Coal mine underground horizontal directional drilling drainage and mining system and method

Through the underground horizontal directional drilling drainage system in coal mines, the problems of high investment, large engineering volume and high technical difficulty in the existing coalbed methane well drainage methods have been solved, and continuous underground drainage has been realized, which has the characteristics of low energy consumption and easy maintenance. Simplifying the process and reducing dependence on climate and terrain.

CN118774690APending Publication Date: 2024-10-15XIAN RES INST OF CHINA COAL TECH & ENG GRP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411140824.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

Existing coalbed methane well drainage methods have problems such as high investment cost, large engineering volume, large impact on climate and topography, high technical difficulty, and high energy consumption.

Method used

The coal mine underground horizontal directional drilling drainage system is adopted, including the surface horizontal well section, the underground horizontal directional drilling section and the underground drainage device. The underground connection is realized through the three-opening shaft structure and the three-opening hole structure, using mechanical valves and intelligent The control valve controls the mixture of coal, water and gas to enter the slag discharge box, and achieves accurate measurement and extraction of gas through the filter screen and flow meter.

Benefits of technology

It realizes continuous underground coal mine drainage with a simple structure, simple process flow and low energy consumption. It has a wide range of drainage capabilities and the ability to control drainage pressure. It is easy to maintain and effectively solves the problems of ground facility construction and natural disasters on drainage. Influence.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774690A_ABST
    Figure CN118774690A_ABST
Patent Text Reader

Abstract

The invention discloses a coal mine underground horizontal directional drilling drainage and mining system and method. The system comprises a ground horizontal well section, an underground horizontal directional drilling section and an underground drainage and mining device. The ground horizontal well section is of a third-opening well body structure, a surface casing is put in after the first opening is below a bedrock surface, an intermediate casing is put in after the second opening is below a second opening landing point, a production casing is put in after the third opening is below a designed well depth, and cement paste is used for well cementation; the underground horizontal directional drilling section is of a three-opening body structure, casing pipes are arranged in a first opening and a second opening, grouting and pipe fixing are conducted, and a screen pipe is arranged in a third opening; the ground horizontal well section is butted and communicated with the underground horizontal directional drilling section through the connecting cave; the underground drainage device comprises an orifice buffering five-way valve, a slag discharging box, a water discharging box, a flow meter and an extraction pipeline which are connected in sequence, and is provided with a mechanical valve and an intelligent control valve. The device is simple in structure, simple in technological process, energy-saving, low in consumption and easy to maintain, has the large-range liquid drainage capacity, the capacity of controlling liquid drainage and system pressure and effective deslagging measures, and can achieve continuous drainage and mining.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of coalbed methane extraction, and in particular relates to a horizontal directional drilling and extraction system and a construction method for an underground coal mine. Background Art

[0002] The main technological processes for coalbed methane exploration and development are drilling, fracturing and drainage, and drainage is an important part of coalbed methane development. At present, the main method of coalbed methane well drainage in my country is to construct horizontal wells, and install drainage and gas production equipment in the ground horizontal wells, mainly including rod pumps, electric submersible pumps, screw pumps, hydraulic jet pumps, etc. This method has many disadvantages, such as high investment cost, the need to build ground gathering and transportation systems, processing plants and other facilities, the construction and maintenance of these facilities require a large amount of capital investment; large engineering volume, need to build a large amount of infrastructure, such as well sites, gas gathering stations, pipelines, etc., the engineering volume is large, and requires a lot of manpower and material resources; affected by climate and terrain, ground drainage is greatly affected by climate and terrain, such as heavy rain, earthquakes and other natural disasters may cause damage to drainage facilities, affecting the drainage effect; drainage technology is difficult, drainage equipment is complex, and drainage equipment is mostly electrically driven, the energy consumption is large during the entire drainage cycle, and the drainage process requirements are high. Summary of the invention

[0003] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a horizontal directional drilling and drainage system and method for underground coal mines, so as to overcome the shortcomings of existing ground horizontal well drainage, such as large ground construction investment, large engineering workload, great influence of climate and terrain, and greater difficulty in drainage technology.

