Monitoring and preventing method for water inrush of tunnel and roadway
By designing a monitoring and prevention method for tunnels and tunnels, using expansion balls and follower pipes to monitor and control water flow, the problem that existing technology cannot monitor and quickly handle water inrush in real time is solved, and real-time data collection and safety are achieved. Early warning ensures the safety and processing efficiency of tunnels and roadways.
Patent Information
- Application Number
- CN202410941375.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-10-15
AI Technical Summary
Existing monitoring and prevention methods for water inrush in tunnels and tunnels cannot achieve real-time monitoring and rapid processing, resulting in potential safety hazards and the inability to promptly warn and deal with dangerous situations.
A monitoring and prevention method is designed, including external and internal mechanisms. The expansion ball and the follower tube are used to monitor and control the water flow. The expansion ball is placed to inject air into the follower tube to make it expand and move to a specific position. Combined with Auxiliary mechanisms and safety mechanisms perform drainage and data collection, and use sensors and generators for real-time monitoring and control to ensure safety.
It realizes real-time monitoring and control of water flow, water pressure and sediment conditions in tunnels and roadways, can provide timely warnings, ensure safety, and perform preliminary filling stabilization in dangerous situations, provide channels for subsequent filling of cement slurry, and improve processing Efficiency and safety.
Smart Images

Figure CN118774967A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of tunnel protection, and in particular to a method for monitoring and preventing water inrush in tunnels and lanes. Background Art
[0002] For the research on advance prediction of tunnel geological disasters, China has begun to use methods such as advance pilot pits and horizontal drilling for prediction since the 1990s, and use exploration methods to make advanced geological predictions for tunnels. However, the existing devices generally use pipe drainage or direct cement grouting to seal, which cannot perform real-time monitoring as a whole, and cannot handle danger quickly and promptly when it occurs. Summary of the invention
[0003] In order to solve the technical problem that cannot be dealt with quickly and timely, the present invention provides a monitoring and prevention method for water inrush in tunnels and lanes.
[0004] The present invention is implemented by the following technical scheme: a monitoring and prevention method for water inrush in tunnels and laneways, wherein the monitoring and prevention method is implemented by a monitoring device, wherein the monitoring device comprises: an external mechanism, one side of which is connected to an intermediate tube; an internal mechanism, which is fixedly connected to one end of the intermediate tube, one side of the internal mechanism is connected to a follower tube, one end of the follower tube is fixedly connected to an expansion ball; a safety mechanism, which is connected to the internal mechanism and the external mechanism, and the monitoring and prevention device performs data collection and subsequent safety protection work to ensure the implementation of the method.
[0005] The monitoring and prevention method comprises:
[0006] S1: Identify the possible locations of water inrush, perform external forming and crushing, install the corresponding fixed base, then perform drilling, and carry out preliminary drainage in conjunction with the initial pipeline;
[0007] S2: Place an expansion ball, inject air into the follower tube to make it expand to a certain extent, and then use the device to move the expansion ball to a certain position, while carrying one end of the follower tube to the correct position;
[0008] S3: Install one end of the follower tube to the internal mechanism, fix the internal mechanism with a fixing base, and install the auxiliary mechanism;
[0009] S4: Connect the external mechanism on the outside, fix the auxiliary mechanism with anchor cables, use the monitoring device to drain water, remove the previous drainage device, and pour concrete to fix the base and internal mechanism;
[0010] S5: The testing agency drains the water, monitors the water flow and internal pressure, and uploads data in real time for testing;
[0011] S6: Actively monitor internal water pressure, water flow and sediment content, and control water flow rate;
[0012] S6: Clean the device regularly and make adjustments.
[0013] As a further improvement of the above scheme, the external mechanism includes an intermediate box fixedly connected to one end of the intermediate pipe, and auxiliary boxes and extraction boxes are fixedly connected to both sides of the intermediate box respectively. A plurality of drainage pipes are fixedly connected to one side of the intermediate box, and an auxiliary box connected to the safety mechanism is fixedly connected to the bottom of the extraction box. The external mechanism performs operation and discharge to ensure the progress of the work.
