using an amphibious excavator.
[0037] S2.3: Divers dive underwater and use high-pressure water jets to clean the silt remaining between the three concrete piles.
[0038] The guide sleeve 4 cooperates with the auger 5 to quickly remove the silt between the concrete piles 3, thereby reducing the difficulty in clearing the silt between the concrete piles 3 caused by the small space between the concrete piles 3 and the position limitation of the distribution beam 2 on the top of the concrete pile 3, which makes it difficult for excavators and other equipment to start excavating the silt in the area between the concrete piles 3.
[0039] The guide sleeve 4 is provided, on the one hand, the guide sleeve 4 can cooperate with the drill rod of the auger 5 to realize directional transportation of silt, which is convenient for cleaning the silt between the concrete piles 3. On the other hand, the guide sleeve 4 can be used to assist in limiting the drill rod of the auger 5 to prevent the auger 5 from shaking or deviating during the actual drilling process, so as to facilitate better cleaning of the silt between the concrete piles 3 by drilling with the drill rod of the auger 5.
[0040] The drill rod is moved out of the sleeve while the auger 5 is rotating, so that the mud adhering to the drill rod can be thrown out from between the blades through the rotation of the drill rod, thereby reducing the mud adhering to the drill rod blades, which makes subsequent cleaning difficult.
[0041] Reference Figure 2 and Figure 3 The bottom end of the material guide sleeve 4 is sharply arranged to form a socket end, so that when the material guide sleeve 4 is inserted and hit by a vibration hammer, the bottom end of the material guide sleeve 4 is easier to be inserted into the depth of the underwater mud layer.
[0042] Reference Figures 2 to 4 A high-pressure water gun 41 is installed on the outer periphery of the top of the guide sleeve 4, and the high-pressure water gun 41 is arranged toward the axial direction of the guide sleeve 4; a high-pressure water pump 42 is also arranged on the outer periphery of the guide sleeve 4, and the high-pressure water pump 42 is fixed on the outer periphery of the guide sleeve 4 through a bracket, and the water inlet end and the water outlet end of the high-pressure water pump 42 are respectively connected with a water inlet pipe 43 and a water outlet pipe 44, and a section of the water inlet pipe 43 away from the high-pressure water pump 42 extends to the bottom of the guide sleeve 4. One end of the water outlet pipe 44 away from the high-pressure water pump 42 is connected to the high-pressure water gun 41.
[0043] In step S2.1.3 and step S2.1.4, seawater is pumped into the high-pressure water gun 41 by the high-pressure water pump 42 and sprayed out through the high-pressure water gun 41. The high-pressure water flow sprayed by the high-pressure water gun 41 is used to blow away the silt adhering between the drill pipe blades, making the drill pipe of the spiral drilling rig 5 less likely to be adhered to silt.
[0044] S3: Cutting of concrete pile 3: Cutting of the bottom end of concrete pile 3 at the bottom of the pile base; Figure 5 and Figure 6 , the specific steps are as follows: S3.1: The crane is in place; the crane is moved to the new front end of the high-pile wharf, and the crane spreader is moved above the distribution beam 2 to be dismantled.
[0045] S3.2: Installation of support beam 6: A plurality of support beams 6 are arranged at the bottom of distribution beam 2, and the two ends of support beam 6 are respectively extended out of the two sides of distribution beam 2; support beam 6 is fixed to the bottom of distribution beam 2 by a plurality of expansion bolts. In this embodiment, support beam 6 is a double-jointed I-beam; both ends of support beam 6 are welded and fixed with hanging rings 61.
[0046] S3.3: Spreader connection: connect the spreader of the crane to the lifting rings 61 at both ends of the support beam 6 through cables, specifically, connect the cables to the lifting rings 61 through bow-shaped shackles. Then the crane controls the spreader to move upward to tighten the cables connected to the support beam 6.
[0047] S3.4: Cut off the bottom of the concrete using a wire saw.
[0048] By connecting the crane sling to the support beam 6 fixed at the bottom of the distribution beam 2 before cutting the concrete piles 3, the distribution beam 2 can be temporarily limited by the crane, thereby reducing the situation in which the distribution beam 2 becomes unstable and overturns due to vibration or external loads after all concrete piles 3 at the bottom of the distribution beam 2 are cut off, thereby affecting the safety of underwater workers.