[0004] In order to solve the above technical problems, the present invention adopts the following technical solutions to achieve the above problems:

[0005] A coal mine underground horizontal directional drilling and drainage system, comprising a ground horizontal well section, an underground horizontal directional drilling section and an underground drainage device;

[0006] The ground horizontal well section is a three-opening wellbore structure, the first opening wellbore is below the bedrock surface and a surface casing is arranged therein and cement slurry is used for cementing, the second opening wellbore is to the landing point and the hole is guided and expanded to the second opening landing point and a technical casing is arranged therein and cement slurry is used for cementing, and the third opening wellbore is a horizontal section and is opened to the designed well depth and a production casing is arranged therein and cement slurry is used for cementing;

[0007] The underground horizontal directional drilling section is a three-opening body structure, wherein a casing I is arranged in the first opening body and the casing is fixed by grouting, a casing II is arranged in the second opening body and the casing is fixed by grouting, and a screen pipe is arranged in the third opening body; the end of the three-opening body of the ground horizontal well section is connected to the front end of the three-opening body of the underground horizontal directional drilling section through a connecting cave;

[0008] The downhole drainage device includes an orifice buffer five-way, a slag box, a water discharge box, a flow meter, a mechanical valve, an intelligent control valve, and a drainage pipeline; the front end of the orifice buffer five-way is connected to the end of a casing I in an opening body through a flange and a mechanical valve is installed between the two, the lower end of the orifice buffer five-way is installed with a mechanical valve, the upper end of the orifice buffer five-way is installed with a mechanical valve and a pressure measuring port I, and the rear end of the orifice buffer five-way is installed with two-way mechanical valves and an intelligent control valve; the front end of the slag box is connected to the rear end of the orifice buffer five-way, and the rear end of the slag box is installed with a filter and an intelligent control valve; the front end of the water discharge box is connected to the rear end of the slag box; the upper end of the water discharge tank is connected to the flow meter, and the flow meter is connected to the drainage pipeline.

[0009] The present invention also includes the following technical features:

[0010] Specifically, the first wellbore is drilled to 20m below the bedrock surface using a Φ444.5mm drill bit, and a Φ339.7mm surface casing is lowered; the second wellbore is first drilled to the landing point using a Φ215.9mm drill bit, and then the hole is expanded to the second landing point using a Φ311.15mm guide reaming drill bit, and a Φ244.5mm technical casing is lowered; the horizontal section of the third wellbore is drilled to the designed well depth using a Φ215.9mm drill bit, and a Φ139.7mm production casing is lowered, and the cement slurry returns to a vertical depth of not less than 200m above the landing point.

[0011] Specifically, the first opening body has a diameter of 330 mm, into which a 273 mm casing I is inserted; the second opening body has a diameter of 250 mm, into which a 178 mm casing II is inserted; the third opening body has a diameter of 153 mm, into which a 114 mm screen pipe protection hole is inserted.

[0012] Specifically, a 1# mechanical valve is installed between the orifice buffer five-way and a casing I in an opening body to control the total flow of the production fluid; a 2# mechanical valve 18 is installed at the lower end of the orifice buffer five-way to prevent blocking; a 3# mechanical valve and a pressure measuring port are installed at the upper end of the orifice buffer five-way to monitor its pressure changes in real time; the two-way mechanical valves and intelligent control valves installed at the rear end of the orifice buffer five-way are the 4# mechanical valve and the 1# intelligent control valve on the upper route and the 5# mechanical valve and the 2# intelligent control valve on the lower route, respectively, and the two routes play a redundant role.

[0013] Specifically, a slag discharge port is provided at the lower end of the slag discharge box, and a pressure measuring port II is provided on the side; a 3# intelligent control valve is provided at the rear end of the slag discharge box.

[0014] Specifically, a drain outlet is provided at the lower end of the water discharge tank.

[0015] Specifically, the flow meter is provided with a 6# mechanical valve and a 7# mechanical valve at the front and rear ends respectively, and a 8# mechanical valve 36 is provided on the pipeline connected in parallel with the 6# mechanical valve and the 7# mechanical valve.

[0016] The method for constructing a horizontal directional drilling and drainage system in an underground coal mine is characterized by comprising the following steps:

[0017] Step 1: construct the ground horizontal well section: the ground horizontal well adopts a three-opening well body structure;

[0018] Step 2: construct the connection cave: open the cutter bar of the forging and milling tool, and rotate it under the drive of the drill bit to cut the thickness of the casing wall. After the casing is forged and milled, use the mechanical cavitation tool to complete the cave that meets the actual needs;

[0019] Step 3: construct the underground horizontal directional drilling section, using a three-hole deep body structure;

[0020] Step 4: Downhole horizontal directional drilling docking: The ground horizontal well sends the positioning instrument to the connection cave position through the drilling tool; the downhole horizontal directional drilling drill bit is connected to the strong magnetic short section and the drilling measurement instrument to carry out the connection directional drilling; the positioning instrument spatially locates the direction of the current measuring point through the received strong magnetic intensity value, and reversely deduces the direction of the drill bit; adjust the tool face and guide the drill bit to the center of the cave; when approaching the measuring point, the center distance with the measuring point is judged according to the anti-collision principle, and the trajectory trend is analyzed from the three-dimensional map to achieve docking;