[0014] As a further improvement of the above scheme, the internal mechanism includes: a function box, which is connected with a slow flow unit in the middle, and one end of the intermediate pipe is connected to the function box; an expansion box, which is arranged on the upper side of the function box, and one side of the expansion box is fixedly connected with a feeding pipe connected to the auxiliary box; a slow flow box, which is arranged at the bottom of the function box, and a leakage hole connected to the function box is opened on the slow flow box, and one side of the slow flow box is fixedly connected with a conducting pipe connected to the extraction box; a regulating box, which is arranged in the function box, and the top of the regulating box is connected with an auxiliary pipe extending into the function box, and the pressure relief pipe is connected to the safety mechanism; an embedded pipe, one end of which is connected to the function box, and the other end of the embedded pipe is connected to the follower pipe; a pressure relief pipe, one end of which is connected to the embedded pipe, and the other end is connected to the expansion box; a plurality of trigger pipes are provided, one end of the trigger pipe is connected to the expansion box, and the other end is connected to the function box, and the internal mechanism performs water flow control and data collection to meet work needs.
[0015] As a further improvement of the above scheme, the flow-delaying unit includes: a sensor, which is fixedly connected to the function box, one side of the sensor is fixedly connected to a spring, the other end of the spring is fixedly connected to a mounting frame, one side of the mounting frame is fixedly connected to a guide box that is in sliding contact with the function box; a driving frame, which is rotatably connected to the guide box, the outer side of the driving frame is fixedly connected to driving teeth that cooperate with the guide box; a stabilizing frame, which is fixedly connected to the function box, a telescopic rod is fixedly connected inside the stabilizing frame, and the output end of the telescopic rod is connected to a generator; a follower frame, which is fixedly connected to the generator, a Hall element is arranged inside it, and the Hall element is located on the outer side of the driving frame, and one end of the driving frame is fixedly connected to a transmission rod connected to the input end of the generator. The flow-delaying unit performs the work of slowing down the flow, separating sediment and generating electricity, so as to ensure the continuous operation of the work.
[0016] As a further improvement of the above solution, a buffer sleeve matching the middle pipe is fixedly connected to the function box, a generator connected to the function box is fixedly connected to one side of the guide box, and a plurality of inclined plates are fixedly connected in the damping box.
[0017] As a further improvement of the above scheme, a deformation arc is fixedly connected to one side of the functional box, a sensor group 1 is arranged in the deformation arc, batteries are filled between the expansion box and the functional box, a controller is connected to the battery, and a cleaning door is connected to one side of the extraction box.
[0018] As a further improvement of the above scheme, the auxiliary mechanism includes: an expansion ring, which is fixedly connected to the intermediate tube, and the expansion ring cooperates with the feeding tube, the intermediate tube and the drainage pipe; a contact sleeve, which is provided with multiple ones, and the contact sleeve is connected to the expansion ring, and a leakage pipe connected to the expansion ring is fixedly connected to the contact sleeve; a supporting frame, which is snap-fitted with the functional box, and a safety tube is fixedly connected to the supporting frame, one end of the safety tube is connected to the control box, and the other end passes through the auxiliary box to the outside of the auxiliary box, and the safety tube is connected to a leakage pipe connected to the conducting pipe, and the auxiliary mechanism performs necessary auxiliary work.
[0019] As a further improvement of the above solution, a touch screen is connected to one side of the auxiliary box, a high-pressure pipe is connected to the side of the auxiliary box, and a clamping ring is provided on the supporting frame.
[0020] As a further improvement of the above scheme, a plurality of accommodating grooves are arranged on the outer side of the follower tube, an elastic arc is arranged in the accommodating groove, one end of the elastic arc is connected to the interior of the follower tube, a plurality of one-way sheets are connected in the elastic arc, and the follower tube performs the extension and collection work.
