High-precision positioning construction method for in-situ newly-built pile foundation of old high-pile wharf
By using a floating marker mechanism to record the position information of the old pile foundation and adjust the connecting rope during the in-situ construction of the high-pile wharf, the problem of collision between the new pile foundation and the old pile foundation was solved, and high-precision positioning and stable installation were achieved. Improved construction efficiency and safety.
Patent Information
- Application Number
- CN202411115358.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-10-15
AI Technical Summary
During the in-situ construction of a high pile wharf, the new pile foundation may hit the old pile foundation, affecting construction efficiency and safety.
A floating marking mechanism is used to record the extension direction and tilt angle of the old pile foundation, and this information is used to drive the new pile foundation into a new position to avoid collisions. At the same time, the knotting and adjustment components of the connecting rope are used to ensure positioning stability and reduce floating air bags. offset.
It effectively avoids the collision between the new pile foundation and the old pile foundation, improves the accuracy and safety of the pile foundation installation, and ensures the smooth progress of the construction.
Smart Images

Figure CN118774124A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of high-pile docks, and in particular to a high-precision positioning construction method for a pile foundation newly built in situ of an old high-pile dock. Background Art
[0002] A high-pile wharf is composed of the superstructure (pile platform or cap), pile foundation, shore connection structure, shore lock and wharf equipment. The superstructure constitutes the wharf surface and is connected to the pile foundation as a whole. It directly bears the vertical and horizontal loads acting on the wharf surface and transfers them to the pile foundation. The pile foundation is used to support the superstructure and transfer the load of the superstructure and the wharf surface to the deep foundation. It is also conducive to stabilizing the shore slope.
[0003] A high-pile wharf usually includes a pile foundation and a platform. The pile foundation is driven into the seabed, a beam is set up on the top of the pile foundation, and a platform is set up on the beam. The pile foundation of the high-pile wharf is an inclined pile, and four inclined piles form a group of piles, which are higher than the sea surface. Some old wharves need to be rebuilt because they were built a long time ago, and the new construction is usually in situ. Therefore, the existing high-pile wharf needs to be demolished first. When demolishing, the platform and beam must be dismantled first. Since the pile foundation is tens of meters long, it is impossible to pull out the entire pile foundation, and only the pile foundation two meters below the seabed can be cut to facilitate the subsequent dredging of the seabed. After that, a new pile foundation is driven into the position of the original adjacent pile foundation.
[0004] Regarding the above-mentioned related technologies, since the pile foundations two meters below the seabed still exist and are a group of inclined piles, when new pile foundations are subsequently driven into the seabed, the new pile foundations are likely to collide with the old pile foundations, affecting the construction of the pile foundations. Summary of the invention
[0005] In order to reduce the situation where the new pile foundation hits the old pile foundation, the present application provides a high-precision positioning construction method for a new pile foundation built in situ of an old high-pile wharf.
[0006] The present application provides a high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf, which adopts the following technical solutions: A high-precision positioning construction method for a newly built pile foundation in situ of an old high-pile wharf comprises the following steps: S1: demolish the original pier and leave the pile foundation exposed above the sea; S2: Mark each pile foundation, measure and record the angle and position of each pile foundation, and then cut off the pile foundation to leave the lower pile foundation; S3: a floating marking mechanism is arranged on the top of the lower pile foundation according to the mark, and the extension direction and inclination angle of the corresponding lower pile foundation are recorded on the floating marking mechanism; S4: cleaning silt from the seabed by means of a desilting structure; S5: According to the extension direction and inclination angle of the corresponding lower pile foundation on the floating marking mechanism, the new pile foundation is driven into the new position, and the collision between the new pile foundation and the old pile foundation is avoided, and then the installation of the new pile foundation is completed step by step and in an orderly manner; S6: Complete the construction of the new wharf based on the new pile foundation.