[0021] Step 5, equipment installation: connect the orifice buffer five-way, slag discharge box, water discharge tank, flow meter and extraction pipeline in sequence, and install the mechanical valve and intelligent control valve at the same time;

[0022] Step six, water drainage and gas production stage: In the orifice buffer five-way, the three-phase mixture of coal, water and gas is allowed to enter the slag box through the intelligent control valve and the mechanical valve. After the slag box discharges the coal slag sediment, the two-phase mixture of water and gas is allowed to enter the water discharge tank through the intelligent control valve and the filter. After the water discharge tank discharges the water, the flow meter is used to accurately measure the gas, and then the gas is extracted through the extraction pipeline.

[0023] Specifically, the step one comprises: the first opening well body is drilled to 20 m below the bedrock surface with a hole diameter of Φ444.5 mm using a Φ444.5 mm drill bit, a Φ339.7 mm surface casing is lowered, cementing is performed and solidification is performed, and cement slurry is returned to the ground; the second opening well body is first drilled to the landing point using a Φ215.9 mm drill bit, and then the hole diameter is expanded to Φ311.15 mm to the second opening landing point using a Φ311.15 mm guide reaming drill bit, a Φ244.5 mm technical casing is lowered, and cementing is performed and solidification is performed, and cement slurry is returned to the ground; the third opening well body horizontal section is drilled to a hole diameter of Φ215.9 mm to the designed well depth using a Φ215.9 mm drill bit, a Φ139.7 mm production casing is lowered, and cementing is performed, and cement slurry is returned to a vertical depth of not less than 200 m above the landing point.

[0024] Specifically, the step three includes: first constructing a pilot hole with a diameter of Φ120mm in the first opening body, and then using reaming drill bits of Φ153mm, Φ250mm, and Φ330mm to reame the hole to a borehole diameter of Φ330mm, and then inserting a Φ273mm casing and then grouting to fix the pipe; first constructing a pilot hole with a diameter of Φ120mm in the second opening body, and then using reaming drill bits of Φ153mm and Φ250mm to reame the hole to a borehole diameter of Φ250mm, and then inserting a Φ178mm casing and then grouting to fix the pipe; and constructing a pilot hole with a diameter of Φ120mm in the third opening body, and then using an reaming drill bit of Φ153mm to reame the hole to a borehole diameter of Φ153mm, and then inserting a Φ114mm screen pipe to protect the hole.

[0025] Compared with the prior art, the present invention has the following technical effects:

[0026] The invention has a simple structure, a simple process flow, energy saving and low consumption, is easy to maintain, has a wide range of drainage capabilities and the ability to control drainage and system pressure, and effective slag removal measures. Continuous underground drainage can be achieved by connecting underground drainage devices through horizontal directional drilling in coal mines. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 This is a schematic diagram of the horizontal directional drilling and mining system in an underground coal mine.

[0028] Figure 2 Schematic diagram of the horizontal well section on the ground.

[0029] Figure 3 Schematic diagram of the horizontal directional drilling section underground.

[0030] Figure 4 This is a schematic diagram of the orifice buffer five-way valve and the mechanical valve and intelligent control valve structure.

[0031] Figure 5 This is a schematic diagram of the slag discharge box and intelligent control valve structure.

[0032] Figure 6 This is a schematic diagram of the layout of the water tank, flow meter, and extraction pipeline.

[0033] The meaning of each number in the figure is:

[0034] 1. Wellbore 1; 2. Surface casing; 3. Wellbore 2; 4. Technical casing; 5. Cement slurry; 6. Wellbore 3; 7. Production casing; 8. Connecting cave; 9. Wellbore 1; 10. Casing I; 11. Wellbore 2; 12. Casing II; 13. Wellbore 3; 14. Screen; 15. Flange; 16. Orifice buffer five-way; 17. 1# mechanical valve; 18. 2# mechanical valve; 19. 3# mechanical valve; 20. Pressure measuring port I; 21. 4# mechanical valve Mechanical valve; 22.1# intelligent control valve; 23.5# mechanical valve; 24.2# intelligent control valve; 25. Slag discharge box; 26. Slag discharge port; 27. Filter screen; 28.3# intelligent control valve; 29. ​​Pressure measuring port II; 30. Drain tank; 31. Drain port; 32. Flow meter; 33. Extraction pipeline; 34.6# mechanical valve; 35.7# mechanical valve; 36.8# mechanical valve; 37. Ground horizontal well section; 38. Downhole horizontal directional drilling section; 39. Downhole extraction device. DETAILED DESCRIPTION

[0035] Specific embodiments of the present invention are given below. It should be noted that the present invention is not limited to the following specific embodiments, and all equivalent changes made on the basis of the technical solution of this application fall within the protection scope of the present invention.