[0021] As a further improvement of the above scheme, the expansion ball includes an outermost wear-resistant layer, a barrier layer and an expansion layer are connected to one side of the wear-resistant layer, a plurality of protective layers are connected to the expansion layer, an outer wall of the protective layer is connected to a separation layer located in the expansion layer, a plurality of stabilizing ropes are connected to the separation layer, the other end of the stabilizing rope is connected to a slow-dissolving layer, a dissolving layer is connected to the slow-dissolving layer, and a positioner is connected to the protective layer, so that the expansion ball performs positioning and expansion limitation work.
[0022] Compared with the prior art, the present invention has the following beneficial effects:
[0023] 1. Through the mutual cooperation between multiple devices, drainage of different flow rates can be carried out to relieve pressure in the rock formation. At the same time, the internal water flow, sediment conditions, and internal water pressure can be monitored in real time, and the necessary data can be obtained. Necessary predictions can be made in time, early warnings can be given, and overall safety can be ensured.
[0024] 2. Through the work of the expansion ball and follower tube in conjunction with the expansion box, the rock formation can be initially filled and stabilized in the event of danger to ensure safety. At the same time, a channel can be provided for subsequent filling of cement slurry to facilitate the work. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0026] Figure 2 It is a front cross-sectional schematic diagram of the present invention;
[0027] Figure 3 It is a partial front cross-sectional schematic diagram of the present invention;
[0028] Figure 4 It is a schematic diagram of the main cross-section of the slow flow unit;
[0029] Figure 5 It is a schematic diagram of the main structure of the slow flow unit;
[0030] Figure 6 It is a left side cross-sectional schematic diagram of the present invention;
[0031] Figure 7 It is a schematic cross-sectional view of the main body of the present invention from the left side;
[0032] Figure 8 It is a schematic diagram of the main cross-sectional view of the follower tube;
[0033] Fig. 9 It is a schematic diagram of the main cross-sectional view of the expansion ball;
[0034] Fig.10 Schematic diagram of the structure of the expansion ball.
[0035] Description of main symbols:
[0036] 01. Intermediate box; 02. Touch screen; 03. Auxiliary box; 04. Expansion ring; 05. Contact sleeve; 06. Feeding tube; 07. Battery; 08. Expansion box; 09. Function box; 10. Follow-up tube; 11. Expansion ball; 12. Embedded tube; 13. Support frame; 14. Control box; 15. Conducting tube; 16. Intermediate tube; 17. Drain pipe; 18. Extraction box; 19. Auxiliary box; 20. Safety tube; 21. Drain pipe; 22. Leakage pipe; 23. Slow flow box; 24. Pressure relief pipe; 25. Trigger tube; 26. Auxiliary Auxiliary tube; 27. Drive frame; 28. Detector; 30. Controller; 31. Mounting frame; 32. Spring; 33. Sensor; 34. Guide box; 35. Drive gear; 36. Generator; 37. Follow-up frame; 38. Hall element; 39. Telescopic rod; 40. Stabilizing frame; 42. Elastic arc; 43. One-way plate; 44. Receiving groove; 50. Wear-resistant layer; 51. Barrier layer; 52. Positioner; 53. Protective layer; 54. Expansion layer; 55. Separation layer; 56. Dissolving layer; 57. Stabilizing rope; 58. Slow-dissolving layer. DETAILED DESCRIPTION
[0037] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form a new embodiment.
[0038] Example:
[0039] Please combine Figure 1-10 ,
[0040] A monitoring and prevention method for water inrush in tunnels and laneways, the monitoring and prevention method is implemented by a monitoring device, wherein the monitoring device comprises: an external mechanism, one side of which is connected to an intermediate pipe 16, the external device performs later operations to facilitate overall monitoring, an internal mechanism, which is fixedly connected to one end of the intermediate pipe 16, one side of the internal mechanism is connected to a follower pipe 10, one end of the follower pipe 10 is fixedly connected to an expansion ball 11, the intermediate pipe 16 is conducted, the internal mechanism is embedded in the rock formation to limit it, and at the same time, a certain control is performed on the internal water flow, and a safety mechanism is connected to the internal mechanism and the external mechanism, and the safety mechanism performs certain auxiliary safety work.