[0007] By adopting the above technical solution, after the pile foundation is cut off, a floating marking mechanism is immediately set on the top of the corresponding lower pile foundation. The floating marking mechanism can record the extension direction and inclination angle of the corresponding lower pile foundation. According to the extension direction and inclination angle of the corresponding lower pile foundation on the floating marking mechanism, the new pile foundation is driven into the new position, which can avoid collision between the new pile foundation and the old pile foundation.
[0008] Optionally, in step S2, after the pile foundation is cut off, at least three through holes are opened on the top of the lower pile foundation, the number of connecting ropes is the same as the number of through holes, the connecting ropes pass through the through holes, and then the connecting ropes and the lower pile foundation are connected.
[0009] By adopting the above technical solution, the forces on the multiple connecting ropes can be made more balanced, thereby reducing the rotation and deviation of the floating airbag.
[0010] Optionally, in step S2, before the connecting rope passes through the through hole, the connecting rope is first knotted near the bottom to form a first knot, the connecting rope is passed through the top of the lower pile foundation and through the through hole, and then the connecting rope located on the outside of the lower pile foundation is knotted to form a second knot, and the top of the connecting rope is connected to the bottom of the floating marking mechanism.
[0011] By adopting the above technical solution, the connection between the connecting rope and the lower pile foundation is achieved by knotting the connecting rope, which is simple, fast and convenient for subsequent dismantling.
[0012] Optionally, in step S3, each connecting rope is connected to the bottom of the floating marking mechanism through an adjusting assembly, and the adjusting assembly includes an installation frame arranged at the bottom of the floating marking mechanism, a winding drum rotatably arranged in the installation frame, and a winding spring arranged between the installation frame and the winding drum, and the top of the connecting rope is wound on the winding drum.
[0013] By adopting the above technical solution, when the distance between the sea surface and the seabed becomes larger, the coil spring in the installation frame can be compressed, so that the coil spring exerts a certain elastic force on the winding drum, which has a tendency to pull the floating airbag downward. Therefore, the connecting rope will be tightened to reduce the effect of the floating airbag deviation caused by the relaxation of the connecting rope when the distance between the sea surface and the seabed becomes larger.
[0014] Optionally, in step S3, when the connecting rope is knotted, the distance between the first knot and the second knot is greater than the wall thickness of the lower pile foundation.
[0015] By adopting the above technical solution, it is easy to perform a knotting operation on the connecting rope to form a second knot.
[0016] Optionally, in step S2, when cutting the pile foundation, the pile foundation is cut to at least two meters below the seabed.
[0017] By adopting the above technical solution, subsequent dredging work is facilitated to reduce the impact of pile foundation on subsequent dredging work.
[0018] Optionally, in step S3, the floating marking mechanism includes a counterweight plate and a floating airbag arranged on the top of the counterweight plate, the counterweight plate and the floating airbag are both elliptical in shape, and a plurality of the adjustment components are circumferentially arranged at the bottom of the counterweight plate.
[0019] By adopting the above technical solution, the overall center of gravity of the floating marker mechanism is lowered, which can improve stability in the water. Moreover, the non-circular design helps to reduce the vortex generated when the water flows through the floating airbag. The vortex is a rotating flow formed when the water flows around an object. It will increase the rotational torque of the object. The elliptical or other non-circular design can guide the water flow more smoothly and reduce the formation of vortex.
[0020] Optionally, in step S3, a plurality of water flow channels are provided around the floating airbag, and a collecting channel communicating with the plurality of water flow channels is provided in the middle of the floating airbag.
[0021] By adopting the above technical solution, water can enter the collecting channel through the water flow channel and flow out from the water flow channels at other positions, thereby guiding the water flow so that the water flow can flow through the floating airbag more smoothly and reduce the generation of turbulence and eddy currents.
[0022] Optionally, in step S3, two counterweight blocks symmetrical to each other are circumferentially arranged on the counterweight plate.
[0023] By adopting the above technical solution, the weight of one side of the floating airbag can be increased to serve as a balance point, thereby reducing the rotation of the floating airbag.
[0024] Optionally, in step S2, at least three through holes are arranged along the circumference of the lower pile foundation.