[0036] Embodiment 1:

[0037] like Figures 1 to 6 As shown, this embodiment provides a coal mine underground horizontal directional drilling and drainage system, including a ground horizontal well section 37, an underground horizontal directional drilling section 38 and an underground drainage device 39.

[0038] The ground horizontal well section 37 is a three-opening wellbore structure, the first opening wellbore 1 is below the bedrock surface and a surface casing 2 is arranged therein and cement slurry 5 is used for cementing, the second opening wellbore 3 is to the landing point and guided to the second opening landing point and a technical casing 4 is arranged therein and cement slurry 5 is used for cementing, and the third opening wellbore 6 is a horizontal section and is opened to the designed well depth and a production casing 7 is arranged therein and cement slurry 5 is used for cementing.

[0039] The underground horizontal directional drilling section 38 is a three-opening body structure, wherein the first opening body 9 is provided with a casing I10 and grouting is used to fix the pipe, the second opening body 11 is provided with a casing II12 and grouting is used to fix the pipe, and the third opening body 13 is provided with a screen pipe 14; the end of the three-opening well body 6 of the ground horizontal well section 37 is connected to the front end of the three-opening well body 13 of the underground horizontal directional drilling section 38 through the connecting cave 8. The connecting cave plays a role in connecting the ground horizontal well with the underground horizontal directional drilling hole, and at the same time, it provides a docking space for the two, thereby improving the docking accuracy.

[0040] The downhole drainage device 39 includes an orifice buffer five-way 16, a slag box 25, a water discharge box 30, a flow meter 32, a mechanical valve, an intelligent control valve, and a drainage pipeline 33; the front end of the orifice buffer five-way 16 is connected to the end of an inner casing I10 of an opening body 9 through a flange 15 and a mechanical valve is installed between the two, the lower end of the orifice buffer five-way 16 is installed with a mechanical valve, the upper end of the orifice buffer five-way 16 is installed with a mechanical valve and a pressure measuring port I20, and the rear end of the orifice buffer five-way 16 is installed with two-way mechanical valves and an intelligent control valve; the front end of the slag box 25 is connected to the rear end of the orifice buffer five-way 16, and the rear end of the slag box 25 is installed with a filter screen 27 and an intelligent control valve; the front end of the water discharge box 30 is connected to the rear end of the slag box 25; the upper end of the water discharge tank 30 is connected to the flow meter 32, and the flow meter 32 is connected to the drainage pipeline 33.

[0041] The first wellbore 1 is drilled to 20m below the bedrock surface using a Φ444.5mm drill bit, and a Φ339.7mm surface casing 2 is lowered; the second wellbore 3 is first drilled to the landing point using a Φ215.9mm drill bit, and the landing point position is determined based on the actual drilling situation of the pilot hole, and then the hole is expanded to the second landing point using a Φ311.15mm pilot reaming drill bit, and a Φ244.5mm technical casing 4 is lowered; the horizontal section of the third wellbore 6 is drilled to the designed well depth using a Φ215.9mm drill bit, and a Φ139.7mm production casing 7 is lowered, and the cement slurry 5 is returned to a vertical depth of not less than 200m above the landing point.

[0042] The first opening body 9 has a hole diameter of Ф330mm, and a Ф273mm casing I10 is inserted into it; the second opening body 11 has a hole diameter of Ф250mm, and a Ф178mm casing II12 is inserted into it; the third opening body 13 has a hole diameter of Ф153mm, and a Ф114mm screen pipe 14 is inserted into it to protect the hole.

