Installation construction method of boiler unit economizer

Through scientifically planned combined installation and construction methods, the complexity and difficulty of alignment during the installation of the boiler unit economizer are solved, a safe and efficient installation process and quality acceptance are achieved, and the overall installation efficiency and quality are improved.

CN118775846APending Publication Date: 2024-10-15CEEC BEIJING ELECTRIC POWER CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411038673.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

During the installation process of the economizer of the boiler unit, due to the complexity of more than a hundred tube rows and the difficulty of installation and alignment, the existing technology lacks scientific and reasonable construction process planning, making it difficult to guarantee the installation efficiency and quality.

Method used

A combined installation and construction method is adopted, including the installation of lifting equipment, pre-storage of the economizer import header, hoisting of the lower and upper sets of serpentine pipes, pipe row adjustment, alignment and sealing and anti-wear installation to ensure the scientific rationality and safety of each step. Safety and efficiency.

Benefits of technology

Through the systematic construction process, the installation safety and efficiency of the boiler unit economizer are improved, ensuring the reliability of the installation quality and the accuracy of the overall acceptance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118775846A_ABST
    Figure CN118775846A_ABST
Patent Text Reader

Abstract

The invention discloses an installation construction method of a boiler unit economizer. The installation construction method comprises the steps of hoisting equipment installation and economizer installation. The coal economizer installation sequentially comprises the steps of coal economizer inlet header prestorage, coal economizer coiled pipe lower group hanging installation, coal economizer coiled pipe lower group hoisting, coal economizer connecting pipe and middle header prestorage, coal economizer coiled pipe upper group hanging installation, coal economizer coiled pipe upper group hoisting and secondary coal economizer hoisting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of boiler units, in particular to an installation and construction method of a boiler economizer. Background Art

[0002] The economizer of the boiler unit is divided into three parts, including the economizer coil lower group, economizer coil upper group, and secondary economizer. Each part is divided into more than a hundred tube rows. It is very difficult to install and align. The installation quality must be strictly controlled during installation. The installation must be carried out in sequence according to the construction process. The tube row needs to be adjusted before the pipe joint welding. After the installation is completed, the overall alignment and acceptance must be carried out. However, the existing technology does not have a relevant technical solution for how to scientifically and reasonably plan the construction process.

[0003] In view of this, the present invention is proposed. Summary of the invention

[0004] The purpose of the present invention is to overcome the above technical deficiencies and provide a combined installation and construction method for a boiler unit superheating system to achieve safe and efficient installation of the boiler unit superheating system.

[0005] In order to achieve the above technical objectives, the present invention adopts the following technical solutions:

[0006] According to one aspect of the present invention, there is provided a method for installing a boiler unit economizer, including installing a lifting device and installing the economizer;

[0007] The economizer installation includes, in order: pre-storage of economizer inlet header, hanging and installation of economizer serpentine tube lower group, hoisting of economizer serpentine tube lower group, pre-storage of economizer connecting pipe and intermediate header, hanging and installation of economizer serpentine tube upper group, hoisting of economizer serpentine tube upper group, and hoisting of secondary economizer.

[0008] Furthermore, the method also includes installing and adjusting economizer tube banks.

[0009] Furthermore, the method also includes aligning the economizer serpentine tube upper group with the secondary economizer, installing, aligning and accepting the economizer header.

[0010] Furthermore, the method also includes: economizer sealing and anti-wear installation.

[0011] Furthermore, the installation of the lifting equipment specifically includes: the lifting equipment uses a monorail beam, which is positioned under the ceiling wall superheater, and one superheater compartment and one reheater compartment are arranged on both sides of the middle partition wall, which are arranged parallel to the middle partition wall. The ceiling superheater reserves holes for monorail beam lifting ears, and the lifting ears pass through the ceiling superheater and are welded to the ceiling tube fins. Seven 10t chain hoists and 10t unloading cards are hung from the front and rear secondary plate beams between the large plate beams D and F to lift the monorail beam. The two ends of the track are limited by steel plates welded. If there are joints in the middle, webs need to be added at the joints. After installation, both ends of the monorail are reinforced with channel steel to prevent shaking during lifting. After the monorail is installed in place, the 16t electric hoist is tested and accepted before use.