[0025] By adopting the above technical solution, the forces on the multiple connecting ropes can be made more balanced, thereby reducing the rotation and deviation of the floating airbag.
[0026] In summary, the present application includes at least one of the following beneficial technical effects: 1. After the pile foundation is cut off, a floating marking mechanism is immediately set on the top of the corresponding lower pile foundation. The floating marking mechanism can record the extension direction and inclination angle of the corresponding lower pile foundation. According to the extension direction and inclination angle of the corresponding lower pile foundation on the floating marking mechanism, the new pile foundation is driven into the new position to avoid collision between the new pile foundation and the old pile foundation; 2. When the distance between the sea surface and the seabed increases, the coil spring in the installation frame can be compressed, so that the coil spring exerts a certain elastic force on the reel, which has a tendency to pull the floating airbag downward. Therefore, the connecting rope will be tightened to reduce the effect of the floating airbag deviation caused by the relaxation of the connecting rope when the distance between the sea surface and the seabed increases; 3. Two counterweights can increase the weight of one side of the floating airbag to serve as a balance point, thereby reducing the rotation of the floating airbag. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the original pile foundation of the old high-pile wharf using a high-precision positioning construction method; Figure 2 It is a schematic diagram of the lower pile foundation and floating marking mechanism of the high-precision positioning construction method of the newly built pile foundation in situ of the old high-pile wharf; Figure 3 It is a cross-sectional view of the adjustment components of the high-precision positioning construction method for the newly built pile foundation in situ of the old high-pile wharf; Figure 4 This is a bottom view of the counterweight plate of the high-precision positioning construction method for the newly built pile foundation in situ of the old high-pile wharf; Figure 5 It is a cross-sectional view of a floating airbag for a high-precision positioning construction method of a new pile foundation built in situ at an old high-pile wharf.
[0028] Explanation of the reference numerals in the accompanying drawings: 1. lower pile foundation; 2. through hole; 3. connecting rope; 4. first knot; 5. second knot; 6. floating marking mechanism; 7. counterweight plate; 8. floating airbag; 9. adjustment assembly; 10. mounting frame; 11. winding drum; 12. winding spring; 13. counterweight block; 14. water flow channel; 15. aggregation channel. DETAILED DESCRIPTION
[0029] The following is combined with Figures 1 to 5 This application is described in further detail.
[0030] The present application embodiment discloses a high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf. Figure 1 The high-precision positioning construction method for the newly built pile foundation in situ of the old high-pile wharf includes the following steps: S1: Before construction, on-site investigation and assessment are required. A detailed investigation and assessment of the structure, materials, and surrounding environment of the terminal is conducted. Based on the investigation results, a detailed demolition plan is formulated, including the scope, method, sequence, and schedule of demolition, and safety measures and emergency plans are prepared to deal with possible emergencies. Determine the design and construction technical plan, including equipment selection, staffing, etc. Train personnel involved in the demolition work on safe operating procedures, safety protection measures, and emergency response methods. Prepare the required construction machinery and equipment, such as cranes, cutting machines, and transport vehicles. If necessary, formulate a traffic control plan and announce it to the public in advance to reduce the impact on surrounding traffic. Communicate and coordinate with all relevant parties, including the construction unit, design unit, supervision unit, construction unit, and quality supervision department.
[0031] After the pre-construction preparations were completed, the original dock was dismantled, leaving the pile foundation exposed above the sea.
[0032] S2: Mark each pile foundation and give each pile foundation a number, measure and record the angle and position of each pile foundation, and then draw a scaled plan. The scaled plan records the number, inclination direction and inclination angle of each pile foundation, and records the actual distance between two adjacent pile foundations.
[0033] It should be noted that when measuring the angle of a pile foundation, an inclinometer and a total station can be used, or a sonar device can be used to measure the position and shape of the pile foundation and then calculate the inclination angle, or an ultrasonic device can be used to detect the internal structure of the pile foundation and evaluate the inclination of the pile foundation by analyzing the reflected sound waves.