[0041] Monitoring and prevention methods include:
[0042] S1: Identify the possible locations of water inrush, perform external forming and crushing, install the corresponding fixed base, and then perform drilling. In addition, carry out preliminary drainage and preliminary positioning in conjunction with the initial pipeline to reduce the possibility of omission. The base treatment facilitates the subsequent installation and the stability of the overall device, and drains and releases pressure to facilitate subsequent installation;
[0043] S2: Place the expansion ball 11, inject air into the follower tube 10 to make it expand to a certain extent, and then use the device to move the expansion ball 11 to a certain position, and at the same time carry one end of the follower tube 10 to the right position, and the expansion ball 11 is guided to move, driving the follower tube 10 to move, and move along the internal gap;
[0044] S3: Install one end of the follower tube 10 to the internal mechanism, fix the internal mechanism with a fixing base, install the auxiliary mechanism, connect the device, and achieve preliminary limitation;
[0045] S4: Connect the external mechanism on the outside, and use anchor cables to fix the auxiliary mechanism, use the monitoring device to drain water, remove the previous drainage device, pour concrete to fix the base and the internal mechanism, and use anchor cables to limit the whole. In the subsequent work, stabilize the entire device to avoid collapse;
[0046] S5: The testing agency drains the water, monitors the water flow and internal pressure, and uploads data in real time for testing;
[0047] S6: Actively monitor the internal water pressure, water flow and sediment content, and control the water flow rate at the same time. When the water flows, measure the flow and sediment to achieve partial monitoring;
[0048] S7: Clean the device regularly and make adjustments.
[0049] The external mechanism includes an intermediate box 01 fixedly connected to one end of the intermediate pipe 16, and auxiliary boxes 03 and extraction boxes 18 are fixedly connected to both sides of the intermediate box 01, and multiple drainage pipes 21 are fixedly connected to one side of the intermediate box 01. The bottom of the extraction box 18 is fixedly connected to an auxiliary box 19 connected to the safety mechanism. The intermediate box 01 is limited, the auxiliary box 03 and the extraction box 18 provide necessary space, and the auxiliary box 19 is extended to limit.
[0050] The internal mechanism includes: a function box 09, which is connected with a slow flow unit in the middle, one end of the intermediate pipe 16 is connected to the function box 09, the function box 09 performs necessary restrictions, the slow flow unit performs buffering, and generates electricity at the same time, and the device is self-sufficient in power supply to ensure the continuous and stable operation of the entire device, an expansion box 08, which is arranged on the upper side of the function box 09, one side of the expansion box 08 is fixedly connected with a feeding pipe 06 connected to the auxiliary box 03, the expansion box 08 is filled with main group metal carbonates or other active compounds, which react with water to produce a large amount of gas, a slow flow box 23, which is arranged at the bottom of the function box 09, the slow flow box 23 is provided with a leakage hole connected to the function box 09, one side of the slow flow box 23 is fixedly connected with a conducting pipe 15 connected to the extraction box 18, the slow flow box 23 guides and intercepts the flow, so that the silt can be settled, and a regulating box 14, which is arranged in the function box 09. An auxiliary pipe 26 extending into the function box 09 is connected to the top, and the pressure relief pipe 24 is connected to the safety mechanism. The control box 14 and the auxiliary pipe 26 cooperate to perform auxiliary water flow control. The embedded tube 12 is connected at one end to the function box 09, and the other end of the embedded tube 12 is connected to the follower tube 10. The embedded tube 12 is extended and connected as needed. The pressure relief pipe 24 is connected at one end to the embedded tube 12, and the other end is connected to the expansion box 08. The pressure relief pipe 24 performs unidirectional gas flow, so that the gas enters the embedded tube 12 through the pressure relief pipe 24, and further enters the follower tube 10 and the expansion ball 11 for filling. There are multiple trigger tubes 25, one end of which is connected to the expansion box 08, and the other end is connected to the function box 09. The trigger tube 25 is more necessary to control the valve thereon to allow water to flow into the expansion box 08 to achieve the filling work.