[0012] Furthermore, the pre-storage of the economizer inlet header specifically includes: the left and right sections of the economizer inlet header, which need to be pre-stored in advance to the position 34m in front of the rear flue by using an 80t tower crane before installing the economizer tube row, and then temporarily suspended on the rooting beam of the economizer serpentine tube lower group tube row hanging device by two steel wire ropes with a diameter of ≥14mm, and installed in place after the economizer tube row is adjusted and aligned.

[0013] Furthermore, the hoisting of the lower group of economizer serpentine tubes specifically includes: the weight of the tube row of the lower group of economizer serpentine tubes is about 2.27t, the specification size is 10200*2280mm, and it is hoisted in bulk. Before hoisting, the tube row is transported to the designated hoisting position, and then the 80t tower crane hook and the tube row are connected by two 4-strand steel wire ropes through a 1t clamp. After hoisting, it is airdropped to a position about 35m to the left of the rear furnace, and then the economizer tube row is moved to its position for temporary suspension by using the two arranged electric hoist hooks. When the temporarily suspended tube rows exceed the number of tube rows connected by the hanging plate in the design drawings, the hanging plate is connected to formally put the tube row in place.

[0014] Furthermore, the economizer connecting pipe and the intermediate header are pre-stored, specifically including: the upper and lower tube rows of the economizer serpentine tube are connected through the lower outlet header, the economizer connecting pipe and the upper inlet header. The lower outlet header is divided into 2 sections, each with a single weight of 4.537t; the connecting pipe is divided into left and right parts, with a total weight of 7.769t; the upper inlet header is divided into 2 sections, each with a single weight of 4.583t. After the lower tube row of the economizer serpentine tube is hoisted, it is airdropped to the 38m position of the rear flue by an 80t tower crane, and the lower outlet header is temporarily hung on the rooting beam of the middle lower tube row hanging device by 2 steel wire ropes with a diameter of ≥14mm; similarly, the economizer connecting pipe and the upper inlet header are also pre-stored to the installation position through their own hanging devices and fixed firmly.

[0015] Furthermore, the hoisting of the economizer serpentine tube upper group specifically includes: the weight of a single piece of the economizer serpentine tube upper group tube row is about 2.02t, and the specification size is 10200*1800mmmm. Its installation method is consistent with the installation method of the economizer serpentine tube lower group tube row. Use an 80t tower crane to drop the tube row to a position about 45m on the left side of the rear furnace, and temporarily hang it on the lifting ear below the wall-wrapped header.

[0016] Furthermore, the weight of a single piece of the secondary economizer is about 0.83t, and the specification size is 4655*2054mm. The hoisting method of the secondary economizer is the same as the hoisting method of the economizer serpentine pipe.

[0017] The combined installation construction method for the economizer of a boiler unit provided by the present invention has scientific and reasonable settings of various steps, ensuring a safe and efficient installation process. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 A flow chart of a boiler unit economizer installation construction method is provided for an embodiment of the present invention. DETAILED DESCRIPTION

[0019] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.

[0020] An embodiment of the present invention provides an installation and construction method for a boiler unit economizer.

[0021] 1Overall process introduction

[0022] As the economizer in this project is not designed with suspended pipes, the upper tube row of the economizer serpentine tube is hung under the lower connecting box of the front enclosing wall, middle partition wall and rear enclosing wall through a hanging device, and the lower tube row of the economizer serpentine tube is hung on the steel frame at the lower position of the denitrification through a hanging device. Therefore, before installing the economizer, the front enclosing wall, middle partition wall and rear enclosing wall must be aligned and inspected, the welding work with the ceiling superheater must also be completed, and the lower steel frame of the denitrification must also be aligned and installed to have load-bearing capacity.