[0043] A 1# mechanical valve 17 is installed between the orifice buffer five-way 16 and the inner casing I10 of the opening body 9 to control the total flow of the produced fluid; a 1# mechanical valve 18 is installed at the lower end of the orifice buffer five-way 16 to prevent it from being blocked by coal slime; a 1# mechanical valve 19 and a pressure measuring port are installed at the upper end of the orifice buffer five-way 16 to monitor its pressure changes in real time; the two-way mechanical valves and intelligent control valves installed at the rear end of the orifice buffer five-way 16 are the upper 4# mechanical valve 21 and the 1# intelligent control valve 22 and the lower 5# mechanical valve The mechanical valve 23 and the 2# intelligent control valve 24 play a redundant role in both routes to prevent coal slime from clogging the pipeline; under normal use, only the 4# mechanical valve 21 on the upper route and the 1# intelligent control valve 22 are used, the 4# mechanical valve 21 is fully open and the 1# intelligent control valve 22 automatically adjusts the valve opening according to the pressure requirements. When the 1# intelligent control valve 22 on the upper route fails, the 4# mechanical valve 21 on the upper route is closed and the 5# mechanical valve 23 and the 2# intelligent control valve 24 on the lower route are opened, and the 1# intelligent control valve 22 on the upper route is replaced in turn.

[0044] A slag discharge port 26 is provided at the lower end of the slag discharge box 25, and a pressure measuring port II29 is provided on the side; the rear end of the slag discharge box 25 is a 3# intelligent control valve 28; the coal slime is discharged through the slag discharge port 26 after being precipitated in the slag discharge box 25, and a filter screen 27 and a 3# intelligent control valve 28 are installed at the rear end of the slag discharge box 25. The filter screen 27 can further filter the coal slime so that only a gas-water mixture exists after passing through the 3# intelligent control valve 28. The 3# intelligent control valve 28 automatically adjusts the valve opening according to the pressure requirements; the pressure measuring port II29 can measure the pressure in the slag discharge box 25 through a pressure gauge to determine whether it is blocked.

[0045] A drain port 31 is provided at the lower end of the drain tank 30 , and the front end of the drain tank 30 is connected to the rear end of the slag discharge box 25 , and water is discharged through the drain port 31 of the drain tank 30 .

[0046] The front and rear ends of the flow meter 32 are respectively provided with a 6# mechanical valve 34 and a 7# mechanical valve 35, and a 8# mechanical valve 36 is provided on the pipeline connected in parallel with the 6# mechanical valve 34 and the 7# mechanical valve 35. Under normal use, only the lower 6# mechanical valve 34 and the 7# mechanical valve 35 are opened. When the lower flow meter 32 fails, the lower 6# mechanical valve 34 and the 7# mechanical valve 35 are closed, and the upper 8# mechanical valve 36 is opened.

[0047] The principle of the underground horizontal directional drilling and drainage system in coal mines is to first construct a horizontal well on the ground, and then connect the caves to achieve precise docking between the underground horizontal directional drilling and the ground horizontal well. When the underground horizontal directional drilling and the ground horizontal well are docked, the mechanical valve and intelligent control valve of the underground drainage device are controlled to complete the coalbed methane drainage in the coal mine. The coalbed methane production process during the surface coalbed methane drainage includes the single-phase water flow stage, the gas-water two-phase flow stage and the single-phase gas flow stage, while the coalbed methane production process during the underground coalbed methane drainage includes the water-slag two-phase flow stage, the gas-water-slag three-phase flow stage and the gas-water two-phase flow stage. Therefore, there are differences in drainage equipment and drainage process between the surface coalbed methane drainage and the underground coalbed methane drainage.

[0048] Water-slag two-phase flow stage: mainly refers to the stage from the start of coal seam well drainage to the drop of wellbore liquid column pressure to reservoir pressure. Since the wellbore liquid column pressure is much higher than the original reservoir pressure, the pressure drop has no effect on the coal seam and will not cause stress sensitivity, speed sensitivity, etc. In view of the production characteristics of this stage, the water discharge device plays a major role by observing the pressure gauge, and at the same time controls the mechanical valve and intelligent control valve of the underground drainage device to achieve rapid water discharge from the water discharge device and slow slag discharge from the slag discharge device. Therefore, the fastest pressure drop rate of 160L / d is adopted to increase the slag discharge cycle and shorten the water discharge cycle.

[0049] Gas-water-slag three-phase flow stage: mainly refers to the stage of controlling the wellbore liquid column pressure from the original reservoir pressure to the desorption pressure. Since the coal reservoir pressure drops below the original reservoir pressure at this time, pressure conduction is likely to cause coal rock stress sensitivity, coal powder migration, fracturing crack closure, and large-scale migration of coal slag. The slag discharge device plays a major role, and at the same time controls the mechanical valve and intelligent control valve of the underground drainage device to achieve rapid slag discharge from the slag discharge device and slow water discharge from the water discharge device. Therefore, the pressure drop rate in this stage is relatively slow, controlled at 90L / d.