[0034] Determine the order of cutting piles according to the proportionally scaled plan view, and gradually cut off the pile foundations in that order, leaving the lower pile foundation 1, so that the top of the lower pile foundation 1 is a plane, and when cutting off the pile foundations, cut off the pile foundations to at least two meters below the seabed. In this embodiment, cut off to two meters below the seabed.
[0035] It should be noted that when cutting the pile foundation, a cutting device is required. The cutting device can be a diamond wire saw, an abrasive jet cutting device, a super pile driving ship or a ring cutting device to achieve the cutting of the pile foundation.
[0036] S3: Reference Figure 2After the truncation of a pile foundation is completed each time, at least three through holes 2 are opened on the top of the lower pile foundation 1. The number of the connecting rope 3 is the same as the number of through holes 2. First, mark the place where the knot is to be tied on the connecting rope 3 to facilitate the subsequent knotting operation. The connecting rope 3 is knotted near the bottom to form the first knot 4. The connecting rope 3 is inserted from the top of the lower pile foundation 1 and passes through the through hole 2. Then, the connecting rope 3 located outside the pile foundation is knotted to form the second knot 5, thereby connecting the connecting rope 3 and the lower pile foundation 1. According to the mark of the pile foundation, a floating marking mechanism 6 is installed on the top of the pile foundation, and the top of the connecting rope 3 is connected to the bottom of the floating marking mechanism 6. When the connecting rope 3 is knotted, the distance between the first knot 4 and the second knot 5 is greater than the wall thickness of the lower pile foundation 1. Such a configuration can facilitate the knotting operation of the connecting rope 3 to form the second knot 5.
[0037] In this embodiment, the number of through holes 2 on the top of each lower pile foundation 1 is four, and the four through holes 2 are arranged along the circumference of the lower pile foundation 1. Since the floating marking mechanism 6 is connected to the lower pile foundation 1 through multiple connecting ropes 3, when the floating marking mechanism 6 itself has a large buoyancy, the connecting ropes 3 can be tightened as much as possible to keep the force of each connecting rope 3 as similar as possible, so that the floating marking mechanism 6 is not easy to deviate and rotate, so that the floating marking mechanism 6 is located directly above the top of the corresponding lower pile foundation 1 as much as possible, so as to improve the accuracy of the position of the lower pile foundation 1 displayed by the floating marking mechanism 6.
[0038] Reference Figure 2 and Figure 3 Preferably, the floating marking mechanism 6 includes a counterweight plate 7 and a floating airbag 8, the floating airbag 8 is installed on the top of the counterweight plate 7, the counterweight plate 7 and the floating airbag 8 are both elliptical, and the floating airbag 8 can provide sufficient buoyancy in the water. A plurality of adjustment components 9 are installed at the bottom of the counterweight plate 7, and the plurality of adjustment components 9 are circumferentially arranged at the bottom of the counterweight plate 7. The number of the adjustment components 9 is the same as the number of the connecting ropes 3, and each connecting rope 3 is connected to the bottom of the counterweight plate 7 through the adjustment component 9. The adjusting component 9 includes a mounting frame 10, a winding drum 11 and a coil spring 12. The mounting frame 10 is fixed to the bottom of the counterweight plate 7. The winding drum 11 is rotatably connected to the inside of the mounting frame 10. The rotating axis of the winding drum 11 is horizontally arranged. The coil spring 12 is located inside the mounting frame 10. The fixed end of the coil spring 12 is connected to the inner wall of the mounting frame 10. The movable end of the coil spring 12 is connected to the rotating axis of the winding drum 11, and the top of the connecting rope 3 is wound on the winding drum 11. In the present embodiment, there are two coil springs 12, and the two coil springs 12 are symmetrically arranged about the winding drum 11.
[0039] When the floating marking mechanism 6 is put into the water, the floating airbag 8 can provide sufficient buoyancy for the entire floating marking mechanism 6, and the extension direction and inclination angle corresponding to the lower pile foundation 1 can be pasted on the top of the floating airbag 8 by means of a sticker. Considering that the seawater will have a certain degree of turbidity during construction, the turbid water may absorb or scatter light and reduce the saturation of the color. Therefore, it is particularly important to choose a marking color that can provide the best visibility on the turbid sea surface, such as orange. Orange is one of the colors with high visibility and is usually very eye-catching in the marine environment. It can still maintain good visibility under low visibility conditions.