[0023] Combination Figure 1The overall construction process can be summarized as follows: equipment inspection, alloy steel spectrum analysis → equipment pipe row ball passing → header marking → lifting electric hoist installation → (economizer serpentine lower group hanging device rooting beam installation) → economizer inlet header pre-storage → economizer serpentine lower group hanging installation → economizer serpentine lower group hoisting → economizer connecting pipe and intermediate header pre-storage → economizer serpentine upper group hanging installation → economizer serpentine upper group hoisting → secondary economizer hoisting → economizer pipe row installation, adjustment → economizer serpentine upper group and secondary economizer alignment → economizer header installation, alignment, acceptance → economizer sealing, anti-wear installation → overall acceptance

[0024] The following is an example to describe the above steps in detail.

[0025] 2. Installation of lifting equipment

[0026] 2.1 The secondary plate beam and the left side wall hanging rod beam are slowly installed. As the economizer lifting entrance, the left side wall of the furnace is temporarily suspended on the top plate and not put into place.

[0027] 2.2 The lifting equipment uses a monorail beam, which is placed under the ceiling wall superheater. One is arranged in each superheater compartment and reheater compartment on both sides of the middle partition wall, and is arranged parallel to the middle partition wall. The ceiling superheater reserves a monorail beam lifting ear hole, and the lifting ear passes through the ceiling superheater and is welded to the ceiling tube fin. Seven 10t chain hoists and 10t unloading cards are hung from the front and rear secondary plate beams between the large plate beams to hang the monorail beam. The two ends of the track are welded with steel plates to limit the position. If there is a joint in the middle, a web needs to be added at the joint; after installation, the two ends of the monorail are reinforced with channel steel to prevent shaking during lifting. After the monorail is installed in place, the 16t electric hoist shall be tested and accepted in accordance with the following four aspects in accordance with the requirements of JB-T9008.2-2015 "Wire Rope Electric Hoist Part 2: Test Method" before use.

[0028] (1) No-load test

[0029] At rated frequency and rated voltage, perform no-load operation on the test bench, lifting and lowering for at least two cycles, and perform the following tests:

[0030] 1) Record the special phase heart pressure and current:

[0031] 2) Check the function of the lifting height limiter: activate the limiter and check whether the hook stops moving in the corresponding direction. At this time, the action in the opposite direction can be carried out:

[0032] 3) Start the lifting mechanism to lower the hook, rotate the drum twice, and check whether the wire rope can be discharged freely from the drum.

[0033] (2) Determine the lifting and lowering speed

[0034] The lifting and lowering speeds are measured under rated voltage, rated frequency and rated load conditions.

[0035] Lifting speed: When the lifting distance exceeds 0.5m, use a stopwatch to measure the lifting distance within 10s, or take a fixed distance and measure the time required, and calculate the lifting speed. Measure four times in a row and take the average value.

[0036] Descent speed: When the descent distance exceeds 0.5m, use the same method to test and calculate the descent speed.

[0037] (3) Static load test

[0038] Under the conditions of rated voltage and rated frequency, the electric hoist lifts the rated load to a height of 100mm to 200mm from the ground, and then gradually, slowly and steadily loads it to 1.25 times the rated load. The suspension time should not be less than 10 minutes.

[0039] After unloading, visually inspect all parts for cracks, permanent deformation, paint peeling, damage, loose connections, and other abnormalities.

[0040] (4) Dynamic load test

[0041] Under the conditions of rated voltage, rated frequency and test load of 1.1 times the rated load, the hoisting mechanism shall operate continuously according to the cycle period in Appendix A corresponding to the design reference working level, which shall not be less than 30 minutes.

[0042] For electric hoists with operating mechanisms, the electric hoists run back and forth continuously for 10 cycles, and the one-way running distance of each cycle should not be less than 2m.

[0043] After unloading, visually inspect all parts for cracks, permanent deformation, paint peeling, damage, loose connections, and other abnormalities.

[0044] Note: For electric hoists equipped with a lifting weight limiter, when conducting static load tests and dynamic load tests, the lifting weight limiter must be released before the test.

[0045] 3. Economizer Installation

[0046] 3.1 The left (4.312t) and right (4.693t) sections of the economizer inlet header should be pre-stored at the 34m position on the front side of the rear flue by using an 80t tower crane before installing the economizer tube bank. Then, they should be temporarily suspended on the rooting beam of the economizer serpentine tube lower group tube bank hanging device by two steel wire ropes with a diameter of ≥14mm. After the economizer tube bank is adjusted and aligned, they can be installed in place.