[0050] Gas-water two-phase flow stage: mainly refers to the stage of continuous gas production after the wellbore liquid column pressure is lower than the coal rock desorption pressure. In this stage, the fluid flow state changes from three-phase water flow to two-phase flow state. Under the pressure difference of the coal reservoir, gas and water are produced from the coal seam, promoting further desorption of coal rock. Since the reservoir pressure has a great influence on reservoir stress damage, velocity sensitivity, coal powder migration, and Jamin effect, the water discharge device plays a major role, and at the same time controls the mechanical valve and intelligent control valve of the underground drainage device to achieve slow slag and water discharge from the slag discharge device and the water discharge device. The pressure drop rate in this stage is mainly slow, controlled at 10L / d, to ensure stable and continuous production of gas and water from the coal seam and obtain the maximum gas production.

[0051] Embodiment 2:

[0052] This embodiment provides a construction method of a horizontal directional drilling and drainage system in a coal mine in Example 1, comprising the following steps:

[0053] Step 1, construct the ground horizontal well section: the ground horizontal well adopts a three-wellbore structure; specifically, the first wellbore is drilled with a Φ444.5mm drill bit to 20m below the bedrock surface with a hole diameter of Φ444.5mm, and a Φ339.7mm surface casing is lowered, cementing is performed and solidification is allowed, and the cement slurry is returned to the ground; the second wellbore is first drilled with a Φ215.9mm drill bit to the landing point, and the landing point position is determined according to the actual drilling situation of the pilot hole, and then the hole diameter is expanded to Φ311.15mm to the second landing point with a Φ311.15mm pilot reaming drill bit, and the Φ244.5mm technical casing is lowered, and then cementing is performed and solidification is allowed, and the cement slurry is returned to the ground; the horizontal section of the third wellbore is drilled with a Φ215.9mm drill bit to a hole diameter of Φ215.9mm to the designed well depth, and a Φ139.7mm production casing is lowered and cementing is performed, and the cement slurry is returned to a vertical depth of not less than 200m above the landing point.

[0054] Step 2: Construction of connecting caves: Use drilling tools to send specially designed mechanical devices into the forging and milling well section, and then use hydraulic control to open the cutter bar of the forging and milling tool and rotate it driven by the drilling tool to cut the casing wall thickness. After forging and milling the casing, use mechanical cavitation tools to complete the cave that meets actual needs.

[0055] Step three, construct the underground horizontal directional drilling section, adopting a three-opening deep body structure; specifically including: first construct a pilot hole with a diameter of Φ120mm in the first opening body, and then use reaming drill bits Φ153mm, Φ250mm, and Φ330mm to expand the hole to a borehole diameter of Φ330mm in sequence, and then lower a Φ273mm casing and then grouting to fix the pipe; first construct a pilot hole with a diameter of Φ120mm in the second opening body, and then use reaming drill bits Φ153mm and Φ250mm to expand the hole to a borehole diameter of Φ250mm in sequence, and then lower a Φ178mm casing and then grouting to fix the pipe; third opening body constructs a pilot hole with a diameter of Φ120mm, and then uses an reaming drill bit Φ153mm to expand the hole to a borehole diameter of Φ153mm, and then lowers a Φ114mm screen pipe to protect the hole.

[0056] Step 4: Downhole horizontal directional drilling docking: The ground horizontal well sends the positioning instrument to the connection cave position through the drilling tool; the downhole horizontal directional drilling drill bit is connected to the strong magnetic short joint and the drilling measurement instrument to carry out connected directional drilling; the positioning instrument spatially locates the direction of the current measuring point through the received strong magnetic intensity value, and infers the direction of the drill bit; adjust the tool face to guide the drill bit to the center of the cave; when approaching the measuring point, judge the center distance of the measuring point according to the anti-collision principle, analyze the trajectory trend from the three-dimensional graph, and achieve docking.

[0057] Step 5, equipment installation: connect the orifice buffer five-way, slag discharge box, water discharge tank, flow meter and extraction pipeline in sequence, and install accessories such as mechanical valves and intelligent control valves.

[0058] Step six, water drainage and gas production stage: In the orifice buffer five-way, the three-phase mixture of coal, water and gas is allowed to enter the slag box through the intelligent control valve and the mechanical valve. After the slag box discharges the coal slag sediment, the two-phase mixture of water and gas is allowed to enter the water discharge tank through the intelligent control valve and the filter. After the water discharge tank discharges the water, the flow meter is used to accurately measure the gas, and then the gas is extracted through the extraction pipeline.

[0059] The preferred embodiments of the present invention are described in detail above in conjunction with the accompanying drawings. However, the present invention is not limited to the specific details in the above embodiments. Within the technical concept of the present invention, a variety of simple modifications can be made to the technical solution of the present invention, and these simple modifications all belong to the protection scope of the present invention.