[0049] S4: Lifting away the concrete piles 3: At the new front end of the high-pile wharf, the distribution beam 2 together with the cut concrete piles 3 are lifted away from the high-pile wharf by a crane.
[0050] S5: Repeat steps S1 to S4 until the remaining high-pile docks are dismantled.
[0051] During the demolition construction process of the high-pile wharf in this application, the relevant demolition equipment is basically deployed and operated on the high-pile wharf, and there is no need for large engineering ships such as floating cranes and transport ships to enter the site for operation. This effectively solves the problem of difficulty in dismantling and assembling the high-pile wharf due to the environment such as thick mud layers and shallow water levels that restrict the entry of floating cranes and transport ships for operation.
[0052] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A construction method for dismantling an old high-pile dock with inclined piles in a thick mud layer in restricted waters. Features: The following steps are involved: S1: Removal of the panel (1): cutting the panel (1) at two adjacent pile foundations at the front end of the high-pile wharf and lifting it away from the high-pile wharf; S2: silt removal: cleaning the silt around the concrete pile (3) at the bottom of the pile foundation at the forefront of the high-pile wharf until the bottom of the concrete pile (3) is cut; S3: cutting off the concrete pile (3): cutting off the bottom end of the concrete pile (3) of the pile foundation; S4: Lifting away the concrete piles (3): At the new front end of the high-pile wharf, the distribution beam (2) together with the cut concrete piles (3) are lifted away from the high-pile wharf by a crane; S5: Repeat steps S1 to S4 until the remaining high-pile docks are dismantled.
2. A method for dismantling an old high-pile dock with inclined piles in a deep mud layer in restricted waters according to claim 1, Features: The specific steps of step S2 are as follows: S2.1: Mud cleaning between piles: a plurality of guide sleeves (4) are driven obliquely downward into the mud between piles of the adjacent concrete piles (3) of the pile foundation to be removed, and at the new front end of the high-pile wharf, the drill rod of the auger (5) is moved into the guide sleeve (4), and the auger (5) drives the drill rod to drill along the guide sleeve (4), so as to bring the mud in the guide sleeve (4) out of the guide sleeve (4); S2.2: Cleaning the silt around the pile: Use an amphibious excavator to remove the silt around the concrete pile (3).
3. The method for dismantling an old high-pile dock with inclined piles in a deep mud layer in restricted waters according to claim 2, Features: A high-pressure water gun (41) is supported on the outer periphery of the top end of the material guiding sleeve (4), and the high-pressure water gun (41) is arranged toward the axial direction of the material guiding sleeve (4).
4. A method for dismantling an old high-pile dock with inclined piles in a deep mud layer in restricted waters according to claim 3, Features: A high-pressure water pump (42) is also provided on the outer periphery of the material guiding sleeve (4); the water inlet end and the water outlet end of the high-pressure water pump (42) are respectively connected to a water inlet pipe (43) and a water outlet pipe (44), and the water outlet pipe (44) is connected to the high-pressure water gun (41).
5. A method for dismantling an old high-pile dock with inclined pile groups in a deep mud layer in restricted waters according to any one of claims 2 to 4, Features: The bottom end of the material guiding sleeve (4) is sharpened to form a socket end.
6. The method for dismantling an old high-pile dock with inclined piles in a deep mud layer in restricted waters according to claim 1, Features: In step S3, before cutting the concrete pile (3), the crane sling is first connected to the distribution beam (2) to be removed.
7. A method for dismantling an old high-pile dock with inclined piles in a deep mud layer in restricted waters according to claim 6, Features: In step S3, when connecting the distribution beam (2) and the crane sling, a plurality of support beams (6) are evenly arranged at the bottom of the distribution beam (2), and the two ends of the support beam (6) are respectively extended out of the two sides of the distribution beam (2), and the crane sling is respectively connected to the two ends of the support beam (6) by cables.
8. The method for dismantling an old high-pile dock with inclined piles in a deep mud layer in restricted waters according to claim 7, Features: In step S3, when the support beam (6) is arranged at the bottom of the distribution beam (2), the hoisting support beam (6) is fixed to the bottom of the distribution beam (2) by means of expansion bolts.