[0051] The slow flow unit includes: a sensor 33, which is fixedly connected to the function box 09, a spring 32 is fixedly connected to one side of the sensor 33, the other end of the spring 32 is fixedly connected to a mounting frame 31, one side of the mounting frame 31 is fixedly connected to a guide box 34 that is in sliding contact with the function box 09, the sensor 33 performs pressure testing, the spring 32 performs elastic support, the mounting frame 31 guides the guide box 34 to achieve work needs, a drive frame 27, which is rotatably connected to the guide box 34, the outer side of the drive frame 27 is fixedly connected to a drive tooth 35 that matches the guide box 34, the drive frame 27 provides support and stability, and rotates along with the rotation of the drive tooth 35, The stabilizing frame 40 is fixedly connected to the functional box 09. A telescopic rod 39 is fixedly connected inside the stabilizing frame 40. The output end of the telescopic rod 39 is connected to the generator 36. The generator 36 performs buffering and interception. The follower frame 37 is fixedly connected to the generator 36. A Hall element 38 is arranged inside the follower frame 37. The Hall element 38 is located on the outside of the driving frame 27. One end of the driving frame 27 is fixedly connected to a transmission rod connected to the input end of the generator 36. The stabilizing frame 40 is limited. The telescopic rod 39 supports the generator 36. At the same time, when the driving frame 27 rotates, the generator 36 outputs electricity. The Hall element 38 is an existing mechanism for detecting the rotation speed of the driving frame 27.
[0052] A buffer sleeve matching the middle pipe 16 is fixedly connected to the function box 09, a generator 36 connected to the function box 09 is fixedly connected to one side of the guide box 34, and a plurality of inclined plates are fixedly connected in the slow flow box 23. The buffer sleeve provides a certain buffer to reduce the scouring of the surrounding area. The generator 36 is raised so that the silt can gather on one side of the generator 36, and then enter the slow flow box 23 for collection, and finally enter the extraction box 18.
[0053] A deformation arc is fixedly connected to one side of the function box 09, and a sensor group 1 is arranged inside the deformation arc. A battery 07 is filled between the expansion box 08 and the function box 09, and a controller 30 is connected to the battery 07. A cleaning door is connected to one side of the extraction box 18. The sensor group 1 measures certain pressure, vibration, temperature and humidity as well as some other data. The battery 07 stores electricity, and the controller 30 controls some internal devices.
[0054] The auxiliary mechanism includes: an expansion ring 04, which is fixedly connected to the middle tube 16, the expansion ring 04 cooperates with the feeding tube 06, the middle tube 16, and the drainage tube 21, the expansion ring 04 expands a large area to reduce the pressure of the overall device, and a contact sleeve 05, which is provided with multiple, the contact sleeve 05 is connected to the expansion ring 04, and the contact sleeve 05 is fixedly connected with a leakage pipe 22 connected to the expansion ring 04, the contact sleeve 05 is expanded and collected, and the leakage pipe 22 is inserted with an anchor cable to ensure the overall stability, and at the same time, a leakage hole is provided in the expansion ring 04 to guide the water that may seep out of the anchor cable into the expansion ring 04 Collection, expansion circle 04 is provided with drain holes for draining water, and a certain internal risk assessment is performed based on the seeping water combined with practice and necessary data. The supporting frame 13 is snap-connected with the functional box 09, and a safety pipe 20 is fixedly connected to the supporting frame 13. One end of the safety pipe 20 is connected to the regulating box 14, and the other end passes through the auxiliary box 19 to the outside of the auxiliary box 19. The safety pipe 20 is connected to a discharge pipe 17 connected to the conducting pipe 15. The supporting frame 13 is limited, and the safety pipe 20 can be used for rapid diversion and rapid water discharge to relieve pressure in the rock formation and reduce possible pipe bursts.