[0060] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction. In order to avoid unnecessary repetition, the present invention will not further describe various possible combinations.

[0061] In addition, various embodiments of the present invention may be arbitrarily combined, and as long as they do not violate the concept of the present invention, they should also be regarded as the contents disclosed by the present invention.

Claims

1. A horizontal directional drilling and drainage system for underground coal mines, characterized in that: It includes a ground horizontal well section (37), an underground horizontal directional drilling section (38) and an underground drainage device (39); The surface horizontal well section (37) is a three-wellbore structure, wherein the first wellbore (1) is opened to below the bedrock surface and a surface casing (2) is arranged therein and cement slurry (5) is used for cementing, the second wellbore (3) is opened to the landing point and is guided to expand the hole to the second landing point and a technical casing (4) is arranged therein and cement slurry (5) is used for cementing, and the third wellbore (6) is a horizontal section and is opened to the designed well depth and a production casing (7) is arranged therein and cement slurry (5) is used for cementing; The underground horizontal directional drilling section (38) is a three-opening body structure, wherein a casing I (10) is arranged in the first opening body (9) and the casing is fixed by grouting, a casing II (12) is arranged in the second opening body (11) and the casing is fixed by grouting, and a screen tube (14) is arranged in the third opening body (13); the end of the three-opening body (6) of the ground horizontal well section (37) is connected to the front end of the three-opening body (13) of the underground horizontal directional drilling section (38) through a connecting cave (8); The downhole drainage device (39) comprises an orifice buffer five-way (16), a slag discharge box (25), a water discharge box (30), a flow meter (32), a mechanical valve, an intelligent control valve, and a drainage pipeline (33); the front end of the orifice buffer five-way (16) is connected to the end of the inner casing I (10) of an opening body (9) through a flange (15) and a mechanical valve is installed between the two, the lower end of the orifice buffer five-way (16) is equipped with a mechanical valve, and the upper end of the orifice buffer five-way (16) is equipped with a mechanical valve. A mechanical valve and a pressure measuring port I (20) are installed, and a two-way mechanical valve and an intelligent control valve are installed at the rear end of the orifice buffer five-way (16); the front end of the slag discharge box (25) is connected to the rear end of the orifice buffer five-way (16), and a filter screen (27) and an intelligent control valve are installed at the rear end of the slag discharge box (25); the front end of the water discharge box (30) is connected to the rear end of the slag discharge box (25); the upper end of the water discharge box (30) is connected to a flow meter (32), and the flow meter (32) is connected to a pumping pipeline (33).

2. The underground horizontal directional drilling and drainage system of a coal mine according to claim 1, characterized in that: The first wellbore (1) is drilled to 20 m below the bedrock surface using a Φ444.5 mm drill bit, and a Φ339.7 mm surface casing (2) is lowered; the second wellbore (3) is firstly drilled to a landing point using a Φ215.9 mm drill bit, and then the hole is expanded to the second landing point using a Φ311.15 mm guide expansion drill bit, and a Φ244.5 mm technical casing (4) is lowered; the horizontal section of the third wellbore (6) is drilled to a designed well depth using a Φ215.9 mm drill bit, and a Φ139.7 mm production casing (7) is lowered, and the cement slurry (5) is returned to a vertical depth of not less than 200 m above the landing point.

3. The underground horizontal directional drilling and drainage system of a coal mine according to claim 1, characterized in that: The first opening body (9) has a hole diameter of 330 mm, into which a 273 mm casing I (10) is inserted; the second opening body (11) has a hole diameter of 250 mm, into which a 178 mm casing II (12) is inserted; the third opening body (13) has a hole diameter of 153 mm, into which a 114 mm screen pipe (14) is inserted to protect the hole.

4. The underground horizontal directional drilling and drainage system of a coal mine according to claim 1, characterized in that: A 1# mechanical valve (17) is installed between the orifice buffer five-way (16) and the inner casing I (10) of the opening body (9) to control the total flow of the production and drainage fluid; a 1# mechanical valve (18) is installed at the lower end of the orifice buffer five-way (16) to prevent blockage; a 1# mechanical valve (19) and a pressure measuring port are installed at the upper end of the orifice buffer five-way (16) to monitor the pressure change in real time; two-way mechanical valves and intelligent control valves installed at the rear end of the orifice buffer five-way (16) are respectively an upper-way 4# mechanical valve (21) and a 1# intelligent control valve (22) and a lower-way 5# mechanical valve (23) and a 2# intelligent control valve (24), and the two-way play a redundant role.