[0047] 3.2 The weight of the lower tube bank of the economizer serpentine tube is about 2.27t, and the size is 10200*2280mm. It is hoisted in bulk. Before hoisting, the tube bank is transported to the designated hoisting position, and then the 80t tower crane hook and the tube bank are connected by two φ10 steel wire ropes with four strands through a 1t clamp. After hoisting, it is airdropped to the position about 35m to the left of the rear furnace, and then the economizer tube bank is moved to its position for temporary suspension by using the two electric hoist hooks. When the temporarily suspended tube banks exceed the number of tube banks connected by the hanging plate in the design drawings, the hanging plate is connected to formally put the tube bank in place.

[0048] 3.3 The upper and lower tube rows of the economizer serpentine tubes are connected through the lower outlet header, economizer connecting pipe and upper inlet header. The lower outlet header is divided into 2 sections, each weighing 4.537t; the connecting pipe is divided into left and right parts, with a total weight of 7.769t; the upper inlet header is divided into 2 sections, each weighing 4.583t. After the lower tube row of the economizer serpentine tube is hoisted, it is airdropped to the position of 38m at the rear flue using an 80t tower crane, and the lower outlet header is temporarily hung on the rooting beam of the middle lower tube row hanging device using two steel wire ropes with a diameter of ≥14mm; similarly, the economizer connecting pipe and the upper inlet header are also pre-stored in the installation position through their own hanging devices and fixed firmly;

[0049] 3.4 The weight of the upper tube row of economizer serpentine tube is about 2.02t, and the specification size is 10200*1800mm. Its installation method is the same as that of the lower tube row of economizer serpentine tube. Use 80t tower crane to drop the tube row to the left side of the rear furnace about 45m, and temporarily hang it on the lifting ear below the wall-wrapped header.

[0050] 3.5 The weight of a single secondary economizer is about 0.83t, and the size is 4655*2054mm. Its hoisting method is the same as that of the economizer serpentine pipe. The secondary economizer pipes are installed from right to left in sequence, and each pipe must be firmly installed on the block between the middle partition wall and the rear wall.

[0051] 3.6 The economizer outlet header is divided into two sections, the left section weighs 4.385t and the right section weighs 4.49t. Considering that the size of this header is too long after ground assembly and is easy to deform during hoisting, it is hoisted in sections and pre-stored on a 53m support. After the overall adjustment of the economizer tube row is completed, it will be welded in place.

[0052] 4. Installation and adjustment of economizer

[0053] After the alignment of the economizer tube bank and header is completed, the welding of the economizer tube group and header can be carried out. After the welding is completed, the gap between the economizer and the wall-wrapped superheater, and between the tube banks, is inspected to meet the requirements of the drawings.

[0054] 5. Installation of economizer seal and anti-wear device

[0055] The seal, anti-wear and other accessories of the economizer can be partially installed first without affecting the hoisting, welding and inspection of the economizer. If it affects the welding of the pipe row, it should be installed in time after the welding inspection is completed.

[0056] 6Overall acceptance

[0057] After the economizer welding is completed, the gap between the tube rows and between the tube rows and the wall is adjusted. Then the acceptance work is carried out

[0058] The above is only a preferred implementation of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.

Claims

1. A method for installing and constructing a boiler unit economizer, characterized in that: Including lifting equipment installation and economizer installation; The economizer installation includes, in order: pre-storage of economizer inlet header, hanging and installation of economizer serpentine tube lower group, hoisting of economizer serpentine tube lower group, pre-storage of economizer connecting pipe and intermediate header, hanging and installation of economizer serpentine tube upper group, hoisting of economizer serpentine tube upper group, and hoisting of secondary economizer.

2. The installation and construction method of the boiler unit economizer according to claim 1, characterized in that: The method also includes installing and adjusting the economizer tube bank.

3. The installation and construction method of the boiler unit economizer according to claim 1, characterized in that: The method also includes aligning the upper group of economizer serpentine tubes with the secondary economizer, installing, aligning and accepting the economizer header.