[0055] A touch screen 02 is connected to one side of the auxiliary box 03, a high-pressure pipe is connected to the side of the auxiliary box 03, a clamping ring is provided on the supporting frame 13, the touch screen 02 is an existing mechanism, and the internal measurement data is displayed. When necessary, the high-pressure pipe is connected to an external device to supply pressure to the inside and fill the internal gaps.
[0056] A plurality of receiving grooves 44 are provided on the outer side of the follower tube 10, and an elastic arc 42 is provided in the receiving groove 44. One end of the elastic arc 42 is connected to the interior of the follower tube 10, and a plurality of one-way sheets 43 are connected in the elastic arc 42. The receiving grooves 44 are used for certain storage, the elastic arcs 42 are used for water conduction, and the one-way sheets 43 are used for auxiliary one-way conduction.
[0057] The follower pipe 10. A monitoring and prevention method for water inrush in tunnels and lanes as claimed in claim 1, characterized in that the expansion ball 11 includes an outermost wear-resistant layer 50, a barrier layer 51 and an expansion layer 54 are connected to one side of the wear-resistant layer 50, a plurality of protective layers 53 are connected to the expansion layer 54, an outer wall of the protective layer 53 is connected to a partition layer 55 located in the expansion layer 54, a plurality of stabilizing ropes 57 are connected to the partition layer 55, the other end of the stabilizing rope 57 is connected to a slow-dissolving layer 58, a dissolving layer 56 is connected to the slow-dissolving layer 58, and a positioner 5 is connected to the protective layer 53. 2. The wear-resistant layer 50 is used for protection to reduce scratches on the rock formation, the barrier layer 51 is used for water isolation, the expansion layer 54 is used for internal bonding and stabilization, the protective layer 53 is used for protection, the positioner 52 is an existing mechanism for providing position, the stabilizing rope 57 is used for connection, the dissolving layer 56 and the separation layer 55 are filled with chemical substances, and the reaction produces a large amount of gas, which can make the expansion ball 11 expand as a whole, and the slow-dissolving layer 58 and the dissolving layer 56 use soluble substances, which slowly decompose after entering, so that the substances in the separation layer 55 and the dissolving layer 56 come into contact and react.
[0058] The pressure relief pipe 24, the trigger pipe 25, the embedded pipe 12, the feeding pipe 06, the discharge pipe 17, the auxiliary pipe 26, the safety pipe 20 and the drain pipe 21 are all connected with a one-way valve, the pressure relief pipe 24, the trigger pipe 25, the auxiliary pipe 26, the safety pipe 20 are all connected with an electromagnetic valve, and the bottom of 23 is connected with a detector 28, which is an existing mechanism and can be used for detection.
[0059] The implementation principle of the embodiment of the present application is:
[0060] When working, first drill a hole to conduct the rock formation, and at the same time install a temporary flow control. Place the expansion ball 11 connected to the follow-up tube 10 in the channel, and use the device to move the expansion ball 11 to a certain depth. The substances in the internal dissolving layer 56 and the separation layer 55 react to produce gas, which makes the wear-resistant layer 50 expand, so that the expansion ball 11 is stuck in the rock formation to achieve the limitation. Then connect one end of the follow-up tube 10 to the embedded tube 12, remove the temporary device, and install the function box 09 in the rock formation, and make the contact sleeve 05 enter the rock formation. The expansion ring 04 contacts the surface of the rock formation, pour concrete, so that the function box 09 is embedded in the surface rock formation to limit it, install the anchor cable in the leaking pipe 22, and limit the whole, so that the whole is safe in the subsequent use process, limit the rock formation, and achieve protection.