[0040] When the distance between the sea surface and the seabed increases, the connecting rope 3 wound on the winding drum 11 is reduced, and the unfolded connecting rope 3 is increased, so that the coil spring 12 in the installation frame 10 can be compressed, so that the coil spring 12 exerts a certain elastic force on the winding drum 11, with a tendency to pull the floating airbag 8 downward. Since the elastic potential energy is smaller than the buoyancy of the floating airbag 8, the connecting rope 3 will only be tightened to reduce the effect of the floating airbag 8 deviation caused by the relaxation of the connecting rope 3 when the distance between the sea surface and the seabed increases.
[0041] The material of the connecting rope 3 can be nylon, polypropylene, polyethylene, hollow rope or other materials with a density lower than seawater. In the present embodiment, the connecting rope 3 is a nylon rope.
[0042] It should be noted that, since the counterweight plate 7 is arranged at the bottom of the floating airbag 8, the overall center of gravity of the floating marking mechanism 6 is lower, which can improve the stability in the water; moreover, the counterweight plate 7 and the floating airbag 8 are both elliptical in design, and the non-circular design helps to reduce the vortex generated when the water flows through the floating airbag 8. The vortex is a rotating flow formed when the water flows around an object, which will increase the rotational torque of the object. The elliptical or other non-circular design can guide the water flow more smoothly and reduce the formation of vortexes; the major axis and minor axis of the elliptical floating airbag 8 provide different resistance characteristics in the water, which helps to increase the stability of the floating airbag 8 and reduce the rotation caused by the impact of the water flow.
[0043] Reference Figure 2 and Figure 4 Preferably, two counterweight blocks 13 are fixed to the counterweight plate 7 in the circumferential direction. The two counterweight blocks 13 are symmetrically arranged with respect to the circular shape of the counterweight plate 7, and the two counterweight blocks 13 are respectively located at two ends corresponding to the short axis of the elliptical counterweight plate 7. With such an arrangement, the weight of one side of the floating airbag 8 can be increased to serve as a balance point, thereby reducing the self-rotation of the floating airbag 8.
[0044] Reference Figure 2 and Figure 5Furthermore, a plurality of water flow channels 14 are provided around the floating airbag 8, and a collection channel 15 connected to the plurality of water flow channels 14 is provided in the middle of the floating airbag 8, and the water flow channels 14 and the collection channel 15 are not connected to the interior of the floating airbag 8. In this way, water can enter the collection channel 15 through the water flow channels 14 and flow out from the water flow channels 14 at other positions, so that the water flow can be guided, so that the water flow can flow through the floating airbag 8 more smoothly, and the generation of turbulence and eddy currents can be reduced.
[0045] S4: The silt on the seabed is cleaned by a dredging structure, which may be a grab dredger, a suction dredger or a submarine industrial robot. When dredging, it should be noted that the depth of the silt to be cleaned needs to be the same as the height of the cut-off pile foundation, that is, in this embodiment, the dredging depth is 2 meters; in addition, when the pile foundation is cut off by the cutting equipment, part of the silt on the top of the lower pile foundation 1 will be removed. Therefore, in this step, the top of the lower pile foundation 1 does not need to be cleaned again, so that the connecting rope 3 can be avoided as much as possible during the dredging operation.
[0046] It should be noted that before driving a new pile foundation, clearing the silt on the seabed has the following effects: it can improve the bearing capacity of the pile foundation. The silt on the seabed usually has a lower bearing capacity. Clearing the silt can ensure that the pile foundation is directly supported on a harder soil layer, thereby improving the bearing capacity and stability of the pile foundation; the silt layer is highly compressible. If the pile foundation is driven directly on the silt, it may cause the pile foundation to settle, affecting the stability and safety of the structure; the silt may cause the pile foundation to shift or tilt during construction. Clearing the silt on the seabed helps to ensure the verticality of the pile foundation.