5. The underground horizontal directional drilling and drainage system of a coal mine according to claim 1, characterized in that: The slag discharge box (25) is provided with a slag discharge port (26) at the lower end and a pressure measuring port II (29) at the side; and a 3# intelligent control valve (28) is provided at the rear end of the slag discharge box (25).

6. The underground coal mine horizontal directional drilling and drainage system according to claim 1, characterized in that: The lower end of the water discharge tank (30) is provided with a water discharge port (31).

7. The underground horizontal directional drilling and drainage system of a coal mine according to claim 1, characterized in that: The flow meter (32) is provided with a 6# mechanical valve (34) and a 7# mechanical valve (35) at the front and rear ends respectively, and a 8# mechanical valve (36) is provided on a pipeline connected in parallel with the 6# mechanical valve (34) and the 7# mechanical valve (35).

8. The method for constructing a horizontal directional drilling and drainage system for an underground coal mine according to claim 1, characterized in that: The following steps are involved: Step 1: construct the ground horizontal well section: the ground horizontal well adopts a three-opening well body structure; Step 2: construct the connection cave: open the cutter bar of the forging and milling tool, and rotate it under the drive of the drill bit to cut the thickness of the casing wall. After the casing is forged and milled, use the mechanical cavitation tool to complete the cave that meets the actual needs; Step 3: construct the underground horizontal directional drilling section, using a three-hole deep body structure; Step 4: Downhole horizontal directional drilling connection: The ground horizontal well sends the positioning instrument to the connection cave position through the drilling tool; the downhole horizontal directional drilling drill bit is connected with the strong magnetic short section and the drilling measurement instrument to carry out the connection directional drilling; The positioning instrument spatially locates the current measuring point through the received strong magnetic intensity value, and infers the position of the drill bit; Adjust the tool face and guide the drill bit to the center of the cave; when approaching the measuring point, determine the center distance from the measuring point based on the anti-collision principle, analyze the trajectory trend from the three-dimensional graph, and achieve docking; Step 5, equipment installation: connect the orifice buffer five-way, slag discharge box, water discharge tank, flow meter and extraction pipeline in sequence, and install the mechanical valve and intelligent control valve at the same time; Step six, water drainage and gas production stage: In the orifice buffer five-way, the three-phase mixture of coal, water and gas is allowed to enter the slag box through the intelligent control valve and the mechanical valve. After the slag box discharges the coal slag sediment, the two-phase mixture of water and gas is allowed to enter the water discharge tank through the intelligent control valve and the filter. After the water discharge tank discharges the water, the flow meter is used to accurately measure the gas, and then the gas is extracted through the extraction pipeline.

9. The method for constructing a horizontal directional drilling and drainage system in an underground coal mine according to claim 8, characterized in that: The step one comprises: the first opening well body is drilled to 20 m below the bedrock surface with a hole diameter of Φ444.5 mm using a Φ444.5 mm drill bit, a Φ339.7 mm surface casing is lowered, cementing is performed and the cement slurry is returned to the ground; the second opening well body is first drilled to the landing point using a Φ215.9 mm drill bit, and then the hole diameter is expanded to Φ311.15 mm to the second opening landing point using a Φ311.15 mm guide reaming drill bit, a Φ244.5 mm technical casing is lowered, and cementing is performed and the cement slurry is returned to the ground; the third opening well body horizontal section is drilled to a hole diameter of Φ215.9 mm to the designed well depth using a Φ215.9 mm drill bit, a Φ139.7 mm production casing is lowered, and cementing is performed, and the cement slurry is returned to a vertical depth of not less than 200 m above the landing point.

10. The method for constructing a horizontal directional drilling and drainage system for an underground coal mine according to claim 8, characterized in that: The step three comprises: first constructing a pilot hole with a diameter of Φ120mm in the first opening body, and then using reaming drill bits of Φ153mm, Φ250mm, and Φ330mm to reaming the hole to a borehole diameter of Φ330mm in sequence, and then inserting a Φ273mm casing and then grouting to fix the pipe; first constructing a pilot hole with a diameter of Φ120mm in the second opening body, and then using reaming drill bits of Φ153mm and Φ250mm to reaming the hole to a borehole diameter of Φ250mm in sequence, and then inserting a Φ178mm casing and then grouting to fix the pipe; and constructing a pilot hole with a diameter of Φ120mm in the third opening body, and then using a reaming drill bit of Φ153mm to reaming the hole to a borehole diameter of Φ153mm, and then inserting a Φ114mm screen pipe to protect the hole.