[0061] During the overall operation, the water inside the rock formation enters the follower pipe 10 through the elastic arc 42, then merges into the embedded pipe 12, and is further discharged through the functional box 09, the driving teeth 35, the intermediate pipe 16, the intermediate box 01 and the drainage pipe 21. During the discharge process, the silt inside the water flow is gathered in the slow flow box 23 through the lifting of the generator 36 and the buffering interception of the slow flow box 23, and then flushed through the conducting pipe 15 to flow to the extraction box 18, and then artificial exploration and measurement are carried out for discharge. In the process of water flow passing through the driving teeth 35, the driving teeth 35 are driven to rotate, and further the driving frame 27 and the input end of the generator 36 are driven to rotate to generate electricity, which enters the battery 07 for storage. At the same time, the Hall element 38 monitors the flow rate, and cooperates with the work of sensors and some devices to monitor multiple data.
[0062] Due to excessive water flow, dramatic increase in sand content and human control in the rock formation, the water in the functional box 09 enters the expansion box 08 to react and generate a large amount of gas, which enters the follower pipe 10 after passing through the pressure relief pipe 24 and the embedded pipe 12, so that the containing groove 44 is straightened and the follower pipe 10 is rapidly expanded, filling the internal space of the rock formation to achieve filling, water blocking and support. When necessary, solidified materials are filled into the interior through the auxiliary box 03, and the rock formation is evenly filled through the diversion of the follower pipe 10 to achieve protection. After filling and solidification, the functional box 09 can be taken out for recycling.
[0063] The above-mentioned embodiments are only preferred embodiments of the present invention and cannot be used to limit the scope of protection of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.
Claims
1. A method for monitoring and preventing water inrush in tunnels and lanes, characterized in that: The monitoring and prevention method is implemented by a monitoring device. Wherein, the monitoring device comprises: an external mechanism having an intermediate tube connected to one side thereof; An internal mechanism is fixedly connected to one end of the intermediate tube, one side of the internal mechanism is connected to a follower tube, and one end of the follower tube is fixedly connected to an expansion ball; Security agencies, which connect to internal agencies as well as external agencies; The monitoring and prevention method comprises: S1: Identify the possible locations of water inrush, perform external forming and crushing, install the corresponding fixed base, then perform drilling, and carry out preliminary drainage in conjunction with the initial pipeline; S2: Place an expansion ball, inject air into the follower tube to make it expand to a certain extent, and then use the device to move the expansion ball to a certain position, while carrying one end of the follower tube to the correct position; S3: Install one end of the follower tube to the internal mechanism, fix the internal mechanism with a fixing base, and install the auxiliary mechanism; S4: Connect the external mechanism on the outside, fix the auxiliary mechanism with anchor cables, use the monitoring device to drain water, remove the previous drainage device, and pour concrete to fix the base and internal mechanism; S5: The testing agency drains the water, monitors the water flow and internal pressure, and uploads data in real time for testing; S6: Actively monitor internal water pressure, water flow and sediment content, and control water flow rate; S6: Clean the device regularly and make adjustments.
2. A method for monitoring and preventing water inrush in tunnels and lanes as claimed in claim 1, characterized in that: The external mechanism includes an intermediate box fixedly connected to one end of the intermediate tube, an auxiliary box and an extraction box are fixedly connected to both sides of the intermediate box, a plurality of drainage pipes are fixedly connected to one side of the intermediate box, and an auxiliary box connected to the safety mechanism is fixedly connected to the bottom of the extraction box.
3. A method for monitoring and preventing water inrush in tunnels and lanes as claimed in claim 2, characterized in that: The internal institutions include: A function box, in the middle of which a slow flow unit is connected, and one end of the intermediate pipe is connected to the function box; An expansion box is arranged on the upper side of the functional box, and a feeding pipe connected to the auxiliary box is fixedly connected to one side of the expansion box; A slow flow box is arranged at the bottom of the function box, the slow flow box is provided with a leakage hole connected to the function box, and one side of the slow flow box is fixedly connected with a conducting pipe connected to the extraction box; A control box is arranged in the function box, and the top of the control box is connected with an auxiliary pipe extending into the function box, and the pressure relief pipe is connected with the safety mechanism; An embedded tube, one end of which is connected to the function box, and the other end of which is connected to the follower tube; A pressure relief pipe, one end of which is connected to the embedded pipe and the other end of which is connected to the expansion tank; A plurality of trigger tubes are provided, one end of which is connected to the expansion box, and the other end of which is connected to the function box.