[0047] S5: Since the extension direction and inclination angle of the corresponding lower pile foundation 1 are recorded on the floating airbag 8, the new pile foundation is driven into the new position according to the extension direction and inclination angle of the corresponding lower pile foundation 1 on the floating marking mechanism 6, and the collision between the new pile foundation and the old pile foundation is avoided, and then the installation of the new pile foundation is completed step by step and in an orderly manner.
[0048] S6: Complete the construction of the new wharf based on the new pile foundation.
[0049] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf, characterized in that: The following steps are involved: S1: demolish the original pier and leave the pile foundation exposed above the sea; S2: Mark each pile foundation, measure and record the angle and position of each pile foundation, and then cut off the pile foundation to leave the lower pile foundation (1); S3: a floating marking mechanism (6) is arranged on the top of the lower pile foundation (1) according to the marking, and the floating marking mechanism (6) records the extension direction and the inclination angle of the corresponding lower pile foundation (1); S4: cleaning silt from the seabed by means of a desilting structure; S5: According to the extension direction and inclination angle of the corresponding lower pile foundation (1) on the floating marking mechanism (6), the new pile foundation is driven into the new position, and collision between the new pile foundation and the old pile foundation is avoided, and then the installation of the new pile foundation is completed step by step and in an orderly manner; S6: Complete the construction of the new wharf based on the new pile foundation.
2. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 1 is characterized by: In step S2, after the pile foundation is cut off, at least three through holes (2) are opened on the top of the lower pile foundation (1), the number of the connecting ropes (3) is the same as the number of the through holes (2), the connecting ropes (3) pass through the through holes (2), and then the connecting ropes (3) and the lower pile foundation (1) are connected.
3. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 2 is characterized by: In step S2, before the connecting rope (3) passes through the through hole (2), a knot is first tied at a position near the bottom of the connecting rope (3) to form a first knot (4), the connecting rope (3) is passed from the top of the lower pile foundation (1) and passed through the through hole (2), and then the connecting rope (3) located outside the lower pile foundation (1) is knotted to form a second knot (5), and the top of the connecting rope (3) is connected to the bottom of the floating marking mechanism (6).
4. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 3 is characterized by: In step S3, each connecting rope (3) is connected to the bottom of the floating marking mechanism (6) through an adjusting component (9), wherein the adjusting component (9) comprises a mounting frame (10) arranged at the bottom of the floating marking mechanism (6), a winding drum (11) rotatably arranged in the mounting frame (10), and a winding spring (12) arranged between the mounting frame (10) and the winding drum (11), and the top of the connecting rope (3) is wound on the winding drum (11).
5. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 3 is characterized by: In step S3, when the connecting rope (3) is knotted, the distance between the first knot (4) and the second knot (5) is made greater than the wall thickness of the lower pile foundation (1).
6. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 1 is characterized by: In step S2, when cutting the pile foundation, the pile foundation is cut to at least two meters below the seabed.
7. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 4 is characterized by: In step S3, the floating marking mechanism (6) comprises a counterweight plate (7) and a floating airbag (8) arranged on the top of the counterweight plate (7), the counterweight plate (7) and the floating airbag (8) are both elliptical in shape, and a plurality of the adjustment components (9) are circumferentially arranged at the bottom of the counterweight plate (7).
8. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 7 is characterized by: In step S3, a plurality of water flow channels (14) are arranged on the periphery of the floating airbag (8), and a collecting channel (15) communicating with the plurality of water flow channels (14) is arranged in the middle of the floating airbag (8).
9. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 7 is characterized by: In step S3, two counterweight blocks (13) symmetrical to each other are arranged circumferentially on the counterweight plate (7).
10. The high-precision positioning construction method for the in-situ construction of a new pile foundation of an old high-pile wharf according to claim 2 is characterized by: In step S2, at least three through holes (2) are arranged along the circumference of the lower pile foundation (1).