4. The installation and construction method of a boiler unit economizer according to claim 1, characterized in that: The method also includes: economizer sealing and anti-wear installation.

5. The installation and construction method of a boiler unit economizer according to claim 1, characterized in that: The installation of the lifting equipment specifically includes: the lifting equipment uses a monorail beam, which is positioned under the ceiling wall-wrapped superheater, and one is arranged in each of the superheater compartment and the reheater compartment on both sides of the middle partition wall, which are arranged parallel to the middle partition wall. The ceiling superheater reserves holes for monorail beam lifting ears, and the lifting ears pass through the ceiling superheater and are welded to the ceiling tube fins. Seven 10t chain hoists and 10t unloading cards are hung from the front and rear secondary plate beams and secondary plate beams between the large plate beams D and F to lift the monorail beam. The two ends of the track are limited by steel plates welded. If there is a joint in the middle, a web needs to be added at the joint; after installation, both ends of the monorail are reinforced with channel steel to prevent shaking during lifting. After the monorail is installed in place, the 16t electric hoist is tested and accepted before use.

6. The installation and construction method of a boiler unit economizer according to claim 1, characterized in that: The economizer inlet header pre-storage specifically includes: the left and right sections of the economizer inlet header, which need to be pre-stored in advance to the position 34m in front of the rear flue by using an 80t tower crane before installing the economizer tube bank, and then temporarily suspended on the rooting beam of the economizer serpentine tube lower group tube bank hanging device by two steel wire ropes with a diameter of ≥14mm, and then installed in place after the economizer tube bank is adjusted and aligned.

7. The installation and construction method of a boiler unit economizer according to claim 1, characterized in that: The hoisting of the lower group of economizer serpentine tubes specifically includes: the weight of the tube row of the lower group of economizer serpentine tubes is about 2.27t, the specification size is 10200*2280mm, and it is hoisted in bulk. Before hoisting, the tube row is transported to the designated hoisting position, and then the 80t tower crane hook and the tube row are connected by two 4-strand steel wire ropes through a 1t clamp. After hoisting, it is airdropped to a position about 35m to the left of the rear furnace, and then the economizer tube row is moved to its position for temporary suspension by using the two arranged electric hoist hooks. When the temporarily suspended tube rows exceed the number of tube rows connected by the hanging plate in the design drawings, the hanging plate is connected to formally put the tube row in place.

8. The installation and construction method of a boiler unit economizer according to claim 1, characterized in that: The economizer connecting pipe and the intermediate header are pre-stored, specifically including: the upper and lower tube rows of the economizer serpentine tube are connected through the lower outlet header, the economizer connecting pipe and the upper inlet header. The lower outlet header is divided into 2 sections, each with a single weight of 4.537t; the connecting pipe is divided into left and right parts, with a total weight of 7.769t; the upper inlet header is divided into 2 sections, each with a single weight of 4.583t. After the lower tube row of the economizer serpentine tube is hoisted, it is airdropped to the 38m position of the rear flue by an 80t tower crane, and the lower outlet header is temporarily hung on the rooting beam of the middle lower tube row hanging device by 2 steel wire ropes with a diameter of ≥14mm; similarly, the economizer connecting pipe and the upper inlet header are also pre-stored to the installation position through their own hanging devices and fixed firmly.

9. The installation and construction method of a boiler unit economizer according to claim 1, characterized in that: The hoisting of the economizer serpentine tube upper group specifically includes: the weight of a single piece of the economizer serpentine tube upper group tube row is about 2.02t, and the specification size is 10200*1800mmmm. Its installation method is consistent with the installation method of the economizer serpentine tube lower group tube row. Use an 80t tower crane to drop the tube row to a position about 45m on the left side of the rear furnace, and temporarily hang it on the lifting ear below the wall-wrapped header.

10. The installation and construction method of a boiler unit economizer according to claim 1, characterized in that: The weight of the secondary economizer is about 0.83t, and the size is 4655*2054mm. The hoisting method is the same as the economizer serpentine pipe hoisting method.