4. A method for monitoring and preventing water inrush in tunnels and lanes as claimed in claim 3, characterized in that: The slow flow unit comprises: A sensor fixedly connected to the function box, one side of the sensor is fixedly connected to a spring, the other end of the spring is fixedly connected to a mounting frame, one side of the mounting frame is fixedly connected to a guide box in sliding contact with the function box; A driving frame, which is rotatably connected to the guide box, and a driving tooth matched with the guide box is fixedly connected to the outer side of the driving frame; A stabilizing frame, which is fixedly connected to the functional box, a telescopic rod is fixedly connected inside the stabilizing frame, and an output end of the telescopic rod is connected to a generator; The follower frame is fixedly connected to the generator, and a Hall element is arranged inside the follower frame. The Hall element is located outside the driving frame, and one end of the driving frame is fixedly connected to a transmission rod connected to the input end of the generator.
5. A method for monitoring and preventing water inrush in tunnels and lanes as claimed in claim 4, characterized in that: A buffer sleeve matched with the middle pipe is fixedly connected to the function box, a generator connected to the function box is fixedly connected to one side of the guide box, and a plurality of inclined plates are fixedly connected inside the damping box.
6. A method for monitoring and preventing water inrush in tunnels and lanes as claimed in claim 4, characterized in that: A deformation arc is fixedly connected to one side of the functional box, a sensor group 1 is arranged in the deformation arc, a battery is filled between the expansion box and the functional box, a controller is connected to the battery, and a cleaning door is connected to one side of the extraction box.
7. A method for monitoring and preventing water inrush in tunnels and lanes as claimed in claim 6, characterized in that: The auxiliary mechanism includes: An expansion ring, which is fixedly connected to the middle pipe, and the expansion ring cooperates with the feeding pipe, the middle pipe, and the drainage pipe; A contact sleeve, which is provided in plurality, wherein the contact sleeve is connected to the expansion ring, and a leakage pipe connected to the expansion ring is fixedly connected inside the contact sleeve; A supporting frame is snap-connected with the functional box, a safety tube is fixedly connected inside the supporting frame, one end of the safety tube is connected to the regulating box, and the other end passes through the auxiliary box to the outside of the auxiliary box, and a leakage pipe connected to the conducting pipe is connected to the safety tube.
8. A method for monitoring and preventing water inrush in tunnels and lanes as claimed in claim 7, characterized in that: A touch screen is connected to one side of the auxiliary box, a high-pressure pipe is connected to the side of the auxiliary box, and a clamping ring is arranged on the supporting frame.
9. A method for monitoring and preventing water inrush in tunnels and lanes as claimed in claim 1, characterized in that: A plurality of accommodating grooves are arranged on the outer side of the follower tube, an elastic arc is arranged in the accommodating groove, one end of the elastic arc is connected to the inside of the follower tube, and a plurality of one-way sheets are connected in the elastic arc.
10. A method for monitoring and preventing water inrush in tunnels and lanes according to claim 1, characterized in that: The expansion ball includes an outermost wear-resistant layer, one side of the wear-resistant layer is connected to a barrier layer and an expansion layer, the expansion layer is connected to a plurality of protective layers, the outer wall of the protective layer is connected to a separation layer located in the expansion layer, the separation layer is connected to a plurality of stabilizing ropes, the other end of the stabilizing rope is connected to a slow-dissolving layer, the slow-dissolving layer is connected to a dissolving layer, and the protective layer is connected to a positioner.